I. PEKERJAAN PERSIAPAN
1 Sewa Tempat Direksi Teknis / Gudang Sementara Ls 1.00 19,706,698.20 19,706,698.20 1,970,669.82 21,677,368.02
2 Pembuatan Papan Nama Proyek Ls 1.00 1,088,054.00 1,088,054.00 108,805.40 1,196,859.40
II PENYIAPAN RKK
1 Pembuatan Dokumen Rencana Keselamatan Konstruksi Set 1.00 250,000.00 250,000.00 25,000.00 275,000.00
2 Pembuatan Prosedur Dan Instruksi Kerja Set 1.00 150,000.00 150,000.00 15,000.00 165,000.00
3 Penyiapan Formulir Set 1.00 100,000.00 100,000.00 10,000.00 110,000.00
III SOSIALISASI, PROMOSI DAN PELATIHAN
1 Induksi Keselamatan Konstruksi(Safety Induction) Org 20.00 12,500.00 250,000.00 25,000.00 275,000.00
2 Pengarahan Keselamatan Konstruksi (Safety Briefing) Org 20.00 12,500.00 250,000.00 25,000.00 275,000.00
3 Pelatihan Keselamatan Konstruksi:
- Bekerja di ketinggian Org 20.00 12,500.00 250,000.00 25,000.00 275,000.00
- Pelatihan K3 : P3K Org 20.00 12,500.00 250,000.00 25,000.00 275,000.00
4 Simulasi Keselamatan Konstruksi Org 20.00 12,500.00 250,000.00 25,000.00 275,000.00
5 Spanduk (Banner) Lbr 1.00 156,000.00 156,000.00 15,600.00 171,600.00
6 Poster Lbr 1.00 156,000.00 156,000.00 15,600.00 171,600.00
7 Papan Informasi K3 Bh 1.00 156,000.00 156,000.00 15,600.00 171,600.00
IV ALAT PELINDUNG KERJA DAN DIRI
1 Alat Pelindung Kerja (APK)
- Pembatas Area Ls 1.00 280,000.00 280,000.00 28,000.00 308,000.00
2 APD (Alat Pelindung Diri)
- Topi Pelindung (Safety Helmet) Bh 20.00 35,000.00 700,000.00 70,000.00 770,000.00
- Sepatu Keselamatan (Safety Shoes) Psg 20.00 76,000.00 1,520,000.00 152,000.00 1,672,000.00
- Rompi Keselamatan (Safety Vest) Bh 20.00 18,000.00 360,000.00 36,000.00 396,000.00
- Sarung Tangan (Safety Gloves) Bh 20.00 6,500.00 130,000.00 13,000.00 143,000.00
- Pelindung Pernapasan dan Mulut (Masker) Bh 20.00 4,800.00 96,000.00 9,600.00 105,600.00
V ASURANSI DAN PERIJINAN
1 Asuransi Ls 1.00 989,000.00 989,000.00 98,900.00 1,087,900.00
VI PERSONIL K3 DAN PENGENDALIAN RESIKO K3
1 Tenaga Paramedis OB
2 Pelaporan & Penyelidikan Insiden Ls 1.00 250,000.00 250,000.00 25,000.00 275,000.00
VII FASILITAS SARANA, PRASARANA DAN ALAT KESEHATAN
1 Peralatan P3K (Kotak P3K, Obat Luka, Perban, dan lain lain) Ls 1.00 380,000.00 380,000.00 38,000.00 418,000.00
2 Sabun Cuci tangan, Hand Sanitizer dan Tisu Ls 1.00 65,000.00 65,000.00 6,500.00 71,500.00
3 Wastafel Portable Unit 1.00 350,000.00 350,000.00 35,000.00 385,000.00
4 Thermo Scan Unit 1.00 132,000.00 132,000.00 13,200.00 145,200.00
5 Alat Semprot Disinfektan Bh 1.00 98,000.00 98,000.00 9,800.00 107,800.00
NO URAIAN PEKERJAAN SAT. VOL HARGA SATUAN JUMLAH HARGA PPN TOTAL HARGA
(Rp) (Rp) 10% (Rp)
II PEKERJAAN BONGKARAN
JUMLAH SUB II -
3 Urugan Tanah Kembali Bekas Galian Pondasi M³ 59.04 63,307.75 3,737,689.56 373,768.96 4,111,458.52
4 Urugan Tanah Kembali Bekas Galian Saluran M³ 11.31 63,307.75 716,200.58 71,620.06 787,820.63
6 Urugan Pasir Bawah Pondasi Saluran M³ 76.10 240,545.00 18,304,650.63 1,830,465.06 20,135,115.70
7 Urugan Pasir Bawah Lantai Rabat Beton Saluran Keliling (T = 5cm) M³ 12.47 240,545.00 2,999,024.86 299,902.49 3,298,927.34
IV PEKERJAAN PONDASI
V PEKERJAAN STRUKTUR
1 Sloof 15/20
8 Rabat Beton Lantai untuk Selasar (T = 10cm) M³ 3.62 1,027,270.24 3,714,609.18 371,460.92 4,086,070.10
5 Rabat Beton Lantai Ruang Kelas dan Selasar (T = 10cm) M³ 24.70 1,027,270.24 25,372,033.98 2,537,203.40 27,909,237.37
6 Rabat Beton Lantai Saluran (T = 5cm) M³ 1.70 1,027,270.24 1,743,318.68 174,331.87 1,917,650.55
1 Keramik uk. 40 x 40 (Ruang Kelas dan Selasar) M² 210.83 177,261.03 37,371,055.60 3,737,105.56 41,108,161.16
2 Plint Keramik uk 10 x 40 (Ruang Kelas) M' 106.40 54,455.00 5,794,012.00 579,401.20 6,373,413.20
1 Pemasangan Rangka Atap Baja Ringan + Reng M² 339.28 161,063.30 54,645,090.02 5,464,509.00 60,109,599.02
2 Pasang 1 m2 atap Spandek Zincalume 0.4 mm M' 339.28 144,090.10 48,886,472.48 4,888,647.25 53,775,119.73
3 Pasang 1 m Nok Bubungan Spandek Zincalume M² 25.60 87,813.00 2,248,012.80 224,801.28 2,472,814.08
4 Pemasangan 1 m’ papan lisplank GRC M² 29.28 70,449.50 2,062,761.36 206,276.14 2,269,037.50
5 Pengerjaan 1 M2 Plafon Kalsiboard + Rangka Hollow 4 x 4 M² 204.91 209,377.30 42,902,665.03 4,290,266.50 47,192,931.54
6 Pemasangan 1 m’ List profil cornees gypsum M' 200.16 41,923.75 8,391,457.80 839,145.78 9,230,603.58
A INTERIOR
1 Pengecatan Dinding Tembok + Beton (Luar & Dalam) M² 594.94 42,305.56 25,169,269.87 2,516,926.99 27,686,196.85
2 Pengecatan Plafond + Listplafond (Dalam) M² 200.16 38,498.90 7,705,939.82 770,593.98 8,476,533.81
3 Pengecatan Listplank M² 15.37 52,959.50 813,923.96 81,392.40 895,316.36
XI PEKERJAAN LISTRIK
1 Pek. Instalasi Listrik dari Panel ke Titik Lampu, Stop Kontak, & Saklar Titik 18.00 257,680.50 4,638,249.00 463,824.90 5,102,073.90
2 Pas. Saklar Ganda bh 6.00 81,598.00 489,588.00 48,958.80 538,546.80
3 Pas. Lampu Philips LED 12 watt + Fitting Tempel (Luar) bh 4.00 208,230.00 832,920.00 83,292.00 916,212.00
4 Pas. Lampu TL 2 x 36 Watt , Arcrilic + Fitting Tempel (Dalam) bh 12.00 526,460.00 6,317,520.00 631,752.00 6,949,272.00
NO URAIAN PEKERJAAN SAT. VOL HARGA SATUAN JUMLAH HARGA PPN TOTAL HARGA
(Rp) (Rp) 10% (Rp)
II PEKERJAAN BONGKARAN
2 Urugan Tanah Kembali Bekas Galian Pondasi M³ 2.88 63,307.75 182,452.94 18,245.29 200,698.23
4 Urugan Sirtu Peninggi Lantai (Ruangan dan Selasar) M³ 2.93 263,712.50 773,270.98 77,327.10 850,598.08
IV PEKERJAAN PONDASI
V PEKERJAAN STRUKTUR
NO URAIAN PEKERJAAN SAT. VOL HARGA SATUAN JUMLAH HARGA PPN TOTAL HARGA
(Rp) (Rp) 10% (Rp)
1 Keramik uk. 40 x 40 (Ruang Kelas dan Selasar) M² 140.07 177,261.03 24,828,419.99 2,482,842.00 27,311,261.99
2 Plint Keramik uk 10 x 40 (Ruang Kelas) M' 66.04 54,455.00 3,596,208.20 359,620.82 3,955,829.02
1 Pekerjaan Plafon Kalsiboard + Rangka Hollow 4 x 4 M² 107.55 209,377.30 22,517,481.73 2,251,748.17 24,769,229.90
2 List Plafon Corness Gipsum M' 46.00 41,923.75 1,928,492.50 192,849.25 2,121,341.75
3 Pemasangan Atap spandek M² 224.04 144,090.10 32,282,234.18 3,228,223.42 35,510,457.60
4 Pemasangan Nok Bubungan Zincalume M' 18.20 87,813.00 1,598,196.60 159,819.66 1,758,016.26
5 Pemasangan Lisplank GRC M² 9.74 70,449.50 686,319.03 68,631.90 754,950.93
XI PEKERJAAN LISTRIK
1 Pek. Instalasi Listrik dari Panel ke Titik Lampu, Stop Kontak, & Saklar Titik 14.00 257,680.50 3,607,527.00 360,752.70 3,968,279.70
2 Pas. Stop Kontak bh 3.00 87,098.00 261,294.00 26,129.40 287,423.40
3 Pas. Saklar Tunggal bh 1.00 70,598.00 70,598.00 7,059.80 77,657.80
4 Pas. Saklar Ganda bh 4.00 81,598.00 326,392.00 32,639.20 359,031.20
5 Pas. Lampu Philips LED 12 watt + Fitting Tempel (Luar) bh 2.00 208,230.00 416,460.00 41,646.00 458,106.00
6 Pas. Lampu TL 2 x 36 watt Acrilic + Fitting Tempel (Dalam) bh 10.00 526,460.00 5,264,600.00 526,460.00 5,791,060.00
NO URAIAN PEKERJAAN SAT. VOL HARGA SATUAN JUMLAH HARGA PPN TOTAL HARGA
(Rp) (Rp) 10% (Rp)
II PEKERJAAN BONGKARAN
IV PEKERJAAN PONDASI
JUMLAH SUB IV -
V PEKERJAAN STRUKTUR
1 Rabat Beton Lantai Ruang Kelas dan Selasar (T = 10cm) M³ 18.93 1,027,270.24 19,446,739.24 1,944,673.92 21,391,413.17
2 Rabat Beton Lantai Saluran (T = 5cm) M³ 2.69 1,027,270.24 2,759,658.77 275,965.88 3,035,624.64
1 Keramik uk. 40 x 40 (Ruang Kelas dan Selasar) M² 140.07 177,261.03 24,828,419.99 2,482,842.00 27,311,261.99
2 Plint Keramik uk 10 x 40 (Ruang Kelas) M' 66.04 54,455.00 3,596,208.20 359,620.82 3,955,829.02
1 Pekerjaan Plafon Kalsiboard + Rangka Hollow 4 x 4 M² 195.05 209,377.30 40,837,995.48 4,083,799.55 44,921,795.03
2 List Plafon Corness Gipsum M' 58.80 83,412.33 4,904,644.87 490,464.49 5,395,109.36
3 Pemasangan Nok Bubungan Zincalume M' 193.81 87,813.00 17,018,879.32 1,701,887.93 18,720,767.26
4 Pemasangan Lisplank GRC M² 11.48 70,449.50 808,760.26 80,876.03 889,636.29
X PEKERJAAN PENGECATAN
A INTERIOR
XI PEKERJAAN LISTRIK
1 Pek. Instalasi Listrik dari Panel ke Titik Lampu, Stop Kontak, & Saklar Titik 12.00 257,680.50 3,092,166.00 309,216.60 3,401,382.60
2 Pas. Stop Kontak bh 2.00 87,098.00 174,196.00 17,419.60 191,615.60
3 Pas. Saklar Ganda bh 4.00 81,598.00 326,392.00 32,639.20 359,031.20
4 Pas. Lampu Philips LED 12 watt + Fitting Tempel (Luar) bh 4.00 208,230.00 832,920.00 83,292.00 916,212.00
5 Pas. Lampu TL 2 x 36 watt Acrilic + Fitting Tempel (Dalam) bh 8.00 208,230.00 1,665,840.00 166,584.00 1,832,424.00
NO URAIAN PEKERJAAN SAT. VOL HARGA SATUAN JUMLAH HARGA PPN TOTAL HARGA
(Rp) (Rp) 10% (Rp)
II PEKERJAAN BONGKARAN
IV PEKERJAAN PONDASI
JUMLAH SUB IV -
V PEKERJAAN STRUKTUR
1 Rabat Beton Lantai Ruang Kelas dan Selasar (T = 10cm) M³ 11.24 1,027,270.24 11,545,747.02 1,154,574.70 12,700,321.73
2 Rabat Beton Lantai Saluran (T = 5cm) M³ 1.95 1,027,270.24 2,003,587.87 200,358.79 2,203,946.66
1 Keramik uk. 40 x 40 (Ruang Kelas dan Selasar) M² 70.03 177,261.03 12,414,209.99 1,241,421.00 13,655,630.99
2 Plint Keramik uk 10 x 40 (Ruang Kelas) M' 35.60 54,455.00 1,938,598.00 193,859.80 2,132,457.80
1 Pekerjaan Plafon Kalsiboard + Rangka Hollow 4 x 4 M² 118.77 209,377.30 24,868,265.36 2,486,826.54 27,355,091.90
X PEKERJAAN PENGECATAN
A INTERIOR
XI PEKERJAAN LISTRIK
1 Pek. Instalasi Listrik dari Panel ke Titik Lampu, Stop Kontak, & Saklar Titik 10.00 257,680.50 2,576,805.00 257,680.50 2,834,485.50
2 Pas. Stop Kontak bh 3.00 87,098.00 261,294.00 26,129.40 287,423.40
3 Pas. Saklar Ganda bh 2.00 81,598.00 163,196.00 16,319.60 179,515.60
4 Pas. Lampu Philips LED 12 watt + Fitting Tempel (Luar) bh 2.00 208,230.00 416,460.00 41,646.00 458,106.00
5 Pas. Lampu TL 2 x 36 watt Acrilic + Fitting Tempel (Dalam) bh 3.00 208,230.00 624,690.00 62,469.00 687,159.00
NO URAIAN PEKERJAAN SAT. VOL HARGA SATUAN JUMLAH HARGA PPN TOTAL HARGA
(Rp) (Rp) 10% (Rp)
II PEKERJAAN BONGKARAN
IV PEKERJAAN PONDASI
V PEKERJAAN STRUKTUR
1 Rabat Beton Lantai Ruang Kelas dan Selasar (T = 10cm) M³ 28.47 1,027,270.24 29,248,181.40 2,924,818.14 32,172,999.54
2 Rabat Beton Lantai Saluran (T = 5cm) M³ 3.40 1,027,270.24 3,496,827.89 349,682.79 3,846,510.68
1 Plesteran Dinding dan beton Seluruh, 1Pc : 5Psr M² 25.00 49,100.86 1,227,521.50 122,752.15 1,350,273.65
2 Acian Dinding dan Beton Seluruh M² 25.00 33,480.70 837,017.50 83,701.75 920,719.25
3 Pasangan Dinding 1/2 bata merah , 1Pc : 5Psr ( untuk saluran ) M² 54.76 241,021.03 13,198,311.42 1,319,831.14 14,518,142.56
4 Plesteran Dinding Saluran M² 76.96 49,100.86 3,778,802.19 377,880.22 4,156,682.40
5 Acian Dinding Saluran M² 76.96 33,480.70 2,576,674.67 257,667.47 2,834,342.14
1 Keramik uk. 40 x 40 (Ruang Kelas dan Selasar) M² 209.72 177,261.03 37,175,625.32 3,717,562.53 40,893,187.85
2 Plint Keramik uk 10 x 40 (Ruang Kelas) M' 102.30 54,455.00 5,570,746.50 557,074.65 6,127,821.15
1 Pekerjaan Plafon Kalsiboard + Rangka Hollow 4 x 4 M² 161.32 209,377.30 33,776,222.59 3,377,622.26 37,153,844.85
X PEKERJAAN PENGECATAN
XI PEKERJAAN LISTRIK
1 Pek. Instalasi Listrik dari Panel ke Titik Lampu, Stop Kontak, & Saklar Titik 6.00 257,680.50 1,546,083.00 154,608.30 1,700,691.30
2 Pas. Stop Kontak bh 2.00 87,098.00 174,196.00 17,419.60 191,615.60
3 Pas. Saklar Ganda bh 2.00 81,598.00 163,196.00 16,319.60 179,515.60
4 Pas. Lampu Philips LED 12 watt + Fitting Tempel bh 6.00 208,230.00 1,249,380.00 124,938.00 1,374,318.00
II PEKERJAAN BONGKARAN
JUMLAH SUB II -
IV PEKERJAAN PONDASI
V PEKERJAAN STRUKTUR
1 Sloff 15/20
1 Pasangan Dinding Batako , 1Pc : 5Psr M² 102.72 166,975.36 17,151,542.00 1,715,154.20 18,866,696.20
2 Plesteran pondasi, 1Pc : 5Psr M² 21.08 49,100.86 1,035,046.13 103,504.61 1,138,550.74
3 Plesteran Dinding dan beton, 1Pc : 5Psr M² 205.44 49,100.86 10,087,182.48 1,008,718.25 11,095,900.72
4 Acian Pondasi, Dinding dan Beton M² 226.52 33,480.70 7,583,981.20 758,398.12 8,342,379.32
1 Keramik Lantai KM/WC uk. 20x20 M² 24.96 209,745.40 5,235,245.18 523,524.52 5,758,769.70
2 Keramik Dinding KM/WC uk. 20x25 M² 32.30 227,785.40 7,357,468.42 735,746.84 8,093,215.26
3 Lantai Beton Rabat Tebal 5 cm (K-100) M³ 0.99 1,027,270.24 1,014,943.00 101,494.30 1,116,437.29
X PEKERJAAN PENGECATAN
A INTERIOR
1 Pek. Instalasi Listrik dari Panel ke Titik Lampu, Stop Kontak, & Saklar Titik 3.00 257,680.50 773,041.50 77,304.15 850,345.65
2 Pas. Saklar Tunggal bh 3.00 70,598.00 211,794.00 21,179.40 232,973.40
3 Pas. Stop Kontak bh 1.00 87,098.00 87,098.00 8,709.80 95,807.80
4 Pas. Lampu Philips LED 12 watt + Fitting Tempel bh 3.00 208,230.00 624,690.00 62,469.00 687,159.00
1 Septictank (1 Unit) & Sumur Peresapan (3 Unit) Ls 1.00 8,100,000.00 8,100,000.00 810,000.00 8,910,000.00
2 Pasang Instalasi Air Kotor Pipa PVC Ø 4" + Accesoris (Limbah Padat) M' 10.00 259,542.25 2,595,422.50 259,542.25 2,854,964.75
3 Pasang Instalasi Air Kotor Pipa PVC Ø 2" + Accesoris (Limbah Cair) M' 10.00 116,916.25 1,169,162.50 116,916.25 1,286,078.75
4 Pasang Instalasi Air Bersih Pipa Galvanis Ø 1/2" + Accesoris M' 20.00 73,035.88 1,460,717.50 146,071.75 1,606,789.25
5 Pasang Kran Stainless Steel Ø 1/2" (km/wc) Bh 10.00 325,776.00 3,257,760.00 325,776.00 3,583,536.00
6 Pasang Kloset Jongkok Komplit Unit 2.00 666,710.00 1,333,420.00 133,342.00 1,466,762.00
7 Pasangan Floor Drain Bh 2.00 215,154.50 430,309.00 43,030.90 473,339.90
1 Galian Tanah Pondasi Footplate Gapura M³ 4.88 100,933.25 492,554.26 49,255.43 541,809.69
2 Urugan Tanah Kembali Hasil Galian Footplate M³ 1.63 63,307.75 102,980.61 10,298.06 113,278.67
3 Urug Pasir Bawah Pondasi m3 0.24 472,455.50 113,389.32 11,338.93 124,728.25
JUMLAH SUB II 779,816.61
III PEKERJAAN PONDASI GAPURA
1 Pas Pondasi Batu Kali Amstamping m3 9.60 357,754.50 3,434,443.20 343,444.32 3,777,887.52
2 Pas Pondasi Batu Kali m3 2.16 578,250.05 1,249,020.11 124,902.01 1,373,922.12
3 Lantai Kerja Beton Pondasi Footplate (t = 10cm) M³ 0.10 1,027,270.24 102,727.02 10,272.70 112,999.73
4 Pondasi Footplate (Gapura)
a. Beton K-175 M³ 0.30 1,162,017.16 348,605.15 34,860.51 383,465.66
b. Pembesian + Pemasangan Angkur Kg 22.90 21,672.59 496,368.12 49,636.81 546,004.93
c. Bekesting M² 0.60 59,482.50 35,689.50 3,568.95 39,258.45
JUMLAH SUB III 6,233,538.40
IV PEKERJAAN STRUKTUR GAPURA
1 Kolom Pedestal 40/140 (Gapura)
a. Beton K-175 M³ 0.25 1,162,017.16 292,828.32 29,282.83 322,111.16
b. Pembesian Kg 29.85 21,672.59 646,936.82 64,693.68 711,630.50
c. Bekesting M² 0.84 113,833.50 95,620.14 9,562.01 105,182.15
2 Sloof 15/20 (Gapura)
a. Beton K-175 M³ 0.85 1,162,017.16 984,809.54 98,480.95 1,083,290.50
b. Pembesian Kg 258.80 21,672.59 5,608,866.83 560,886.68 6,169,753.51
c. Bekesting M² 13.56 71,582.50 970,658.70 97,065.87 1,067,724.57
3 Kolom 20/20 (Gapura)
a. Beton K-175 M³ 0.50 1,162,017.16 581,008.58 58,100.86 639,109.44
b. Pembesian Kg 64.92 21,672.59 1,406,936.64 140,693.66 1,547,630.30
c. Bekesting M² 2.00 113,833.50 227,667.00 22,766.70 250,433.70
4 Kolom 10/20 (Gapura)
a. Beton K-175 M³ 0.22 1,162,017.16 254,191.25 25,419.13 279,610.38
b. Pembesian Kg 28.85 21,672.59 625,358.15 62,535.81 687,893.96
c. Bekesting M² 0.88 113,833.50 99,604.31 9,960.43 109,564.74
JUMLAH SUB IV 12,973,934.91
V PEKERJAAN PASANGAN DAN PLESTERAN GAPURA
1 Pasangan Dinding 1/2 bata merah , 1Pc : 5Psr (Gapura) M² 18.68 241,021.03 4,502,272.78 450,227.28 4,952,500.06
2 Plesteran Dinding dan beton, 1Pc : 5Psr (Gapura) M² 31.08 49,100.86 1,526,054.73 152,605.47 1,678,660.20
3 Acian Dinding dan Beton (Gapura) M² 31.08 33,480.70 1,040,580.16 104,058.02 1,144,638.17
B PAGAR 23 M + 23 M
I PEKERJAAN PERSIAPAN PAGAR
1 Pemasangan bouwplank M' 46.00 27,690.30 1,273,753.80 127,375.38 1,401,129.18
HARGA
JUMLAH HARGA PPN TOTAL HARGA
NO URAIAN PEKERJAAN SAT. VOL SATUAN
(Rp) 10% (Rp)
(Rp)
1 Galian Tanah Pondasi dan Bak Air M³ 26.73 100,933.25 2,698,248.57 269,824.86 2,968,073.43
2 Urugan Tanah Kembali Hasil Galian M³ 6.68 63,307.75 423,101.52 42,310.15 465,411.67
2 Kolom 20/25
1 Pemasangan dan Perakitan Besi L 70.70.7 Kg 537.26 32,158.50 17,277,604.34 1,727,760.43 19,005,364.78
2 Pemasangan dan Perakitan Besi L 50.50.5 Kg 143.64 32,158.50 4,619,246.94 461,924.69 5,081,171.63
1 Plesteran Dinding dan Pelat beton, 1Pc : 5Psr M² 30.95 49,100.86 1,519,671.62 151,967.16 1,671,638.78
2 Acian Dinding & Pelat Beton M² 30.95 33,480.70 1,036,227.67 103,622.77 1,139,850.43
1 Pengecatan Dinding & Pelat Beton Bak Air M² 30.95 42,305.56 1,309,357.08 130,935.71 1,440,292.79
2 Pengecetan Besi L 70.70.7 M² 203.84 52,959.50 10,795,264.48 1,079,526.45 11,874,790.93
3 Pengecetan Besi L 50.50.5 M² 76.00 52,959.50 4,024,922.00 402,492.20 4,427,414.20
1 Instalasi Pipa Bak Ke Tower E 1,5" M1 12.00 165,088.00 1,981,056.00 198,105.60 2,179,161.60
b. Tee Gip Dia 1" ke Dia 3/4" Bh 2.00 32,554.06 65,108.12 6,510.81 71,618.94
3 Instalasi Pipa Tower outlet Ke kamar mandi 3/4" Komplit Acecories M² 10.00 87,954.63 879,546.25 87,954.63 967,500.88
a. Tee Gip Dia 3/4" ke Dia 1/2" Bh 3.00 21,179.83 63,539.48 6,353.95 69,893.43
1 Tandon Stainless 500 Ltr + Onkos Kerja /Biaya Instalasi Bh 2.00 1,790,030.00 3,580,060.00 358,006.00 3,938,066.00
2 Penutup Mainhole Bak Air Ls 1.00 330,000.00 330,000.00 33,000.00 363,000.00
3 Pompa Transfer Unit 1.00 3,719,100.00 3,719,100.00 371,910.00 4,091,010.00
1. merk/Type Grundfos NS 4-23m
2. Kapasitas 60 Liter/menit
3. Ketinggian sampai dengan 18 m
4. Daya sampai 750 Watt
4 Strainer Dia. 1 1/2" sekualitas ONDA Bh 1.00 1,747,218.00 1,747,218.00 174,721.80 1,921,939.80
5 Check Valve Dia. 1 1/2" sekualitas ONDA Bh 1.00 552,444.75 552,444.75 55,244.48 607,689.23
6 Ball Valve Dia. 1 1/2" sekualitas ONDA Bh 1.00 605,993.73 605,993.73 60,599.37 666,593.10
HARGA JUMLAH
PPN TOTAL HARGA
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA
10% (Rp)
(Rp) (Rp)
JUMLAH I 145,953.38
II PEKERJAAN PONDASI
1 Pasangan pondasi menerus 1 Pc : 5 Ps M³ 0.23 578,250.05 130,106.26 13,010.63 143,116.89
JUMLAH II 143,116.89
4 Kolom 20 x 20 cm
a Beton K- 175 M³ 0.08 1,324,240.21 107,263.46 10,726.35 117,989.80
IV PEKERJAAN PASANGAN
1 Pasangan dinding bata merah , 1Pc : 5Psr M² 2.19 166,975.36 365,676.04 36,567.60 402,243.64
2 Plesteran Dinding dan beton, 1Pc : 5Psr M² 1.32 49,100.86 64,813.14 6,481.31 71,294.45
JUMLAH IV 719,168.68
JUMLAH V 150,406.33
HARGA JUMLAH
PPN TOTAL HARGA
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA
10% (Rp)
(Rp) (Rp)
VI PEKERJAAN PENGECATAN
1 Pengecatan tembok Eksterior M² 2.83 42,305.56 119,724.73 11,972.47 131,697.21
JUMLAH VI 131,697.21
3 Pemasangan Pipa PVC Dia. 1/2" (Dari Tempat Penampungan M 10.00 43,133.75 431,337.50 43,133.75 474,471.25