ENGINEER ESTIMATE ( E E )
KEGIATAN : KEGIATAN PENYEDIAAN FASILITAS PELAYANAN, SARANA,
PEKERJAAN : PRASARANA DAN ALAT KESEHATAN UNTUK UKP RUJUKAN, UKM DAN UKM
RUJUKAN TINGKAT DAERAH PROVINSI SUB KEGIATAN PEMELIHARAAN
SARANA FASILITAS LAYANAN KESEHATAN
PEKERJAAN REHABILITASI GEDUNG IGD DAN JANTUNG TERPADU Lt.
3
drg. WAN FAJRIATUL MAMNUNAH, Sp.KG
NIP. 19780618 200903 2 001
ENGINEER ESTIMATE
INSTANSI : RSUD ARIFIN ACHMAD PEKANBARU
KEGIATAN PENYEDIAAN FASILITAS PELAYANAN, SARANA, PRASARANA DAN ALAT KESEHATAN UNTUK UKP RUJUKAN, UKM DAN UKM RUJUKAN TINGKAT DAERAH PROVINSI SUB
KEGIATAN PEMELIHARAAN SARANA FASILITAS LAYANAN KESEHATAN BELANJA
KEGIATAN : PEMELIHARAAN BANGUNAN GEDUNG-BANGUNAN GEDUNG TEMPAT KERJA-BANGUNAN GEDUNG KANTOR
PEKERJAAN REHABILITASI GEDUNG IGD DAN JANTUNG TERPADU Lt. 3
PEKERJAAN :
LOKASI : KOTA PEKANBARU
NILAI HPS : Rp2.690.793.000 TAHUN ANGGARAN 2022
0 PEKERJAAN PERSIAPAN
Pekerjaan Papan Nama Proyek Proyek 1.00 Unit 557,381.00
Mobilisasi dan Demobilisasi 1.00 Ls 12,475,000.00
Biaya SMK 3 Konstruksi
A Penyiapan RK3K
* Terdiri atas Pembuatan manual, prosedur, instruksi kerja, izin kerja 1.00 Set
750,000.00
1 PEKERJAAN PEMBONGKARAN
A Pembongkaran Dinding Bata 243.00 m2 94,888.18
B Pekerjaan Pembongkaran Kusen Pintu dan Jendela 20.00 Unit 142,334.50
C Pekerjaan Pembongkaran Lantai 605.87 m2 8,452.40
D Pekerjaan Pemindahan Material Bongkaran 42.44 m3 185,034.85
Total Pekerjaan Pembongkaran (1)
JUMLAH HARGA
557,381.00
12,475,000.00
750,000.00
300,000.00
150,000.00
500,000.00
500,000.00
1,800,000.00
150,000.00
900,000.00
165,000.00
1,475,000.00
4,350,000.00
750,000.00
3,468,918.92
100,000.00
75,000.00
75,000.00
75,000.00
75,000.00
75,000.00
450,000.00
300,000.00
29,516,299.92
23,057,827.25
2,846,690.00
5,121,055.59
7,853,526.66
38,879,099.50
9,660,050.40
26,454,377.52
31,841,861.04
16,357,297.56
13,263,442.66
13,841,311.77
111,418,340.95
3 PEKERJAAN LANTAI
A Pekerjaan Screed Lantai 2-3 cm 370.18 m2 88,851.50
B Pekerjaan Vinyl Lantai + Plint 370.18 m2 588,885.66
C Pekerjaan Lantai Homogenous 60x60 Polish 206.40 m2 423,209.27
D Pekerjaan Plint Lantai Homogenous 10x60 139.50 m2 43,751.51
D Pekerjaan Lantai Kamar Mandi Homogenous 60x60 Unpolish 8.10 m2 423,209.27
Total Pekerjaan Lantai (3)
60,170,652.00
9,865,560.00
8,264,682.00
9,123,900.00
4,422,064.00
5,696,534.00
330,000,000.00
110,000,000.00
537,543,392.00
348,400.00
7,698,900.00
813,900.00
502,400.00
3,000,000.00
12,363,600.00
9,469,906.99
2,025,672.82
11,495,579.81
ENGINEERING ESTIMATE (E.E)
PEKERJAAN MEKANIKAL ELEKTRIKAL PLUMBING
KEGIATAN KESEHATAN BELANJA PEMELIHARAAN BANGUNAN GEDUNG-BANGUNAN GEDUNG TEMPAT KERJA-BANGUNAN GEDUNG
: KANTOR
INSTALASI
- Instalasi Penerangan NYM 3 x 2,5 mm + pipa conduit ( Bongkar pasang/pasan ttk 71.00 Rp
SUB TOTAL
SUB TOTAL
7.3 PEKERJAAN AC
Page 4 of 35
UKM
KERJA-BANGUNAN GEDUNG
357,060 Rp 25,351,260
Rp 25,351,260
81,136 Rp 162,272
62,744 Rp 250,976
261,140 Rp 261,140
68,288 Rp 68,288
357,060 Rp 6,070,020
Rp 6,812,696
105,794,100 105,794,100
48,740,100 48,740,100
1,254,300 1,254,300
18,250,000 18,250,000
45,500,000 45,500,000
Magnehelic Secondary c/w Housing
Range : 0 - 500 Pa unit 1.00
Electric Heater
Kap : 7 Kw unit 1
Brand : Local or Equivalen
Control System
Sensor Temperature + PID Controller unit 1
Sensor Humidity + PID Controller
B.1.1. Instalasi Refrigerant Lengkap Dengan Isolasi, Fitting, Support dan jasa VRV syste
Ø 3/8" c.w/Isolasi m 25
Ø 7/8" c.w/Isolasi m 25
B.1.1.3 Pipa Drain PVC Lengkap Dengan Isolasi, Fitting, Support dan jasa
Ø 1" c.w/Isolasi m 16
B.1.3. Instalasi Refrigerant Lengkap Dengan Isolasi, Fitting, Support dan jasa VRV syste
Ø 1/4" c.w/Isolasi m 25.00
Ø 1/2" c.w/Isolasi m 25.00
B.1.3.2 Pipa Drain PVC Lengkap Dengan Isolasi, Fitting, Support dan jasa
Ø 1" c.w/Isolasi m 16.00
Page 5 of 35
4,500,000 4,500,000
4,500,000 4,500,000
3,000,000 3,000,000
1,500,000 1,500,000
175,000 175,000
1,500,000 1,500,000
3,500,000 3,500,000
850,000 850,000
850,000 850,000
157,000 3,925,000
468,000 11,700,000
35,000 560,000
1,052,000 4,208,000
295,000 295,000
2,755,000 2,755,000
1,028,000 1,028,000
5,256,000 5,256,000
4,500,000 4,500,000
35,000 525,000
35,000 875,000
45,000 3,375,000
285,000 9,975,000
8,500,000 8,500,000
350,000 700,000
350,000 700,000
138,000 3,450,000
183,000 4,575,000
35,000 560,000
35,000 1,050,000
35,000 1,750,000
45,000 5,850,000
B.1.5 Pemasangan unit Bekas R. OK
FXMQ 200 MAV4 unit 1.00
B.1.5. Instalasi Refrigerant Lengkap Dengan Isolasi, Fitting, Support dan jasa VRV syste
Ø 3/8" c.w/Isolasi m 25.00
Ø 7/8" c.w/Isolasi m 25.00
B.1.5.2 Pipa Drain PVC Lengkap Dengan Isolasi, Fitting, Support dan jasa
Ø 1" c.w/Isolasi m 16.00
SUB TOTAL
SUB TOTAL
SUB TOTAL
7.6 PEKERJAAN TELEPON
PERALATAN UTAMA
Instalasi
Page 6 of 35
1,500,000 1,500,000
157,000 3,925,000
468,000 11,700,000
35,000 560,000
423,000 26,226,000
1,828,000 1,828,000
2,755,000 2,755,000
2,197,000 2,197,000
35,000 525,000
35,000 875,000
45,000 3,150,000
2,800,000 2,800,000
3,000,000 3,000,000
Rp 377.066.500
Rp 434.588 Rp 869.176
Rp 271.304 Rp 813.912
Rp 366.300 Rp 8.058.600
Rp 9.741.688
Rp 941.248 Rp 941.248
Rp 250.976 Rp 250.976
Rp 203.940 Rp 203.940
Rp 195.624 Rp 195.624
Rp 457.688 Rp 457.688
Rp 178.992 Rp 178.992
Rp 359.832 Rp 8.635.968
Rp 258.368 Rp 258.368
Rp 11.122.804
Rp 256.520 Rp 256.520
Rp 128.260 Rp 128.260
- Instalasi Telepon ITC + conduit Tak Langsung / Extention ( Bongkar pasang/p ttk 4.00
SUB TOTAL
SUB TOTAL
SUB TOTAL
SUB TOTAL
SUB TOTAL
TOTAL PEKERJAAN ELEKTRIKAL LANTAI 3
8 PEKERJAAN MEKANIKAL
Lantai.3
a. Pemipaan Air Bersih
Pipa PPR PN.10
- dia. 1.5 " m' 6.00
- dia. 1" m' 36.00
- dia. 3/4" m' 36.00
- dia. 1/2" m' 36.00
- Fitting & Accessories lot 1.00
Rp 2.813.580
Rp 123.640 Rp 123.640
Rp 607.200 Rp 4.857.600
Rp 4.981.240
Rp 203.940 Rp 203.940
Rp 3.528.800 Rp 3.528.800
Rp 1.432.200 Rp 1.432.200
Rp 607.200 Rp 2.428.800
Rp 7.593.740
Rp 2.314.400 Rp 4.628.800
Rp 607.200 Rp 1.214.400
Rp 5.843.200
Rp 5.000.000 Rp 5.000.000
Rp -
Rp -
Rp 389.400 Rp 1.168.200
Rp 6.168.200
Rp 457.494.908
Rp 112.552 Rp 675.312
Rp 80.212 Rp 2.887.632
Rp 49.808 Rp 1.793.088
Rp 43.340 Rp 1.560.240
Rp 2.000.000 Rp 2.000.000
Rp 251.900 Rp 1.007.600
b. Pemipaan Air Kotor, Bekas & Vent
Pipa PVC Class D
- dia. 4" m' 43.00
- dia. 3" m' 23.00
- dia. 2.5" m' 42.00
- dia. 2" m' 52.00
Fitting & Accessories lot 1.00
SUB TOTAL
PEKERJAAN INTALASI
b. Lantai.3
Pipa Tembaga ( medical grade ASTM B819/B88 )
- dia. 1 3/8" m' 6.00
- dia. 1 1/8" m' 6.00
- dia. 7/8" m' 37.00
- dia. 3/4" m' 32.00
- dia. 5/8" m' 28.00
- Fitting & Accessories lot 1.00
SUB TOTAL
TOTAL PEKERJAAN MEKANIKAL LANTAI 3
Page 8 of 35
ENGINEER ESTIMATE
Rp 131.956 Rp 5.674.108
Rp 100.540 Rp 2.312.420
Rp 61.820 Rp 2.596.440
Rp 38.720 Rp 2.013.440
Rp 5.000.000 Rp 5.000.000
Rp 27.520.280
Rp 792.836 Rp 4.757.016
Rp 633.160 Rp 3.798.960
Rp 437.536 Rp 16.188.832
Rp 357.236 Rp 11.431.552
Rp 310.200 Rp 8.685.600
Rp 5.000.000 Rp 5.000.000
Rp 49.861.960
Rp 77.382.240
INSTANSI : RSUD ARIFIN ACHMAD PEKANBARU
KEGIATAN PENYEDIAAN FASILITAS PELAYANAN, SARANA, PRASARANA DAN ALAT KESEHATAN UNTUK UKP RUJUKAN, UKM DAN
KEGIATAN UKM RUJUKAN TINGKAT DAERAH PROVINSI SUB KEGIATAN PEMELIHARAAN SARANA FASILITAS LAYANAN KESEHATAN BELANJA
PEMELIHARAAN BANGUNAN GEDUNG-BANGUNAN GEDUNG TEMPAT KERJA-BANGUNAN GEDUNG KANTOR
:
PEKERJAAN : PEKERJAAN REHABILITASI GEDUNG IGD DAN JANTUNG TERPADU Lt. 3
LOKASI : KOTA PEKANBARU
NILAI HPS : 2.690.793.000,00
TAHUN ANGGARAN 2022
JUMLAH HARGA
7,518,962.58
1,567,835.68
2,964,979.93
12,051,778.19
177,793,034.79
33,676,143.01
10,996,749.77
76,173,436.51
2,327,650.99
9,745,911.88
310,712,926.93
174,200.00
5,132,600.00
542,600.00
251,200.00
1,500,000.00
7,600,600.00
15,000,000.00
10,000,000.00
10,000,000.00
78,900,000.00
40,698,000.00
22,788,000.00
8,327,000.00
24,938,000.00
17,700,000.00
45,540,000.00
23,998,000.00
18,348,000.00
19,285,000.00
17,816,000.00
37,990,000.00
6,210,000.00
9,500,000.00
47,875,000.00
15,000,000.00
469,913,000.00
792,677,705.12
ANALISA HARGA SATUAN
INSTANSI : PEMERINTAH PROVINSI RIAU
OPD : RSUD ARIFIN ACHMAD
PEKERJAAN REHABILITASI GEDUNG IGD DAN JANTUNG TERPADU
PEKERJAAN : Lt. 3
LOKASI : PEKANBARU
TAHUN ANGGARAN : 2022
B BAHAN
Besi beton (polos/ulir) kg 10.500 Rp 13,800.00 Rp 144,900.00
Kawat beton kg 0.150 Rp 21,000.00 Rp 3,150.00
JUMLAH HARGA BAHAN Rp 148,050.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 167,273.50
E Overhead & Profit (Contoh 15 %) 10% Rp 16,727.35
F Harga Satuan Pekerjaan (D+E) Rp 184,000.85
G Pembesian 1 kg dengan besi polos atau besi ulir Rp 18,400.09
C.5. Pemasangan 1 m2 Mini Wiremesh / Kawat Galvanis Panjang 240 cm
Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja OH 0.042 Rp 121,300.00 Rp 5,094.60
Tukang Besi OH 0.004 Rp 129,500.00 Rp 518.00
Kepala Tukang OH 0.002 Rp 145,700.00 Rp 291.40
Mandor OH 0.042 Rp 161,900.00 Rp 6,799.80
JUMLAH TENAGA KERJA Rp 12,703.80
B BAHAN
Kawat Jaring / Galvanish Lbr 0.143 Rp 900,000.00 Rp 129,060.00
JUMLAH HARGA BAHAN Rp 129,060.00
C PERALATAN
Mesin Las Jam 0.013 Rp 45,000.00
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 141,763.80
E Overhead & Profit (Contoh 15 %) 10% Rp 14,176.38
F Harga Satuan Pekerjaan (D+E) Rp 155,940.18
C.6. Pemasangan 1 M2 Bekisting untuk Pondasi
Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja OH 0.520 Rp 121,300.00 Rp 63,076.00
Tukang Kayu OH 0.260 Rp 129,500.00 Rp 33,670.00
Kepala Tukang OH 0.026 Rp 145,700.00 Rp 3,788.20
Mandor OH 0.026 Rp 161,900.00 Rp 4,209.40
JUMLAH TENAGA KERJA Rp 104,743.60
B BAHAN
Kayu kelas III m3 0.040 Rp 2,300,000.00 Rp 92,000.00
Paku 5 cm – 12 cm kg 0.300 Rp 21,000.00 Rp 6,300.00
Minyak bekisting Liter 0.100 Rp 9,660.00 Rp 966.00
JUMLAH TENAGA KERJA Rp 99,266.00
C PERALATAN
15,162.50
323.80
15,486.30
-
15,486.30
1,548.63
17,034.93
17,034.00
Jumlah
Harga
(Rp)
53,913.81
3,594.18
57,507.99
-
57,507.99
5,750.80
63,258.79
63,258.00
A.6.1. Pekerjaan 1 Unit Pembongkaran Kusen dan Pintu Aluminium
Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja OH 1.000 Rp 121,300.00 Rp
Mandor OH 0.050 Rp 161,900.00 Rp
JUMLAH TENAGA KERJA Rp
B BAHAN
121,300.00
8,095.00
129,395.00
-
129,395.00
12,939.50
142,334.50
142,334.00
Jumlah
Harga
(Rp)
12,130.00
1,619.00
13,749.00
-
13,749.00
1,374.90
15,123.90
15,123.00
K.11 Pemasangan 1m2 dinding bata merah tebal ½ batu campuran 1SP :4PP
Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L.01 OH 0.300 Rp 121,300.00 Rp
Tukang batu L.02 OH 0.100 Rp 129,500.00 Rp
Kepala tukang L.03 OH 0.010 Rp 145,700.00 Rp
Mandor L.04 OH 0.015 Rp 161,900.00 Rp
JUMLAH TENAGA KERJA Rp
B BAHAN
Batu bata M2 70.000 Rp 642.00 Rp
Semen Portland kg 11.500 Rp 1,540.00 Rp
Pasir Pasang M3 0.043 Rp 160,500.00 Rp
JUMLAH HARGA BAHAN Rp
C PERALATAN
D Jumlah (A+B+C) Rp
E Overhead & Profit 10% x D Rp
F Harga Satuan Pekerjaan (D+E) Rp
G Pembulatan Rp
Jumlah
Harga
(Rp)
36,390.00
12,950.00
1,457.00
2,428.50
53,225.50
44,940.00
17,710.00
6,901.50
69,551.50
122,777.00
12,277.70
135,054.70
135,054.00
Jumlah
Harga
(Rp)
36,390.00
19,425.00
2,185.50
2,428.50
60,429.00
9,609.60
3,852.00
13,461.60
73,890.60
7,389.06
81,279.66
81,279.00
L.6 Pemasangan 1M2 Acian
Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja OH 0.200 Rp 121,300.00 Rp
Tukang batu OH 0.100 Rp 129,500.00 Rp
Kepala tukang OH 0.010 Rp 145,700.00 Rp
Mandor OH 0.010 Rp 161,900.00 Rp
JUMLAH TENAGA KERJA Rp
B BAHAN
Semen Portland kg 3.250 Rp 1,540.00 Rp
JUMLAH HARGA BAHAN Rp
C PERALATAN
D Jumlah (A+B+C) Rp
E Overhead & Profit 10% x D Rp
F Harga Satuan Pekerjaan (D+E) Rp
G Pembulatan Rp
Jumlah
Harga
(Rp)
24,260.00
12,950.00
1,457.00
1,619.00
40,286.00
5,005.00
5,005.00
45,291.00
4,529.10
45,291.00
45,291.00
ANALISA PEKERJAAN PINTU DAN JENDELA
1. Pemasangan 1 m1 Kusen Aluminium 4"
Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L.01 OH 0.043 Rp 121,300.00 Rp 5,215.90
Tukang Khusus Aluminium L.02 OH 0.043 Rp 129,500.00 Rp 5,568.50
Kepala Tukang L.03 OH 0.004 Rp 145,700.00 Rp 626.51
Mandor L.04 OH 0.002 Rp 161,900.00 Rp 339.99
JUMLAH TENAGA KERJA Rp 11,750.90
B BAHAN
Profil Aluminium 4" - Alexindo m3 1.000 Rp 140,000.00 Rp 140,000.00
Skrup Fixer Buah 2.000 Rp 550.00 Rp 1,100.00
Sealant Tube 0.060 Rp 20,000.00 Rp 1,200.00
JUMLAH HARGA BAHAN Rp 142,300.00
C PERALATAN
V BAHAN FINISHING
1 Cat Dasar Dulux Interior / Alkali Resisting Interior Kg Rp 60,700.00
2 Plamir Kg Rp 47,120.00
3 Meni Kg Rp 62,320.00
4 Wood Filler Kg Rp 180,000.00
5 Thinner Liter Rp 20,000.00
6 Amplas Lembar Rp 5,000.00
7 Kwas Cat 4" Buah Rp 13,520.00
8 Plamir Tembok Kg Rp 47,120.00
9 Waterproofing Liquid Kg Rp 30,000.00
10 Lem Kayu Liter Rp 11,000.00
34
34
No JENIS BAHAN BANGUNAN / TENAGA KERJA SATUAN HARGA SATUAN ( Rp )
11 12.533,00
Seal tape Buah Rp
12 Coating Kg Rp 82,500.00
13 Finish Floor Hardener M2 Rp 12,500.00
14 Cat Minyak Kg Rp 61,375.00
15 Cat Dinding Interior - Dulux Professional Diamond A1000 Matt - Wh Kg Rp 70,840.00
16 Cat Plafond - Dulux Professional Diamond A1000 Matt - White Kg Rp 70,840.00
16 Residu Kg Rp 13,520.00
17 Ijuk Kg Rp 39,400.00
18 Kuas Gulung Kg Rp 33,857.00
19 Flicote Kg Rp 61,666.00
20 Residu Liter Rp 15,000.00
21 Dempul Kg Rp 25,000.00
22 Minyak Cat Liter Rp 29,400.00
23 Amplas Lbr Rp 6,000.00
24 Kuas Golong Bh Rp 25,200.00
25 Kuas 3" Bh Rp 7,500.00
26 Atap Genteng Metal 0.3mm Lbr Rp 60,000.00
27 Singap M2 Rp 750,000.00
28 Vernish Coating Batu Alam Kg Rp 40,000.00
29 Politur Liter Rp 40,000.00
30 Colour Hardener Kg Rp 23,800.00
31 Realese Agent Kg Rp 123,500.00
32 Wallpaper m1 Rp 15,000.00
33 Karpet m2 Rp 150,000.00
34 HPL (High Pressure Laminated) - Taco A/B/H - Motif Kayu Lembar Rp 165,000.00
VI BAHAN SANITARI
1 Wastafel Unit
2 Floor drain Buah
3 Kitchenzink Stainless steel Unit
4 Kran dinding Stainless steel Toto / Wasser FSD E004 Buah Rp 130,000.00
5 Pipa PVC AW dia 1/2" - Wavin / Rucika m Rp 5,825.00
6 Pipa PVC AW dia 3/4" - Wavin / Rucika m Rp 7,925.00
7 Pipa PVC AW dia 1" - Wavin / Rucika m Rp 10,825.00
8 Pipa PVC AW dia 1.5" - Wavin / Rucika m Rp 18,600.00
9 Pipa PVC AW dia 3" - Wavin / Rucika m Rp 48,900.00
35
35