JENIS PEKERJAAN : Pekerjaan Beton Bertulang (200 kg + Bekisting)

SATUAN PEMBAYARAN : M3

NO. KOMPONEN SATUAN KOEFISIEN HARGA SATUAN ( Rp ) JUMLAH HARGA (Rp)

A. TENAGA
1. Pekerja (L01) Oh 6,3500 90.000,00 571.500,00
2 Tukang Batu (L02) Oh 0,2750 120.000,00 33.000,00
3 Tukang Kayu Oh 1,6500 120.000,00 198.000,00
4 Tukang Besi Oh 1,4000 120.000,00 168.000,00
5 Kepala Tukang (L03) Oh 0,3330 130.000,00 43.290,00
6 Mandor (L04) Oh 0,3180 130.000,00 41.340,00
JUMLAH HARGA TENAGA 1.055.130,00
B. BAHAN
1 Kayu Kelas III M3 0,3200 1.725.000,00 552.000,00
2 Paku 5-12 cm Kg 3,2000 24.000,00 76.800,00
3 Minyak Bekisting Liter 1,6000 16.500,00 26.400,00
4 Besi Beton Polos Kg 112,0000 15.000,00 1.680.000,00
5 Kawar Beton Kg 3,0000 30.000,00 90.000,00
6 Portland Cement Kg 336,0000 1.500,00 504.000,00
7 Pasir Beton M3 0,5400 175.000,00 94.500,00
8 Kerikil M3 0,8100 328.000,00 265.680,00
9 Kayu Kelas II Balok M3 0,1400 3.400.000,00 476.000,00
11 Dolken Dia 8-10, 4 M Btg 16,0000 10.000,00 160.000,00
JUMLAH HARGA BAHAN 3.925.380,00
C. PERALATAN

JUMLAH HARGA PERALATAN 0,00


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 4.980.510,00
E. OVERHEAD & PROFIT 15 % x D 747.076,50
F. HARGA SATUAN PEKERJAAN ( D + E ) 5.727.586,50