REALISASI KEGIATAN REHABILITASI DAN REKONSTRUKSI PASCAGEMPA

PEMBANGUNAN RUMAH KORBAN BENCANA DI KOTA PALU

Nama POKMAS : BIROBULI UTARA II


Kelurahan : BIROBULI UTARA
Kecamatan : PALU SELATAN
Kota : PALU

JADWAL PELAKSANAAN PEKERJAAN TERHADAP BAHAN MATERIAL


BOBOT
PENYALURAN DANA
NO JENIS BAHAN BANGUNAN BOBOT AGUSTUS SEPTEMBER OKTOBER PERSENTASE
TAHAP I
(%) II III INDIVIDU
IV I II III IV I II III IV
A. TAHAP I

1 H. YOS SOEDARSO MARDJUNI 25,000,000.00 8.333 0.000 0.000 0.000 0.000 0.000 0%

2 MOH. ARISANDI 25,000,000.00 8.333 0.833 1.250 1.250 1.250 1.250 70%

3 TJATOER MARIJONO 25,000,000.00 8.333 0.000 0.000 0.000 0.000 0.000 0%

4 SAMUEL PANGKEY 25,000,000.00 8.333 0.000 0.000 0.000 0.583 0.833 17%

5 ALEX 25,000,000.00 8.333 1.667 2.083 1.250 1.250 1.250 90%

6 SUYANTI 25,000,000.00 8.333 0.833 0.833 0.833 0.833 0.417 45%

7 ZENDI ALDI BUDIAWAN 25,000,000.00 8.333 0.000 0.833 0.833 2.083 2.083 70%

8 TUGIMIN 25,000,000.00 8.333 0.000 0.000 0.833 1.667 1.667 50%

9 BILHAN MOWELUA 25,000,000.00 8.333 0.833 0.833 0.833 0.833 0.000 40%

10 MOH. ARIF 25,000,000.00 8.333 1.250 1.250 1.250 1.667 1.667 85%

11 RIDWAN LANCONG 25,000,000.00 8.333 0.000 0.000 0.000 1.250 1.250 30%

12 WATI 25,000,000.00 8.333 0.000 0.000 0.000 0.000 0.417 5%

A. TAHAP I 150,000,000.00 50.000

B. TAHAP II 120,000,000.00 40.000 RENCANA TAHAP I RENCANA TAHAP II RENCANA TAHAP III

C. TAHAP III 30,000,000.00 10.000

TOTAL DANA POKMAS 300,000,000.00 100.000

BOBOT REALISASI 5.417 7.083 7.083 11.417 10.833 0.000

BOBOT REALISASI KUMULATIF 5.417 12.500 19.583 31.000 41.833 41.833