LAPORAN BULANAN KEADAAN DANA

NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020


NO. SPMK DAN TANGGAL : IK.02.04/SPMK/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Agustus 2020 / Invoice 01
TANGGAL : 01 September 2020
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

NO. JLH. PEMBAYARAN TAGIHAN INVOICE JLH. PEMBAYARAN SISA DANA


URAIAN TOTAL DANA
S/D BULAN LALU NO. 01 S/D BULAN INI Rp.

I. BIAYA LANGSUNG PERSONIL 4,166,344,500.00 - 48,808,655.00 48,808,655.00 4,117,535,845.00


-
II. BIAYA LANGSUNG NON PERSONIL 1,285,850,000.00 - 21,774,500.00 21,774,500.00 1,264,075,500.00
BIAYA MOBILISASI DAN DEMOBILISASI - - - - -
BIAYA PERJALANAN DINAS 21,600,000.00 - - - 21,600,000.00
BIAYA KANTOR 335,000,000.00 - 5,762,000.00 5,762,000.00 329,238,000.00
BIAYA PELAPORAN 26,250,000.00 - 1,500,000.00 1,500,000.00 24,750,000.00
BIAYA AKOMODASI 903,000,000.00 - 14,512,500.00 14,512,500.00 888,487,500.00

SUB TOTAL (I+II) 5,452,194,500.00 - 70,583,155.00 70,583,155.00 5,381,611,345.00


PPN 545,219,450.00 - 7,058,315.50 7,058,315.50 538,161,134.50
SUB TOTAL 5,997,413,950.00 - 77,641,470.50 77,641,470.50 5,919,772,479.50
NILAI KONTRAK DIBULATKAN 5,997,413,000.00
PENGEMBALIAN UANG MUKA 899,611,950.00 - 10,000,000.00 10,000,000.00 889,611,950.00
TOTAL 5,097,801,050.00 - 67,641,470.50 67,641,470.50 5,030,160,529.50
DIBULATKAN - 67,641,471.00 67,641,471.00 5,030,160,530.00

1,199,482,600.00

Jayapura, 01 September 2020

PPK PENGAWASAN Konsultan Supervisi


SATKER P2JN PROVINSI PAPUA (JAYAPURA)
PT. WINSOLUSI KONSULTAN

SAM RANDA, S.T, M.Eng ISNAINI SYAWIK, ST


NIP. 19830422 200801 1 006 Direktur Utama
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/SPMK/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Agustus 2020 / Invoice 01
TANGGAL : 01 September 2020
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

REKAPITULASI INVOICE

NO. URAIAN BIAYA (Rp.)

I. BIAYA LANGSUNG PERSONIL 48,808,655.00

II. BIAYA LANGSUNG NON PERSONIL 21,774,500.00


BIAYA MOBILISASI DAN DEMOBILISASI -
BIAYA PERJALANAN DINAS -
BIAYA KANTOR 5,762,000.00
BIAYA PELAPORAN 1,500,000.00
BIAYA AKOMODASI 14,512,500.00

SUB TOTAL ( I + II ) 70,583,155.00


PPN 10% 7,058,315.50
SUB TOTAL 77,641,470.50
PENGEMBALIAN UANG MUKA 15% 10,000,000.00
TOTAL 67,641,470.50
DIBULATKAN 67,641,471.00

Total Pembayaran pada Tagihan ini Rp. 67,641,471.00


Terbilang : Err:511

Mohon Tagihan untuk bulan Agustus 2020 dimasukan pada rekening PT. WINSOLUSI KONSULTAN Nomor Rekening :
0416.01.000160.300 BRI Cabang Kelapa Gading 2

Jayapura, 01 September 2020


PPK PENGAWASAN Konsultan Supervisi
SATKER P2JN PROVINSI PAPUA (JAYAPURA)
PT. WINSOLUSI KONSULTAN

SAM RANDA, S.T, M.Eng ISNAINI SYAWIK, ST


NIP. 19830422 200801 1 006 Direktur Utama
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/SPMK/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Agustus 2020 / Invoice 01
TANGGAL : 01 September 2020
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

II. BIAYA LANGSUNG NON PERSONIL


HARGA PEMBAYARAN TAGIHAN INVOICE NO. 01 PEMBAYARAN
JUMLAH HARGA
SATUAN S/D (Bulan Agustus 2020) S/D SISA DANA
NO. URAIAN JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU JUMLAH BULAN INI
ORANG TRIP
(Rp) (RP) (Rp) (Rp)
a MOBILISASI DAN DEMOBILISASI
- Mobilisasi
Site Supervision Engineer - - Trip - - - - - - - -
Quality Engineer-1 - - Trip - - - - - - - -
Inspection Engineer/Quantity Engineer - - Trip - - - - - - - -
Health Safety Enviroment Engineer - - - - - - - - - -
- Demobilisasi
Site Supervision Engineer - - Trip - - - - - - - -
Quality Engineer-1 - - Trip - - - - - - - -
Inspection Engineer/Quantity Engineer - - Trip - - - - - - - -
Health Safety Enviroment Engineer - - Trip - - - - - - - -
Sub Total a - - - - -
b BIAYA PERJALANAN DINAS
Tiket Perjalanan (PP) Termasuk Ongkos Taxi 6.00 Trip 2,000,000.00 12,000,000.00 - - - - - 12,000,000.00
Biaya Penginapan 24.00 Hari 400,000.00 9,600,000.00 - - - - - 9,600,000.00

Sub Total b 21,600,000.00 - - - 21,600,000.00


HARGA PEMBAYARAN TAGIHAN INVOICE NO. 01 PEMBAYARAN
SATUAN JUMLAH HARGA S/D (Bulan Agustus 2020) S/D SISA DANA
NO. URAIAN JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU JUMLAH BULAN INI
VOLUME BULAN
(Rp) (RP) (Rp) (Rp)
c BIAYA KANTOR
Sewa Kantor 1.00 25.00 Bln 5,000,000.00 125,000,000.00 - 1.00 0.43 2,150,000.00 2,150,000.00 122,850,000.00
Biaya Operasional Kantor (Air dan Listrik) 1.00 25.00 Bln 1,500,000.00 37,500,000.00 - 1.00 0.43 645,000.00 645,000.00 36,855,000.00
Sewa Penunjang Kantor :
- Laptop-1 1.00 25.00 Bln 1,600,000.00 40,000,000.00 - 1.00 0.43 688,000.00 688,000.00 39,312,000.00
- Laptop-2 1.00 25.00 Bln 1,600,000.00 40,000,000.00 - 1.00 0.43 688,000.00 688,000.00 39,312,000.00
- Printer A3 1.00 25.00 Bln 700,000.00 17,500,000.00 - 1.00 0.43 301,000.00 301,000.00 17,199,000.00
- Printer A4 1.00 25.00 Bln 500,000.00 12,500,000.00 - 1.00 0.43 215,000.00 215,000.00 12,285,000.00
Komunikasi (Pulsa Telepon + lnternet) 1.00 25.00 Bln 1,500,000.00 37,500,000.00 - 1.00 0.43 645,000.00 645,000.00 36,855,000.00
Bahan untuk peralatan kantor 1.00 25.00 Bln 1,000,000.00 25,000,000.00 - 1.00 0.43 430,000.00 430,000.00 24,570,000.00

Sub Total c 335,000,000.00 - 5,762,000.00 5,762,000.00 329,238,000.00


d BIAYA PELAPORAN
Laporan RMK 5.00 5.00 Eks 150,000.00 750,000.00 - 5.00 1.00 750,000.00 750,000.00 -
Laporan Pendahuluan 5.00 5.00 Eks 150,000.00 750,000.00 - 5.00 1.00 750,000.00 750,000.00 -
Laporan Bulanan 125.00 5.00 Eks 100,000.00 12,500,000.00 - - - - - 12,500,000.00
Laporan Triwulan 40.00 5.00 Eks 250,000.00 10,000,000.00 - - - - - 10,000,000.00
Laporan Akhir 5.00 5.00 Eks 250,000.00 1,250,000.00 - - - - - 1,250,000.00
Hard Disk (File Laporan dan Dokumentasi) 1.00 1.00 Buah 1,000,000.00 1,000,000.00 - - - - - 1,000,000.00

Sub Total d 26,250,000.00 - 1,500,000.00 1,500,000.00 24,750,000.00

e BIAYA AKOMODASI
- Biaya Sewa
Sewa Mobil Double Gardan-1 1.00 25.00 Bln 25,000,000.00 625,000,000.00 - 1.00 0.43 10,750,000.00 10,750,000.00 614,250,000.00
Sewa Motor Lapangan -1 1.00 25.00 Bln 2,500,000.00 62,500,000.00 - 1.00 0.43 1,075,000.00 1,075,000.00 61,425,000.00
Sewa Motor Lapangan -2 1.00 25.00 Bln 2,500,000.00 62,500,000.00 - 1.00 0.43 1,075,000.00 1,075,000.00 61,425,000.00
- Tunjangan Perumahan
Site Supervision Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 - 1.00 0.43 430,000.00 430,000.00 24,570,000.00
Quality Engineer-1 1.00 24.00 Bln 1,000,000.00 24,000,000.00 - 1.00 - - - 24,000,000.00
Inspection Engineer/Quantity Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 - 1.00 0.43 430,000.00 430,000.00 24,570,000.00
Health Safety Enviroment Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 - 1.00 0.43 430,000.00 430,000.00 24,570,000.00
Inspector -1 1.00 23.00 Bln 750,000.00 17,250,000.00 - 1.00 - - - 17,250,000.00
Surveyor Technician -1 1.00 25.00 Bln 750,000.00 18,750,000.00 - 1.00 0.43 322,500.00 322,500.00 18,427,500.00
Material Technician -1 1.00 24.00 Bln 750,000.00 18,000,000.00 - 1.00 - - - 18,000,000.00

Sub Total e 903,000,000.00 - 14,512,500.00 14,512,500.00 888,487,500.00

Sub Total a+b+c+d+e 1,285,850,000.00 - 21,774,500.00 21,774,500.00 1,264,075,500.00


NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/SPMK/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Agustus 2020 / Invoice 01
TANGGAL : 01 September 2020
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

I. BIAYA LANGSUNG PERSONIL


HARGA JUMLAH HARGA PEMBAYARAN TAGIHAN INVOICE NO. 01 PEMBAYARAN
URAIAN SATUAN S/D (Bulan Agustus 2020) S/D SISA DANA
NO. JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU ORANG WAKTU/ JUMLAH BULAN INI
(Rp) BULAN (RP) (Rp) (Rp)
a BIAYA TENAGA AHLI
Site Supervision Engineer 1.00 25.00 OB 32,697,000.00 817,425,000.00 - 1.00 0.43 14,059,710.00 14,059,710.00 803,365,290.00
Quality Engineer-1 1.00 24.00 OB 30,880,500.00 741,132,000.00 - 1.00 - - - 741,132,000.00
Inspection Engineer/Quantity Engineer 1.00 25.00 OB 30,880,500.00 772,012,500.00 - 1.00 0.43 13,278,615.00 13,278,615.00 758,733,885.00
Health Safety Enviroment Engineer 1.00 25.00 OB 25,431,000.00 635,775,000.00 - 1.00 0.43 10,935,330.00 10,935,330.00 624,839,670.00

Sub Total a 2,966,344,500.00 - 38,273,655.00 38,273,655.00 2,928,070,845.00


b BIAYA ASISTEN TENAGA AHLI
Inspector -1 1.00 23.00 OB 12,500,000.00 287,500,000.00 - 1.00 - - - 287,500,000.00
Surveyor Technician -1 1.00 25.00 OB 12,500,000.00 312,500,000.00 - 1.00 0.43 5,375,000.00 5,375,000.00 307,125,000.00
Material Technician -1 1.00 24.00 OB 12,500,000.00 300,000,000.00 - 1.00 - - - 300,000,000.00

Sub Total b 900,000,000.00 - 5,375,000.00 5,375,000.00 894,625,000.00


c BIAYA STAF PENDUKUNG
Operator Komputer 1.00 25.00 OB 8,000,000.00 200,000,000.00 - 1.00 0.43 3,440,000.00 3,440,000.00 196,560,000.00
Pesuruh/Penjaga Kantor 1.00 25.00 OB 4,000,000.00 100,000,000.00 - 1.00 0.43 1,720,000.00 1,720,000.00 98,280,000.00

Sub Total c 300,000,000.00 - 5,160,000.00 5,160,000.00 294,840,000.00

TOTAL a+b+c 4,166,344,500.00 - - - 48,808,655.00 48,808,655.00 4,117,535,845.00


LAPORAN BULANAN KEADAAN DANA
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/SPMK/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : September 2020 / Invoice 02
TANGGAL : 01 Oktober 2020
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

NO. JLH. PEMBAYARAN TAGIHAN INVOICE JLH. PEMBAYARAN SISA DANA


URAIAN TOTAL DANA
S/D BULAN LALU NO. 02 S/D BULAN INI Rp.

I. BIAYA LANGSUNG PERSONIL 4,166,344,500.00 48,808,655.00 130,860,700.00 179,669,355.00 3,986,675,145.00


-
II. BIAYA LANGSUNG NON PERSONIL 1,285,850,000.00 21,774,500.00 48,350,000.00 70,124,500.00 1,215,725,500.00
BIAYA MOBILISASI DAN DEMOBILISASI - - - - -
BIAYA PERJALANAN DINAS 21,600,000.00 - - - 21,600,000.00
BIAYA KANTOR 335,000,000.00 5,762,000.00 13,400,000.00 19,162,000.00 315,838,000.00
BIAYA PELAPORAN 26,250,000.00 1,500,000.00 500,000.00 2,000,000.00 24,250,000.00
BIAYA AKOMODASI 903,000,000.00 14,512,500.00 34,450,000.00 48,962,500.00 854,037,500.00

SUB TOTAL (I+II) 5,452,194,500.00 70,583,155.00 179,210,700.00 249,793,855.00 5,202,400,645.00


PPN 545,219,450.00 7,058,315.50 17,921,070.00 24,979,385.50 520,240,064.50
SUB TOTAL 5,997,413,950.00 77,641,470.50 197,131,770.00 274,773,240.50 5,722,640,709.50
NILAI KONTRAK DIBULATKAN 5,997,413,000.00
PENGEMBALIAN UANG MUKA 899,611,950.00 10,000,000.00 79,961,195.00 89,961,195.00 809,650,755.00
TOTAL 5,097,801,050.00 67,641,470.50 117,170,575.00 184,812,045.50 4,912,989,954.50
DIBULATKAN 67,641,471.00 117,170,575.00 184,812,046.00 4,912,989,955.00

1,199,482,600.00

Jayapura, 01 Oktober 2020

PPK PENGAWASAN Konsultan Supervisi


SATKER P2JN PROVINSI PAPUA (JAYAPURA)
PT. WINSOLUSI KONSULTAN

SAM RANDA, S.T, M.Eng ISNAINI SYAWIK, ST


NIP. 19830422 200801 1 006 Direktur Utama
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/SPMK/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : September 2020 / Invoice 02
TANGGAL : 01 Oktober 2020
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

REKAPITULASI INVOICE

NO. URAIAN BIAYA (Rp.)

I. BIAYA LANGSUNG PERSONIL 130,860,700.00

II. BIAYA LANGSUNG NON PERSONIL 48,350,000.00


BIAYA MOBILISASI DAN DEMOBILISASI -
BIAYA PERJALANAN DINAS -
BIAYA KANTOR 13,400,000.00
BIAYA PELAPORAN 500,000.00
BIAYA AKOMODASI 34,450,000.00

SUB TOTAL ( I + II ) 179,210,700.00


PPN 10% 17,921,070.00
SUB TOTAL 197,131,770.00
PENGEMBALIAN UANG MUKA 15% 79,961,195.00
TOTAL 117,170,575.00
DIBULATKAN 117,170,575.00

Total Pembayaran pada Tagihan ini Rp. 117,170,575.00


Terbilang : Err:511

Mohon Tagihan untuk bulan September 2020 dimasukan pada rekening PT. WINSOLUSI KONSULTAN Nomor Rekening :
0416.01.000160.300 BRI Cabang Kelapa Gading 2

Jayapura, 01 Oktober 2020


PPK PENGAWASAN Konsultan Supervisi
SATKER P2JN PROVINSI PAPUA (JAYAPURA)
PT. WINSOLUSI KONSULTAN

SAM RANDA, S.T, M.Eng ISNAINI SYAWIK, ST


NIP. 19830422 200801 1 006 Direktur Utama
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/SPMK/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : September 2020 / Invoice 02
TANGGAL : 01 Oktober 2020
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

I. BIAYA LANGSUNG PERSONIL


HARGA JUMLAH HARGA PEMBAYARAN TAGIHAN INVOICE NO. 02 PEMBAYARAN
URAIAN SATUAN S/D (Bulan September 2020) S/D SISA DANA
NO. JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU ORANG WAKTU/ JUMLAH BULAN INI
(Rp) BULAN (RP) (Rp) (Rp)
a BIAYA TENAGA AHLI
Site Supervision Engineer 1.00 25.00 OB 32,697,000.00 817,425,000.00 14,059,710.00 1.00 1.00 32,697,000.00 46,756,710.00 770,668,290.00
Quality Engineer-1 1.00 24.00 OB 30,880,500.00 741,132,000.00 - 1.00 0.40 12,352,200.00 12,352,200.00 728,779,800.00
Inspection Engineer/Quantity Engineer 1.00 25.00 OB 30,880,500.00 772,012,500.00 13,278,615.00 1.00 1.00 30,880,500.00 44,159,115.00 727,853,385.00
Health Safety Enviroment Engineer 1.00 25.00 OB 25,431,000.00 635,775,000.00 10,935,330.00 1.00 1.00 25,431,000.00 36,366,330.00 599,408,670.00

Sub Total a 2,966,344,500.00 38,273,655.00 101,360,700.00 139,634,355.00 2,826,710,145.00


b BIAYA ASISTEN TENAGA AHLI
Inspector -1 1.00 23.00 OB 12,500,000.00 287,500,000.00 - - - - - 287,500,000.00
Surveyor Technician -1 1.00 25.00 OB 12,500,000.00 312,500,000.00 5,375,000.00 1.00 1.00 12,500,000.00 17,875,000.00 294,625,000.00
Material Technician -1 1.00 24.00 OB 12,500,000.00 300,000,000.00 - 1.00 0.40 5,000,000.00 5,000,000.00 295,000,000.00

Sub Total b 900,000,000.00 5,375,000.00 17,500,000.00 22,875,000.00 877,125,000.00


c BIAYA STAF PENDUKUNG
Operator Komputer 1.00 25.00 OB 8,000,000.00 200,000,000.00 3,440,000.00 1.00 1.00 8,000,000.00 11,440,000.00 188,560,000.00
Pesuruh/Penjaga Kantor 1.00 25.00 OB 4,000,000.00 100,000,000.00 1,720,000.00 1.00 1.00 4,000,000.00 5,720,000.00 94,280,000.00

Sub Total c 300,000,000.00 5,160,000.00 12,000,000.00 17,160,000.00 282,840,000.00

TOTAL a+b+c 4,166,344,500.00 48,808,655.00 - - 130,860,700.00 179,669,355.00 3,986,675,145.00


NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/SPMK/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : September 2020 / Invoice 02
TANGGAL : 01 Oktober 2020
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

II. BIAYA LANGSUNG NON PERSONIL


HARGA PEMBAYARAN TAGIHAN INVOICE NO. 02 PEMBAYARAN
JUMLAH HARGA
SATUAN S/D (Bulan September 2020) S/D SISA DANA
NO. URAIAN JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU JUMLAH BULAN INI
ORANG TRIP
(Rp) (RP) (Rp) (Rp)
a MOBILISASI DAN DEMOBILISASI
- Mobilisasi
Site Supervision Engineer - - Trip - - - - - - - -
Quality Engineer-1 - - Trip - - - - - - - -
Inspection Engineer/Quantity Engineer - - Trip - - - - - - - -
Health Safety Enviroment Engineer - - - - - - - - - -
- Demobilisasi
Site Supervision Engineer - - Trip - - - - - - - -
Quality Engineer-1 - - Trip - - - - - - - -
Inspection Engineer/Quantity Engineer - - Trip - - - - - - - -
Health Safety Enviroment Engineer - - Trip - - - - - - - -
Sub Total a - - - - -
b BIAYA PERJALANAN DINAS
Tiket Perjalanan (PP) Termasuk Ongkos Taxi 6.00 Trip 2,000,000.00 12,000,000.00 - - - - - 12,000,000.00
Biaya Penginapan 24.00 Hari 400,000.00 9,600,000.00 - - - - - 9,600,000.00

Sub Total b 21,600,000.00 - - - 21,600,000.00


HARGA PEMBAYARAN TAGIHAN INVOICE NO. 02 PEMBAYARAN
SATUAN JUMLAH HARGA S/D (Bulan September 2020) S/D SISA DANA
NO. URAIAN JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU JUMLAH BULAN INI
VOLUME BULAN
(Rp) (RP) (Rp) (Rp)
c BIAYA KANTOR
Sewa Kantor 1.00 25.00 Bln 5,000,000.00 125,000,000.00 2,150,000.00 1.00 1.00 5,000,000.00 7,150,000.00 117,850,000.00
Biaya Operasional Kantor (Air dan Listrik) 1.00 25.00 Bln 1,500,000.00 37,500,000.00 645,000.00 1.00 1.00 1,500,000.00 2,145,000.00 35,355,000.00
Sewa Penunjang Kantor :
- Laptop-1 1.00 25.00 Bln 1,600,000.00 40,000,000.00 688,000.00 1.00 1.00 1,600,000.00 2,288,000.00 37,712,000.00
- Laptop-2 1.00 25.00 Bln 1,600,000.00 40,000,000.00 688,000.00 1.00 1.00 1,600,000.00 2,288,000.00 37,712,000.00
- Printer A3 1.00 25.00 Bln 700,000.00 17,500,000.00 301,000.00 1.00 1.00 700,000.00 1,001,000.00 16,499,000.00
- Printer A4 1.00 25.00 Bln 500,000.00 12,500,000.00 215,000.00 1.00 1.00 500,000.00 715,000.00 11,785,000.00
Komunikasi (Pulsa Telepon + lnternet) 1.00 25.00 Bln 1,500,000.00 37,500,000.00 645,000.00 1.00 1.00 1,500,000.00 2,145,000.00 35,355,000.00
Bahan untuk peralatan kantor 1.00 25.00 Bln 1,000,000.00 25,000,000.00 430,000.00 1.00 1.00 1,000,000.00 1,430,000.00 23,570,000.00

Sub Total c 335,000,000.00 5,762,000.00 13,400,000.00 19,162,000.00 315,838,000.00


d BIAYA PELAPORAN
Laporan RMK 5.00 5.00 Eks 150,000.00 750,000.00 750,000.00 - - - 750,000.00 -
Laporan Pendahuluan 5.00 5.00 Eks 150,000.00 750,000.00 750,000.00 - - - 750,000.00 -
Laporan Bulanan 125.00 5.00 Eks 100,000.00 12,500,000.00 - 5.00 1.00 500,000.00 500,000.00 12,000,000.00
Laporan Triwulan 40.00 5.00 Eks 250,000.00 10,000,000.00 - - - - - 10,000,000.00
Laporan Akhir 5.00 5.00 Eks 250,000.00 1,250,000.00 - - - - - 1,250,000.00
Hard Disk (File Laporan dan Dokumentasi) 1.00 1.00 Buah 1,000,000.00 1,000,000.00 - - - - - 1,000,000.00

Sub Total d 26,250,000.00 1,500,000.00 500,000.00 2,000,000.00 24,250,000.00


e BIAYA AKOMODASI
- Biaya Sewa
Sewa Mobil Double Gardan-1 1.00 25.00 Bln 25,000,000.00 625,000,000.00 10,750,000.00 1.00 1.00 25,000,000.00 35,750,000.00 589,250,000.00
Sewa Motor Lapangan -1 1.00 25.00 Bln 2,500,000.00 62,500,000.00 1,075,000.00 1.00 1.00 2,500,000.00 3,575,000.00 58,925,000.00
Sewa Motor Lapangan -2 1.00 25.00 Bln 2,500,000.00 62,500,000.00 1,075,000.00 1.00 1.00 2,500,000.00 3,575,000.00 58,925,000.00
- Tunjangan Perumahan
Site Supervision Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 430,000.00 1.00 1.00 1,000,000.00 1,430,000.00 23,570,000.00
Quality Engineer-1 1.00 24.00 Bln 1,000,000.00 24,000,000.00 - 1.00 0.40 400,000.00 400,000.00 23,600,000.00
Inspection Engineer/Quantity Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 430,000.00 1.00 1.00 1,000,000.00 1,430,000.00 23,570,000.00
Health Safety Enviroment Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 430,000.00 1.00 1.00 1,000,000.00 1,430,000.00 23,570,000.00
Inspector -1 1.00 23.00 Bln 750,000.00 17,250,000.00 - 1.00 - - - 17,250,000.00
Surveyor Technician -1 1.00 25.00 Bln 750,000.00 18,750,000.00 322,500.00 1.00 1.00 750,000.00 1,072,500.00 17,677,500.00
Material Technician -1 1.00 24.00 Bln 750,000.00 18,000,000.00 - 1.00 0.40 300,000.00 300,000.00 17,700,000.00

Sub Total e 903,000,000.00 14,512,500.00 34,450,000.00 48,962,500.00 854,037,500.00

Sub Total a+b+c+d+e 1,285,850,000.00 21,774,500.00 48,350,000.00 70,124,500.00 1,215,725,500.00


Kompleks Bina Marga Tanah Hitam Jl.Abepantai Telp. (0967) 587136, Fax. (0967) 587136

BERITA ACARA PEMERIKSAAN PEKERJAAN


No.:

Pekerjaan : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)


Lokasi : Wilayah Satker PJN Wilayah I (Jayapura)
Tanggal #REF!

Pada hari ini Jumat tanggal Dua Puluh bulan Desember tahun Dua Ribu Sembilan Belas, Kami yang bertanda
tangan di bawah ini : PPK Pengawasan Satker Perencanaan dan Pengawasan Jalan Nasional Provinsi Papua,
Pengawasan Teknis Jembatan Ruas Mugi - Batas Batu (MYC) yang di laksanakan oleh PT. WINSOLUSI
KONSULTAN, PT. ANUGERAH KRIDA PRADANA, KSO berdasarkan Kontrak Nomor :
HK.02.03/PW.MYC.JBT.MUGI-BTS.BATU/APBN/P2JN-PUA/002/2017, Tanggal 03 Maret 2017, SPMK
Nomor : IK.02.04/SPMK/PW.MYC.JBT.MUGI-BTS.BATU/APBN/P2JN-PUA/002/2017, Tanggal 13 Maret
2017

1. NILAI KONTRAK
A. BIAYA LANGSUNG PERSONIL
1. BIAYA TENAGA AHLI : Rp. 2,966,344,500
2. BIAYA ASISTEN TENAGA AHLI : Rp. 900,000,000
3. BIAYA STAFF PENDUKUNG : Rp. 300,000,000

B. BIAYA LANGSUNG NON PERSONIL


1. BIAYA MOBILISASI DAN DEMOBILISASI : Rp. -
2. BIAYA PERJALANAN DINAS : Rp. 21,600,000
3. BIAYA KANTOR : Rp. 335,000,000
4. BIAYA PELAPORAN : Rp. 26,250,000
5. BIAYA AKOMODASI : Rp. 903,000,000

SUB JUMLAH : Rp. 5,452,194,500


PPN 10% : Rp. 545,219,450
JUMLAH : Rp. 5,997,413,950
PEMBULATAN : Rp. 5,997,413,420
2. PEMBAYARAN

Pembiayaan Invoice XXXIV bulan Desember 2019 / 34 yang telah dikeluarkan dan dipertanggung jawabkan
kepada Satuan Kerja Perencanaan & Pengawasan Jalan Nasional Propinsi Papua Tahun Anggaran 2018 Meliputi :

A. BIAYA LANGSUNG PERSONIL


1. BIAYA TENAGA AHLI : Rp. #REF!
2. BIAYA ASISTEN TENAGA AHLI : Rp. #REF!
3. BIAYA STAFF PENDUKUNG : Rp. #REF!
B. BIAYA LANGSUNG NON PERSONIL
1. BIAYA MOBILISASI DAN DEMOBILISASI : Rp. -
2. BIAYA PERJALANAN DINAS : Rp. -
3. BIAYA KANTOR : Rp. #REF!
4. BIAYA PELAPORAN : Rp. #REF!
5. BIAYA AKOMODASI : Rp. #REF!

SUB JUMLAH : Rp. #REF!


PPN 10% : Rp. #REF!
JUMLAH : Rp. #REF!
PENGEMBALIAN UANG MUKA : Rp. -
TOTAL : Rp. #REF!
PEMBULATAN : Rp. #REF!

Err:511

Jumlah ini akan dibayarkan melalui rekening :

PT. WINSOLUSI KONSULTAN Nomor Rekening : 0416.01.000160.300 BRI Cabang Kelapa Gading 2

Demikian Berita Acara ini dibuat dengan sebenarnya dalam rangkap 7 (tujuh) untuk dipergunakan seperlunya.

PPK PENGAWASAN
PT. WINSOLUSI KONSULTAN
SATKER P2JN PROVINSI PAPUA
(JAYAPURA)

ISNAINI SYAWIK, ST A. FADHOLI KARIM, ST


DIREKTUR UTAMA NIP. 19850313 201012 1 001
Kompleks Bina Marga Tanah Hitam Jl.Abepantai Telp. (0967) 587136, Fax. (0967) 587136

BERITA ACARA PEMERIKSAAN PEKERJAAN


No.:

Pekerjaan : PENGAWASAN TEKNIS PEMBANGUNAN JALAN MEMBERAMO - ELELIM II (MYC)


Lokasi : Satker PJN Wilayah I (Jayapura)
Tanggal : 01 Oktkober 2020

Pada hari ini Kamis tanggal Satu bulan Oktober tahun Dua Ribu Dua Puluh, Kami yang bertanda tangan di
bawah ini : PPK Pengawasan Satker Perencanaan dan Pengawasan Jalan Nasional Provinsi Papua (Jayapura),
PENGAWASAN TEKNIS PEMBANGUNAN JALAN MEMBERAMO - ELELIM II (MYC) yang
dilaksanakan oleh PT. WINSOLUSI KONSULTAN berdasarkan Kontrak Nomor :
HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, Tanggal, tanggal 18 Agustus 2020, SPMK Nomor :
IK.02.04/SPMK/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, Tanggal tanggal 19 Agustus 2020

1. NILAI KONTRAK
A. BIAYA LANGSUNG PERSONIL
1. BIAYA TENAGA AHLI : Rp. 2,966,344,500
2. BIAYA ASISTEN TENAGA AHLI : Rp. 900,000,000
3. BIAYA STAFF PENDUKUNG : Rp. 300,000,000

B. BIAYA LANGSUNG NON PERSONIL


1. BIAYA MOBILISASI DAN DEMOBILISASI : Rp. -
2. BIAYA PERJALANAN DINAS : Rp. 21,600,000
3. BIAYA KANTOR : Rp. 335,000,000
4. BIAYA PELAPORAN : Rp. 26,250,000
5. BIAYA AKOMODASI : Rp. 903,000,000

SUB JUMLAH : Rp. 5,452,194,500


PPN 10% : Rp. 545,219,450
JUMLAH : Rp. 5,997,413,950
PEMBULATAN : Rp. 5,997,413,000
2. PEMBAYARAN
Pembiayaan Invoice II bulan September 2020 / 02 yang telah dikeluarkan dan dipertanggung jawabkan kepada
Satuan Kerja Perencanaan & Pengawasan Jalan Nasional Propinsi Papua (Jayapura) Tahun Anggaran 2020
Meliputi :
A. BIAYA LANGSUNG PERSONIL
1. BIAYA TENAGA AHLI : Rp. 101,360,700
2. BIAYA ASISTEN TENAGA AHLI : Rp. 17,500,000
3. BIAYA STAFF PENDUKUNG : Rp. 12,000,000
B. BIAYA LANGSUNG NON PERSONIL
1. BIAYA MOBILISASI DAN DEMOBILISASI : Rp. -
2. BIAYA PERJALANAN DINAS : Rp. -
3. BIAYA KANTOR : Rp. 13,400,000
4. BIAYA PELAPORAN : Rp. 500,000
5. BIAYA AKOMODASI : Rp. 34,450,000

SUB JUMLAH : Rp. 179,210,700


PPN 10% : Rp. 17,921,070
JUMLAH : Rp. 197,131,770
PENGEMBALIAN UANG MUKA : Rp. 79,961,195
TOTAL : Rp. 117,170,575
PEMBULATAN : Rp. 117,170,575

Err:511

Jumlah ini akan dibayarkan melalui rekening :

PT. WINSOLUSI KONSULTAN Nomor Rekening : 0416.01.000160.300 BRI Cabang Kelapa Gading 2

Demikian Berita Acara ini dibuat dengan sebenarnya dalam rangkap 7 (tujuh) untuk dipergunakan seperlunya.

PPK PENGAWASAN
PT. WINSOLUSI KONSULTAN
SATKER P2JN PROVINSI PAPUA
(JAYAPURA)

ISNAINI SYAWIK, ST SAM RANDA, S.T, M.Eng


DIREKTUR UTAMA NIP. 19830422 200801 1 006
LAPORAN BULANAN KEADAAN DANA
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/SPMK/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Oktober 2020 / Invoice 03
TANGGAL : 02 November 2020
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

NO. JLH. PEMBAYARAN TAGIHAN INVOICE JLH. PEMBAYARAN SISA DANA


URAIAN TOTAL DANA
S/D BULAN LALU NO. 03 S/D BULAN INI Rp.

I. BIAYA LANGSUNG PERSONIL 4,166,344,500.00 179,669,355.00 162,264,000.00 341,933,355.00 3,824,411,145.00


-
II. BIAYA LANGSUNG NON PERSONIL 1,285,850,000.00 70,124,500.00 50,972,500.00 121,097,000.00 1,164,753,000.00
BIAYA MOBILISASI DAN DEMOBILISASI - - - - -
BIAYA PERJALANAN DINAS 21,600,000.00 - - - 21,600,000.00
BIAYA KANTOR 335,000,000.00 19,162,000.00 13,400,000.00 32,562,000.00 302,438,000.00
BIAYA PELAPORAN 26,250,000.00 2,000,000.00 1,750,000.00 3,750,000.00 22,500,000.00
BIAYA AKOMODASI 903,000,000.00 48,962,500.00 35,822,500.00 84,785,000.00 818,215,000.00

SUB TOTAL (I+II) 5,452,194,500.00 249,793,855.00 213,236,500.00 463,030,355.00 4,989,164,145.00


PPN 545,219,450.00 24,979,385.50 21,323,650.00 46,303,035.50 498,916,414.50
SUB TOTAL 5,997,413,950.00 274,773,240.50 234,560,150.00 509,333,390.50 5,488,080,559.50
NILAI KONTRAK DIBULATKAN 5,997,413,000.00
PENGEMBALIAN UANG MUKA 899,611,950.00 89,961,195.00 89,961,195.00 179,922,390.00 719,689,560.00
TOTAL 5,097,801,050.00 184,812,045.50 144,598,955.00 329,411,000.50 4,768,390,999.50
DIBULATKAN 184,812,046.00 144,598,955.00 329,411,001.00 4,768,391,000.00

1,199,482,600.00

Jayapura, 02 November 2020

PPK PENGAWASAN Konsultan Supervisi


SATKER P2JN PROVINSI PAPUA (JAYAPURA)
PT. WINSOLUSI KONSULTAN

SAM RANDA, S.T, M.Eng ISNAINI SYAWIK, ST


NIP. 19830422 200801 1 006 Direktur Utama
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/SPMK/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Oktober 2020 / Invoice 03
TANGGAL : 02 November 2020
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

REKAPITULASI INVOICE

NO. URAIAN BIAYA (Rp.)

I. BIAYA LANGSUNG PERSONIL 162,264,000.00

II. BIAYA LANGSUNG NON PERSONIL 50,972,500.00


BIAYA MOBILISASI DAN DEMOBILISASI -
BIAYA PERJALANAN DINAS -
BIAYA KANTOR 13,400,000.00
BIAYA PELAPORAN 1,750,000.00
BIAYA AKOMODASI 35,822,500.00

SUB TOTAL ( I + II ) 213,236,500.00


PPN 10% 21,323,650.00
SUB TOTAL 234,560,150.00
PENGEMBALIAN UANG MUKA 15% 89,961,195.00
TOTAL 144,598,955.00
DIBULATKAN 144,598,955.00

Total Pembayaran pada Tagihan ini Rp. 144,598,955.00


Terbilang : Err:511

Mohon Tagihan untuk bulan Oktober 2020 dimasukan pada rekening PT. WINSOLUSI KONSULTAN Nomor Rekening :
0416.01.000160.300 BRI Cabang Kelapa Gading 2

Jayapura, 02 November 2020


PPK PENGAWASAN Konsultan Supervisi
SATKER P2JN PROVINSI PAPUA (JAYAPURA)
PT. WINSOLUSI KONSULTAN

SAM RANDA, S.T, M.Eng ISNAINI SYAWIK, ST


NIP. 19830422 200801 1 006 Direktur Utama
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/SPMK/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Oktober 2020 / Invoice 03
TANGGAL : 02 November 2020
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

I. BIAYA LANGSUNG PERSONIL


HARGA JUMLAH HARGA PEMBAYARAN TAGIHAN INVOICE NO. 03 PEMBAYARAN
URAIAN SATUAN S/D (Bulan Oktober 2020) S/D SISA DANA
NO. JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU ORANG WAKTU/ JUMLAH BULAN INI
(Rp) BULAN (RP) (Rp) (Rp)
a BIAYA TENAGA AHLI
Site Supervision Engineer 1.00 25.00 OB 32,697,000.00 817,425,000.00 46,756,710.00 1.00 1.00 32,697,000.00 79,453,710.00 737,971,290.00
Quality Engineer-1 1.00 24.00 OB 30,880,500.00 741,132,000.00 12,352,200.00 1.00 1.00 30,880,500.00 43,232,700.00 697,899,300.00
Inspection Engineer/Quantity Engineer 1.00 25.00 OB 30,880,500.00 772,012,500.00 44,159,115.00 1.00 1.00 30,880,500.00 75,039,615.00 696,972,885.00
Health Safety Enviroment Engineer 1.00 25.00 OB 25,431,000.00 635,775,000.00 36,366,330.00 1.00 1.00 25,431,000.00 61,797,330.00 573,977,670.00

Sub Total a 2,966,344,500.00 139,634,355.00 119,889,000.00 259,523,355.00 2,706,821,145.00


b BIAYA ASISTEN TENAGA AHLI
Inspector -1 1.00 23.00 OB 12,500,000.00 287,500,000.00 - 1.00 0.43 5,375,000.00 5,375,000.00 282,125,000.00
Surveyor Technician -1 1.00 25.00 OB 12,500,000.00 312,500,000.00 17,875,000.00 1.00 1.00 12,500,000.00 30,375,000.00 282,125,000.00
Material Technician -1 1.00 24.00 OB 12,500,000.00 300,000,000.00 5,000,000.00 1.00 1.00 12,500,000.00 17,500,000.00 282,500,000.00

Sub Total b 900,000,000.00 22,875,000.00 30,375,000.00 53,250,000.00 846,750,000.00


c BIAYA STAF PENDUKUNG
Operator Komputer 1.00 25.00 OB 8,000,000.00 200,000,000.00 11,440,000.00 1.00 1.00 8,000,000.00 19,440,000.00 180,560,000.00
Pesuruh/Penjaga Kantor 1.00 25.00 OB 4,000,000.00 100,000,000.00 5,720,000.00 1.00 1.00 4,000,000.00 9,720,000.00 90,280,000.00

Sub Total c 300,000,000.00 17,160,000.00 12,000,000.00 29,160,000.00 270,840,000.00

TOTAL a+b+c 4,166,344,500.00 179,669,355.00 - - 162,264,000.00 341,933,355.00 3,824,411,145.00


NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/SPMK/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Oktober 2020 / Invoice 03
TANGGAL : 02 November 2020
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

II. BIAYA LANGSUNG NON PERSONIL


HARGA PEMBAYARAN TAGIHAN INVOICE NO. 03 PEMBAYARAN
JUMLAH HARGA
SATUAN S/D (Bulan Oktober 2020) S/D SISA DANA
NO. URAIAN JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU JUMLAH BULAN INI
ORANG TRIP
(Rp) (RP) (Rp) (Rp)
a MOBILISASI DAN DEMOBILISASI
- Mobilisasi
Site Supervision Engineer - - Trip - - - - - - - -
Quality Engineer-1 - - Trip - - - - - - - -
Inspection Engineer/Quantity Engineer - - Trip - - - - - - - -
Health Safety Enviroment Engineer - - - - - - - - - -
- Demobilisasi
Site Supervision Engineer - - Trip - - - - - - - -
Quality Engineer-1 - - Trip - - - - - - - -
Inspection Engineer/Quantity Engineer - - Trip - - - - - - - -
Health Safety Enviroment Engineer - - Trip - - - - - - - -
Sub Total a - - - - -
b BIAYA PERJALANAN DINAS
Tiket Perjalanan (PP) Termasuk Ongkos Taxi 6.00 Trip 2,000,000.00 12,000,000.00 - - - - - 12,000,000.00
Biaya Penginapan 24.00 Hari 400,000.00 9,600,000.00 - - - - - 9,600,000.00

Sub Total b 21,600,000.00 - - - 21,600,000.00


HARGA PEMBAYARAN TAGIHAN INVOICE NO. 03 PEMBAYARAN
SATUAN JUMLAH HARGA S/D (Bulan Oktober 2020) S/D SISA DANA
NO. URAIAN JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU JUMLAH BULAN INI
VOLUME BULAN
(Rp) (RP) (Rp) (Rp)
c BIAYA KANTOR
Sewa Kantor 1.00 25.00 Bln 5,000,000.00 125,000,000.00 7,150,000.00 1.00 1.00 5,000,000.00 12,150,000.00 112,850,000.00
Biaya Operasional Kantor (Air dan Listrik) 1.00 25.00 Bln 1,500,000.00 37,500,000.00 2,145,000.00 1.00 1.00 1,500,000.00 3,645,000.00 33,855,000.00
Sewa Penunjang Kantor :
- Laptop-1 1.00 25.00 Bln 1,600,000.00 40,000,000.00 2,288,000.00 1.00 1.00 1,600,000.00 3,888,000.00 36,112,000.00
- Laptop-2 1.00 25.00 Bln 1,600,000.00 40,000,000.00 2,288,000.00 1.00 1.00 1,600,000.00 3,888,000.00 36,112,000.00
- Printer A3 1.00 25.00 Bln 700,000.00 17,500,000.00 1,001,000.00 1.00 1.00 700,000.00 1,701,000.00 15,799,000.00
- Printer A4 1.00 25.00 Bln 500,000.00 12,500,000.00 715,000.00 1.00 1.00 500,000.00 1,215,000.00 11,285,000.00
Komunikasi (Pulsa Telepon + lnternet) 1.00 25.00 Bln 1,500,000.00 37,500,000.00 2,145,000.00 1.00 1.00 1,500,000.00 3,645,000.00 33,855,000.00
Bahan untuk peralatan kantor 1.00 25.00 Bln 1,000,000.00 25,000,000.00 1,430,000.00 1.00 1.00 1,000,000.00 2,430,000.00 22,570,000.00

Sub Total c 335,000,000.00 19,162,000.00 13,400,000.00 32,562,000.00 302,438,000.00


d BIAYA PELAPORAN
Laporan RMK 5.00 5.00 Eks 150,000.00 750,000.00 750,000.00 - - - 750,000.00 -
Laporan Pendahuluan 5.00 5.00 Eks 150,000.00 750,000.00 750,000.00 - - - 750,000.00 -
Laporan Bulanan 125.00 5.00 Eks 100,000.00 12,500,000.00 500,000.00 5.00 1.00 500,000.00 1,000,000.00 11,500,000.00
Laporan Triwulan 40.00 5.00 Eks 250,000.00 10,000,000.00 - 5.00 1.00 1,250,000.00 1,250,000.00 8,750,000.00
Laporan Akhir 5.00 5.00 Eks 250,000.00 1,250,000.00 - - - - - 1,250,000.00
Hard Disk (File Laporan dan Dokumentasi) 1.00 1.00 Buah 1,000,000.00 1,000,000.00 - - - - - 1,000,000.00

Sub Total d 26,250,000.00 2,000,000.00 1,750,000.00 3,750,000.00 22,500,000.00

e BIAYA AKOMODASI
- Biaya Sewa
Sewa Mobil Double Gardan-1 1.00 25.00 Bln 25,000,000.00 625,000,000.00 35,750,000.00 1.00 1.00 25,000,000.00 60,750,000.00 564,250,000.00
Sewa Motor Lapangan -1 1.00 25.00 Bln 2,500,000.00 62,500,000.00 3,575,000.00 1.00 1.00 2,500,000.00 6,075,000.00 56,425,000.00
Sewa Motor Lapangan -2 1.00 25.00 Bln 2,500,000.00 62,500,000.00 3,575,000.00 1.00 1.00 2,500,000.00 6,075,000.00 56,425,000.00
- Tunjangan Perumahan
Site Supervision Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 1,430,000.00 1.00 1.00 1,000,000.00 2,430,000.00 22,570,000.00
Quality Engineer-1 1.00 24.00 Bln 1,000,000.00 24,000,000.00 400,000.00 1.00 1.00 1,000,000.00 1,400,000.00 22,600,000.00
Inspection Engineer/Quantity Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 1,430,000.00 1.00 1.00 1,000,000.00 2,430,000.00 22,570,000.00
Health Safety Enviroment Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 1,430,000.00 1.00 1.00 1,000,000.00 2,430,000.00 22,570,000.00
Inspector -1 1.00 23.00 Bln 750,000.00 17,250,000.00 - 1.00 0.43 322,500.00 322,500.00 16,927,500.00
Surveyor Technician -1 1.00 25.00 Bln 750,000.00 18,750,000.00 1,072,500.00 1.00 1.00 750,000.00 1,822,500.00 16,927,500.00
Material Technician -1 1.00 24.00 Bln 750,000.00 18,000,000.00 300,000.00 1.00 1.00 750,000.00 1,050,000.00 16,950,000.00

Sub Total e 903,000,000.00 48,962,500.00 35,822,500.00 84,785,000.00 818,215,000.00

Sub Total a+b+c+d+e 1,285,850,000.00 70,124,500.00 50,972,500.00 121,097,000.00 1,164,753,000.00


LAPORAN BULANAN KEADAAN DANA
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : November 2020 / Invoice 04
TANGGAL : 01 Desember 2020
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

NO. JLH. PEMBAYARAN TAGIHAN INVOICE JLH. PEMBAYARAN SISA DANA


URAIAN TOTAL DANA
S/D BULAN LALU NO. 04 S/D BULAN INI Rp.

I. BIAYA LANGSUNG PERSONIL 4,166,344,500.00 341,933,355.00 169,389,000.00 511,322,355.00 3,655,022,145.00


-
II. BIAYA LANGSUNG NON PERSONIL 1,285,850,000.00 121,097,000.00 50,150,000.00 171,247,000.00 1,114,603,000.00
BIAYA MOBILISASI DAN DEMOBILISASI - - - - -
BIAYA PERJALANAN DINAS 21,600,000.00 - - - 21,600,000.00
BIAYA KANTOR 335,000,000.00 32,562,000.00 13,400,000.00 45,962,000.00 289,038,000.00
BIAYA PELAPORAN 26,250,000.00 3,750,000.00 500,000.00 4,250,000.00 22,000,000.00
BIAYA AKOMODASI 903,000,000.00 84,785,000.00 36,250,000.00 121,035,000.00 781,965,000.00

SUB TOTAL (I+II) 5,452,194,500.00 463,030,355.00 219,539,000.00 682,569,355.00 4,769,625,145.00


PPN 545,219,450.00 46,303,035.50 21,953,900.00 68,256,935.50 476,962,514.50
SUB TOTAL 5,997,413,950.00 509,333,390.50 241,492,900.00 750,826,290.50 5,246,587,659.50
NILAI KONTRAK DIBULATKAN 5,997,413,000.00
PENGEMBALIAN UANG MUKA 899,611,950.00 179,922,390.00 89,961,195.00 269,883,585.00 629,728,365.00
TOTAL 5,097,801,050.00 329,411,000.50 151,531,705.00 480,942,705.50 4,616,859,294.50
DIBULATKAN 329,411,000.00 151,531,705.00 480,942,705.00 4,616,859,295.00

1,199,482,600.00

Jayapura, 01 Desember 2020

PPK PENGAWASAN Konsultan Supervisi


SATKER P2JN PROVINSI PAPUA (JAYAPURA)
PT. WINSOLUSI KONSULTAN

SAM RANDA, S.T, M.Eng ISNAINI SYAWIK, ST


NIP. 19830422 200801 1 006 Direktur Utama
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : November 2020 / Invoice 04
TANGGAL : 01 Desember 2020
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

REKAPITULASI INVOICE

NO. URAIAN BIAYA (Rp.)

I. BIAYA LANGSUNG PERSONIL 169,389,000.00

II. BIAYA LANGSUNG NON PERSONIL 50,150,000.00


BIAYA MOBILISASI DAN DEMOBILISASI -
BIAYA PERJALANAN DINAS -
BIAYA KANTOR 13,400,000.00
BIAYA PELAPORAN 500,000.00
BIAYA AKOMODASI 36,250,000.00

SUB TOTAL ( I + II ) 219,539,000.00


PPN 10% 21,953,900.00
SUB TOTAL 241,492,900.00
PENGEMBALIAN UANG MUKA 15% 89,961,195.00
TOTAL 151,531,705.00
DIBULATKAN 151,531,705.00

Total Pembayaran pada Tagihan ini Rp. 151,531,705.00


Terbilang : Err:511

Mohon Tagihan untuk bulan November 2020 dimasukan pada rekening PT. WINSOLUSI KONSULTAN Nomor Rekening :
0416.01.000160.300 BRI Cabang Kelapa Gading 2

Jayapura, 01 Desember 2020


PPK PENGAWASAN Konsultan Supervisi
SATKER P2JN PROVINSI PAPUA (JAYAPURA)
PT. WINSOLUSI KONSULTAN

SAM RANDA, S.T, M.Eng ISNAINI SYAWIK, ST


NIP. 19830422 200801 1 006 Direktur Utama
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : November 2020 / Invoice 04
TANGGAL : 01 Desember 2020
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

I. BIAYA LANGSUNG PERSONIL


HARGA JUMLAH HARGA PEMBAYARAN TAGIHAN INVOICE NO. 04 PEMBAYARAN
URAIAN SATUAN S/D (Bulan November 2020) S/D SISA DANA
NO. JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU ORANG WAKTU/ JUMLAH BULAN INI
(Rp) BULAN (RP) (Rp) (Rp)
a BIAYA TENAGA AHLI
Site Supervision Engineer 1.00 25.00 OB 32,697,000.00 817,425,000.00 79,453,710.00 1.00 1.00 32,697,000.00 112,150,710.00 705,274,290.00
Quality Engineer-1 1.00 24.00 OB 30,880,500.00 741,132,000.00 43,232,700.00 1.00 1.00 30,880,500.00 74,113,200.00 667,018,800.00
Inspection Engineer/Quantity Engineer 1.00 25.00 OB 30,880,500.00 772,012,500.00 75,039,615.00 1.00 1.00 30,880,500.00 105,920,115.00 666,092,385.00
Health Safety Enviroment Engineer 1.00 25.00 OB 25,431,000.00 635,775,000.00 61,797,330.00 1.00 1.00 25,431,000.00 87,228,330.00 548,546,670.00

Sub Total a 2,966,344,500.00 259,523,355.00 119,889,000.00 379,412,355.00 2,586,932,145.00


b BIAYA ASISTEN TENAGA AHLI
Inspector -1 1.00 23.00 OB 12,500,000.00 287,500,000.00 5,375,000.00 1.00 1.00 12,500,000.00 17,875,000.00 269,625,000.00
Surveyor Technician -1 1.00 25.00 OB 12,500,000.00 312,500,000.00 30,375,000.00 1.00 1.00 12,500,000.00 42,875,000.00 269,625,000.00
Material Technician -1 1.00 24.00 OB 12,500,000.00 300,000,000.00 17,500,000.00 1.00 1.00 12,500,000.00 30,000,000.00 270,000,000.00
Sub Total b 900,000,000.00 53,250,000.00 37,500,000.00 90,750,000.00 809,250,000.00
c BIAYA STAF PENDUKUNG
Operator Komputer 1.00 25.00 OB 8,000,000.00 200,000,000.00 19,440,000.00 1.00 1.00 8,000,000.00 27,440,000.00 172,560,000.00
Pesuruh/Penjaga Kantor 1.00 25.00 OB 4,000,000.00 100,000,000.00 9,720,000.00 1.00 1.00 4,000,000.00 13,720,000.00 86,280,000.00

Sub Total c 300,000,000.00 29,160,000.00 12,000,000.00 41,160,000.00 258,840,000.00

TOTAL a+b+c 4,166,344,500.00 341,933,355.00 - - 169,389,000.00 511,322,355.00 3,655,022,145.00


NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : November 2020 / Invoice 04
TANGGAL : 01 Desember 2020
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

II. BIAYA LANGSUNG NON PERSONIL


HARGA PEMBAYARAN TAGIHAN INVOICE NO. 04 PEMBAYARAN
JUMLAH HARGA
SATUAN S/D (Bulan November 2020) S/D SISA DANA
NO. URAIAN JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU JUMLAH BULAN INI
ORANG TRIP
(Rp) (RP) (Rp) (Rp)
a MOBILISASI DAN DEMOBILISASI
- Mobilisasi
Site Supervision Engineer - - Trip - - - - - - - -
Quality Engineer-1 - - Trip - - - - - - - -
Inspection Engineer/Quantity Engineer - - Trip - - - - - - - -
Health Safety Enviroment Engineer - - - - - - - - - -
- Demobilisasi
Site Supervision Engineer - - Trip - - - - - - - -
Quality Engineer-1 - - Trip - - - - - - - -
Inspection Engineer/Quantity Engineer - - Trip - - - - - - - -
Health Safety Enviroment Engineer - - Trip - - - - - - - -
Sub Total a - - - - -
b BIAYA PERJALANAN DINAS
Tiket Perjalanan (PP) Termasuk Ongkos Taxi 6.00 Trip 2,000,000.00 12,000,000.00 - - - - - 12,000,000.00
Biaya Penginapan 24.00 Hari 400,000.00 9,600,000.00 - - - - - 9,600,000.00

Sub Total b 21,600,000.00 - - - 21,600,000.00


HARGA PEMBAYARAN TAGIHAN INVOICE NO. 04 PEMBAYARAN
SATUAN JUMLAH HARGA S/D (Bulan November 2020) S/D SISA DANA
NO. URAIAN JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU JUMLAH BULAN INI
VOLUME BULAN
(Rp) (RP) (Rp) (Rp)
c BIAYA KANTOR
Sewa Kantor 1.00 25.00 Bln 5,000,000.00 125,000,000.00 12,150,000.00 1.00 1.00 5,000,000.00 17,150,000.00 107,850,000.00
Sewa Operasional Kantor (Air dan Listrik) 1.00 25.00 Bln 1,500,000.00 37,500,000.00 3,645,000.00 1.00 1.00 1,500,000.00 5,145,000.00 32,355,000.00
Sewa Penunjang Kantor :
- Laptop-1 1.00 25.00 Bln 1,600,000.00 40,000,000.00 3,888,000.00 1.00 1.00 1,600,000.00 5,488,000.00 34,512,000.00
- Laptop-2 1.00 25.00 Bln 1,600,000.00 40,000,000.00 3,888,000.00 1.00 1.00 1,600,000.00 5,488,000.00 34,512,000.00
- Printer A3 1.00 25.00 Bln 700,000.00 17,500,000.00 1,701,000.00 1.00 1.00 700,000.00 2,401,000.00 15,099,000.00
- Printer A4 1.00 25.00 Bln 500,000.00 12,500,000.00 1,215,000.00 1.00 1.00 500,000.00 1,715,000.00 10,785,000.00
Komunikasi (Pulsa Telepon + lnternet) 1.00 25.00 Bln 1,500,000.00 37,500,000.00 3,645,000.00 1.00 1.00 1,500,000.00 5,145,000.00 32,355,000.00
Bahan untuk peralatan kantor 1.00 25.00 Bln 1,000,000.00 25,000,000.00 2,430,000.00 1.00 1.00 1,000,000.00 3,430,000.00 21,570,000.00

Sub Total c 335,000,000.00 32,562,000.00 13,400,000.00 45,962,000.00 289,038,000.00


d BIAYA PELAPORAN
Laporan RMK 5.00 5.00 Eks 150,000.00 750,000.00 750,000.00 - - - 750,000.00 -
Laporan Pendahuluan 5.00 5.00 Eks 150,000.00 750,000.00 750,000.00 - - - 750,000.00 -
Laporan Bulanan 125.00 5.00 Eks 100,000.00 12,500,000.00 1,000,000.00 5.00 1.00 500,000.00 1,500,000.00 11,000,000.00
Laporan Triwulan 40.00 5.00 Eks 250,000.00 10,000,000.00 1,250,000.00 - - - 1,250,000.00 8,750,000.00
Laporan Akhir 5.00 5.00 Eks 250,000.00 1,250,000.00 - - - - - 1,250,000.00
Hard Disk (File Laporan dan Dokumentasi) 1.00 1.00 Buah 1,000,000.00 1,000,000.00 - - - - - 1,000,000.00

Sub Total d 26,250,000.00 3,750,000.00 500,000.00 4,250,000.00 22,000,000.00


e BIAYA AKOMODASI
- Biaya Sewa
Sewa Mobil Double Gardan-1 1.00 25.00 Bln 25,000,000.00 625,000,000.00 60,750,000.00 1.00 1.00 25,000,000.00 85,750,000.00 539,250,000.00
Sewa Motor Lapangan -1 1.00 25.00 Bln 2,500,000.00 62,500,000.00 6,075,000.00 1.00 1.00 2,500,000.00 8,575,000.00 53,925,000.00
Sewa Motor Lapangan -2 1.00 25.00 Bln 2,500,000.00 62,500,000.00 6,075,000.00 1.00 1.00 2,500,000.00 8,575,000.00 53,925,000.00
- Tunjangan Perumahan
Site Supervision Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 2,430,000.00 1.00 1.00 1,000,000.00 3,430,000.00 21,570,000.00
Quality Engineer-1 1.00 24.00 Bln 1,000,000.00 24,000,000.00 1,400,000.00 1.00 1.00 1,000,000.00 2,400,000.00 21,600,000.00
Inspection Engineer/Quantity Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 2,430,000.00 1.00 1.00 1,000,000.00 3,430,000.00 21,570,000.00
Health Safety Enviroment Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 2,430,000.00 1.00 1.00 1,000,000.00 3,430,000.00 21,570,000.00
Inspector -1 1.00 23.00 Bln 750,000.00 17,250,000.00 322,500.00 1.00 1.00 750,000.00 1,072,500.00 16,177,500.00
Surveyor Technician -1 1.00 25.00 Bln 750,000.00 18,750,000.00 1,822,500.00 1.00 1.00 750,000.00 2,572,500.00 16,177,500.00
Material Technician -1 1.00 24.00 Bln 750,000.00 18,000,000.00 1,050,000.00 1.00 1.00 750,000.00 1,800,000.00 16,200,000.00

Sub Total e 903,000,000.00 84,785,000.00 36,250,000.00 121,035,000.00 781,965,000.00

Sub Total a+b+c+d+e 1,285,850,000.00 121,097,000.00 50,150,000.00 171,247,000.00 1,114,603,000.00


Kompleks Bina Marga Tanah Hitam Jl.Abepantai Telp. (0967) 587136, Fax. (0967) 587136

BERITA ACARA PEMERIKSAAN PEKERJAAN


No.:

Pekerjaan : PENGAWASAN TEKNIS PEMBANGUNAN JALAN MEMBERAMO - ELELIM II (MYC)


Lokasi : Satker PJN Wilayah I (Jayapura)
Tanggal : 01 Desember 2020

Pada hari ini Selasa tanggal Satu bulan Desember tahun Dua Ribu Dua Puluh, Kami yang bertanda tangan di
bawah ini : PPK Pengawasan Satker Perencanaan dan Pengawasan Jalan Nasional Provinsi Papua (Jayapura),
PENGAWASAN TEKNIS PEMBANGUNAN JALAN MEMBERAMO - ELELIM II (MYC) yang
dilaksanakan oleh PT. WINSOLUSI KONSULTAN berdasarkan Kontrak Nomor :
HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, Tanggal, tanggal 18 Agustus 2020, SPMK Nomor :
IK.02.04/SPMK/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, Tanggal tanggal 19 Agustus 2020

1. NILAI KONTRAK
A. BIAYA LANGSUNG PERSONIL
1. BIAYA TENAGA AHLI : Rp. 2,966,344,500
2. BIAYA ASISTEN TENAGA AHLI : Rp. 900,000,000
3. BIAYA STAFF PENDUKUNG : Rp. 300,000,000

B. BIAYA LANGSUNG NON PERSONIL


1. BIAYA MOBILISASI DAN DEMOBILISASI : Rp. -
2. BIAYA PERJALANAN DINAS : Rp. 21,600,000
3. BIAYA KANTOR : Rp. 335,000,000
4. BIAYA PELAPORAN : Rp. 26,250,000
5. BIAYA AKOMODASI : Rp. 903,000,000

SUB JUMLAH : Rp. 5,452,194,500


PPN 10% : Rp. 545,219,450
JUMLAH : Rp. 5,997,413,950
PEMBULATAN : Rp. 5,997,413,000
2. PEMBAYARAN
Pembiayaan Invoice IV bulan November 2020 / 04 yang telah dikeluarkan dan dipertanggung jawabkan kepada
Satuan Kerja Perencanaan & Pengawasan Jalan Nasional Propinsi Papua (Jayapura) Tahun Anggaran 2020
Meliputi :
A. BIAYA LANGSUNG PERSONIL
1. BIAYA TENAGA AHLI : Rp. 119,889,000
2. BIAYA ASISTEN TENAGA AHLI : Rp. 37,500,000
3. BIAYA STAFF PENDUKUNG : Rp. 12,000,000
B. BIAYA LANGSUNG NON PERSONIL
1. BIAYA MOBILISASI DAN DEMOBILISASI : Rp. -
2. BIAYA PERJALANAN DINAS : Rp. -
3. BIAYA KANTOR : Rp. 13,400,000
4. BIAYA PELAPORAN : Rp. 500,000
5. BIAYA AKOMODASI : Rp. 36,250,000

SUB JUMLAH : Rp. 219,539,000


PPN 10% : Rp. 21,953,900
JUMLAH : Rp. 241,492,900
PENGEMBALIAN UANG MUKA : Rp. 89,961,195
TOTAL : Rp. 151,531,705
PEMBULATAN : Rp. 151,531,705

Err:511

Jumlah ini akan dibayarkan melalui rekening :

PT. WINSOLUSI KONSULTAN Nomor Rekening : 0416.01.000160.300 BRI Cabang Kelapa Gading 2

Demikian Berita Acara ini dibuat dengan sebenarnya dalam rangkap 7 (tujuh) untuk dipergunakan seperlunya.

PPK PENGAWASAN
PT. WINSOLUSI KONSULTAN
SATKER P2JN PROVINSI PAPUA
(JAYAPURA)

ISNAINI SYAWIK, ST SAM RANDA, S.T, M.Eng


DIREKTUR UTAMA NIP. 19830422 200801 1 006
LAPORAN BULANAN KEADAAN DANA
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Desember 2020 / Invoice 05
TANGGAL : 21 Desember 2020
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

NO. JLH. PEMBAYARAN TAGIHAN INVOICE JLH. PEMBAYARAN SISA DANA


URAIAN TOTAL DANA
S/D BULAN LALU NO. 05 S/D BULAN INI Rp.

I. BIAYA LANGSUNG PERSONIL 4,166,344,500.00 511,322,355.00 113,490,630.00 624,812,985.00 3,541,531,515.00


-
II. BIAYA LANGSUNG NON PERSONIL 1,285,850,000.00 171,247,000.00 33,765,500.00 205,012,500.00 1,080,837,500.00
BIAYA MOBILISASI DAN DEMOBILISASI - - - - -
BIAYA PERJALANAN DINAS 21,600,000.00 - - - 21,600,000.00
BIAYA KANTOR 335,000,000.00 45,962,000.00 8,978,000.00 54,940,000.00 280,060,000.00
BIAYA PELAPORAN 26,250,000.00 4,250,000.00 500,000.00 4,750,000.00 21,500,000.00
BIAYA AKOMODASI 903,000,000.00 121,035,000.00 24,287,500.00 145,322,500.00 757,677,500.00

SUB TOTAL (I+II) 5,452,194,500.00 682,569,355.00 147,256,130.00 829,825,485.00 4,622,369,015.00


PPN 545,219,450.00 68,256,935.50 14,725,613.00 82,982,548.50 462,236,901.50
SUB TOTAL 5,997,413,950.00 750,826,290.50 161,981,743.00 912,808,033.50 5,084,605,916.50
NILAI KONTRAK DIBULATKAN 5,997,413,000.00
PENGEMBALIAN UANG MUKA 899,611,950.00 269,883,585.00 77,968,399.00 347,851,984.00 551,759,966.00
TOTAL 5,097,801,050.00 480,942,705.50 84,013,344.00 564,956,049.50 4,532,845,950.50
DIBULATKAN 480,942,705.00 84,013,344.00 564,956,049.00 4,532,845,951.00

1,199,482,600.00

Jayapura, 21 Desember 2020

PPK PENGAWASAN Konsultan Supervisi


SATKER P2JN PROVINSI PAPUA (JAYAPURA)
PT. WINSOLUSI KONSULTAN

SAM RANDA, S.T, M.Eng ISNAINI SYAWIK, ST


NIP. 19830422 200801 1 006 Direktur Utama
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Desember 2020 / Invoice 05
TANGGAL : 21 Desember 2020
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

REKAPITULASI INVOICE

NO. URAIAN BIAYA (Rp.)

I. BIAYA LANGSUNG PERSONIL 113,490,630.00

II. BIAYA LANGSUNG NON PERSONIL 33,765,500.00


BIAYA MOBILISASI DAN DEMOBILISASI -
BIAYA PERJALANAN DINAS -
BIAYA KANTOR 8,978,000.00
BIAYA PELAPORAN 500,000.00
BIAYA AKOMODASI 24,287,500.00

SUB TOTAL ( I + II ) 147,256,130.00


PPN 10% 14,725,613.00
SUB TOTAL 161,981,743.00
PENGEMBALIAN UANG MUKA 15% 77,968,399.00
TOTAL 84,013,344.00
DIBULATKAN 84,013,344.00

Total Pembayaran pada Tagihan ini Rp. 84,013,344.00


Terbilang : Err:511

Mohon Tagihan untuk bulan Desember 2020 dimasukan pada rekening PT. WINSOLUSI KONSULTAN Nomor Rekening :
0416.01.000160.300 BRI Cabang Kelapa Gading 2

Jayapura, 21 Desember 2020


PPK PENGAWASAN Konsultan Supervisi
SATKER P2JN PROVINSI PAPUA (JAYAPURA)
PT. WINSOLUSI KONSULTAN

SAM RANDA, S.T, M.Eng ISNAINI SYAWIK, ST


NIP. 19830422 200801 1 006 Direktur Utama
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Desember 2020 / Invoice 05
TANGGAL : 21 Desember 2020
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

I. BIAYA LANGSUNG PERSONIL


HARGA JUMLAH HARGA PEMBAYARAN TAGIHAN INVOICE NO. 05 PEMBAYARAN
URAIAN SATUAN S/D (Bulan Desember 2020) S/D SISA DANA
NO. JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU ORANG WAKTU/ JUMLAH BULAN INI
(Rp) BULAN (RP) (Rp) (Rp)
a BIAYA TENAGA AHLI
Site Supervision Engineer 1.00 25.00 OB 32,697,000.00 817,425,000.00 112,150,710.00 1.00 0.67 21,906,990.00 134,057,700.00 683,367,300.00
Quality Engineer-1 1.00 24.00 OB 30,880,500.00 741,132,000.00 74,113,200.00 1.00 0.67 20,689,935.00 94,803,135.00 646,328,865.00
Inspection Engineer/Quantity Engineer 1.00 25.00 OB 30,880,500.00 772,012,500.00 105,920,115.00 1.00 0.67 20,689,935.00 126,610,050.00 645,402,450.00
Health Safety Enviroment Engineer 1.00 25.00 OB 25,431,000.00 635,775,000.00 87,228,330.00 1.00 0.67 17,038,770.00 104,267,100.00 531,507,900.00

Sub Total a 2,966,344,500.00 379,412,355.00 80,325,630.00 459,737,985.00 2,506,606,515.00


b BIAYA ASISTEN TENAGA AHLI
Inspector -1 1.00 23.00 OB 12,500,000.00 287,500,000.00 17,875,000.00 1.00 0.67 8,375,000.00 26,250,000.00 261,250,000.00
Surveyor Technician -1 1.00 25.00 OB 12,500,000.00 312,500,000.00 42,875,000.00 1.00 0.67 8,375,000.00 51,250,000.00 261,250,000.00
Material Technician -1 1.00 24.00 OB 12,500,000.00 300,000,000.00 30,000,000.00 1.00 0.67 8,375,000.00 38,375,000.00 261,625,000.00
Sub Total b 900,000,000.00 90,750,000.00 25,125,000.00 115,875,000.00 784,125,000.00
c BIAYA STAF PENDUKUNG
Operator Komputer 1.00 25.00 OB 8,000,000.00 200,000,000.00 27,440,000.00 1.00 0.67 5,360,000.00 32,800,000.00 167,200,000.00
Pesuruh/Penjaga Kantor 1.00 25.00 OB 4,000,000.00 100,000,000.00 13,720,000.00 1.00 0.67 2,680,000.00 16,400,000.00 83,600,000.00
Sub Total c 300,000,000.00 41,160,000.00 8,040,000.00 49,200,000.00 250,800,000.00

TOTAL a+b+c 4,166,344,500.00 511,322,355.00 - - 113,490,630.00 624,812,985.00 3,541,531,515.00


NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Desember 2020 / Invoice 05
TANGGAL : 21 Desember 2020
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

II. BIAYA LANGSUNG NON PERSONIL


HARGA PEMBAYARAN TAGIHAN INVOICE NO. 05 PEMBAYARAN
JUMLAH HARGA
SATUAN S/D (Bulan Desember 2020) S/D SISA DANA
NO. URAIAN JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU JUMLAH BULAN INI
ORANG TRIP
(Rp) (RP) (Rp) (Rp)
a MOBILISASI DAN DEMOBILISASI
- Mobilisasi
Site Supervision Engineer - - Trip - - - - - - - -
Quality Engineer-1 - - Trip - - - - - - - -
Inspection Engineer/Quantity Engineer - - Trip - - - - - - - -
Health Safety Enviroment Engineer - - - - - - - - - -
- Demobilisasi
Site Supervision Engineer - - Trip - - - - - - - -
Quality Engineer-1 - - Trip - - - - - - - -
Inspection Engineer/Quantity Engineer - - Trip - - - - - - - -
Health Safety Enviroment Engineer - - Trip - - - - - - - -
Sub Total a - - - - -
b BIAYA PERJALANAN DINAS
Tiket Perjalanan (PP) Termasuk Ongkos Taxi 6.00 Trip 2,000,000.00 12,000,000.00 - - - - - 12,000,000.00
Biaya Penginapan 24.00 Hari 400,000.00 9,600,000.00 - - - - - 9,600,000.00

Sub Total b 21,600,000.00 - - - 21,600,000.00


HARGA PEMBAYARAN TAGIHAN INVOICE NO. 05 PEMBAYARAN
SATUAN JUMLAH HARGA S/D (Bulan Desember 2020) S/D SISA DANA
NO. URAIAN JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU JUMLAH BULAN INI
VOLUME BULAN
(Rp) (RP) (Rp) (Rp)
c BIAYA KANTOR
Sewa Kantor 1.00 25.00 Bln 5,000,000.00 125,000,000.00 17,150,000.00 1.00 0.67 3,350,000.00 20,500,000.00 104,500,000.00
Sewa Operasional Kantor (Air dan Listrik) 1.00 25.00 Bln 1,500,000.00 37,500,000.00 5,145,000.00 1.00 0.67 1,005,000.00 6,150,000.00 31,350,000.00
Sewa Penunjang Kantor :
- Laptop-1 1.00 25.00 Bln 1,600,000.00 40,000,000.00 5,488,000.00 1.00 0.67 1,072,000.00 6,560,000.00 33,440,000.00
- Laptop-2 1.00 25.00 Bln 1,600,000.00 40,000,000.00 5,488,000.00 1.00 0.67 1,072,000.00 6,560,000.00 33,440,000.00
- Printer A3 1.00 25.00 Bln 700,000.00 17,500,000.00 2,401,000.00 1.00 0.67 469,000.00 2,870,000.00 14,630,000.00
- Printer A4 1.00 25.00 Bln 500,000.00 12,500,000.00 1,715,000.00 1.00 0.67 335,000.00 2,050,000.00 10,450,000.00
Komunikasi (Pulsa Telepon + lnternet) 1.00 25.00 Bln 1,500,000.00 37,500,000.00 5,145,000.00 1.00 0.67 1,005,000.00 6,150,000.00 31,350,000.00
Bahan untuk peralatan kantor 1.00 25.00 Bln 1,000,000.00 25,000,000.00 3,430,000.00 1.00 0.67 670,000.00 4,100,000.00 20,900,000.00

Sub Total c 335,000,000.00 45,962,000.00 8,978,000.00 54,940,000.00 280,060,000.00


d BIAYA PELAPORAN
Laporan RMK 5.00 5.00 Eks 150,000.00 750,000.00 750,000.00 - - - 750,000.00 -
Laporan Pendahuluan 5.00 5.00 Eks 150,000.00 750,000.00 750,000.00 - - - 750,000.00 -
Laporan Bulanan 125.00 5.00 Eks 100,000.00 12,500,000.00 1,500,000.00 5.00 1.00 500,000.00 2,000,000.00 10,500,000.00
Laporan Triwulan 40.00 5.00 Eks 250,000.00 10,000,000.00 1,250,000.00 - - - 1,250,000.00 8,750,000.00
Laporan Akhir 5.00 5.00 Eks 250,000.00 1,250,000.00 - - - - - 1,250,000.00
Hard Disk (File Laporan dan Dokumentasi) 1.00 1.00 Buah 1,000,000.00 1,000,000.00 - - - - - 1,000,000.00

Sub Total d 26,250,000.00 4,250,000.00 500,000.00 4,750,000.00 21,500,000.00


e BIAYA AKOMODASI
- Biaya Sewa
Sewa Mobil Double Gardan-1 1.00 25.00 Bln 25,000,000.00 625,000,000.00 85,750,000.00 1.00 0.67 16,750,000.00 102,500,000.00 522,500,000.00
Sewa Motor Lapangan -1 1.00 25.00 Bln 2,500,000.00 62,500,000.00 8,575,000.00 1.00 0.67 1,675,000.00 10,250,000.00 52,250,000.00
Sewa Motor Lapangan -2 1.00 25.00 Bln 2,500,000.00 62,500,000.00 8,575,000.00 1.00 0.67 1,675,000.00 10,250,000.00 52,250,000.00
- Tunjangan Perumahan
Site Supervision Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 3,430,000.00 1.00 0.67 670,000.00 4,100,000.00 20,900,000.00
Quality Engineer-1 1.00 24.00 Bln 1,000,000.00 24,000,000.00 2,400,000.00 1.00 0.67 670,000.00 3,070,000.00 20,930,000.00
Inspection Engineer/Quantity Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 3,430,000.00 1.00 0.67 670,000.00 4,100,000.00 20,900,000.00
Health Safety Enviroment Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 3,430,000.00 1.00 0.67 670,000.00 4,100,000.00 20,900,000.00
Inspector -1 1.00 23.00 Bln 750,000.00 17,250,000.00 1,072,500.00 1.00 0.67 502,500.00 1,575,000.00 15,675,000.00
Surveyor Technician -1 1.00 25.00 Bln 750,000.00 18,750,000.00 2,572,500.00 1.00 0.67 502,500.00 3,075,000.00 15,675,000.00
Material Technician -1 1.00 24.00 Bln 750,000.00 18,000,000.00 1,800,000.00 1.00 0.67 502,500.00 2,302,500.00 15,697,500.00

Sub Total e 903,000,000.00 121,035,000.00 24,287,500.00 145,322,500.00 757,677,500.00

Sub Total a+b+c+d+e 1,285,850,000.00 171,247,000.00 33,765,500.00 205,012,500.00 1,080,837,500.00


LAPORAN BULANAN KEADAAN DANA
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Januari 2021 / Invoice 06
TANGGAL : 01 Februari 2021
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

NO. JLH. PEMBAYARAN TAGIHAN INVOICE JLH. PEMBAYARAN SISA DANA


URAIAN TOTAL DANA
S/D BULAN LALU NO. 06 S/D BULAN INI Rp.

I. BIAYA LANGSUNG PERSONIL 4,166,344,500.00 624,812,985.00 225,287,370.00 850,100,355.00 3,316,244,145.00


-
II. BIAYA LANGSUNG NON PERSONIL 1,285,850,000.00 205,012,500.00 67,784,500.00 272,797,000.00 1,013,053,000.00
BIAYA MOBILISASI DAN DEMOBILISASI - - - - -
BIAYA PERJALANAN DINAS 21,600,000.00 - - - 21,600,000.00
BIAYA KANTOR 335,000,000.00 54,940,000.00 17,822,000.00 72,762,000.00 262,238,000.00
BIAYA PELAPORAN 26,250,000.00 4,750,000.00 1,750,000.00 6,500,000.00 19,750,000.00
BIAYA AKOMODASI 903,000,000.00 145,322,500.00 48,212,500.00 193,535,000.00 709,465,000.00

SUB TOTAL (I+II) 5,452,194,500.00 829,825,485.00 293,071,870.00 1,122,897,355.00 4,329,297,145.00


PPN 545,219,450.00 82,982,548.50 29,307,187.00 112,289,735.50 432,929,714.50
SUB TOTAL 5,997,413,950.00 912,808,033.50 322,379,057.00 1,235,187,090.50 4,762,226,859.50
NILAI KONTRAK DIBULATKAN 5,997,413,000.00
PENGEMBALIAN UANG MUKA 899,611,950.00 347,851,984.00 110,351,993.00 458,203,977.00 441,407,973.00
TOTAL 5,097,801,050.00 564,956,049.50 212,027,064.00 776,983,113.50 4,320,818,886.50
DIBULATKAN 564,956,049.00 212,027,064.00 776,983,113.00 4,320,818,887.00

1,199,482,600.00

Jayapura, 01 Februari 2021

PPK PENGAWASAN Konsultan Supervisi


SATKER P2JN PROVINSI PAPUA (JAYAPURA)
PT. WINSOLUSI KONSULTAN

SAM RANDA, S.T, M.Eng ISNAINI SYAWIK, ST


NIP. 19830422 200801 1 006 Direktur Utama
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Januari 2021 / Invoice 06
TANGGAL : 01 Februari 2021
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

REKAPITULASI INVOICE

NO. URAIAN BIAYA (Rp.)

I. BIAYA LANGSUNG PERSONIL 225,287,370.00

II. BIAYA LANGSUNG NON PERSONIL 67,784,500.00


BIAYA MOBILISASI DAN DEMOBILISASI -
BIAYA PERJALANAN DINAS -
BIAYA KANTOR 17,822,000.00
BIAYA PELAPORAN 1,750,000.00
BIAYA AKOMODASI 48,212,500.00

SUB TOTAL ( I + II ) 293,071,870.00


PPN 10% 29,307,187.00
SUB TOTAL 322,379,057.00
PENGEMBALIAN UANG MUKA 15% 110,351,993.00
TOTAL 212,027,064.00
DIBULATKAN 212,027,064.00

Total Pembayaran pada Tagihan ini Rp. 212,027,064.00


Terbilang : Err:511

Mohon Tagihan untuk bulan Januari 2021 dimasukan pada rekening PT. WINSOLUSI KONSULTAN Nomor Rekening :
0416.01.000160.300 BRI Cabang Kelapa Gading 2

Jayapura, 01 Februari 2021


PPK PENGAWASAN Konsultan Supervisi
SATKER P2JN PROVINSI PAPUA (JAYAPURA)
PT. WINSOLUSI KONSULTAN

SAM RANDA, S.T, M.Eng ISNAINI SYAWIK, ST


NIP. 19830422 200801 1 006 Direktur Utama
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Januari 2021 / Invoice 06
TANGGAL : 01 Februari 2021
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

I. BIAYA LANGSUNG PERSONIL


HARGA JUMLAH HARGA PEMBAYARAN TAGIHAN INVOICE NO. 06 PEMBAYARAN
URAIAN SATUAN S/D (Bulan Januari 2021) S/D SISA DANA
NO. JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU ORANG WAKTU/ JUMLAH BULAN INI
(Rp) BULAN (RP) (Rp) (Rp)
a BIAYA TENAGA AHLI
Site Supervision Engineer 1.00 25.00 OB 32,697,000.00 817,425,000.00 134,057,700.00 1.00 1.33 43,487,010.00 177,544,710.00 639,880,290.00
Quality Engineer-1 1.00 24.00 OB 30,880,500.00 741,132,000.00 94,803,135.00 1.00 1.33 41,071,065.00 135,874,200.00 605,257,800.00
Inspection Engineer/Quantity Engineer 1.00 25.00 OB 30,880,500.00 772,012,500.00 126,610,050.00 1.00 1.33 41,071,065.00 167,681,115.00 604,331,385.00
Health Safety Enviroment Engineer 1.00 25.00 OB 25,431,000.00 635,775,000.00 104,267,100.00 1.00 1.33 33,823,230.00 138,090,330.00 497,684,670.00

Sub Total a 2,966,344,500.00 459,737,985.00 159,452,370.00 619,190,355.00 2,347,154,145.00


b BIAYA ASISTEN TENAGA AHLI
Inspector -1 1.00 23.00 OB 12,500,000.00 287,500,000.00 26,250,000.00 1.00 1.33 16,625,000.00 42,875,000.00 244,625,000.00
Surveyor Technician -1 1.00 25.00 OB 12,500,000.00 312,500,000.00 51,250,000.00 1.00 1.33 16,625,000.00 67,875,000.00 244,625,000.00
Material Technician -1 1.00 24.00 OB 12,500,000.00 300,000,000.00 38,375,000.00 1.00 1.33 16,625,000.00 55,000,000.00 245,000,000.00

Sub Total b 900,000,000.00 115,875,000.00 49,875,000.00 165,750,000.00 734,250,000.00


c BIAYA STAF PENDUKUNG
Operator Komputer 1.00 25.00 OB 8,000,000.00 200,000,000.00 32,800,000.00 1.00 1.33 10,640,000.00 43,440,000.00 156,560,000.00
Pesuruh/Penjaga Kantor 1.00 25.00 OB 4,000,000.00 100,000,000.00 16,400,000.00 1.00 1.33 5,320,000.00 21,720,000.00 78,280,000.00

Sub Total c 300,000,000.00 49,200,000.00 15,960,000.00 65,160,000.00 234,840,000.00

TOTAL a+b+c 4,166,344,500.00 624,812,985.00 - - 225,287,370.00 850,100,355.00 3,316,244,145.00


NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Januari 2021 / Invoice 06
TANGGAL : 01 Februari 2021
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

II. BIAYA LANGSUNG NON PERSONIL


HARGA PEMBAYARAN TAGIHAN INVOICE NO. 06 PEMBAYARAN
JUMLAH HARGA
SATUAN S/D (Bulan Januari 2021) S/D SISA DANA
NO. URAIAN JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU JUMLAH BULAN INI
ORANG TRIP
(Rp) (RP) (Rp) (Rp)
a MOBILISASI DAN DEMOBILISASI
- Mobilisasi
Site Supervision Engineer - - Trip - - - - - - - -
Quality Engineer-1 - - Trip - - - - - - - -
Inspection Engineer/Quantity Engineer - - Trip - - - - - - - -
Health Safety Enviroment Engineer - - - - - - - - - -
- Demobilisasi
Site Supervision Engineer - - Trip - - - - - - - -
Quality Engineer-1 - - Trip - - - - - - - -
Inspection Engineer/Quantity Engineer - - Trip - - - - - - - -
Health Safety Enviroment Engineer - - Trip - - - - - - - -
Sub Total a - - - - -
b BIAYA PERJALANAN DINAS
Tiket Perjalanan (PP) Termasuk Ongkos Taxi 6.00 Trip 2,000,000.00 12,000,000.00 - - - - - 12,000,000.00
Biaya Penginapan 24.00 Hari 400,000.00 9,600,000.00 - - - - - 9,600,000.00

Sub Total b 21,600,000.00 - - - 21,600,000.00


HARGA PEMBAYARAN TAGIHAN INVOICE NO. 06 PEMBAYARAN
SATUAN JUMLAH HARGA S/D (Bulan Januari 2021) S/D SISA DANA
NO. URAIAN JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU JUMLAH BULAN INI
VOLUME BULAN
(Rp) (RP) (Rp) (Rp)
c BIAYA KANTOR
Sewa Kantor 1.00 25.00 Bln 5,000,000.00 125,000,000.00 20,500,000.00 1.00 1.33 6,650,000.00 27,150,000.00 97,850,000.00
Sewa Operasional Kantor (Air dan Listrik) 1.00 25.00 Bln 1,500,000.00 37,500,000.00 6,150,000.00 1.00 1.33 1,995,000.00 8,145,000.00 29,355,000.00
Sewa Penunjang Kantor :
- Laptop-1 1.00 25.00 Bln 1,600,000.00 40,000,000.00 6,560,000.00 1.00 1.33 2,128,000.00 8,688,000.00 31,312,000.00
- Laptop-2 1.00 25.00 Bln 1,600,000.00 40,000,000.00 6,560,000.00 1.00 1.33 2,128,000.00 8,688,000.00 31,312,000.00
- Printer A3 1.00 25.00 Bln 700,000.00 17,500,000.00 2,870,000.00 1.00 1.33 931,000.00 3,801,000.00 13,699,000.00
- Printer A4 1.00 25.00 Bln 500,000.00 12,500,000.00 2,050,000.00 1.00 1.33 665,000.00 2,715,000.00 9,785,000.00
Komunikasi (Pulsa Telepon + lnternet) 1.00 25.00 Bln 1,500,000.00 37,500,000.00 6,150,000.00 1.00 1.33 1,995,000.00 8,145,000.00 29,355,000.00
Bahan untuk peralatan kantor 1.00 25.00 Bln 1,000,000.00 25,000,000.00 4,100,000.00 1.00 1.33 1,330,000.00 5,430,000.00 19,570,000.00

Sub Total c 335,000,000.00 54,940,000.00 17,822,000.00 72,762,000.00 262,238,000.00


d BIAYA PELAPORAN
Laporan RMK 5.00 5.00 Eks 150,000.00 750,000.00 750,000.00 - - - 750,000.00 -
Laporan Pendahuluan 5.00 5.00 Eks 150,000.00 750,000.00 750,000.00 - - - 750,000.00 -
Laporan Bulanan 125.00 5.00 Eks 100,000.00 12,500,000.00 2,000,000.00 5.00 1.00 500,000.00 2,500,000.00 10,000,000.00
Laporan Triwulan 40.00 5.00 Eks 250,000.00 10,000,000.00 1,250,000.00 5.00 1.00 1,250,000.00 2,500,000.00 7,500,000.00
Laporan Akhir 5.00 5.00 Eks 250,000.00 1,250,000.00 - - - - - 1,250,000.00
Hard Disk (File Laporan dan Dokumentasi) 1.00 1.00 Buah 1,000,000.00 1,000,000.00 - - - - - 1,000,000.00

Sub Total d 26,250,000.00 4,750,000.00 1,750,000.00 6,500,000.00 19,750,000.00

e BIAYA AKOMODASI
- Biaya Sewa
Sewa Mobil Double Gardan-1 1.00 25.00 Bln 25,000,000.00 625,000,000.00 102,500,000.00 1.00 1.33 33,250,000.00 135,750,000.00 489,250,000.00
Sewa Motor Lapangan -1 1.00 25.00 Bln 2,500,000.00 62,500,000.00 10,250,000.00 1.00 1.33 3,325,000.00 13,575,000.00 48,925,000.00
Sewa Motor Lapangan -2 1.00 25.00 Bln 2,500,000.00 62,500,000.00 10,250,000.00 1.00 1.33 3,325,000.00 13,575,000.00 48,925,000.00
- Tunjangan Perumahan
Site Supervision Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 4,100,000.00 1.00 1.33 1,330,000.00 5,430,000.00 19,570,000.00
Quality Engineer-1 1.00 24.00 Bln 1,000,000.00 24,000,000.00 3,070,000.00 1.00 1.33 1,330,000.00 4,400,000.00 19,600,000.00
Inspection Engineer/Quantity Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 4,100,000.00 1.00 1.33 1,330,000.00 5,430,000.00 19,570,000.00
Health Safety Enviroment Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 4,100,000.00 1.00 1.33 1,330,000.00 5,430,000.00 19,570,000.00
Inspector -1 1.00 23.00 Bln 750,000.00 17,250,000.00 1,575,000.00 1.00 1.33 997,500.00 2,572,500.00 14,677,500.00
Surveyor Technician -1 1.00 25.00 Bln 750,000.00 18,750,000.00 3,075,000.00 1.00 1.33 997,500.00 4,072,500.00 14,677,500.00
Material Technician -1 1.00 24.00 Bln 750,000.00 18,000,000.00 2,302,500.00 1.00 1.33 997,500.00 3,300,000.00 14,700,000.00

Sub Total e 903,000,000.00 145,322,500.00 48,212,500.00 193,535,000.00 709,465,000.00

Sub Total a+b+c+d+e 1,285,850,000.00 205,012,500.00 67,784,500.00 272,797,000.00 1,013,053,000.00


LAPORAN BULANAN KEADAAN DANA
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Februari 2021 / Invoice 07
TANGGAL : 01 Maret 2021
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

NO. JLH. PEMBAYARAN TAGIHAN INVOICE JLH. PEMBAYARAN SISA DANA


URAIAN TOTAL DANA
S/D BULAN LALU NO. 07 S/D BULAN INI Rp.

I. BIAYA LANGSUNG PERSONIL 4,166,344,500.00 850,100,355.00 169,389,000.00 1,019,489,355.00 3,146,855,145.00


-
II. BIAYA LANGSUNG NON PERSONIL 1,285,850,000.00 272,797,000.00 50,150,000.00 322,947,000.00 962,903,000.00
BIAYA MOBILISASI DAN DEMOBILISASI - - - - -
BIAYA PERJALANAN DINAS 21,600,000.00 - - - 21,600,000.00
BIAYA KANTOR 335,000,000.00 72,762,000.00 13,400,000.00 86,162,000.00 248,838,000.00
BIAYA PELAPORAN 26,250,000.00 6,500,000.00 500,000.00 7,000,000.00 19,250,000.00
BIAYA AKOMODASI 903,000,000.00 193,535,000.00 36,250,000.00 229,785,000.00 673,215,000.00

SUB TOTAL (I+II) 5,452,194,500.00 1,122,897,355.00 219,539,000.00 1,342,436,355.00 4,109,758,145.00


PPN 545,219,450.00 112,289,735.50 21,953,900.00 134,243,635.50 410,975,814.50
SUB TOTAL 5,997,413,950.00 1,235,187,090.50 241,492,900.00 1,476,679,990.50 4,520,733,959.50
NILAI KONTRAK DIBULATKAN 5,997,413,000.00
PENGEMBALIAN UANG MUKA 899,611,950.00 458,203,977.00 110,351,993.00 568,555,970.00 331,055,980.00
TOTAL 5,097,801,050.00 776,983,113.50 131,140,907.00 908,124,020.50 4,189,677,979.50
DIBULATKAN 776,983,113.00 131,140,907.00 908,124,020.00 4,189,677,980.00

1,199,482,600.00

Jayapura, 01 Maret 2021

PPK PENGAWASAN Konsultan Supervisi


SATKER P2JN PROVINSI PAPUA (JAYAPURA)
PT. WINSOLUSI KONSULTAN

SAM RANDA, S.T, M.Eng ISNAINI SYAWIK, ST


NIP. 19830422 200801 1 006 Direktur Utama
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Februari 2021 / Invoice 07
TANGGAL : 01 Maret 2021
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

REKAPITULASI INVOICE

NO. URAIAN BIAYA (Rp.)

I. BIAYA LANGSUNG PERSONIL 169,389,000.00

II. BIAYA LANGSUNG NON PERSONIL 50,150,000.00


BIAYA MOBILISASI DAN DEMOBILISASI -
BIAYA PERJALANAN DINAS -
BIAYA KANTOR 13,400,000.00
BIAYA PELAPORAN 500,000.00
BIAYA AKOMODASI 36,250,000.00

SUB TOTAL ( I + II ) 219,539,000.00


PPN 10% 21,953,900.00
SUB TOTAL 241,492,900.00
PENGEMBALIAN UANG MUKA 15% 110,351,993.00
TOTAL 131,140,907.00
DIBULATKAN 131,140,907.00

Total Pembayaran pada Tagihan ini Rp. 131,140,907.00


Terbilang : Err:511

Mohon Tagihan untuk bulan Februari 2021 dimasukan pada rekening PT. WINSOLUSI KONSULTAN Nomor Rekening :
0416.01.000160.300 BRI Cabang Kelapa Gading 2

Jayapura, 01 Maret 2021


PPK PENGAWASAN Konsultan Supervisi
SATKER P2JN PROVINSI PAPUA (JAYAPURA)
PT. WINSOLUSI KONSULTAN

SAM RANDA, S.T, M.Eng ISNAINI SYAWIK, ST


NIP. 19830422 200801 1 006 Direktur Utama
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Februari 2021 / Invoice 07
TANGGAL : 01 Maret 2021
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

I. BIAYA LANGSUNG PERSONIL


HARGA JUMLAH HARGA PEMBAYARAN TAGIHAN INVOICE NO. 07 PEMBAYARAN
URAIAN SATUAN S/D (Bulan Februari 2021) S/D SISA DANA
NO. JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU ORANG WAKTU/ JUMLAH BULAN INI
(Rp) BULAN (RP) (Rp) (Rp)
a BIAYA TENAGA AHLI
Site Supervision Engineer 1.00 25.00 OB 32,697,000.00 817,425,000.00 177,544,710.00 1.00 1.00 32,697,000.00 210,241,710.00 607,183,290.00
Quality Engineer-1 1.00 24.00 OB 30,880,500.00 741,132,000.00 135,874,200.00 1.00 1.00 30,880,500.00 166,754,700.00 574,377,300.00
Inspection Engineer/Quantity Engineer 1.00 25.00 OB 30,880,500.00 772,012,500.00 167,681,115.00 1.00 1.00 30,880,500.00 198,561,615.00 573,450,885.00
Health Safety Enviroment Engineer 1.00 25.00 OB 25,431,000.00 635,775,000.00 138,090,330.00 1.00 1.00 25,431,000.00 163,521,330.00 472,253,670.00

Sub Total a 2,966,344,500.00 619,190,355.00 119,889,000.00 739,079,355.00 2,227,265,145.00


b BIAYA ASISTEN TENAGA AHLI
Inspector -1 1.00 23.00 OB 12,500,000.00 287,500,000.00 42,875,000.00 1.00 1.00 12,500,000.00 55,375,000.00 232,125,000.00
Surveyor Technician -1 1.00 25.00 OB 12,500,000.00 312,500,000.00 67,875,000.00 1.00 1.00 12,500,000.00 80,375,000.00 232,125,000.00
Material Technician -1 1.00 24.00 OB 12,500,000.00 300,000,000.00 55,000,000.00 1.00 1.00 12,500,000.00 67,500,000.00 232,500,000.00

Sub Total b 900,000,000.00 165,750,000.00 37,500,000.00 203,250,000.00 696,750,000.00


c BIAYA STAF PENDUKUNG
Operator Komputer 1.00 25.00 OB 8,000,000.00 200,000,000.00 43,440,000.00 1.00 1.00 8,000,000.00 51,440,000.00 148,560,000.00
Pesuruh/Penjaga Kantor 1.00 25.00 OB 4,000,000.00 100,000,000.00 21,720,000.00 1.00 1.00 4,000,000.00 25,720,000.00 74,280,000.00

Sub Total c 300,000,000.00 65,160,000.00 12,000,000.00 77,160,000.00 222,840,000.00

TOTAL a+b+c 4,166,344,500.00 850,100,355.00 - - 169,389,000.00 1,019,489,355.00 3,146,855,145.00


NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Februari 2021 / Invoice 07
TANGGAL : 01 Maret 2021
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

II. BIAYA LANGSUNG NON PERSONIL


HARGA PEMBAYARAN TAGIHAN INVOICE NO. 07 PEMBAYARAN
JUMLAH HARGA
SATUAN S/D (Bulan Februari 2021) S/D SISA DANA
NO. URAIAN JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU JUMLAH BULAN INI
ORANG TRIP
(Rp) (RP) (Rp) (Rp)
a MOBILISASI DAN DEMOBILISASI
- Mobilisasi
Site Supervision Engineer - - Trip - - - - - - - -
Quality Engineer-1 - - Trip - - - - - - - -
Inspection Engineer/Quantity Engineer - - Trip - - - - - - - -
Health Safety Enviroment Engineer - - - - - - - - - -
- Demobilisasi
Site Supervision Engineer - - Trip - - - - - - - -
Quality Engineer-1 - - Trip - - - - - - - -
Inspection Engineer/Quantity Engineer - - Trip - - - - - - - -
Health Safety Enviroment Engineer - - Trip - - - - - - - -
Sub Total a - - - - -
b BIAYA PERJALANAN DINAS
Tiket Perjalanan (PP) Termasuk Ongkos Taxi 6.00 Trip 2,000,000.00 12,000,000.00 - - - - - 12,000,000.00
Biaya Penginapan 24.00 Hari 400,000.00 9,600,000.00 - - - - - 9,600,000.00

Sub Total b 21,600,000.00 - - - 21,600,000.00


HARGA PEMBAYARAN TAGIHAN INVOICE NO. 07 PEMBAYARAN
SATUAN JUMLAH HARGA S/D (Bulan Februari 2021) S/D SISA DANA
NO. URAIAN JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU JUMLAH BULAN INI
VOLUME BULAN
(Rp) (RP) (Rp) (Rp)
c BIAYA KANTOR
Sewa Kantor 1.00 25.00 Bln 5,000,000.00 125,000,000.00 27,150,000.00 1.00 1.00 5,000,000.00 32,150,000.00 92,850,000.00
Sewa Operasional Kantor (Air dan Listrik) 1.00 25.00 Bln 1,500,000.00 37,500,000.00 8,145,000.00 1.00 1.00 1,500,000.00 9,645,000.00 27,855,000.00
Sewa Penunjang Kantor :
- Laptop-1 1.00 25.00 Bln 1,600,000.00 40,000,000.00 8,688,000.00 1.00 1.00 1,600,000.00 10,288,000.00 29,712,000.00
- Laptop-2 1.00 25.00 Bln 1,600,000.00 40,000,000.00 8,688,000.00 1.00 1.00 1,600,000.00 10,288,000.00 29,712,000.00
- Printer A3 1.00 25.00 Bln 700,000.00 17,500,000.00 3,801,000.00 1.00 1.00 700,000.00 4,501,000.00 12,999,000.00
- Printer A4 1.00 25.00 Bln 500,000.00 12,500,000.00 2,715,000.00 1.00 1.00 500,000.00 3,215,000.00 9,285,000.00
Komunikasi (Pulsa Telepon + lnternet) 1.00 25.00 Bln 1,500,000.00 37,500,000.00 8,145,000.00 1.00 1.00 1,500,000.00 9,645,000.00 27,855,000.00
Bahan untuk peralatan kantor 1.00 25.00 Bln 1,000,000.00 25,000,000.00 5,430,000.00 1.00 1.00 1,000,000.00 6,430,000.00 18,570,000.00

Sub Total c 335,000,000.00 72,762,000.00 13,400,000.00 86,162,000.00 248,838,000.00


d BIAYA PELAPORAN
Laporan RMK 5.00 5.00 Eks 150,000.00 750,000.00 750,000.00 - - - 750,000.00 -
Laporan Pendahuluan 5.00 5.00 Eks 150,000.00 750,000.00 750,000.00 - - - 750,000.00 -
Laporan Bulanan 125.00 5.00 Eks 100,000.00 12,500,000.00 2,500,000.00 5.00 1.00 500,000.00 3,000,000.00 9,500,000.00
Laporan Triwulan 40.00 5.00 Eks 250,000.00 10,000,000.00 2,500,000.00 - - - 2,500,000.00 7,500,000.00
Laporan Akhir 5.00 5.00 Eks 250,000.00 1,250,000.00 - - - - - 1,250,000.00
Hard Disk (File Laporan dan Dokumentasi) 1.00 1.00 Buah 1,000,000.00 1,000,000.00 - - - - - 1,000,000.00

Sub Total d 26,250,000.00 6,500,000.00 500,000.00 7,000,000.00 19,250,000.00

e BIAYA AKOMODASI
- Biaya Sewa
Sewa Mobil Double Gardan-1 1.00 25.00 Bln 25,000,000.00 625,000,000.00 135,750,000.00 1.00 1.00 25,000,000.00 160,750,000.00 464,250,000.00
Sewa Motor Lapangan -1 1.00 25.00 Bln 2,500,000.00 62,500,000.00 13,575,000.00 1.00 1.00 2,500,000.00 16,075,000.00 46,425,000.00
Sewa Motor Lapangan -2 1.00 25.00 Bln 2,500,000.00 62,500,000.00 13,575,000.00 1.00 1.00 2,500,000.00 16,075,000.00 46,425,000.00
- Tunjangan Perumahan
Site Supervision Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 5,430,000.00 1.00 1.00 1,000,000.00 6,430,000.00 18,570,000.00
Quality Engineer-1 1.00 24.00 Bln 1,000,000.00 24,000,000.00 4,400,000.00 1.00 1.00 1,000,000.00 5,400,000.00 18,600,000.00
Inspection Engineer/Quantity Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 5,430,000.00 1.00 1.00 1,000,000.00 6,430,000.00 18,570,000.00
Health Safety Enviroment Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 5,430,000.00 1.00 1.00 1,000,000.00 6,430,000.00 18,570,000.00
Inspector -1 1.00 23.00 Bln 750,000.00 17,250,000.00 2,572,500.00 1.00 1.00 750,000.00 3,322,500.00 13,927,500.00
Surveyor Technician -1 1.00 25.00 Bln 750,000.00 18,750,000.00 4,072,500.00 1.00 1.00 750,000.00 4,822,500.00 13,927,500.00
Material Technician -1 1.00 24.00 Bln 750,000.00 18,000,000.00 3,300,000.00 1.00 1.00 750,000.00 4,050,000.00 13,950,000.00

Sub Total e 903,000,000.00 193,535,000.00 36,250,000.00 229,785,000.00 673,215,000.00

Sub Total a+b+c+d+e 1,285,850,000.00 272,797,000.00 50,150,000.00 322,947,000.00 962,903,000.00


LAPORAN BULANAN KEADAAN DANA
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/SPMK/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Maret 2021 / Invoice 08
TANGGAL : 01 April 2021
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

NO. JLH. PEMBAYARAN TAGIHAN INVOICE JLH. PEMBAYARAN SISA DANA


URAIAN TOTAL DANA
S/D BULAN LALU NO. 08 S/D BULAN INI Rp.

I. BIAYA LANGSUNG PERSONIL 4,166,344,500.00 1,019,489,355.00 169,389,000.00 1,188,878,355.00 2,977,466,145.00


-
II. BIAYA LANGSUNG NON PERSONIL 1,285,850,000.00 322,947,000.00 50,150,000.00 373,097,000.00 912,753,000.00
BIAYA MOBILISASI DAN DEMOBILISASI - - - - -
BIAYA PERJALANAN DINAS 21,600,000.00 - - - 21,600,000.00
BIAYA KANTOR 335,000,000.00 86,162,000.00 13,400,000.00 99,562,000.00 235,438,000.00
BIAYA PELAPORAN 26,250,000.00 7,000,000.00 500,000.00 7,500,000.00 18,750,000.00
BIAYA AKOMODASI 903,000,000.00 229,785,000.00 36,250,000.00 266,035,000.00 636,965,000.00

SUB TOTAL (I+II) 5,452,194,500.00 1,342,436,355.00 219,539,000.00 1,561,975,355.00 3,890,219,145.00


PPN 545,219,450.00 134,243,635.50 21,953,900.00 156,197,535.50 389,021,914.50
SUB TOTAL 5,997,413,950.00 1,476,679,990.50 241,492,900.00 1,718,172,890.50 4,279,241,059.50
NILAI KONTRAK DIBULATKAN 5,997,413,000.00
PENGEMBALIAN UANG MUKA 899,611,950.00 568,555,970.00 110,351,993.00 678,907,963.00 220,703,987.00
TOTAL 5,097,801,050.00 908,124,020.50 131,140,907.00 1,039,264,927.50 4,058,537,072.50
DIBULATKAN 908,124,020.00 131,140,907.00 1,039,264,927.00 4,058,537,073.00

1,199,482,600.00

Jayapura, 01 April 2021

PPK PENGAWASAN Konsultan Supervisi


SATKER P2JN PROVINSI PAPUA (JAYAPURA)
PT. WINSOLUSI KONSULTAN

SAM RANDA, S.T, M.Eng ISNAINI SYAWIK, ST


NIP. 19830422 200801 1 006 Direktur Utama
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/SPMK/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Maret 2021 / Invoice 08
TANGGAL : 01 April 2021
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

REKAPITULASI INVOICE

NO. URAIAN BIAYA (Rp.)

I. BIAYA LANGSUNG PERSONIL 169,389,000.00

II. BIAYA LANGSUNG NON PERSONIL 50,150,000.00


BIAYA MOBILISASI DAN DEMOBILISASI -
BIAYA PERJALANAN DINAS -
BIAYA KANTOR 13,400,000.00
BIAYA PELAPORAN 500,000.00
BIAYA AKOMODASI 36,250,000.00

SUB TOTAL ( I + II ) 219,539,000.00


PPN 10% 21,953,900.00
SUB TOTAL 241,492,900.00
PENGEMBALIAN UANG MUKA 15% 110,351,993.00
TOTAL 131,140,907.00
DIBULATKAN 131,140,907.00

Total Pembayaran pada Tagihan ini Rp. 131,140,907.00


Terbilang : Err:511

Mohon Tagihan untuk bulan Maret 2021 dimasukan pada rekening PT. WINSOLUSI KONSULTAN Nomor Rekening :
0416.01.000160.300 BRI Cabang Kelapa Gading 2

Jayapura, 01 April 2021


PPK PENGAWASAN Konsultan Supervisi
SATKER P2JN PROVINSI PAPUA (JAYAPURA)
PT. WINSOLUSI KONSULTAN

SAM RANDA, S.T, M.Eng ISNAINI SYAWIK, ST


NIP. 19830422 200801 1 006 Direktur Utama
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/SPMK/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Maret 2021 / Invoice 08
TANGGAL : 01 April 2021
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

I. BIAYA LANGSUNG PERSONIL


HARGA JUMLAH HARGA PEMBAYARAN TAGIHAN INVOICE NO. 08 PEMBAYARAN
URAIAN SATUAN S/D (Bulan Maret 2021) S/D SISA DANA
NO. JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU ORANG WAKTU/ JUMLAH BULAN INI
(Rp) BULAN (RP) (Rp) (Rp)
a BIAYA TENAGA AHLI
Site Supervision Engineer 1.00 25.00 OB 32,697,000.00 817,425,000.00 210,241,710.00 1.00 1.00 32,697,000.00 242,938,710.00 574,486,290.00
Quality Engineer-1 1.00 24.00 OB 30,880,500.00 741,132,000.00 166,754,700.00 1.00 1.00 30,880,500.00 197,635,200.00 543,496,800.00
Inspection Engineer/Quantity Engineer 1.00 25.00 OB 30,880,500.00 772,012,500.00 198,561,615.00 1.00 1.00 30,880,500.00 229,442,115.00 542,570,385.00
Health Safety Enviroment Engineer 1.00 25.00 OB 25,431,000.00 635,775,000.00 163,521,330.00 1.00 1.00 25,431,000.00 188,952,330.00 446,822,670.00

Sub Total a 2,966,344,500.00 739,079,355.00 119,889,000.00 858,968,355.00 2,107,376,145.00


b BIAYA ASISTEN TENAGA AHLI
Inspector -1 1.00 23.00 OB 12,500,000.00 287,500,000.00 55,375,000.00 1.00 1.00 12,500,000.00 67,875,000.00 219,625,000.00
Surveyor Technician -1 1.00 25.00 OB 12,500,000.00 312,500,000.00 80,375,000.00 1.00 1.00 12,500,000.00 92,875,000.00 219,625,000.00
Material Technician -1 1.00 24.00 OB 12,500,000.00 300,000,000.00 67,500,000.00 1.00 1.00 12,500,000.00 80,000,000.00 220,000,000.00

Sub Total b 900,000,000.00 203,250,000.00 37,500,000.00 240,750,000.00 659,250,000.00


c BIAYA STAF PENDUKUNG
Operator Komputer 1.00 25.00 OB 8,000,000.00 200,000,000.00 51,440,000.00 1.00 1.00 8,000,000.00 59,440,000.00 140,560,000.00
Pesuruh/Penjaga Kantor 1.00 25.00 OB 4,000,000.00 100,000,000.00 25,720,000.00 1.00 1.00 4,000,000.00 29,720,000.00 70,280,000.00

Sub Total c 300,000,000.00 77,160,000.00 12,000,000.00 89,160,000.00 210,840,000.00

TOTAL a+b+c 4,166,344,500.00 1,019,489,355.00 - - 169,389,000.00 1,188,878,355.00 2,977,466,145.00


NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/SPMK/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Maret 2021 / Invoice 08
TANGGAL : 01 April 2021
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

II. BIAYA LANGSUNG NON PERSONIL


HARGA PEMBAYARAN TAGIHAN INVOICE NO. 08 PEMBAYARAN
JUMLAH HARGA
SATUAN S/D (Bulan Maret 2021) S/D SISA DANA
NO. URAIAN JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU JUMLAH BULAN INI
ORANG TRIP
(Rp) (RP) (Rp) (Rp)
a MOBILISASI DAN DEMOBILISASI
- Mobilisasi
Site Supervision Engineer - - Trip - - - - - - - -
Quality Engineer-1 - - Trip - - - - - - - -
Inspection Engineer/Quantity Engineer - - Trip - - - - - - - -
Health Safety Enviroment Engineer - - - - - - - - - -
- Demobilisasi
Site Supervision Engineer - - Trip - - - - - - - -
Quality Engineer-1 - - Trip - - - - - - - -
Inspection Engineer/Quantity Engineer - - Trip - - - - - - - -
Health Safety Enviroment Engineer - - Trip - - - - - - - -
Sub Total a - - - - -
b BIAYA PERJALANAN DINAS
Tiket Perjalanan (PP) Termasuk Ongkos Taxi 6.00 Trip 2,000,000.00 12,000,000.00 - - - - - 12,000,000.00
Biaya Penginapan 24.00 Hari 400,000.00 9,600,000.00 - - - - - 9,600,000.00

Sub Total b 21,600,000.00 - - - 21,600,000.00


HARGA PEMBAYARAN TAGIHAN INVOICE NO. 08 PEMBAYARAN
SATUAN JUMLAH HARGA S/D (Bulan Maret 2021) S/D SISA DANA
NO. URAIAN JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU JUMLAH BULAN INI
VOLUME BULAN
(Rp) (RP) (Rp) (Rp)
c BIAYA KANTOR
Sewa Kantor 1.00 25.00 Bln 5,000,000.00 125,000,000.00 32,150,000.00 1.00 1.00 5,000,000.00 37,150,000.00 87,850,000.00
Sewa Operasional Kantor (Air dan Listrik) 1.00 25.00 Bln 1,500,000.00 37,500,000.00 9,645,000.00 1.00 1.00 1,500,000.00 11,145,000.00 26,355,000.00
Sewa Penunjang Kantor :
- Laptop-1 1.00 25.00 Bln 1,600,000.00 40,000,000.00 10,288,000.00 1.00 1.00 1,600,000.00 11,888,000.00 28,112,000.00
- Laptop-2 1.00 25.00 Bln 1,600,000.00 40,000,000.00 10,288,000.00 1.00 1.00 1,600,000.00 11,888,000.00 28,112,000.00
- Printer A3 1.00 25.00 Bln 700,000.00 17,500,000.00 4,501,000.00 1.00 1.00 700,000.00 5,201,000.00 12,299,000.00
- Printer A4 1.00 25.00 Bln 500,000.00 12,500,000.00 3,215,000.00 1.00 1.00 500,000.00 3,715,000.00 8,785,000.00
Komunikasi (Pulsa Telepon + lnternet) 1.00 25.00 Bln 1,500,000.00 37,500,000.00 9,645,000.00 1.00 1.00 1,500,000.00 11,145,000.00 26,355,000.00
Bahan untuk peralatan kantor 1.00 25.00 Bln 1,000,000.00 25,000,000.00 6,430,000.00 1.00 1.00 1,000,000.00 7,430,000.00 17,570,000.00

Sub Total c 335,000,000.00 86,162,000.00 13,400,000.00 99,562,000.00 235,438,000.00


d BIAYA PELAPORAN
Laporan RMK 5.00 5.00 Eks 150,000.00 750,000.00 750,000.00 - - - 750,000.00 -
Laporan Pendahuluan 5.00 5.00 Eks 150,000.00 750,000.00 750,000.00 - - - 750,000.00 -
Laporan Bulanan 125.00 5.00 Eks 100,000.00 12,500,000.00 3,000,000.00 5.00 1.00 500,000.00 3,500,000.00 9,000,000.00
Laporan Triwulan 40.00 5.00 Eks 250,000.00 10,000,000.00 2,500,000.00 - - - 2,500,000.00 7,500,000.00
Laporan Akhir 5.00 5.00 Eks 250,000.00 1,250,000.00 - - - - - 1,250,000.00
Hard Disk (File Laporan dan Dokumentasi) 1.00 1.00 Buah 1,000,000.00 1,000,000.00 - - - - - 1,000,000.00

Sub Total d 26,250,000.00 7,000,000.00 500,000.00 7,500,000.00 18,750,000.00


e BIAYA AKOMODASI
- Biaya Sewa
Sewa Mobil Double Gardan-1 1.00 25.00 Bln 25,000,000.00 625,000,000.00 160,750,000.00 1.00 1.00 25,000,000.00 185,750,000.00 439,250,000.00
Sewa Motor Lapangan -1 1.00 25.00 Bln 2,500,000.00 62,500,000.00 16,075,000.00 1.00 1.00 2,500,000.00 18,575,000.00 43,925,000.00
Sewa Motor Lapangan -2 1.00 25.00 Bln 2,500,000.00 62,500,000.00 16,075,000.00 1.00 1.00 2,500,000.00 18,575,000.00 43,925,000.00
- Tunjangan Perumahan
Site Supervision Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 6,430,000.00 1.00 1.00 1,000,000.00 7,430,000.00 17,570,000.00
Quality Engineer-1 1.00 24.00 Bln 1,000,000.00 24,000,000.00 5,400,000.00 1.00 1.00 1,000,000.00 6,400,000.00 17,600,000.00
Inspection Engineer/Quantity Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 6,430,000.00 1.00 1.00 1,000,000.00 7,430,000.00 17,570,000.00
Health Safety Enviroment Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 6,430,000.00 1.00 1.00 1,000,000.00 7,430,000.00 17,570,000.00
Inspector -1 1.00 23.00 Bln 750,000.00 17,250,000.00 3,322,500.00 1.00 1.00 750,000.00 4,072,500.00 13,177,500.00
Surveyor Technician -1 1.00 25.00 Bln 750,000.00 18,750,000.00 4,822,500.00 1.00 1.00 750,000.00 5,572,500.00 13,177,500.00
Material Technician -1 1.00 24.00 Bln 750,000.00 18,000,000.00 4,050,000.00 1.00 1.00 750,000.00 4,800,000.00 13,200,000.00

Sub Total e 903,000,000.00 229,785,000.00 36,250,000.00 266,035,000.00 636,965,000.00

Sub Total a+b+c+d+e 1,285,850,000.00 322,947,000.00 50,150,000.00 373,097,000.00 912,753,000.00


LAPORAN BULANAN KEADAAN DANA
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/SPMK/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : April 2021 / Invoice 09
TANGGAL : 03 Mei 2021
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

P
NO. JLH. PEMBAYARAN TAGIHAN INVOICE JLH. PEMBAYARAN SISA DANA
URAIAN TOTAL DANA
S/D BULAN LALU NO. 09 S/D BULAN INI Rp.

I. BIAYA LANGSUNG PERSONIL 4,166,344,500.00 1,188,878,355.00 169,389,000.00 1,358,267,355.00 2,808,077,145.00


-
II. BIAYA LANGSUNG NON PERSONIL 1,285,850,000.00 373,097,000.00 51,400,000.00 424,497,000.00 861,353,000.00
BIAYA MOBILISASI DAN DEMOBILISASI - - - - -
BIAYA PERJALANAN DINAS 21,600,000.00 - - - 21,600,000.00
BIAYA KANTOR 335,000,000.00 99,562,000.00 13,400,000.00 112,962,000.00 222,038,000.00
BIAYA PELAPORAN 26,250,000.00 7,500,000.00 1,750,000.00 9,250,000.00 17,000,000.00
BIAYA AKOMODASI 903,000,000.00 266,035,000.00 36,250,000.00 302,285,000.00 600,715,000.00

SUB TOTAL (I+II) 5,452,194,500.00 1,561,975,355.00 220,789,000.00 1,782,764,355.00 3,669,430,145.00


PPN 545,219,450.00 156,197,535.50 22,078,900.00 178,276,435.50 366,943,014.50
SUB TOTAL 5,997,413,950.00 1,718,172,890.50 242,867,900.00 1,961,040,790.50 4,036,373,159.50
NILAI KONTRAK DIBULATKAN 5,997,413,000.00
PENGEMBALIAN UANG MUKA 899,611,950.00 678,907,963.00 110,351,993.00 789,259,956.00 110,351,994.00
TOTAL 5,097,801,050.00 1,039,264,927.50 132,515,907.00 1,171,780,834.50 3,926,021,165.50
DIBULATKAN 1,039,264,927.00 132,515,907.00 1,171,780,834.00 3,926,021,166.00

1,199,482,600.00

Jayapura, 01 Mei 2021

PPK PENGAWASAN Konsultan Supervisi


SATKER P2JN PROVINSI PAPUA (JAYAPURA)
PT. WINSOLUSI KONSULTAN

SAM RANDA, S.T, M.Eng ISNAINI SYAWIK, ST


NIP. 19830422 200801 1 006 Direktur Utama
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/SPMK/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : April 2021 / Invoice 09
TANGGAL : 03 Mei 2021
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

REKAPITULASI INVOICE

NO. URAIAN BIAYA (Rp.)

I. BIAYA LANGSUNG PERSONIL 169,389,000.00

II. BIAYA LANGSUNG NON PERSONIL 51,400,000.00


BIAYA MOBILISASI DAN DEMOBILISASI -
BIAYA PERJALANAN DINAS -
BIAYA KANTOR 13,400,000.00
BIAYA PELAPORAN 1,750,000.00
BIAYA AKOMODASI 36,250,000.00

SUB TOTAL ( I + II ) 220,789,000.00


PPN 10% 22,078,900.00
SUB TOTAL 242,867,900.00
PENGEMBALIAN UANG MUKA 15% 110,351,993.00
TOTAL 132,515,907.00
DIBULATKAN 132,515,907.00

Total Pembayaran pada Tagihan ini Rp. 132,515,907.00


Terbilang : Err:511

Mohon Tagihan untuk bulan April 2021 dimasukan pada rekening PT. WINSOLUSI KONSULTAN Nomor Rekening :
0416.01.000160.300 BRI Cabang Kelapa Gading 2

Jayapura, 01 Mei 2021


PPK PENGAWASAN Konsultan Supervisi
SATKER P2JN PROVINSI PAPUA (JAYAPURA)
PT. WINSOLUSI KONSULTAN

SAM RANDA, S.T, M.Eng ISNAINI SYAWIK, ST


NIP. 19830422 200801 1 006 Direktur Utama
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/SPMK/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : April 2021 / Invoice 09
TANGGAL : 03 Mei 2021
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

I. BIAYA LANGSUNG PERSONIL


HARGA JUMLAH HARGA PEMBAYARAN TAGIHAN INVOICE NO. 09 PEMBAYARAN
URAIAN SATUAN S/D (Bulan April 2021) S/D SISA DANA
NO. JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU ORANG WAKTU/ JUMLAH BULAN INI
(Rp) BULAN (RP) (Rp) (Rp)
a BIAYA TENAGA AHLI
Site Supervision Engineer 1.00 25.00 OB 32,697,000.00 817,425,000.00 242,938,710.00 1.00 1.00 32,697,000.00 275,635,710.00 541,789,290.00
Quality Engineer-1 1.00 24.00 OB 30,880,500.00 741,132,000.00 197,635,200.00 1.00 1.00 30,880,500.00 228,515,700.00 512,616,300.00
Inspection Engineer/Quantity Engineer 1.00 25.00 OB 30,880,500.00 772,012,500.00 229,442,115.00 1.00 1.00 30,880,500.00 260,322,615.00 511,689,885.00
Health Safety Enviroment Engineer 1.00 25.00 OB 25,431,000.00 635,775,000.00 188,952,330.00 1.00 1.00 25,431,000.00 214,383,330.00 421,391,670.00

Sub Total a 2,966,344,500.00 858,968,355.00 119,889,000.00 978,857,355.00 1,987,487,145.00


b BIAYA ASISTEN TENAGA AHLI
Inspector -1 1.00 23.00 OB 12,500,000.00 287,500,000.00 67,875,000.00 1.00 1.00 12,500,000.00 80,375,000.00 207,125,000.00
Surveyor Technician -1 1.00 25.00 OB 12,500,000.00 312,500,000.00 92,875,000.00 1.00 1.00 12,500,000.00 105,375,000.00 207,125,000.00
Material Technician -1 1.00 24.00 OB 12,500,000.00 300,000,000.00 80,000,000.00 1.00 1.00 12,500,000.00 92,500,000.00 207,500,000.00

Sub Total b 900,000,000.00 240,750,000.00 37,500,000.00 278,250,000.00 621,750,000.00


c BIAYA STAF PENDUKUNG
Operator Komputer 1.00 25.00 OB 8,000,000.00 200,000,000.00 59,440,000.00 1.00 1.00 8,000,000.00 67,440,000.00 132,560,000.00
Pesuruh/Penjaga Kantor 1.00 25.00 OB 4,000,000.00 100,000,000.00 29,720,000.00 1.00 1.00 4,000,000.00 33,720,000.00 66,280,000.00

Sub Total c 300,000,000.00 89,160,000.00 12,000,000.00 101,160,000.00 198,840,000.00

TOTAL a+b+c 4,166,344,500.00 1,188,878,355.00 - - 169,389,000.00 1,358,267,355.00 2,808,077,145.00


NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/SPMK/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : April 2021 / Invoice 09
TANGGAL : 03 Mei 2021
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

II. BIAYA LANGSUNG NON PERSONIL


HARGA PEMBAYARAN TAGIHAN INVOICE NO. 09 PEMBAYARAN
JUMLAH HARGA
SATUAN S/D (Bulan April 2021) S/D SISA DANA
NO. URAIAN JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU JUMLAH BULAN INI
ORANG TRIP
(Rp) (RP) (Rp) (Rp)
a MOBILISASI DAN DEMOBILISASI
- Mobilisasi
Site Supervision Engineer - - Trip - - - - - - - -
Quality Engineer-1 - - Trip - - - - - - - -
Inspection Engineer/Quantity Engineer - - Trip - - - - - - - -
Health Safety Enviroment Engineer - - - - - - - - - -
- Demobilisasi
Site Supervision Engineer - - Trip - - - - - - - -
Quality Engineer-1 - - Trip - - - - - - - -
Inspection Engineer/Quantity Engineer - - Trip - - - - - - - -
Health Safety Enviroment Engineer - - Trip - - - - - - - -
Sub Total a - - - - -
b BIAYA PERJALANAN DINAS
Tiket Perjalanan (PP) Termasuk Ongkos Taxi 6.00 Trip 2,000,000.00 12,000,000.00 - - - - - 12,000,000.00
Biaya Penginapan 24.00 Hari 400,000.00 9,600,000.00 - - - - - 9,600,000.00

Sub Total b 21,600,000.00 - - - 21,600,000.00


HARGA PEMBAYARAN TAGIHAN INVOICE NO. 09 PEMBAYARAN
SATUAN JUMLAH HARGA S/D (Bulan April 2021) S/D SISA DANA
NO. URAIAN JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU JUMLAH BULAN INI
VOLUME BULAN
(Rp) (RP) (Rp) (Rp)
c BIAYA KANTOR
Sewa Kantor 1.00 25.00 Bln 5,000,000.00 125,000,000.00 37,150,000.00 1.00 1.00 5,000,000.00 42,150,000.00 82,850,000.00
Sewa Operasional Kantor (Air dan Listrik) 1.00 25.00 Bln 1,500,000.00 37,500,000.00 11,145,000.00 1.00 1.00 1,500,000.00 12,645,000.00 24,855,000.00
Sewa Penunjang Kantor :
- Laptop-1 1.00 25.00 Bln 1,600,000.00 40,000,000.00 11,888,000.00 1.00 1.00 1,600,000.00 13,488,000.00 26,512,000.00
- Laptop-2 1.00 25.00 Bln 1,600,000.00 40,000,000.00 11,888,000.00 1.00 1.00 1,600,000.00 13,488,000.00 26,512,000.00
- Printer A3 1.00 25.00 Bln 700,000.00 17,500,000.00 5,201,000.00 1.00 1.00 700,000.00 5,901,000.00 11,599,000.00
- Printer A4 1.00 25.00 Bln 500,000.00 12,500,000.00 3,715,000.00 1.00 1.00 500,000.00 4,215,000.00 8,285,000.00
Komunikasi (Pulsa Telepon + lnternet) 1.00 25.00 Bln 1,500,000.00 37,500,000.00 11,145,000.00 1.00 1.00 1,500,000.00 12,645,000.00 24,855,000.00
Bahan untuk peralatan kantor 1.00 25.00 Bln 1,000,000.00 25,000,000.00 7,430,000.00 1.00 1.00 1,000,000.00 8,430,000.00 16,570,000.00

Sub Total c 335,000,000.00 99,562,000.00 13,400,000.00 112,962,000.00 222,038,000.00


d BIAYA PELAPORAN
Laporan RMK 5.00 5.00 Eks 150,000.00 750,000.00 750,000.00 - - - 750,000.00 -
Laporan Pendahuluan 5.00 5.00 Eks 150,000.00 750,000.00 750,000.00 - - - 750,000.00 -
Laporan Bulanan 125.00 5.00 Eks 100,000.00 12,500,000.00 3,500,000.00 5.00 1.00 500,000.00 4,000,000.00 8,500,000.00
Laporan Triwulan 40.00 5.00 Eks 250,000.00 10,000,000.00 2,500,000.00 5.00 1.00 1,250,000.00 3,750,000.00 6,250,000.00
Laporan Akhir 5.00 5.00 Eks 250,000.00 1,250,000.00 - - - - - 1,250,000.00
Hard Disk (File Laporan dan Dokumentasi) 1.00 1.00 Buah 1,000,000.00 1,000,000.00 - - - - - 1,000,000.00

Sub Total d 26,250,000.00 7,500,000.00 1,750,000.00 9,250,000.00 17,000,000.00

e BIAYA AKOMODASI
- Biaya Sewa
Sewa Mobil Double Gardan-1 1.00 25.00 Bln 25,000,000.00 625,000,000.00 185,750,000.00 1.00 1.00 25,000,000.00 210,750,000.00 414,250,000.00
Sewa Motor Lapangan -1 1.00 25.00 Bln 2,500,000.00 62,500,000.00 18,575,000.00 1.00 1.00 2,500,000.00 21,075,000.00 41,425,000.00
Sewa Motor Lapangan -2 1.00 25.00 Bln 2,500,000.00 62,500,000.00 18,575,000.00 1.00 1.00 2,500,000.00 21,075,000.00 41,425,000.00
- Tunjangan Perumahan
Site Supervision Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 7,430,000.00 1.00 1.00 1,000,000.00 8,430,000.00 16,570,000.00
Quality Engineer-1 1.00 24.00 Bln 1,000,000.00 24,000,000.00 6,400,000.00 1.00 1.00 1,000,000.00 7,400,000.00 16,600,000.00
Inspection Engineer/Quantity Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 7,430,000.00 1.00 1.00 1,000,000.00 8,430,000.00 16,570,000.00
Health Safety Enviroment Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 7,430,000.00 1.00 1.00 1,000,000.00 8,430,000.00 16,570,000.00
Inspector -1 1.00 23.00 Bln 750,000.00 17,250,000.00 4,072,500.00 1.00 1.00 750,000.00 4,822,500.00 12,427,500.00
Surveyor Technician -1 1.00 25.00 Bln 750,000.00 18,750,000.00 5,572,500.00 1.00 1.00 750,000.00 6,322,500.00 12,427,500.00
Material Technician -1 1.00 24.00 Bln 750,000.00 18,000,000.00 4,800,000.00 1.00 1.00 750,000.00 5,550,000.00 12,450,000.00

Sub Total e 903,000,000.00 266,035,000.00 36,250,000.00 302,285,000.00 600,715,000.00

Sub Total a+b+c+d+e 1,285,850,000.00 373,097,000.00 51,400,000.00 424,497,000.00 861,353,000.00


LAPORAN BULANAN KEADAAN DANA
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Mei 2021 / Invoice 10
TANGGAL : 01 Juni 2021
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

NO. JLH. PEMBAYARAN TAGIHAN INVOICE JLH. PEMBAYARAN SISA DANA


URAIAN TOTAL DANA
S/D BULAN LALU NO. 10 S/D BULAN INI Rp.

I. BIAYA LANGSUNG PERSONIL 4,166,344,500.00 1,358,267,355.00 169,389,000.00 1,527,656,355.00 2,638,688,145.00


-
II. BIAYA LANGSUNG NON PERSONIL 1,285,850,000.00 424,497,000.00 50,150,000.00 474,647,000.00 811,203,000.00
BIAYA MOBILISASI DAN DEMOBILISASI - - - - -
BIAYA PERJALANAN DINAS 21,600,000.00 - - - 21,600,000.00
BIAYA KANTOR 335,000,000.00 112,962,000.00 13,400,000.00 126,362,000.00 208,638,000.00
BIAYA PELAPORAN 26,250,000.00 9,250,000.00 500,000.00 9,750,000.00 16,500,000.00
BIAYA AKOMODASI 903,000,000.00 302,285,000.00 36,250,000.00 338,535,000.00 564,465,000.00

SUB TOTAL (I+II) 5,452,194,500.00 1,782,764,355.00 219,539,000.00 2,002,303,355.00 3,449,891,145.00


PPN 545,219,450.00 178,276,435.50 21,953,900.00 200,230,335.50 344,989,114.50
SUB TOTAL 5,997,413,950.00 1,961,040,790.50 241,492,900.00 2,202,533,690.50 3,794,880,259.50
NILAI KONTRAK DIBULATKAN 5,997,413,000.00
PENGEMBALIAN UANG MUKA 899,611,950.00 789,259,956.00 110,351,994.00 899,611,950.00 -
TOTAL 5,097,801,050.00 1,171,780,834.50 131,140,906.00 1,302,921,740.50 3,794,880,259.50
DIBULATKAN 1,171,780,834.00 131,140,906.00 1,302,921,740.00 3,794,880,260.00

1,199,482,600.00

Jayapura, 01 Juni 2021

PPK PENGAWASAN Konsultan Supervisi


SATKER P2JN PROVINSI PAPUA (JAYAPURA)
PT. WINSOLUSI KONSULTAN

SAM RANDA, S.T, M.Eng ISNAINI SYAWIK, ST


NIP. 19830422 200801 1 006 Direktur Utama
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Mei 2021 / Invoice 10
TANGGAL : 01 Juni 2021
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

REKAPITULASI INVOICE

NO. URAIAN BIAYA (Rp.)

I. BIAYA LANGSUNG PERSONIL 169,389,000.00

II. BIAYA LANGSUNG NON PERSONIL 50,150,000.00


BIAYA MOBILISASI DAN DEMOBILISASI -
BIAYA PERJALANAN DINAS -
BIAYA KANTOR 13,400,000.00
BIAYA PELAPORAN 500,000.00
BIAYA AKOMODASI 36,250,000.00

SUB TOTAL ( I + II ) 219,539,000.00


PPN 10% 21,953,900.00
SUB TOTAL 241,492,900.00
PENGEMBALIAN UANG MUKA 15% 110,351,994.00
TOTAL 131,140,906.00
DIBULATKAN 131,140,906.00

Total Pembayaran pada Tagihan ini Rp. 131,140,906.00


Terbilang : Err:511

Mohon Tagihan untuk bulan Mei 2021 dimasukan pada rekening PT. WINSOLUSI KONSULTAN Nomor Rekening :
0416.01.000160.300 BRI Cabang Kelapa Gading 2

Jayapura, 01 Juni 2021


PPK PENGAWASAN Konsultan Supervisi
SATKER P2JN PROVINSI PAPUA (JAYAPURA)
PT. WINSOLUSI KONSULTAN

SAM RANDA, S.T, M.Eng ISNAINI SYAWIK, ST


NIP. 19830422 200801 1 006 Direktur Utama
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Mei 2021 / Invoice 10
TANGGAL : 01 Juni 2021
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

I. BIAYA LANGSUNG PERSONIL


HARGA JUMLAH HARGA PEMBAYARAN TAGIHAN INVOICE NO. 10 PEMBAYARAN
URAIAN SATUAN S/D (Bulan Mei 2021) S/D SISA DANA
NO. JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU ORANG WAKTU/ JUMLAH BULAN INI
(Rp) BULAN (RP) (Rp) (Rp)
a BIAYA TENAGA AHLI
Site Supervision Engineer 1.00 25.00 OB 32,697,000.00 817,425,000.00 275,635,710.00 1.00 1.00 32,697,000.00 308,332,710.00 509,092,290.00
Quality Engineer-1 1.00 24.00 OB 30,880,500.00 741,132,000.00 228,515,700.00 1.00 1.00 30,880,500.00 259,396,200.00 481,735,800.00
Inspection Engineer/Quantity Engineer 1.00 25.00 OB 30,880,500.00 772,012,500.00 260,322,615.00 1.00 1.00 30,880,500.00 291,203,115.00 480,809,385.00
Health Safety Enviroment Engineer 1.00 25.00 OB 25,431,000.00 635,775,000.00 214,383,330.00 1.00 1.00 25,431,000.00 239,814,330.00 395,960,670.00

Sub Total a 2,966,344,500.00 978,857,355.00 119,889,000.00 1,098,746,355.00 1,867,598,145.00


b BIAYA ASISTEN TENAGA AHLI
Inspector -1 1.00 23.00 OB 12,500,000.00 287,500,000.00 80,375,000.00 1.00 1.00 12,500,000.00 92,875,000.00 194,625,000.00
Surveyor Technician -1 1.00 25.00 OB 12,500,000.00 312,500,000.00 105,375,000.00 1.00 1.00 12,500,000.00 117,875,000.00 194,625,000.00
Material Technician -1 1.00 24.00 OB 12,500,000.00 300,000,000.00 92,500,000.00 1.00 1.00 12,500,000.00 105,000,000.00 195,000,000.00
Sub Total b 900,000,000.00 278,250,000.00 37,500,000.00 315,750,000.00 584,250,000.00
c BIAYA STAF PENDUKUNG
Operator Komputer 1.00 25.00 OB 8,000,000.00 200,000,000.00 67,440,000.00 1.00 1.00 8,000,000.00 75,440,000.00 124,560,000.00
Pesuruh/Penjaga Kantor 1.00 25.00 OB 4,000,000.00 100,000,000.00 33,720,000.00 1.00 1.00 4,000,000.00 37,720,000.00 62,280,000.00
Sub Total c 300,000,000.00 101,160,000.00 12,000,000.00 113,160,000.00 186,840,000.00

TOTAL a+b+c 4,166,344,500.00 1,358,267,355.00 - - 169,389,000.00 1,527,656,355.00 2,638,688,145.00


NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Mei 2021 / Invoice 10
TANGGAL : 01 Juni 2021
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

II. BIAYA LANGSUNG NON PERSONIL


HARGA PEMBAYARAN TAGIHAN INVOICE NO. 10 PEMBAYARAN
JUMLAH HARGA
SATUAN S/D (Bulan Mei 2021) S/D SISA DANA
NO. URAIAN JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU JUMLAH BULAN INI
ORANG TRIP
(Rp) (RP) (Rp) (Rp)
a MOBILISASI DAN DEMOBILISASI
- Mobilisasi
Site Supervision Engineer - - Trip - - - - - - - -
Quality Engineer-1 - - Trip - - - - - - - -
Inspection Engineer/Quantity Engineer - - Trip - - - - - - - -
Health Safety Enviroment Engineer - - - - - - - - - -
- Demobilisasi
Site Supervision Engineer - - Trip - - - - - - - -
Quality Engineer-1 - - Trip - - - - - - - -
Inspection Engineer/Quantity Engineer - - Trip - - - - - - - -
Health Safety Enviroment Engineer - - Trip - - - - - - - -
Sub Total a - - - - -
b BIAYA PERJALANAN DINAS
Tiket Perjalanan (PP) Termasuk Ongkos Taxi 6.00 Trip 2,000,000.00 12,000,000.00 - - - - - 12,000,000.00
Biaya Penginapan 24.00 Hari 400,000.00 9,600,000.00 - - - - - 9,600,000.00

Sub Total b 21,600,000.00 - - - 21,600,000.00


HARGA PEMBAYARAN TAGIHAN INVOICE NO. 10 PEMBAYARAN
SATUAN JUMLAH HARGA S/D (Bulan Mei 2021) S/D SISA DANA
NO. URAIAN JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU JUMLAH BULAN INI
VOLUME BULAN
(Rp) (RP) (Rp) (Rp)
c BIAYA KANTOR
Sewa Kantor 1.00 25.00 Bln 5,000,000.00 125,000,000.00 42,150,000.00 1.00 1.00 5,000,000.00 47,150,000.00 77,850,000.00
Sewa Operasional Kantor (Air dan Listrik) 1.00 25.00 Bln 1,500,000.00 37,500,000.00 12,645,000.00 1.00 1.00 1,500,000.00 14,145,000.00 23,355,000.00
Sewa Penunjang Kantor :
- Laptop-1 1.00 25.00 Bln 1,600,000.00 40,000,000.00 13,488,000.00 1.00 1.00 1,600,000.00 15,088,000.00 24,912,000.00
- Laptop-2 1.00 25.00 Bln 1,600,000.00 40,000,000.00 13,488,000.00 1.00 1.00 1,600,000.00 15,088,000.00 24,912,000.00
- Printer A3 1.00 25.00 Bln 700,000.00 17,500,000.00 5,901,000.00 1.00 1.00 700,000.00 6,601,000.00 10,899,000.00
- Printer A4 1.00 25.00 Bln 500,000.00 12,500,000.00 4,215,000.00 1.00 1.00 500,000.00 4,715,000.00 7,785,000.00
Komunikasi (Pulsa Telepon + lnternet) 1.00 25.00 Bln 1,500,000.00 37,500,000.00 12,645,000.00 1.00 1.00 1,500,000.00 14,145,000.00 23,355,000.00
Bahan untuk peralatan kantor 1.00 25.00 Bln 1,000,000.00 25,000,000.00 8,430,000.00 1.00 1.00 1,000,000.00 9,430,000.00 15,570,000.00

Sub Total c 335,000,000.00 112,962,000.00 13,400,000.00 126,362,000.00 208,638,000.00


d BIAYA PELAPORAN
Laporan RMK 5.00 5.00 Eks 150,000.00 750,000.00 750,000.00 - - - 750,000.00 -
Laporan Pendahuluan 5.00 5.00 Eks 150,000.00 750,000.00 750,000.00 - - - 750,000.00 -
Laporan Bulanan 125.00 5.00 Eks 100,000.00 12,500,000.00 4,000,000.00 5.00 1.00 500,000.00 4,500,000.00 8,000,000.00
Laporan Triwulan 40.00 5.00 Eks 250,000.00 10,000,000.00 3,750,000.00 - - - 3,750,000.00 6,250,000.00
Laporan Akhir 5.00 5.00 Eks 250,000.00 1,250,000.00 - - - - - 1,250,000.00
Hard Disk (File Laporan dan Dokumentasi) 1.00 1.00 Buah 1,000,000.00 1,000,000.00 - - - - - 1,000,000.00

Sub Total d 26,250,000.00 9,250,000.00 500,000.00 9,750,000.00 16,500,000.00


e BIAYA AKOMODASI
- Biaya Sewa
Sewa Mobil Double Gardan-1 1.00 25.00 Bln 25,000,000.00 625,000,000.00 210,750,000.00 1.00 1.00 25,000,000.00 235,750,000.00 389,250,000.00
Sewa Motor Lapangan -1 1.00 25.00 Bln 2,500,000.00 62,500,000.00 21,075,000.00 1.00 1.00 2,500,000.00 23,575,000.00 38,925,000.00
Sewa Motor Lapangan -2 1.00 25.00 Bln 2,500,000.00 62,500,000.00 21,075,000.00 1.00 1.00 2,500,000.00 23,575,000.00 38,925,000.00
- Tunjangan Perumahan
Site Supervision Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 8,430,000.00 1.00 1.00 1,000,000.00 9,430,000.00 15,570,000.00
Quality Engineer-1 1.00 24.00 Bln 1,000,000.00 24,000,000.00 7,400,000.00 1.00 1.00 1,000,000.00 8,400,000.00 15,600,000.00
Inspection Engineer/Quantity Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 8,430,000.00 1.00 1.00 1,000,000.00 9,430,000.00 15,570,000.00
Health Safety Enviroment Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 8,430,000.00 1.00 1.00 1,000,000.00 9,430,000.00 15,570,000.00
Inspector -1 1.00 23.00 Bln 750,000.00 17,250,000.00 4,822,500.00 1.00 1.00 750,000.00 5,572,500.00 11,677,500.00
Surveyor Technician -1 1.00 25.00 Bln 750,000.00 18,750,000.00 6,322,500.00 1.00 1.00 750,000.00 7,072,500.00 11,677,500.00
Material Technician -1 1.00 24.00 Bln 750,000.00 18,000,000.00 5,550,000.00 1.00 1.00 750,000.00 6,300,000.00 11,700,000.00

Sub Total e 903,000,000.00 302,285,000.00 36,250,000.00 338,535,000.00 564,465,000.00

Sub Total a+b+c+d+e 1,285,850,000.00 424,497,000.00 50,150,000.00 474,647,000.00 811,203,000.00


LAPORAN BULANAN KEADAAN DANA
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Juni 2021 / Invoice 11
TANGGAL : 01 Juli 2021
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

NO. JLH. PEMBAYARAN TAGIHAN INVOICE JLH. PEMBAYARAN SISA DANA


URAIAN TOTAL DANA
S/D BULAN LALU NO. 11 S/D BULAN INI Rp.

I. BIAYA LANGSUNG PERSONIL 4,166,344,500.00 1,527,656,355.00 169,389,000.00 1,697,045,355.00 2,469,299,145.00


-
II. BIAYA LANGSUNG NON PERSONIL 1,285,850,000.00 474,647,000.00 50,150,000.00 524,797,000.00 761,053,000.00
BIAYA MOBILISASI DAN DEMOBILISASI - - - - -
BIAYA PERJALANAN DINAS 21,600,000.00 - - - 21,600,000.00
BIAYA KANTOR 335,000,000.00 126,362,000.00 13,400,000.00 139,762,000.00 195,238,000.00
BIAYA PELAPORAN 26,250,000.00 9,750,000.00 500,000.00 10,250,000.00 16,000,000.00
BIAYA AKOMODASI 903,000,000.00 338,535,000.00 36,250,000.00 374,785,000.00 528,215,000.00

SUB TOTAL (I+II) 5,452,194,500.00 2,002,303,355.00 219,539,000.00 2,221,842,355.00 3,230,352,145.00


PPN 545,219,450.00 200,230,335.50 21,953,900.00 222,184,235.50 323,035,214.50
SUB TOTAL 5,997,413,950.00 2,202,533,690.50 241,492,900.00 2,444,026,590.50 3,553,387,359.50
NILAI KONTRAK DIBULATKAN 5,997,413,000.00
PENGEMBALIAN UANG MUKA 899,611,950.00 899,611,950.00 - 899,611,950.00 -
TOTAL 5,097,801,050.00 1,302,921,740.50 241,492,900.00 1,544,414,640.50 3,553,387,359.50
DIBULATKAN 1,302,921,740.00 241,492,900.00 1,544,414,640.00 3,553,387,360.00

1,199,482,600.00

Jayapura, 01 Juli 2021

PPK PENGAWASAN Konsultan Supervisi


SATKER P2JN PROVINSI PAPUA (JAYAPURA)
PT. WINSOLUSI KONSULTAN

SAM RANDA, S.T, M.Eng ISNAINI SYAWIK, ST


NIP. 19830422 200801 1 006 Direktur Utama
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Juni 2021 / Invoice 11
TANGGAL : 01 Juli 2021
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

REKAPITULASI INVOICE

NO. URAIAN BIAYA (Rp.)

I. BIAYA LANGSUNG PERSONIL 169,389,000.00

II. BIAYA LANGSUNG NON PERSONIL 50,150,000.00


BIAYA MOBILISASI DAN DEMOBILISASI -
BIAYA PERJALANAN DINAS -
BIAYA KANTOR 13,400,000.00
BIAYA PELAPORAN 500,000.00
BIAYA AKOMODASI 36,250,000.00

SUB TOTAL ( I + II ) 219,539,000.00


PPN 10% 21,953,900.00
SUB TOTAL 241,492,900.00
PENGEMBALIAN UANG MUKA 15% -
TOTAL 241,492,900.00
DIBULATKAN 241,492,900.00

Total Pembayaran pada Tagihan ini Rp. 241,492,900.00


Terbilang : Err:511

Mohon Tagihan untuk bulan Juni 2021 dimasukan pada rekening PT. WINSOLUSI KONSULTAN Nomor Rekening :
0416.01.000160.300 BRI Cabang Kelapa Gading 2

Jayapura, 01 Juli 2021


PPK PENGAWASAN Konsultan Supervisi
SATKER P2JN PROVINSI PAPUA (JAYAPURA)
PT. WINSOLUSI KONSULTAN

SAM RANDA, S.T, M.Eng ISNAINI SYAWIK, ST


NIP. 19830422 200801 1 006 Direktur Utama
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Juni 2021 / Invoice 11
TANGGAL : 01 Juli 2021
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

I. BIAYA LANGSUNG PERSONIL


HARGA JUMLAH HARGA PEMBAYARAN TAGIHAN INVOICE NO. 11 PEMBAYARAN
URAIAN SATUAN S/D (Bulan Juni 2021) S/D SISA DANA
NO. JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU ORANG WAKTU/ JUMLAH BULAN INI
(Rp) BULAN (RP) (Rp) (Rp)
a BIAYA TENAGA AHLI
Site Supervision Engineer 1.00 25.00 OB 32,697,000.00 817,425,000.00 308,332,710.00 1.00 1.00 32,697,000.00 341,029,710.00 476,395,290.00
Quality Engineer-1 1.00 24.00 OB 30,880,500.00 741,132,000.00 259,396,200.00 1.00 1.00 30,880,500.00 290,276,700.00 450,855,300.00
Inspection Engineer/Quantity Engineer 1.00 25.00 OB 30,880,500.00 772,012,500.00 291,203,115.00 1.00 1.00 30,880,500.00 322,083,615.00 449,928,885.00
Health Safety Enviroment Engineer 1.00 25.00 OB 25,431,000.00 635,775,000.00 239,814,330.00 1.00 1.00 25,431,000.00 265,245,330.00 370,529,670.00

Sub Total a 2,966,344,500.00 1,098,746,355.00 119,889,000.00 1,218,635,355.00 1,747,709,145.00


b BIAYA ASISTEN TENAGA AHLI
Inspector -1 1.00 23.00 OB 12,500,000.00 287,500,000.00 92,875,000.00 1.00 1.00 12,500,000.00 105,375,000.00 182,125,000.00
Surveyor Technician -1 1.00 25.00 OB 12,500,000.00 312,500,000.00 117,875,000.00 1.00 1.00 12,500,000.00 130,375,000.00 182,125,000.00
Material Technician -1 1.00 24.00 OB 12,500,000.00 300,000,000.00 105,000,000.00 1.00 1.00 12,500,000.00 117,500,000.00 182,500,000.00
Sub Total b 900,000,000.00 315,750,000.00 37,500,000.00 353,250,000.00 546,750,000.00
c BIAYA STAF PENDUKUNG
Operator Komputer 1.00 25.00 OB 8,000,000.00 200,000,000.00 75,440,000.00 1.00 1.00 8,000,000.00 83,440,000.00 116,560,000.00
Pesuruh/Penjaga Kantor 1.00 25.00 OB 4,000,000.00 100,000,000.00 37,720,000.00 1.00 1.00 4,000,000.00 41,720,000.00 58,280,000.00
Sub Total c 300,000,000.00 113,160,000.00 12,000,000.00 125,160,000.00 174,840,000.00

TOTAL a+b+c 4,166,344,500.00 1,527,656,355.00 - - 169,389,000.00 1,697,045,355.00 2,469,299,145.00


NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Juni 2021 / Invoice 11
TANGGAL : 01 Juli 2021
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

II. BIAYA LANGSUNG NON PERSONIL


HARGA PEMBAYARAN TAGIHAN INVOICE NO. 11 PEMBAYARAN
JUMLAH HARGA
SATUAN S/D (Bulan Juni 2021) S/D SISA DANA
NO. URAIAN JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU JUMLAH BULAN INI
ORANG TRIP
(Rp) (RP) (Rp) (Rp)
a MOBILISASI DAN DEMOBILISASI
- Mobilisasi
Site Supervision Engineer - - Trip - - - - - - - -
Quality Engineer-1 - - Trip - - - - - - - -
Inspection Engineer/Quantity Engineer - - Trip - - - - - - - -
Health Safety Enviroment Engineer - - - - - - - - - -
- Demobilisasi
Site Supervision Engineer - - Trip - - - - - - - -
Quality Engineer-1 - - Trip - - - - - - - -
Inspection Engineer/Quantity Engineer - - Trip - - - - - - - -
Health Safety Enviroment Engineer - - Trip - - - - - - - -
Sub Total a - - - - -
b BIAYA PERJALANAN DINAS
Tiket Perjalanan (PP) Termasuk Ongkos Taxi 6.00 Trip 2,000,000.00 12,000,000.00 - - - - - 12,000,000.00
Biaya Penginapan 24.00 Hari 400,000.00 9,600,000.00 - - - - - 9,600,000.00

Sub Total b 21,600,000.00 - - - 21,600,000.00


HARGA PEMBAYARAN TAGIHAN INVOICE NO. 11 PEMBAYARAN
SATUAN JUMLAH HARGA S/D (Bulan Juni 2021) S/D SISA DANA
NO. URAIAN JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU JUMLAH BULAN INI
VOLUME BULAN
(Rp) (RP) (Rp) (Rp)
c BIAYA KANTOR
Sewa Kantor 1.00 25.00 Bln 5,000,000.00 125,000,000.00 47,150,000.00 1.00 1.00 5,000,000.00 52,150,000.00 72,850,000.00
Sewa Operasional Kantor (Air dan Listrik) 1.00 25.00 Bln 1,500,000.00 37,500,000.00 14,145,000.00 1.00 1.00 1,500,000.00 15,645,000.00 21,855,000.00
Sewa Penunjang Kantor :
- Laptop-1 1.00 25.00 Bln 1,600,000.00 40,000,000.00 15,088,000.00 1.00 1.00 1,600,000.00 16,688,000.00 23,312,000.00
- Laptop-2 1.00 25.00 Bln 1,600,000.00 40,000,000.00 15,088,000.00 1.00 1.00 1,600,000.00 16,688,000.00 23,312,000.00
- Printer A3 1.00 25.00 Bln 700,000.00 17,500,000.00 6,601,000.00 1.00 1.00 700,000.00 7,301,000.00 10,199,000.00
- Printer A4 1.00 25.00 Bln 500,000.00 12,500,000.00 4,715,000.00 1.00 1.00 500,000.00 5,215,000.00 7,285,000.00
Komunikasi (Pulsa Telepon + lnternet) 1.00 25.00 Bln 1,500,000.00 37,500,000.00 14,145,000.00 1.00 1.00 1,500,000.00 15,645,000.00 21,855,000.00
Bahan untuk peralatan kantor 1.00 25.00 Bln 1,000,000.00 25,000,000.00 9,430,000.00 1.00 1.00 1,000,000.00 10,430,000.00 14,570,000.00

Sub Total c 335,000,000.00 126,362,000.00 13,400,000.00 139,762,000.00 195,238,000.00


d BIAYA PELAPORAN
Laporan RMK 5.00 5.00 Eks 150,000.00 750,000.00 750,000.00 - - - 750,000.00 -
Laporan Pendahuluan 5.00 5.00 Eks 150,000.00 750,000.00 750,000.00 - - - 750,000.00 -
Laporan Bulanan 125.00 5.00 Eks 100,000.00 12,500,000.00 4,500,000.00 5.00 1.00 500,000.00 5,000,000.00 7,500,000.00
Laporan Triwulan 40.00 5.00 Eks 250,000.00 10,000,000.00 3,750,000.00 - - - 3,750,000.00 6,250,000.00
Laporan Akhir 5.00 5.00 Eks 250,000.00 1,250,000.00 - - - - - 1,250,000.00
Hard Disk (File Laporan dan Dokumentasi) 1.00 1.00 Buah 1,000,000.00 1,000,000.00 - - - - - 1,000,000.00

Sub Total d 26,250,000.00 9,750,000.00 500,000.00 10,250,000.00 16,000,000.00


e BIAYA AKOMODASI
- Biaya Sewa
Sewa Mobil Double Gardan-1 1.00 25.00 Bln 25,000,000.00 625,000,000.00 235,750,000.00 1.00 1.00 25,000,000.00 260,750,000.00 364,250,000.00
Sewa Motor Lapangan -1 1.00 25.00 Bln 2,500,000.00 62,500,000.00 23,575,000.00 1.00 1.00 2,500,000.00 26,075,000.00 36,425,000.00
Sewa Motor Lapangan -2 1.00 25.00 Bln 2,500,000.00 62,500,000.00 23,575,000.00 1.00 1.00 2,500,000.00 26,075,000.00 36,425,000.00
- Tunjangan Perumahan
Site Supervision Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 9,430,000.00 1.00 1.00 1,000,000.00 10,430,000.00 14,570,000.00
Quality Engineer-1 1.00 24.00 Bln 1,000,000.00 24,000,000.00 8,400,000.00 1.00 1.00 1,000,000.00 9,400,000.00 14,600,000.00
Inspection Engineer/Quantity Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 9,430,000.00 1.00 1.00 1,000,000.00 10,430,000.00 14,570,000.00
Health Safety Enviroment Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 9,430,000.00 1.00 1.00 1,000,000.00 10,430,000.00 14,570,000.00
Inspector -1 1.00 23.00 Bln 750,000.00 17,250,000.00 5,572,500.00 1.00 1.00 750,000.00 6,322,500.00 10,927,500.00
Surveyor Technician -1 1.00 25.00 Bln 750,000.00 18,750,000.00 7,072,500.00 1.00 1.00 750,000.00 7,822,500.00 10,927,500.00
Material Technician -1 1.00 24.00 Bln 750,000.00 18,000,000.00 6,300,000.00 1.00 1.00 750,000.00 7,050,000.00 10,950,000.00

Sub Total e 903,000,000.00 338,535,000.00 36,250,000.00 374,785,000.00 528,215,000.00

Sub Total a+b+c+d+e 1,285,850,000.00 474,647,000.00 50,150,000.00 524,797,000.00 761,053,000.00


LAPORAN BULANAN KEADAAN DANA
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Juli 2021 / Invoice 12
TANGGAL : 01 Agustus 2021
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

NO. JLH. PEMBAYARAN TAGIHAN INVOICE JLH. PEMBAYARAN SISA DANA


URAIAN TOTAL DANA
S/D BULAN LALU NO. 12 S/D BULAN INI Rp.

I. BIAYA LANGSUNG PERSONIL 4,166,344,500.00 1,697,045,355.00 169,389,000.00 1,866,434,355.00 2,299,910,145.00


-
II. BIAYA LANGSUNG NON PERSONIL 1,285,850,000.00 524,797,000.00 51,400,000.00 576,197,000.00 709,653,000.00
BIAYA MOBILISASI DAN DEMOBILISASI - - - - -
BIAYA PERJALANAN DINAS 21,600,000.00 - - - 21,600,000.00
BIAYA KANTOR 335,000,000.00 139,762,000.00 13,400,000.00 153,162,000.00 181,838,000.00
BIAYA PELAPORAN 26,250,000.00 10,250,000.00 1,750,000.00 12,000,000.00 14,250,000.00
BIAYA AKOMODASI 903,000,000.00 374,785,000.00 36,250,000.00 411,035,000.00 491,965,000.00

SUB TOTAL (I+II) 5,452,194,500.00 2,221,842,355.00 220,789,000.00 2,442,631,355.00 3,009,563,145.00


PPN 545,219,450.00 222,184,235.50 22,078,900.00 244,263,135.50 300,956,314.50
SUB TOTAL 5,997,413,950.00 2,444,026,590.50 242,867,900.00 2,686,894,490.50 3,310,519,459.50
NILAI KONTRAK DIBULATKAN 5,997,413,000.00
PENGEMBALIAN UANG MUKA 899,611,950.00 899,611,950.00 - 899,611,950.00 -
TOTAL 5,097,801,050.00 1,544,414,640.50 242,867,900.00 1,787,282,540.50 3,310,519,459.50
DIBULATKAN 1,544,414,640.00 242,867,900.00 1,787,282,540.00 3,310,519,460.00

1,199,482,600.00

Jayapura, 01 Agustus 2021

PPK PENGAWASAN Konsultan Supervisi


SATKER P2JN PROVINSI PAPUA (JAYAPURA)
PT. WINSOLUSI KONSULTAN

SAM RANDA, S.T, M.Eng ISNAINI SYAWIK, ST


NIP. 19830422 200801 1 006 Direktur Utama
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Juli 2021 / Invoice 12
TANGGAL : 01 Agustus 2021
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

REKAPITULASI INVOICE

NO. URAIAN BIAYA (Rp.)

I. BIAYA LANGSUNG PERSONIL 169,389,000.00

II. BIAYA LANGSUNG NON PERSONIL 51,400,000.00


BIAYA MOBILISASI DAN DEMOBILISASI -
BIAYA PERJALANAN DINAS -
BIAYA KANTOR 13,400,000.00
BIAYA PELAPORAN 1,750,000.00
BIAYA AKOMODASI 36,250,000.00

SUB TOTAL ( I + II ) 220,789,000.00


PPN 10% 22,078,900.00
SUB TOTAL 242,867,900.00
PENGEMBALIAN UANG MUKA 15% -
TOTAL 242,867,900.00
DIBULATKAN 242,867,900.00

Total Pembayaran pada Tagihan ini Rp. 242,867,900.00


Terbilang : Err:511

Mohon Tagihan untuk bulan Juli 2021 dimasukan pada rekening PT. WINSOLUSI KONSULTAN Nomor Rekening :
0416.01.000160.300 BRI Cabang Kelapa Gading 2

Jayapura, 01 Agustus 2021


PPK PENGAWASAN Konsultan Supervisi
SATKER P2JN PROVINSI PAPUA (JAYAPURA)
PT. WINSOLUSI KONSULTAN

SAM RANDA, S.T, M.Eng ISNAINI SYAWIK, ST


NIP. 19830422 200801 1 006 Direktur Utama
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Juli 2021 / Invoice 12
TANGGAL : 01 Agustus 2021
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

I. BIAYA LANGSUNG PERSONIL


HARGA JUMLAH HARGA PEMBAYARAN TAGIHAN INVOICE NO. 12 PEMBAYARAN
URAIAN SATUAN S/D (Bulan Juli 2021) S/D SISA DANA
NO. JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU ORANG WAKTU/ JUMLAH BULAN INI
(Rp) BULAN (RP) (Rp) (Rp)
a BIAYA TENAGA AHLI
Site Supervision Engineer 1.00 25.00 OB 32,697,000.00 817,425,000.00 341,029,710.00 1.00 1.00 32,697,000.00 373,726,710.00 443,698,290.00
Quality Engineer-1 1.00 24.00 OB 30,880,500.00 741,132,000.00 290,276,700.00 1.00 1.00 30,880,500.00 321,157,200.00 419,974,800.00
Inspection Engineer/Quantity Engineer 1.00 25.00 OB 30,880,500.00 772,012,500.00 322,083,615.00 1.00 1.00 30,880,500.00 352,964,115.00 419,048,385.00
Health Safety Enviroment Engineer 1.00 25.00 OB 25,431,000.00 635,775,000.00 265,245,330.00 1.00 1.00 25,431,000.00 290,676,330.00 345,098,670.00

Sub Total a 2,966,344,500.00 1,218,635,355.00 119,889,000.00 1,338,524,355.00 1,627,820,145.00


b BIAYA ASISTEN TENAGA AHLI
Inspector -1 1.00 23.00 OB 12,500,000.00 287,500,000.00 105,375,000.00 1.00 1.00 12,500,000.00 117,875,000.00 169,625,000.00
Surveyor Technician -1 1.00 25.00 OB 12,500,000.00 312,500,000.00 130,375,000.00 1.00 1.00 12,500,000.00 142,875,000.00 169,625,000.00
Material Technician -1 1.00 24.00 OB 12,500,000.00 300,000,000.00 117,500,000.00 1.00 1.00 12,500,000.00 130,000,000.00 170,000,000.00
Sub Total b 900,000,000.00 353,250,000.00 37,500,000.00 390,750,000.00 509,250,000.00
c BIAYA STAF PENDUKUNG
Operator Komputer 1.00 25.00 OB 8,000,000.00 200,000,000.00 83,440,000.00 1.00 1.00 8,000,000.00 91,440,000.00 108,560,000.00
Pesuruh/Penjaga Kantor 1.00 25.00 OB 4,000,000.00 100,000,000.00 41,720,000.00 1.00 1.00 4,000,000.00 45,720,000.00 54,280,000.00
Sub Total c 300,000,000.00 125,160,000.00 12,000,000.00 137,160,000.00 162,840,000.00

TOTAL a+b+c 4,166,344,500.00 1,697,045,355.00 - - 169,389,000.00 1,866,434,355.00 2,299,910,145.00


NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Juli 2021 / Invoice 12
TANGGAL : 01 Agustus 2021
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

II. BIAYA LANGSUNG NON PERSONIL


HARGA PEMBAYARAN TAGIHAN INVOICE NO. 12 PEMBAYARAN
JUMLAH HARGA
SATUAN S/D (Bulan Juli 2021) S/D SISA DANA
NO. URAIAN JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU JUMLAH BULAN INI
ORANG TRIP
(Rp) (RP) (Rp) (Rp)
a MOBILISASI DAN DEMOBILISASI
- Mobilisasi
Site Supervision Engineer - - Trip - - - - - - - -
Quality Engineer-1 - - Trip - - - - - - - -
Inspection Engineer/Quantity Engineer - - Trip - - - - - - - -
Health Safety Enviroment Engineer - - - - - - - - - -
- Demobilisasi
Site Supervision Engineer - - Trip - - - - - - - -
Quality Engineer-1 - - Trip - - - - - - - -
Inspection Engineer/Quantity Engineer - - Trip - - - - - - - -
Health Safety Enviroment Engineer - - Trip - - - - - - - -
Sub Total a - - - - -
b BIAYA PERJALANAN DINAS
Tiket Perjalanan (PP) Termasuk Ongkos Taxi 6.00 Trip 2,000,000.00 12,000,000.00 - - - - - 12,000,000.00
Biaya Penginapan 24.00 Hari 400,000.00 9,600,000.00 - - - - - 9,600,000.00

Sub Total b 21,600,000.00 - - - 21,600,000.00


HARGA PEMBAYARAN TAGIHAN INVOICE NO. 12 PEMBAYARAN
SATUAN JUMLAH HARGA S/D (Bulan Juli 2021) S/D SISA DANA
NO. URAIAN JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU JUMLAH BULAN INI
VOLUME BULAN
(Rp) (RP) (Rp) (Rp)
c BIAYA KANTOR
Sewa Kantor 1.00 25.00 Bln 5,000,000.00 125,000,000.00 52,150,000.00 1.00 1.00 5,000,000.00 57,150,000.00 67,850,000.00
Sewa Operasional Kantor (Air dan Listrik) 1.00 25.00 Bln 1,500,000.00 37,500,000.00 15,645,000.00 1.00 1.00 1,500,000.00 17,145,000.00 20,355,000.00
Sewa Penunjang Kantor :
- Laptop-1 1.00 25.00 Bln 1,600,000.00 40,000,000.00 16,688,000.00 1.00 1.00 1,600,000.00 18,288,000.00 21,712,000.00
- Laptop-2 1.00 25.00 Bln 1,600,000.00 40,000,000.00 16,688,000.00 1.00 1.00 1,600,000.00 18,288,000.00 21,712,000.00
- Printer A3 1.00 25.00 Bln 700,000.00 17,500,000.00 7,301,000.00 1.00 1.00 700,000.00 8,001,000.00 9,499,000.00
- Printer A4 1.00 25.00 Bln 500,000.00 12,500,000.00 5,215,000.00 1.00 1.00 500,000.00 5,715,000.00 6,785,000.00
Komunikasi (Pulsa Telepon + lnternet) 1.00 25.00 Bln 1,500,000.00 37,500,000.00 15,645,000.00 1.00 1.00 1,500,000.00 17,145,000.00 20,355,000.00
Bahan untuk peralatan kantor 1.00 25.00 Bln 1,000,000.00 25,000,000.00 10,430,000.00 1.00 1.00 1,000,000.00 11,430,000.00 13,570,000.00

Sub Total c 335,000,000.00 139,762,000.00 13,400,000.00 153,162,000.00 181,838,000.00


d BIAYA PELAPORAN
Laporan RMK 5.00 5.00 Eks 150,000.00 750,000.00 750,000.00 - - - 750,000.00 -
Laporan Pendahuluan 5.00 5.00 Eks 150,000.00 750,000.00 750,000.00 - - - 750,000.00 -
Laporan Bulanan 125.00 5.00 Eks 100,000.00 12,500,000.00 5,000,000.00 5.00 1.00 500,000.00 5,500,000.00 7,000,000.00
Laporan Triwulan 40.00 5.00 Eks 250,000.00 10,000,000.00 3,750,000.00 5.00 1.00 1,250,000.00 5,000,000.00 5,000,000.00
Laporan Akhir 5.00 5.00 Eks 250,000.00 1,250,000.00 - - - - - 1,250,000.00
Hard Disk (File Laporan dan Dokumentasi) 1.00 1.00 Buah 1,000,000.00 1,000,000.00 - - - - - 1,000,000.00

Sub Total d 26,250,000.00 10,250,000.00 1,750,000.00 12,000,000.00 14,250,000.00


e BIAYA AKOMODASI
- Biaya Sewa
Sewa Mobil Double Gardan-1 1.00 25.00 Bln 25,000,000.00 625,000,000.00 260,750,000.00 1.00 1.00 25,000,000.00 285,750,000.00 339,250,000.00
Sewa Motor Lapangan -1 1.00 25.00 Bln 2,500,000.00 62,500,000.00 26,075,000.00 1.00 1.00 2,500,000.00 28,575,000.00 33,925,000.00
Sewa Motor Lapangan -2 1.00 25.00 Bln 2,500,000.00 62,500,000.00 26,075,000.00 1.00 1.00 2,500,000.00 28,575,000.00 33,925,000.00
- Tunjangan Perumahan
Site Supervision Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 10,430,000.00 1.00 1.00 1,000,000.00 11,430,000.00 13,570,000.00
Quality Engineer-1 1.00 24.00 Bln 1,000,000.00 24,000,000.00 9,400,000.00 1.00 1.00 1,000,000.00 10,400,000.00 13,600,000.00
Inspection Engineer/Quantity Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 10,430,000.00 1.00 1.00 1,000,000.00 11,430,000.00 13,570,000.00
Health Safety Enviroment Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 10,430,000.00 1.00 1.00 1,000,000.00 11,430,000.00 13,570,000.00
Inspector -1 1.00 23.00 Bln 750,000.00 17,250,000.00 6,322,500.00 1.00 1.00 750,000.00 7,072,500.00 10,177,500.00
Surveyor Technician -1 1.00 25.00 Bln 750,000.00 18,750,000.00 7,822,500.00 1.00 1.00 750,000.00 8,572,500.00 10,177,500.00
Material Technician -1 1.00 24.00 Bln 750,000.00 18,000,000.00 7,050,000.00 1.00 1.00 750,000.00 7,800,000.00 10,200,000.00

Sub Total e 903,000,000.00 374,785,000.00 36,250,000.00 411,035,000.00 491,965,000.00

Sub Total a+b+c+d+e 1,285,850,000.00 524,797,000.00 51,400,000.00 576,197,000.00 709,653,000.00


LAPORAN BULANAN KEADAAN DANA
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Agustus 2021 / Invoice 13
TANGGAL : 01 September 2021
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

NO. JLH. PEMBAYARAN TAGIHAN INVOICE JLH. PEMBAYARAN SISA DANA


URAIAN TOTAL DANA
S/D BULAN LALU NO. 13 S/D BULAN INI Rp.

I. BIAYA LANGSUNG PERSONIL 4,166,344,500.00 1,866,434,355.00 169,389,000.00 2,035,823,355.00 2,130,521,145.00


-
II. BIAYA LANGSUNG NON PERSONIL 1,285,850,000.00 576,197,000.00 50,150,000.00 626,347,000.00 659,503,000.00
BIAYA MOBILISASI DAN DEMOBILISASI - - - - -
BIAYA PERJALANAN DINAS 21,600,000.00 - - - 21,600,000.00
BIAYA KANTOR 335,000,000.00 153,162,000.00 13,400,000.00 166,562,000.00 168,438,000.00
BIAYA PELAPORAN 26,250,000.00 12,000,000.00 500,000.00 12,500,000.00 13,750,000.00
BIAYA AKOMODASI 903,000,000.00 411,035,000.00 36,250,000.00 447,285,000.00 455,715,000.00

SUB TOTAL (I+II) 5,452,194,500.00 2,442,631,355.00 219,539,000.00 2,662,170,355.00 2,790,024,145.00


PPN 545,219,450.00 244,263,135.50 21,953,900.00 266,217,035.50 279,002,414.50
SUB TOTAL 5,997,413,950.00 2,686,894,490.50 241,492,900.00 2,928,387,390.50 3,069,026,559.50
NILAI KONTRAK DIBULATKAN 5,997,413,000.00
PENGEMBALIAN UANG MUKA 899,611,950.00 899,611,950.00 - 899,611,950.00 -
TOTAL 5,097,801,050.00 1,787,282,540.50 241,492,900.00 2,028,775,440.50 3,069,026,559.50
DIBULATKAN 1,787,282,540.00 241,492,900.00 2,028,775,440.00 3,069,026,560.00

1,199,482,600.00

Jayapura, 01 September 2021

PPK PENGAWASAN Konsultan Supervisi


SATKER P2JN PROVINSI PAPUA (JAYAPURA)
PT. WINSOLUSI KONSULTAN

SAM RANDA, S.T, M.Eng ISNAINI SYAWIK, ST


NIP. 19830422 200801 1 006 Direktur Utama
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Agustus 2021 / Invoice 13
TANGGAL : 01 September 2021
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

REKAPITULASI INVOICE

NO. URAIAN BIAYA (Rp.)

I. BIAYA LANGSUNG PERSONIL 169,389,000.00

II. BIAYA LANGSUNG NON PERSONIL 50,150,000.00


BIAYA MOBILISASI DAN DEMOBILISASI -
BIAYA PERJALANAN DINAS -
BIAYA KANTOR 13,400,000.00
BIAYA PELAPORAN 500,000.00
BIAYA AKOMODASI 36,250,000.00

SUB TOTAL ( I + II ) 219,539,000.00


PPN 10% 21,953,900.00
SUB TOTAL 241,492,900.00
PENGEMBALIAN UANG MUKA 15% -
TOTAL 241,492,900.00
DIBULATKAN 241,492,900.00

Total Pembayaran pada Tagihan ini Rp. 241,492,900.00


Terbilang : Err:511

Mohon Tagihan untuk bulan Agustus 2021 dimasukan pada rekening PT. WINSOLUSI KONSULTAN Nomor Rekening :
0416.01.000160.300 BRI Cabang Kelapa Gading 2

Jayapura, 01 September 2021


PPK PENGAWASAN Konsultan Supervisi
SATKER P2JN PROVINSI PAPUA (JAYAPURA)
PT. WINSOLUSI KONSULTAN

SAM RANDA, S.T, M.Eng ISNAINI SYAWIK, ST


NIP. 19830422 200801 1 006 Direktur Utama
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Agustus 2021 / Invoice 13
TANGGAL : 01 September 2021
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

I. BIAYA LANGSUNG PERSONIL


HARGA JUMLAH HARGA PEMBAYARAN TAGIHAN INVOICE NO. 13 PEMBAYARAN
URAIAN SATUAN S/D (Bulan Agustus 2021) S/D SISA DANA
NO. JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU ORANG WAKTU/ JUMLAH BULAN INI
(Rp) BULAN (RP) (Rp) (Rp)
a BIAYA TENAGA AHLI
Site Supervision Engineer 1.00 25.00 OB 32,697,000.00 817,425,000.00 373,726,710.00 1.00 1.00 32,697,000.00 406,423,710.00 411,001,290.00
Quality Engineer-1 1.00 24.00 OB 30,880,500.00 741,132,000.00 321,157,200.00 1.00 1.00 30,880,500.00 352,037,700.00 389,094,300.00
Inspection Engineer/Quantity Engineer 1.00 25.00 OB 30,880,500.00 772,012,500.00 352,964,115.00 1.00 1.00 30,880,500.00 383,844,615.00 388,167,885.00
Health Safety Enviroment Engineer 1.00 25.00 OB 25,431,000.00 635,775,000.00 290,676,330.00 1.00 1.00 25,431,000.00 316,107,330.00 319,667,670.00

Sub Total a 2,966,344,500.00 1,338,524,355.00 119,889,000.00 1,458,413,355.00 1,507,931,145.00


b BIAYA ASISTEN TENAGA AHLI
Inspector -1 1.00 23.00 OB 12,500,000.00 287,500,000.00 117,875,000.00 1.00 1.00 12,500,000.00 130,375,000.00 157,125,000.00
Surveyor Technician -1 1.00 25.00 OB 12,500,000.00 312,500,000.00 142,875,000.00 1.00 1.00 12,500,000.00 155,375,000.00 157,125,000.00
Material Technician -1 1.00 24.00 OB 12,500,000.00 300,000,000.00 130,000,000.00 1.00 1.00 12,500,000.00 142,500,000.00 157,500,000.00
Sub Total b 900,000,000.00 390,750,000.00 37,500,000.00 428,250,000.00 471,750,000.00
c BIAYA STAF PENDUKUNG
Operator Komputer 1.00 25.00 OB 8,000,000.00 200,000,000.00 91,440,000.00 1.00 1.00 8,000,000.00 99,440,000.00 100,560,000.00
Pesuruh/Penjaga Kantor 1.00 25.00 OB 4,000,000.00 100,000,000.00 45,720,000.00 1.00 1.00 4,000,000.00 49,720,000.00 50,280,000.00
Sub Total c 300,000,000.00 137,160,000.00 12,000,000.00 149,160,000.00 150,840,000.00

TOTAL a+b+c 4,166,344,500.00 1,866,434,355.00 - - 169,389,000.00 2,035,823,355.00 2,130,521,145.00


NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Agustus 2021 / Invoice 13
TANGGAL : 01 September 2021
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

II. BIAYA LANGSUNG NON PERSONIL


HARGA PEMBAYARAN TAGIHAN INVOICE NO. 13 PEMBAYARAN
JUMLAH HARGA
SATUAN S/D (Bulan Agustus 2021) S/D SISA DANA
NO. URAIAN JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU JUMLAH BULAN INI
ORANG TRIP
(Rp) (RP) (Rp) (Rp)
a MOBILISASI DAN DEMOBILISASI
- Mobilisasi
Site Supervision Engineer - - Trip - - - - - - - -
Quality Engineer-1 - - Trip - - - - - - - -
Inspection Engineer/Quantity Engineer - - Trip - - - - - - - -
Health Safety Enviroment Engineer - - - - - - - - - -
- Demobilisasi
Site Supervision Engineer - - Trip - - - - - - - -
Quality Engineer-1 - - Trip - - - - - - - -
Inspection Engineer/Quantity Engineer - - Trip - - - - - - - -
Health Safety Enviroment Engineer - - Trip - - - - - - - -
Sub Total a - - - - -
b BIAYA PERJALANAN DINAS
Tiket Perjalanan (PP) Termasuk Ongkos Taxi 6.00 Trip 2,000,000.00 12,000,000.00 - - - - - 12,000,000.00
Biaya Penginapan 24.00 Hari 400,000.00 9,600,000.00 - - - - - 9,600,000.00

Sub Total b 21,600,000.00 - - - 21,600,000.00


HARGA PEMBAYARAN TAGIHAN INVOICE NO. 13 PEMBAYARAN
SATUAN JUMLAH HARGA S/D (Bulan Agustus 2021) S/D SISA DANA
NO. URAIAN JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU JUMLAH BULAN INI
VOLUME BULAN
(Rp) (RP) (Rp) (Rp)
c BIAYA KANTOR
Sewa Kantor 1.00 25.00 Bln 5,000,000.00 125,000,000.00 57,150,000.00 1.00 1.00 5,000,000.00 62,150,000.00 62,850,000.00
Sewa Operasional Kantor (Air dan Listrik) 1.00 25.00 Bln 1,500,000.00 37,500,000.00 17,145,000.00 1.00 1.00 1,500,000.00 18,645,000.00 18,855,000.00
Sewa Penunjang Kantor :
- Laptop-1 1.00 25.00 Bln 1,600,000.00 40,000,000.00 18,288,000.00 1.00 1.00 1,600,000.00 19,888,000.00 20,112,000.00
- Laptop-2 1.00 25.00 Bln 1,600,000.00 40,000,000.00 18,288,000.00 1.00 1.00 1,600,000.00 19,888,000.00 20,112,000.00
- Printer A3 1.00 25.00 Bln 700,000.00 17,500,000.00 8,001,000.00 1.00 1.00 700,000.00 8,701,000.00 8,799,000.00
- Printer A4 1.00 25.00 Bln 500,000.00 12,500,000.00 5,715,000.00 1.00 1.00 500,000.00 6,215,000.00 6,285,000.00
Komunikasi (Pulsa Telepon + lnternet) 1.00 25.00 Bln 1,500,000.00 37,500,000.00 17,145,000.00 1.00 1.00 1,500,000.00 18,645,000.00 18,855,000.00
Bahan untuk peralatan kantor 1.00 25.00 Bln 1,000,000.00 25,000,000.00 11,430,000.00 1.00 1.00 1,000,000.00 12,430,000.00 12,570,000.00

Sub Total c 335,000,000.00 153,162,000.00 13,400,000.00 166,562,000.00 168,438,000.00


d BIAYA PELAPORAN
Laporan RMK 5.00 5.00 Eks 150,000.00 750,000.00 750,000.00 - - - 750,000.00 -
Laporan Pendahuluan 5.00 5.00 Eks 150,000.00 750,000.00 750,000.00 - - - 750,000.00 -
Laporan Bulanan 125.00 5.00 Eks 100,000.00 12,500,000.00 5,500,000.00 5.00 1.00 500,000.00 6,000,000.00 6,500,000.00
Laporan Triwulan 40.00 5.00 Eks 250,000.00 10,000,000.00 5,000,000.00 - - - 5,000,000.00 5,000,000.00
Laporan Akhir 5.00 5.00 Eks 250,000.00 1,250,000.00 - - - - - 1,250,000.00
Hard Disk (File Laporan dan Dokumentasi) 1.00 1.00 Buah 1,000,000.00 1,000,000.00 - - - - - 1,000,000.00

Sub Total d 26,250,000.00 12,000,000.00 500,000.00 12,500,000.00 13,750,000.00


e BIAYA AKOMODASI
- Biaya Sewa
Sewa Mobil Double Gardan-1 1.00 25.00 Bln 25,000,000.00 625,000,000.00 285,750,000.00 1.00 1.00 25,000,000.00 310,750,000.00 314,250,000.00
Sewa Motor Lapangan -1 1.00 25.00 Bln 2,500,000.00 62,500,000.00 28,575,000.00 1.00 1.00 2,500,000.00 31,075,000.00 31,425,000.00
Sewa Motor Lapangan -2 1.00 25.00 Bln 2,500,000.00 62,500,000.00 28,575,000.00 1.00 1.00 2,500,000.00 31,075,000.00 31,425,000.00
- Tunjangan Perumahan
Site Supervision Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 11,430,000.00 1.00 1.00 1,000,000.00 12,430,000.00 12,570,000.00
Quality Engineer-1 1.00 24.00 Bln 1,000,000.00 24,000,000.00 10,400,000.00 1.00 1.00 1,000,000.00 11,400,000.00 12,600,000.00
Inspection Engineer/Quantity Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 11,430,000.00 1.00 1.00 1,000,000.00 12,430,000.00 12,570,000.00
Health Safety Enviroment Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 11,430,000.00 1.00 1.00 1,000,000.00 12,430,000.00 12,570,000.00
Inspector -1 1.00 23.00 Bln 750,000.00 17,250,000.00 7,072,500.00 1.00 1.00 750,000.00 7,822,500.00 9,427,500.00
Surveyor Technician -1 1.00 25.00 Bln 750,000.00 18,750,000.00 8,572,500.00 1.00 1.00 750,000.00 9,322,500.00 9,427,500.00
Material Technician -1 1.00 24.00 Bln 750,000.00 18,000,000.00 7,800,000.00 1.00 1.00 750,000.00 8,550,000.00 9,450,000.00

Sub Total e 903,000,000.00 411,035,000.00 36,250,000.00 447,285,000.00 455,715,000.00

Sub Total a+b+c+d+e 1,285,850,000.00 576,197,000.00 50,150,000.00 626,347,000.00 659,503,000.00


LAPORAN BULANAN KEADAAN DANA
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : September 2021 / Invoice 14
TANGGAL : 01 Oktober 2021
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

NO. JLH. PEMBAYARAN TAGIHAN INVOICE JLH. PEMBAYARAN SISA DANA


URAIAN TOTAL DANA
S/D BULAN LALU NO. 14 S/D BULAN INI Rp.

I. BIAYA LANGSUNG PERSONIL 4,166,344,500.00 2,035,823,355.00 169,389,000.00 2,205,212,355.00 1,961,132,145.00


-
II. BIAYA LANGSUNG NON PERSONIL 1,285,850,000.00 626,347,000.00 50,150,000.00 676,497,000.00 609,353,000.00
BIAYA MOBILISASI DAN DEMOBILISASI - - - - -
BIAYA PERJALANAN DINAS 21,600,000.00 - - - 21,600,000.00
BIAYA KANTOR 335,000,000.00 166,562,000.00 13,400,000.00 179,962,000.00 155,038,000.00
BIAYA PELAPORAN 26,250,000.00 12,500,000.00 500,000.00 13,000,000.00 13,250,000.00
BIAYA AKOMODASI 903,000,000.00 447,285,000.00 36,250,000.00 483,535,000.00 419,465,000.00

SUB TOTAL (I+II) 5,452,194,500.00 2,662,170,355.00 219,539,000.00 2,881,709,355.00 2,570,485,145.00


PPN 545,219,450.00 266,217,035.50 21,953,900.00 288,170,935.50 257,048,514.50
SUB TOTAL 5,997,413,950.00 2,928,387,390.50 241,492,900.00 3,169,880,290.50 2,827,533,659.50
NILAI KONTRAK DIBULATKAN 5,997,413,000.00
PENGEMBALIAN UANG MUKA 899,611,950.00 899,611,950.00 - 899,611,950.00 -
TOTAL 5,097,801,050.00 2,028,775,440.50 241,492,900.00 2,270,268,340.50 2,827,533,659.50
DIBULATKAN 2,028,775,440.00 241,492,900.00 2,270,268,340.00 2,827,533,660.00

1,199,482,600.00

Jayapura, 01 Oktober 2021

PPK PENGAWASAN Konsultan Supervisi


SATKER P2JN PROVINSI PAPUA (JAYAPURA)
PT. WINSOLUSI KONSULTAN

SAM RANDA, S.T, M.Eng ISNAINI SYAWIK, ST


NIP. 19830422 200801 1 006 Direktur Utama
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : September 2021 / Invoice 14
TANGGAL : 01 Oktober 2021
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

REKAPITULASI INVOICE

NO. URAIAN BIAYA (Rp.)

I. BIAYA LANGSUNG PERSONIL 169,389,000.00

II. BIAYA LANGSUNG NON PERSONIL 50,150,000.00


BIAYA MOBILISASI DAN DEMOBILISASI -
BIAYA PERJALANAN DINAS -
BIAYA KANTOR 13,400,000.00
BIAYA PELAPORAN 500,000.00
BIAYA AKOMODASI 36,250,000.00

SUB TOTAL ( I + II ) 219,539,000.00


PPN 10% 21,953,900.00
SUB TOTAL 241,492,900.00
PENGEMBALIAN UANG MUKA 15% -
TOTAL 241,492,900.00
DIBULATKAN 241,492,900.00

Total Pembayaran pada Tagihan ini Rp. 241,492,900.00


Terbilang : Err:511

Mohon Tagihan untuk bulan September 2021 dimasukan pada rekening PT. WINSOLUSI KONSULTAN Nomor Rekening :
0416.01.000160.300 BRI Cabang Kelapa Gading 2

Jayapura, 01 Oktober 2021


PPK PENGAWASAN Konsultan Supervisi
SATKER P2JN PROVINSI PAPUA (JAYAPURA)
PT. WINSOLUSI KONSULTAN

SAM RANDA, S.T, M.Eng ISNAINI SYAWIK, ST


NIP. 19830422 200801 1 006 Direktur Utama
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : September 2021 / Invoice 14
TANGGAL : 01 Oktober 2021
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

I. BIAYA LANGSUNG PERSONIL


HARGA JUMLAH HARGA PEMBAYARAN TAGIHAN INVOICE NO. 14 PEMBAYARAN
URAIAN SATUAN S/D (Bulan September 2021) S/D SISA DANA
NO. JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU ORANG WAKTU/ JUMLAH BULAN INI
(Rp) BULAN (RP) (Rp) (Rp)
a BIAYA TENAGA AHLI
Site Supervision Engineer 1.00 25.00 OB 32,697,000.00 817,425,000.00 406,423,710.00 1.00 1.00 32,697,000.00 439,120,710.00 378,304,290.00
Quality Engineer-1 1.00 24.00 OB 30,880,500.00 741,132,000.00 352,037,700.00 1.00 1.00 30,880,500.00 382,918,200.00 358,213,800.00
Inspection Engineer/Quantity Engineer 1.00 25.00 OB 30,880,500.00 772,012,500.00 383,844,615.00 1.00 1.00 30,880,500.00 414,725,115.00 357,287,385.00
Health Safety Enviroment Engineer 1.00 25.00 OB 25,431,000.00 635,775,000.00 316,107,330.00 1.00 1.00 25,431,000.00 341,538,330.00 294,236,670.00

Sub Total a 2,966,344,500.00 1,458,413,355.00 119,889,000.00 1,578,302,355.00 1,388,042,145.00


b BIAYA ASISTEN TENAGA AHLI
Inspector -1 1.00 23.00 OB 12,500,000.00 287,500,000.00 130,375,000.00 1.00 1.00 12,500,000.00 142,875,000.00 144,625,000.00
Surveyor Technician -1 1.00 25.00 OB 12,500,000.00 312,500,000.00 155,375,000.00 1.00 1.00 12,500,000.00 167,875,000.00 144,625,000.00
Material Technician -1 1.00 24.00 OB 12,500,000.00 300,000,000.00 142,500,000.00 1.00 1.00 12,500,000.00 155,000,000.00 145,000,000.00
Sub Total b 900,000,000.00 428,250,000.00 37,500,000.00 465,750,000.00 434,250,000.00
c BIAYA STAF PENDUKUNG
Operator Komputer 1.00 25.00 OB 8,000,000.00 200,000,000.00 99,440,000.00 1.00 1.00 8,000,000.00 107,440,000.00 92,560,000.00
Pesuruh/Penjaga Kantor 1.00 25.00 OB 4,000,000.00 100,000,000.00 49,720,000.00 1.00 1.00 4,000,000.00 53,720,000.00 46,280,000.00
Sub Total c 300,000,000.00 149,160,000.00 12,000,000.00 161,160,000.00 138,840,000.00

TOTAL a+b+c 4,166,344,500.00 2,035,823,355.00 - - 169,389,000.00 2,205,212,355.00 1,961,132,145.00


NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : September 2021 / Invoice 14
TANGGAL : 01 Oktober 2021
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

II. BIAYA LANGSUNG NON PERSONIL


HARGA PEMBAYARAN TAGIHAN INVOICE NO. 14 PEMBAYARAN
JUMLAH HARGA
SATUAN S/D (Bulan September 2021) S/D SISA DANA
NO. URAIAN JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU JUMLAH BULAN INI
ORANG TRIP
(Rp) (RP) (Rp) (Rp)
a MOBILISASI DAN DEMOBILISASI
- Mobilisasi
Site Supervision Engineer - - Trip - - - - - - - -
Quality Engineer-1 - - Trip - - - - - - - -
Inspection Engineer/Quantity Engineer - - Trip - - - - - - - -
Health Safety Enviroment Engineer - - - - - - - - - -
- Demobilisasi
Site Supervision Engineer - - Trip - - - - - - - -
Quality Engineer-1 - - Trip - - - - - - - -
Inspection Engineer/Quantity Engineer - - Trip - - - - - - - -
Health Safety Enviroment Engineer - - Trip - - - - - - - -
Sub Total a - - - - -
b BIAYA PERJALANAN DINAS
Tiket Perjalanan (PP) Termasuk Ongkos Taxi 6.00 Trip 2,000,000.00 12,000,000.00 - - - - - 12,000,000.00
Biaya Penginapan 24.00 Hari 400,000.00 9,600,000.00 - - - - - 9,600,000.00

Sub Total b 21,600,000.00 - - - 21,600,000.00


HARGA PEMBAYARAN TAGIHAN INVOICE NO. 14 PEMBAYARAN
SATUAN JUMLAH HARGA S/D (Bulan September 2021) S/D SISA DANA
NO. URAIAN JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU JUMLAH BULAN INI
VOLUME BULAN
(Rp) (RP) (Rp) (Rp)
c BIAYA KANTOR
Sewa Kantor 1.00 25.00 Bln 5,000,000.00 125,000,000.00 62,150,000.00 1.00 1.00 5,000,000.00 67,150,000.00 57,850,000.00
Sewa Operasional Kantor (Air dan Listrik) 1.00 25.00 Bln 1,500,000.00 37,500,000.00 18,645,000.00 1.00 1.00 1,500,000.00 20,145,000.00 17,355,000.00
Sewa Penunjang Kantor :
- Laptop-1 1.00 25.00 Bln 1,600,000.00 40,000,000.00 19,888,000.00 1.00 1.00 1,600,000.00 21,488,000.00 18,512,000.00
- Laptop-2 1.00 25.00 Bln 1,600,000.00 40,000,000.00 19,888,000.00 1.00 1.00 1,600,000.00 21,488,000.00 18,512,000.00
- Printer A3 1.00 25.00 Bln 700,000.00 17,500,000.00 8,701,000.00 1.00 1.00 700,000.00 9,401,000.00 8,099,000.00
- Printer A4 1.00 25.00 Bln 500,000.00 12,500,000.00 6,215,000.00 1.00 1.00 500,000.00 6,715,000.00 5,785,000.00
Komunikasi (Pulsa Telepon + lnternet) 1.00 25.00 Bln 1,500,000.00 37,500,000.00 18,645,000.00 1.00 1.00 1,500,000.00 20,145,000.00 17,355,000.00
Bahan untuk peralatan kantor 1.00 25.00 Bln 1,000,000.00 25,000,000.00 12,430,000.00 1.00 1.00 1,000,000.00 13,430,000.00 11,570,000.00

Sub Total c 335,000,000.00 166,562,000.00 13,400,000.00 179,962,000.00 155,038,000.00


d BIAYA PELAPORAN
Laporan RMK 5.00 5.00 Eks 150,000.00 750,000.00 750,000.00 - - - 750,000.00 -
Laporan Pendahuluan 5.00 5.00 Eks 150,000.00 750,000.00 750,000.00 - - - 750,000.00 -
Laporan Bulanan 125.00 5.00 Eks 100,000.00 12,500,000.00 6,000,000.00 5.00 1.00 500,000.00 6,500,000.00 6,000,000.00
Laporan Triwulan 40.00 5.00 Eks 250,000.00 10,000,000.00 5,000,000.00 - - - 5,000,000.00 5,000,000.00
Laporan Akhir 5.00 5.00 Eks 250,000.00 1,250,000.00 - - - - - 1,250,000.00
Hard Disk (File Laporan dan Dokumentasi) 1.00 1.00 Buah 1,000,000.00 1,000,000.00 - - - - - 1,000,000.00

Sub Total d 26,250,000.00 12,500,000.00 500,000.00 13,000,000.00 13,250,000.00


e BIAYA AKOMODASI
- Biaya Sewa
Sewa Mobil Double Gardan-1 1.00 25.00 Bln 25,000,000.00 625,000,000.00 310,750,000.00 1.00 1.00 25,000,000.00 335,750,000.00 289,250,000.00
Sewa Motor Lapangan -1 1.00 25.00 Bln 2,500,000.00 62,500,000.00 31,075,000.00 1.00 1.00 2,500,000.00 33,575,000.00 28,925,000.00
Sewa Motor Lapangan -2 1.00 25.00 Bln 2,500,000.00 62,500,000.00 31,075,000.00 1.00 1.00 2,500,000.00 33,575,000.00 28,925,000.00
- Tunjangan Perumahan
Site Supervision Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 12,430,000.00 1.00 1.00 1,000,000.00 13,430,000.00 11,570,000.00
Quality Engineer-1 1.00 24.00 Bln 1,000,000.00 24,000,000.00 11,400,000.00 1.00 1.00 1,000,000.00 12,400,000.00 11,600,000.00
Inspection Engineer/Quantity Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 12,430,000.00 1.00 1.00 1,000,000.00 13,430,000.00 11,570,000.00
Health Safety Enviroment Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 12,430,000.00 1.00 1.00 1,000,000.00 13,430,000.00 11,570,000.00
Inspector -1 1.00 23.00 Bln 750,000.00 17,250,000.00 7,822,500.00 1.00 1.00 750,000.00 8,572,500.00 8,677,500.00
Surveyor Technician -1 1.00 25.00 Bln 750,000.00 18,750,000.00 9,322,500.00 1.00 1.00 750,000.00 10,072,500.00 8,677,500.00
Material Technician -1 1.00 24.00 Bln 750,000.00 18,000,000.00 8,550,000.00 1.00 1.00 750,000.00 9,300,000.00 8,700,000.00

Sub Total e 903,000,000.00 447,285,000.00 36,250,000.00 483,535,000.00 419,465,000.00

Sub Total a+b+c+d+e 1,285,850,000.00 626,347,000.00 50,150,000.00 676,497,000.00 609,353,000.00


LAPORAN BULANAN KEADAAN DANA
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Oktober 2021 / Invoice 15
TANGGAL : 01 November 2021
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

NO. JLH. PEMBAYARAN TAGIHAN INVOICE JLH. PEMBAYARAN SISA DANA


URAIAN TOTAL DANA
S/D BULAN LALU NO. 15 S/D BULAN INI Rp.

I. BIAYA LANGSUNG PERSONIL 4,166,344,500.00 2,205,212,355.00 169,389,000.00 2,374,601,355.00 1,791,743,145.00


-
II. BIAYA LANGSUNG NON PERSONIL 1,285,850,000.00 676,497,000.00 51,400,000.00 727,897,000.00 557,953,000.00
BIAYA MOBILISASI DAN DEMOBILISASI - - - - -
BIAYA PERJALANAN DINAS 21,600,000.00 - - - 21,600,000.00
BIAYA KANTOR 335,000,000.00 179,962,000.00 13,400,000.00 193,362,000.00 141,638,000.00
BIAYA PELAPORAN 26,250,000.00 13,000,000.00 1,750,000.00 14,750,000.00 11,500,000.00
BIAYA AKOMODASI 903,000,000.00 483,535,000.00 36,250,000.00 519,785,000.00 383,215,000.00

SUB TOTAL (I+II) 5,452,194,500.00 2,881,709,355.00 220,789,000.00 3,102,498,355.00 2,349,696,145.00


PPN 545,219,450.00 288,170,935.50 22,078,900.00 310,249,835.50 234,969,614.50
SUB TOTAL 5,997,413,950.00 3,169,880,290.50 242,867,900.00 3,412,748,190.50 2,584,665,759.50
NILAI KONTRAK DIBULATKAN 5,997,413,000.00
PENGEMBALIAN UANG MUKA 899,611,950.00 899,611,950.00 - 899,611,950.00 -
TOTAL 5,097,801,050.00 2,270,268,340.50 242,867,900.00 2,513,136,240.50 2,584,665,759.50
DIBULATKAN 2,270,268,340.00 242,867,900.00 2,513,136,240.00 2,584,665,760.00

1,199,482,600.00

Jayapura, 01 November 2021

PPK PENGAWASAN Konsultan Supervisi


SATKER P2JN PROVINSI PAPUA (JAYAPURA)
PT. WINSOLUSI KONSULTAN

SAM RANDA, S.T, M.Eng ISNAINI SYAWIK, ST


NIP. 19830422 200801 1 006 Direktur Utama
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Oktober 2021 / Invoice 15
TANGGAL : 01 November 2021
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

REKAPITULASI INVOICE

NO. URAIAN BIAYA (Rp.)

I. BIAYA LANGSUNG PERSONIL 169,389,000.00

II. BIAYA LANGSUNG NON PERSONIL 51,400,000.00


BIAYA MOBILISASI DAN DEMOBILISASI -
BIAYA PERJALANAN DINAS -
BIAYA KANTOR 13,400,000.00
BIAYA PELAPORAN 1,750,000.00
BIAYA AKOMODASI 36,250,000.00

SUB TOTAL ( I + II ) 220,789,000.00


PPN 10% 22,078,900.00
SUB TOTAL 242,867,900.00
PENGEMBALIAN UANG MUKA 15% -
TOTAL 242,867,900.00
DIBULATKAN 242,867,900.00

Total Pembayaran pada Tagihan ini Rp. 242,867,900.00


Terbilang : Err:511

Mohon Tagihan untuk bulan Oktober 2021 dimasukan pada rekening PT. WINSOLUSI KONSULTAN Nomor Rekening :
0416.01.000160.300 BRI Cabang Kelapa Gading 2

Jayapura, 01 November 2021


PPK PENGAWASAN Konsultan Supervisi
SATKER P2JN PROVINSI PAPUA (JAYAPURA)
PT. WINSOLUSI KONSULTAN

SAM RANDA, S.T, M.Eng ISNAINI SYAWIK, ST


NIP. 19830422 200801 1 006 Direktur Utama
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Oktober 2021 / Invoice 15
TANGGAL : 01 November 2021
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

I. BIAYA LANGSUNG PERSONIL


HARGA JUMLAH HARGA PEMBAYARAN TAGIHAN INVOICE NO. 15 PEMBAYARAN
URAIAN SATUAN S/D (Bulan Oktober 2021) S/D SISA DANA
NO. JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU ORANG WAKTU/ JUMLAH BULAN INI
(Rp) BULAN (RP) (Rp) (Rp)
a BIAYA TENAGA AHLI
Site Supervision Engineer 1.00 25.00 OB 32,697,000.00 817,425,000.00 439,120,710.00 1.00 1.00 32,697,000.00 471,817,710.00 345,607,290.00
Quality Engineer-1 1.00 24.00 OB 30,880,500.00 741,132,000.00 382,918,200.00 1.00 1.00 30,880,500.00 413,798,700.00 327,333,300.00
Inspection Engineer/Quantity Engineer 1.00 25.00 OB 30,880,500.00 772,012,500.00 414,725,115.00 1.00 1.00 30,880,500.00 445,605,615.00 326,406,885.00
Health Safety Enviroment Engineer 1.00 25.00 OB 25,431,000.00 635,775,000.00 341,538,330.00 1.00 1.00 25,431,000.00 366,969,330.00 268,805,670.00

Sub Total a 2,966,344,500.00 1,578,302,355.00 119,889,000.00 1,698,191,355.00 1,268,153,145.00


b BIAYA ASISTEN TENAGA AHLI
Inspector -1 1.00 23.00 OB 12,500,000.00 287,500,000.00 142,875,000.00 1.00 1.00 12,500,000.00 155,375,000.00 132,125,000.00
Surveyor Technician -1 1.00 25.00 OB 12,500,000.00 312,500,000.00 167,875,000.00 1.00 1.00 12,500,000.00 180,375,000.00 132,125,000.00
Material Technician -1 1.00 24.00 OB 12,500,000.00 300,000,000.00 155,000,000.00 1.00 1.00 12,500,000.00 167,500,000.00 132,500,000.00
Sub Total b 900,000,000.00 465,750,000.00 37,500,000.00 503,250,000.00 396,750,000.00
c BIAYA STAF PENDUKUNG
Operator Komputer 1.00 25.00 OB 8,000,000.00 200,000,000.00 107,440,000.00 1.00 1.00 8,000,000.00 115,440,000.00 84,560,000.00
Pesuruh/Penjaga Kantor 1.00 25.00 OB 4,000,000.00 100,000,000.00 53,720,000.00 1.00 1.00 4,000,000.00 57,720,000.00 42,280,000.00
Sub Total c 300,000,000.00 161,160,000.00 12,000,000.00 173,160,000.00 126,840,000.00

TOTAL a+b+c 4,166,344,500.00 2,205,212,355.00 - - 169,389,000.00 2,374,601,355.00 1,791,743,145.00


NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Oktober 2021 / Invoice 15
TANGGAL : 01 November 2021
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

II. BIAYA LANGSUNG NON PERSONIL


HARGA PEMBAYARAN TAGIHAN INVOICE NO. 15 PEMBAYARAN
JUMLAH HARGA
SATUAN S/D (Bulan Oktober 2021) S/D SISA DANA
NO. URAIAN JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU JUMLAH BULAN INI
ORANG TRIP
(Rp) (RP) (Rp) (Rp)
a MOBILISASI DAN DEMOBILISASI
- Mobilisasi
Site Supervision Engineer - - Trip - - - - - - - -
Quality Engineer-1 - - Trip - - - - - - - -
Inspection Engineer/Quantity Engineer - - Trip - - - - - - - -
Health Safety Enviroment Engineer - - - - - - - - - -
- Demobilisasi
Site Supervision Engineer - - Trip - - - - - - - -
Quality Engineer-1 - - Trip - - - - - - - -
Inspection Engineer/Quantity Engineer - - Trip - - - - - - - -
Health Safety Enviroment Engineer - - Trip - - - - - - - -
Sub Total a - - - - -
b BIAYA PERJALANAN DINAS
Tiket Perjalanan (PP) Termasuk Ongkos Taxi 6.00 Trip 2,000,000.00 12,000,000.00 - - - - - 12,000,000.00
Biaya Penginapan 24.00 Hari 400,000.00 9,600,000.00 - - - - - 9,600,000.00

Sub Total b 21,600,000.00 - - - 21,600,000.00


HARGA PEMBAYARAN TAGIHAN INVOICE NO. 15 PEMBAYARAN
SATUAN JUMLAH HARGA S/D (Bulan Oktober 2021) S/D SISA DANA
NO. URAIAN JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU JUMLAH BULAN INI
VOLUME BULAN
(Rp) (RP) (Rp) (Rp)
c BIAYA KANTOR
Sewa Kantor 1.00 25.00 Bln 5,000,000.00 125,000,000.00 67,150,000.00 1.00 1.00 5,000,000.00 72,150,000.00 52,850,000.00
Sewa Operasional Kantor (Air dan Listrik) 1.00 25.00 Bln 1,500,000.00 37,500,000.00 20,145,000.00 1.00 1.00 1,500,000.00 21,645,000.00 15,855,000.00
Sewa Penunjang Kantor :
- Laptop-1 1.00 25.00 Bln 1,600,000.00 40,000,000.00 21,488,000.00 1.00 1.00 1,600,000.00 23,088,000.00 16,912,000.00
- Laptop-2 1.00 25.00 Bln 1,600,000.00 40,000,000.00 21,488,000.00 1.00 1.00 1,600,000.00 23,088,000.00 16,912,000.00
- Printer A3 1.00 25.00 Bln 700,000.00 17,500,000.00 9,401,000.00 1.00 1.00 700,000.00 10,101,000.00 7,399,000.00
- Printer A4 1.00 25.00 Bln 500,000.00 12,500,000.00 6,715,000.00 1.00 1.00 500,000.00 7,215,000.00 5,285,000.00
Komunikasi (Pulsa Telepon + lnternet) 1.00 25.00 Bln 1,500,000.00 37,500,000.00 20,145,000.00 1.00 1.00 1,500,000.00 21,645,000.00 15,855,000.00
Bahan untuk peralatan kantor 1.00 25.00 Bln 1,000,000.00 25,000,000.00 13,430,000.00 1.00 1.00 1,000,000.00 14,430,000.00 10,570,000.00

Sub Total c 335,000,000.00 179,962,000.00 13,400,000.00 193,362,000.00 141,638,000.00


d BIAYA PELAPORAN
Laporan RMK 5.00 5.00 Eks 150,000.00 750,000.00 750,000.00 - - - 750,000.00 -
Laporan Pendahuluan 5.00 5.00 Eks 150,000.00 750,000.00 750,000.00 - - - 750,000.00 -
Laporan Bulanan 125.00 5.00 Eks 100,000.00 12,500,000.00 6,500,000.00 5.00 1.00 500,000.00 7,000,000.00 5,500,000.00
Laporan Triwulan 40.00 5.00 Eks 250,000.00 10,000,000.00 5,000,000.00 5.00 1.00 1,250,000.00 6,250,000.00 3,750,000.00
Laporan Akhir 5.00 5.00 Eks 250,000.00 1,250,000.00 - - - - - 1,250,000.00
Hard Disk (File Laporan dan Dokumentasi) 1.00 1.00 Buah 1,000,000.00 1,000,000.00 - - - - - 1,000,000.00

Sub Total d 26,250,000.00 13,000,000.00 1,750,000.00 14,750,000.00 11,500,000.00


e BIAYA AKOMODASI
- Biaya Sewa
Sewa Mobil Double Gardan-1 1.00 25.00 Bln 25,000,000.00 625,000,000.00 335,750,000.00 1.00 1.00 25,000,000.00 360,750,000.00 264,250,000.00
Sewa Motor Lapangan -1 1.00 25.00 Bln 2,500,000.00 62,500,000.00 33,575,000.00 1.00 1.00 2,500,000.00 36,075,000.00 26,425,000.00
Sewa Motor Lapangan -2 1.00 25.00 Bln 2,500,000.00 62,500,000.00 33,575,000.00 1.00 1.00 2,500,000.00 36,075,000.00 26,425,000.00
- Tunjangan Perumahan
Site Supervision Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 13,430,000.00 1.00 1.00 1,000,000.00 14,430,000.00 10,570,000.00
Quality Engineer-1 1.00 24.00 Bln 1,000,000.00 24,000,000.00 12,400,000.00 1.00 1.00 1,000,000.00 13,400,000.00 10,600,000.00
Inspection Engineer/Quantity Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 13,430,000.00 1.00 1.00 1,000,000.00 14,430,000.00 10,570,000.00
Health Safety Enviroment Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 13,430,000.00 1.00 1.00 1,000,000.00 14,430,000.00 10,570,000.00
Inspector -1 1.00 23.00 Bln 750,000.00 17,250,000.00 8,572,500.00 1.00 1.00 750,000.00 9,322,500.00 7,927,500.00
Surveyor Technician -1 1.00 25.00 Bln 750,000.00 18,750,000.00 10,072,500.00 1.00 1.00 750,000.00 10,822,500.00 7,927,500.00
Material Technician -1 1.00 24.00 Bln 750,000.00 18,000,000.00 9,300,000.00 1.00 1.00 750,000.00 10,050,000.00 7,950,000.00

Sub Total e 903,000,000.00 483,535,000.00 36,250,000.00 519,785,000.00 383,215,000.00

Sub Total a+b+c+d+e 1,285,850,000.00 676,497,000.00 51,400,000.00 727,897,000.00 557,953,000.00


LAPORAN BULANAN KEADAAN DANA
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : November 2021 / Invoice 16
TANGGAL : 01 Desember 2021
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

NO. JLH. PEMBAYARAN TAGIHAN INVOICE JLH. PEMBAYARAN SISA DANA


URAIAN TOTAL DANA
S/D BULAN LALU NO. 16 S/D BULAN INI Rp.

I. BIAYA LANGSUNG PERSONIL 4,166,344,500.00 2,374,601,355.00 169,389,000.00 2,543,990,355.00 1,622,354,145.00


-
II. BIAYA LANGSUNG NON PERSONIL 1,285,850,000.00 727,897,000.00 50,150,000.00 778,047,000.00 507,803,000.00
BIAYA MOBILISASI DAN DEMOBILISASI - - - - -
BIAYA PERJALANAN DINAS 21,600,000.00 - - - 21,600,000.00
BIAYA KANTOR 335,000,000.00 193,362,000.00 13,400,000.00 206,762,000.00 128,238,000.00
BIAYA PELAPORAN 26,250,000.00 14,750,000.00 500,000.00 15,250,000.00 11,000,000.00
BIAYA AKOMODASI 903,000,000.00 519,785,000.00 36,250,000.00 556,035,000.00 346,965,000.00

SUB TOTAL (I+II) 5,452,194,500.00 3,102,498,355.00 219,539,000.00 3,322,037,355.00 2,130,157,145.00


PPN 545,219,450.00 310,249,835.50 21,953,900.00 332,203,735.50 213,015,714.50
SUB TOTAL 5,997,413,950.00 3,412,748,190.50 241,492,900.00 3,654,241,090.50 2,343,172,859.50
NILAI KONTRAK DIBULATKAN 5,997,413,000.00
PENGEMBALIAN UANG MUKA 899,611,950.00 899,611,950.00 - 899,611,950.00 -
TOTAL 5,097,801,050.00 2,513,136,240.50 241,492,900.00 2,754,629,140.50 2,343,172,859.50
DIBULATKAN 2,513,136,240.00 241,492,900.00 2,754,629,140.00 2,343,172,860.00

1,199,482,600.00

Jayapura, 01 Desember 2021

PPK PENGAWASAN Konsultan Supervisi


SATKER P2JN PROVINSI PAPUA (JAYAPURA)
PT. WINSOLUSI KONSULTAN

SAM RANDA, S.T, M.Eng ISNAINI SYAWIK, ST


NIP. 19830422 200801 1 006 Direktur Utama
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : November 2021 / Invoice 16
TANGGAL : 01 Desember 2021
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

REKAPITULASI INVOICE

NO. URAIAN BIAYA (Rp.)

I. BIAYA LANGSUNG PERSONIL 169,389,000.00

II. BIAYA LANGSUNG NON PERSONIL 50,150,000.00


BIAYA MOBILISASI DAN DEMOBILISASI -
BIAYA PERJALANAN DINAS -
BIAYA KANTOR 13,400,000.00
BIAYA PELAPORAN 500,000.00
BIAYA AKOMODASI 36,250,000.00

SUB TOTAL ( I + II ) 219,539,000.00


PPN 10% 21,953,900.00
SUB TOTAL 241,492,900.00
PENGEMBALIAN UANG MUKA 15% -
TOTAL 241,492,900.00
DIBULATKAN 241,492,900.00

Total Pembayaran pada Tagihan ini Rp. 241,492,900.00


Terbilang : Err:511

Mohon Tagihan untuk bulan November 2021 dimasukan pada rekening PT. WINSOLUSI KONSULTAN Nomor Rekening :
0416.01.000160.300 BRI Cabang Kelapa Gading 2

Jayapura, 01 Desember 2021


PPK PENGAWASAN Konsultan Supervisi
SATKER P2JN PROVINSI PAPUA (JAYAPURA)
PT. WINSOLUSI KONSULTAN

SAM RANDA, S.T, M.Eng ISNAINI SYAWIK, ST


NIP. 19830422 200801 1 006 Direktur Utama
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : November 2021 / Invoice 16
TANGGAL : 01 Desember 2021
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

I. BIAYA LANGSUNG PERSONIL


HARGA JUMLAH HARGA PEMBAYARAN TAGIHAN INVOICE NO. 16 PEMBAYARAN
URAIAN SATUAN S/D (Bulan November 2021) S/D SISA DANA
NO. JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU ORANG WAKTU/ JUMLAH BULAN INI
(Rp) BULAN (RP) (Rp) (Rp)
a BIAYA TENAGA AHLI
Site Supervision Engineer 1.00 25.00 OB 32,697,000.00 817,425,000.00 471,817,710.00 1.00 1.00 32,697,000.00 504,514,710.00 312,910,290.00
Quality Engineer-1 1.00 24.00 OB 30,880,500.00 741,132,000.00 413,798,700.00 1.00 1.00 30,880,500.00 444,679,200.00 296,452,800.00
Inspection Engineer/Quantity Engineer 1.00 25.00 OB 30,880,500.00 772,012,500.00 445,605,615.00 1.00 1.00 30,880,500.00 476,486,115.00 295,526,385.00
Health Safety Enviroment Engineer 1.00 25.00 OB 25,431,000.00 635,775,000.00 366,969,330.00 1.00 1.00 25,431,000.00 392,400,330.00 243,374,670.00

Sub Total a 2,966,344,500.00 1,698,191,355.00 119,889,000.00 1,818,080,355.00 1,148,264,145.00


b BIAYA ASISTEN TENAGA AHLI
Inspector -1 1.00 23.00 OB 12,500,000.00 287,500,000.00 155,375,000.00 1.00 1.00 12,500,000.00 167,875,000.00 119,625,000.00
Surveyor Technician -1 1.00 25.00 OB 12,500,000.00 312,500,000.00 180,375,000.00 1.00 1.00 12,500,000.00 192,875,000.00 119,625,000.00
Material Technician -1 1.00 24.00 OB 12,500,000.00 300,000,000.00 167,500,000.00 1.00 1.00 12,500,000.00 180,000,000.00 120,000,000.00
Sub Total b 900,000,000.00 503,250,000.00 37,500,000.00 540,750,000.00 359,250,000.00
c BIAYA STAF PENDUKUNG
Operator Komputer 1.00 25.00 OB 8,000,000.00 200,000,000.00 115,440,000.00 1.00 1.00 8,000,000.00 123,440,000.00 76,560,000.00
Pesuruh/Penjaga Kantor 1.00 25.00 OB 4,000,000.00 100,000,000.00 57,720,000.00 1.00 1.00 4,000,000.00 61,720,000.00 38,280,000.00
Sub Total c 300,000,000.00 173,160,000.00 12,000,000.00 185,160,000.00 114,840,000.00

TOTAL a+b+c 4,166,344,500.00 2,374,601,355.00 - - 169,389,000.00 2,543,990,355.00 1,622,354,145.00


NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : November 2021 / Invoice 16
TANGGAL : 01 Desember 2021
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

II. BIAYA LANGSUNG NON PERSONIL


HARGA PEMBAYARAN TAGIHAN INVOICE NO. 16 PEMBAYARAN
JUMLAH HARGA
SATUAN S/D (Bulan November 2021) S/D SISA DANA
NO. URAIAN JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU JUMLAH BULAN INI
ORANG TRIP
(Rp) (RP) (Rp) (Rp)
a MOBILISASI DAN DEMOBILISASI
- Mobilisasi
Site Supervision Engineer - - Trip - - - - - - - -
Quality Engineer-1 - - Trip - - - - - - - -
Inspection Engineer/Quantity Engineer - - Trip - - - - - - - -
Health Safety Enviroment Engineer - - - - - - - - - -
- Demobilisasi
Site Supervision Engineer - - Trip - - - - - - - -
Quality Engineer-1 - - Trip - - - - - - - -
Inspection Engineer/Quantity Engineer - - Trip - - - - - - - -
Health Safety Enviroment Engineer - - Trip - - - - - - - -
Sub Total a - - - - -
b BIAYA PERJALANAN DINAS
Tiket Perjalanan (PP) Termasuk Ongkos Taxi 6.00 Trip 2,000,000.00 12,000,000.00 - - - - - 12,000,000.00
Biaya Penginapan 24.00 Hari 400,000.00 9,600,000.00 - - - - - 9,600,000.00

Sub Total b 21,600,000.00 - - - 21,600,000.00


HARGA PEMBAYARAN TAGIHAN INVOICE NO. 16 PEMBAYARAN
SATUAN JUMLAH HARGA S/D (Bulan November 2021) S/D SISA DANA
NO. URAIAN JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU JUMLAH BULAN INI
VOLUME BULAN
(Rp) (RP) (Rp) (Rp)
c BIAYA KANTOR
Sewa Kantor 1.00 25.00 Bln 5,000,000.00 125,000,000.00 72,150,000.00 1.00 1.00 5,000,000.00 77,150,000.00 47,850,000.00
Sewa Operasional Kantor (Air dan Listrik) 1.00 25.00 Bln 1,500,000.00 37,500,000.00 21,645,000.00 1.00 1.00 1,500,000.00 23,145,000.00 14,355,000.00
Sewa Penunjang Kantor :
- Laptop-1 1.00 25.00 Bln 1,600,000.00 40,000,000.00 23,088,000.00 1.00 1.00 1,600,000.00 24,688,000.00 15,312,000.00
- Laptop-2 1.00 25.00 Bln 1,600,000.00 40,000,000.00 23,088,000.00 1.00 1.00 1,600,000.00 24,688,000.00 15,312,000.00
- Printer A3 1.00 25.00 Bln 700,000.00 17,500,000.00 10,101,000.00 1.00 1.00 700,000.00 10,801,000.00 6,699,000.00
- Printer A4 1.00 25.00 Bln 500,000.00 12,500,000.00 7,215,000.00 1.00 1.00 500,000.00 7,715,000.00 4,785,000.00
Komunikasi (Pulsa Telepon + lnternet) 1.00 25.00 Bln 1,500,000.00 37,500,000.00 21,645,000.00 1.00 1.00 1,500,000.00 23,145,000.00 14,355,000.00
Bahan untuk peralatan kantor 1.00 25.00 Bln 1,000,000.00 25,000,000.00 14,430,000.00 1.00 1.00 1,000,000.00 15,430,000.00 9,570,000.00

Sub Total c 335,000,000.00 193,362,000.00 13,400,000.00 206,762,000.00 128,238,000.00


d BIAYA PELAPORAN
Laporan RMK 5.00 5.00 Eks 150,000.00 750,000.00 750,000.00 - - - 750,000.00 -
Laporan Pendahuluan 5.00 5.00 Eks 150,000.00 750,000.00 750,000.00 - - - 750,000.00 -
Laporan Bulanan 125.00 5.00 Eks 100,000.00 12,500,000.00 7,000,000.00 5.00 1.00 500,000.00 7,500,000.00 5,000,000.00
Laporan Triwulan 40.00 5.00 Eks 250,000.00 10,000,000.00 6,250,000.00 - - - 6,250,000.00 3,750,000.00
Laporan Akhir 5.00 5.00 Eks 250,000.00 1,250,000.00 - - - - - 1,250,000.00
Hard Disk (File Laporan dan Dokumentasi) 1.00 1.00 Buah 1,000,000.00 1,000,000.00 - - - - - 1,000,000.00

Sub Total d 26,250,000.00 14,750,000.00 500,000.00 15,250,000.00 11,000,000.00


e BIAYA AKOMODASI
- Biaya Sewa
Sewa Mobil Double Gardan-1 1.00 25.00 Bln 25,000,000.00 625,000,000.00 360,750,000.00 1.00 1.00 25,000,000.00 385,750,000.00 239,250,000.00
Sewa Motor Lapangan -1 1.00 25.00 Bln 2,500,000.00 62,500,000.00 36,075,000.00 1.00 1.00 2,500,000.00 38,575,000.00 23,925,000.00
Sewa Motor Lapangan -2 1.00 25.00 Bln 2,500,000.00 62,500,000.00 36,075,000.00 1.00 1.00 2,500,000.00 38,575,000.00 23,925,000.00
- Tunjangan Perumahan
Site Supervision Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 14,430,000.00 1.00 1.00 1,000,000.00 15,430,000.00 9,570,000.00
Quality Engineer-1 1.00 24.00 Bln 1,000,000.00 24,000,000.00 13,400,000.00 1.00 1.00 1,000,000.00 14,400,000.00 9,600,000.00
Inspection Engineer/Quantity Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 14,430,000.00 1.00 1.00 1,000,000.00 15,430,000.00 9,570,000.00
Health Safety Enviroment Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 14,430,000.00 1.00 1.00 1,000,000.00 15,430,000.00 9,570,000.00
Inspector -1 1.00 23.00 Bln 750,000.00 17,250,000.00 9,322,500.00 1.00 1.00 750,000.00 10,072,500.00 7,177,500.00
Surveyor Technician -1 1.00 25.00 Bln 750,000.00 18,750,000.00 10,822,500.00 1.00 1.00 750,000.00 11,572,500.00 7,177,500.00
Material Technician -1 1.00 24.00 Bln 750,000.00 18,000,000.00 10,050,000.00 1.00 1.00 750,000.00 10,800,000.00 7,200,000.00

Sub Total e 903,000,000.00 519,785,000.00 36,250,000.00 556,035,000.00 346,965,000.00

Sub Total a+b+c+d+e 1,285,850,000.00 727,897,000.00 50,150,000.00 778,047,000.00 507,803,000.00


LAPORAN BULANAN KEADAAN DANA
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Desember 2021 / Invoice 17
TANGGAL : 21 Desember 2021
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

NO. JLH. PEMBAYARAN TAGIHAN INVOICE JLH. PEMBAYARAN SISA DANA


URAIAN TOTAL DANA
S/D BULAN LALU NO. 17 S/D BULAN INI Rp.

I. BIAYA LANGSUNG PERSONIL 4,166,344,500.00 2,543,990,355.00 113,490,630.00 2,657,480,985.00 1,508,863,515.00


-
II. BIAYA LANGSUNG NON PERSONIL 1,285,850,000.00 778,047,000.00 33,765,500.00 811,812,500.00 474,037,500.00
BIAYA MOBILISASI DAN DEMOBILISASI - - - - -
BIAYA PERJALANAN DINAS 21,600,000.00 - - - 21,600,000.00
BIAYA KANTOR 335,000,000.00 206,762,000.00 8,978,000.00 215,740,000.00 119,260,000.00
BIAYA PELAPORAN 26,250,000.00 15,250,000.00 500,000.00 15,750,000.00 10,500,000.00
BIAYA AKOMODASI 903,000,000.00 556,035,000.00 24,287,500.00 580,322,500.00 322,677,500.00

SUB TOTAL (I+II) 5,452,194,500.00 3,322,037,355.00 147,256,130.00 3,469,293,485.00 1,982,901,015.00


PPN 545,219,450.00 332,203,735.50 14,725,613.00 346,929,348.50 198,290,101.50
SUB TOTAL 5,997,413,950.00 3,654,241,090.50 161,981,743.00 3,816,222,833.50 2,181,191,116.50
NILAI KONTRAK DIBULATKAN 5,997,413,000.00
PENGEMBALIAN UANG MUKA 899,611,950.00 899,611,950.00 - 899,611,950.00 -
TOTAL 5,097,801,050.00 2,754,629,140.50 161,981,743.00 2,916,610,883.50 2,181,191,116.50
DIBULATKAN 2,754,629,140.00 161,981,743.00 2,916,610,883.00 2,181,191,117.00

1,199,482,600.00

Jayapura, 21 Desember 2021

PPK PENGAWASAN Konsultan Supervisi


SATKER P2JN PROVINSI PAPUA (JAYAPURA)
PT. WINSOLUSI KONSULTAN

SAM RANDA, S.T, M.Eng ISNAINI SYAWIK, ST


NIP. 19830422 200801 1 006 Direktur Utama
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Desember 2021 / Invoice 17
TANGGAL : 21 Desember 2021
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

REKAPITULASI INVOICE

NO. URAIAN BIAYA (Rp.)

I. BIAYA LANGSUNG PERSONIL 113,490,630.00

II. BIAYA LANGSUNG NON PERSONIL 33,765,500.00


BIAYA MOBILISASI DAN DEMOBILISASI -
BIAYA PERJALANAN DINAS -
BIAYA KANTOR 8,978,000.00
BIAYA PELAPORAN 500,000.00
BIAYA AKOMODASI 24,287,500.00

SUB TOTAL ( I + II ) 147,256,130.00


PPN 10% 14,725,613.00
SUB TOTAL 161,981,743.00
PENGEMBALIAN UANG MUKA 15% -
TOTAL 161,981,743.00
DIBULATKAN 161,981,743.00

Total Pembayaran pada Tagihan ini Rp. 161,981,743.00


Terbilang : Err:511

Mohon Tagihan untuk bulan Desember 2021 dimasukan pada rekening PT. WINSOLUSI KONSULTAN Nomor Rekening :
0416.01.000160.300 BRI Cabang Kelapa Gading 2

Jayapura, 21 Desember 2021


PPK PENGAWASAN Konsultan Supervisi
SATKER P2JN PROVINSI PAPUA (JAYAPURA)
PT. WINSOLUSI KONSULTAN

SAM RANDA, S.T, M.Eng ISNAINI SYAWIK, ST


NIP. 19830422 200801 1 006 Direktur Utama
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Desember 2021 / Invoice 17
TANGGAL : 21 Desember 2021
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

I. BIAYA LANGSUNG PERSONIL


HARGA JUMLAH HARGA PEMBAYARAN TAGIHAN INVOICE NO. 17 PEMBAYARAN
URAIAN SATUAN S/D (Bulan Desember 2021) S/D SISA DANA
NO. JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU ORANG WAKTU/ JUMLAH BULAN INI
(Rp) BULAN (RP) (Rp) (Rp)
a BIAYA TENAGA AHLI
Site Supervision Engineer 1.00 25.00 OB 32,697,000.00 817,425,000.00 504,514,710.00 1.00 0.67 21,906,990.00 526,421,700.00 291,003,300.00
Quality Engineer-1 1.00 24.00 OB 30,880,500.00 741,132,000.00 444,679,200.00 1.00 0.67 20,689,935.00 465,369,135.00 275,762,865.00
Inspection Engineer/Quantity Engineer 1.00 25.00 OB 30,880,500.00 772,012,500.00 476,486,115.00 1.00 0.67 20,689,935.00 497,176,050.00 274,836,450.00
Health Safety Enviroment Engineer 1.00 25.00 OB 25,431,000.00 635,775,000.00 392,400,330.00 1.00 0.67 17,038,770.00 409,439,100.00 226,335,900.00

Sub Total a 2,966,344,500.00 1,818,080,355.00 80,325,630.00 1,898,405,985.00 1,067,938,515.00


b BIAYA ASISTEN TENAGA AHLI
Inspector -1 1.00 23.00 OB 12,500,000.00 287,500,000.00 167,875,000.00 1.00 0.67 8,375,000.00 176,250,000.00 111,250,000.00
Surveyor Technician -1 1.00 25.00 OB 12,500,000.00 312,500,000.00 192,875,000.00 1.00 0.67 8,375,000.00 201,250,000.00 111,250,000.00
Material Technician -1 1.00 24.00 OB 12,500,000.00 300,000,000.00 180,000,000.00 1.00 0.67 8,375,000.00 188,375,000.00 111,625,000.00
Sub Total b 900,000,000.00 540,750,000.00 25,125,000.00 565,875,000.00 334,125,000.00
c BIAYA STAF PENDUKUNG
Operator Komputer 1.00 25.00 OB 8,000,000.00 200,000,000.00 123,440,000.00 1.00 0.67 5,360,000.00 128,800,000.00 71,200,000.00
Pesuruh/Penjaga Kantor 1.00 25.00 OB 4,000,000.00 100,000,000.00 61,720,000.00 1.00 0.67 2,680,000.00 64,400,000.00 35,600,000.00
Sub Total c 300,000,000.00 185,160,000.00 8,040,000.00 193,200,000.00 106,800,000.00

TOTAL a+b+c 4,166,344,500.00 2,543,990,355.00 - - 113,490,630.00 2,657,480,985.00 1,508,863,515.00


NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Desember 2021 / Invoice 17
TANGGAL : 21 Desember 2021
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

II. BIAYA LANGSUNG NON PERSONIL


HARGA PEMBAYARAN TAGIHAN INVOICE NO. 17 PEMBAYARAN
JUMLAH HARGA
SATUAN S/D (Bulan Desember 2021) S/D SISA DANA
NO. URAIAN JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU JUMLAH BULAN INI
ORANG TRIP
(Rp) (RP) (Rp) (Rp)
a MOBILISASI DAN DEMOBILISASI
- Mobilisasi
Site Supervision Engineer - - Trip - - - - - - - -
Quality Engineer-1 - - Trip - - - - - - - -
Inspection Engineer/Quantity Engineer - - Trip - - - - - - - -
Health Safety Enviroment Engineer - - - - - - - - - -
- Demobilisasi
Site Supervision Engineer - - Trip - - - - - - - -
Quality Engineer-1 - - Trip - - - - - - - -
Inspection Engineer/Quantity Engineer - - Trip - - - - - - - -
Health Safety Enviroment Engineer - - Trip - - - - - - - -
Sub Total a - - - - -
b BIAYA PERJALANAN DINAS
Tiket Perjalanan (PP) Termasuk Ongkos Taxi 6.00 Trip 2,000,000.00 12,000,000.00 - - - - - 12,000,000.00
Biaya Penginapan 24.00 Hari 400,000.00 9,600,000.00 - - - - - 9,600,000.00

Sub Total b 21,600,000.00 - - - 21,600,000.00


HARGA PEMBAYARAN TAGIHAN INVOICE NO. 17 PEMBAYARAN
SATUAN JUMLAH HARGA S/D (Bulan Desember 2021) S/D SISA DANA
NO. URAIAN JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU JUMLAH BULAN INI
VOLUME BULAN
(Rp) (RP) (Rp) (Rp)
c BIAYA KANTOR
Sewa Kantor 1.00 25.00 Bln 5,000,000.00 125,000,000.00 77,150,000.00 1.00 0.67 3,350,000.00 80,500,000.00 44,500,000.00
Sewa Operasional Kantor (Air dan Listrik) 1.00 25.00 Bln 1,500,000.00 37,500,000.00 23,145,000.00 1.00 0.67 1,005,000.00 24,150,000.00 13,350,000.00
Sewa Penunjang Kantor :
- Laptop-1 1.00 25.00 Bln 1,600,000.00 40,000,000.00 24,688,000.00 1.00 0.67 1,072,000.00 25,760,000.00 14,240,000.00
- Laptop-2 1.00 25.00 Bln 1,600,000.00 40,000,000.00 24,688,000.00 1.00 0.67 1,072,000.00 25,760,000.00 14,240,000.00
- Printer A3 1.00 25.00 Bln 700,000.00 17,500,000.00 10,801,000.00 1.00 0.67 469,000.00 11,270,000.00 6,230,000.00
- Printer A4 1.00 25.00 Bln 500,000.00 12,500,000.00 7,715,000.00 1.00 0.67 335,000.00 8,050,000.00 4,450,000.00
Komunikasi (Pulsa Telepon + lnternet) 1.00 25.00 Bln 1,500,000.00 37,500,000.00 23,145,000.00 1.00 0.67 1,005,000.00 24,150,000.00 13,350,000.00
Bahan untuk peralatan kantor 1.00 25.00 Bln 1,000,000.00 25,000,000.00 15,430,000.00 1.00 0.67 670,000.00 16,100,000.00 8,900,000.00

Sub Total c 335,000,000.00 206,762,000.00 8,978,000.00 215,740,000.00 119,260,000.00


d BIAYA PELAPORAN
Laporan RMK 5.00 5.00 Eks 150,000.00 750,000.00 750,000.00 - - - 750,000.00 -
Laporan Pendahuluan 5.00 5.00 Eks 150,000.00 750,000.00 750,000.00 - - - 750,000.00 -
Laporan Bulanan 125.00 5.00 Eks 100,000.00 12,500,000.00 7,500,000.00 5.00 1.00 500,000.00 8,000,000.00 4,500,000.00
Laporan Triwulan 40.00 5.00 Eks 250,000.00 10,000,000.00 6,250,000.00 - - - 6,250,000.00 3,750,000.00
Laporan Akhir 5.00 5.00 Eks 250,000.00 1,250,000.00 - - - - - 1,250,000.00
Hard Disk (File Laporan dan Dokumentasi) 1.00 1.00 Buah 1,000,000.00 1,000,000.00 - - - - - 1,000,000.00

Sub Total d 26,250,000.00 15,250,000.00 500,000.00 15,750,000.00 10,500,000.00


e BIAYA AKOMODASI
- Biaya Sewa
Sewa Mobil Double Gardan-1 1.00 25.00 Bln 25,000,000.00 625,000,000.00 385,750,000.00 1.00 0.67 16,750,000.00 402,500,000.00 222,500,000.00
Sewa Motor Lapangan -1 1.00 25.00 Bln 2,500,000.00 62,500,000.00 38,575,000.00 1.00 0.67 1,675,000.00 40,250,000.00 22,250,000.00
Sewa Motor Lapangan -2 1.00 25.00 Bln 2,500,000.00 62,500,000.00 38,575,000.00 1.00 0.67 1,675,000.00 40,250,000.00 22,250,000.00
- Tunjangan Perumahan
Site Supervision Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 15,430,000.00 1.00 0.67 670,000.00 16,100,000.00 8,900,000.00
Quality Engineer-1 1.00 24.00 Bln 1,000,000.00 24,000,000.00 14,400,000.00 1.00 0.67 670,000.00 15,070,000.00 8,930,000.00
Inspection Engineer/Quantity Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 15,430,000.00 1.00 0.67 670,000.00 16,100,000.00 8,900,000.00
Health Safety Enviroment Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 15,430,000.00 1.00 0.67 670,000.00 16,100,000.00 8,900,000.00
Inspector -1 1.00 23.00 Bln 750,000.00 17,250,000.00 10,072,500.00 1.00 0.67 502,500.00 10,575,000.00 6,675,000.00
Surveyor Technician -1 1.00 25.00 Bln 750,000.00 18,750,000.00 11,572,500.00 1.00 0.67 502,500.00 12,075,000.00 6,675,000.00
Material Technician -1 1.00 24.00 Bln 750,000.00 18,000,000.00 10,800,000.00 1.00 0.67 502,500.00 11,302,500.00 6,697,500.00

Sub Total e 903,000,000.00 556,035,000.00 24,287,500.00 580,322,500.00 322,677,500.00

Sub Total a+b+c+d+e 1,285,850,000.00 778,047,000.00 33,765,500.00 811,812,500.00 474,037,500.00


LAPORAN BULANAN KEADAAN DANA
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Januari 2022 / Invoice 18
TANGGAL : 01 Februari 2022
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

NO. JLH. PEMBAYARAN TAGIHAN INVOICE JLH. PEMBAYARAN SISA DANA


URAIAN TOTAL DANA
S/D BULAN LALU NO. 18 S/D BULAN INI Rp.

I. BIAYA LANGSUNG PERSONIL 4,166,344,500.00 2,657,480,985.00 169,389,000.00 2,826,869,985.00 1,339,474,515.00


-
II. BIAYA LANGSUNG NON PERSONIL 1,285,850,000.00 811,812,500.00 51,400,000.00 863,212,500.00 422,637,500.00
BIAYA MOBILISASI DAN DEMOBILISASI - - - - -
BIAYA PERJALANAN DINAS 21,600,000.00 - - - 21,600,000.00
BIAYA KANTOR 335,000,000.00 215,740,000.00 13,400,000.00 229,140,000.00 105,860,000.00
BIAYA PELAPORAN 26,250,000.00 15,750,000.00 1,750,000.00 17,500,000.00 8,750,000.00
BIAYA AKOMODASI 903,000,000.00 580,322,500.00 36,250,000.00 616,572,500.00 286,427,500.00

SUB TOTAL (I+II) 5,452,194,500.00 3,469,293,485.00 220,789,000.00 3,690,082,485.00 1,762,112,015.00


PPN 545,219,450.00 346,929,348.50 22,078,900.00 369,008,248.50 176,211,201.50
SUB TOTAL 5,997,413,950.00 3,816,222,833.50 242,867,900.00 4,059,090,733.50 1,938,323,216.50
NILAI KONTRAK DIBULATKAN 5,997,413,000.00
PENGEMBALIAN UANG MUKA 899,611,950.00 899,611,950.00 - 899,611,950.00 -
TOTAL 5,097,801,050.00 2,916,610,883.50 242,867,900.00 3,159,478,783.50 1,938,323,216.50
DIBULATKAN 2,916,610,883.00 242,867,900.00 3,159,478,783.00 1,938,323,217.00

1,199,482,600.00

Jayapura, 01 Februari 2022

PPK PENGAWASAN Konsultan Supervisi


SATKER P2JN PROVINSI PAPUA (JAYAPURA)
PT. WINSOLUSI KONSULTAN

SAM RANDA, S.T, M.Eng ISNAINI SYAWIK, ST


NIP. 19830422 200801 1 006 Direktur Utama
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Januari 2022 / Invoice 18
TANGGAL : 01 Februari 2022
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

REKAPITULASI INVOICE

NO. URAIAN BIAYA (Rp.)

I. BIAYA LANGSUNG PERSONIL 169,389,000.00

II. BIAYA LANGSUNG NON PERSONIL 51,400,000.00


BIAYA MOBILISASI DAN DEMOBILISASI -
BIAYA PERJALANAN DINAS -
BIAYA KANTOR 13,400,000.00
BIAYA PELAPORAN 1,750,000.00
BIAYA AKOMODASI 36,250,000.00

SUB TOTAL ( I + II ) 220,789,000.00


PPN 10% 22,078,900.00
SUB TOTAL 242,867,900.00
PENGEMBALIAN UANG MUKA 15% -
TOTAL 242,867,900.00
DIBULATKAN 242,867,900.00

Total Pembayaran pada Tagihan ini Rp. 242,867,900.00


Terbilang : Err:511

Mohon Tagihan untuk bulan Januari 2022 dimasukan pada rekening PT. WINSOLUSI KONSULTAN Nomor Rekening :
0416.01.000160.300 BRI Cabang Kelapa Gading 2

Jayapura, 01 Februari 2022


PPK PENGAWASAN Konsultan Supervisi
SATKER P2JN PROVINSI PAPUA (JAYAPURA)
PT. WINSOLUSI KONSULTAN

SAM RANDA, S.T, M.Eng ISNAINI SYAWIK, ST


NIP. 19830422 200801 1 006 Direktur Utama
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Januari 2022 / Invoice 18
TANGGAL : 01 Februari 2022
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

I. BIAYA LANGSUNG PERSONIL


HARGA JUMLAH HARGA PEMBAYARAN TAGIHAN INVOICE NO. 18 PEMBAYARAN
URAIAN SATUAN S/D (Bulan Januari 2022) S/D SISA DANA
NO. JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU ORANG WAKTU/ JUMLAH BULAN INI
(Rp) BULAN (RP) (Rp) (Rp)
a BIAYA TENAGA AHLI
Site Supervision Engineer 1.00 25.00 OB 32,697,000.00 817,425,000.00 526,421,700.00 1.00 1.00 32,697,000.00 559,118,700.00 258,306,300.00
Quality Engineer-1 1.00 24.00 OB 30,880,500.00 741,132,000.00 465,369,135.00 1.00 1.00 30,880,500.00 496,249,635.00 244,882,365.00
Inspection Engineer/Quantity Engineer 1.00 25.00 OB 30,880,500.00 772,012,500.00 497,176,050.00 1.00 1.00 30,880,500.00 528,056,550.00 243,955,950.00
Health Safety Enviroment Engineer 1.00 25.00 OB 25,431,000.00 635,775,000.00 409,439,100.00 1.00 1.00 25,431,000.00 434,870,100.00 200,904,900.00

Sub Total a 2,966,344,500.00 1,898,405,985.00 119,889,000.00 2,018,294,985.00 948,049,515.00


b BIAYA ASISTEN TENAGA AHLI
Inspector -1 1.00 23.00 OB 12,500,000.00 287,500,000.00 176,250,000.00 1.00 1.00 12,500,000.00 188,750,000.00 98,750,000.00
Surveyor Technician -1 1.00 25.00 OB 12,500,000.00 312,500,000.00 201,250,000.00 1.00 1.00 12,500,000.00 213,750,000.00 98,750,000.00
Material Technician -1 1.00 24.00 OB 12,500,000.00 300,000,000.00 188,375,000.00 1.00 1.00 12,500,000.00 200,875,000.00 99,125,000.00
Sub Total b 900,000,000.00 565,875,000.00 37,500,000.00 603,375,000.00 296,625,000.00
c BIAYA STAF PENDUKUNG
Operator Komputer 1.00 25.00 OB 8,000,000.00 200,000,000.00 128,800,000.00 1.00 1.00 8,000,000.00 136,800,000.00 63,200,000.00
Pesuruh/Penjaga Kantor 1.00 25.00 OB 4,000,000.00 100,000,000.00 64,400,000.00 1.00 1.00 4,000,000.00 68,400,000.00 31,600,000.00
Sub Total c 300,000,000.00 193,200,000.00 12,000,000.00 205,200,000.00 94,800,000.00

TOTAL a+b+c 4,166,344,500.00 2,657,480,985.00 - - 169,389,000.00 2,826,869,985.00 1,339,474,515.00


NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Januari 2022 / Invoice 18
TANGGAL : 01 Februari 2022
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

II. BIAYA LANGSUNG NON PERSONIL


HARGA PEMBAYARAN TAGIHAN INVOICE NO. 18 PEMBAYARAN
JUMLAH HARGA
SATUAN S/D (Bulan Januari 2022) S/D SISA DANA
NO. URAIAN JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU JUMLAH BULAN INI
ORANG TRIP
(Rp) (RP) (Rp) (Rp)
a MOBILISASI DAN DEMOBILISASI
- Mobilisasi
Site Supervision Engineer - - Trip - - - - - - - -
Quality Engineer-1 - - Trip - - - - - - - -
Inspection Engineer/Quantity Engineer - - Trip - - - - - - - -
Health Safety Enviroment Engineer - - - - - - - - - -
- Demobilisasi
Site Supervision Engineer - - Trip - - - - - - - -
Quality Engineer-1 - - Trip - - - - - - - -
Inspection Engineer/Quantity Engineer - - Trip - - - - - - - -
Health Safety Enviroment Engineer - - Trip - - - - - - - -
Sub Total a - - - - -
b BIAYA PERJALANAN DINAS
Tiket Perjalanan (PP) Termasuk Ongkos Taxi 6.00 Trip 2,000,000.00 12,000,000.00 - - - - - 12,000,000.00
Biaya Penginapan 24.00 Hari 400,000.00 9,600,000.00 - - - - - 9,600,000.00

Sub Total b 21,600,000.00 - - - 21,600,000.00


HARGA PEMBAYARAN TAGIHAN INVOICE NO. 18 PEMBAYARAN
SATUAN JUMLAH HARGA S/D (Bulan Januari 2022) S/D SISA DANA
NO. URAIAN JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU JUMLAH BULAN INI
VOLUME BULAN
(Rp) (RP) (Rp) (Rp)
c BIAYA KANTOR
Sewa Kantor 1.00 25.00 Bln 5,000,000.00 125,000,000.00 80,500,000.00 1.00 1.00 5,000,000.00 85,500,000.00 39,500,000.00
Sewa Operasional Kantor (Air dan Listrik) 1.00 25.00 Bln 1,500,000.00 37,500,000.00 24,150,000.00 1.00 1.00 1,500,000.00 25,650,000.00 11,850,000.00
Sewa Penunjang Kantor :
- Laptop-1 1.00 25.00 Bln 1,600,000.00 40,000,000.00 25,760,000.00 1.00 1.00 1,600,000.00 27,360,000.00 12,640,000.00
- Laptop-2 1.00 25.00 Bln 1,600,000.00 40,000,000.00 25,760,000.00 1.00 1.00 1,600,000.00 27,360,000.00 12,640,000.00
- Printer A3 1.00 25.00 Bln 700,000.00 17,500,000.00 11,270,000.00 1.00 1.00 700,000.00 11,970,000.00 5,530,000.00
- Printer A4 1.00 25.00 Bln 500,000.00 12,500,000.00 8,050,000.00 1.00 1.00 500,000.00 8,550,000.00 3,950,000.00
Komunikasi (Pulsa Telepon + lnternet) 1.00 25.00 Bln 1,500,000.00 37,500,000.00 24,150,000.00 1.00 1.00 1,500,000.00 25,650,000.00 11,850,000.00
Bahan untuk peralatan kantor 1.00 25.00 Bln 1,000,000.00 25,000,000.00 16,100,000.00 1.00 1.00 1,000,000.00 17,100,000.00 7,900,000.00

Sub Total c 335,000,000.00 215,740,000.00 13,400,000.00 229,140,000.00 105,860,000.00


d BIAYA PELAPORAN
Laporan RMK 5.00 5.00 Eks 150,000.00 750,000.00 750,000.00 - - - 750,000.00 -
Laporan Pendahuluan 5.00 5.00 Eks 150,000.00 750,000.00 750,000.00 - - - 750,000.00 -
Laporan Bulanan 125.00 5.00 Eks 100,000.00 12,500,000.00 8,000,000.00 5.00 1.00 500,000.00 8,500,000.00 4,000,000.00
Laporan Triwulan 40.00 5.00 Eks 250,000.00 10,000,000.00 6,250,000.00 5.00 1.00 1,250,000.00 7,500,000.00 2,500,000.00
Laporan Akhir 5.00 5.00 Eks 250,000.00 1,250,000.00 - - - - - 1,250,000.00
Hard Disk (File Laporan dan Dokumentasi) 1.00 1.00 Buah 1,000,000.00 1,000,000.00 - - - - - 1,000,000.00

Sub Total d 26,250,000.00 15,750,000.00 1,750,000.00 17,500,000.00 8,750,000.00


e BIAYA AKOMODASI
- Biaya Sewa
Sewa Mobil Double Gardan-1 1.00 25.00 Bln 25,000,000.00 625,000,000.00 402,500,000.00 1.00 1.00 25,000,000.00 427,500,000.00 197,500,000.00
Sewa Motor Lapangan -1 1.00 25.00 Bln 2,500,000.00 62,500,000.00 40,250,000.00 1.00 1.00 2,500,000.00 42,750,000.00 19,750,000.00
Sewa Motor Lapangan -2 1.00 25.00 Bln 2,500,000.00 62,500,000.00 40,250,000.00 1.00 1.00 2,500,000.00 42,750,000.00 19,750,000.00
- Tunjangan Perumahan
Site Supervision Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 16,100,000.00 1.00 1.00 1,000,000.00 17,100,000.00 7,900,000.00
Quality Engineer-1 1.00 24.00 Bln 1,000,000.00 24,000,000.00 15,070,000.00 1.00 1.00 1,000,000.00 16,070,000.00 7,930,000.00
Inspection Engineer/Quantity Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 16,100,000.00 1.00 1.00 1,000,000.00 17,100,000.00 7,900,000.00
Health Safety Enviroment Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 16,100,000.00 1.00 1.00 1,000,000.00 17,100,000.00 7,900,000.00
Inspector -1 1.00 23.00 Bln 750,000.00 17,250,000.00 10,575,000.00 1.00 1.00 750,000.00 11,325,000.00 5,925,000.00
Surveyor Technician -1 1.00 25.00 Bln 750,000.00 18,750,000.00 12,075,000.00 1.00 1.00 750,000.00 12,825,000.00 5,925,000.00
Material Technician -1 1.00 24.00 Bln 750,000.00 18,000,000.00 11,302,500.00 1.00 1.00 750,000.00 12,052,500.00 5,947,500.00

Sub Total e 903,000,000.00 580,322,500.00 36,250,000.00 616,572,500.00 286,427,500.00

Sub Total a+b+c+d+e 1,285,850,000.00 811,812,500.00 51,400,000.00 863,212,500.00 422,637,500.00


LAPORAN BULANAN KEADAAN DANA
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Februari 2022 / Invoice 19
TANGGAL : 01 Maret 2022
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

NO. JLH. PEMBAYARAN TAGIHAN INVOICE JLH. PEMBAYARAN SISA DANA


URAIAN TOTAL DANA
S/D BULAN LALU NO. 19 S/D BULAN INI Rp.

I. BIAYA LANGSUNG PERSONIL 4,166,344,500.00 2,826,869,985.00 169,389,000.00 2,996,258,985.00 1,170,085,515.00


-
II. BIAYA LANGSUNG NON PERSONIL 1,285,850,000.00 863,212,500.00 50,150,000.00 913,362,500.00 372,487,500.00
BIAYA MOBILISASI DAN DEMOBILISASI - - - - -
BIAYA PERJALANAN DINAS 21,600,000.00 - - - 21,600,000.00
BIAYA KANTOR 335,000,000.00 229,140,000.00 13,400,000.00 242,540,000.00 92,460,000.00
BIAYA PELAPORAN 26,250,000.00 17,500,000.00 500,000.00 18,000,000.00 8,250,000.00
BIAYA AKOMODASI 903,000,000.00 616,572,500.00 36,250,000.00 652,822,500.00 250,177,500.00

SUB TOTAL (I+II) 5,452,194,500.00 3,690,082,485.00 219,539,000.00 3,909,621,485.00 1,542,573,015.00


PPN 545,219,450.00 369,008,248.50 21,953,900.00 390,962,148.50 154,257,301.50
SUB TOTAL 5,997,413,950.00 4,059,090,733.50 241,492,900.00 4,300,583,633.50 1,696,830,316.50
NILAI KONTRAK DIBULATKAN 5,997,413,000.00
PENGEMBALIAN UANG MUKA 899,611,950.00 899,611,950.00 - 899,611,950.00 -
TOTAL 5,097,801,050.00 3,159,478,783.50 241,492,900.00 3,400,971,683.50 1,696,830,316.50
DIBULATKAN 3,159,478,783.00 241,492,900.00 3,400,971,683.00 1,696,830,317.00

1,199,482,600.00

Jayapura, 01 Maret 2022

PPK PENGAWASAN Konsultan Supervisi


SATKER P2JN PROVINSI PAPUA (JAYAPURA)
PT. WINSOLUSI KONSULTAN

SAM RANDA, S.T, M.Eng ISNAINI SYAWIK, ST


NIP. 19830422 200801 1 006 Direktur Utama
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Februari 2022 / Invoice 19
TANGGAL : 01 Maret 2022
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

REKAPITULASI INVOICE

NO. URAIAN BIAYA (Rp.)

I. BIAYA LANGSUNG PERSONIL 169,389,000.00

II. BIAYA LANGSUNG NON PERSONIL 50,150,000.00


BIAYA MOBILISASI DAN DEMOBILISASI -
BIAYA PERJALANAN DINAS -
BIAYA KANTOR 13,400,000.00
BIAYA PELAPORAN 500,000.00
BIAYA AKOMODASI 36,250,000.00

SUB TOTAL ( I + II ) 219,539,000.00


PPN 10% 21,953,900.00
SUB TOTAL 241,492,900.00
PENGEMBALIAN UANG MUKA 15% -
TOTAL 241,492,900.00
DIBULATKAN 241,492,900.00

Total Pembayaran pada Tagihan ini Rp. 241,492,900.00


Terbilang : Err:511

Mohon Tagihan untuk bulan Februari 2022 dimasukan pada rekening PT. WINSOLUSI KONSULTAN Nomor Rekening :
0416.01.000160.300 BRI Cabang Kelapa Gading 2

Jayapura, 01 Maret 2022


PPK PENGAWASAN Konsultan Supervisi
SATKER P2JN PROVINSI PAPUA (JAYAPURA)
PT. WINSOLUSI KONSULTAN

SAM RANDA, S.T, M.Eng ISNAINI SYAWIK, ST


NIP. 19830422 200801 1 006 Direktur Utama
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Februari 2022 / Invoice 19
TANGGAL : 01 Maret 2022
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

I. BIAYA LANGSUNG PERSONIL


HARGA JUMLAH HARGA PEMBAYARAN TAGIHAN INVOICE NO. 19 PEMBAYARAN
URAIAN SATUAN S/D (Bulan Februari 2022) S/D SISA DANA
NO. JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU ORANG WAKTU/ JUMLAH BULAN INI
(Rp) BULAN (RP) (Rp) (Rp)
a BIAYA TENAGA AHLI
Site Supervision Engineer 1.00 25.00 OB 32,697,000.00 817,425,000.00 559,118,700.00 1.00 1.00 32,697,000.00 591,815,700.00 225,609,300.00
Quality Engineer-1 1.00 24.00 OB 30,880,500.00 741,132,000.00 496,249,635.00 1.00 1.00 30,880,500.00 527,130,135.00 214,001,865.00
Inspection Engineer/Quantity Engineer 1.00 25.00 OB 30,880,500.00 772,012,500.00 528,056,550.00 1.00 1.00 30,880,500.00 558,937,050.00 213,075,450.00
Health Safety Enviroment Engineer 1.00 25.00 OB 25,431,000.00 635,775,000.00 434,870,100.00 1.00 1.00 25,431,000.00 460,301,100.00 175,473,900.00

Sub Total a 2,966,344,500.00 2,018,294,985.00 119,889,000.00 2,138,183,985.00 828,160,515.00


b BIAYA ASISTEN TENAGA AHLI
Inspector -1 1.00 23.00 OB 12,500,000.00 287,500,000.00 188,750,000.00 1.00 1.00 12,500,000.00 201,250,000.00 86,250,000.00
Surveyor Technician -1 1.00 25.00 OB 12,500,000.00 312,500,000.00 213,750,000.00 1.00 1.00 12,500,000.00 226,250,000.00 86,250,000.00
Material Technician -1 1.00 24.00 OB 12,500,000.00 300,000,000.00 200,875,000.00 1.00 1.00 12,500,000.00 213,375,000.00 86,625,000.00
Sub Total b 900,000,000.00 603,375,000.00 37,500,000.00 640,875,000.00 259,125,000.00
c BIAYA STAF PENDUKUNG
Operator Komputer 1.00 25.00 OB 8,000,000.00 200,000,000.00 136,800,000.00 1.00 1.00 8,000,000.00 144,800,000.00 55,200,000.00
Pesuruh/Penjaga Kantor 1.00 25.00 OB 4,000,000.00 100,000,000.00 68,400,000.00 1.00 1.00 4,000,000.00 72,400,000.00 27,600,000.00
Sub Total c 300,000,000.00 205,200,000.00 12,000,000.00 217,200,000.00 82,800,000.00

TOTAL a+b+c 4,166,344,500.00 2,826,869,985.00 - - 169,389,000.00 2,996,258,985.00 1,170,085,515.00


NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Februari 2022 / Invoice 19
TANGGAL : 01 Maret 2022
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

II. BIAYA LANGSUNG NON PERSONIL


HARGA PEMBAYARAN TAGIHAN INVOICE NO. 19 PEMBAYARAN
JUMLAH HARGA
SATUAN S/D (Bulan Februari 2022) S/D SISA DANA
NO. URAIAN JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU JUMLAH BULAN INI
ORANG TRIP
(Rp) (RP) (Rp) (Rp)
a MOBILISASI DAN DEMOBILISASI
- Mobilisasi
Site Supervision Engineer - - Trip - - - - - - - -
Quality Engineer-1 - - Trip - - - - - - - -
Inspection Engineer/Quantity Engineer - - Trip - - - - - - - -
Health Safety Enviroment Engineer - - - - - - - - - -
- Demobilisasi
Site Supervision Engineer - - Trip - - - - - - - -
Quality Engineer-1 - - Trip - - - - - - - -
Inspection Engineer/Quantity Engineer - - Trip - - - - - - - -
Health Safety Enviroment Engineer - - Trip - - - - - - - -
Sub Total a - - - - -
b BIAYA PERJALANAN DINAS
Tiket Perjalanan (PP) Termasuk Ongkos Taxi 6.00 Trip 2,000,000.00 12,000,000.00 - - - - - 12,000,000.00
Biaya Penginapan 24.00 Hari 400,000.00 9,600,000.00 - - - - - 9,600,000.00

Sub Total b 21,600,000.00 - - - 21,600,000.00


HARGA PEMBAYARAN TAGIHAN INVOICE NO. 19 PEMBAYARAN
SATUAN JUMLAH HARGA S/D (Bulan Februari 2022) S/D SISA DANA
NO. URAIAN JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU JUMLAH BULAN INI
VOLUME BULAN
(Rp) (RP) (Rp) (Rp)
c BIAYA KANTOR
Sewa Kantor 1.00 25.00 Bln 5,000,000.00 125,000,000.00 85,500,000.00 1.00 1.00 5,000,000.00 90,500,000.00 34,500,000.00
Sewa Operasional Kantor (Air dan Listrik) 1.00 25.00 Bln 1,500,000.00 37,500,000.00 25,650,000.00 1.00 1.00 1,500,000.00 27,150,000.00 10,350,000.00
Sewa Penunjang Kantor :
- Laptop-1 1.00 25.00 Bln 1,600,000.00 40,000,000.00 27,360,000.00 1.00 1.00 1,600,000.00 28,960,000.00 11,040,000.00
- Laptop-2 1.00 25.00 Bln 1,600,000.00 40,000,000.00 27,360,000.00 1.00 1.00 1,600,000.00 28,960,000.00 11,040,000.00
- Printer A3 1.00 25.00 Bln 700,000.00 17,500,000.00 11,970,000.00 1.00 1.00 700,000.00 12,670,000.00 4,830,000.00
- Printer A4 1.00 25.00 Bln 500,000.00 12,500,000.00 8,550,000.00 1.00 1.00 500,000.00 9,050,000.00 3,450,000.00
Komunikasi (Pulsa Telepon + lnternet) 1.00 25.00 Bln 1,500,000.00 37,500,000.00 25,650,000.00 1.00 1.00 1,500,000.00 27,150,000.00 10,350,000.00
Bahan untuk peralatan kantor 1.00 25.00 Bln 1,000,000.00 25,000,000.00 17,100,000.00 1.00 1.00 1,000,000.00 18,100,000.00 6,900,000.00

Sub Total c 335,000,000.00 229,140,000.00 13,400,000.00 242,540,000.00 92,460,000.00


d BIAYA PELAPORAN
Laporan RMK 5.00 5.00 Eks 150,000.00 750,000.00 750,000.00 - - - 750,000.00 -
Laporan Pendahuluan 5.00 5.00 Eks 150,000.00 750,000.00 750,000.00 - - - 750,000.00 -
Laporan Bulanan 125.00 5.00 Eks 100,000.00 12,500,000.00 8,500,000.00 5.00 1.00 500,000.00 9,000,000.00 3,500,000.00
Laporan Triwulan 40.00 5.00 Eks 250,000.00 10,000,000.00 7,500,000.00 - - - 7,500,000.00 2,500,000.00
Laporan Akhir 5.00 5.00 Eks 250,000.00 1,250,000.00 - - - - - 1,250,000.00
Hard Disk (File Laporan dan Dokumentasi) 1.00 1.00 Buah 1,000,000.00 1,000,000.00 - - - - - 1,000,000.00

Sub Total d 26,250,000.00 17,500,000.00 500,000.00 18,000,000.00 8,250,000.00


e BIAYA AKOMODASI
- Biaya Sewa
Sewa Mobil Double Gardan-1 1.00 25.00 Bln 25,000,000.00 625,000,000.00 427,500,000.00 1.00 1.00 25,000,000.00 452,500,000.00 172,500,000.00
Sewa Motor Lapangan -1 1.00 25.00 Bln 2,500,000.00 62,500,000.00 42,750,000.00 1.00 1.00 2,500,000.00 45,250,000.00 17,250,000.00
Sewa Motor Lapangan -2 1.00 25.00 Bln 2,500,000.00 62,500,000.00 42,750,000.00 1.00 1.00 2,500,000.00 45,250,000.00 17,250,000.00
- Tunjangan Perumahan
Site Supervision Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 17,100,000.00 1.00 1.00 1,000,000.00 18,100,000.00 6,900,000.00
Quality Engineer-1 1.00 24.00 Bln 1,000,000.00 24,000,000.00 16,070,000.00 1.00 1.00 1,000,000.00 17,070,000.00 6,930,000.00
Inspection Engineer/Quantity Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 17,100,000.00 1.00 1.00 1,000,000.00 18,100,000.00 6,900,000.00
Health Safety Enviroment Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 17,100,000.00 1.00 1.00 1,000,000.00 18,100,000.00 6,900,000.00
Inspector -1 1.00 23.00 Bln 750,000.00 17,250,000.00 11,325,000.00 1.00 1.00 750,000.00 12,075,000.00 5,175,000.00
Surveyor Technician -1 1.00 25.00 Bln 750,000.00 18,750,000.00 12,825,000.00 1.00 1.00 750,000.00 13,575,000.00 5,175,000.00
Material Technician -1 1.00 24.00 Bln 750,000.00 18,000,000.00 12,052,500.00 1.00 1.00 750,000.00 12,802,500.00 5,197,500.00

Sub Total e 903,000,000.00 616,572,500.00 36,250,000.00 652,822,500.00 250,177,500.00

Sub Total a+b+c+d+e 1,285,850,000.00 863,212,500.00 50,150,000.00 913,362,500.00 372,487,500.00


LAPORAN BULANAN KEADAAN DANA
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Maret 2022 / Invoice 20
TANGGAL : 01 April 2022
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

NO. JLH. PEMBAYARAN TAGIHAN INVOICE JLH. PEMBAYARAN SISA DANA


URAIAN TOTAL DANA
S/D BULAN LALU NO. 20 S/D BULAN INI Rp.

I. BIAYA LANGSUNG PERSONIL 4,166,344,500.00 2,996,258,985.00 169,389,000.00 3,165,647,985.00 1,000,696,515.00


-
II. BIAYA LANGSUNG NON PERSONIL 1,285,850,000.00 913,362,500.00 50,150,000.00 963,512,500.00 322,337,500.00
BIAYA MOBILISASI DAN DEMOBILISASI - - - - -
BIAYA PERJALANAN DINAS 21,600,000.00 - - - 21,600,000.00
BIAYA KANTOR 335,000,000.00 242,540,000.00 13,400,000.00 255,940,000.00 79,060,000.00
BIAYA PELAPORAN 26,250,000.00 18,000,000.00 500,000.00 18,500,000.00 7,750,000.00
BIAYA AKOMODASI 903,000,000.00 652,822,500.00 36,250,000.00 689,072,500.00 213,927,500.00

SUB TOTAL (I+II) 5,452,194,500.00 3,909,621,485.00 219,539,000.00 4,129,160,485.00 1,323,034,015.00


PPN 545,219,450.00 390,962,148.50 21,953,900.00 412,916,048.50 132,303,401.50
SUB TOTAL 5,997,413,950.00 4,300,583,633.50 241,492,900.00 4,542,076,533.50 1,455,337,416.50
NILAI KONTRAK DIBULATKAN 5,997,413,000.00
PENGEMBALIAN UANG MUKA 899,611,950.00 899,611,950.00 - 899,611,950.00 -
TOTAL 5,097,801,050.00 3,400,971,683.50 241,492,900.00 3,642,464,583.50 1,455,337,416.50
DIBULATKAN 3,400,971,683.00 241,492,900.00 3,642,464,583.00 1,455,337,417.00

1,199,482,600.00

Jayapura, 01 April 2022

PPK PENGAWASAN Konsultan Supervisi


SATKER P2JN PROVINSI PAPUA (JAYAPURA)
PT. WINSOLUSI KONSULTAN

SAM RANDA, S.T, M.Eng ISNAINI SYAWIK, ST


NIP. 19830422 200801 1 006 Direktur Utama
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Maret 2022 / Invoice 20
TANGGAL : 01 April 2022
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

REKAPITULASI INVOICE

NO. URAIAN BIAYA (Rp.)

I. BIAYA LANGSUNG PERSONIL 169,389,000.00

II. BIAYA LANGSUNG NON PERSONIL 50,150,000.00


BIAYA MOBILISASI DAN DEMOBILISASI -
BIAYA PERJALANAN DINAS -
BIAYA KANTOR 13,400,000.00
BIAYA PELAPORAN 500,000.00
BIAYA AKOMODASI 36,250,000.00

SUB TOTAL ( I + II ) 219,539,000.00


PPN 10% 21,953,900.00
SUB TOTAL 241,492,900.00
PENGEMBALIAN UANG MUKA 15% -
TOTAL 241,492,900.00
DIBULATKAN 241,492,900.00

Total Pembayaran pada Tagihan ini Rp. 241,492,900.00


Terbilang : Err:511

Mohon Tagihan untuk bulan Maret 2022 dimasukan pada rekening PT. WINSOLUSI KONSULTAN Nomor Rekening :
0416.01.000160.300 BRI Cabang Kelapa Gading 2

Jayapura, 01 April 2022


PPK PENGAWASAN Konsultan Supervisi
SATKER P2JN PROVINSI PAPUA (JAYAPURA)
PT. WINSOLUSI KONSULTAN

SAM RANDA, S.T, M.Eng ISNAINI SYAWIK, ST


NIP. 19830422 200801 1 006 Direktur Utama
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Maret 2022 / Invoice 20
TANGGAL : 01 April 2022
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

I. BIAYA LANGSUNG PERSONIL


HARGA JUMLAH HARGA PEMBAYARAN TAGIHAN INVOICE NO. 20 PEMBAYARAN
URAIAN SATUAN S/D (Bulan Maret 2022) S/D SISA DANA
NO. JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU ORANG WAKTU/ JUMLAH BULAN INI
(Rp) BULAN (RP) (Rp) (Rp)
a BIAYA TENAGA AHLI
Site Supervision Engineer 1.00 25.00 OB 32,697,000.00 817,425,000.00 591,815,700.00 1.00 1.00 32,697,000.00 624,512,700.00 192,912,300.00
Quality Engineer-1 1.00 24.00 OB 30,880,500.00 741,132,000.00 527,130,135.00 1.00 1.00 30,880,500.00 558,010,635.00 183,121,365.00
Inspection Engineer/Quantity Engineer 1.00 25.00 OB 30,880,500.00 772,012,500.00 558,937,050.00 1.00 1.00 30,880,500.00 589,817,550.00 182,194,950.00
Health Safety Enviroment Engineer 1.00 25.00 OB 25,431,000.00 635,775,000.00 460,301,100.00 1.00 1.00 25,431,000.00 485,732,100.00 150,042,900.00

Sub Total a 2,966,344,500.00 2,138,183,985.00 119,889,000.00 2,258,072,985.00 708,271,515.00


b BIAYA ASISTEN TENAGA AHLI
Inspector -1 1.00 23.00 OB 12,500,000.00 287,500,000.00 201,250,000.00 1.00 1.00 12,500,000.00 213,750,000.00 73,750,000.00
Surveyor Technician -1 1.00 25.00 OB 12,500,000.00 312,500,000.00 226,250,000.00 1.00 1.00 12,500,000.00 238,750,000.00 73,750,000.00
Material Technician -1 1.00 24.00 OB 12,500,000.00 300,000,000.00 213,375,000.00 1.00 1.00 12,500,000.00 225,875,000.00 74,125,000.00
Sub Total b 900,000,000.00 640,875,000.00 37,500,000.00 678,375,000.00 221,625,000.00
c BIAYA STAF PENDUKUNG
Operator Komputer 1.00 25.00 OB 8,000,000.00 200,000,000.00 144,800,000.00 1.00 1.00 8,000,000.00 152,800,000.00 47,200,000.00
Pesuruh/Penjaga Kantor 1.00 25.00 OB 4,000,000.00 100,000,000.00 72,400,000.00 1.00 1.00 4,000,000.00 76,400,000.00 23,600,000.00
Sub Total c 300,000,000.00 217,200,000.00 12,000,000.00 229,200,000.00 70,800,000.00

TOTAL a+b+c 4,166,344,500.00 2,996,258,985.00 - - 169,389,000.00 3,165,647,985.00 1,000,696,515.00


NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Maret 2022 / Invoice 20
TANGGAL : 01 April 2022
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

II. BIAYA LANGSUNG NON PERSONIL


HARGA PEMBAYARAN TAGIHAN INVOICE NO. 20 PEMBAYARAN
JUMLAH HARGA
SATUAN S/D (Bulan Maret 2022) S/D SISA DANA
NO. URAIAN JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU JUMLAH BULAN INI
ORANG TRIP
(Rp) (RP) (Rp) (Rp)
a MOBILISASI DAN DEMOBILISASI
- Mobilisasi
Site Supervision Engineer - - Trip - - - - - - - -
Quality Engineer-1 - - Trip - - - - - - - -
Inspection Engineer/Quantity Engineer - - Trip - - - - - - - -
Health Safety Enviroment Engineer - - - - - - - - - -
- Demobilisasi
Site Supervision Engineer - - Trip - - - - - - - -
Quality Engineer-1 - - Trip - - - - - - - -
Inspection Engineer/Quantity Engineer - - Trip - - - - - - - -
Health Safety Enviroment Engineer - - Trip - - - - - - - -
Sub Total a - - - - -
b BIAYA PERJALANAN DINAS
Tiket Perjalanan (PP) Termasuk Ongkos Taxi 6.00 Trip 2,000,000.00 12,000,000.00 - - - - - 12,000,000.00
Biaya Penginapan 24.00 Hari 400,000.00 9,600,000.00 - - - - - 9,600,000.00

Sub Total b 21,600,000.00 - - - 21,600,000.00


HARGA PEMBAYARAN TAGIHAN INVOICE NO. 20 PEMBAYARAN
SATUAN JUMLAH HARGA S/D (Bulan Maret 2022) S/D SISA DANA
NO. URAIAN JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU JUMLAH BULAN INI
VOLUME BULAN
(Rp) (RP) (Rp) (Rp)
c BIAYA KANTOR
Sewa Kantor 1.00 25.00 Bln 5,000,000.00 125,000,000.00 90,500,000.00 1.00 1.00 5,000,000.00 95,500,000.00 29,500,000.00
Sewa Operasional Kantor (Air dan Listrik) 1.00 25.00 Bln 1,500,000.00 37,500,000.00 27,150,000.00 1.00 1.00 1,500,000.00 28,650,000.00 8,850,000.00
Sewa Penunjang Kantor :
- Laptop-1 1.00 25.00 Bln 1,600,000.00 40,000,000.00 28,960,000.00 1.00 1.00 1,600,000.00 30,560,000.00 9,440,000.00
- Laptop-2 1.00 25.00 Bln 1,600,000.00 40,000,000.00 28,960,000.00 1.00 1.00 1,600,000.00 30,560,000.00 9,440,000.00
- Printer A3 1.00 25.00 Bln 700,000.00 17,500,000.00 12,670,000.00 1.00 1.00 700,000.00 13,370,000.00 4,130,000.00
- Printer A4 1.00 25.00 Bln 500,000.00 12,500,000.00 9,050,000.00 1.00 1.00 500,000.00 9,550,000.00 2,950,000.00
Komunikasi (Pulsa Telepon + lnternet) 1.00 25.00 Bln 1,500,000.00 37,500,000.00 27,150,000.00 1.00 1.00 1,500,000.00 28,650,000.00 8,850,000.00
Bahan untuk peralatan kantor 1.00 25.00 Bln 1,000,000.00 25,000,000.00 18,100,000.00 1.00 1.00 1,000,000.00 19,100,000.00 5,900,000.00

Sub Total c 335,000,000.00 242,540,000.00 13,400,000.00 255,940,000.00 79,060,000.00


d BIAYA PELAPORAN
Laporan RMK 5.00 5.00 Eks 150,000.00 750,000.00 750,000.00 - - - 750,000.00 -
Laporan Pendahuluan 5.00 5.00 Eks 150,000.00 750,000.00 750,000.00 - - - 750,000.00 -
Laporan Bulanan 125.00 5.00 Eks 100,000.00 12,500,000.00 9,000,000.00 5.00 1.00 500,000.00 9,500,000.00 3,000,000.00
Laporan Triwulan 40.00 5.00 Eks 250,000.00 10,000,000.00 7,500,000.00 - - - 7,500,000.00 2,500,000.00
Laporan Akhir 5.00 5.00 Eks 250,000.00 1,250,000.00 - - - - - 1,250,000.00
Hard Disk (File Laporan dan Dokumentasi) 1.00 1.00 Buah 1,000,000.00 1,000,000.00 - - - - - 1,000,000.00

Sub Total d 26,250,000.00 18,000,000.00 500,000.00 18,500,000.00 7,750,000.00


e BIAYA AKOMODASI
- Biaya Sewa
Sewa Mobil Double Gardan-1 1.00 25.00 Bln 25,000,000.00 625,000,000.00 452,500,000.00 1.00 1.00 25,000,000.00 477,500,000.00 147,500,000.00
Sewa Motor Lapangan -1 1.00 25.00 Bln 2,500,000.00 62,500,000.00 45,250,000.00 1.00 1.00 2,500,000.00 47,750,000.00 14,750,000.00
Sewa Motor Lapangan -2 1.00 25.00 Bln 2,500,000.00 62,500,000.00 45,250,000.00 1.00 1.00 2,500,000.00 47,750,000.00 14,750,000.00
- Tunjangan Perumahan
Site Supervision Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 18,100,000.00 1.00 1.00 1,000,000.00 19,100,000.00 5,900,000.00
Quality Engineer-1 1.00 24.00 Bln 1,000,000.00 24,000,000.00 17,070,000.00 1.00 1.00 1,000,000.00 18,070,000.00 5,930,000.00
Inspection Engineer/Quantity Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 18,100,000.00 1.00 1.00 1,000,000.00 19,100,000.00 5,900,000.00
Health Safety Enviroment Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 18,100,000.00 1.00 1.00 1,000,000.00 19,100,000.00 5,900,000.00
Inspector -1 1.00 23.00 Bln 750,000.00 17,250,000.00 12,075,000.00 1.00 1.00 750,000.00 12,825,000.00 4,425,000.00
Surveyor Technician -1 1.00 25.00 Bln 750,000.00 18,750,000.00 13,575,000.00 1.00 1.00 750,000.00 14,325,000.00 4,425,000.00
Material Technician -1 1.00 24.00 Bln 750,000.00 18,000,000.00 12,802,500.00 1.00 1.00 750,000.00 13,552,500.00 4,447,500.00

Sub Total e 903,000,000.00 652,822,500.00 36,250,000.00 689,072,500.00 213,927,500.00

Sub Total a+b+c+d+e 1,285,850,000.00 913,362,500.00 50,150,000.00 963,512,500.00 322,337,500.00


LAPORAN BULANAN KEADAAN DANA
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : April 2022 / Invoice 21
TANGGAL : 01 Mei 2022
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

NO. JLH. PEMBAYARAN TAGIHAN INVOICE JLH. PEMBAYARAN SISA DANA


URAIAN TOTAL DANA
S/D BULAN LALU NO. 21 S/D BULAN INI Rp.

I. BIAYA LANGSUNG PERSONIL 4,166,344,500.00 3,165,647,985.00 169,389,000.00 3,335,036,985.00 831,307,515.00


-
II. BIAYA LANGSUNG NON PERSONIL 1,285,850,000.00 963,512,500.00 51,400,000.00 1,014,912,500.00 270,937,500.00
BIAYA MOBILISASI DAN DEMOBILISASI - - - - -
BIAYA PERJALANAN DINAS 21,600,000.00 - - - 21,600,000.00
BIAYA KANTOR 335,000,000.00 255,940,000.00 13,400,000.00 269,340,000.00 65,660,000.00
BIAYA PELAPORAN 26,250,000.00 18,500,000.00 1,750,000.00 20,250,000.00 6,000,000.00
BIAYA AKOMODASI 903,000,000.00 689,072,500.00 36,250,000.00 725,322,500.00 177,677,500.00

SUB TOTAL (I+II) 5,452,194,500.00 4,129,160,485.00 220,789,000.00 4,349,949,485.00 1,102,245,015.00


PPN 545,219,450.00 412,916,048.50 22,078,900.00 434,994,948.50 110,224,501.50
SUB TOTAL 5,997,413,950.00 4,542,076,533.50 242,867,900.00 4,784,944,433.50 1,212,469,516.50
NILAI KONTRAK DIBULATKAN 5,997,413,000.00
PENGEMBALIAN UANG MUKA 899,611,950.00 899,611,950.00 - 899,611,950.00 -
TOTAL 5,097,801,050.00 3,642,464,583.50 242,867,900.00 3,885,332,483.50 1,212,469,516.50
DIBULATKAN 3,642,464,583.00 242,867,900.00 3,885,332,483.00 1,212,469,517.00

1,199,482,600.00

Jayapura, 01 Mei 2022

PPK PENGAWASAN Konsultan Supervisi


SATKER P2JN PROVINSI PAPUA (JAYAPURA)
PT. WINSOLUSI KONSULTAN

SAM RANDA, S.T, M.Eng ISNAINI SYAWIK, ST


NIP. 19830422 200801 1 006 Direktur Utama
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : April 2022 / Invoice 21
TANGGAL : 01 Mei 2022
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

REKAPITULASI INVOICE

NO. URAIAN BIAYA (Rp.)

I. BIAYA LANGSUNG PERSONIL 169,389,000.00

II. BIAYA LANGSUNG NON PERSONIL 51,400,000.00


BIAYA MOBILISASI DAN DEMOBILISASI -
BIAYA PERJALANAN DINAS -
BIAYA KANTOR 13,400,000.00
BIAYA PELAPORAN 1,750,000.00
BIAYA AKOMODASI 36,250,000.00

SUB TOTAL ( I + II ) 220,789,000.00


PPN 10% 22,078,900.00
SUB TOTAL 242,867,900.00
PENGEMBALIAN UANG MUKA 15% -
TOTAL 242,867,900.00
DIBULATKAN 242,867,900.00

Total Pembayaran pada Tagihan ini Rp. 242,867,900.00


Terbilang : Err:511

Mohon Tagihan untuk bulan April 2022 dimasukan pada rekening PT. WINSOLUSI KONSULTAN Nomor Rekening :
0416.01.000160.300 BRI Cabang Kelapa Gading 2

Jayapura, 01 Mei 2022


PPK PENGAWASAN Konsultan Supervisi
SATKER P2JN PROVINSI PAPUA (JAYAPURA)
PT. WINSOLUSI KONSULTAN

SAM RANDA, S.T, M.Eng ISNAINI SYAWIK, ST


NIP. 19830422 200801 1 006 Direktur Utama
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : April 2022 / Invoice 21
TANGGAL : 01 Mei 2022
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

I. BIAYA LANGSUNG PERSONIL


HARGA JUMLAH HARGA PEMBAYARAN TAGIHAN INVOICE NO. 21 PEMBAYARAN
URAIAN SATUAN S/D (Bulan April 2022) S/D SISA DANA
NO. JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU ORANG WAKTU/ JUMLAH BULAN INI
(Rp) BULAN (RP) (Rp) (Rp)
a BIAYA TENAGA AHLI
Site Supervision Engineer 1.00 25.00 OB 32,697,000.00 817,425,000.00 624,512,700.00 1.00 1.00 32,697,000.00 657,209,700.00 160,215,300.00
Quality Engineer-1 1.00 24.00 OB 30,880,500.00 741,132,000.00 558,010,635.00 1.00 1.00 30,880,500.00 588,891,135.00 152,240,865.00
Inspection Engineer/Quantity Engineer 1.00 25.00 OB 30,880,500.00 772,012,500.00 589,817,550.00 1.00 1.00 30,880,500.00 620,698,050.00 151,314,450.00
Health Safety Enviroment Engineer 1.00 25.00 OB 25,431,000.00 635,775,000.00 485,732,100.00 1.00 1.00 25,431,000.00 511,163,100.00 124,611,900.00

Sub Total a 2,966,344,500.00 2,258,072,985.00 119,889,000.00 2,377,961,985.00 588,382,515.00


b BIAYA ASISTEN TENAGA AHLI
Inspector -1 1.00 23.00 OB 12,500,000.00 287,500,000.00 213,750,000.00 1.00 1.00 12,500,000.00 226,250,000.00 61,250,000.00
Surveyor Technician -1 1.00 25.00 OB 12,500,000.00 312,500,000.00 238,750,000.00 1.00 1.00 12,500,000.00 251,250,000.00 61,250,000.00
Material Technician -1 1.00 24.00 OB 12,500,000.00 300,000,000.00 225,875,000.00 1.00 1.00 12,500,000.00 238,375,000.00 61,625,000.00
Sub Total b 900,000,000.00 678,375,000.00 37,500,000.00 715,875,000.00 184,125,000.00
c BIAYA STAF PENDUKUNG
Operator Komputer 1.00 25.00 OB 8,000,000.00 200,000,000.00 152,800,000.00 1.00 1.00 8,000,000.00 160,800,000.00 39,200,000.00
Pesuruh/Penjaga Kantor 1.00 25.00 OB 4,000,000.00 100,000,000.00 76,400,000.00 1.00 1.00 4,000,000.00 80,400,000.00 19,600,000.00
Sub Total c 300,000,000.00 229,200,000.00 12,000,000.00 241,200,000.00 58,800,000.00

TOTAL a+b+c 4,166,344,500.00 3,165,647,985.00 - - 169,389,000.00 3,335,036,985.00 831,307,515.00


NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : April 2022 / Invoice 21
TANGGAL : 01 Mei 2022
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

II. BIAYA LANGSUNG NON PERSONIL


HARGA PEMBAYARAN TAGIHAN INVOICE NO. 21 PEMBAYARAN
JUMLAH HARGA
SATUAN S/D (Bulan April 2022) S/D SISA DANA
NO. URAIAN JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU JUMLAH BULAN INI
ORANG TRIP
(Rp) (RP) (Rp) (Rp)
a MOBILISASI DAN DEMOBILISASI
- Mobilisasi
Site Supervision Engineer - - Trip - - - - - - - -
Quality Engineer-1 - - Trip - - - - - - - -
Inspection Engineer/Quantity Engineer - - Trip - - - - - - - -
Health Safety Enviroment Engineer - - - - - - - - - -
- Demobilisasi
Site Supervision Engineer - - Trip - - - - - - - -
Quality Engineer-1 - - Trip - - - - - - - -
Inspection Engineer/Quantity Engineer - - Trip - - - - - - - -
Health Safety Enviroment Engineer - - Trip - - - - - - - -
Sub Total a - - - - -
b BIAYA PERJALANAN DINAS
Tiket Perjalanan (PP) Termasuk Ongkos Taxi 6.00 Trip 2,000,000.00 12,000,000.00 - - - - - 12,000,000.00
Biaya Penginapan 24.00 Hari 400,000.00 9,600,000.00 - - - - - 9,600,000.00

Sub Total b 21,600,000.00 - - - 21,600,000.00


HARGA PEMBAYARAN TAGIHAN INVOICE NO. 21 PEMBAYARAN
SATUAN JUMLAH HARGA S/D (Bulan April 2022) S/D SISA DANA
NO. URAIAN JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU JUMLAH BULAN INI
VOLUME BULAN
(Rp) (RP) (Rp) (Rp)
c BIAYA KANTOR
Sewa Kantor 1.00 25.00 Bln 5,000,000.00 125,000,000.00 95,500,000.00 1.00 1.00 5,000,000.00 100,500,000.00 24,500,000.00
Sewa Operasional Kantor (Air dan Listrik) 1.00 25.00 Bln 1,500,000.00 37,500,000.00 28,650,000.00 1.00 1.00 1,500,000.00 30,150,000.00 7,350,000.00
Sewa Penunjang Kantor :
- Laptop-1 1.00 25.00 Bln 1,600,000.00 40,000,000.00 30,560,000.00 1.00 1.00 1,600,000.00 32,160,000.00 7,840,000.00
- Laptop-2 1.00 25.00 Bln 1,600,000.00 40,000,000.00 30,560,000.00 1.00 1.00 1,600,000.00 32,160,000.00 7,840,000.00
- Printer A3 1.00 25.00 Bln 700,000.00 17,500,000.00 13,370,000.00 1.00 1.00 700,000.00 14,070,000.00 3,430,000.00
- Printer A4 1.00 25.00 Bln 500,000.00 12,500,000.00 9,550,000.00 1.00 1.00 500,000.00 10,050,000.00 2,450,000.00
Komunikasi (Pulsa Telepon + lnternet) 1.00 25.00 Bln 1,500,000.00 37,500,000.00 28,650,000.00 1.00 1.00 1,500,000.00 30,150,000.00 7,350,000.00
Bahan untuk peralatan kantor 1.00 25.00 Bln 1,000,000.00 25,000,000.00 19,100,000.00 1.00 1.00 1,000,000.00 20,100,000.00 4,900,000.00

Sub Total c 335,000,000.00 255,940,000.00 13,400,000.00 269,340,000.00 65,660,000.00


d BIAYA PELAPORAN
Laporan RMK 5.00 5.00 Eks 150,000.00 750,000.00 750,000.00 - - - 750,000.00 -
Laporan Pendahuluan 5.00 5.00 Eks 150,000.00 750,000.00 750,000.00 - - - 750,000.00 -
Laporan Bulanan 125.00 5.00 Eks 100,000.00 12,500,000.00 9,500,000.00 5.00 1.00 500,000.00 10,000,000.00 2,500,000.00
Laporan Triwulan 40.00 5.00 Eks 250,000.00 10,000,000.00 7,500,000.00 5.00 1.00 1,250,000.00 8,750,000.00 1,250,000.00
Laporan Akhir 5.00 5.00 Eks 250,000.00 1,250,000.00 - - - - - 1,250,000.00
Hard Disk (File Laporan dan Dokumentasi) 1.00 1.00 Buah 1,000,000.00 1,000,000.00 - - - - - 1,000,000.00

Sub Total d 26,250,000.00 18,500,000.00 1,750,000.00 20,250,000.00 6,000,000.00


e BIAYA AKOMODASI
- Biaya Sewa
Sewa Mobil Double Gardan-1 1.00 25.00 Bln 25,000,000.00 625,000,000.00 477,500,000.00 1.00 1.00 25,000,000.00 502,500,000.00 122,500,000.00
Sewa Motor Lapangan -1 1.00 25.00 Bln 2,500,000.00 62,500,000.00 47,750,000.00 1.00 1.00 2,500,000.00 50,250,000.00 12,250,000.00
Sewa Motor Lapangan -2 1.00 25.00 Bln 2,500,000.00 62,500,000.00 47,750,000.00 1.00 1.00 2,500,000.00 50,250,000.00 12,250,000.00
- Tunjangan Perumahan
Site Supervision Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 19,100,000.00 1.00 1.00 1,000,000.00 20,100,000.00 4,900,000.00
Quality Engineer-1 1.00 24.00 Bln 1,000,000.00 24,000,000.00 18,070,000.00 1.00 1.00 1,000,000.00 19,070,000.00 4,930,000.00
Inspection Engineer/Quantity Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 19,100,000.00 1.00 1.00 1,000,000.00 20,100,000.00 4,900,000.00
Health Safety Enviroment Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 19,100,000.00 1.00 1.00 1,000,000.00 20,100,000.00 4,900,000.00
Inspector -1 1.00 23.00 Bln 750,000.00 17,250,000.00 12,825,000.00 1.00 1.00 750,000.00 13,575,000.00 3,675,000.00
Surveyor Technician -1 1.00 25.00 Bln 750,000.00 18,750,000.00 14,325,000.00 1.00 1.00 750,000.00 15,075,000.00 3,675,000.00
Material Technician -1 1.00 24.00 Bln 750,000.00 18,000,000.00 13,552,500.00 1.00 1.00 750,000.00 14,302,500.00 3,697,500.00

Sub Total e 903,000,000.00 689,072,500.00 36,250,000.00 725,322,500.00 177,677,500.00

Sub Total a+b+c+d+e 1,285,850,000.00 963,512,500.00 51,400,000.00 1,014,912,500.00 270,937,500.00


LAPORAN BULANAN KEADAAN DANA
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Mei 2022 / Invoice 22
TANGGAL : 01 Juni 2022
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

NO. JLH. PEMBAYARAN TAGIHAN INVOICE JLH. PEMBAYARAN SISA DANA


URAIAN TOTAL DANA
S/D BULAN LALU NO. 22 S/D BULAN INI Rp.

I. BIAYA LANGSUNG PERSONIL 4,166,344,500.00 3,335,036,985.00 169,389,000.00 3,504,425,985.00 661,918,515.00


-
II. BIAYA LANGSUNG NON PERSONIL 1,285,850,000.00 1,014,912,500.00 50,150,000.00 1,065,062,500.00 220,787,500.00
BIAYA MOBILISASI DAN DEMOBILISASI - - - - -
BIAYA PERJALANAN DINAS 21,600,000.00 - - - 21,600,000.00
BIAYA KANTOR 335,000,000.00 269,340,000.00 13,400,000.00 282,740,000.00 52,260,000.00
BIAYA PELAPORAN 26,250,000.00 20,250,000.00 500,000.00 20,750,000.00 5,500,000.00
BIAYA AKOMODASI 903,000,000.00 725,322,500.00 36,250,000.00 761,572,500.00 141,427,500.00

SUB TOTAL (I+II) 5,452,194,500.00 4,349,949,485.00 219,539,000.00 4,569,488,485.00 882,706,015.00


PPN 545,219,450.00 434,994,948.50 21,953,900.00 456,948,848.50 88,270,601.50
SUB TOTAL 5,997,413,950.00 4,784,944,433.50 241,492,900.00 5,026,437,333.50 970,976,616.50
NILAI KONTRAK DIBULATKAN 5,997,413,000.00
PENGEMBALIAN UANG MUKA 899,611,950.00 899,611,950.00 - 899,611,950.00 -
TOTAL 5,097,801,050.00 3,885,332,483.50 241,492,900.00 4,126,825,383.50 970,976,616.50
DIBULATKAN 3,885,332,483.00 241,492,900.00 4,126,825,383.00 970,976,617.00

1,199,482,600.00

Jayapura, 01 Juni 2022

PPK PENGAWASAN Konsultan Supervisi


SATKER P2JN PROVINSI PAPUA (JAYAPURA)
PT. WINSOLUSI KONSULTAN

SAM RANDA, S.T, M.Eng ISNAINI SYAWIK, ST


NIP. 19830422 200801 1 006 Direktur Utama
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Mei 2022 / Invoice 22
TANGGAL : 01 Juni 2022
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

REKAPITULASI INVOICE

NO. URAIAN BIAYA (Rp.)

I. BIAYA LANGSUNG PERSONIL 169,389,000.00

II. BIAYA LANGSUNG NON PERSONIL 50,150,000.00


BIAYA MOBILISASI DAN DEMOBILISASI -
BIAYA PERJALANAN DINAS -
BIAYA KANTOR 13,400,000.00
BIAYA PELAPORAN 500,000.00
BIAYA AKOMODASI 36,250,000.00

SUB TOTAL ( I + II ) 219,539,000.00


PPN 10% 21,953,900.00
SUB TOTAL 241,492,900.00
PENGEMBALIAN UANG MUKA 15% -
TOTAL 241,492,900.00
DIBULATKAN 241,492,900.00

Total Pembayaran pada Tagihan ini Rp. 241,492,900.00


Terbilang : Err:511

Mohon Tagihan untuk bulan Mei 2022 dimasukan pada rekening PT. WINSOLUSI KONSULTAN Nomor Rekening :
0416.01.000160.300 BRI Cabang Kelapa Gading 2

Jayapura, 01 Juni 2022


PPK PENGAWASAN Konsultan Supervisi
SATKER P2JN PROVINSI PAPUA (JAYAPURA)
PT. WINSOLUSI KONSULTAN

SAM RANDA, S.T, M.Eng ISNAINI SYAWIK, ST


NIP. 19830422 200801 1 006 Direktur Utama
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Mei 2022 / Invoice 22
TANGGAL : 01 Juni 2022
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

I. BIAYA LANGSUNG PERSONIL


HARGA JUMLAH HARGA PEMBAYARAN TAGIHAN INVOICE NO. 22 PEMBAYARAN
URAIAN SATUAN S/D (Bulan Mei 2022) S/D SISA DANA
NO. JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU ORANG WAKTU/ JUMLAH BULAN INI
(Rp) BULAN (RP) (Rp) (Rp)
a BIAYA TENAGA AHLI
Site Supervision Engineer 1.00 25.00 OB 32,697,000.00 817,425,000.00 657,209,700.00 1.00 1.00 32,697,000.00 689,906,700.00 127,518,300.00
Quality Engineer-1 1.00 24.00 OB 30,880,500.00 741,132,000.00 588,891,135.00 1.00 1.00 30,880,500.00 619,771,635.00 121,360,365.00
Inspection Engineer/Quantity Engineer 1.00 25.00 OB 30,880,500.00 772,012,500.00 620,698,050.00 1.00 1.00 30,880,500.00 651,578,550.00 120,433,950.00
Health Safety Enviroment Engineer 1.00 25.00 OB 25,431,000.00 635,775,000.00 511,163,100.00 1.00 1.00 25,431,000.00 536,594,100.00 99,180,900.00

Sub Total a 2,966,344,500.00 2,377,961,985.00 119,889,000.00 2,497,850,985.00 468,493,515.00


b BIAYA ASISTEN TENAGA AHLI
Inspector -1 1.00 23.00 OB 12,500,000.00 287,500,000.00 226,250,000.00 1.00 1.00 12,500,000.00 238,750,000.00 48,750,000.00
Surveyor Technician -1 1.00 25.00 OB 12,500,000.00 312,500,000.00 251,250,000.00 1.00 1.00 12,500,000.00 263,750,000.00 48,750,000.00
Material Technician -1 1.00 24.00 OB 12,500,000.00 300,000,000.00 238,375,000.00 1.00 1.00 12,500,000.00 250,875,000.00 49,125,000.00
Sub Total b 900,000,000.00 715,875,000.00 37,500,000.00 753,375,000.00 146,625,000.00
c BIAYA STAF PENDUKUNG
Operator Komputer 1.00 25.00 OB 8,000,000.00 200,000,000.00 160,800,000.00 1.00 1.00 8,000,000.00 168,800,000.00 31,200,000.00
Pesuruh/Penjaga Kantor 1.00 25.00 OB 4,000,000.00 100,000,000.00 80,400,000.00 1.00 1.00 4,000,000.00 84,400,000.00 15,600,000.00
Sub Total c 300,000,000.00 241,200,000.00 12,000,000.00 253,200,000.00 46,800,000.00

TOTAL a+b+c 4,166,344,500.00 3,335,036,985.00 - - 169,389,000.00 3,504,425,985.00 661,918,515.00


NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Mei 2022 / Invoice 22
TANGGAL : 01 Juni 2022
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

II. BIAYA LANGSUNG NON PERSONIL


HARGA PEMBAYARAN TAGIHAN INVOICE NO. 22 PEMBAYARAN
JUMLAH HARGA
SATUAN S/D (Bulan Mei 2022) S/D SISA DANA
NO. URAIAN JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU JUMLAH BULAN INI
ORANG TRIP
(Rp) (RP) (Rp) (Rp)
a MOBILISASI DAN DEMOBILISASI
- Mobilisasi
Site Supervision Engineer - - Trip - - - - - - - -
Quality Engineer-1 - - Trip - - - - - - - -
Inspection Engineer/Quantity Engineer - - Trip - - - - - - - -
Health Safety Enviroment Engineer - - - - - - - - - -
- Demobilisasi
Site Supervision Engineer - - Trip - - - - - - - -
Quality Engineer-1 - - Trip - - - - - - - -
Inspection Engineer/Quantity Engineer - - Trip - - - - - - - -
Health Safety Enviroment Engineer - - Trip - - - - - - - -
Sub Total a - - - - -
b BIAYA PERJALANAN DINAS
Tiket Perjalanan (PP) Termasuk Ongkos Taxi 6.00 Trip 2,000,000.00 12,000,000.00 - - - - - 12,000,000.00
Biaya Penginapan 24.00 Hari 400,000.00 9,600,000.00 - - - - - 9,600,000.00

Sub Total b 21,600,000.00 - - - 21,600,000.00


HARGA PEMBAYARAN TAGIHAN INVOICE NO. 22 PEMBAYARAN
SATUAN JUMLAH HARGA S/D (Bulan Mei 2022) S/D SISA DANA
NO. URAIAN JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU JUMLAH BULAN INI
VOLUME BULAN
(Rp) (RP) (Rp) (Rp)
c BIAYA KANTOR
Sewa Kantor 1.00 25.00 Bln 5,000,000.00 125,000,000.00 100,500,000.00 1.00 1.00 5,000,000.00 105,500,000.00 19,500,000.00
Sewa Operasional Kantor (Air dan Listrik) 1.00 25.00 Bln 1,500,000.00 37,500,000.00 30,150,000.00 1.00 1.00 1,500,000.00 31,650,000.00 5,850,000.00
Sewa Penunjang Kantor :
- Laptop-1 1.00 25.00 Bln 1,600,000.00 40,000,000.00 32,160,000.00 1.00 1.00 1,600,000.00 33,760,000.00 6,240,000.00
- Laptop-2 1.00 25.00 Bln 1,600,000.00 40,000,000.00 32,160,000.00 1.00 1.00 1,600,000.00 33,760,000.00 6,240,000.00
- Printer A3 1.00 25.00 Bln 700,000.00 17,500,000.00 14,070,000.00 1.00 1.00 700,000.00 14,770,000.00 2,730,000.00
- Printer A4 1.00 25.00 Bln 500,000.00 12,500,000.00 10,050,000.00 1.00 1.00 500,000.00 10,550,000.00 1,950,000.00
Komunikasi (Pulsa Telepon + lnternet) 1.00 25.00 Bln 1,500,000.00 37,500,000.00 30,150,000.00 1.00 1.00 1,500,000.00 31,650,000.00 5,850,000.00
Bahan untuk peralatan kantor 1.00 25.00 Bln 1,000,000.00 25,000,000.00 20,100,000.00 1.00 1.00 1,000,000.00 21,100,000.00 3,900,000.00

Sub Total c 335,000,000.00 269,340,000.00 13,400,000.00 282,740,000.00 52,260,000.00


d BIAYA PELAPORAN
Laporan RMK 5.00 5.00 Eks 150,000.00 750,000.00 750,000.00 - - - 750,000.00 -
Laporan Pendahuluan 5.00 5.00 Eks 150,000.00 750,000.00 750,000.00 - - - 750,000.00 -
Laporan Bulanan 125.00 5.00 Eks 100,000.00 12,500,000.00 10,000,000.00 5.00 1.00 500,000.00 10,500,000.00 2,000,000.00
Laporan Triwulan 40.00 5.00 Eks 250,000.00 10,000,000.00 8,750,000.00 - - - 8,750,000.00 1,250,000.00
Laporan Akhir 5.00 5.00 Eks 250,000.00 1,250,000.00 - - - - - 1,250,000.00
Hard Disk (File Laporan dan Dokumentasi) 1.00 1.00 Buah 1,000,000.00 1,000,000.00 - - - - - 1,000,000.00

Sub Total d 26,250,000.00 20,250,000.00 500,000.00 20,750,000.00 5,500,000.00


e BIAYA AKOMODASI
- Biaya Sewa
Sewa Mobil Double Gardan-1 1.00 25.00 Bln 25,000,000.00 625,000,000.00 502,500,000.00 1.00 1.00 25,000,000.00 527,500,000.00 97,500,000.00
Sewa Motor Lapangan -1 1.00 25.00 Bln 2,500,000.00 62,500,000.00 50,250,000.00 1.00 1.00 2,500,000.00 52,750,000.00 9,750,000.00
Sewa Motor Lapangan -2 1.00 25.00 Bln 2,500,000.00 62,500,000.00 50,250,000.00 1.00 1.00 2,500,000.00 52,750,000.00 9,750,000.00
- Tunjangan Perumahan
Site Supervision Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 20,100,000.00 1.00 1.00 1,000,000.00 21,100,000.00 3,900,000.00
Quality Engineer-1 1.00 24.00 Bln 1,000,000.00 24,000,000.00 19,070,000.00 1.00 1.00 1,000,000.00 20,070,000.00 3,930,000.00
Inspection Engineer/Quantity Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 20,100,000.00 1.00 1.00 1,000,000.00 21,100,000.00 3,900,000.00
Health Safety Enviroment Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 20,100,000.00 1.00 1.00 1,000,000.00 21,100,000.00 3,900,000.00
Inspector -1 1.00 23.00 Bln 750,000.00 17,250,000.00 13,575,000.00 1.00 1.00 750,000.00 14,325,000.00 2,925,000.00
Surveyor Technician -1 1.00 25.00 Bln 750,000.00 18,750,000.00 15,075,000.00 1.00 1.00 750,000.00 15,825,000.00 2,925,000.00
Material Technician -1 1.00 24.00 Bln 750,000.00 18,000,000.00 14,302,500.00 1.00 1.00 750,000.00 15,052,500.00 2,947,500.00

Sub Total e 903,000,000.00 725,322,500.00 36,250,000.00 761,572,500.00 141,427,500.00

Sub Total a+b+c+d+e 1,285,850,000.00 1,014,912,500.00 50,150,000.00 1,065,062,500.00 220,787,500.00


LAPORAN BULANAN KEADAAN DANA
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Juni 2022 / Invoice 23
TANGGAL : 01 Juli 2022
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

NO. JLH. PEMBAYARAN TAGIHAN INVOICE JLH. PEMBAYARAN SISA DANA


URAIAN TOTAL DANA
S/D BULAN LALU NO. 23 S/D BULAN INI Rp.

I. BIAYA LANGSUNG PERSONIL 4,166,344,500.00 3,504,425,985.00 169,389,000.00 3,673,814,985.00 492,529,515.00


-
II. BIAYA LANGSUNG NON PERSONIL 1,285,850,000.00 1,065,062,500.00 50,150,000.00 1,115,212,500.00 170,637,500.00
BIAYA MOBILISASI DAN DEMOBILISASI - - - - -
BIAYA PERJALANAN DINAS 21,600,000.00 - - - 21,600,000.00
BIAYA KANTOR 335,000,000.00 282,740,000.00 13,400,000.00 296,140,000.00 38,860,000.00
BIAYA PELAPORAN 26,250,000.00 20,750,000.00 500,000.00 21,250,000.00 5,000,000.00
BIAYA AKOMODASI 903,000,000.00 761,572,500.00 36,250,000.00 797,822,500.00 105,177,500.00

SUB TOTAL (I+II) 5,452,194,500.00 4,569,488,485.00 219,539,000.00 4,789,027,485.00 663,167,015.00


PPN 545,219,450.00 456,948,848.50 21,953,900.00 478,902,748.50 66,316,701.50
SUB TOTAL 5,997,413,950.00 5,026,437,333.50 241,492,900.00 5,267,930,233.50 729,483,716.50
NILAI KONTRAK DIBULATKAN 5,997,413,000.00
PENGEMBALIAN UANG MUKA 899,611,950.00 899,611,950.00 - 899,611,950.00 -
TOTAL 5,097,801,050.00 4,126,825,383.50 241,492,900.00 4,368,318,283.50 729,483,716.50
DIBULATKAN 4,126,825,383.00 241,492,900.00 4,368,318,283.00 729,483,717.00

1,199,482,600.00

Jayapura, 01 Juli 2022

PPK PENGAWASAN Konsultan Supervisi


SATKER P2JN PROVINSI PAPUA (JAYAPURA)
PT. WINSOLUSI KONSULTAN

SAM RANDA, S.T, M.Eng ISNAINI SYAWIK, ST


NIP. 19830422 200801 1 006 Direktur Utama
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Juni 2022 / Invoice 23
TANGGAL : 01 Juli 2022
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

REKAPITULASI INVOICE

NO. URAIAN BIAYA (Rp.)

I. BIAYA LANGSUNG PERSONIL 169,389,000.00

II. BIAYA LANGSUNG NON PERSONIL 50,150,000.00


BIAYA MOBILISASI DAN DEMOBILISASI -
BIAYA PERJALANAN DINAS -
BIAYA KANTOR 13,400,000.00
BIAYA PELAPORAN 500,000.00
BIAYA AKOMODASI 36,250,000.00

SUB TOTAL ( I + II ) 219,539,000.00


PPN 10% 21,953,900.00
SUB TOTAL 241,492,900.00
PENGEMBALIAN UANG MUKA 15% -
TOTAL 241,492,900.00
DIBULATKAN 241,492,900.00

Total Pembayaran pada Tagihan ini Rp. 241,492,900.00


Terbilang : Err:511

Mohon Tagihan untuk bulan Juni 2022 dimasukan pada rekening PT. WINSOLUSI KONSULTAN Nomor Rekening :
0416.01.000160.300 BRI Cabang Kelapa Gading 2

Jayapura, 01 Juli 2022


PPK PENGAWASAN Konsultan Supervisi
SATKER P2JN PROVINSI PAPUA (JAYAPURA)
PT. WINSOLUSI KONSULTAN

SAM RANDA, S.T, M.Eng ISNAINI SYAWIK, ST


NIP. 19830422 200801 1 006 Direktur Utama
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Juni 2022 / Invoice 23
TANGGAL : 01 Juli 2022
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

I. BIAYA LANGSUNG PERSONIL


HARGA JUMLAH HARGA PEMBAYARAN TAGIHAN INVOICE NO. 23 PEMBAYARAN
URAIAN SATUAN S/D (Bulan Juni 2022) S/D SISA DANA
NO. JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU ORANG WAKTU/ JUMLAH BULAN INI
(Rp) BULAN (RP) (Rp) (Rp)
a BIAYA TENAGA AHLI
Site Supervision Engineer 1.00 25.00 OB 32,697,000.00 817,425,000.00 689,906,700.00 1.00 1.00 32,697,000.00 722,603,700.00 94,821,300.00
Quality Engineer-1 1.00 24.00 OB 30,880,500.00 741,132,000.00 619,771,635.00 1.00 1.00 30,880,500.00 650,652,135.00 90,479,865.00
Inspection Engineer/Quantity Engineer 1.00 25.00 OB 30,880,500.00 772,012,500.00 651,578,550.00 1.00 1.00 30,880,500.00 682,459,050.00 89,553,450.00
Health Safety Enviroment Engineer 1.00 25.00 OB 25,431,000.00 635,775,000.00 536,594,100.00 1.00 1.00 25,431,000.00 562,025,100.00 73,749,900.00

Sub Total a 2,966,344,500.00 2,497,850,985.00 119,889,000.00 2,617,739,985.00 348,604,515.00


b BIAYA ASISTEN TENAGA AHLI
Inspector -1 1.00 23.00 OB 12,500,000.00 287,500,000.00 238,750,000.00 1.00 1.00 12,500,000.00 251,250,000.00 36,250,000.00
Surveyor Technician -1 1.00 25.00 OB 12,500,000.00 312,500,000.00 263,750,000.00 1.00 1.00 12,500,000.00 276,250,000.00 36,250,000.00
Material Technician -1 1.00 24.00 OB 12,500,000.00 300,000,000.00 250,875,000.00 1.00 1.00 12,500,000.00 263,375,000.00 36,625,000.00
Sub Total b 900,000,000.00 753,375,000.00 37,500,000.00 790,875,000.00 109,125,000.00
c BIAYA STAF PENDUKUNG
Operator Komputer 1.00 25.00 OB 8,000,000.00 200,000,000.00 168,800,000.00 1.00 1.00 8,000,000.00 176,800,000.00 23,200,000.00
Pesuruh/Penjaga Kantor 1.00 25.00 OB 4,000,000.00 100,000,000.00 84,400,000.00 1.00 1.00 4,000,000.00 88,400,000.00 11,600,000.00
Sub Total c 300,000,000.00 253,200,000.00 12,000,000.00 265,200,000.00 34,800,000.00

TOTAL a+b+c 4,166,344,500.00 3,504,425,985.00 - - 169,389,000.00 3,673,814,985.00 492,529,515.00


NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Juni 2022 / Invoice 23
TANGGAL : 01 Juli 2022
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

II. BIAYA LANGSUNG NON PERSONIL


HARGA PEMBAYARAN TAGIHAN INVOICE NO. 23 PEMBAYARAN
JUMLAH HARGA
SATUAN S/D (Bulan Juni 2022) S/D SISA DANA
NO. URAIAN JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU JUMLAH BULAN INI
ORANG TRIP
(Rp) (RP) (Rp) (Rp)
a MOBILISASI DAN DEMOBILISASI
- Mobilisasi
Site Supervision Engineer - - Trip - - - - - - - -
Quality Engineer-1 - - Trip - - - - - - - -
Inspection Engineer/Quantity Engineer - - Trip - - - - - - - -
Health Safety Enviroment Engineer - - - - - - - - - -
- Demobilisasi
Site Supervision Engineer - - Trip - - - - - - - -
Quality Engineer-1 - - Trip - - - - - - - -
Inspection Engineer/Quantity Engineer - - Trip - - - - - - - -
Health Safety Enviroment Engineer - - Trip - - - - - - - -
Sub Total a - - - - -
b BIAYA PERJALANAN DINAS
Tiket Perjalanan (PP) Termasuk Ongkos Taxi 6.00 Trip 2,000,000.00 12,000,000.00 - - - - - 12,000,000.00
Biaya Penginapan 24.00 Hari 400,000.00 9,600,000.00 - - - - - 9,600,000.00

Sub Total b 21,600,000.00 - - - 21,600,000.00


HARGA PEMBAYARAN TAGIHAN INVOICE NO. 23 PEMBAYARAN
SATUAN JUMLAH HARGA S/D (Bulan Juni 2022) S/D SISA DANA
NO. URAIAN JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU JUMLAH BULAN INI
VOLUME BULAN
(Rp) (RP) (Rp) (Rp)
c BIAYA KANTOR
Sewa Kantor 1.00 25.00 Bln 5,000,000.00 125,000,000.00 105,500,000.00 1.00 1.00 5,000,000.00 110,500,000.00 14,500,000.00
Sewa Operasional Kantor (Air dan Listrik) 1.00 25.00 Bln 1,500,000.00 37,500,000.00 31,650,000.00 1.00 1.00 1,500,000.00 33,150,000.00 4,350,000.00
Sewa Penunjang Kantor :
- Laptop-1 1.00 25.00 Bln 1,600,000.00 40,000,000.00 33,760,000.00 1.00 1.00 1,600,000.00 35,360,000.00 4,640,000.00
- Laptop-2 1.00 25.00 Bln 1,600,000.00 40,000,000.00 33,760,000.00 1.00 1.00 1,600,000.00 35,360,000.00 4,640,000.00
- Printer A3 1.00 25.00 Bln 700,000.00 17,500,000.00 14,770,000.00 1.00 1.00 700,000.00 15,470,000.00 2,030,000.00
- Printer A4 1.00 25.00 Bln 500,000.00 12,500,000.00 10,550,000.00 1.00 1.00 500,000.00 11,050,000.00 1,450,000.00
Komunikasi (Pulsa Telepon + lnternet) 1.00 25.00 Bln 1,500,000.00 37,500,000.00 31,650,000.00 1.00 1.00 1,500,000.00 33,150,000.00 4,350,000.00
Bahan untuk peralatan kantor 1.00 25.00 Bln 1,000,000.00 25,000,000.00 21,100,000.00 1.00 1.00 1,000,000.00 22,100,000.00 2,900,000.00

Sub Total c 335,000,000.00 282,740,000.00 13,400,000.00 296,140,000.00 38,860,000.00


d BIAYA PELAPORAN
Laporan RMK 5.00 5.00 Eks 150,000.00 750,000.00 750,000.00 - - - 750,000.00 -
Laporan Pendahuluan 5.00 5.00 Eks 150,000.00 750,000.00 750,000.00 - - - 750,000.00 -
Laporan Bulanan 125.00 5.00 Eks 100,000.00 12,500,000.00 10,500,000.00 5.00 1.00 500,000.00 11,000,000.00 1,500,000.00
Laporan Triwulan 40.00 5.00 Eks 250,000.00 10,000,000.00 8,750,000.00 - - - 8,750,000.00 1,250,000.00
Laporan Akhir 5.00 5.00 Eks 250,000.00 1,250,000.00 - - - - - 1,250,000.00
Hard Disk (File Laporan dan Dokumentasi) 1.00 1.00 Buah 1,000,000.00 1,000,000.00 - - - - - 1,000,000.00

Sub Total d 26,250,000.00 20,750,000.00 500,000.00 21,250,000.00 5,000,000.00


e BIAYA AKOMODASI
- Biaya Sewa
Sewa Mobil Double Gardan-1 1.00 25.00 Bln 25,000,000.00 625,000,000.00 527,500,000.00 1.00 1.00 25,000,000.00 552,500,000.00 72,500,000.00
Sewa Motor Lapangan -1 1.00 25.00 Bln 2,500,000.00 62,500,000.00 52,750,000.00 1.00 1.00 2,500,000.00 55,250,000.00 7,250,000.00
Sewa Motor Lapangan -2 1.00 25.00 Bln 2,500,000.00 62,500,000.00 52,750,000.00 1.00 1.00 2,500,000.00 55,250,000.00 7,250,000.00
- Tunjangan Perumahan
Site Supervision Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 21,100,000.00 1.00 1.00 1,000,000.00 22,100,000.00 2,900,000.00
Quality Engineer-1 1.00 24.00 Bln 1,000,000.00 24,000,000.00 20,070,000.00 1.00 1.00 1,000,000.00 21,070,000.00 2,930,000.00
Inspection Engineer/Quantity Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 21,100,000.00 1.00 1.00 1,000,000.00 22,100,000.00 2,900,000.00
Health Safety Enviroment Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 21,100,000.00 1.00 1.00 1,000,000.00 22,100,000.00 2,900,000.00
Inspector -1 1.00 23.00 Bln 750,000.00 17,250,000.00 14,325,000.00 1.00 1.00 750,000.00 15,075,000.00 2,175,000.00
Surveyor Technician -1 1.00 25.00 Bln 750,000.00 18,750,000.00 15,825,000.00 1.00 1.00 750,000.00 16,575,000.00 2,175,000.00
Material Technician -1 1.00 24.00 Bln 750,000.00 18,000,000.00 15,052,500.00 1.00 1.00 750,000.00 15,802,500.00 2,197,500.00

Sub Total e 903,000,000.00 761,572,500.00 36,250,000.00 797,822,500.00 105,177,500.00

Sub Total a+b+c+d+e 1,285,850,000.00 1,065,062,500.00 50,150,000.00 1,115,212,500.00 170,637,500.00


LAPORAN BULANAN KEADAAN DANA
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Juli 2022 / Invoice 24
TANGGAL : 01 Agustus 2022
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

NO. JLH. PEMBAYARAN TAGIHAN INVOICE JLH. PEMBAYARAN SISA DANA


URAIAN TOTAL DANA
S/D BULAN LALU NO. 24 S/D BULAN INI Rp.

I. BIAYA LANGSUNG PERSONIL 4,166,344,500.00 3,673,814,985.00 169,389,000.00 3,843,203,985.00 323,140,515.00


-
II. BIAYA LANGSUNG NON PERSONIL 1,285,850,000.00 1,115,212,500.00 51,400,000.00 1,166,612,500.00 119,237,500.00
BIAYA MOBILISASI DAN DEMOBILISASI - - - - -
BIAYA PERJALANAN DINAS 21,600,000.00 - - - 21,600,000.00
BIAYA KANTOR 335,000,000.00 296,140,000.00 13,400,000.00 309,540,000.00 25,460,000.00
BIAYA PELAPORAN 26,250,000.00 21,250,000.00 1,750,000.00 23,000,000.00 3,250,000.00
BIAYA AKOMODASI 903,000,000.00 797,822,500.00 36,250,000.00 834,072,500.00 68,927,500.00

SUB TOTAL (I+II) 5,452,194,500.00 4,789,027,485.00 220,789,000.00 5,009,816,485.00 442,378,015.00


PPN 545,219,450.00 478,902,748.50 22,078,900.00 500,981,648.50 44,237,801.50
SUB TOTAL 5,997,413,950.00 5,267,930,233.50 242,867,900.00 5,510,798,133.50 486,615,816.50
NILAI KONTRAK DIBULATKAN 5,997,413,000.00
PENGEMBALIAN UANG MUKA 899,611,950.00 899,611,950.00 - 899,611,950.00 -
TOTAL 5,097,801,050.00 4,368,318,283.50 242,867,900.00 4,611,186,183.50 486,615,816.50
DIBULATKAN 4,368,318,283.00 242,867,900.00 4,611,186,183.00 486,615,817.00

1,199,482,600.00

Jayapura, 01 Agustus 2022

PPK PENGAWASAN Konsultan Supervisi


SATKER P2JN PROVINSI PAPUA (JAYAPURA)
PT. WINSOLUSI KONSULTAN

SAM RANDA, S.T, M.Eng ISNAINI SYAWIK, ST


NIP. 19830422 200801 1 006 Direktur Utama
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Juli 2022 / Invoice 24
TANGGAL : 01 Agustus 2022
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

REKAPITULASI INVOICE

NO. URAIAN BIAYA (Rp.)

I. BIAYA LANGSUNG PERSONIL 169,389,000.00

II. BIAYA LANGSUNG NON PERSONIL 51,400,000.00


BIAYA MOBILISASI DAN DEMOBILISASI -
BIAYA PERJALANAN DINAS -
BIAYA KANTOR 13,400,000.00
BIAYA PELAPORAN 1,750,000.00
BIAYA AKOMODASI 36,250,000.00

SUB TOTAL ( I + II ) 220,789,000.00


PPN 10% 22,078,900.00
SUB TOTAL 242,867,900.00
PENGEMBALIAN UANG MUKA 15% -
TOTAL 242,867,900.00
DIBULATKAN 242,867,900.00

Total Pembayaran pada Tagihan ini Rp. 242,867,900.00


Terbilang : Err:511

Mohon Tagihan untuk bulan Juli 2022 dimasukan pada rekening PT. WINSOLUSI KONSULTAN Nomor Rekening :
0416.01.000160.300 BRI Cabang Kelapa Gading 2

Jayapura, 01 Agustus 2022


PPK PENGAWASAN Konsultan Supervisi
SATKER P2JN PROVINSI PAPUA (JAYAPURA)
PT. WINSOLUSI KONSULTAN

SAM RANDA, S.T, M.Eng ISNAINI SYAWIK, ST


NIP. 19830422 200801 1 006 Direktur Utama
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Juli 2022 / Invoice 24
TANGGAL : 01 Agustus 2022
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

I. BIAYA LANGSUNG PERSONIL


HARGA JUMLAH HARGA PEMBAYARAN TAGIHAN INVOICE NO. 24 PEMBAYARAN
URAIAN SATUAN S/D (Bulan Juli 2022) S/D SISA DANA
NO. JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU ORANG WAKTU/ JUMLAH BULAN INI
(Rp) BULAN (RP) (Rp) (Rp)
a BIAYA TENAGA AHLI
Site Supervision Engineer 1.00 25.00 OB 32,697,000.00 817,425,000.00 722,603,700.00 1.00 1.00 32,697,000.00 755,300,700.00 62,124,300.00
Quality Engineer-1 1.00 24.00 OB 30,880,500.00 741,132,000.00 650,652,135.00 1.00 1.00 30,880,500.00 681,532,635.00 59,599,365.00
Inspection Engineer/Quantity Engineer 1.00 25.00 OB 30,880,500.00 772,012,500.00 682,459,050.00 1.00 1.00 30,880,500.00 713,339,550.00 58,672,950.00
Health Safety Enviroment Engineer 1.00 25.00 OB 25,431,000.00 635,775,000.00 562,025,100.00 1.00 1.00 25,431,000.00 587,456,100.00 48,318,900.00

Sub Total a 2,966,344,500.00 2,617,739,985.00 119,889,000.00 2,737,628,985.00 228,715,515.00


b BIAYA ASISTEN TENAGA AHLI
Inspector -1 1.00 23.00 OB 12,500,000.00 287,500,000.00 251,250,000.00 1.00 1.00 12,500,000.00 263,750,000.00 23,750,000.00
Surveyor Technician -1 1.00 25.00 OB 12,500,000.00 312,500,000.00 276,250,000.00 1.00 1.00 12,500,000.00 288,750,000.00 23,750,000.00
Material Technician -1 1.00 24.00 OB 12,500,000.00 300,000,000.00 263,375,000.00 1.00 1.00 12,500,000.00 275,875,000.00 24,125,000.00
Sub Total b 900,000,000.00 790,875,000.00 37,500,000.00 828,375,000.00 71,625,000.00
c BIAYA STAF PENDUKUNG
Operator Komputer 1.00 25.00 OB 8,000,000.00 200,000,000.00 176,800,000.00 1.00 1.00 8,000,000.00 184,800,000.00 15,200,000.00
Pesuruh/Penjaga Kantor 1.00 25.00 OB 4,000,000.00 100,000,000.00 88,400,000.00 1.00 1.00 4,000,000.00 92,400,000.00 7,600,000.00
Sub Total c 300,000,000.00 265,200,000.00 12,000,000.00 277,200,000.00 22,800,000.00

TOTAL a+b+c 4,166,344,500.00 3,673,814,985.00 - - 169,389,000.00 3,843,203,985.00 323,140,515.00


NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Juli 2022 / Invoice 24
TANGGAL : 01 Agustus 2022
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

II. BIAYA LANGSUNG NON PERSONIL


HARGA PEMBAYARAN TAGIHAN INVOICE NO. 24 PEMBAYARAN
JUMLAH HARGA
SATUAN S/D (Bulan Juli 2022) S/D SISA DANA
NO. URAIAN JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU JUMLAH BULAN INI
ORANG TRIP
(Rp) (RP) (Rp) (Rp)
a MOBILISASI DAN DEMOBILISASI
- Mobilisasi
Site Supervision Engineer - - Trip - - - - - - - -
Quality Engineer-1 - - Trip - - - - - - - -
Inspection Engineer/Quantity Engineer - - Trip - - - - - - - -
Health Safety Enviroment Engineer - - - - - - - - - -
- Demobilisasi
Site Supervision Engineer - - Trip - - - - - - - -
Quality Engineer-1 - - Trip - - - - - - - -
Inspection Engineer/Quantity Engineer - - Trip - - - - - - - -
Health Safety Enviroment Engineer - - Trip - - - - - - - -
Sub Total a - - - - -
b BIAYA PERJALANAN DINAS
Tiket Perjalanan (PP) Termasuk Ongkos Taxi 6.00 Trip 2,000,000.00 12,000,000.00 - - - - - 12,000,000.00
Biaya Penginapan 24.00 Hari 400,000.00 9,600,000.00 - - - - - 9,600,000.00

Sub Total b 21,600,000.00 - - - 21,600,000.00


HARGA PEMBAYARAN TAGIHAN INVOICE NO. 24 PEMBAYARAN
SATUAN JUMLAH HARGA S/D (Bulan Juli 2022) S/D SISA DANA
NO. URAIAN JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU JUMLAH BULAN INI
VOLUME BULAN
(Rp) (RP) (Rp) (Rp)
c BIAYA KANTOR
Sewa Kantor 1.00 25.00 Bln 5,000,000.00 125,000,000.00 110,500,000.00 1.00 1.00 5,000,000.00 115,500,000.00 9,500,000.00
Sewa Operasional Kantor (Air dan Listrik) 1.00 25.00 Bln 1,500,000.00 37,500,000.00 33,150,000.00 1.00 1.00 1,500,000.00 34,650,000.00 2,850,000.00
Sewa Penunjang Kantor :
- Laptop-1 1.00 25.00 Bln 1,600,000.00 40,000,000.00 35,360,000.00 1.00 1.00 1,600,000.00 36,960,000.00 3,040,000.00
- Laptop-2 1.00 25.00 Bln 1,600,000.00 40,000,000.00 35,360,000.00 1.00 1.00 1,600,000.00 36,960,000.00 3,040,000.00
- Printer A3 1.00 25.00 Bln 700,000.00 17,500,000.00 15,470,000.00 1.00 1.00 700,000.00 16,170,000.00 1,330,000.00
- Printer A4 1.00 25.00 Bln 500,000.00 12,500,000.00 11,050,000.00 1.00 1.00 500,000.00 11,550,000.00 950,000.00
Komunikasi (Pulsa Telepon + lnternet) 1.00 25.00 Bln 1,500,000.00 37,500,000.00 33,150,000.00 1.00 1.00 1,500,000.00 34,650,000.00 2,850,000.00
Bahan untuk peralatan kantor 1.00 25.00 Bln 1,000,000.00 25,000,000.00 22,100,000.00 1.00 1.00 1,000,000.00 23,100,000.00 1,900,000.00

Sub Total c 335,000,000.00 296,140,000.00 13,400,000.00 309,540,000.00 25,460,000.00


d BIAYA PELAPORAN
Laporan RMK 5.00 5.00 Eks 150,000.00 750,000.00 750,000.00 - - - 750,000.00 -
Laporan Pendahuluan 5.00 5.00 Eks 150,000.00 750,000.00 750,000.00 - - - 750,000.00 -
Laporan Bulanan 125.00 5.00 Eks 100,000.00 12,500,000.00 11,000,000.00 5.00 1.00 500,000.00 11,500,000.00 1,000,000.00
Laporan Triwulan 40.00 5.00 Eks 250,000.00 10,000,000.00 8,750,000.00 5.00 1.00 1,250,000.00 10,000,000.00 -
Laporan Akhir 5.00 5.00 Eks 250,000.00 1,250,000.00 - - - - - 1,250,000.00
Hard Disk (File Laporan dan Dokumentasi) 1.00 1.00 Buah 1,000,000.00 1,000,000.00 - - - - - 1,000,000.00

Sub Total d 26,250,000.00 21,250,000.00 1,750,000.00 23,000,000.00 3,250,000.00


e BIAYA AKOMODASI
- Biaya Sewa
Sewa Mobil Double Gardan-1 1.00 25.00 Bln 25,000,000.00 625,000,000.00 552,500,000.00 1.00 1.00 25,000,000.00 577,500,000.00 47,500,000.00
Sewa Motor Lapangan -1 1.00 25.00 Bln 2,500,000.00 62,500,000.00 55,250,000.00 1.00 1.00 2,500,000.00 57,750,000.00 4,750,000.00
Sewa Motor Lapangan -2 1.00 25.00 Bln 2,500,000.00 62,500,000.00 55,250,000.00 1.00 1.00 2,500,000.00 57,750,000.00 4,750,000.00
- Tunjangan Perumahan
Site Supervision Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 22,100,000.00 1.00 1.00 1,000,000.00 23,100,000.00 1,900,000.00
Quality Engineer-1 1.00 24.00 Bln 1,000,000.00 24,000,000.00 21,070,000.00 1.00 1.00 1,000,000.00 22,070,000.00 1,930,000.00
Inspection Engineer/Quantity Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 22,100,000.00 1.00 1.00 1,000,000.00 23,100,000.00 1,900,000.00
Health Safety Enviroment Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 22,100,000.00 1.00 1.00 1,000,000.00 23,100,000.00 1,900,000.00
Inspector -1 1.00 23.00 Bln 750,000.00 17,250,000.00 15,075,000.00 1.00 1.00 750,000.00 15,825,000.00 1,425,000.00
Surveyor Technician -1 1.00 25.00 Bln 750,000.00 18,750,000.00 16,575,000.00 1.00 1.00 750,000.00 17,325,000.00 1,425,000.00
Material Technician -1 1.00 24.00 Bln 750,000.00 18,000,000.00 15,802,500.00 1.00 1.00 750,000.00 16,552,500.00 1,447,500.00

Sub Total e 903,000,000.00 797,822,500.00 36,250,000.00 834,072,500.00 68,927,500.00

Sub Total a+b+c+d+e 1,285,850,000.00 1,115,212,500.00 51,400,000.00 1,166,612,500.00 119,237,500.00


LAPORAN BULANAN KEADAAN DANA
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Agustus 2022 / Invoice 25
TANGGAL : 01 September 2022
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

NO. JLH. PEMBAYARAN TAGIHAN INVOICE JLH. PEMBAYARAN SISA DANA


URAIAN TOTAL DANA
S/D BULAN LALU NO. 25 S/D BULAN INI Rp.

I. BIAYA LANGSUNG PERSONIL 4,166,344,500.00 3,843,203,985.00 169,389,000.00 4,012,592,985.00 153,751,515.00


-
II. BIAYA LANGSUNG NON PERSONIL 1,285,850,000.00 1,166,612,500.00 50,150,000.00 1,216,762,500.00 69,087,500.00
BIAYA MOBILISASI DAN DEMOBILISASI - - - - -
BIAYA PERJALANAN DINAS 21,600,000.00 - - - 21,600,000.00
BIAYA KANTOR 335,000,000.00 309,540,000.00 13,400,000.00 322,940,000.00 12,060,000.00
BIAYA PELAPORAN 26,250,000.00 23,000,000.00 500,000.00 23,500,000.00 2,750,000.00
BIAYA AKOMODASI 903,000,000.00 834,072,500.00 36,250,000.00 870,322,500.00 32,677,500.00

SUB TOTAL (I+II) 5,452,194,500.00 5,009,816,485.00 219,539,000.00 5,229,355,485.00 222,839,015.00


PPN 545,219,450.00 500,981,648.50 21,953,900.00 522,935,548.50 22,283,901.50
SUB TOTAL 5,997,413,950.00 5,510,798,133.50 241,492,900.00 5,752,291,033.50 245,122,916.50
NILAI KONTRAK DIBULATKAN 5,997,413,000.00
PENGEMBALIAN UANG MUKA 899,611,950.00 899,611,950.00 - 899,611,950.00 -
TOTAL 5,097,801,050.00 4,611,186,183.50 241,492,900.00 4,852,679,083.50 245,122,916.50
DIBULATKAN 4,611,186,183.00 241,492,900.00 4,852,679,083.00 245,122,917.00

1,199,482,600.00

Jayapura, 01 September 2022

PPK PENGAWASAN Konsultan Supervisi


SATKER P2JN PROVINSI PAPUA (JAYAPURA)
PT. WINSOLUSI KONSULTAN

SAM RANDA, S.T, M.Eng ISNAINI SYAWIK, ST


NIP. 19830422 200801 1 006 Direktur Utama
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Agustus 2022 / Invoice 25
TANGGAL : 01 September 2022
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

REKAPITULASI INVOICE

NO. URAIAN BIAYA (Rp.)

I. BIAYA LANGSUNG PERSONIL 169,389,000.00

II. BIAYA LANGSUNG NON PERSONIL 50,150,000.00


BIAYA MOBILISASI DAN DEMOBILISASI -
BIAYA PERJALANAN DINAS -
BIAYA KANTOR 13,400,000.00
BIAYA PELAPORAN 500,000.00
BIAYA AKOMODASI 36,250,000.00

SUB TOTAL ( I + II ) 219,539,000.00


PPN 10% 21,953,900.00
SUB TOTAL 241,492,900.00
PENGEMBALIAN UANG MUKA 15% -
TOTAL 241,492,900.00
DIBULATKAN 241,492,900.00

Total Pembayaran pada Tagihan ini Rp. 241,492,900.00


Terbilang : Err:511

Mohon Tagihan untuk bulan Agustus 2022 dimasukan pada rekening PT. WINSOLUSI KONSULTAN Nomor Rekening :
0416.01.000160.300 BRI Cabang Kelapa Gading 2

Jayapura, 01 September 2022


PPK PENGAWASAN Konsultan Supervisi
SATKER P2JN PROVINSI PAPUA (JAYAPURA)
PT. WINSOLUSI KONSULTAN

SAM RANDA, S.T, M.Eng ISNAINI SYAWIK, ST


NIP. 19830422 200801 1 006 Direktur Utama
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Agustus 2022 / Invoice 25
TANGGAL : 01 September 2022
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

I. BIAYA LANGSUNG PERSONIL


HARGA JUMLAH HARGA PEMBAYARAN TAGIHAN INVOICE NO. 25 PEMBAYARAN
URAIAN SATUAN S/D (Bulan Agustus 2022) S/D SISA DANA
NO. JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU ORANG WAKTU/ JUMLAH BULAN INI
(Rp) BULAN (RP) (Rp) (Rp)
a BIAYA TENAGA AHLI
Site Supervision Engineer 1.00 25.00 OB 32,697,000.00 817,425,000.00 755,300,700.00 1.00 1.00 32,697,000.00 787,997,700.00 29,427,300.00
Quality Engineer-1 1.00 24.00 OB 30,880,500.00 741,132,000.00 681,532,635.00 1.00 1.00 30,880,500.00 712,413,135.00 28,718,865.00
Inspection Engineer/Quantity Engineer 1.00 25.00 OB 30,880,500.00 772,012,500.00 713,339,550.00 1.00 1.00 30,880,500.00 744,220,050.00 27,792,450.00
Health Safety Enviroment Engineer 1.00 25.00 OB 25,431,000.00 635,775,000.00 587,456,100.00 1.00 1.00 25,431,000.00 612,887,100.00 22,887,900.00

Sub Total a 2,966,344,500.00 2,737,628,985.00 119,889,000.00 2,857,517,985.00 108,826,515.00


b BIAYA ASISTEN TENAGA AHLI
Inspector -1 1.00 23.00 OB 12,500,000.00 287,500,000.00 263,750,000.00 1.00 1.00 12,500,000.00 276,250,000.00 11,250,000.00
Surveyor Technician -1 1.00 25.00 OB 12,500,000.00 312,500,000.00 288,750,000.00 1.00 1.00 12,500,000.00 301,250,000.00 11,250,000.00
Material Technician -1 1.00 24.00 OB 12,500,000.00 300,000,000.00 275,875,000.00 1.00 1.00 12,500,000.00 288,375,000.00 11,625,000.00
Sub Total b 900,000,000.00 828,375,000.00 37,500,000.00 865,875,000.00 34,125,000.00
c BIAYA STAF PENDUKUNG
Operator Komputer 1.00 25.00 OB 8,000,000.00 200,000,000.00 184,800,000.00 1.00 1.00 8,000,000.00 192,800,000.00 7,200,000.00
Pesuruh/Penjaga Kantor 1.00 25.00 OB 4,000,000.00 100,000,000.00 92,400,000.00 1.00 1.00 4,000,000.00 96,400,000.00 3,600,000.00
Sub Total c 300,000,000.00 277,200,000.00 12,000,000.00 289,200,000.00 10,800,000.00

TOTAL a+b+c 4,166,344,500.00 3,843,203,985.00 - - 169,389,000.00 4,012,592,985.00 153,751,515.00


NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : Agustus 2022 / Invoice 25
TANGGAL : 01 September 2022
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

II. BIAYA LANGSUNG NON PERSONIL


HARGA PEMBAYARAN TAGIHAN INVOICE NO. 25 PEMBAYARAN
JUMLAH HARGA
SATUAN S/D (Bulan Agustus 2022) S/D SISA DANA
NO. URAIAN JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU JUMLAH BULAN INI
ORANG TRIP
(Rp) (RP) (Rp) (Rp)
a MOBILISASI DAN DEMOBILISASI
- Mobilisasi
Site Supervision Engineer - - Trip - - - - - - - -
Quality Engineer-1 - - Trip - - - - - - - -
Inspection Engineer/Quantity Engineer - - Trip - - - - - - - -
Health Safety Enviroment Engineer - - - - - - - - - -
- Demobilisasi
Site Supervision Engineer - - Trip - - - - - - - -
Quality Engineer-1 - - Trip - - - - - - - -
Inspection Engineer/Quantity Engineer - - Trip - - - - - - - -
Health Safety Enviroment Engineer - - Trip - - - - - - - -
Sub Total a - - - - -
b BIAYA PERJALANAN DINAS
Tiket Perjalanan (PP) Termasuk Ongkos Taxi 6.00 Trip 2,000,000.00 12,000,000.00 - - - - - 12,000,000.00
Biaya Penginapan 24.00 Hari 400,000.00 9,600,000.00 - - - - - 9,600,000.00

Sub Total b 21,600,000.00 - - - 21,600,000.00


HARGA PEMBAYARAN TAGIHAN INVOICE NO. 25 PEMBAYARAN
SATUAN JUMLAH HARGA S/D (Bulan Agustus 2022) S/D SISA DANA
NO. URAIAN JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU JUMLAH BULAN INI
VOLUME BULAN
(Rp) (RP) (Rp) (Rp)
c BIAYA KANTOR
Sewa Kantor 1.00 25.00 Bln 5,000,000.00 125,000,000.00 115,500,000.00 1.00 1.00 5,000,000.00 120,500,000.00 4,500,000.00
Sewa Operasional Kantor (Air dan Listrik) 1.00 25.00 Bln 1,500,000.00 37,500,000.00 34,650,000.00 1.00 1.00 1,500,000.00 36,150,000.00 1,350,000.00
Sewa Penunjang Kantor :
- Laptop-1 1.00 25.00 Bln 1,600,000.00 40,000,000.00 36,960,000.00 1.00 1.00 1,600,000.00 38,560,000.00 1,440,000.00
- Laptop-2 1.00 25.00 Bln 1,600,000.00 40,000,000.00 36,960,000.00 1.00 1.00 1,600,000.00 38,560,000.00 1,440,000.00
- Printer A3 1.00 25.00 Bln 700,000.00 17,500,000.00 16,170,000.00 1.00 1.00 700,000.00 16,870,000.00 630,000.00
- Printer A4 1.00 25.00 Bln 500,000.00 12,500,000.00 11,550,000.00 1.00 1.00 500,000.00 12,050,000.00 450,000.00
Komunikasi (Pulsa Telepon + lnternet) 1.00 25.00 Bln 1,500,000.00 37,500,000.00 34,650,000.00 1.00 1.00 1,500,000.00 36,150,000.00 1,350,000.00
Bahan untuk peralatan kantor 1.00 25.00 Bln 1,000,000.00 25,000,000.00 23,100,000.00 1.00 1.00 1,000,000.00 24,100,000.00 900,000.00

Sub Total c 335,000,000.00 309,540,000.00 13,400,000.00 322,940,000.00 12,060,000.00


d BIAYA PELAPORAN
Laporan RMK 5.00 5.00 Eks 150,000.00 750,000.00 750,000.00 - - - 750,000.00 -
Laporan Pendahuluan 5.00 5.00 Eks 150,000.00 750,000.00 750,000.00 - - - 750,000.00 -
Laporan Bulanan 125.00 5.00 Eks 100,000.00 12,500,000.00 11,500,000.00 5.00 1.00 500,000.00 12,000,000.00 500,000.00
Laporan Triwulan 40.00 5.00 Eks 250,000.00 10,000,000.00 10,000,000.00 - - - 10,000,000.00 -
Laporan Akhir 5.00 5.00 Eks 250,000.00 1,250,000.00 - - - - - 1,250,000.00
Hard Disk (File Laporan dan Dokumentasi) 1.00 1.00 Buah 1,000,000.00 1,000,000.00 - - - - - 1,000,000.00

Sub Total d 26,250,000.00 23,000,000.00 500,000.00 23,500,000.00 2,750,000.00


e BIAYA AKOMODASI
- Biaya Sewa
Sewa Mobil Double Gardan-1 1.00 25.00 Bln 25,000,000.00 625,000,000.00 577,500,000.00 1.00 1.00 25,000,000.00 602,500,000.00 22,500,000.00
Sewa Motor Lapangan -1 1.00 25.00 Bln 2,500,000.00 62,500,000.00 57,750,000.00 1.00 1.00 2,500,000.00 60,250,000.00 2,250,000.00
Sewa Motor Lapangan -2 1.00 25.00 Bln 2,500,000.00 62,500,000.00 57,750,000.00 1.00 1.00 2,500,000.00 60,250,000.00 2,250,000.00
- Tunjangan Perumahan
Site Supervision Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 23,100,000.00 1.00 1.00 1,000,000.00 24,100,000.00 900,000.00
Quality Engineer-1 1.00 24.00 Bln 1,000,000.00 24,000,000.00 22,070,000.00 1.00 1.00 1,000,000.00 23,070,000.00 930,000.00
Inspection Engineer/Quantity Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 23,100,000.00 1.00 1.00 1,000,000.00 24,100,000.00 900,000.00
Health Safety Enviroment Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 23,100,000.00 1.00 1.00 1,000,000.00 24,100,000.00 900,000.00
Inspector -1 1.00 23.00 Bln 750,000.00 17,250,000.00 15,825,000.00 1.00 1.00 750,000.00 16,575,000.00 675,000.00
Surveyor Technician -1 1.00 25.00 Bln 750,000.00 18,750,000.00 17,325,000.00 1.00 1.00 750,000.00 18,075,000.00 675,000.00
Material Technician -1 1.00 24.00 Bln 750,000.00 18,000,000.00 16,552,500.00 1.00 1.00 750,000.00 17,302,500.00 697,500.00

Sub Total e 903,000,000.00 834,072,500.00 36,250,000.00 870,322,500.00 32,677,500.00

Sub Total a+b+c+d+e 1,285,850,000.00 1,166,612,500.00 50,150,000.00 1,216,762,500.00 69,087,500.00


LAPORAN BULANAN KEADAAN DANA
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : September 2022 / Invoice 26
TANGGAL : 07 September 2022
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

NO. JLH. PEMBAYARAN TAGIHAN INVOICE JLH. PEMBAYARAN SISA DANA


URAIAN TOTAL DANA
S/D BULAN LALU NO. 26 S/D BULAN INI Rp.

I. BIAYA LANGSUNG PERSONIL 4,166,344,500.00 4,012,592,985.00 38,959,470.00 4,051,552,455.00 114,792,045.00


-
II. BIAYA LANGSUNG NON PERSONIL 1,285,850,000.00 1,216,762,500.00 35,269,500.00 1,252,032,000.00 33,818,000.00
BIAYA MOBILISASI DAN DEMOBILISASI - - - - -
BIAYA PERJALANAN DINAS 21,600,000.00 - 21,600,000.00 21,600,000.00 -
BIAYA KANTOR 335,000,000.00 322,940,000.00 3,082,000.00 326,022,000.00 8,978,000.00
BIAYA PELAPORAN 26,250,000.00 23,500,000.00 2,250,000.00 25,750,000.00 500,000.00
BIAYA AKOMODASI 903,000,000.00 870,322,500.00 8,337,500.00 878,660,000.00 24,340,000.00

SUB TOTAL (I+II) 5,452,194,500.00 5,229,355,485.00 74,228,970.00 5,303,584,455.00 148,610,045.00


PPN 545,219,450.00 522,935,548.50 7,422,897.00 530,358,445.50 14,861,004.50
SUB TOTAL 5,997,413,950.00 5,752,291,033.50 81,651,867.00 5,833,942,900.50 163,471,049.50
NILAI KONTRAK DIBULATKAN 5,997,413,000.00
PENGEMBALIAN UANG MUKA 899,611,950.00 899,611,950.00 - 899,611,950.00 -
TOTAL 5,097,801,050.00 4,852,679,083.50 81,651,867.00 4,934,330,950.50 163,471,049.50
DIBULATKAN 4,852,679,083.00 81,651,867.00 4,934,330,950.00 163,471,050.00

1,199,482,600.00

Jayapura, 07 September 2022

PPK PENGAWASAN Konsultan Supervisi


SATKER P2JN PROVINSI PAPUA (JAYAPURA)
PT. WINSOLUSI KONSULTAN

SAM RANDA, S.T, M.Eng ISNAINI SYAWIK, ST


NIP. 19830422 200801 1 006 Direktur Utama
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : September 2022 / Invoice 26
TANGGAL : 07 September 2022
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

REKAPITULASI INVOICE

NO. URAIAN BIAYA (Rp.)

I. BIAYA LANGSUNG PERSONIL 38,959,470.00

II. BIAYA LANGSUNG NON PERSONIL 35,269,500.00


BIAYA MOBILISASI DAN DEMOBILISASI -
BIAYA PERJALANAN DINAS 21,600,000.00
BIAYA KANTOR 3,082,000.00
BIAYA PELAPORAN 2,250,000.00
BIAYA AKOMODASI 8,337,500.00

SUB TOTAL ( I + II ) 74,228,970.00


PPN 10% 7,422,897.00
SUB TOTAL 81,651,867.00
PENGEMBALIAN UANG MUKA 15% -
TOTAL 81,651,867.00
DIBULATKAN 81,651,867.00

Total Pembayaran pada Tagihan ini Rp. 81,651,867.00


Terbilang : Err:511

Mohon Tagihan untuk bulan September 2022 dimasukan pada rekening PT. WINSOLUSI KONSULTAN Nomor Rekening :
0416.01.000160.300 BRI Cabang Kelapa Gading 2

Jayapura, 07 September 2022


PPK PENGAWASAN Konsultan Supervisi
SATKER P2JN PROVINSI PAPUA (JAYAPURA)
PT. WINSOLUSI KONSULTAN

SAM RANDA, S.T, M.Eng ISNAINI SYAWIK, ST


NIP. 19830422 200801 1 006 Direktur Utama
NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : September 2022 / Invoice 26
TANGGAL : 07 September 2022
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

I. BIAYA LANGSUNG PERSONIL


HARGA JUMLAH HARGA PEMBAYARAN TAGIHAN INVOICE NO. 26 PEMBAYARAN
URAIAN SATUAN S/D (Bulan September 2022) S/D SISA DANA
NO. JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU ORANG WAKTU/ JUMLAH BULAN INI
(Rp) BULAN (RP) (Rp) (Rp)
a BIAYA TENAGA AHLI
Site Supervision Engineer 1.00 25.00 OB 32,697,000.00 817,425,000.00 787,997,700.00 1.00 0.23 7,520,310.00 795,518,010.00 21,906,990.00
Quality Engineer-1 1.00 24.00 OB 30,880,500.00 741,132,000.00 712,413,135.00 1.00 0.23 7,102,515.00 719,515,650.00 21,616,350.00
Inspection Engineer/Quantity Engineer 1.00 25.00 OB 30,880,500.00 772,012,500.00 744,220,050.00 1.00 0.23 7,102,515.00 751,322,565.00 20,689,935.00
Health Safety Enviroment Engineer 1.00 25.00 OB 25,431,000.00 635,775,000.00 612,887,100.00 1.00 0.23 5,849,130.00 618,736,230.00 17,038,770.00

Sub Total a 2,966,344,500.00 2,857,517,985.00 27,574,470.00 2,885,092,455.00 81,252,045.00


b BIAYA ASISTEN TENAGA AHLI
Inspector -1 1.00 23.00 OB 12,500,000.00 287,500,000.00 276,250,000.00 1.00 0.23 2,875,000.00 279,125,000.00 8,375,000.00
Surveyor Technician -1 1.00 25.00 OB 12,500,000.00 312,500,000.00 301,250,000.00 1.00 0.23 2,875,000.00 304,125,000.00 8,375,000.00
Material Technician -1 1.00 24.00 OB 12,500,000.00 300,000,000.00 288,375,000.00 1.00 0.23 2,875,000.00 291,250,000.00 8,750,000.00
Sub Total b 900,000,000.00 865,875,000.00 8,625,000.00 874,500,000.00 25,500,000.00
c BIAYA STAF PENDUKUNG
Operator Komputer 1.00 25.00 OB 8,000,000.00 200,000,000.00 192,800,000.00 1.00 0.23 1,840,000.00 194,640,000.00 5,360,000.00
Pesuruh/Penjaga Kantor 1.00 25.00 OB 4,000,000.00 100,000,000.00 96,400,000.00 1.00 0.23 920,000.00 97,320,000.00 2,680,000.00
Sub Total c 300,000,000.00 289,200,000.00 2,760,000.00 291,960,000.00 8,040,000.00

TOTAL a+b+c 4,166,344,500.00 4,012,592,985.00 - - 38,959,470.00 4,051,552,455.00 114,792,045.00


NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020
NO. SPMK DAN TANGGAL : IK.02.04/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
TAGIHAN BULAN / NOMOR : September 2022 / Invoice 26
TANGGAL : 07 September 2022
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)
: - Pembangunan Jalan Memberamo – Elelim II

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

II. BIAYA LANGSUNG NON PERSONIL


HARGA PEMBAYARAN TAGIHAN INVOICE NO. 26 PEMBAYARAN
JUMLAH HARGA
SATUAN S/D (Bulan September 2022) S/D SISA DANA
NO. URAIAN JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU JUMLAH BULAN INI
ORANG TRIP
(Rp) (RP) (Rp) (Rp)
a MOBILISASI DAN DEMOBILISASI
- Mobilisasi
Site Supervision Engineer - - Trip - - - - - - - -
Quality Engineer-1 - - Trip - - - - - - - -
Inspection Engineer/Quantity Engineer - - Trip - - - - - - - -
Health Safety Enviroment Engineer - - - - - - - - - -
- Demobilisasi
Site Supervision Engineer - - Trip - - - - - - - -
Quality Engineer-1 - - Trip - - - - - - - -
Inspection Engineer/Quantity Engineer - - Trip - - - - - - - -
Health Safety Enviroment Engineer - - Trip - - - - - - - -
Sub Total a - - - - -
b BIAYA PERJALANAN DINAS
Tiket Perjalanan (PP) Termasuk Ongkos Taxi 6.00 Trip 2,000,000.00 12,000,000.00 - 3.00 2.00 12,000,000.00 12,000,000.00 -
Biaya Penginapan 24.00 Hari 400,000.00 9,600,000.00 - 3.00 8.00 9,600,000.00 9,600,000.00 -

Sub Total b 21,600,000.00 - 21,600,000.00 21,600,000.00 -


HARGA PEMBAYARAN TAGIHAN INVOICE NO. 26 PEMBAYARAN
SATUAN JUMLAH HARGA S/D (Bulan September 2022) S/D SISA DANA
NO. URAIAN JUMLAH VOLUME SATUAN
(Rp) (Rp) BULAN LALU JUMLAH BULAN INI
VOLUME BULAN
(Rp) (RP) (Rp) (Rp)
c BIAYA KANTOR
Sewa Kantor 1.00 25.00 Bln 5,000,000.00 125,000,000.00 120,500,000.00 1.00 0.23 1,150,000.00 121,650,000.00 3,350,000.00
Sewa Operasional Kantor (Air dan Listrik) 1.00 25.00 Bln 1,500,000.00 37,500,000.00 36,150,000.00 1.00 0.23 345,000.00 36,495,000.00 1,005,000.00
Sewa Penunjang Kantor :
- Laptop-1 1.00 25.00 Bln 1,600,000.00 40,000,000.00 38,560,000.00 1.00 0.23 368,000.00 38,928,000.00 1,072,000.00
- Laptop-2 1.00 25.00 Bln 1,600,000.00 40,000,000.00 38,560,000.00 1.00 0.23 368,000.00 38,928,000.00 1,072,000.00
- Printer A3 1.00 25.00 Bln 700,000.00 17,500,000.00 16,870,000.00 1.00 0.23 161,000.00 17,031,000.00 469,000.00
- Printer A4 1.00 25.00 Bln 500,000.00 12,500,000.00 12,050,000.00 1.00 0.23 115,000.00 12,165,000.00 335,000.00
Komunikasi (Pulsa Telepon + lnternet) 1.00 25.00 Bln 1,500,000.00 37,500,000.00 36,150,000.00 1.00 0.23 345,000.00 36,495,000.00 1,005,000.00
Bahan untuk peralatan kantor 1.00 25.00 Bln 1,000,000.00 25,000,000.00 24,100,000.00 1.00 0.23 230,000.00 24,330,000.00 670,000.00

Sub Total c 335,000,000.00 322,940,000.00 3,082,000.00 326,022,000.00 8,978,000.00


d BIAYA PELAPORAN
Laporan RMK 5.00 5.00 Eks 150,000.00 750,000.00 750,000.00 - - - 750,000.00 -
Laporan Pendahuluan 5.00 5.00 Eks 150,000.00 750,000.00 750,000.00 - - - 750,000.00 -
Laporan Bulanan 125.00 5.00 Eks 100,000.00 12,500,000.00 12,000,000.00 - - - 12,000,000.00 500,000.00
Laporan Triwulan 40.00 5.00 Eks 250,000.00 10,000,000.00 10,000,000.00 - - - 10,000,000.00 -
Laporan Akhir 5.00 5.00 Eks 250,000.00 1,250,000.00 - 5.00 1.00 1,250,000.00 1,250,000.00 -
Hard Disk (File Laporan dan Dokumentasi) 1.00 1.00 Buah 1,000,000.00 1,000,000.00 - 1.00 1.00 1,000,000.00 1,000,000.00 -

Sub Total d 26,250,000.00 23,500,000.00 2,250,000.00 25,750,000.00 500,000.00


e BIAYA AKOMODASI
- Biaya Sewa
Sewa Mobil Double Gardan-1 1.00 25.00 Bln 25,000,000.00 625,000,000.00 602,500,000.00 1.00 0.23 5,750,000.00 608,250,000.00 16,750,000.00
Sewa Motor Lapangan -1 1.00 25.00 Bln 2,500,000.00 62,500,000.00 60,250,000.00 1.00 0.23 575,000.00 60,825,000.00 1,675,000.00
Sewa Motor Lapangan -2 1.00 25.00 Bln 2,500,000.00 62,500,000.00 60,250,000.00 1.00 0.23 575,000.00 60,825,000.00 1,675,000.00
- Tunjangan Perumahan
Site Supervision Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 24,100,000.00 1.00 0.23 230,000.00 24,330,000.00 670,000.00
Quality Engineer-1 1.00 24.00 Bln 1,000,000.00 24,000,000.00 23,070,000.00 1.00 0.23 230,000.00 23,300,000.00 700,000.00
Inspection Engineer/Quantity Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 24,100,000.00 1.00 0.23 230,000.00 24,330,000.00 670,000.00
Health Safety Enviroment Engineer 1.00 25.00 Bln 1,000,000.00 25,000,000.00 24,100,000.00 1.00 0.23 230,000.00 24,330,000.00 670,000.00
Inspector -1 1.00 23.00 Bln 750,000.00 17,250,000.00 16,575,000.00 1.00 0.23 172,500.00 16,747,500.00 502,500.00
Surveyor Technician -1 1.00 25.00 Bln 750,000.00 18,750,000.00 18,075,000.00 1.00 0.23 172,500.00 18,247,500.00 502,500.00
Material Technician -1 1.00 24.00 Bln 750,000.00 18,000,000.00 17,302,500.00 1.00 0.23 172,500.00 17,475,000.00 525,000.00

Sub Total e 903,000,000.00 870,322,500.00 8,337,500.00 878,660,000.00 24,340,000.00

Sub Total a+b+c+d+e 1,285,850,000.00 1,216,762,500.00 35,269,500.00 1,252,032,000.00 33,818,000.00


Kompleks Bina Marga Tanah Hitam Jl.Abepantai Telp. (0967) 587136, Fax. (0967) 587136

BERITA ACARA PEMERIKSAAN PEKERJAAN


No.:

Pekerjaan : PENGAWASAN TEKNIS PEMBANGUNAN JALAN MEMBERAMO - ELELIM II (MYC)


Lokasi : Satker PJN Wilayah I (Jayapura)
Tanggal : 21 Desember 2020

Pada hari ini Senin tanggal Dua Puluh Satu bulan Desember tahun Dua Ribu Dua Puluh, Kami yang bertanda
tangan di bawah ini : PPK Pengawasan Satker Perencanaan dan Pengawasan Jalan Nasional Provinsi Papua
(Jayapura), PENGAWASAN TEKNIS PEMBANGUNAN JALAN MEMBERAMO - ELELIM II (MYC)
yang dilaksanakan oleh PT. WINSOLUSI KONSULTAN berdasarkan Kontrak Nomor :
HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, Tanggal, tanggal 18 Agustus 2020, SPMK Nomor :
IK.02.04/SPMK/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, Tanggal tanggal 19 Agustus 2020

1. NILAI KONTRAK
A. BIAYA LANGSUNG PERSONIL
1. BIAYA TENAGA AHLI : Rp. 2,966,344,500
2. BIAYA ASISTEN TENAGA AHLI : Rp. 900,000,000
3. BIAYA STAFF PENDUKUNG : Rp. 300,000,000

B. BIAYA LANGSUNG NON PERSONIL


1. BIAYA MOBILISASI DAN DEMOBILISASI : Rp. -
2. BIAYA PERJALANAN DINAS : Rp. 21,600,000
3. BIAYA KANTOR : Rp. 335,000,000
4. BIAYA PELAPORAN : Rp. 26,250,000
5. BIAYA AKOMODASI : Rp. 903,000,000

SUB JUMLAH : Rp. 5,452,194,500


PPN 10% : Rp. 545,219,450
JUMLAH : Rp. 5,997,413,950
PEMBULATAN : Rp. 5,997,413,000
2. PEMBAYARAN
Pembiayaan Invoice V bulan Desember 2020 / 05 yang telah dikeluarkan dan dipertanggung jawabkan kepada
Satuan Kerja Perencanaan & Pengawasan Jalan Nasional Propinsi Papua (Jayapura) Tahun Anggaran 2020
Meliputi :
A. BIAYA LANGSUNG PERSONIL
1. BIAYA TENAGA AHLI : Rp. 80,325,630
2. BIAYA ASISTEN TENAGA AHLI : Rp. 25,125,000
3. BIAYA STAFF PENDUKUNG : Rp. 8,040,000
B. BIAYA LANGSUNG NON PERSONIL
1. BIAYA MOBILISASI DAN DEMOBILISASI : Rp. -
2. BIAYA PERJALANAN DINAS : Rp. -
3. BIAYA KANTOR : Rp. 8,978,000
4. BIAYA PELAPORAN : Rp. 500,000
5. BIAYA AKOMODASI : Rp. 24,287,500

SUB JUMLAH : Rp. 147,256,130


PPN 10% : Rp. 14,725,613
JUMLAH : Rp. 161,981,743
PENGEMBALIAN UANG MUKA : Rp. 77,968,399
TOTAL : Rp. 84,013,344
PEMBULATAN : Rp. 84,013,344

Err:511

Jumlah ini akan dibayarkan melalui rekening :

PT. WINSOLUSI KONSULTAN Nomor Rekening : 0416.01.000160.300 BRI Cabang Kelapa Gading 2

Demikian Berita Acara ini dibuat dengan sebenarnya dalam rangkap 7 (tujuh) untuk dipergunakan seperlunya.

PPK PENGAWASAN
PT. WINSOLUSI KONSULTAN
SATKER P2JN PROVINSI PAPUA
(JAYAPURA)

ISNAINI SYAWIK, ST SAM RANDA, S.T, M.Eng


DIREKTUR UTAMA NIP. 19830422 200801 1 006
Kompleks Bina Marga Tanah Hitam Jl.Abepantai Telp. (0967) 587136, Fax. (0967) 587136

BERITA ACARA PEMERIKSAAN PEKERJAAN


No.:

Pekerjaan : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)


Lokasi : Wilayah Satker PJN Wilayah I (Jayapura)
Tanggal : 01 April 2021

Pada hari ini Kamis tanggal Satu bulan April tahun Dua Ribu Dua Puluh Satu, Kami yang bertanda tangan di
bawah ini : PPK Pengawasan Satker Perencanaan dan Pengawasan Jalan Nasional Provinsi Papua (Jayapura),
PENGAWASAN TEKNIS PEMBANGUNAN JALAN MEMBERAMO - ELELIM II (MYC) yang
dilaksanakan oleh PT. WINSOLUSI KONSULTAN berdasarkan Kontrak Nomor :
HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, Tanggal, tanggal 18 Agustus 2020, SPMK Nomor :
IK.02.04/SPMK/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, Tanggal tanggal 19 Agustus 2020

1. NILAI KONTRAK
A. BIAYA LANGSUNG PERSONIL
1. BIAYA TENAGA AHLI : Rp. 2,966,344,500
2. BIAYA ASISTEN TENAGA AHLI : Rp. 900,000,000
3. BIAYA STAFF PENDUKUNG : Rp. 300,000,000

B. BIAYA LANGSUNG NON PERSONIL


1. BIAYA MOBILISASI DAN DEMOBILISASI : Rp. -
2. BIAYA PERJALANAN DINAS : Rp. 21,600,000
3. BIAYA KANTOR : Rp. 335,000,000
4. BIAYA PELAPORAN : Rp. 26,250,000
5. BIAYA AKOMODASI : Rp. 903,000,000

SUB JUMLAH : Rp. 5,452,194,500


PPN 10% : Rp. 545,219,450
JUMLAH : Rp. 5,997,413,950
PEMBULATAN : Rp. 5,997,413,000
2. PEMBAYARAN
Pembiayaan Invoice VIII bulan Maret 2021 / 08 yang telah dikeluarkan dan dipertanggung jawabkan kepada
Satuan Kerja Perencanaan & Pengawasan Jalan Nasional Propinsi Papua (Jayapura) Tahun Anggaran 2020
Meliputi :
A. BIAYA LANGSUNG PERSONIL
1. BIAYA TENAGA AHLI : Rp. 119,889,000
2. BIAYA ASISTEN TENAGA AHLI : Rp. 37,500,000
3. BIAYA STAFF PENDUKUNG : Rp. 12,000,000
B. BIAYA LANGSUNG NON PERSONIL
1. BIAYA MOBILISASI DAN DEMOBILISASI : Rp. -
2. BIAYA PERJALANAN DINAS : Rp. -
3. BIAYA KANTOR : Rp. 13,400,000
4. BIAYA PELAPORAN : Rp. 500,000
5. BIAYA AKOMODASI : Rp. 36,250,000

SUB JUMLAH : Rp. 219,539,000


PPN 10% : Rp. 21,953,900
JUMLAH : Rp. 241,492,900
PENGEMBALIAN UANG MUKA : Rp. 110,351,993
TOTAL : Rp. 131,140,907
PEMBULATAN : Rp. 131,140,907

Err:511

Jumlah ini akan dibayarkan melalui rekening :

PT. WINSOLUSI KONSULTAN Nomor Rekening : 0416.01.000160.300 BRI Cabang Kelapa Gading 2

Demikian Berita Acara ini dibuat dengan sebenarnya dalam rangkap 7 (tujuh) untuk dipergunakan seperlunya.

PPK PENGAWASAN
PT. WINSOLUSI KONSULTAN
SATKER P2JN PROVINSI PAPUA
(JAYAPURA)

ISNAINI SYAWIK, ST SAM RANDA, S.T, M.Eng


DIREKTUR UTAMA NIP. 19830422 200801 1 006
Kompleks Bina Marga Tanah Hitam Jl.Abepantai Telp. (0967) 587136, Fax. (0967) 587136

BERITA ACARA PEMERIKSAAN PEKERJAAN


No.:

Pekerjaan : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)


Lokasi : Wilayah Satker PJN Wilayah I (Jayapura)
Tanggal : 03 Mei 2021

Pada hari ini Senin tanggal Tiga bulan Mei tahun Dua Ribu Dua Puluh Satu, Kami yang bertanda tangan di
bawah ini : PPK Pengawasan Satker Perencanaan dan Pengawasan Jalan Nasional Provinsi Papua (Jayapura),
PENGAWASAN TEKNIS PEMBANGUNAN JALAN MEMBERAMO - ELELIM II (MYC) yang
dilaksanakan oleh PT. WINSOLUSI KONSULTAN berdasarkan Kontrak Nomor :
HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, Tanggal, tanggal 18 Agustus 2020, SPMK Nomor :
IK.02.04/SPMK/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, Tanggal tanggal 19 Agustus 2020

1. NILAI KONTRAK
A. BIAYA LANGSUNG PERSONIL
1. BIAYA TENAGA AHLI : Rp. 2,966,344,500
2. BIAYA ASISTEN TENAGA AHLI : Rp. 900,000,000
3. BIAYA STAFF PENDUKUNG : Rp. 300,000,000

B. BIAYA LANGSUNG NON PERSONIL


1. BIAYA MOBILISASI DAN DEMOBILISASI : Rp. -
2. BIAYA PERJALANAN DINAS : Rp. 21,600,000
3. BIAYA KANTOR : Rp. 335,000,000
4. BIAYA PELAPORAN : Rp. 26,250,000
5. BIAYA AKOMODASI : Rp. 903,000,000

SUB JUMLAH : Rp. 5,452,194,500


PPN 10% : Rp. 545,219,450
JUMLAH : Rp. 5,997,413,950
PEMBULATAN : Rp. 5,997,413,000
2. PEMBAYARAN

Pembiayaan Invoice IX bulan April 2021 / 09 yang telah dikeluarkan dan dipertanggung jawabkan kepada Satuan
Kerja Perencanaan & Pengawasan Jalan Nasional Propinsi Papua (Jayapura) Tahun Anggaran 2021 Meliputi :
A. BIAYA LANGSUNG PERSONIL
1. BIAYA TENAGA AHLI : Rp. 119,889,000
2. BIAYA ASISTEN TENAGA AHLI : Rp. 37,500,000
3. BIAYA STAFF PENDUKUNG : Rp. 12,000,000
B. BIAYA LANGSUNG NON PERSONIL
1. BIAYA MOBILISASI DAN DEMOBILISASI : Rp. -
2. BIAYA PERJALANAN DINAS : Rp. -
3. BIAYA KANTOR : Rp. 13,400,000
4. BIAYA PELAPORAN : Rp. 1,750,000
5. BIAYA AKOMODASI : Rp. 36,250,000

SUB JUMLAH : Rp. 220,789,000


PPN 10% : Rp. 22,078,900
JUMLAH : Rp. 242,867,900
PENGEMBALIAN UANG MUKA : Rp. 110,351,993
TOTAL : Rp. 132,515,907
PEMBULATAN : Rp. 132,515,907

Err:511

Jumlah ini akan dibayarkan melalui rekening :

PT. WINSOLUSI KONSULTAN Nomor Rekening : 0416.01.000160.300 BRI Cabang Kelapa Gading 2

Demikian Berita Acara ini dibuat dengan sebenarnya dalam rangkap 7 (tujuh) untuk dipergunakan seperlunya.

PPK PENGAWASAN
PT. WINSOLUSI KONSULTAN
SATKER P2JN PROVINSI PAPUA
(JAYAPURA)

ISNAINI SYAWIK, ST SAM RANDA, S.T, M.Eng


DIREKTUR UTAMA NIP. 19830422 200801 1 006
Jayapura, 05 Mei 2021

Kepada Yth.
Pejabat Pembuat Komitmen Pengawasan
Satker P2JN Provinsi Papua (Jayapura)
di -
Tempat

FAKTUR TAGIHAN
Nomor : 002/WS/FT/PW.MYC.JL.ME.II/INV.08-09/JPR/V/2021

JUMLAH
NOMOR URAIAN HARGA
( Rp )

1 Invoice VIII (Maret 2021) 131,140,907.00


2 Invoice IX (April 2021) 132,515,907.00

Pekerjaan :
Pengawasan Teknis Pembangunan Jalan Memberamo - Elelim II (MYC)

Berdasarkan :
Kontrak :
HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, Tanggal, tanggal 18 Agustus 2020

SPMK :
IK.02.04/SPMK/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, Tanggal tanggal 19 Agustus 2020

JUMLAH 263,656,814.00

Terbilang : Err:511

PT. WINSOLUSI KONSULTAN

ISNAINI SYAWIK, ST
Direktur Utama
PT. WINSOLUSI KONSULTAN
Management & Engineering
Jalan Letjend. Suprapto Ruko Mega Grosir Cempaka Mas Blok A No. 25
Kel. Sumur Batu Kec. Kemayoran - Jakarta Pusat 10640
Telp. (021) 42884257 / 42884258 Fax. (021) 4281805
Email : winsolusi@gmail.com

TA : 2021
Nomor Bukti :
Akun : 534111

KWITANSI
Nomor : 002/WS/PW.MYC.JL.ME.II/INV.08-09/JPR/V/2021
Sudah Terima dari : Pejabat Pembuat Komitmen Pengawasan
Satuan Kerja Perencanaan Dan Pengawasan Jalan Nasional Provinsi Papua (Jayapura)

Jumlah Uang :
Rp. 263,656,814 263,656,814

Terbilang :
Err:511

Untuk Pembayaran : 01. Invoice VIII (Maret 2021)


02. Invoice IX (April 2021)
Pekerjaan :
Pengawasan Teknis Pembangunan Jalan Memberamo - Elelim II (MYC)
Berdasarkan :
Kontrak :
HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, Tanggal, tanggal 18 Agustus 2020
SPMK :
IK.02.04/SPMK/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, Tanggal tanggal 19 Agustus 2020

Setuju Dibayar Jayapura, 05 Mei 2021


a.n. Kuasa Pengguna Anggaran PT. WINSOLUSI KONSULTAN
Pejabat Pembuat Komitmen Pengawasan
Satuan Kerja Perencanaan Dan Pengawasan Jalan Nasional
Provinsi Papua (Jayapura)

SAM RANDA, S.T, M.Eng ISNAINI SYAWIK, ST


NIP. 19830422 200801 1 006 Direktur Utama

Barang/pekerjaan tersebut telah diterima/diselesaikan dengan lengkap dan baik

Asisten Pengawasan
Pejabat Pembuat Komitmen Pengawasan
Satker P2JN Provinsi Papua (Jayapura)

MITRA TIMANG, ST
NIP. 19940904 201802 2 001
DEPARTEMEN KEUANGAN R.I. SURAT SETORAN PAJAK
DIREKTORAT JENDERAL PAJAK
LEMBAR 1
KANTOR PELAYANAN PAJAK
JAYAPURA (SSP) ARSIP WP

NPWP : 0 2 . 8 6 8 . 9 9 3 . 3 - 0 2 7 . 0 0 0
Diisi sesuai dengan Nomor Pokok Wajib Pajak yang dimiliki

NAMA WP : PT. WINSOLUSI KONSULTAN


ALAMAT : RUKO MEGA GROSIR CEMPAKA MAS BLOK A NO. 25
KEL. SUMUR BATU KEC. KEMAYORAN JAKARTA PUSAT

MAP/Kode Jenis Pajak Kode Jenis setoran Uraian Pembayaran


PPN DN (10%) atas Pembayaran Invoice 08 s/d 09
4 1 1 2 1 1 9 0 0
Pengawasan Teknis Pembangunan Jalan Memberamo - Elelim II (MYC)

Tahun Anggaran 2021

Masa Pajak Tahun


2 0 2 1
Jan Peb Mar Apr Mei Jun Jul Ags Sep Okt Nop Des
Beri tanda silang pada salah astu kolom bulan untuk masa yang berkenaan Diisi tahun terhutangnya pajak

Nomor Ketetapan : / / / /
Diisi sesuai Nomor Ketetapan : STP, SKPKB, SKPKBT

Jumlah Pembayaran Terbilang : Err:511


Diisi dengan rupiah penuh

Rp. 23,968,801

Diterima oleh Kantor Penerima Pembayaran Wajib Pajak/Penyetor


Tanggal, ……………………………. Jayapura, …………………………
Cap dan tanda tangan Cap dan tanda tangan

Nama Jelas : ………………………………………. Isnaini Syawik


Direktur Utama

Ruang Validasi Kantor Penerima Pembayaran

Diisi sesuai buku petunjuk pengisian

F.2.0.32.01
SURAT SETORAN PAJAK
LEMBAR 2
DEPARTEMEN KEUANGAN R.I.
DIREKTORAT JENDERAL PAJAK
KANTOR PELAYANAN PAJAK
JAYAPURA (SSP) UNTUK KPP MELALUI KPPN

NPWP : 0 2 . 8 6 8 . 9 9 3 . 3 - 0 2 7 . 0 0 0
Diisi sesuai dengan Nomor Pokok Wajib Pajak yang dimiliki

NAMA WP : PT. WINSOLUSI KONSULTAN


ALAMAT : RUKO MEGA GROSIR CEMPAKA MAS BLOK A NO. 25
KEL. SUMUR BATU KEC. KEMAYORAN JAKARTA PUSAT

MAP/Kode Jenis Pajak Kode Jenis setoran Uraian Pembayaran


PPN DN (10%) atas Pembayaran Invoice 08 s/d 09
4 1 1 2 1 1 9 0 0 Pengawasan Teknis Pembangunan Jalan Memberamo - Elelim II (MYC)

Tahun Anggaran 2021

Masa Pajak Tahun


2 0 2 1
Jan Peb Mar Apr Mei Jun Jul Ags Sep Okt Nop Des
Beri tanda silang pada salah astu kolom bulan untuk masa yang berkenaan Diisi tahun terhutangnya pajak

Nomor Ketetapan : / / / /
Diisi sesuai Nomor Ketetapan : STP, SKPKB, SKPKBT

Jumlah Pembayaran Terbilang :


Err:511
Diisi dengan rupiah penuh

Rp. 23,968,801

Diterima oleh Kantor Penerima Pembayaran Wajib Pajak/Penyetor


Tanggal, ……………………………. Jayapura, …………………………
Cap dan tanda tangan Cap dan tanda tangan

Nama Jelas : ………………………………………. Isnaini Syawik


Direktur Utama

Ruang Validasi Kantor Penerima Pembayaran

Diisi sesuai buku petunjuk pengisian

F.2.0.32.01
SURAT SETORAN PAJAK
LEMBAR 3
DEPARTEMEN KEUANGAN R.I.
DIREKTORAT JENDERAL PAJAK
KANTOR PELAYANAN PAJAK
JAYAPURA (SSP) UNTUK DILAPORKAN OLEH WP KE KPP

NPWP : 0 2 . 8 6 8 . 9 9 3 . 3 - 0 2 7 . 0 0 0
Diisi sesuai dengan Nomor Pokok Wajib Pajak yang dimiliki

NAMA WP : PT. WINSOLUSI KONSULTAN


ALAMAT : RUKO MEGA GROSIR CEMPAKA MAS BLOK A NO. 25
KEL. SUMUR BATU KEC. KEMAYORAN JAKARTA PUSAT

MAP/Kode Jenis Pajak Kode Jenis setoran Uraian Pembayaran


PPN DN (10%) atas Pembayaran Invoice 08 s/d 09
4 1 1 2 1 1 9 0 0 Pengawasan Teknis Pembangunan Jalan Memberamo - Elelim II (MYC)

Tahun Anggaran 2021

Masa Pajak Tahun


2 0 2 1
Jan Peb Mar Apr Mei Jun Jul Ags Sep Okt Nop Des
Beri tanda silang pada salah astu kolom bulan untuk masa yang berkenaan Diisi tahun terhutangnya pajak

Nomor Ketetapan : / / / /
Diisi sesuai Nomor Ketetapan : STP, SKPKB, SKPKBT

Jumlah Pembayaran Terbilang :


Err:511
Diisi dengan rupiah penuh

Rp. 23,968,801

Diterima oleh Kantor Penerima Pembayaran Wajib Pajak/Penyetor


Tanggal, ……………………………. Jayapura, …………………………
Cap dan tanda tangan Cap dan tanda tangan

Nama Jelas : ………………………………………. Isnaini Syawik


Direktur Utama

Ruang Validasi Kantor Penerima Pembayaran

Diisi sesuai buku petunjuk pengisian

F.2.0.32.01
SURAT SETORAN PAJAK
LEMBAR 4
DEPARTEMEN KEUANGAN R.I.
DIREKTORAT JENDERAL PAJAK
KANTOR PELAYANAN PAJAK
JAYAPURA (SSP) UNTUK BANK PERSEPSI / KANTOR POS &
GIRO

NPWP : 0 2 . 8 6 8 . 9 9 3 . 3 - 0 2 7 . 0 0 0
Diisi sesuai dengan Nomor Pokok Wajib Pajak yang dimiliki

NAMA WP : PT. WINSOLUSI KONSULTAN


ALAMAT : RUKO MEGA GROSIR CEMPAKA MAS BLOK A NO. 25
KEL. SUMUR BATU KEC. KEMAYORAN JAKARTA PUSAT

MAP/Kode Jenis Pajak Kode Jenis setoran Uraian Pembayaran


PPN DN (10%) atas Pembayaran Invoice 08 s/d 09
4 1 1 2 1 1 9 0 0 Pengawasan Teknis Pembangunan Jalan Memberamo - Elelim II (MYC)

Tahun Anggaran 2021

Masa Pajak Tahun


2 0 2 1
Jan Peb Mar Apr Mei Jun Jul Ags Sep Okt Nop Des
Beri tanda silang pada salah astu kolom bulan untuk masa yang berkenaan Diisi tahun terhutangnya pajak

Nomor Ketetapan : / / / /
Diisi sesuai Nomor Ketetapan : STP, SKPKB, SKPKBT

Jumlah Pembayaran Terbilang :


Err:511
Diisi dengan rupiah penuh

Rp. 23,968,801

Diterima oleh Kantor Penerima Pembayaran Wajib Pajak/Penyetor


Tanggal, ……………………………. Jayapura, …………………………
Cap dan tanda tangan Cap dan tanda tangan

Nama Jelas : ………………………………………. Isnaini Syawik


Direktur Utama

Ruang Validasi Kantor Penerima Pembayaran

Diisi sesuai buku petunjuk pengisian

F.2.0.32.01
SURAT SETORAN PAJAK
LEMBAR 1
DEPARTEMEN KEUANGAN R.I.
DIREKTORAT JENDERAL PAJAK
KANTOR PELAYANAN PAJAK
JAYAPURA (SSP) ARSIP WP

NPWP : 0 2 . 8 6 8 . 9 9 3 . 3 - 0 2 7 . 0 0 0
Diisi sesuai dengan Nomor Pokok Wajib Pajak yang dimiliki

NAMA WP : PT. WINSOLUSI KONSULTAN


ALAMAT : RUKO MEGA GROSIR CEMPAKA MAS BLOK A NO. 25
KEL. SUMUR BATU KEC. KEMAYORAN JAKARTA PUSAT

MAP/Kode Jenis Pajak Kode Jenis setoran Uraian Pembayaran


PPh Ps 4 Ay 2 (4%) atas Pembayaran Invoice 08 s/d 09
4 1 1 1 2 8 4 0 9 Pengawasan Teknis Pembangunan Jalan Memberamo - Elelim II (MYC)

Tahun Anggaran 2021

Masa Pajak Tahun


2 0 2 1
Jan Peb Mar Apr Mei Jun Jul Ags Sep Okt Nop Des
Beri tanda silang pada salah astu kolom bulan untuk masa yang berkenaan Diisi tahun terutangnya pajak

Nomor Ketetapan : / / / /
Diisi sesuai Nomor Ketetapan : STP, SKPKB, SKPKBT

Jumlah Pembayaran Terbilang : Err:511


Diisi dengan rupiah penuh

Rp. 9,587,521

Diterima oleh Kantor Penerima Pembayaran Wajib Pajak/Penyetor


Tanggal, ……………………………. Jayapura, …………………………
Cap dan tanda tangan Cap dan tanda tangan

Isnaini Syawik
Nama Jelas : ………………………………………. Direktur Utama

Ruang Validasi Kantor Penerima Pembayaran

Diisi sesuai buku petunjuk pengisian

F.2.0.32.01
SURAT SETORAN PAJAK
LEMBAR 2
DEPARTEMEN KEUANGAN R.I.
DIREKTORAT JENDERAL PAJAK
KANTOR PELAYANAN PAJAK
JAYAPURA (SSP) UNTUK KPP MELALUI KPPN

NPWP : 0 2 . 8 6 8 . 9 9 3 . 3 - 0 2 7 . 0 0 0
Diisi sesuai dengan Nomor Pokok Wajib Pajak yang dimiliki

NAMA WP : PT. WINSOLUSI KONSULTAN


ALAMAT : RUKO MEGA GROSIR CEMPAKA MAS BLOK A NO. 25
KEL. SUMUR BATU KEC. KEMAYORAN JAKARTA PUSAT

MAP/Kode Jenis Pajak Kode Jenis setoran Uraian Pembayaran


PPh Ps 4 Ay 2 (4%) atas Pembayaran Invoice 08 s/d 09
4 1 1 1 2 8 4 0 9 Pengawasan Teknis Pembangunan Jalan Memberamo - Elelim II (MYC)

Tahun Anggaran 2021

Masa Pajak Tahun


2 0 2 1
Jan Peb Mar Apr Mei Jun Jul Ags Sep Okt Nop Des
Beri tanda silang pada salah astu kolom bulan untuk masa yang berkenaan Diisi tahun terutangnya pajak

Nomor Ketetapan : / / / /
Diisi sesuai Nomor Ketetapan : STP, SKPKB, SKPKBT

Jumlah Pembayaran Terbilang : Err:511


Diisi dengan rupiah penuh

Rp. 9,587,521

Diterima oleh Kantor Penerima Pembayaran Wajib Pajak/Penyetor


Tanggal, ……………………………. Jayapura, …………………………
Cap dan tanda tangan Cap dan tanda tangan

Isnaini Syawik
Nama Jelas : ………………………………………. Direktur Utama

Ruang Validasi Kantor Penerima Pembayaran

Diisi sesuai buku petunjuk pengisian

F.2.0.32.01
SURAT SETORAN PAJAK
LEMBAR 3
DEPARTEMEN KEUANGAN R.I.
DIREKTORAT JENDERAL PAJAK
KANTOR PELAYANAN PAJAK
JAYAPURA (SSP) UNTUK DILAPORKAN OLEH WP KE KPP

NPWP : 0 2 . 8 6 8 . 9 9 3 . 3 - 0 2 7 . 0 0 0
Diisi sesuai dengan Nomor Pokok Wajib Pajak yang dimiliki

NAMA WP : PT. WINSOLUSI KONSULTAN


ALAMAT : RUKO MEGA GROSIR CEMPAKA MAS BLOK A NO. 25
KEL. SUMUR BATU KEC. KEMAYORAN JAKARTA PUSAT

MAP/Kode Jenis Pajak Kode Jenis setoran Uraian Pembayaran


PPh Ps 4 Ay 2 (4%) atas Pembayaran Invoice 08 s/d 09
4 1 1 1 2 8 4 0 9 Pengawasan Teknis Pembangunan Jalan Memberamo - Elelim II (MYC)

Tahun Anggaran 2021

Masa Pajak Tahun


2 0 2 1
Jan Peb Mar Apr Mei Jun Jul Ags Sep Okt Nop Des
Beri tanda silang pada salah astu kolom bulan untuk masa yang berkenaan Diisi tahun terutangnya pajak

Nomor Ketetapan : / / / /
Diisi sesuai Nomor Ketetapan : STP, SKPKB, SKPKBT

Jumlah Pembayaran Terbilang : Err:511


Diisi dengan rupiah penuh

Rp. 9,587,521

Diterima oleh Kantor Penerima Pembayaran Wajib Pajak/Penyetor


Tanggal, ……………………………. Jayapura, …………………………
Cap dan tanda tangan Cap dan tanda tangan

Isnaini Syawik
Nama Jelas : ………………………………………. Direktur Utama

Ruang Validasi Kantor Penerima Pembayaran

Diisi sesuai buku petunjuk pengisian

F.2.0.32.01
SURAT SETORAN PAJAK
LEMBAR 4
DEPARTEMEN KEUANGAN R.I.
DIREKTORAT JENDERAL PAJAK

(SSP)
KANTOR PELAYANAN PAJAK UNTUK BANK PERSEPSI / KANTOR POS &
JAYAPURA GIRO

NPWP : 0 2 . 8 6 8 . 9 9 3 . 3 - 0 2 7 . 0 0 0
Diisi sesuai dengan Nomor Pokok Wajib Pajak yang dimiliki

NAMA WP : PT. WINSOLUSI KONSULTAN


ALAMAT : RUKO MEGA GROSIR CEMPAKA MAS BLOK A NO. 25
KEL. SUMUR BATU KEC. KEMAYORAN JAKARTA PUSAT

MAP/Kode Jenis Pajak Kode Jenis setoran Uraian Pembayaran


PPh Ps 4 Ay 2 (4%) atas Pembayaran Invoice 08 s/d 09
4 1 1 1 2 8 4 0 9 Pengawasan Teknis Pembangunan Jalan Memberamo - Elelim II (MYC)

Tahun Anggaran 2021

Masa Pajak Tahun


2 0 2 1
Jan Peb Mar Apr Mei Jun Jul Ags Sep Okt Nop Des
Beri tanda silang pada salah astu kolom bulan untuk masa yang berkenaan Diisi tahun terutangnya pajak

Nomor Ketetapan : / / / /
Diisi sesuai Nomor Ketetapan : STP, SKPKB, SKPKBT

Jumlah Pembayaran Terbilang : Err:511


Diisi dengan rupiah penuh

Rp. 9,587,521

Diterima oleh Kantor Penerima Pembayaran Wajib Pajak/Penyetor


Tanggal, ……………………………. Jayapura, …………………………
Cap dan tanda tangan Cap dan tanda tangan

Isnaini Syawik
Nama Jelas : ………………………………………. Direktur Utama

Ruang Validasi Kantor Penerima Pembayaran

Diisi sesuai buku petunjuk pengisian

F.2.0.32.01
RENCANA PENARIKAN TAGIHAN

NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020


NO. SPMK DAN TANGGAL : IK.02.04/SPMK/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

No Uraian Nilai Invoice Jadwal Penarikan

Invoice VI dan Invoice VII (Januari


1 343,167,971 Maret 2021
2021 dan Februari 2021)

Invoice VIII dan Invoice XI (Maret


2 263,656,814 Mei 2021
2021 dan April 2021)

Invoice X dan Invoice XI (Mei


372,633,806 Juli 2021
2021 dan Juni 2021)

Invoice XII dan Invoice XIII (Juli


484,360,800 September 2021
2021 dan Agustus 2021)

Invoice XIV dan Invoice XV


(September 2021 dan Oktober 484,360,800 November 2021
2021)
Invoice XVI dan Invoice XVII
3 (November 2021 dan Desember 482,985,800 Desember 2021
2021)

Total 2,431,165,991

0
Konsultan Supervisi
PT. WINSOLUSI KONSULTAN

ISNAINI SYAWIK, ST
Direktur Utama
RENCANA PENARIKAN TAGIHAN

NO. KONTRAK DAN TANGGAL : HK.02.03/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 18 Agustus 2020


NO. SPMK DAN TANGGAL : IK.02.04/SPMK/PW.MYC.JL.ME.II/APBN/Bb18.6.2/025/2020, tanggal 19 Agustus 2020
JENIS PEKERJAAN : Pengawasan Teknis Pembangunan Jalan Memberamo – Elelim II (MYC)

LOKASI : Wilayah Satker PJN Wilayah I (Jayapura)


WAKTU : 25 Bulan

No Uraian Nilai Invoice Jadwal Penarikan

Invoice VI dan Invoice VII (Januari


1 343,167,971 Maret 2021
2021 dan Februari 2021)

Invoice VIII dan Invoice XI (Maret


2 263,656,814 Mei 2021
2021 dan April 2021)

Invoice X dan Invoice XI (Mei


372,633,806 Juli 2021
2021 dan Juni 2021)

Invoice XII dan Invoice XIII (Juli


484,360,800 September 2021
2021 dan Agustus 2021)

Invoice XIV dan Invoice XV


(September 2021 dan Oktober 484,360,800 November 2021
2021)
Invoice XVI dan Invoice XVII
3 (November 2021 dan Desember 1,357,844,809 Desember 2021
2021)

Total 3,306,025,000

0
Konsultan Supervisi
PT. WINSOLUSI KONSULTAN

ISNAINI SYAWIK, ST
Direktur Utama
Invoice Bulan Nilai Tagihan (Kotor)
UANG MUKA 899,611,950
1 Agustus 2020 67,641,471
2 September 2020 117,170,575
3 Oktober 2020 144,598,955 2020 1,464,568,000
4 November 2020 151,531,705
5 Desember 2020 84,013,344
6 Januari 2021 212,027,064
7 Februari 2021 131,140,907
8 Maret 2021 131,140,907
9 April 2021 132,515,907
10 Mei 2021 131,140,906
11 Juni 2021 241,492,900
12 Juli 2021 242,867,900 2021 2,431,165,991
13 Agustus 2021 241,492,900
14 September 2021 241,492,900
15 Oktober 2021 242,867,900
16 November 2021 241,492,900
17 Desember 2021 241,492,900
18 Januari 2022 242,867,900
19 Februari 2022 241,492,900
20 Maret 2022 241,492,900
21 April 2022 242,867,900
22 Mei 2022 241,492,900 2022 2,017,720,067
23 Juni 2022 241,492,900
24 Juli 2022 242,867,900
25 Agustus 2022 241,492,900
26 September 2022 81,651,867
T OT A L 5,913,454,058

5,913,454,058
Mamberamo elelim 2
1. Nilai kontrak nya brp? 5,997,413,000
2. Nilai kontrak 2020 nya brp? 2,018,231,000
3. Akhir kontrak tgl brp? 07 September 2020
343,167,971 4. Perlu buat jaminan atau tdk? Seperti pengalaman tahun sebelumnya, tidak perlu
299,492,047 5. Utk rincian minta tlg dibuat sampai akhir atau desember rincian sampai akhir kontra

Hitungan full 1 bulan

?????
hun sebelumnya, tidak perlu
rincian sampai akhir kontrak

Anda mungkin juga menyukai