BILL OF QUANTITY (BOQ)

KEGIATAN : PEMBANGUNAN SIRING/DINDING PENAHAN TANAH


PEKERJAAN : PEMBANGUNAN SIRING/DINDING PENAHAN TANAH SD NEGERI 021 BALIKPAPAN TENGAH
LOKASI : RT.20 KEL. KARANG JATI BALIKPAPAN TENGAH KOTA BALIKPAPAN

NO URAIAN PEKERJAAN SATUAN ANALISA VOLUME HARGA SATUAN JUMLAH HARGA

1 2 3 4 5 6 7
I PEKERJAAN PERSIAPAN
A Air dan listrik kerja Ls 1.00 2,500,000.00 2,500,000.00
B Mobilisasi dan Demobilsasi Ls 1.00 5,000,000.00 5,000,000.00
C Pekerjaan sondir Min.Qc = 250 kg/cm2 Ls 1.00 5,000,000.00 5,000,000.00
D Pembongkaran Paving Block M2 291.00 45,800.00 13,327,800.00
SUB TOTAL I 25,827,800.00
II PEKERJAAN TANAH
A Pembersihan M2 523.57 100,000.00 52,357,000.00
B Timbunan Tanah M3 72.27 150,000.00 10,839,750.00
SUB TOTAL II 63,196,750.00
III PEKERJAAAN SIRING / DINDING PENAHAN TANAH
A SIRING/TURAP BETON TYPE 1
1 Galian Tanah M3 75.44 107,008.85 8,072,212.60
2 Urugan pasir M3 3.21 156,000.00 500,760.00
3 Lantai Kerja tebal 100 mm mutu beton f'c =9,8 Mpa (K125) M3 6.42 1,153,700.00 7,406,754.00
4 Urugan kembali M3 22.63 80,210.63 1,815,206.66
5 Pembesian besi ulir KG 7,805.92 17,919.55 139,878,528.94
6 Bekesting M2 353.10 150,971.67 53,308,096.68
7 Pekerjaan weep hole PVC Ø2" + Ijuk M' 54.00 48,951.98 2,643,406.92
8 Cor Beton Mutu f'c =26,4 Mpa (K300) M3 99.51 2,965,079.73 295,055,083.93
B SIRING/TURAP BETON TYPE 2
1 Galian Tanah M3 92.15 107,008.85 9,860,865.53
2 Urugan pasir M3 2.91 156,000.00 453,960.00
3 Lantai Kerja mutu beton f'c =9,8 Mpa (K125) M3 5.82 1,153,700.00 6,714,534.00
4 Urugan kembali M3 27.65 80,210.63 2,217,422.87
5 Pembesian besi ulir KG 5,481.71 17,919.55 98,229,821.23
6 Bekesting M2 271.60 150,971.67 41,003,905.57
7 Pekerjaan weep hole PVC Ø2" + Ijuk M' 48.00 48,951.98 2,349,695.04
8 Cor Beton Mutu f'c =26,4 Mpa (K300) M3 78.09 2,965,079.73 231,528,250.72
SUB TOTAL III 901,038,504.68
IV PEKERJAAN SALURAN DRAINASE
A SALURAN DRAINASE
1 Urugan pasir M3 0.97 156,000.00 151,320.00
3 Lantai Kerja mutu beton f'c =9,8 Mpa (K125) M3 1.94 1,153,700.00 2,238,178.00
4 Pembesian polos KG 897.01 17,919.55 16,073,970.75
5 Bekesting M2 33.95 150,971.67 5,125,488.20
6 Cor Beton Mutu f'c =21,7 Mpa (K250) M3 3.88 2,315,156.06 8,982,805.51
SUB TOTAL IV 32,571,762.46
V PEKERJAAN AKSES JALAN
A AKSES JALAN MASUK
1 Plastik Cor M2 25.65 4,307.27 110,481.48
2 Perkerasan Beton Semen Mutu Beton K-250 t=15cm M3 3.85 2,434,663.19 9,367,366.62
SUB TOTAL V 9,477,848.10
VI PEKERJAAN LAPANGAN UPACARA
A LAPANGAN UPACARA
1 Plastik Cor M2 363.75 4,307.27 1,566,769.46
2 Perkerasan Beton Semen Mutu Beton K-250 t=15cm M3 54.56 2,434,663.19 132,841,310.30
SUB TOTAL VI 134,408,079.77
VII PEKERJAAN LAIN-LAIN
A PAGAR PASANGAN BATA
1 Pagar Pangan Bata Finishing Cat t=120cm M2 48.50 900,000.00 43,650,000.00
SUB TOTAL VI 43,650,000.00