HRG.SATUAN JUMLAH
No. URAIAN PEKERJAAN VOLUME SAT
Rp. Rp.
1 2 3 4 5 6
I. PEKERJAAN PERSIAPAN
2 Pengukuran/ Pasang Bouwplank 46.00 M' 82,795.00 3,808,570.00
SUB JUMLAH Rp 3,808,570.00
II. PEKERJAAN TANAH DAN PASIR
1 Galian Tanah Pondasi 35.50 M3 101,275.00 3,595,647.35
2 Urugan Tanah Kembali 13.16 M3 33,758.00 444,138.81
3 Urugan Tanah Timbun Peninggian Lantai 33 Cm 25.39 M3 365,768.00 9,288,129.71
4 Urugan Pasir Bawah Lantai & Pondasi 5 Cm 6.37 M3 760,510.00 4,841,026.41
SUB JUMLAH Rp 18,168,942.27
III. PEKERJAAN BETON / PASANGAN / PLESTERAN
1 Pondasi Batu Bata 1 PC : 4 PS 17.00 M3 2,140,717.00 36,384,696.49
2 Cor Beton Bertulang Sloof 15/20 + Bekisting 1.89 M3 6,743,219.00 12,734,569.08
3 Cor Beton Bertulang Kolom 20/20 + Bekisting 2.70 M3 11,240,604.00 30,327,149.59
4 Cor Beton Bertulang Kolom 15/15 + Bekisting 0.48 M3 11,240,604.00 5,387,059.47
5 Cor Beton Bertulang Kolom 10/10 (Kolom Praktis) 10.65 M' 100,801.00 1,073,530.65
6 Cor Beton Bertulang Ringbalk 15/20 + Bekisting 2.57 M3 9,132,980.00 23,443,218.04
7 Cor Beton Bertulang Ringbalk 15/35 + Bekisting 0.37 M3 9,132,980.00 3,356,370.15
8 Dinding Pasangan Bata 1/3 Bata 1Pc :3Psr 37.22 M3 2,140,717.00 79,686,852.38
9 Plesteran Dinding luar dalam Tebal 15 mm 403.70 M2 97,170.00 39,227,431.83
10 Cor Lantai tebal 7cm 5.39 M3 5,473,761.00 29,484,413.63
11 Cor Dag tebal 12cm dan Kanopi 0.95 M3 5,641,821.00 5,346,189.58
SUB JUMLAH Rp 266,451,480.88
IV. PEKERJAAN KAYU
1 Rangka Plafond Kayu Bus 106.95 M2 110,336.00 11,800,435.20
2 Plafond tripleks 106.95 M2 69,607.00 7,444,468.65
3 Kusen pintu dan jendela 0.75 M3 8,940,160.00 6,712,093.32
SUB JUMLAH Rp 25,956,997.17
V. PEKERJAAN ATAP
1 Rangka Kuda-Kuda Kayu Bus,5/10 1.48 M3 7,329,490.00 10,821,039.15
2 Gording Kayu Bus, 5/10 0.98 M3 6,190,685.00 6,095,348.45
3 Kaso kayu Bus, 5/5 0.62 M3 6,190,685.00 3,833,272.15
4 Reng kayu bus, 3/2 0.24 M3 6,190,685.00 1,462,883.63
5 Pas. Atap Sakura Roof 130.82 M2 89,281.00 11,679,383.30
6 Bubungan/Nok atap Sakura roof 10.30 M' 102,125.00 1,051,887.50
7 Listplank papan kayu bus 2x 2/20 104.80 M' 72,636.00 7,612,252.80
SUB JUMLAH Rp 42,556,066.98
VI. PEKERJAAN PASANG MEMASANG
1 Pas Pintu Utama Panel Papan lebar 70cm (double) 2.00 BH 2,071,718.00 4,143,436.00
2 Pas Pintu Panel Papan 80cmx210cm 3.00 BH 2,113,906.00 6,341,718.00
3 Pas. Pintu Panel Papan 70cmx210cm 1.00 BH 2,071,718.00 2,071,718.00
4 Pas. Pintu Kamar mandi 70cmx210cm 1.00 BH 2,563,173.00 2,563,173.00
5 Pas. Jendela Kaca Ungkit 40cm x 190cm 2.00 BH 624,185.00 1,248,370.00
6 Pas. Jendela Kaca Ungkit 50cm x 170cm 4.00 BH 624,185.00 2,496,740.00
7 Pas. Jendela Kaca Ungkit 40cm x 115cm 2.00 BH 624,185.00 1,248,370.00
8 Pas. Jendela Kaca Ungkit 60cm x 35cm 2.00 BH 326,802.00 653,604.00
Pas. Jendela Kaca Ungkit 40cm x 40cm 2.00 BH 312,092.50 624,185.00
9 Pas. Keramik Lantai 40x40 76.39 M2 298,502.00 22,802,567.78
10 Pas. Ubin Lantai dan dinding Kamar mandi 20x20 14.04 M2 317,813.00 4,462,094.52
SUB JUMLAH Rp 48,655,976.30
VII. PEKERJAAN PENGECATAN
1 Cat Residu 44.29 M2 25,728.00 1,139,521.42
2 Cat Meny Kayu 22.52 M2 18,825.00 424,003.01
3 Cat Tembok + Plafond 510.65 M2 19,192.00 9,800,375.61
4 Cat Kilat Kayu 22.52 M2 71,027.00 1,599,769.53
SUB JUMLAH Rp 12,963,669.57
REKAPITULASI
I PEKERJAAN PERSIAPAN ……………………………….. Rp 3,808,570.00
TERBILANG : EMPAT RATUS DELAPAN BELAS JUTA LIMA RATUS ENAM PULUH RIBU RUPIAH
Merauke, Oktober2018
Pemohon,
ANALISA HARGA SATUAN
PEKERJAAN : PEMBANGUNAN RUMAH PRIBADI PERMANEN LUAS 76.95 M2
LOKASI : DISTRIK MERAUKE
KAB. / PROVINSI : MERAUKE - PAPUA
TAHUN : 2018
HARGA JUMLAH
No. URAIAN PEKERJAAN ANALISA
SATUAN HARGA
1 2 4 5 6 = (4) x (5)
I. PEKERJAAN PERSIAPAN