Anda di halaman 1dari 21

ENGINEERING ESTIMATE (EE)

Kegiatan : Pembangunan Fasilitas Kesehatan Lainnya


Pekerjaan : Pembangunan Pustu Bora-bora
Lokasi : Bora-bora Distrik Tor atas, Kabupaten Sarmi
Tahun : 2022

HARGA
NO. URAIAN PEKERJAAN SATUAN VOLUME SATUAN JUMLAH
(Rp) (Rp)
a b c d e f
I. PEKERJAAN PERSIAPAN
1 Pembersihan lokasi M2 119.00 31,750.00 3,778,250.00
2 Barak kerja/direksi keet & gudang M2 30.00 520,000.00 15,600,000.00
3 Mobilisasi material Ls 2.00 13,390,000.00 26,780,000.00
4 Papan nama kegiatan Bh 1.00 1,500,000.00 1,500,000.00
Rp 47,658,250.00
II. PEKERJAAN KAYU
1 Pasang bouwplank M' 48.00 136,287.00 6,541,776.00
2 Kolom kayu besi 10/10 cm M3 1.24 6,832,440.00 8,472,225.60
3 Pondasi Titik batu kali M3 3.89 6,832,440.00 26,544,029.40
4 Ring balok kayu besi 5/10 cm M3 0.56 6,832,440.00 3,812,501.52
5 Dinding papan kayu besi t = 2 cm M2 315.00 309,637.66 97,535,862.58
6 Pasang top gavel M2 0.70 309,637.66 216,746.36
7 Kuda - kuda kayu Besi 5/10 M3 1.47 8,689,880.00 12,774,123.60
8 Balok Ikatan Angin kayu Besi 5/10 M3 0.19 8,689,880.00 1,668,456.96
9 Gording kayu matoa 5/10 M3 1.29 6,621,498.00 8,541,732.42
10 Kusen pintu, jendela dan ventilasi ky bs 5/10 cm M3 0.91 10,604,460.00 9,650,058.60
11 Jalusi kayu besi M2 8.00 818,095.00 6,544,760.00
12 Jendela ungkit kaca ky besi M2 17.25 766,018.00 13,213,810.50
14 Pintu panel kayu besi M2 20.66 997,302.00 20,604,259.32
15 Tangga kayu M3 0.15 10,604,460.00 1,590,669.00
Rp 217,711,011.86
III. PEKERJAAN BETON
1 Pek. Pas. Pondasi batu karang M3 8.75 2,112,975.00
1 Pek. Cor Lantai KM/WC M3 0.32 3,044,711.50 959,084.12
2 Floor Lantai KM/WC M2 4.50 49,252.60 221,636.70
Rp 1,180,720.82
IV. PEKERJAAN ATAP
1 Atap metal soka M2 203.60 198,576.95 40,430,266.25
2 Nok genteng metal soka M' 53.14 195,075.69 10,366,321.94
3 Lisplank ky besi 2 x 2,5/30 M' 61.00 104,665.00 6,384,565.00
4 Plafond triplek 3 mm M2 161.08 280,846.20 45,238,705.90
5 List plafond kayu matoa diprofil M' 240.00 71,591.20 17,181,888.00
Rp 119,601,747.08
V. PEKERJAAN LANTAI
1 Lantai papan kayu besi t = 3 cm M2 80.09 308,666.50 24,721,099.99
2 Pasang balok lantai kayu besi 5/15 dan 5/10 cm M2 80.09 345,956.04 27,707,619.29
Rp 52,428,719.28
VI. PEKERJAAN PENGECATAN
1 Cat dinding M2 315.00 84,946.30 26,758,084.50
2 Cat plafond M2 161.08 22,450.31 3,616,295.93
3 Cat kusen pintu / jendela, daun pintu, daun jendela ,
jalusi dan lisplank M2 116.67 84,946.30 9,910,854.71
Rp 40,285,235.15
a b c d e f
VII. PEKERJAAN ALAT GANTUNG
1 Kunci tanam 2 SLAGG Bh 10.00 408,056.60 4,080,566.00
2 Engsel pintu ring nylon Bh 30.00 78,614.15 2,358,424.50
3 Grendel pintu Bh 10.00 72,752.20 727,522.00
4 Engsel jendela ring nylon Bh 50.00 63,676.10 3,183,805.00
5 Grendel jendela Bh 50.00 72,752.20 3,637,610.00
6 Hak angin/kait angin Bh 50.00 76,014.15 3,800,707.50
7 Hendle tarikan Bh 50.00 138,380.50 6,919,025.00
8 Baut dia. 12 mm Bh 60.00 38,542.00 2,312,520.00
Rp 27,020,180.00
VIII. PEKERJAAN LISTRIK
1 Pasang lampu Philips SL 40 watt Bh 7.00 574,936.50 4,024,555.50
2 Pasang lampu Philips SL 25 wat Bh 9.00 464,436.50 4,179,928.50
3 Pasang stop kontak Bh 8.00 335,736.50 2,685,892.00
4 Pas. Box Limit Bh 2.00 438,436.50 876,873.00
Rp 11,767,249.00
IX. PEKERJAAN SANITASI
1 Pek. Pas. Klosed Jongkok bh 2.00 2,033,080.00 4,066,160.00
2 Pek. Pas. Bak Air Fiber KM/WC bh 2.00 900,000.00 1,800,000.00
3 Pek. Pas. Pipa PVC 4" m' 4.00 191,340.67 765,362.68
4 Pek. Pas. Pipa PVC 1 1/2" m' 4.00 58,732.71 234,930.84
5 Pek. Pas. Pipa PVC 1/2" m' 4.00 35,303.46 141,213.84
6 Pek. Pas. Kran Air 1/2" bh 2.00 84,826.00 169,652.00
7 Pek. Pas. Septictank unit 2.00 8,000,000.00 16,000,000.00
Rp 23,177,319.36
X. PEKERJAAN AKHIR
1 Pekerjaan Pembersihan Akhir Ls 1.00 2,273,000.00 2,273,000.00
2 Foto dokumentasi dan pelaporan Ls 1.00 1,560,000.00 1,560,000.00
Rp 3,833,000.00
a b c d e f

R E K A P I T U L A S I
Pekerjaan : Pembangunan Pustu Bora-bora
Lokasi : Bora-bora Distrik Tor atas, Kabupaten Sarmi
Tahun : 2022

I. PEKERJAAN PERSIAPAN ……………………………………… Rp 47,658,250.00


II. PEKERJAAN KAYU ……………………………………… Rp 217,711,011.86
III. PEKERJAAN BETON ……………………………………… Rp 1,180,720.82
IV. PEKERJAAN ATAP ……………………………………… Rp 119,601,747.08
V. PEKERJAAN LANTAI ……………………………………… Rp 52,428,719.28
VI. PEKERJAAN PENGECATAN ……………………………………… Rp 40,285,235.15
VII. PEKERJAAN ALAT GANTUNG ……………………………………… Rp 27,020,180.00
IX. PEKERJAAN LISTRIK ……………………………………… Rp 11,767,249.00
X. PEKERJAAN SANITASI ……………………………………… Rp 23,177,319.36
XI. PEKERJAAN AKHIR ……………………………………… Rp 3,833,000.00

REAL COST ……………………………………… Rp 544,663,432.55


PPN 11 % ……………………………………… Rp 59,912,977.58
J U M L A H ……………………………………… Rp 604,576,410.13
DIBULATKAN ……………………………………… Rp 604,500,000.00

TERBILANG : ENAM RATUS EMPAT JUTA LIMA RATUS RIBU RUPIAH

Sarmi, 2022

Konsultan Perencana
CV. FILATLAS CONSULINDO

AUNURRAFIQ SALEH, ST.


Direktur
DAFTAR ANALISA HARGA SATUAN
Pekerjaan : Pembangunan Pustu Bora-bora
Lokasi : Bora-bora Distrik Tor atas, Kabupaten Sarmi
Tahun : 2022

ANALISA
No. URAIAN PEKERJAAN SATUAN HARGA SATUAN JUMLAH HARGA
SATUAN
a b d e f g
1 1 M' PENGUKURAN DAN PASANG BOUWPLANK
Kayu 5/7 0.0120 M3 4,127,500.00 49,530.00
Paku biasa 2"-5" 0.0200 Kg 26,000.00 520.00
Kayu papan 3/20 0.0070 M3 4,500,000.00 31,500.00
Tukang kayu 0.1000 Oh 203,200.00 20,320.00
Pekerja 0.1000 Oh 152,400.00 15,240.00
Kepala tukang 0.0100 Oh 266,700.00 2,667.00
Mandor 0.0500 Oh 330,200.00 16,510.00
136,287.00
2 1 M2 PEMBUATAN GUDANG DAN ALAT-ALAT
Dolken kayu dia. 8-10/400 cm 1.7000 Btg 50,000.00 85,000.00
Kayu 0.2100 M3 4,500,000.00 945,000.00
Paku biasa campuran 0.3000 Kg 26,000.00 7,800.00
Semen portland 10.5000 Kg 3,450.00 36,225.00
Pasir beton 0.0300 M3 700,000.00 21,000.00
Koral beton 0.0500 M3 1,900,000.00 95,000.00
Seng gelombang bjls 0,32 1.5000 Lbr 195,000.00 292,500.00
Tukang kayu 2.0000 Oh 203,200.00 406,400.00
Pekerja 1.0000 Oh 152,400.00 152,400.00
Kepala tukang 0.2000 Oh 266,700.00 53,340.00
Mandor 0.0500 Oh 330,200.00 16,510.00
2,111,175.00
3 1 M2 PEMBERSIHAN LAPANGAN DAN PERATAAN
Pekerja 0.1000 Oh 152,400.00 15,240.00
Mandor 0.0500 Oh 330,200.00 16,510.00
31,750.00
4 1 M3 PASANG KUSEN PINTU DAN JENDELA KAYU BESI
Balok kayu besi 1.2000 M3 4,500,000.00 5,400,000.00
Pekerja 6.0000 Oh 152,400.00 914,400.00
Tukang kayu 18.0000 Oh 203,200.00 3,657,600.00
Kepala tukang 2.0000 Oh 266,700.00 533,400.00
Mandor 0.3000 Oh 330,200.00 99,060.00
10,604,460.00
5 1 M2 PASANG JENDELA KACA KAYU BESI
Papan kayu besi 0.0350 M3 4,500,000.00 157,500.00
Lem kayu 0.3000 Ltr 45,500.00 13,650.00
Pekerja 0.8000 Oh 152,400.00 121,920.00
Tukang kayu 2.0000 Oh 203,200.00 406,400.00
Kepala tukang 0.2000 Oh 266,700.00 53,340.00
Mandor 0.0400 Oh 330,200.00 13,208.00
766,018.00
6 1 M2 PASANG JALUSI MATI KAYU BESI
Papan kayu besi 0.0600 M3 4,500,000.00 270,000.00
Paku biasa campuran 0.1500 Kg 26,000.00 3,900.00
Pekerja 0.5000 Oh 152,400.00 76,200.00
Tukang kayu 2.0000 Oh 203,200.00 406,400.00
Kepala tukang 0.2000 Oh 266,700.00 53,340.00
Mandor 0.0250 Oh 330,200.00 8,255.00
818,095.00
a b d e f g

7 1 M2 PAS PINTU PANEL KAYU BESI


Papan kayu besi 0.1546 M3 4,500,000.00 695,520.00
Paku biasa campuran 0.0500 Kg 26,000.00 1,300.00
Pekerja 0.3500 Oh 152,400.00 53,340.00
Tukang kayu 1.0500 Oh 203,200.00 213,360.00
Kepala tukang 0.1050 Oh 266,700.00 28,003.50
Mandor 0.0175 Oh 330,200.00 5,778.50
997,302.00

8 1 M3 PASANG KONSTRUKSI KUDA-KUDA KAYU BESI


Balok kayu besi 1.1000 M3 4,500,000.00 4,950,000.00
Besi strip 15.0000 Kg 19,000.00 285,000.00
Paku biasa campuran 0.8000 Kg 26,000.00 20,800.00
Pekerja 4.0000 Oh 152,400.00 609,600.00
Tukang kayu 12.0000 Oh 203,200.00 2,438,400.00
Kepala tukang 1.2000 Oh 266,700.00 320,040.00
Mandor 0.2000 Oh 330,200.00 66,040.00
8,689,880.00
9 1 M3 PASANG GORDING KAYU MATOA
Balok kayu matoa 1.1000 M3 4,127,500.00 4,540,250.00
Paku biasa campuran 0.8000 Kg 26,000.00 20,800.00
Pekerja 2.4000 Oh 152,400.00 365,760.00
Tukang kayu 7.2000 Oh 203,200.00 1,463,040.00
Kepala tukang 0.7200 Oh 266,700.00 192,024.00
Mandor 0.1200 Oh 330,200.00 39,624.00
6,621,498.00
10 1 M' PASANG LISPLANG UK. 2,5/30, KAYU BESI
Papan kayu besi 0.0090 M3 4,500,000.00 40,500.00
Paku biasa campuran 0.0500 Kg 26,000.00 1,300.00
Pekerja 0.1000 Oh 152,400.00 15,240.00
Tukang kayu 0.2000 Oh 203,200.00 40,640.00
Kepala tukang 0.0200 Oh 266,700.00 5,334.00
Mandor 0.0050 Oh 330,200.00 1,651.00
104,665.00
11 1 M2 PASANG RANGKA + DINDING PEMISAH KAYU BESI
Balok kayu besi 0.0117 M3 4,500,000.00 52,851.16
Papan kayu besi 0.0218 M3 4,500,000.00 97,920.00
Paku biasa campuran 0.3000 Kg 26,000.00 7,800.00
Pekerja 0.1500 Oh 152,400.00 22,860.00
Tukang kayu 0.4500 Oh 203,200.00 91,440.00
Kepala tukang 0.0450 Oh 266,700.00 12,001.50
Mandor 0.0750 Oh 330,200.00 24,765.00
309,637.66
12 1 M2 PASANG LANTAI PAPAN KAYU BESI T,3 cm
Papan kayu besi 0.0330 M3 4,500,000.00 148,500.00
Paku biasa campuran 0.3500 Kg 26,000.00 9,100.00
Pekerja 0.1500 Oh 152,400.00 22,860.00
Tukang kayu 0.4500 Oh 203,200.00 91,440.00
Kepala tukang 0.0450 Oh 266,700.00 12,001.50
Mandor 0.0750 Oh 330,200.00 24,765.00
308,666.50
13 1 M' PAS. LIST PLAFOND - KAYU PROFIL
Kayu profil 1.0500 M' 60,000.00 63,000.00
Paku biasa campuran 0.0100 Kg 26,000.00 260.00
Pekerja 0.0210 Oh 152,400.00 3,200.40
Tukang kayu 0.0210 Oh 203,200.00 4,267.20
Kepala tukang 0.0020 Oh 266,700.00 533.40
Mandor 0.0010 Oh 330,200.00 330.20
71,591.20
a b d e f g

14 1 M2 PASANG ATAP SENG METAL SOKA/SEJENIS


Atap seng metal Soka/sejenis 0.8403 Lbr 195,000.00 163,865.55
Paku seng 0.0200 Kg 32,500.00 650.00
Pekerja 0.1200 Oh 152,400.00 18,288.00
Tukang kayu 0.0600 Oh 203,200.00 12,192.00
Kepala tukang 0.0060 Oh 266,700.00 1,600.20
Mandor 0.0060 Oh 330,200.00 1,981.20
198,576.95
15 1 M2 PASANG NOK ATAP SENG METAL SOKA/SEJENIS
Nok seng metal Soka/sejenis 1.4286 bh 92,900.00 132,714.29
Paku seng 0.0400 Kg 32,500.00 1,300.00
Papan kayu besi 0.0060 M3 4,500,000.00 27,000.00
Pekerja 0.1200 Oh 152,400.00 18,288.00
Tukang kayu 0.0600 Oh 203,200.00 12,192.00
Kepala tukang 0.0060 Oh 266,700.00 1,600.20
Mandor 0.0060 Oh 330,200.00 1,981.20
195,075.69
16 1 M2 PLAFOND TRIPLEKS 3 MM + RANGKA KAYU MATOA
Balok kayu matoa/kayu putih 0.0230 M3 4,127,500.00 94,932.50
Paku biasa campuran 0.0600 Kg 26,000.00 1,560.00
Tripleks 3 mm 0.3900 Lbr 120,000.00 46,800.00
Pekerja 0.2700 Oh 152,400.00 41,148.00
Tukang kayu 0.4000 Oh 203,200.00 81,280.00
Kepala tukang 0.0400 Oh 266,700.00 10,668.00
Mandor 0.0135 Oh 330,200.00 4,457.70
280,846.20
1 TTK. PAS LAMPU PHILIPS SL 40 WATT
Lampu SL Phillips 40 Watt 1.0000 Set 230,100.00 230,100.00
Kabel Listrik 10.0000 M' 9,880.00 98,800.00
Saklar 1.0000 Bh 42,900.00 42,900.00
Pekerja 0.6000 OH 152,400.00 91,440.00
Tukang Listrik 0.4500 OH 203,200.00 91,440.00
Kepala Tukang Listrik 0.0450 OH 266,700.00 12,001.50
Mandor 0.0250 OH 330,200.00 8,255.00
574,936.50
1 TTK. PAS LAMPU PHILIPS SL 25 WATT
Lampu SL Phillips 25 Watt 1.0000 Set 119,600.00 119,600.00
Kabel Listrik 10.0000 M' 9,880.00 98,800.00
Saklar 1.0000 Bh 42,900.00 42,900.00
Pekerja 0.6000 OH 152,400.00 91,440.00
Tukang Listrik 0.4500 OH 203,200.00 91,440.00
Kepala Tukang Listrik 0.0450 OH 266,700.00 12,001.50
Mandor 0.0250 OH 330,200.00 8,255.00
464,436.50
1 TTK. PAS. STOP KONTAK
Stop Kontak 1.0000 Bh 33,800.00 33,800.00
Kabel Listrik 10.0000 M' 9,880.00 98,800.00
Pekerja 0.6000 OH 152,400.00 91,440.00
Tukang Listrik 0.4500 OH 203,200.00 91,440.00
Kepala Tukang Listrik 0.0450 OH 266,700.00 12,001.50
Mandor 0.0250 OH 330,200.00 8,255.00
335,736.50
1 BH PASANG BOX LIMIT
Box Limit + Limit 1.0000 Unit 136,500.00 136,500.00
Kabel Listrik 10.0000 M' 9,880.00 98,800.00
Pekerja 0.6000 OH 152,400.00 91,440.00
Tukang Listrik 0.4500 OH 203,200.00 91,440.00
Kepala Tukang Listrik 0.0450 OH 266,700.00 12,001.50
Mandor 0.0250 OH 330,200.00 8,255.00
438,436.50
a b d e f g

17 1 BH PASANG KUNCI TANAM


Kunci tanam 1.0000 Bh 260,000.00 260,000.00
Pekerja 0.0600 Oh 152,400.00 9,144.00
Tukang kayu 0.6000 Oh 203,200.00 121,920.00
Kepala tukang 0.0600 Oh 266,700.00 16,002.00
Mandor 0.0030 Oh 330,200.00 990.60
408,056.60
18 1 BH PASANG ENGSEL PINTU
Engsel pintu 1.0000 Bh 41,600.00 41,600.00
Pekerja 0.0150 Oh 152,400.00 2,286.00
Tukang kayu 0.1500 Oh 203,200.00 30,480.00
Kepala tukang 0.0150 Oh 266,700.00 4,000.50
Mandor 0.0008 Oh 330,200.00 247.65
78,614.15
19 1 BH PASANG ENGSEL JENDELA
Engsel jendela 1.0000 Bh 39,000.00 39,000.00
Pekerja 0.0100 Oh 152,400.00 1,524.00
Tukang kayu 0.1000 Oh 203,200.00 20,320.00
Kepala tukang 0.0100 Oh 266,700.00 2,667.00
Mandor 0.0005 Oh 330,200.00 165.10
63,676.10
20 1 BH PASANG KAIT ANGIN
Kait angin 1.0000 Bh 39,000.00 39,000.00
Pekerja 0.0150 Oh 152,400.00 2,286.00
Tukang kayu 0.1500 Oh 203,200.00 30,480.00
Kepala tukang 0.0150 Oh 266,700.00 4,000.50
Mandor 0.0008 Oh 330,200.00 247.65
76,014.15

21 1 BH PASANG GRENDEL
Grendel 1.0000 Bh 23,400.00 23,400.00
Pekerja 0.0200 Oh 152,400.00 3,048.00
Tukang kayu 0.2000 Oh 203,200.00 40,640.00
Kepala tukang 0.0200 Oh 266,700.00 5,334.00
Mandor 0.0010 Oh 330,200.00 330.20
72,752.20
22 1 BH PASANG PEGANGAN
Pegangan/handle 1.0000 Bh 15,000.00 15,000.00
Pekerja 0.0500 Oh 152,400.00 7,620.00
Tukang kayu 0.5000 Oh 203,200.00 101,600.00
Kepala tukang 0.0500 Oh 266,700.00 13,335.00
Mandor 0.0025 Oh 330,200.00 825.50
138,380.50
23 1 M2 PASANG KACA BENING/POLOS
Kaca bening/polos 5 mm 1.1000 M2 643,890.00 708,279.00
Pekerja 0.0150 Oh 152,400.00 2,286.00
Tukang kayu 0.1500 Oh 203,200.00 30,480.00
Kepala tukang 0.0150 Oh 266,700.00 4,000.50
Mandor 0.0008 Oh 330,200.00 247.65
745,293.15
24 1 M2 MENGECAT KAYU BARU, 1 LAPIS PLAMIR,
1 LAPIS CAT DASAR, 3 LAPIS CAT PENUTUP
Cat meni 0.2000 Kg 45,500.00 9,100.00
Plamir 0.1500 Kg 31,800.00 4,770.00
Cat dasar/cat kayu 0.1700 Kg 71,500.00 12,155.00
Cat penutup/cat kayu 0.3500 Kg 71,500.00 25,025.00
Pekerja 0.0700 Oh 152,400.00 10,668.00
Tukang cat 0.1050 Oh 203,200.00 21,336.00
Kepala tukang 0.0040 Oh 266,700.00 1,066.80
Mandor 0.0025 Oh 330,200.00 825.50
84,946.30
a b d e f g

25 1 M2 MENGECAT PAFOND BARU DENGAN CAT TEMBOK


1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP
Cat dasar/cat tembok 0.1000 Kg 11,375.00 1,137.50
Cat penutup/cat tembok 0.2600 Kg 11,375.00 2,957.50
Pekerja 0.0200 Oh 152,400.00 3,048.00
Tukang cat 0.0630 Oh 203,200.00 12,801.60
Kepala tukang 0.0063 Oh 266,700.00 1,680.21
Mandor 0.0025 Oh 330,200.00 825.50
22,450.31
26 1 M2 CAT RESIDU/TER
Residu 0.3500 Ltr 34,300.00 12,005.00
Pekerja 0.1000 Oh 152,400.00 15,240.00
Mandor 0.0060 Oh 330,200.00 1,981.20
29,226.20
27 1 M3 PASANG RING BALK & KOLOM KAYU BESI
Kayu besi 1.1000 m3 4,500,000.00 4,950,000.00
Paku biasa campuran 0.5000 kg 26,000.00 13,000.00
Tukang kayu 6.0000 h/o 203,200.00 1,219,200.00
Kepala tukang 0.6000 h/o 266,700.00 160,020.00
Pekerja 3.0000 h/o 152,400.00 457,200.00
Mandor 0.1000 h/o 330,200.00 33,020.00
6,832,440.00
28 1 BH TIANG DILANCIPKAN
Tukang kayu 0.2500 h/o 203,200.00 50,800.00
Kepala tukang 0.0250 h/o 266,700.00 6,667.50
Pekerja 0.1000 h/o 152,400.00 15,240.00
Mandor 0.0050 h/o 330,200.00 1,651.00
A 74,358.50
1BH TIANG DIPANCANGKAN
Kayu besi 20/20 cm 0.0960 m3 4,500,000.00 432,000.00
Tukang kayu 0.0800 h/o 203,200.00 16,256.00
Kepala tukang 0.0080 h/o 266,700.00 2,133.60
Pekerja 3.6000 h/o 152,400.00 548,640.00
Mandor 0.0860 h/o 330,200.00 28,397.20
B 1,027,426.80

1 BH TIANG DIPASANG A+B 1,101,785.30


29 1 M2 PEMASANGAN GELAGAR BALOK LANTAI KAYU BESI
Kayu besi 0.0238 m3 4,500,000.00 106,965.24
Paku biasa campuran 0.3000 kg 26,000.00 7,800.00
Tukang kayu 0.8000 h/o 203,200.00 162,560.00
Kepala tukang 0.0800 h/o 266,700.00 21,336.00
Pekerja 0.2800 h/o 152,400.00 42,672.00
Mandor 0.0140 h/o 330,200.00 4,622.80
345,956.04
30 1 BH PAS. BAUT DIA. 12 mm
Baut dia. 12 mm 1.0000 bh 20,000.00 20,000.00
Pekerja 0.1000 h/o 152,400.00 15,240.00
Mandor 0.0100 h/o 330,200.00 3,302.00
38,542.00
31 PEK.PAS. PONDASI BATU KARANG
Batu Karang 1.2000 M3 700,000.00 840,000.00
Semen 3.2600 Sak 158,800.00 517,688.00
Pasir 0.5200 M3 700,000.00 364,000.00
Pekerja 1.5000 OH 152,400.00 228,600.00
Tukang Batu 0.6000 OH 203,200.00 121,920.00
Kepala Tukang Batu 0.0600 OH 266,700.00 16,002.00
Mandor 0.0750 OH 330,200.00 24,765.00
2,112,975.00
a b d e f g

32 1 M3 PEK. COR LANTAI 1:3:5


Semen 4.3600 Sak 158,800.00 692,368.00
Kerikil 0.8700 M3 1,900,000.00 1,653,000.00
Pasir 0.5200 M3 700,000.00 364,000.00
Pekerja 1.6500 OH 152,400.00 251,460.00
Tukang Batu 0.2500 OH 203,200.00 50,800.00
Kepala Tukang Batu 0.0250 OH 266,700.00 6,667.50
Mandor 0.0800 OH 330,200.00 26,416.00
3,044,711.50
33 1 M2 PEK. FLOOR LANTAI
Semen 0.012 Sak 158,800.00 1,905.60
Amplas 0.100 Lbr 15,000.00 1,500.00
Pekerja 0.150 OH 152,400.00 22,860.00
Tukang Batu 0.100 OH 203,200.00 20,320.00
Kepala Tukang 0.010 OH 266,700.00 2,667.00
49,252.60
34 1 M3 PEKERJAAN PENIMBUNAN
Karang timbunan 1.2000 M3 450,000.00 540,000.00
Pekerja 0.3000 OH 152,400.00 45,720.00
Mandor 0.0100 OH 266,700.00 2,667.00
588,387.00
35 1 BH KLOSED JONGKOK
Klosed jongkok 1.0000 Bh 1098600 1,098,600.00
Semen 0.1200 Zak 172500 20,700.00
Pasir 0.0100 M3 700000 7,000.00
Pekerja 1.0000 OH 152,400.00 152,400.00
Tukang 1.5000 OH 203,200.00 304,800.00
Kepala tukang 1.5000 OH 266,700.00 400,050.00
Mandor 0.1500 OH 330,200.00 49,530.00
2,033,080.00
36 1 M PIPA PVC 4 "
Pipa PVC 4" 1.2000 M' 90,500.00 108,600.00
Perlengkapan 1.0000 set 38,010.00
Pekerja 0.0810 OH 152,400.00 12,344.40
Tukang batu 0.1350 OH 203,200.00 27,432.00
Kepala tukang 0.0135 OH 266,700.00 3,600.45
Mandor 0.0041 OH 330,200.00 1,353.82
191,340.67
37 1 M PIPA PVC 1,5"
Pipa PVC 1,5" 1.2000 M' 23,987.50 28,785.00
Perlengkapan 1.0000 set 10,074.75
Pekerja 0.0360 OH 152,400.00 5,486.40
Tukang batu 0.0600 OH 203,200.00 12,192.00
Kepala tukang 0.0060 OH 266,700.00 1,600.20
Mandor 0.0018 OH 330,200.00 594.36
58,732.71
38 1 M PIPA PVC 0,5"
Pipa PVC 1,5" 1.2000 M' 9,525.00 11,430.00
Perlengkapan 1.0000 set 4,000.50
Pekerja 0.0360 OH 152,400.00 5,486.40
Tukang batu 0.0600 OH 203,200.00 12,192.00
Kepala tukang 0.0060 OH 266,700.00 1,600.20
Mandor 0.0018 OH 330,200.00 594.36
35,303.46
39 1 BH KRAN AIR 0,5"
Kran air 0,5" 1.0000 Bh 43,430.00 43,430.00
Seal tape 0.0250 Bh 15,000.00 375.00
Pekerja 0.0100 OH 152,400.00 1,524.00
Tukang batu 0.1000 OH 203,200.00 20,320.00
Kepala tukang 0.0100 OH 266,700.00 2,667.00
Mandor 0.0500 OH 330,200.00 16,510.00
84,826.00
DAFTAR HARGA BAHAN

Pekerjaan : Pembangunan Pustu Bora-bora


Lokasi : Bora-bora Distrik Tor atas, Kabupaten Sarmi
Tahun : 2022

No JENIS BAHAN/MATERIAL SATUAN HARGA (Rp)


a b d e
A. HARGA BAHAN
1 Balok ky besi M3 4,500,000.00
2 Papan ky besi M3 4,500,000.00
3 Balok ky matoa M3 4,127,500.00
4 Papan ky matoa M3 4,127,500.00
5 Kayu 5/7 M3 4,127,500.00
6 Kayu papan 3/20 M3 4,500,000.00
7 Dolken dia. 8-10 cm/4 M btg 50,000.00
8 Kayu profil M' 60,000.00
9 Batu karang M3 700,000.00
10 Karang Timbunan M3 450,000.00
11 Tripleks 3 mm Lbr 120,000.00
12 Lampu philips 40 watt set 230,100.00
13 Lampu philips 25 watt set 119,600.00
14 Stop kontak bh 33,800.00
15 Box limit + limit unit 136,500.00
16 Saklar bh 42,900.00
17 Kabel listrik m' 9,880.00
18 Besi strip Kg 19,000.00
19 Cat dasar/cat kayu Kg 71,500.00
20 Cat penutup/cat kayu Kg 71,500.00
21 Cat dasar/cat tembok Kg 11,375.00
24 Cat penutup/cat tembok Kg 11,375.00
25 Cat atap Kg
26 Plamir Kg 31,800.00
27 Cat meni Kg 45,500.00
28 Ampelas Lbr 15,000.00
29 Politur Ltr 34,300.00
30 Politur jadi Ltr 34,300.00
31 Lem kayu Ltr 45,500.00
32 Paku biasa campuran Kg 26,000.00
33 Paku seng Kg 32,500.00
34 Pasir beton M3 700,000.00
35 Koral beton M3 1,900,000.00
36 Klosed jongkok Bh 1,098,600.00
37 Pipa PVC 4" M' 90,500.00
38 Pipa PVC 1/2" M' 9,525.00
39 Pipa PVC 1 1/2" M' 23,987.50
40 Kran Air 1/2" Bh 43,430.00
41 Semen portland kg 3,450.00
42 Seng metal Soka/Sejenis Lbr 195,000.00
43 Nok seng metal Soka/sejenis bh 92,900.00
44 Kunci tanam royal besar Bh 260,000.00
45 Engsel Kupu-kupu Ring Nilon pintu Bh 41,600.00
46 Engsel Kupu-kupu Ring Nilon jendela Bh 39,000.00
47 Hak Angin Biasa Bh 39,000.00
48 Pegangan pintu/jendela Bh 15,000.00
49 Grendel Jendela (Klip) Bh 23,400.00
50 Kaca polos/bening 5 mm M2 643,890.00
51 Baut dia 12 mm Bh 20,000.00
a b d e
B. UPAH TUKANG
1 Pekerja Orang/hari 152,400.00
2 Tukang kayu/batu/besi Orang/hari 203,200.00
3 Kepala tukang kayu/batu/besi Orang/hari 266,700.00
4 Mandor Orang/hari 330,200.00
BOBOT PRESTASI KEMAJUAN PEKERJAAN
TANGGAL
PEKERJAAN : Pembangunan Perumahan Komunitas Adat Tradisional (KAT) Type 36

INSTANSI : DINAS SOSIAL KABUPATEN SARMI.


NOMOR SPK : 06/SPK-OTSUS/DINSOS/2017, tanggal 27 Agustus 2017
HARGA BORONGAN : Rp.225.700.000
LOKASI : AMSIRA DISTRIK FERKAM KABUPATEN SARMI
KONTRAKTOR : CV. CITRA NARANSOM PERKASA
KONSULTAN PENGAWAS : CV. FURIATAMA CONSULTANT

NILAI KEMAJUAN
NO. URAIAN PEKERJAAN REALISASI
VOLUME SAT BOBOT PEKERJAA
BOBOT (%)
(%) N (%)
a b c d e f g
I. PEKERJAAN PERSIAPAN
1 Pembersihan lokasi 119.00 M2 0.694 100 0.69
2 Barak kerja/direksi keet & gudang 30.00 M2 2.864 100 2.86
4 Papan nama kegiatan 1.00 Bh 0.275 100 0.28

II. PEKERJAAN KAYU


1 Pasang bouwplank 48.00 M' 1.201 100 1.20
2 Kolom kayu besi 10/10 cm 1.24 M3 1.555 100 1.56
4 Ring balok kayu besi 5/10 cm 0.56 M3 0.700 100 0.70
5 Dinding papan kayu besi t = 2 cm 315.00 M2 17.908 100 17.91
6 Pasang top gavel 0.70 M2 0.040 100 0.04
7 Kuda - kuda kayu Besi 5/10 1.47 M3 2.345 100 2.35
8 Balok Ikatan Angin kayu Besi 5/10 0.19 M3 0.306 100 0.31
9 Gording kayu matoa 5/10 1.29 M3 1.568 100 1.57
10 Kusen pintu, jendela dan ventilasi ky bs 5/10 cm 0.91 M3 1.772 100 1.77
11 Jalusi kayu besi 8.00 M2 1.202 100 1.20
12 Jendela ungkit kaca ky besi 17.25 M2 2.426 100 2.43
14 Pintu panel kayu besi 20.66 M2 3.783 100 3.78
### #REF! #REF! #REF! #REF! 100 #REF!
15 Tangga kayu 0.15 M3 0.292 100 0.29

III. PEKERJAAN BETON


1 Pek. Pas. Pondasi batu karang 8.75 M3 0.000 100 0.00
1 Pek. Cor Lantai KM/WC 0.32 M3 0.176 100 0.18
### #REF! #REF! #REF! #REF! 100 #REF!
2 Floor Lantai KM/WC 4.50 M2 0.041 100 0.04

IV. PEKERJAAN ATAP


1 Atap metal soka 203.60 M2 7.423 100 7.42
2 Nok genteng metal soka 53.14 M' 1.903 100 1.90
3 Lisplank ky besi 2 x 2,5/30 61.00 M' 1.172 100 1.17
4 Plafond triplek 3 mm 161.08 M2 8.306 0 0.00
5 List plafond kayu matoa diprofil 240.00 M' 3.155 0 0.00

V. PEKERJAAN LANTAI
1 Lantai papan kayu besi t = 3 cm 80.09 M2 4.539 100 4.54
2 Pasang balok lantai kayu besi 5/15 dan 5/10 cm 80.09 M2 5.087 100 5.09

VI. PEKERJAAN PENGECATAN


1 Cat dinding 315.00 M2 4.913 0 0.00
2 Cat plafond 161.08 M2 0.664 0 0.00
3 Cat kusen pintu / jendela, daun pintu, daun jendela , -
jalusi dan lisplank 116.67 M2 1.820 0 0.00

VII. PEKERJAAN ALAT GANTUNG


1 Kunci tanam 2 SLAGG 10.00 Bh 0.749 0 0.00
2 Engsel pintu ring nylon 30.00 Bh 0.433 0 0.00
3 Grendel pintu 10.00 Bh 0.134 0 0.00
4 Engsel jendela ring nylon 50.00 Bh 0.585 0 0.00
5 Grendel jendela 50.00 Bh 0.668 0 0.00
6 Hak angin/kait angin 50.00 Bh 0.698 0 0.00
7 Hendle tarikan 50.00 Bh 1.270 0 0.00
8 Baut dia. 12 mm 60.00 Bh 0.425 0 0.00

VIII. PEKERJAAN LISTRIK


1 Pasang lampu Philips SL 40 watt 7.00 Bh 0.739 0 0.00
2 Pasang lampu Philips SL 25 wat 9.00 Bh 0.767 0 0.00
3 Pasang stop kontak 8.00 Bh 0.493 0 0.00
4 Pas. Box Limit 2.00 Bh 0.161 0 0.00
a b c d e f g
IX. PEKERJAAN AKHIR
1 Pekerjaan Pembersihan Akhir 1.00 Ls 0.417 0 0.00
2 Foto dokumentasi dan pelaporan 1.00 Ls 0.286 0 0.00

JUMLAH #REF! #REF!

Kemajuan pekerjaan sampai saat ini sebesar 75.79 % (tujuh lima koma tujuh sembilan persen)
Demikian bobot prestasi kemajuan pekerjaan ini dibuat untuk dipergunakan sebagaimana mestinya.
Setuju dibuat, Dibuat Oleh :
KONTRAKTOR PELAKSANA KONSULTAN PENGAWAS
CV. CITRA NARANSOM PERKASA CV. FURIATAMA CONSULTANT

YONIAS KIM PUJI DWI ASTANTO


Direktur Kuasa Direktur
Mengetahui/ menyetujui,
PEJABAT PEMBUAT KOMITMEN
DINAS SOSIAL
Kabupaten sarmi

AGUSTINUS TANEM, SE, M.Ec.Dev


NIP. 19750827 200502 1 001
BOBOT PRESTASI KEMAJUAN PEKERJAAN
TANGGAL
PEKERJAAN : Pembangunan Perumahan Komunitas Adat Tradisional (KAT) Type 36

INSTANSI : DINAS SOSIAL KABUPATEN SARMI.


NOMOR SPK : 06/SPK-OTSUS/DINSOS/2017, tanggal 27 Agustus 2017
HARGA BORONGAN : Rp.225.700.000
LOKASI : AMSIRA DISTRIK FERKAM KABUPATEN SARMI
KONTRAKTOR : CV. CITRA NARANSOM PERKASA
KONSULTAN PENGAWAS : CV. FURIATAMA CONSULTANT

NILAI KEMAJUAN
NO. URAIAN PEKERJAAN REALISASI
VOLUME SAT BOBOT PEKERJAA
BOBOT (%)
(%) N (%)
a b c d e f g
I. PEKERJAAN PERSIAPAN
1 Pembersihan lokasi 119.00 M2 0.69 100 0.69
2 Barak kerja/direksi keet & gudang 30.00 M2 2.86 100 2.86
4 Papan nama kegiatan 1.00 Bh 0.28 100 0.28

II. PEKERJAAN KAYU


1 Pasang bouwplank 48.00 M' 1.20 100 1.20
2 Kolom kayu besi 10/10 cm 1.24 M3 1.56 100 1.56
4 Ring balok kayu besi 5/10 cm 0.56 M3 0.70 100 0.70
5 Dinding papan kayu besi t = 2 cm 315.00 M2 17.91 100 17.91
6 Pasang top gavel 0.70 M2 0.04 100 0.04
7 Kuda - kuda kayu Besi 5/10 1.47 M3 2.35 100 2.35
8 Balok Ikatan Angin kayu Besi 5/10 0.19 M3 0.31 100 0.31
9 Gording kayu matoa 5/10 1.29 M3 1.57 100 1.57
10 Kusen pintu, jendela dan ventilasi ky bs 5/10 cm 0.91 M3 1.77 100 1.77
11 Jalusi kayu besi 8.00 M2 1.20 100 1.20
12 Jendela ungkit kaca ky besi 17.25 M2 2.43 0 0.00
14 Pintu panel kayu besi 20.66 M2 3.78 0 0.00
### #REF! #REF! #REF! #REF! 0 #REF!
15 Tangga kayu 0.15 M3 0.29 0 0.00

III. PEKERJAAN BETON


1 Pek. Pas. Pondasi batu karang 8.75 M3 0.00 100 0.00
1 Pek. Cor Lantai KM/WC 0.32 M3 0.18 100 0.18
### #REF! #REF! #REF! #REF! 100 #REF!
2 Floor Lantai KM/WC 4.50 M2 0.04 0 0.00

IV. PEKERJAAN ATAP


1 Atap metal soka 203.60 M2 7.42 100 7.42
2 Nok genteng metal soka 53.14 M' 1.90 1 0.02
3 Lisplank ky besi 2 x 2,5/30 61.00 M' 1.17 0 0.00
4 Plafond triplek 3 mm 161.08 M2 8.31 0 0.00
5 List plafond kayu matoa diprofil 240.00 M' 3.15 0 0.00

V. PEKERJAAN LANTAI
1 Lantai papan kayu besi t = 3 cm 80.09 M2 4.54 0 0.00
2 Pasang balok lantai kayu besi 5/15 dan 5/10 cm 80.09 M2 5.09 0 0.00

VI. PEKERJAAN PENGECATAN


1 Cat dinding 315.00 M2 4.91 0 0.00
2 Cat plafond 161.08 M2 0.66 0 0.00
3 Cat kusen pintu / jendela, daun pintu, daun jendela , -
jalusi dan lisplank 116.67 M2 1.82 0 0.00

VII. PEKERJAAN ALAT GANTUNG


1 Kunci tanam 2 SLAGG 10.00 Bh 0.75 0 0.00
2 Engsel pintu ring nylon 30.00 Bh 0.43 0 0.00
3 Grendel pintu 10.00 Bh 0.13 0 0.00
4 Engsel jendela ring nylon 50.00 Bh 0.58 0 0.00
5 Grendel jendela 50.00 Bh 0.67 0 0.00
6 Hak angin/kait angin 50.00 Bh 0.70 0 0.00
7 Hendle tarikan 50.00 Bh 1.27 0 0.00
8 Baut dia. 12 mm 60.00 Bh 0.42 0 0.00

VIII. PEKERJAAN LISTRIK


1 Pasang lampu Philips SL 40 watt 7.00 Bh 0.74 0 0.00
2 Pasang lampu Philips SL 25 wat 9.00 Bh 0.77 0 0.00
3 Pasang stop kontak 8.00 Bh 0.49 0 0.00
4 Pas. Box Limit 2.00 Bh 0.16 0 0.00
a b c d e f g
IX. PEKERJAAN AKHIR
1 Pekerjaan Pembersihan Akhir 1.00 Ls 0.42 0 0.00
2 Foto dokumentasi dan pelaporan 1.00 Ls 0.29 0 0.00

JUMLAH #REF! #REF!

Kemajuan pekerjaan sampai saat ini sebesar 55.26 % (Lima lima koma dua enam persen)
Demikian bobot prestasi kemajuan pekerjaan ini dibuat untuk dipergunakan sebagaimana mestinya.
Setuju dibuat, Dibuat Oleh :
KONTRAKTOR PELAKSANA KONSULTAN PENGAWAS
CV. CITRA NARANSOM PERKASA CV. FURIATAMA CONSULTANT

YONIAS KIM PUJI DWI ASTANTO


Direktur Kuasa Direktur
BOBOT PRESTASI KEMAJUAN PEKERJAAN
TANGGAL
PEKERJAAN : Pembangunan Perumahan Komunitas Adat Tradisional (KAT) Type 36

INSTANSI : DINAS SOSIAL KABUPATEN SARMI.


NOMOR SPK : 06/SPK-OTSUS/DINSOS/2017, tanggal 27 Agustus 2017
HARGA BORONGAN : Rp.225.700.000
LOKASI : AMSIRA DISTRIK FERKAM KABUPATEN SARMI
KONTRAKTOR : CV. CITRA NARANSOM PERKASA
KONSULTAN PENGAWAS : CV. FURIATAMA CONSULTANT

NILAI KEMAJUAN
NO. URAIAN PEKERJAAN REALISASI
VOLUME SAT BOBOT PEKERJAA
BOBOT (%)
(%) N (%)
a b c d e f g
I. PEKERJAAN PERSIAPAN
1 Pembersihan lokasi 119.00 M2 0.694 100 0.69
2 Barak kerja/direksi keet & gudang 30.00 M2 2.864 100 2.86
4 Papan nama kegiatan 1.00 Bh 0.275 100 0.28

II. PEKERJAAN KAYU


1 Pasang bouwplank 48.00 M' 1.201 100 1.20
2 Kolom kayu besi 10/10 cm 1.24 M3 1.555 100 1.56
4 Ring balok kayu besi 5/10 cm 0.56 M3 0.700 100 0.70
5 Dinding papan kayu besi t = 2 cm 315.00 M2 17.908 100 17.91
6 Pasang top gavel 0.70 M2 0.040 100 0.04
7 Kuda - kuda kayu Besi 5/10 1.47 M3 2.345 100 2.35
8 Balok Ikatan Angin kayu Besi 5/10 0.19 M3 0.306 100 0.31
9 Gording kayu matoa 5/10 1.29 M3 1.568 100 1.57
10 Kusen pintu, jendela dan ventilasi ky bs 5/10 cm 0.91 M3 1.772 100 1.77
11 Jalusi kayu besi 8.00 M2 1.202 100 1.20
12 Jendela ungkit kaca ky besi 17.25 M2 2.426 100 2.43
14 Pintu panel kayu besi 20.66 M2 3.783 100 3.78
### #REF! #REF! #REF! #REF! 100 #REF!
15 Tangga kayu 0.15 M3 0.292 100 0.29

III. PEKERJAAN BETON


1 Pek. Pas. Pondasi batu karang 8.75 M3 0.000 100 0.00
1 Pek. Cor Lantai KM/WC 0.32 M3 0.176 100 0.18
### #REF! #REF! #REF! #REF! 100 #REF!
2 Floor Lantai KM/WC 4.50 M2 0.041 100 0.04

IV. PEKERJAAN ATAP


1 Atap metal soka 203.60 M2 7.423 100 7.42
2 Nok genteng metal soka 53.14 M' 1.903 100 1.90
3 Lisplank ky besi 2 x 2,5/30 61.00 M' 1.172 100 1.17
4 Plafond triplek 3 mm 161.08 M2 8.306 100 8.31
5 List plafond kayu matoa diprofil 240.00 M' 3.155 100 3.15

V. PEKERJAAN LANTAI
1 Lantai papan kayu besi t = 3 cm 80.09 M2 4.539 100 4.54
2 Pasang balok lantai kayu besi 5/15 dan 5/10 cm 80.09 M2 5.087 100 5.09

VI. PEKERJAAN PENGECATAN


1 Cat dinding 315.00 M2 4.913 100 4.91
2 Cat plafond 161.08 M2 0.664 100 0.66
3 Cat kusen pintu / jendela, daun pintu, daun jendela , -
jalusi dan lisplank 116.67 M2 1.820 100 1.82

VII. PEKERJAAN ALAT GANTUNG


1 Kunci tanam 2 SLAGG 10.00 Bh 0.749 100 0.75
2 Engsel pintu ring nylon 30.00 Bh 0.433 100 0.43
3 Grendel pintu 10.00 Bh 0.134 100 0.13
4 Engsel jendela ring nylon 50.00 Bh 0.585 100 0.58
5 Grendel jendela 50.00 Bh 0.668 100 0.67
6 Hak angin/kait angin 50.00 Bh 0.698 100 0.70
7 Hendle tarikan 50.00 Bh 1.270 100 1.27
8 Baut dia. 12 mm 60.00 Bh 0.425 100 0.42

VIII. PEKERJAAN LISTRIK


1 Pasang lampu Philips SL 40 watt 7.00 Bh 0.739 100 0.74
2 Pasang lampu Philips SL 25 wat 9.00 Bh 0.767 100 0.77
3 Pasang stop kontak 8.00 Bh 0.493 100 0.49
4 Pas. Box Limit 2.00 Bh 0.161 100 0.16
a b c d e f g
IX. PEKERJAAN AKHIR
1 Pekerjaan Pembersihan Akhir 1.00 Ls 0.417 100 0.42
2 Foto dokumentasi dan pelaporan 1.00 Ls 0.286 100 0.29

JUMLAH #REF! #REF!

Kemajuan pekerjaan sampai saat ini sebesar 100 % (seratus persen)


Demikian bobot prestasi kemajuan pekerjaan ini dibuat untuk dipergunakan sebagaimana mestinya.
Setuju dibuat, Dibuat Oleh :
KONTRAKTOR PELAKSANA KONSULTAN PENGAWAS
CV. CITRA NARANSOM PERKASA CV. FURIATAMA CONSULTANT

YONIAS KIM PUJI DWI ASTANTO


Direktur Kuasa Direktur
Mengetahui/ menyetujui,
PEJABAT PEMBUAT KOMITMEN
DINAS SOSIAL
Kabupaten sarmi

AGUSTINUS TANEM, SE, M.Ec.Dev


NIP. 19750827 200502 1 001