REKAP PROGRESS BULAN AGUSTUS

PEKERJAAN PEMBANGUNAN JALAN TOL CILEUNYI - SUMEDANG - DAWUAN (CISUMDAWU)


SEKSI 5A STA 43+300 s/d STA 46+500
30 Juli 2021 s/d 02 September 2021
PT. ADHI KARYA (PERSERO) ,Tbk PT. BINA MITRA INDOSEJAHTERA

NOMOR KONTRAK : Progress Rencana : %

TANGGAL KONTRAK : Progress Aktual : %

NILAI KONTRAK : Rp 353,478,767,922.60 Exclude PPN Deviasi : - %

PENYEDIA JASA : PT. B M I S Sisa Waktu : 120 Hari


PT. ADHI KARYA (PERSERO) ,Tbk
PENGUNA JASA : Mulai : 25 Juni 2021

Selesai : 31 Desember 2021

Durasi : 190 Hari Kalender

REALISASI PEKERJAAN
KONTRAK AWAL
NO URAIAN PEKERJAAN S/D BULAN LALU BULAN INI S/D BULAN INI
BIAYA BOBOT JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT
(Rp.) (%) (Rp.) (%) (Rp.) (%) (Rp.) (%)

I PEKERJAAN PERSIAPAN 11,275,263,442.00 3.190 722,500,000.00 0.204 1,026,269,000.00 0.290 1,748,769,000.00 0.495

II PEMBONGKARAN 1,157,500,000.00 0.327 443,048,623.00 0.125 34,955,520.00 0.010 478,004,143.00 0.135

III PEKERJAAN TANAH 334,347,783,784.80 94.588 1,537,440,320.00 0.435 5,046,490,300.00 1.428 6,583,930,620.00 1.863

IV LAPIS PONDASI AGREGATE (Subgrade Preparation) 5,940,574,112.80 1.681 - - - - - -

V PEKERJAAN LAIN LAIN 757,646,583.00 0.214 320,656,583.00 0.091 46,575,000.00 0.013 367,231,583.00 0.104

JUMLAH TOTAL 353,478,767,922.60 100.000 3,023,645,526.00 0.855 6,154,289,820.00 1.741 9,177,935,346.00 2.596

Diperiksa dan disetujui oleh, Dibuat oleh,


PENGUNA JASA PENYEDIA JASA
PT. ADHI KARYA (PERSERO), Tbk PT. BINA MITRA INDOSEJAHTERA

Sarining Setyo Prastowo Hendra


Project Manager Project Manager
PROGRESS BULAN AGUSTUS
PEKERJAAN PEMBANGUNAN JALAN TOL CILEUNYI - SUMEDANG - DAWUAN (CISUMDAWU)

SEKSI 5A STA 43+300 s/d STA 46+500


PT. ADHI KARYA (PERSERO) ,Tbk PT. BINA MITRA INDOSEJAHTERA

NOMOR KONTRAK : - BULAN KE : 03


TANGGAL KONTRAK : - DARI TANGGAL : 30 Juli 2021
NILAI KONTRAK : - S/D TANGGAL : 02 September 2021
PENYIDIA JASA : PT. B M I S
PT. ADHI KARYA (PERSERO) ,Tbk
PENGUNA JASA :

KONTRAK AWAL REALISASI SISA


S/D BULAN LALU BULAN INI S/D BULAN INI PEKERJAAN
NO. URAIAN SATUAN
KUANTITAS BOBOT BOBOT BOBOT
KUANTITAS KUANTITAS KUANTITAS (%)
(%) (%) (%)

I PEKERJAAN PERSIAPAN
1 Mob Demob Fleet 10.00 2.00 20% 4.00 40% 6.00 60% 40.00%
2 Pekerjaaan Buangan Hasil Clearing m3 171,645.57 - 0% 10,020.00 6% 10,020.00 6% 94.16%
3 Pekerjaan Lereng Timbunan m2 239,864.00 - 0% - 0% - 0% 100.00%
4 Pekerjaan Lereng Galian m2 43,586.82 - 0% - 0% - 0% 100.00%
5* Pekerjaan Jalan Akses ke Quary Ungkal m 5,300.00 - 0% - 0% - 0% 100.00%
6* Pembuatan Akses Kerja dalam ROW m 3,200.00 1,500.00 47% 885.00 28% 2,385.00 75% 25.47%

II PEMBONGKARAN
1 Pembongkaran Pasangan Batu atau Bata m3 1,000.00 423.89 42% 57.55 6% 481.44 48% 51.86%
2 Pembongkaran Struktur m3 500.00 - 0% - 0% - 0% 100.00%
3 Pembongkaran Rumah m2 8,000.00 3,154.41 39% 226.70 3% 3,381.11 42% 57.74%

III PEKERJAAN TANAH


1 Pembersihan Tempat Kerja m2 572,351.89 72,030.00 13% 106,725.00 19% 178,755.00 31% 68.77%
2 Galian Biasa untuk Dibuang (Waste) m3 291,817.77 - 0% - 0% - 0% 100.00%
3 Galian Biasa untuk Timbunan m3 878,803.89 - 0% 25,434.00 3% 25,434.00 3% 97.11%
4 Galian Biasa untuk Material Pengisi di Median m3 12,904.24 - 0% - 0% - 0% 100.00%
5 Galian Batu Lunak untuk di Buang m3 - - -
6 Addiitonal Cost of Common Excavation as Waste Material with >2 km (each km) Rate Only 145,908.89 - 0% - 0% - 0% 100.00%
7 Common Borrow Material m3 894,998.44 7,876.00 1% - 0% 7,876.00 1% 99.12%
8 Common Embankment m3 - - -
9 Persiapan Badan Jalan (Subgrade Preparation) m2 175,170.11 - 0% - 0% - 0% 100.00%
10* Pengadaan Geotextile Stabilisator 75 KN/m (Geotextile Composite) m2 452,146.35 - 0% 27,040.00 6% 27,040.00 6% 94.02%
11* Pemasangan Geotextile Stabilisator 75 KN/m (Geotextile Composite) m2 452,146.35 - 0% 806.00 0% 806.00 0% 99.82%
12* Pengadaan Geotextile Filter Separator 11.5 KN/m (Geotextile Non Woven) m2 390,470.78 - 0% - 0% - 0% 100.00%
13* Pemasangan Geotextile Filter Separator 11.5 KN/m (Geotextile Non Woven) m2 390,470.78 - 0% - 0% - 0% 100.00%
PROGRESS BULAN AGUSTUS
PEKERJAAN PEMBANGUNAN JALAN TOL CILEUNYI - SUMEDANG - DAWUAN (CISUMDAWU)

SEKSI 5A STA 43+300 s/d STA 46+500


PT. ADHI KARYA (PERSERO) ,Tbk PT. BINA MITRA INDOSEJAHTERA

NOMOR KONTRAK : - BULAN KE : 03


TANGGAL KONTRAK : - DARI TANGGAL : 30 Juli 2021
NILAI KONTRAK : - S/D TANGGAL : 02 September 2021
PENYIDIA JASA : PT. B M I S
PT. ADHI KARYA (PERSERO) ,Tbk
PENGUNA JASA :

KONTRAK AWAL REALISASI SISA


S/D BULAN LALU BULAN INI S/D BULAN INI PEKERJAAN
NO. URAIAN SATUAN
KUANTITAS BOBOT BOBOT BOBOT
KUANTITAS KUANTITAS KUANTITAS (%)
(%) (%) (%)
14* Urugan Material Berbutir (Granular fill) m3 98,000.00 - 0% 90.00 0% 90.00 0% 99.91%
PROGRESS BULAN AGUSTUS
PEKERJAAN PEMBANGUNAN JALAN TOL CILEUNYI - SUMEDANG - DAWUAN (CISUMDAWU)

SEKSI 5A STA 43+300 s/d STA 46+500


PT. ADHI KARYA (PERSERO) ,Tbk PT. BINA MITRA INDOSEJAHTERA

NOMOR KONTRAK : - BULAN KE : 03


TANGGAL KONTRAK : - DARI TANGGAL : 30 Juli 2021
NILAI KONTRAK : - S/D TANGGAL : 02 September 2021
PENYIDIA JASA : PT. B M I S
PT. ADHI KARYA (PERSERO) ,Tbk
PENGUNA JASA :

KONTRAK AWAL REALISASI SISA


S/D BULAN LALU BULAN INI S/D BULAN INI PEKERJAAN
NO. URAIAN SATUAN
KUANTITAS BOBOT BOBOT BOBOT
KUANTITAS KUANTITAS KUANTITAS (%)
(%) (%) (%)

IV LAPIS PONDASI AGREGATE (Subgrade Preparation)


1 Lapis Pondasi Agregate Kelas A m3 15,349.07 - 0% - 0% - 0% 100.00%
2 Lapis Pondasi Agregate Kelas B m3 3,511.54 - 0% - 0% - 0% 100.00%

V PEKERJAAN LAIN LAIN


1* Pemasangan Gorong Gorong RCP D = 60 cm bh 60.00 24.00 40% - 0% 24.00 40% 60.00%
2* Pemasangan Saluran Box Culvert D = 60 cm bh 75.00 8.00 11% - 0% 8.00 11% 89.33%
3* Pemasangan Saluran Box Culvert D = 80 cm bh 75.00 26.00 35% 36.00 48% 62.00 83% 17.33%
4* Pemasangan Saluran Box Culvert D = 2000 cm bh 25.00 12.00 48% - 0% 12.00 48% 52.00%
5* Pekerjaan Detour Sta 43+600 m' 150.00 - 0% 125.00 83% 125.00 83% 16.67%
6* Pekerjaan Detour Sta 44+000 m' 150.00 116.00 77% - 0% 116.00 77% 22.67%
7* Pekerjaan Detour Sta 45+700 m' 150.00 - 0% - 0% - 0% 100.00%
8* Pekerjaan Detour Sta 46+000 m' 150.00 - 0% - 0% - 0% 100.00%
9* Pekerjaan Penimbunan Villa m3 855.61 855.61 100% - 0% 855.61 100% 0.00%
10* Penyiapan Disposal Area ls 1.00 - 0% - 0% - 0% 100.00%
11* Galian Saluran DS-5 m' 6,400.00 - 0% - 0% - 0% 100.00%
-

Diperiksa dan disetujui oleh, Dibuat oleh,


PENGUNA JASA PENYEDIA JASA
PT. ADHI KARYA (PERSERO), Tbk PT. BINA MITRA INDOSEJAHTERA

Sarining Setyo Prastowo Hendra


Project Manager Project Manager
PROGRESS BULAN AGUSTUS
PEKERJAAN PEMBANGUNAN JALAN TOL CILEUNYI - SUMEDANG - DAWUAN (CISUMDAWU)
SEKSI 5A STA 43+300 s/d STA 46+500
PT. ADHI KARYA (PERSERO) ,Tbk PT. BINA MITRA INDOSEJAHTERA

NOMOR KONTRAK : - BULAN KE : 03


TANGGAL KONTRAK : - DARI TANGGAL : 30 Juli 2021
NILAI KONTRAK : - S/D TANGGAL : 02 September 2021
PENYIDIA JASA : PT. B M I S
PT. ADHI KARYA (PERSERO) ,Tbk
PENGUNA JASA :

KONTRAK AWAL REALISASI BOBOT


S/D BULAN LALU BULAN INI S/D BULAN INI PRESTASI
NO. URAIAN SATUAN HARGA SATUAN JUMLAH HARGA BOBOT
KUANTITAS BOBOT BOBOT BOBOT
KUANTITAS KUANTITAS KUANTITAS (%)
(Rp) (Rp) (%) (%) (%) (%)

I PEKERJAAN PERSIAPAN
1 Mob Demob Fleet 10.00 125,000,000.00 1,250,000,000.00 0.354 2.00 0.071 4.00 0.141 6.00 0.212 60.000
2 Pekerjaaan Buangan Hasil Clearing m3 171,645.57 24,700.00 4,239,645,579.00 1.199 - - 10,020.00 0.070 10,020.00 0.070 5.838
3 Pekerjaan Lereng Timbunan m2 239,864.00 10,750.00 2,578,538,000.00 0.729 - - - - - - -
4 Pekerjaan Lereng Galian m2 43,586.82 12,150.00 529,579,863.00 0.150 - - - - - - -
5* Pekerjaan Jalan Akses ke Quary Ungkal m 5,300.00 315,000.00 1,669,500,000.00 0.472 - - - - - - -
6* Pembuatan Akses Kerja dalam ROW m 3,200.00 315,000.00 1,008,000,000.00 0.285 1,500.00 0.134 885.00 0.079 2,385.00 0.213 74.531

SUB JUMLAH : 11,275,263,442.00 3.190 0.204 0.290 0.495

II PEMBONGKARAN
1 Pembongkaran Pasangan Batu atau Bata m3 1,000.00 115,000.00 115,000,000.00 0.033 423.89 0.014 57.55 0.002 481.44 0.016 48.144
2 Pembongkaran Struktur m3 500.00 85,000.00 42,500,000.00 0.012 - - - - - - -
3 Pembongkaran Rumah m2 8,000.00 125,000.00 1,000,000,000.00 0.283 3,154.41 0.112 226.70 0.008 3,381.11 0.120 42.264

SUB JUMLAH : 1,157,500,000.00 0.327 0.125 0.010 0.135

III PEKERJAAN TANAH


1 Pembersihan Tempat Kerja m2 572,351.89 5,400.00 3,090,700,206.00 0.874 72,030.00 0.110 106,725.00 0.163 178,755.00 0.273 31.232
2 Galian Biasa untuk Dibuang (Waste) m3 291,817.77 39,200.00 11,439,256,584.00 3.236 - - - - - - -
3 Galian Biasa untuk Timbunan m3 878,803.89 46,600.00 40,952,261,274.00 11.585 - - 25,434.00 0.335 25,434.00 0.335 2.894
4 Galian Biasa untuk Material Pengisi di Median m3 12,904.24 35,000.00 451,648,400.00 0.128 - - - - - - -
5 Galian Batu Lunak untuk di Buang m3 - 58,200.00 - - - - -
6 Addiitonal Cost of Common Excavation as Waste Material with >2 km (each km) Rate Only 145,908.89 45,200.00 6,595,081,602.00 1.866 - - - - - - -
7 Common Borrow Material m3 894,998.44 145,820.00 130,508,672,520.80 36.921 7,876.00 0.325 - - 7,876.00 0.325 0.880
8 Common Embankment m3 - 41,500.00 - - - - -
9 Persiapan Badan Jalan (Subgrade Preparation) m2 175,170.11 14,350.00 2,513,691,078.50 0.711 - - - - - - -
10* Pengadaan Geotextile Stabilisator 75 KN/m (Geotextile Composite) m2 452,146.35 120,000.00 54,257,562,000.00 15.350 - - 27,040.00 0.918 27,040.00 0.918 5.980
11* Pemasangan Geotextile Stabilisator 75 KN/m (Geotextile Composite) m2 452,146.35 5,150.00 2,328,553,702.50 0.659 - - 806.00 0.001 806.00 0.001 0.178
12* Pengadaan Geotextile Filter Separator 11.5 KN/m (Geotextile Non Woven) m2 390,470.78 105,000.00 40,999,431,900.00 11.599 - - - - - - -
13* Pemasangan Geotextile Filter Separator 11.5 KN/m (Geotextile Non Woven) m2 390,470.78 5,150.00 2,010,924,517.00 0.569 - - - - - - -
14* Urugan Material Berbutir (Granular fill) m3 98,000.00 400,000.00 39,200,000,000.00 11.090 - - 90.00 0.010 90.00 0.010 0.092

SUB JUMLAH : 334,347,783,784.80 94.588 0.435 1.428 1.863

IV LAPIS PONDASI AGREGATE (Subgrade Preparation)


1 Lapis Pondasi Agregate Kelas A m3 15,349.07 318,160.00 4,883,460,111.20 1.382 - - - - - - -
2 Lapis Pondasi Agregate Kelas B m3 3,511.54 301,040.00 1,057,114,001.60 0.299 - - - - - - -
PROGRESS BULAN AGUSTUS
PEKERJAAN PEMBANGUNAN JALAN TOL CILEUNYI - SUMEDANG - DAWUAN (CISUMDAWU)
SEKSI 5A STA 43+300 s/d STA 46+500
PT. ADHI KARYA (PERSERO) ,Tbk PT. BINA MITRA INDOSEJAHTERA

NOMOR KONTRAK : - BULAN KE : 03


TANGGAL KONTRAK : - DARI TANGGAL : 30 Juli 2021
NILAI KONTRAK : - S/D TANGGAL : 02 September 2021
PENYIDIA JASA : PT. B M I S
PT. ADHI KARYA (PERSERO) ,Tbk
PENGUNA JASA :

KONTRAK AWAL REALISASI BOBOT


S/D BULAN LALU BULAN INI S/D BULAN INI PRESTASI
NO. URAIAN SATUAN HARGA SATUAN JUMLAH HARGA BOBOT
KUANTITAS BOBOT BOBOT BOBOT
KUANTITAS KUANTITAS KUANTITAS (%)
(Rp) (Rp) (%) (%) (%) (%)
SUB JUMLAH : 5,940,574,112.80 1.681 - - -
PROGRESS BULAN AGUSTUS
PEKERJAAN PEMBANGUNAN JALAN TOL CILEUNYI - SUMEDANG - DAWUAN (CISUMDAWU)
SEKSI 5A STA 43+300 s/d STA 46+500
PT. ADHI KARYA (PERSERO) ,Tbk PT. BINA MITRA INDOSEJAHTERA

NOMOR KONTRAK : - BULAN KE : 03


TANGGAL KONTRAK : - DARI TANGGAL : 30 Juli 2021
NILAI KONTRAK : - S/D TANGGAL : 02 September 2021
PENYIDIA JASA : PT. B M I S
PT. ADHI KARYA (PERSERO) ,Tbk
PENGUNA JASA :

KONTRAK AWAL REALISASI BOBOT


S/D BULAN LALU BULAN INI S/D BULAN INI PRESTASI
NO. URAIAN SATUAN HARGA SATUAN JUMLAH HARGA BOBOT
KUANTITAS BOBOT BOBOT BOBOT
KUANTITAS KUANTITAS KUANTITAS (%)
(Rp) (Rp) (%) (%) (%) (%)

V PEKERJAAN LAIN LAIN


1* Pemasangan Gorong Gorong RCP D = 60 cm bh 60.00 200,000.00 12,000,000.00 0.003 24.00 0.001 - - 24.00 0.001 40.000
2* Pemasangan Saluran Box Culvert D = 60 cm bh 75.00 200,000.00 15,000,000.00 0.004 8.00 0.000 - - 8.00 0.000 10.667
3* Pemasangan Saluran Box Culvert D = 80 cm bh 75.00 200,000.00 15,000,000.00 0.004 26.00 0.001 36.00 0.002 62.00 0.004 82.667
4* Pemasangan Saluran Box Culvert D = 2000 cm bh 25.00 250,000.00 6,250,000.00 0.002 12.00 0.001 - - 12.00 0.001 48.000
5* Pekerjaan Detour Sta 43+600 m' 150.00 315,000.00 47,250,000.00 0.013 - - 125.00 0.011 125.00 0.011 83.333
6* Pekerjaan Detour Sta 44+000 m' 150.00 315,000.00 47,250,000.00 0.013 116.00 0.010 - - 116.00 0.010 77.333
7* Pekerjaan Detour Sta 45+700 m' 150.00 315,000.00 47,250,000.00 0.013 - - - - - - -
8* Pekerjaan Detour Sta 46+000 m' 150.00 315,000.00 47,250,000.00 0.013 - - - - - - -
9* Pekerjaan Penimbunan Villa m3 855.61 315,000.00 269,516,583.00 0.076 855.61 0.076 - - 855.61 0.076 100.000
10* Penyiapan Disposal Area ls 1.00 - - - - -
11* Galian Saluran DS-5 m' 6,400.00 39,200.00 250,880,000.00 0.071 - - - - - - -

SUB JUMLAH : 757,646,583.00 0.214 0.091 0.013 0.104


TOTAL JUMLAH : 353,478,767,922.60 100.000 0.855 1.741 2.596

Diperiksa dan disetujui oleh, Dibuat oleh,


PENGUNA JASA PENYEDIA JASA
PT. ADHI KARYA (PERSERO), Tbk PT. BINA MITRA INDOSEJAHTERA

Sarining Setyo Prastowo Hendra


Project Manager Project Manager