LAPORAN MINGGUAN
NAMA PAKET : PEMBANGUNAN BANGUNAN PERKUATAN TEBING SUNGAI MEZAYA BULAN : SEPTEMBER
KONTRAKTOR : CV. YUDHA PRATAMA PERIODE MASA PELAKSANAAN : 120 HARI KALENDER
NOMOR KONTRAK : 602.1/468/PI-N/2022 WAKTU TERPAKAI : 74 HARI KALENDER
Bulan : Ke - 3 (Tiga)
TANGGAL KONTRAK : 06 JULI 2022 SISA WAKTU : 46 HARI KALENDER
NOMOR SPMK : 602.1/474/PI-N/2022
Minggu : Ke - 12 (Dua Belas)
TANGGAL SPMK : 07 JULI 2022
MASA PELAKSANAAN : 120 (SERATUS DUA PULUH) HARI KALENDER
Tanggal : 12 Sep. s/d 18 Sep. 2022
KONSULTAN SUPERVISI : CV. BABO CONSULTANT
(
MATA V
URAIAN PEKERJAAN B T % KET.
PEMBAYAR JUMLAH HARGA
O A MG - 1 MG - 2 MG - 3 MG - 4 MG - 5 MG - 6 MG - 7 MG - 8 MG - 9 MG - 10 MG - 11 MG - 12 MG - 13 MG - 14 MG - 15 MG - 16 MG - 17 MG - 18 MG - 19 MG - 20
AAN (Rp.)
)
T L
07/7 - 10/7 11/7 - 17/7 18/7 - 24/7 25/7 - 31/7 01/8 - 07/8 08/8 - 14/8 15/8 - 21/8 22/8 - 28/8 29/8 - 31/8 01/9 - 04/9 05/9 - 11/9 12/9 - 18/9 19/9 - 25/9 26/9 - 30/9 01/10 - 02/10 03/10 - 09/10 10/10 - 16/10 17/10 - 23/10 24/10 - 31/10 01/11 - 03/11
100
1 Mobilisasi / Demobilisasi Alat 12,500,000.00 0.902% 0.070% 0.070% 0.070% 0.070% 0.070% 0.070% 0.070% 0.070% 0.070% 0.271%
80
B. PEKERJAAN KONSTRUKSI
70
1 Galian Tanah dengan Alat Berat 26,423,977.99 1.908% 0.119% 0.119% 0.204% 0.204% 0.204% 0.204% 0.204% 0.204% 0.204% 0.119% 0.119%
2 Pasangan Bronjong Type 1 457,218,851.50 33.007% 2.063% 2.063% 3.536% 3.536% 3.536% 3.536% 3.536% 3.536% 3.536% 2.063% 2.063% 60
3 Pasangan Bronjong Type 2 417,547,171.80 30.143% 1.884% 1.884% 3.230% 3.230% 3.230% 3.230% 3.230% 3.230% 3.230% 1.884% 1.884% 50
4 Pasangan Bronjong Type 3 141,956,714.03 10.248% 1.281% 1.537% 1.537% 1.537% 1.537% 1.537% 1.281%
40
5 Pekerjaan Timbunan Tanah atau Pengurugan Kembali 261,396,934.14 18.871% 1.179% 1.179% 2.359% 2.359% 2.359% 2.359% 2.359% 2.359% 1.179% 1.179%
30
6 Pekerjaan Pemasangan Geotex 45,213,061.20 3.264% 0.204% 0.204% 0.408% 0.408% 0.408% 0.408% 0.408% 0.408% 0.204% 0.204%
7 Pekerjaan Pengeringan dengan Pompa (2 Unit) 4,500,000.00 0.325% 0.020% 0.020% 0.024% 0.024% 0.024% 0.024% 0.024% 0.024% 0.024% 0.024% 0.024% 0.024% 0.020% 0.020% 20
1 Biaya Keselamatan Konstruksi 18,450,000.00 1.332% 0.067% 0.067% 0.067% 0.067% 0.067% 0.067% 0.067% 0.067% 0.067% 0.067% 0.067% 0.067% 0.067% 0.067% 0.067% 0.067% 0.067% 0.067% 0.067% 0.067%
0
TOTAL NILAI FISIK PEKERJAAN 1,385,206,710.66 100.00%
PROGRESS MINGGUAN 0.137% 0.137% 0.137% 0.137% 0.137% 0.276% 4.223% 4.312% 8.617% 9.982% 10.186% 11.366% 11.366% 11.366% 11.024% 6.924% 6.601% 1.470% 1.266% 0.337%
RENCANA
KOMULATIF PROGRESS MINGGUAN 0 0.137% 0.274% 0.410% 0.547% 0.684% 0.960% 5.183% 9.496% 18.113% 28.095% 38.281% 49.646% 61.012% 72.377% 83.401% 90.325% 96.926% 98.396% 99.663% 100.000%
PROGRESS MINGGUAN 0.018% 0.018% 0.018% 0.018% 0.018% 0.018% 2.289% 6.343% 7.830% 2.584% 16.914% 11.367%
REALISASI
KOMULATIF PROGRESS MINGGUAN 0 0.018% 0.036% 0.054% 0.072% 0.090% 0.108% 2.397% 8.740% 16.570% 19.154% 36.067% 47.435%
DEVIASI -0.119% -0.237% -0.356% -0.475% -0.594% -0.852% -2.786% -0.756% -1.543% -8.941% -2.213% -2.212%