RENCANA ANGGARAN BIAYA (RAB)

RUMAH TINGGAL 2 LANTAI

NO URAIAN PEKERJAAN VOLUME SAT. HARGA SATUAN JUMLAH HARGA


I PEKERJAAN PERSIAPAN
Pembersihan Lahan 1 Ls 500,000.00 500,000.00
Pembuatan Strager 3 Buah 427,444.00 1,282,332.00
Pemasangan Pagar BRC Galvanis 160 M2 31,376.00 5,020,160.00
JUMLAH I 6,802,492.00
II PEKERJAAN PONDASI
A Pekerjaan Pemasangan Batu Gunung
Galian Tanah Pondasi Batu Kali 69.92 M3 83,737.00 5,854,891.04
Galian Tanah Pondasi Poer 22.5 M3 85,000.00 1,912,500.00
Urugan Pasir Bawah Pondasi 2.21 M3 244,695.00 540,286.56
Pas. Batu Kosong (Aanstamping) 1.47 M3 444,427.50 654,197.28
Pondasi Batu Kali 38.64 M3 751,885.00 29,052,836.40
Urugan Tanah Bekas Galian 23.11 M3 60,225.00 1,391,498.63
JUMLAH A 39,406,209.91
B Pekerjaan Sloof 20 x 40
1. Bekisting ( 2 kali pakai) 7.36 M3 2,675,750.00 19,693,520.00
a. Kayu Kelas III M2 2,100,000.00
b. Paku 5 - 10 cm Kg 30,000.00
c. Minyak Bekisting Ltr 45,750.00
d. Tenaga Kerja Borong 500,000.00
2. Pembesian 53.67 Buah 529,000.00 28,389,666.67
a. Besi Beton kg 13,000.00
b. Kawat Besi kg 16,000.00
c. Tenaga Kerja Borong 500,000.00
3. Beton K250 7.36 M3 1,209,587.50 8,902,564.00
JUMLAH B 56,985,750.67
JUMLAH II (A+B) 96,391,960.57
III PEKERJAAN BETON
A Pekerjaan Kolom uk.40 x 40
1. Bekisting ( 2 kali pakai ) 14.72 M3 2,375,750.00 34,971,040.00
a. Kayu Kelas III M2 2,100,000.00
b. Paku 5 - 10 cm Kg 30,000.00
c. Minyak Bekisting Ltr 45,750.00
d. Plywood 9 mm Lmbr 200,000.00
2. Pembesian 46 Buah 529,000.00 24,334,000.00
a. Besi Beton Kg 13,000.00
b. Kawat Besi Kg 16,000.00
c. Tenaga Kerja Borong 500,000.00
3. Beton K250 14.72 M3 1,209,587.50 17,805,128.00
JUMLAH A 77,110,168.00
B Pekerjaan Balok uk.20 x 40
1. Bekisting ( 2 kali pakai ) 7.36 M3 2,375,750.00 17,485,520.00
a. Kayu Kelas III M2 2,100,000.00
b. Paku 5 - 10 cm Kg 30,000.00
c. Minyak Bekisting Ltr 45,750.00
d. Plywood 9 mm Lmbr 200,000.00
2. Pembesian 53.67 Buah 529,000.00 28,389,666.67
a. Besi Beton Kg 13,000.00
b. Kawat Besi Kg 16,000.00
c. Tenaga Kerja Borong 500,000.00
3. Beton K250 7.36 M3 1,209,587.50 8,902,564.00
JUMLAH B 54,777,750.67
C Pekerjaan Ringbalk uk.30 x 15
1. Bekisting ( 2 kali pakai ) 4.392 M3 2,375,750.00 10,434,294.00
a. Kayu Kelas III M2 2,100,000.00
b. Paku 5 - 10 cm Kg 30,000.00
c. Minyak Bekisting Ltr 45,750.00
d. Plywood 9 mm Lmbr 200,000.00
2. Pembesian 48.8 Buah 529,000.00 25,815,200.00
a. Besi Beton Kg 13,000.00
b. Kawat Besi Kg 16,000.00
c. Tenaga Kerja Borong 500,000.00
3. Beton K250 4.39 M3 1,209,587.50
JUMLAH C 36,249,494.00
JUMLAH III (A+B+C) 168,137,412.67
IV PEKERJAAN DINDING
Pekerjaan Batu Bata
1. Pas Batu Bata + Spesi 83.42 M3 270,503.70 22,566,500.67
2. Plesteran 83.42 M2 44,995.72 3,753,722.95
JUMLAH IV 26,320,223.61
V PEKERJAAN KAYU
1. Kusen Pintu dan Kusen Jendela Kelas I 0.79 M3 6,870,050.00 5,426,240.29
2. Kayu Untuk Kuda-Kuda 6.82 M3 3,560,000.00 24,279,200.00
3. Pintu 70 9 Buah 545,000.00 4,905,000.00
4. Pintu 150 2 Buah 1,170,000.00 2,340,000.00
5. Engsel Pintu 36 Buah 17,000.00 612,000.00
6. Kunci Pintu 10 Buah 185,000.00 1,850,000.00
7. Rangka Atap/Reng 30 Unit 75,000.00 2,250,000.00
JUMLAH V 41,662,440.29
VI FINISHING
1. Acian 83.42 M2 40,775.63 3,401,666.16
2. Cat Dasar 83.42 Kg 146,830.00 12,249,145.92
3. Cat 83.42 Kg 728,334.00 60,760,535.62
4. Kuas 5 Buah 10,000.00 50,000.00
5. Roll 3 Buah 11,000.00 33,000.00
6. Aplus 4 Sak 170,000.00 680,000.00
7. Amplas 4 M1 9,000.00 36,000.00
8. Bak Cat 4 Buah 8,000.00 32,000.00
9. Tenaga Kerja 3 OH 85,000.00 255,000.00
JUMLAH VI 77,497,347.69