PROGRESS PEKERJAAN MINGGUAN

PEKERJAAN : INSULASI PIPA dan MESIN


LOKASI : PLTSa PUTRI CEMPO SOLO
MINGGU KE : 7 (Tujuh)
PERIODE : 06 Desember 2022 s/d #############

Harga Satuan PERIODE MINGGU INI PERIODE S/D SISA PROGRESS


PERIODE S/D MINGGU INI
Upah Jumlah Upah (M-7) MINGGU LALU PEKERJAAN
NO Uraian Pekerjaan Sat. Volume Bobot (%)
(Rp) (Rp)
VOL. VOL. VOL. VOL.
BOBOT (%) BOBOT (%) BOBOT (%) BOBOT (%)
PEKERJAAN PEKERJAAN PEKERJAAN PEKERJAAN
0,90
1 PRELIMINERIES 90,855%
Akomodasi Ls 1,00 12.500.000,00 12.500.000,00 11.356.882,46 0,757% 0,02 0,017% 0,75 0,568% 0,77 0,585% 0,23 0,172%
Transportasi Ls 1,00 10.000.000,00 10.000.000,00 9.085.505,97 0,606% 0,02 0,013% 0,75 0,454% 0,77 0,468% 0,23 0,138%

2 INSULASI PIPA
Blanket long Armaflex m² 785 185.000,00 145.225.000,00 131.944.260,42 8,796% 0,00 0,000% 424,17 4,753% 424,17 4,753% 360,83 4,043%
Blanket short Armaflex m² 46 210.000,00 9.660.000,00 8.776.598,77 0,585% 0,00 0,000% 22,77 0,290% 22,77 0,290% 23,23 0,295%
Blanket rockwoll m² 1.485 250.000,00 371.250.000,00 337.299.409,06 22,487% 56,43 0,854% 272,01 4,119% 328,44 4,973% 1.156,56 17,513%
Cladding 2.5" m² 955,65 125.000,00 119.456.250,00 108.532.047,23 7,235% 0,00 0,000% 447,45 3,388% 447,45 3,388% 508,20 3,848%
Cladding >12" m² 1.782 145.000,00 258.390.000,00 234.760.388,71 15,651% 45,98 0,404% 342,50 3,008% 388,48 3,412% 1.393,52 12,239%

3 INSULASI MESIN
Blanket rockwoll m² 1.500 285.000,00 427.500.000,00 388.405.380,13 25,894% 102,45 1,769% 191,85 3,312% 294,30 5,080% 1.205,70 20,813%
Clading m² 1.800 165.000,00 297.000.000,00 269.839.527,25 17,989% 90,00 0,899% 122,22 1,221% 212,22 2,121% 1.587,78 15,868%

TOTAL 1.650.981.250,00
Pembulatan 1.650.000.000,00
1.500.000.000,00 100% 3,957% 21,113% 25,069% 74,931%
Discount 1.500.000.000,00
TOTAL 1.500.000.000,00

7 JUNI 2022
PT. DIGITHA CAKRA SINERGI