Sesuai Kontrak Add 2 BOBOT PEKERJAAN

S.D MINGGU KOMULATIF


NO URAIAN PEKERJAAN JUMLAH HARGA BOBOT % MINGGU INI
LALU BOBOT %

1 SMKK 93.057.500,00 0,431% 0,010 0,063 0,074


2 MIN 1 MANADO 1.718.245.769,61 7,951% 3,261 0,983 4,244
3 MTsN 1 MANADO 1.026.630.670,24 4,751% - -
4 MIN 1 BITUNG (SARI KELAPA) 1.177.041.767,32 5,447% 1,814 0,441 2,255
(GIRIAN) 3.988.342.758,39 18,457% 9,299 0,430 9,729
5 MTsN 1 MINAHASA 1.042.827.231,55 4,826% - -
6 MIN 1 MINAHASA 183.163.558,31 0,848% - -
7 MTs N 1 SANGIHE 4.591.172.019,91 21,246% 6,680 5,018 11,698
8 MIN 1 SANGIHE 4.636.245.046,33 21,455% 7,190 3,681 10,871
9 MIN 2 SANGIHE 3.152.430.349,06 14,588% 3,370 1,086 4,456

JUMLAH 21.609.156.670,71
PPN 11% X A 2.377.007.233,78 100,000% 31,624 43,325 43,325
JUMLAH TOTAL ( A + B ) 23.986.163.904,49