BO- WAKTU PELAKSANAAN

NO JENIS PEKERJAAN BOT


(%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22

I PEKERJAAN PERSIAPAN 1.12 0.56 0.56

II PEKERJAAN TANAH 7.97 1.99 1.99 1.99 1.99

III PEKERJAAN PONDASI & BETON 7.12 1.78 1.78 1.78 1.78

IV PEKERJAAN PASANGAN 30.85 7.71 7.71 7.71 7.71

V PEKERJAAN PLAFOND 4.50 1.50 1.50 1.50

VI PEKERJAAN LANTAI 9.38 3.13 3.13 3.13

VII PEKERJAAN KOSEN PINTU DAN JENDELA 2.26 1.13 1.13

VIII PEKERJAAN SANITARY 1.43 0.72 0.72

IX PEKERJAAN ATAP 20.17 10.08 10.08

X PEKERJAAN SITE IMPROVEMENT 8.01 2.67 2.67 2.67

XI PEKERJAAN MEKANIKAL ELEKTRIKAL 0.99 0.99

XII PEKERJAAN FURNITURE 6.21 6.21

Total (%) 100.00

Rencana fisik per minggu 2.55 2.55 1.99 1.99 1.78 2.91 2.91 9.49 7.71 7.71 7.71 1.50 1.50 2.22 13.92 13.21 3.13 2.67 2.67 2.67 0.99 6.21

Rencana fisik komulatif 2.55 5.11 7.10 9.09 10.87 13.78 16.69 26.18 33.89 41.61 49.32 50.82 52.32 54.53 68.46 81.67 84.79 87.46 90.13 92.80 93.79 100.00

Gambar 4.7 Hasil Out Put Time Schedule dan Kurva "S" Dengan Menggunakan Microsoft Excel