Memasang 1m3 Pondasi Batu Belah, Campuran 1Pc : 3Ps (P.PB. 01)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 48,400.00 1.500 72,600.00
2 Tukang Batu OH 60,500.00 0.750 45,375.00
3 Kepala Tukang OH 66,550.00 0.075 4,991.25
4 Mandor OH 66,550.00 0.075 4,991.25
Jumlah 127,957.50
B BAHAN
1 Batu Belah 15-20 cm M3 230,230.00 1.200 276,276.00
2 Semen Portland Kg 1,400.00 202.000 282,800.00
3 Pasir M3 58,370.00 0.485 28,309.45
Jumlah 587,385.45
C Jumlah A + B 715,342.95
D Harga Satuan 715,342.95
Acuan : SNI DT 91-0007-2007
Memasang 1m3 Pondasi Batu Belah, Campuran 1Pc : 4Ps (P.PB. 02)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 48,400.00 1.500 72,600.00
2 Tukang Batu OH 60,500.00 0.750 45,375.00
3 Kepala Tukang OH 66,550.00 0.075 4,991.25
4 Mandor OH 66,550.00 0.075 4,991.25
Jumlah 127,957.50
B BAHAN
1 Batu Belah 15-20 cm M3 230,230.00 1.200 276,276.00
2 Semen Portland Kg 1,400.00 163.000 228,200.00
3 Pasir M3 58,370.00 0.520 30,352.40
Jumlah 534,828.40
C Jumlah A + B 662,785.90
D Harga Satuan 662,785.90
Acuan : SNI DT 91-0007-2007
Memasang 1m' talang 1/2 lingkaran D-15 cm, seng plat bjls 30 lebar 45 cm (P. BA 06)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 48,400.00 0.150 7,260.00
2 Tukang Besi OH 60,500.00 0.300 18,150.00
3 Kepala Tukang OH 66,550.00 0.0300 1,996.50
4 Mandor OH 66,550.00 0.0080 532.40
Jumlah 27,938.90
B BAHAN
1 Seng plat m' 20,900.00 1.050 21,945.00
2 Paku 1/2" - 1" Kg 20,900.00 0.010 209.00
3 Besi tulangan kg 15,510.00 0.500 7,755.00
Jumlah 29,909.00
C Jumlah A + B 57,847.90
D Harga Satuan 57,847.90
Acuan : SNI DT 91-0014-2007
1m2 Pasang Talang Datar Seng BJLS 30 / Talang Sembunyi (P.BA. 10)
1m2 Pasang Talang Miring Seng BJLS 30 / Jurai Dalam (P.BA. 11)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 60,000.00 0.040 2,400.00
2 Tukang Kayu OH 77,990.00 0.400 31,196.00
3 Kepala Tukang OH 75,000.00 0.025 1,875.00
4 Mandor OH 75,000.00 0.00125 93.75
Jumlah 35,564.75
B BAHAN
1 Seng Plat 3' x 6' BJLS 30 Lbr 115,720.00 0.50 57,860.00
2 Paku 1/2" - 1" Kg 24,478.00 0.015 367.17
3 Papan Kayu Kelas 2 Tidak Ketam M3 3,278,535.00 0.019 62,292.17
4 Meni Kg 59,099.00 0.300 17,729.70
Jumlah 138,249.04
C Jumlah A + B 173,813.79
D Harga Satuan 173,813.79
Acuan : ABK Bangunan Gedung dan Perumahan - 6.19
Pekerjaan Dinding 8
E. PEKERJAAN Plesteran (P.Pls)
Pekerjaan Plasteran 9
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 48,400.00 0.400 19,360.00
2 Tukang Batu OH 60,500.00 0.200 12,100.00
3 Kepala Tukang OH 66,550.00 0.020 1,331.00
4 Mandor OH 66,550.00 0.022 1,464.10
Jumlah 34,255.10
B BAHAN
1 Semen Portland Kg 1,400.00 8.320 11,648.00
2 Pasir M3 58,370.00 0.032 1,867.84
Jumlah 13,515.84
C Jumlah A + B 47,770.94
D Harga Satuan 47,770.94
Acuan : SNI DT 91-0010-2007
Pekerjaan Plasteran 10
2 Tukang Batu OH 60,500.00 0.100 6,050.00
3 Kepala Tukang OH 66,550.00 0.010 665.50
4 Mandor OH 66,550.00 0.010 665.50
Jumlah 17,061.00
B BAHAN
1 Semen Portland Kg 1,400.00 3.250 4,550.00
Jumlah 4,550.00
C Jumlah A + B 21,611.00
D Harga Satuan 21,611.00
Acuan : SNI DT 91-0010-2007
Pekerjaan Plasteran 11
F. PEKERJAAN KAYU (P.K.)
1m3 Pekerjaan Rangka Badan Kayu Kelas I Uk. 8/8 (P.K. 08)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Tukang Kayu OH 77,990.00 24.000 1,871,760.00
2 Pekerja OH 60,000.00 8.000 480,000.00
3 Kepala Tukang OH 75,000.00 2.400 180,000.00
4 Mandor OH 75,000.00 0.400 30,000.00
Jumlah 2,561,760.00
B BAHAN
1 Kayu Kelas I (Ketam Uk. 8/8) M3 4,667,184.00 1.100 5,133,902.40
2 Paku Kg 24,478.00 6.000 146,868.00
Jumlah 5,280,770.40
C Jumlah A + B 7,842,530.40
D Harga Satuan 7,842,530.40
Acuan : Harga Satuan Bahan, Upah dan Analisa Biaya Pekerjaan BOW - F.27.a
Pekerjaan Kayu 12
Memasang 1m3 Konstruksi Kuda-kuda Konvensional, Kayu Kelas II Bentang 6 m (P.K. 25)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 60,000.00 4.000 240,000.00
2 Tukang Kayu OH 77,990.00 12.000 935,880.00
3 Kepala Tukang OH 75,000.00 1.200 90,000.00
4 Mandor OH 75,000.00 0.200 15,000.00
Jumlah 1,280,880.00
B BAHAN
1 Balok Kayu Kelas II (Tidak Ketam) M3 2,990,460.00 1.100 3,289,506.00
2 Besi Strip Kg 39,377.00 15.000 590,655.00
3 Paku 12 cm Kg 24,478.00 5.600 137,076.80
Jumlah 4,017,237.80
C Jumlah A + B 5,298,117.80
D Harga Satuan 5,298,117.80
Acuan : SNI DT 91-0011-2007
Pekerjaan Kayu 13
Memasang 1m2 Rangka Langit-langit (60 x 60) cm, Kayu Kelas II atau III (P.K. 35)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 3 4 5 6
A TENAGA
1 Pekerja OH 60,000.00 0.200 12,000.00
2 Tukang Kayu OH 77,990.00 0.300 23,397.00
3 Kepala Tukang OH 75,000.00 0.030 2,250.00
4 Mandor OH 75,000.00 0.010 750.00
Jumlah 38,397.00
B BAHAN
1 Kaso-kaso (5x7) cm M3 3,278,535.00 0.0163 53,440.12
2 Paku 7 cm - 10 cm Kg 24,478.00 0.250 6,119.50
Jumlah 59,559.62
C Jumlah A + B 97,956.62
D Harga Satuan 97,956.62
Acuan : SNI DT 91-0011-2007
Pekerjaan Kayu 14
G. PEKERJAAN PENUTUP ATAP (P.PA.)
1m1 Pekerjaan Bumbungan dengan Seng Datar Color 0.35 / 10 m 1 (P.PA. 07)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 60,000.00 0.250 15,000.00
2 Tukang kayu OH 77,990.00 0.250 19,497.50
3 Kepala Tukang OH 75,000.00 0.025 1,875.00
Jumlah 36,372.50
B BAHAN
1 Paku Kg 25,788.00 0.100 2,578.80
2 Seng Datar Color 0.35 Lbr 115,720.00 6.000 694,320.00
3 Papan Kayu Kelas II (tdk ketam) M3 3,278,535.00 0.072 236,054.52
Jumlah 932,953.32
C Jumlah A + B 969,325.82
D Harga Satuan 969,325.82
Jadi 1 M1 96,932.58
Acuan : Harga Satuan Bahan, Upah dan Analisa Biaya Pekerjaan BOW - H.10
Pekerjaan Plafond 16
I. PEKERJAAN SANITASI (P. Snt.)
Pekerjaan Sanitasi 17
Memasang 1m1 Pipa PVC Tipe AW Ø 4" (P.Snt. 14)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 60,000.00 0.081 4,860.00
2 Tukang Batu OH 77,990.00 0.135 10,528.65
3 Kepala Tukang OH 75,000.00 0.0135 1,012.50
4 Mandor OH 75,000.00 0.0041 307.50
Jumlah 16,708.65
B BAHAN
1 Pipa PVC Ø 4" M1 61,980.50 1.200 74,376.60
2 Perlengkapan Ls 61,980.50 35% Harga Pipa 21,693.18
Jumlah 96,069.78
C Jumlah A + B 112,778.43
D Harga Satuan 112,778.43
Acuan : ABK Bangunan Gedung dan Perumahan - 6.32
Pekerjaan Sanitasi 18
J. PEKERJAAN KUNCI DAN KACA (P.KK.)
1m2 Pengecatan Bidang Kayu Baru (1Lapis Plamir, 1Lapis Cat Dasar, 2Lapis Cat Penutup) (P.Ct. 04)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 60,000.00 0.070 4,200.00
2 Tukang Cat OH 70,000.00 0.009 630.00
3 Kepala Tukang OH 75,000.00 0.006 450.00
4 Mandor OH 75,000.00 0.0025 187.50
Jumlah 5,467.50
B BAHAN
1 Cat Meni Kg 46,817.93 0.200 9,363.59
2 Dempul Kg 65,405.34 0.150 9,810.80
3 Cat Dasar Kg 31,305.12 0.170 5,321.87
4 Cat Kilat Penutup 2 Kali Kg 65,405.34 0.260 17,005.39
41,501.64
C Jumlah A + B 46,969.14
D Harga Satuan 46,969.14
Acuan : ABK Bangunan Gedung dan Perumahan - 6.8
1m2 Pengecatan Tembok Baru (1 Lapis Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup)
Dengan Cat Mutu Baik. (P.Ct. 11)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 60,000.00 0.020 1,200.00
2 Tukang Cat OH 70,000.00 0.063 4,410.00
3 Kepala Tukang OH 75,000.00 0.0063 472.50
4 Mandor OH 75,000.00 0.0025 187.50
Jumlah 6,270.00
B BAHAN
1 Plamur (dempul tembok) Kg 49,054.01 0.100 4,905.40
2 Cat Dasar tembok Kg 31,305.12 0.120 3,756.61
3 Cat Tembok Penutup 2 x Kg 43,324.05 0.260 11,264.25
19,926.27
C Jumlah A + B 26,196.27
D Harga Satuan 26,196.27
Acuan : ABK Bangunan Gedung dan Perumahan - 6.14
Pekerjaan Pengecatan 23
M. PEKERJAAN BONGKARAN (P. Bkr.)
1m2 Pekerjaan Bongkaran Dinding Tembok Plesteran Simpai (P. Bkr. 02)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 70,950.00 1.000 70,950.00
2 Mandor OH 98,230.00 0.050 4,911.50
Jumlah 75,861.50
B Jumlah A 75,861.50
C Harga Satuan 75,861.50
Acuan : Harga Satuan Bahan, Upah dan Analisa Biaya Pekerjaan BOW - L.4
Pekerjaan Bongkaran 24
HARGA SATUAN BAHAN DAN UPAH BERDASARKAN HARGA SATUAN BAHAN DAN UPAH YANG DIKELUARKAN OLEH DINAS
PEKERJAAN UMUM KABUPATEN KETAPANG
MENGETAHUI / MENYETUJUI
KEPALA SEKOLAH PONTIANAK, APRIL 2012
MADRASAH ALIYAH NEGERI 2 KETAPANG DIBUAT OLEH KONSULTAN PERENCANA
PT.QUADRAN KONSULINDO
TENTANG
STANDARISASI HARGA SATUAN BAHAN, UPAH DAN ANALISA
BIAYA PEKERJAAN YANG TERDIRI DARI ANALISA E DAN ANALISA
BIAYA KONSTRUKSI BANGUNAN GEDUNG DAN PERUMAHAN (ABK-SNI) KOTA PONTIANAK
TAHUN ANGGARAN 2010
HARGA
A. UPAH
1 Mandor Lapangan Org/hari L.061 60,500.00 6,050.00 66,550.00
2 Mekanik Org/hari L.071 60,500.00 6,050.00 66,550.00
3 Kepala Tukang Org/hari L.073 60,500.00 6,050.00 66,550.00
4 Tukang Batu / Kayu / Gali / Besi / Cor / Semen / Cat / Listrik / Pancang Org/hari L.079 55,000.00 5,500.00 60,500.00
5 Operator terlatih Org/hari L.081 49,500.00 4,950.00 54,450.00
6 Operator semi terlatih Org/hari L.082 44,000.00 4,400.00 48,400.00
7 Sopir Org/hari L.091 49,500.00 4,950.00 54,450.00
8 Pekerja / Buruh Lapangan Tak terlatih Org/hari L.101 44,000.00 4,400.00 48,400.00
9 Pekerja / Buruh Lapangan terlatih Org/hari L.106 49,500.00 4,950.00 54,450.00
HARGA TERMASUK
NO MATERIAL SATUAN KODE KEUNTUNGAN
(OVERHEAD)
(Rp)
B. BAHAN PENGISI
1 Batu Kong M³ M.101 192,500.00
2 Batu Sap Pinang M³ - 215,050.00
3 Batu pecah 15-20 cm M³ - 230,230.00
4 Batu pecah 10-15 cm M³ M.020 246,070.00
5 Batu pecah 5-7 cm M³ M.022 271,060.00
6 Batu pecah 3-5 cm M³ M.023 290,700.00
7 Batu pecah 2-3 cm M³ M.024 327,030.00
8 Batu pecah 1-2 cm M³ M.025 373,580.00
9 Batu pecah 1-1 cm M³ - 394,900.00
10 Batu pecah 0,5 cm M³ M.026 394,900.00
11 Stone Dust M³ - 371,360.00
12 Aspal Kg - 9,900.00
13 Pasir M³ M.040 58,370.00
14 Semen PC Zak M.080 70,400.00
15 Semen PC Kg - 1,400.00
16 Tanah Ex. Peniraman M³ M.050.a 115,060.00
17 Tanah EX. Peladis M³ M.050 220,000.00
18 Paving Block Bh - 2,200.00
19 Paving Stone Bh - 3,630.00
20 Batu Bata 5 x 11 x 22cm Bh - 2,530.00
21 Bataco 15 x 30 x 7 cm Bh - 990.00
22 Bataco 20 x 40 x 9 cm ( press ) Bh - 2,530.00
23 Bataco 20 x 40 x 7 cm ( press ) Bh - 2,310.00
24 Kerawang ( roster ) 18 x 18 cm Bh - 3,300.00
25 Kerawang press ( roster ) 30 x 30 cm Bh - 26,400.00
26 Keramik 20 x 20 cm Kotak - 50,120.00
27 Keramik 30 x 30 cm Kotak - 40,030.00
28 Keramik 30 x 30 cm Unpolished Kotak - 54,450.00
29 Keramik 30 x 30 cm Artistik Kotak - 64,130.00
30 Keramik 40 x 40 cm (biasa) Kotak - 71,390.00
31 Keramik 40 x 40 cm (anti gores) Kotak - 96,250.00
32 Keramik 40 x 40 cm Unpolished Kotak - 98,450.00
33 Keramik 60 x 60 cm (anti gores) Kotak - 277,200.00
Keramik 60 x 60 cm (Unpolished) Kotak - 346,500.00
34 Granito 40 x 40 cm Kotak - 189,420.00
35 Marmer M² - 453,750.00
36 Wood Flooring M² - 275,000.00
37 List Keramik WC. 8 x 20 cm Bh - 242,000.00
38 Plint Kayu uk. 2 x 10 cm M1 - 46,750.00
39 Keramik dinding 20 x 20 cm Kotak - 50,380.00
40 Keramik dinding 20 x 25 cm Kotak - 54,890.00
41 Floor Hardener Kg - 8,250.00
HARGA TERMASUK
NO MATERIAL SATUAN KODE KEUNTUNGAN
(OVERHEAD)
(Rp)
C. BAHAN KAYU
1 Ky. Belian tdk ketam Uk. 6/6 - 4 M M³ - 9,736,320.00
2 Ky. Belian tdk ketam Uk. 7/7 - 4 M M³ - 11,463,540.00
3 Ky. Belian tdk ketam Uk. 8/8 - 4 M M³ - 9,063,230.00
4 Ky. Belian tdk ketam Uk. 9/9 - 4 M M³ M.181.a 9,350,550.00
5 Ky. Belian tdk ketam Uk. 10/10 - 4 M M³ M.181.b 7,903,940.00
6 Ky. Belian tdk ketam Uk. 12/12 - 4 M M³ - 8,116,350.00
7 Ky. Belian tdk ketam Uk. 18/18 - 4 M M³ - 7,370,770.00
8 Ky. Belian ketam Uk. 6/6 - 4 M M³ - 8,934,750.00
9 Ky. Belian ketam Uk. 7/7 - 4 M M³ - 11,892,210.00
10 Ky. Belian ketam Uk. 8/8 - 4 M M³ - 10,771,200.00
11 Ky. Belian ketam Uk. 5/10 - 4 M M³ - 10,771,200.00
12 Ky. Belian ketam Uk. 4/8 - 4 M M³ - 9,453,120.00
13 Papan belian ketam (4m) M³ M.181.e 16,958,370.00
14 Papan belian tdk ketam (4m) M³ M.181.d 15,074,070.00
15 Ky. klas I Bengkirai uk. 8/8 - 4 M ( ketam ) M³ M.181.f 6,660,170.00
16 Ky. klas I Bengkirai uk. 8/8 - 4 M ( tdk ketam ) M³ M.181.g 11,297,220.00
17 Ky. klas I Bengkirai uk. 7/7 - 4 M ( tdk ketam ) M³ - 4,630,120.00
18 Ky. klas I Bengkirai uk. 7/7 - 4 M ( ketam ) M³ - 6,033,170.00
19 Ky. klas I Bengkirai uk. 5/10 - 4 M ( ketam / untuk kusen ) M³ - 11,550,000.00
20 Kusen Ky Kelas I Bangkirai uk. 5/10 M³ - 82,500.00
21 Ky. klas II Mabang uk. 8/8 - 4 M ( tdk ketam ) M³ M.181.h 2,194,720.00
22 Ky. klas II Mabang uk. 8/8 - 4 M ( ketam ) M³ M.181.i 3,293,620.00
23 Ky. klas II Mabang uk. 7/7 - 4 M ( tdk ketam ) M³ - 3,724,160.00
24 Ky. klas II Mabang uk. 7/7 - 4 M ( ketam ) M³ - 3,168,550.00
25 Ky. klas II Mabang uk. 4/6 - 4 M ( tdk ketam ) M³ - 2,764,960.00
26 Ky. klas II Mabang uk. 5/7 - 4 M ( tdk ketam ) M³ - 1,883,750.00
27 Ky. klas II Mabang uk. 5/10 - 4 M ( tdk ketam ) M³ - 3,053,270.00
28 Ky. klas II Mabang uk. 6/10 - 4 M ( tdk ketam ) M³ - 3,244,010.00
29 Ky. klas II Mabang uk. 6/12 - 4 M ( tdk ketam ) M³ - 3,949,990.00
30 Ky. klas II Mabang uk. 4/8 - 4 M ( tdk ketam ) M³ - 4,109,820.00
31 Ky. klas II Mabang uk. 8/15 - 4 M ( tdk ketam ) M³ - 2,520,870.00
32 Ky. klas II Mabang uk. 8/12 - 4 M ( tdk ketam ) M³ - 4,947,360.00
33 Ky klas III uk. 3/5 - 4 M ( tdk ketam) M³ - 962,500.00
34 Ky klas III uk. 4/6 - 4 M ( tdk ketam) M³ - 2,046,110.00
35 Papan kayu klas II (mabang) tdk ketam M³ M.181.j 4,541,790.00
36 Papan kayu klas II (mabang) ketam M³ M.181.k 6,331,160.00
37 Papan kayu klas I tdk ketam M³ - 9,052,120.00
38 Papan kayu klas I ketam M³ - 7,562,500.00
39 Papan mal klas III M³ M.181.l 1,323,520.00
40 Papan Simpiran M³ - 604,780.00
41 Renglat kayu klas I uk 1/8 cm Btg - 19,360.00
42 Kayu profil 10cm Btg - 20,680.00
43 Kayu cerucuk /dolken ø 6 - 8 - Pj. 4 M Btg - 5,630.00
44 Kayu cerucuk /dolken ø10 - Pj. 4 M Btg - 10,450.00
45 Kayu cerucuk /dolken ø12 - Pj. 12 M Btg - 66,000.00
46 Kayu cerucuk /dolken ø 15 - Pj. 12 M Btg - 82,500.00
47 Kayu Simpiran / Bakar M³ - 181,500.00
48 Alas kayu hutan Btg - 16,500.00
D. BAHAN CAT
1 Amplas Lbr - 2,310.00
2 Minyak cat Kg - 27,940.00
3 Cat kilat Kg - 42,130.00
4 Plamur Kg - 29,480.00
5 Cat dasar Kg - 33,000.00
6 Cat tembok Kg - 36,520.00
7 Cat tembok type weather shield Kg - 40,260.00
8 Cat tembok type weather coat (acrylic) Kg - 80,080.00
9 Cat seng Kg - 42,900.00
10 Dempul Kg - 27,940.00
11 Plitur Kg - 39,160.00
12 Thiner Ltr M.090.f 22,990.00
13 Thiner ND Ltr - 32,450.00
14 Melamic Ltr - 56,540.00
15 Vernis Ltr - 30,910.00
16 Meni Kg - 44,220.00
17 Oker Kg - 55,820.00
18 Lem Kayu Kg - 20,400.00
19 Sealent Tube - 137,500.00
20 Soda Api Kg - 11,660.00
21 Sabun / cream pembersih kotoran Kg - 20,350.00
22 Teak Oil Ltr - 44,000.00
23 Ter / Residu Ltr - 25,300.00
24 Kuas 4" Bh - 17,710.00
25 Road Line Paint ( Cat Marka ) Ltr M.090.e 49,500.00
26 Glass Bit Kg M.090.g 36,520.00
HARGA TERMASUK
NO MATERIAL SATUAN KODE KEUNTUNGAN
(OVERHEAD)
(Rp)
F. BAHAN PENGANTUNG
1 Pintu Plastik untuk WC Bh - 302,500.00
2 Kait angin Bh - 14,850.00
3 Handle Jendela Bh - 16,500.00
4 Handle Pintu Bh - 110,000.00
5 Engsel jendela Bh - 24,750.00
6 Engsel pintu Bh - 33,000.00
7 Slot pintu Bh - 20,350.00
8 Slot jendela Bh - 11,550.00
9 Kunci tanam 2 slag (setaraf Belluci) Bh - 184,250.00
10 Kunci tanam 1 slag Bh - 118,250.00
11 Kunci tanam antik Bh - 179,020.00
12 Kunci tanam biasa Bh - 86,900.00
13 Kunci silinder Bh - 107,250.00
14 Door Closer Bh - 123,750.00
15 Door Stoper Bh - 22,000.00
16 Paku Seng Kg M.166.a 24,530.00
17 Paku campuran 1" - 5 " Kg M.166.b 20,900.00
18 Paku beton Kg - 27,500.00
19 Paku Atap Seng Kg M.166.c 27,500.00
20 Paku triplek Kg - 28,870.00
21 Paku GRC Kg - 28,870.00
22 Paku Zincallume Kg - 38,500.00
23 Sekrup Gypsum Kg - 66,000.00
24 Sekrup Fixer Bh - 330.00
25 Engsel Angin Bh - 11,000.00
G. BAHAN ATAP
1 Sirap belian Lbr - 5,500.00
2 Asbes Lbr - 55,000.00
3 Eternit M² - 71,500.00
4 Genteng Metal Type Prima 0.35 Lbr - 69,630.00
5 Genteng Metal Type Royal 0.35 Lbr - 69,630.00
6 Genteng Metal Type Classic 0.35 Lbr - 67,320.00
7 Genteng Metal Stone ( Type Classic 0.35 ) Lbr - 88,880.00
8 Genteng Metal Stone ( Type Prima 0.35 ) Lbr - 88,880.00
9 Atap Metal Supersheet 0.35 (polos) M' - 93,500.00
10 Atap Metal Supersheet 0.35 (polos) M² - 116,930.00
11 Atap Trim Deck 0.3 (polos) M² - 104,530.00
12 Atap Trim Deck 0.33 (color) M² - 117,420.00
13 Nok bubungan genteng metal 1/2 lingkaran 0.35 (pj 40cm) Bh - 71,500.00
14 Nok bubungan genteng metal stone 1/2 lingkaran 0.35 (pj 40cm) Bh - 88,000.00
15 Nok bubungan genteng metal kotak 0.35 M' - 85,360.00
16 Nok bubungan genteng metal stone kotak 0.35 M' - 101,200.00
17 Nok bubungan Trim Deck (polos) M' - 114,400.00
18 Nok bubungan Trim Deck (color) M' - 128,700.00
19 Seng Gelombang Bjls 30 Lbr - 71,390.00
20 Seng Gelombang Bjls 20 Lbr - 51,370.00
21 Seng Plat Bjls 20 Lbr - 52,800.00
22 Seng Plat Bjls 30 Lbr - 71,500.00
23 Seng Plat Bjls 30 (lebar 45 cm) M' - 20,900.00
24 Plat Datar Color 0.35 Lbr - 60,500.00
25 Zincalume Gelombang Persegi 0.35 (polos) M² - 114,120.00
26 Zincalume Gelombang Persegi 0.30 (polos) M² - 100,370.00
27 Zincalume Gelombang Persegi 0.35 (color) M² - 127,870.00
28 Zincalume Gelombang Persegi 0.30 (color) M² - 114,120.00
29 Zincalume Plat 0.2 Lbr - 130,900.00
30 Aluminium Foil M² - 55,000.00
HARGA TERMASUK
NO MATERIAL SATUAN KODE KEUNTUNGAN
(OVERHEAD)
(Rp)
H. BAHAN KACA
1 Kaca Polos, t = 5 mm M² - 109,450.00
2 Kaca Polos, t = 12mm M² - 422,400.00
3 Kaca Rayben, t = 5 mm M² - 146,300.00
4 Kaca Cermin t = 3mm M² - 156,750.00
5 Kaca Patri M² - 1,045,000.00
6 Sealent Kg - 111,650.00
7 Nako + Bingkai (80 x 15) x 10 daun polos Bh - 214,500.00
8 Nako + Bingkai (80 x 15) x 10 daun rayben Bh - 225,500.00
9 Kaca Es M² - 167,200.00
I. BAHAN TRIPLEK
1 Triplek t = 3 mm Lbr - 60,500.00
2 Triplek t = 6 mm Lbr - 133,100.00
3 Triplek t =9 mm Lbr - 165,000.00
4 Multiplek t = 10 mm Lbr - 187,000.00
5 Multiplek t = 12 mm Lbr - 222,200.00
HARGA TERMASUK
NO MATERIAL SATUAN KODE KEUNTUNGAN
(OVERHEAD)
(Rp)
J. BAHAN SANITASI
1 Kloset duduk monoblok Bh - 1,705,000.00
2 Kloset duduk putih (setaraf TOTO) Bh - 2,145,000.00
3 Kloset duduk warna (setaraf TOTO) Bh - 2,343,000.00
4 Kloset jongkok (setaraf TOTO) Bh - 204,600.00
5 Kloset jongkok (setaraf INA) Bh - 137,500.00
6 Kran air uk 1/2" Bh - 38,500.00
7 Pipa paralon dia 1/2" Btg - 17,820.00
8 Pipa paralon dia 3/4" Btg - 27,670.00
9 Pipa paralon dia 1" Btg - 40,700.00
10 Pipa paralon dia 2" Btg - 61,820.00
11 Pipa paralon dia 3" Btg - 117,150.00
12 Pipa paralon dia 4" Btg - 154,000.00
TENTANG
STANDARISASI HARGA SATUAN BAHAN, UPAH DAN ANALISA
BIAYA PEKERJAAN YANG TERDIRI DARI ANALISA E DAN ANALISA
BIAYA KONSTRUKSI BANGUNAN GEDUNG DAN PERUMAHAN (ABK-SNI) KOTA PONTIANAK
TAHUN ANGGARAN 2010
HARGA
A. UPAH
1 Mandor Lapangan Org/hari L.061 60,500.00 6,050.00 66,550.00
2 Mekanik Org/hari L.071 60,500.00 6,050.00 66,550.00
3 Kepala Tukang Org/hari L.073 60,500.00 6,050.00 66,550.00
4 Tukang Batu / Kayu / Gali / Besi / Cor / Semen / Cat / Listrik / Pancang Org/hari L.079 55,000.00 5,500.00 60,500.00
5 Operator terlatih Org/hari L.081 49,500.00 4,950.00 54,450.00
6 Operator semi terlatih Org/hari L.082 44,000.00 4,400.00 48,400.00
7 Sopir Org/hari L.091 49,500.00 4,950.00 54,450.00
8 Pekerja / Buruh Lapangan Tak terlatih Org/hari L.101 44,000.00 4,400.00 48,400.00
9 Pekerja / Buruh Lapangan terlatih Org/hari L.106 49,500.00 4,950.00 54,450.00
HARGA TERMASUK
NO MATERIAL SATUAN KODE KEUNTUNGAN
(OVERHEAD)
(Rp)
B. BAHAN PENGISI
1 Batu Kong M³ M.101 192,500.00
2 Batu Sap Pinang M³ - 215,050.00
3 Batu pecah 15-20 cm M³ - 230,230.00
4 Batu pecah 10-15 cm M³ M.020 246,070.00
5 Batu pecah 5-7 cm M³ M.022 271,060.00
6 Batu pecah 3-5 cm M³ M.023 290,700.00
7 Batu pecah 2-3 cm M³ M.024 327,030.00
8 Batu pecah 1-2 cm M³ M.025 373,580.00
9 Batu pecah 1-1 cm M³ - 394,900.00
10 Batu pecah 0,5 cm M³ M.026 394,900.00
11 Stone Dust M³ - 371,360.00
12 Aspal Kg - 9,900.00
13 Pasir M³ M.040 58,370.00
14 Semen PC Zak M.080 70,400.00
15 Semen PC Kg - 1,400.00
16 Tanah Ex. Peniraman M³ M.050.a 115,060.00
17 Tanah EX. Peladis M³ M.050 220,000.00
18 Paving Block Bh - 2,200.00
19 Paving Stone Bh - 3,630.00
20 Batu Bata 5 x 11 x 22cm Bh - 2,530.00
21 Bataco 15 x 30 x 7 cm Bh - 990.00
22 Bataco 20 x 40 x 9 cm ( press ) Bh - 2,530.00
23 Bataco 20 x 40 x 7 cm ( press ) Bh - 2,310.00
24 Kerawang ( roster ) 18 x 18 cm Bh - 3,300.00
25 Kerawang press ( roster ) 30 x 30 cm Bh - 26,400.00
26 Keramik 20 x 20 cm Kotak - 50,120.00
27 Keramik 30 x 30 cm Kotak - 40,030.00
28 Keramik 30 x 30 cm Unpolished Kotak - 54,450.00
29 Keramik 30 x 30 cm Artistik Kotak - 64,130.00
30 Keramik 40 x 40 cm (biasa) Kotak - 71,390.00
31 Keramik 40 x 40 cm (anti gores) Kotak - 96,250.00
32 Keramik 40 x 40 cm Unpolished Kotak - 98,450.00
33 Keramik 60 x 60 cm (anti gores) Kotak - 277,200.00
34 Granito 40 x 40 cm Kotak - 189,420.00
35 Marmer M² - 453,750.00
36 Wood Flooring M² - 275,000.00
37 List Keramik WC. 8 x 20 cm Bh - 242,000.00
38 Plint Kayu uk. 2 x 10 cm M1 - 46,750.00
39 Keramik dinding 20 x 20 cm Kotak - 50,380.00
40 Keramik dinding 20 x 25 cm Kotak - 54,890.00
41 Floor Hardener Kg - 8,250.00
42 Beton Ready Mix B 0 M³ - 792,000.00
HARGA TERMASUK
NO MATERIAL SATUAN KODE KEUNTUNGAN
(OVERHEAD)
(Rp)
C. BAHAN KAYU
1 Ky. Belian tdk ketam Uk. 6/6 - 4 M M³ - 9,736,320.00
2 Ky. Belian tdk ketam Uk. 7/7 - 4 M M³ - 11,463,540.00
3 Ky. Belian tdk ketam Uk. 8/8 - 4 M M³ - 9,063,230.00
4 Ky. Belian tdk ketam Uk. 9/9 - 4 M M³ M.181.a 9,350,550.00
5 Ky. Belian tdk ketam Uk. 10/10 - 4 M M³ M.181.b 7,903,940.00
6 Ky. Belian tdk ketam Uk. 12/12 - 4 M M³ - 8,116,350.00
7 Ky. Belian tdk ketam Uk. 18/18 - 4 M M³ - 7,370,770.00
8 Ky. Belian ketam Uk. 6/6 - 4 M M³ - 8,934,750.00
9 Ky. Belian ketam Uk. 7/7 - 4 M M³ - 11,892,210.00
10 Ky. Belian ketam Uk. 8/8 - 4 M M³ - 10,771,200.00
11 Ky. Belian ketam Uk. 5/10 - 4 M M³ - 10,771,200.00
12 Ky. Belian ketam Uk. 4/8 - 4 M M³ - 9,453,120.00
13 Papan belian ketam (4m) M³ M.181.e 16,958,370.00
14 Papan belian tdk ketam (4m) M³ M.181.d 15,074,070.00
15 Ky. klas I Bengkirai uk. 8/8 - 4 M ( ketam ) M³ M.181.f 6,660,170.00
16 Ky. klas I Bengkirai uk. 8/8 - 4 M ( tdk ketam ) M³ M.181.g 11,297,220.00
17 Ky. klas I Bengkirai uk. 7/7 - 4 M ( tdk ketam ) M³ - 4,630,120.00
18 Ky. klas I Bengkirai uk. 7/7 - 4 M ( ketam ) M³ - 6,033,170.00
19 Ky. klas I Bengkirai uk. 5/10 - 4 M ( ketam / untuk kusen ) M³ - 11,550,000.00
20 Kusen Ky Kelas I Bangkirai uk. 5/10 M³ - 82,500.00
21 Ky. klas II Mabang uk. 8/8 - 4 M ( tdk ketam ) M³ M.181.h 2,194,720.00
22 Ky. klas II Mabang uk. 8/8 - 4 M ( ketam ) M³ M.181.i 3,293,620.00
23 Ky. klas II Mabang uk. 7/7 - 4 M ( tdk ketam ) M³ - 3,724,160.00
24 Ky. klas II Mabang uk. 7/7 - 4 M ( ketam ) M³ - 3,168,550.00
25 Ky. klas II Mabang uk. 4/6 - 4 M ( tdk ketam ) M³ - 2,764,960.00
26 Ky. klas II Mabang uk. 5/7 - 4 M ( tdk ketam ) M³ - 1,883,750.00
27 Ky. klas II Mabang uk. 5/10 - 4 M ( tdk ketam ) M³ - 3,053,270.00
28 Ky. klas II Mabang uk. 6/10 - 4 M ( tdk ketam ) M³ - 3,244,010.00
29 Ky. klas II Mabang uk. 6/12 - 4 M ( tdk ketam ) M³ - 3,949,990.00
30 Ky. klas II Mabang uk. 4/8 - 4 M ( tdk ketam ) M³ - 4,109,820.00
31 Ky. klas II Mabang uk. 8/15 - 4 M ( tdk ketam ) M³ - 2,520,870.00
32 Ky. klas II Mabang uk. 8/12 - 4 M ( tdk ketam ) M³ - 4,947,360.00
33 Ky klas III uk. 3/5 - 4 M ( tdk ketam) M³ - 962,500.00
34 Ky klas III uk. 4/6 - 4 M ( tdk ketam) M³ - 2,046,110.00
35 Papan kayu klas II (mabang) tdk ketam M³ M.181.j 4,541,790.00
36 Papan kayu klas II (mabang) ketam M³ M.181.k 6,331,160.00
37 Papan kayu klas I tdk ketam M³ - 9,052,120.00
38 Papan kayu klas I ketam M³ - 7,562,500.00
39 Papan mal klas III M³ M.181.l 1,323,520.00
40 Papan Simpiran M³ - 604,780.00
41 Renglat kayu klas I uk 1/8 cm Btg - 19,360.00
42 Kayu profil 10cm Btg - 20,680.00
43 Kayu cerucuk /dolken ø 6 - 8 - Pj. 4 M Btg - 5,630.00
44 Kayu cerucuk /dolken ø10 - Pj. 4 M Btg - 10,450.00
45 Kayu cerucuk /dolken ø12 - Pj. 12 M Btg - 66,000.00
46 Kayu cerucuk /dolken ø 15 - Pj. 12 M Btg - 82,500.00
47 Kayu Simpiran / Bakar M³ - 181,500.00
48 Alas kayu hutan Btg - 16,500.00
D. BAHAN CAT
1 Amplas Lbr - 2,310.00
2 Minyak cat Kg - 27,940.00
3 Cat kilat Kg - 42,130.00
4 Plamur Kg - 29,480.00
5 Cat dasar Kg - 33,000.00
6 Cat tembok Kg - 36,520.00
7 Cat tembok type weather shield Kg - 40,260.00
8 Cat tembok type weather coat (acrylic) Kg - 80,080.00
9 Cat seng Kg - 42,900.00
10 Dempul Kg - 27,940.00
11 Plitur Kg - 39,160.00
12 Thiner Ltr M.090.f 22,990.00
13 Thiner ND Ltr - 32,450.00
14 Melamic Ltr - 56,540.00
15 Vernis Ltr - 30,910.00
16 Meni Kg - 44,220.00
17 Oker Kg - 55,820.00
18 Lem Kayu Kg - 20,400.00
19 Sealent Tube - 137,500.00
20 Soda Api Kg - 11,660.00
21 Sabun / cream pembersih kotoran Kg - 20,350.00
22 Teak Oil Ltr - 44,000.00
23 Ter / Residu Ltr - 25,300.00
24 Kuas 4" Bh - 17,710.00
25 Road Line Paint ( Cat Marka ) Ltr M.090.e 49,500.00
26 Glass Bit Kg M.090.g 36,520.00
HARGA TERMASUK
NO MATERIAL SATUAN KODE KEUNTUNGAN
(OVERHEAD)
(Rp)
F. BAHAN PENGANTUNG
1 Pintu Plastik untuk WC Bh - 302,500.00
2 Kait angin Bh - 14,850.00
3 Handle Jendela Bh - 16,500.00
4 Handle Pintu Bh - 110,000.00
5 Engsel jendela Bh - 24,750.00
6 Engsel pintu Bh - 33,000.00
7 Slot pintu Bh - 20,350.00
8 Slot jendela Bh - 11,550.00
9 Kunci tanam 2 slag (setaraf Belluci) Bh - 184,250.00
10 Kunci tanam 1 slag Bh - 118,250.00
11 Kunci tanam antik Bh - 179,020.00
12 Kunci tanam biasa Bh - 86,900.00
13 Kunci silinder Bh - 107,250.00
14 Door Closer Bh - 123,750.00
15 Door Stoper Bh - 22,000.00
16 Paku Seng Kg M.166.a 24,530.00
17 Paku campuran 1" - 5 " Kg M.166.b 20,900.00
18 Paku beton Kg - 27,500.00
19 Paku Atap Seng Kg M.166.c 27,500.00
20 Paku triplek Kg - 28,870.00
21 Paku GRC Kg - 28,870.00
22 Paku Zincallume Kg - 38,500.00
23 Sekrup Gypsum Kg - 66,000.00
24 Sekrup Fixer Bh - 330.00
25 Engsel Angin Bh - 11,000.00
G. BAHAN ATAP
1 Sirap belian Lbr - 5,500.00
2 Asbes Lbr - 55,000.00
3 Eternit M² - 71,500.00
4 Genteng Metal Type Prima 0.35 Lbr - 69,630.00
5 Genteng Metal Type Royal 0.35 Lbr - 69,630.00
6 Genteng Metal Type Classic 0.35 Lbr - 67,320.00
7 Genteng Metal Stone ( Type Classic 0.35 ) Lbr - 88,880.00
8 Genteng Metal Stone ( Type Prima 0.35 ) Lbr - 88,880.00
9 Atap Metal Supersheet 0.35 (polos) M' - 93,500.00
10 Atap Metal Supersheet 0.35 (polos) M² - 116,930.00
11 Atap Trim Deck 0.3 (polos) M² - 104,530.00
12 Atap Trim Deck 0.33 (color) M² - 117,420.00
13 Nok bubungan genteng metal 1/2 lingkaran 0.35 (pj 40cm) Bh - 71,500.00
14 Nok bubungan genteng metal stone 1/2 lingkaran 0.35 (pj 40cm) Bh - 88,000.00
15 Nok bubungan genteng metal kotak 0.35 M' - 85,360.00
16 Nok bubungan genteng metal stone kotak 0.35 M' - 101,200.00
17 Nok bubungan Trim Deck (polos) M' - 114,400.00
18 Nok bubungan Trim Deck (color) M' - 128,700.00
19 Seng Gelombang Bjls 30 Lbr - 71,390.00
20 Seng Gelombang Bjls 20 Lbr - 51,370.00
21 Seng Plat Bjls 20 Lbr - 52,800.00
22 Seng Plat Bjls 30 Lbr - 71,500.00
23 Seng Plat Bjls 30 (lebar 45 cm) M' - 20,900.00
24 Plat Datar Color 0.35 Lbr - 60,500.00
25 Zincalume Gelombang Persegi 0.35 (polos) M² - 114,120.00
26 Zincalume Gelombang Persegi 0.30 (polos) M² - 100,370.00
27 Zincalume Gelombang Persegi 0.35 (color) M² - 127,870.00
28 Zincalume Gelombang Persegi 0.30 (color) M² - 114,120.00
29 Zincalume Plat 0.2 Lbr - 130,900.00
30 Aluminium Foil M² - 55,000.00
HARGA TERMASUK
NO MATERIAL SATUAN KODE KEUNTUNGAN
(OVERHEAD)
(Rp)
H. BAHAN KACA
1 Kaca Polos, t = 5 mm M² - 109,450.00
2 Kaca Polos, t = 12mm M² - 422,400.00
3 Kaca Rayben, t = 5 mm M² - 146,300.00
4 Kaca Cermin t = 3mm M² - 156,750.00
5 Kaca Patri M² - 1,045,000.00
6 Sealent Kg - 111,650.00
7 Nako + Bingkai (80 x 15) x 10 daun polos Bh - 214,500.00
8 Nako + Bingkai (80 x 15) x 10 daun rayben Bh - 225,500.00
9 Kaca Es M² - 167,200.00
I. BAHAN TRIPLEK
1 Triplek t = 3 mm Lbr - 60,500.00
2 Triplek t = 6 mm Lbr - 133,100.00
3 Triplek t =9 mm Lbr - 165,000.00
4 Multiplek t = 10 mm Lbr - 187,000.00
5 Multiplek t = 12 mm Lbr - 222,200.00
HARGA TERMASUK
NO MATERIAL SATUAN KODE KEUNTUNGAN
(OVERHEAD)
(Rp)
J. BAHAN SANITASI
1 Kloset duduk monoblok Bh - 1,705,000.00
2 Kloset duduk putih (setaraf TOTO) Bh - 2,145,000.00
3 Kloset duduk warna (setaraf TOTO) Bh - 2,343,000.00
4 Kloset jongkok (setaraf TOTO) Bh - 204,600.00
5 Kloset jongkok (setaraf INA) Bh - 137,500.00
6 Kran air uk 1/2" Bh - 38,500.00
7 Pipa paralon dia 1/2" Btg - 17,820.00
8 Pipa paralon dia 3/4" Btg - 27,670.00
9 Pipa paralon dia 1" Btg - 40,700.00
10 Pipa paralon dia 2" Btg - 61,820.00
11 Pipa paralon dia 3" Btg - 117,150.00
12 Pipa paralon dia 4" Btg - 154,000.00
TERTANDA
PARYADI, S.Hut
Harga Satuan Umum (HSU) Barang dan Jasa Pemerintah Kab. Sekadau Thn. 2012 Lembar 223
Harga Satuan Umum (HSU) Barang dan Jasa Pemerintah Kab. Sekadau Thn. 2012 Lembar 236
Harga Satuan Umum (HSU) Barang dan Jasa Pemerintah Kab. Sekadau Thn. 2012 Lembar 237
2 Pintu Ulir Daun Pintu Belian Ukrn. 0,60 x 2,50 m Buah Rp 2,741,250.00
Ukrn. 0,70 x 2,50 m Buah Rp 3,426,563.00
Ukrn. 0,80 x 2,50 m Buah Rp 4,111,875.00
Ukrn. 1,00 x 2,50 m Buah Rp 4,797,188.00
TENTANG
DAFTAR HARGA SATUAN TANAMAN HIAS
DI KOTA PONTIANAK TAHUN 2010
Periode : Januari 2010
I. RUMPUT (LAWN)
1 Rumput gajah ( Axonopus sp )
a. Tandur 100 Titik/M2 M2 9,000
b. Lempeng, jarak lempeng + 2 cm 25 x 25 cm M2 31,000
2 Rumput golf (Tifton grass) Tandur 100 Titik/M2 M2 10,250
3 Rumput manila (Zoysia matrela),jrk lempeng 2 cm 25 x 25 cm M2 9,000
4 Rumput manila (Zoysia matrela) Tandur 100 Titik/M2 M2 5,000
II PENUTUP TANAH
1 Anggrek tanah (Sphatoglotis plicata), rumpun 35 - 40 2 btg, 3 anakan Polybag 8,000
2 Bayam merah (Alteanthera ficoidea), rumpun 20 - 25 1 btg/rumpun Polybag 2,000
3 Beludru coklat (Episcia reptans) 7 - 10 Tajuk 10 - 15 Polybag 3,000
4 Beludru Hijau (Episcia reptans) 7 - 10 Tajuk 10 - 15 Polybag 3,000
5 Botan (Centaurea candisina) 25 - 30 1 btg Polybag 4,500
6 Cendrawasih (Phyllantus sp) 15 - 20 Tajuk 20 - 25 Polybag 12,017
7 Cocor bebek (Kalanchoe pinnata) 15 - 20 1 btg Polybag 5,000
8 Crossandra 20 - 40 Tajuk 20 - 25 Polybag 11,000
9 Dinding ari (Hemigraphis colorata) 7 - 10 3 s/d 4 btg/rpn Polybag 10,000
10 Dracaena Tricolor 30 Polybag 17,500
11 Gandarusa 15 3 s/d 4 btg/rpn Polybag 3,500
12 Jengger ayam air mancur daun besar 15 - 20 dia. 1 btg Polybag 6,000
13 Jengger ayam air mancur daun kecil 15 - 20 dia. 1 btg Polybag 6,000
14 Jengger ayam a.m. protol besar 20 - 25 dia. Btg 1 cm Polybag 6,000
15 Jengger ayam a.m. protol kecil 20 - 25 dia. Btg 1 cm Polybag 7,000
16 Kembang coklat putih (Zyphyranthes sp) 15 - 20 Tajuk 15 - 20 Polybag 3,250
17 Kembang coklat merah muda (Zyphyranthes sp) 15 - 20 Tajuk 15 - 20 Polybag 3,250
18 Krokot (Althernantera amoenna) 10 5 btg/rpn Polybag 1,000
19 Lili paris bintang (Chlorophytum sp) 10 - 12 1 btg/rpn Polybag 3,250
20 Lili paris kasar (Ophiopogon jaburan) 20 - 25 5 s/d 7 btg/rpn Polybag 5,000
21 Lili paris kasar (Ophiopogon jaburan) 25-35 5 s/d 7 btg/rpn Polybag 10,658
22 Lili paris kucai (Chlorophytum sp) 10 3 s/d 5 btg/rpn Polybag 3,500
21 Lili paris umbi (Chlorophytum sp) 10 3 s/d 5 btg/rpn Polybag 3,250
22 Lili paris brazil (Chlorophytum sp) 15 - 20 3 s/d 5 btg/rpn Polybag 4,500
24 Mirten perak (Malphigia sp) 20 - 25 3 s/d 5 btg/rpn Polybag 12,000
25 Mirten rebah (Malphigia sp) 10 - 15 Tajuk 10 - 15 Polybag 17,500
26 Mirten tegak (Malphigia sp) 30 - 35 3 btg/rpn Polybag 20,000
27 Nanas kerang (Rhoeo discolor) 3-5 1 btg Polybag 3,250
28 Nanas merah (Ananas sp) 15-20 Tajuk 20 - 25 Polybag 4,500
28 Nanas merah (Ananas sp) 30-40 Tajuk 20 - 25 Polybag 7,500
29 Seruni rambat (Wedelia trilobata) 10 3 s/d 5 btg/rpn Polybag 11,996
30 Sutra bombai banci (Portulacca sp) 7 - 10 3 s/d 5 btg/rpn Polybag 1,500
31 Sutra bombai ungu (Portulacca sp) 7 - 10 3 s/d 5 btg/rpn Polybag 2,500
32 Tagetes (Tagetes erecta) 20 - 25 Tajuk 15 - 20 Polybag 2,500
33 Nanas kerang (Rhoeo discolor) 20 1 btg Polybag 5,000
34 Katis kodok hijau (Sansiviera sp) isi 10 10 10 btg/pot Polybag 4,750
35 Katis kodok kuning (Sansiviera sp) isi 10 10 10 btg/pot Polybag 6,250
NO JENIS BAHAN PERTAMANAN UKURAN
TINGGI DIAMETER UNIT HARGA BAHAN
(cm) (cm)
1 2 3 4 5 6
36 Pedang-pedangan strip kuning (Sansiviera sp) 30 - 35 5 s/d 7 btg/rpn Polybag 6,750
37 Pedang-pedangan strip hijau (Sansiviera sp) 30 - 35 5 s/d 7 btg/rpn Polybag 5,250
38 Pandan Kuning Africa 30 Polybag 10,000
39 Pangkas kuning kecil (Duranta repens) 10 3 s/d 5 btg/rpn Polybag 2,000
40 Pangkas kuning sedang (Duranta repens) 15 3 s/d 5 btg/rpn Polybag 3,250
41 Lantana Warna-Warni 15 3 s/d 5 btg/rpn Polybag 6,000
42 Taiwan Beauty bunga ungu (Cuphea sp) 25 Tajuk 15 Polybag 10,500
44 Taiwan Beauty bunga ungu (Cuphea sp) 16 Tajuk 15 Polybag 4,000
45 Cover Crop (Kacang-kacangan) 7-10 10 btg / rpn Polybag 1,500
III PERDU
1 Agave putih (Agave sp) 40 dia. Tajuk 30 Polybag 55,000
2 Agave biasa (Agave sp) 50 dia. Tajuk 40 Polybag 37,500
3 Aglonema (Aglaonema sp) 40 3 btg Polybag 30,000
4 Bilawan (Plumbago aphylia) 10 - 15 3 btg Polybag 40,000
5 Bougenvil berbunga bentukan penuh 60 dia.Tajuk 60 Polybag 125,000
6 Bougenvil hawai (Bougainvillea sp) 60 dia.Tajuk 60 Polybag 150,000
7 Bougenvil Biasa 60 dia.Tajuk 60 Polybag 50,000
8 Dendron biasa (Phillodendron sp) 15 - 20 1 btg Polybag 20,000
9 Dendrose lokal Jkt Merah 20 - 40 dia.Tajuk 10-15 Polybag 17,500
10 Balanceng india (Dieffenbachia sp) 30 3 daun/btg Polybag 22,500
11 Dracena tricolor (Dracena sp) 30 dia. Tajuk 30 Polybag 15,000
12 Kacapiring (Gardenia sp) 50 dia. Tajuk 30 Polybag 12,500
13 Pisang-pisangan (Heliconia sp) bunga
kuning / merah 50 2 s/d 3 btg/rpn Polybag 5,000
14 Spatiphylum lokal (Spatiphylum sp) 15 - 20 3 bth/pot Polybag 11,000
15 Spatiphylum luar (Spatiphylum sp) 15 - 20 3 btg Polybag 25,000
16 Beringin putih kecil (Ficus hybrida) ex Jkt 30 diaTajuk 15 -20 Polybag 145,000
17 Kamboja jepang (Adenium cutanium) bercabang 30 dia.Tajuk 15-20 Polybag 27,500
18 Kamboja putih 100 dia. Btg 3 Polybag 100,000
19 Kamboja rantai 100 dia. Btg 3 Polybag 90,000
20 Kana (Canna hibrida) 40 2 s/d 3 btg/rpn Polybag 10,000
21 Kastuba (Euphorbia pulcherima) 25 - 30 dia. Tajuk 30 Polybag 35,000
22 Kembang sepatu putih (Hibiscus mutabilis) 30 1 btg/pot Polybag 27,500
23 Lusiana 50 - 75 dia. Btg 1,5 Polybag 22,500
24 Mawar putih (Rosa Hybrida) 25 dia.Tajuk15 -20 Polybag 5,000
25 Mawar merah (Rosa Hybrida) 30 dia.Tajuk 15-20 Polybag 5,000
26 Melati costa (Jasminum sp) 50 2 anakan/rpn Polybag 22,500
27 Melati Gambir (Jasminum sp) 50 2 anakan/rpn Polybag 22,500
28 Melati Malaysia Polybag 22,500
29 Oleander (Nerium indicum) 30 1 rpn Polybag 11,000
30 Pepayungan (Cyperus altemifolius) 60 5 anakan/pot Polybag 8,500
31 Pandan hijau jepang (Pandanus sp) 50 1 rpn Polybag 35,000
32 Pandan kuning afrika 50 1 rpn Polybag 37,500
33 Pangkas Hijau 10 3 s/d 5 btg/rpn Polybag 1,500
33 Pangkas Hijau 20-40 3 s/d 5 btg/rpn Polybag 2,250
34 Variegata Polybag 15,000
34 Sambang darah 50 dia. Tajuk 30 Polybag 40,000
35 Siklok Polybag 92,500
36 Wali songo daun kecil (Scheffera sp) 50 1 btg/pot Polybag 20,000
37 Soka bangkok (Ixora sp) 20 1 btg/pot Polybag 6,500
38 Soka jepang bunga orange (Ixora sp) 20 1 btg/pot Polybag 4,000
39 Soka philipina (Ixora sp) 20 1 btg/pot Polybag 4,000
40 Soka siantan (Ixora tricia) 20 1 btg/pot Polybag 4,000
NO JENIS BAHAN PERTAMANAN UKURAN
TINGGI DIAMETER UNIT HARGA BAHAN
(cm) (cm)
1 2 3 4 5 6
41 Soka singapura (Ixora cocineae) bunga
putih, pink 30 1 btg/pot Polybag 4,000
42 Soka jawa/hawai (Ixora sp) 30 1 btg/pot Polybag 5,000
43 Terang bulan daun putih/kuning (Thitonia sp) 20 3 s/d 5 btg/rpn Polybag 6,000
44 Tombak raja (Yucca gloriosa) 40 3 s/d 5 btg/rpn Polybag 52,500
45 Tapak dara 10 - 15 3 s/d 5 btg/rpn Polybag 3,500
46 Pangkas Hijau 3-5 3 s/d 5 btg/rpn Polybag 1,500
47 Pangkas Hijau 20 4 s/d 7 btg/rpn Polybag 2,500
48 Bayam Merah 10 - 15 3 s/d 5 btg/rpn Polybag 2,000
49 Soka Merah 20 1 btg/pot Polybag 6,500
50 Bawang-bawangan 15-20 f5 s/d 7 btg/rpn Polybag 5,050
51 Bawang-bawangan 20-25 f5 s/d 7 btg/rpn Polybag 6,000
52 Veberia Polybag 7,500
53 Vinolia 20-30 5 s/d 10btg/rpn Polybag 6,000
54 Vinolia 10-15 2 s/d 4 btg/rpn Polybag 5,750
55 Vinolia 35-40 12sd 20 btg/rpn Polybag 6,500
56 Variegata Polybag 15,000
57 Aires Polybag 4,950
58 Ketela Merah 10 1sd 2 btg/rpn Polybag 3,650
59 Kana Presiden 15 - 20 1sd 2 btg/rpn Polybag 5,000
IV TANAMAN PAGAR
1 Kedondong laut (Nothopanax sp) 30-65 3 s/d 4 btg/rpn Polybag 6,000
2 Kedondong laut (Nothopanax sp) 60 - 75 3 s/d 4 btg/rpn Polybag 8,750
3 Kemuning (Murraya paniculata) 75 1 btg/rpn Polybag 35,000
4 Lantana pagar (Lantana camara) 30 1rpn Polybag 17,500
5 Mangkokan (Nothopanax sp) 50 3 s/d 4 btg/rpn Polybag 15,000
6 Mirten pagar (Malphigia sp) 50 3 s/d 4 btg/rpn Polybag 15,000
7 The-tehan tinggi (Durantha repens) 30 3 s/d 4 btg/rpn Polybag 13,500
8 The-tehan tinggi (Durantha repens) 50 3 s/d 4 btg/rpn Polybag 23,500
9 The-tehan tinggi (Durantha repens) 70 3 s/d 4 btg/rpn Polybag 30,000
10 Krokot 15 Polybag 1,008
V TANAMAN MERAMBAT
1 Air mata pengantin ( Antigonon leptapus) 30 dia. Tajuk 430 Polybag 40,000
2 Air mata pengantin ( Antigonon leptapus) 50 dia. Tajuk 40 Polybag 47,500
2 Alamanda (Alamanda cathartica) 30 dia. Tajuk 20 Polybag 12,500
3 Alamanda (Alamanda cathartica) 50 dia. Tajuk 40 Polybag 15,000
4 Arabidea (Arabidea sp) 40 dia. Tajuk 30 Polybag 50,000
5 Flame of irian (Orange) 40 dia. Tajuk 30 Polybag 35,000
6 Kembang kelinci (Ipomea sp) 40 dia. Tajuk 30 Polybag 40,000
7 Kembang sungsang (Gloriosa superba) 30 dia. Tajuk 20 Polybag 40,000
8 Lantana rambut ungu (Lantana sp) 20 3 s/d 4 btg/rpn Polybag 7,500
9 Pasiflora 60 dia. Tajuk 40 Polybag 20,000
10 Sirih Gading daun strip kuning (Scindapsus sp) 30 3 s/d 4 btg/rpn Polybag 10,000
11 Sthephanot bunga putih
(Sthepanothis floribunda) 30 dia. Tajuk 40 Polybag 30,000
12 Nona Makan Sirih 30 Polybag 15,000
13 Ubi rambat Kuning 30 Polybag 2,500
VI TANAMAN HIAS
1 Anjuang hijau (Dracaena sp) 60 dia. Tajuk 40 Polybag 10,000
2 Anjuang kribo (Dracaerna sp) 60 dia. Tajuk 40 Polybag 11,000
3 Anjuang kuning (Dracaerna sp) 60 dia. Tajuk 40 Polybag 12,500
NO JENIS BAHAN PERTAMANAN UKURAN
TINGGI DIAMETER UNIT HARGA BAHAN
(cm) (cm)
1 2 3 4 5 6
4 Anjuang merah (Cordelyne terminalis) 40 dia. Tajuk 20 Polybag 8,000
5 Anjuang merah (Cordelyne terminalis) 60 dia. Tajuk 40 Polybag 11,000
6 Anjuang merah (Cordelyne terminalis) 80 dia. Tajuk 50 Polybag 15,000
7 Anjuang suji (Dracaena sp) 60 dia. Tajuk 40 Polybag 13,500
8 Azalea (Azalea sp) 50 dia. Tajuk 40 Polybag 25,000
9 Bakung kecil (Hymenochalys sp) 20 dia. Tajuk 40 Polybag 5,500
10 Beringin bonsai (Ficus benjamina) 100 - 200 dia. Tajuk 100 Polybag 225,000
11 Beringin bonsai bentukan (Ficus benjamina) 100 - 200 dia. Tajuk 100 Polybag 375,000
12 Beringin bonsai putih (Ficus benjamina) 250 dia. Tajuk 100 Polybag 1,000,000
13 Bonsai serut 151 - 200 dia. Tajuk 100 Polybag 2,500,000
14 Nusa indah merah/putih (Nussaenda sp) 50 dia. Tajuk 40 Polybag 20,000
15 Rambusa 50 Polybag 30,000
16 Pakis kelabang kuning (Neprolephis sp) 40 5 s/d 7 btg/rpn Polybag 10,000
17 Pakis krol (Neprolephis sp) 40 5 s/d 7 btg/rpn Polybag 12,500
18 Pakis monyet (Alsophila glauca) 150 - 200 dia. Tajuk 40 Polybag 200,000
19 Pisang kipas (Ravanela madagaskariensis) 200 - 250 dia. Btg 10 Polybag 475,000
20 Puring bor (Codiaeum sp) 75 dia. Tajuk 30 Polybag 20,000
21 Puring buntut (Codiaeum sp) 75 dia. Tajuk 30 Polybag 20,000
22 Puring gelatik (Codiaeum sp) 75 dia. Tajuk 30 Polybag 20,000
23 Puring jet (Codiaeum sp) 40 dia. Tajuk 20 Polybag 14,500
24 Puring jet (Codiaeum sp) 75 dia. Tajuk 30 Polybag 30,000
25 Puring ketapang (Codiaeum sp) 50 dia. Tajuk 30 Polybag 20,000
26 Puring nuri (Codiaeum sp) 60 dia. Tajuk 30 Polybag 20,000
27 Puring Kuning 20 dia. Tajuk 30 Polybag 7,500
28 Siklok dia. Btg 5 Polybag 100,000
29 Sikas/Pakis haji halus (Cycas revoluta) 80 dia. Btg 7,5 Polybag 900,000
30 Sikas diameter tajuk daun (Cycas sp) 100 dia. Btg 10 Polybag 1,000,000
31 Sikas medan (Cycas sp) 100 dia. Btg 10 Polybag 1,350,000
32 Sikas/pakis haji kasar (Cycas rumpi) 50 - 100 dia. Btg 7,5 Polybag 125,000
33 Kamboja kuning (Bali) tinggi (Plumeria sp) 150 - 200 dia. Btg 3 Polybag 400,000
34 Kamboja orange tinggi (Plumeria sp) 150 - 200 dia. Btg 3 Polybag 300,000
35 Lidah Buaya Besar 10-25 2-3 btg/pot Polybag 40,000
36 Lidah Buaya Kecil 50 5-7 btg/pot Polybag 15,000
VII PALEM
1 Kelapa gading (Cocos capitata) 200 - 250 dia. Btg 20 Phn 450,000
2 Kelapa sawit (Elais guineensis) 200 - 250 dia. Btg 40 Phn 450,000
3 Kelapa sayur (Cocos nucifera) 200 - 250 dia. btg 30 Phn 175,000
4 Kurma (Phoenix daetilifera) 100 dia. btg 30 Phn 400,000
5 Kurma (Phoenix daetilifera) >200 dia. Btg 40 Phn 3,500,000
6 Lontar (Borassus flabefiter) 300 dia. Btg 25 Phn 400,000
7 Palm anggur (Lalania loglgessu) 100 dia. Btg 15 Phn 150,000
8 Palm alexander 150 dia. Btg 10 Phn 125,000
9 Palm botol 150 - 200 dia. btg 30 Phn 300,000
10 Palm camedoria 100 3 s/d 5 btg/rpn Phn 110,000
11 Palm camedoria 200 3 s/d 5 btg/rpn Phn 300,000
12 Palm ekor tupai 50-75 Phn 45,000
13 Palm ekor tupai 200 dia. Btg 15 Phn 225,000
14 Palm jepang (Ptychosperma macarthurii) 100 - 150 5 s/d 7 btg/rpn Rmp 110,000
15 Palm jepang (Ptychosperma macarthurii) 150 - 250 5 s/d 7 btg/rpn Rmp 250,000
16 Palm kol (Licuala grandis) 100 dia. Btg 10 Phn 65,000
18 Palm kuning (Chrysalidocarpus lutescens) 50 - 100 3 s/d 5 btg/rpn Phn 42,500
19 Palm kuning (Chrysalidocarpus lutescens) 100 - 150 5 s/d 7 btg/rpn Rmp 125,000
20 Palm korembusa 50 dia. Btg 5 Phn 40,000
NO JENIS BAHAN PERTAMANAN UKURAN
TINGGI DIAMETER UNIT HARGA BAHAN
(cm) (cm)
1 2 3 4 5 6
21 Palm korembusa 100 dia. Btg 7 Phn 60,000
22 Palm korembusa >200 dia. Btg 10 Phn 70,000
23 Palm merah (Cyrtotachis lakka) 150 - 200 3 s/d 5 btg/rpn Phn 110,000
24 Palm merah (Cyrtotachis lakka) 300 - 350 5 s/d 7 btg/rpn Rmp 325,000
25 Palm phoeniks (Phoenix sp) 75 - 100 dia. Btg 8 Phn 175,000
26 Palm phoeniks (Phoenix sp) 150 - 200 dia. Btg 10 Phn 375,000
26 Palm putri 50 Phn 45,000
27 Palm putri 100-150 dia. Btg 10 Phn 140,000
28 Palm putri 150 - 200 dia. Btg 10 Phn 300,000
29 Palm pigni (Phoenix canariensis) 100 - 150 dia. Btg 10 Phn 8,000,000
30 Palm raja (Oredoxa regia) 100 - 200 dia. Btg 20 Phn 150,000
31 Palm raja (Super oredoxa regia) 200 - 300 dia. Btg 25 Phn 425,000
32 Palm ratu 100 - 150 dia. Btg 10 Phn 80,000
33 Palm sadeng (Livistonia rotundifolta) 50 dia. Btg 5 Phn 62,500
34 Palm saderi (Caroutamiti) 150 dia. Btg 8 Phn 70,000
35 Palm seledri tunggal tinggi 150 dia. Btg 8 Phn 150,000
36 Palm seledri tunggal putih 200 dia. Btg 8 Phn 400,000
37 Palm udang 50 3 s/d 5 btg/rpn Phn 35,000
38 Palm waregu (Rhapis excelsa) 150 5 s/d 7 btg/rpn Rmp 50,000
39 Pinang sirih (Areca catechu) 200 dia. Btg 10 Phn 250,000
X BUNGA POTONG
1 Amarilis (Amarylidaceae) 1 Tangkai 17,875
2 Anggrek macan (Arrachnis sp) 1 Tangkai 275,000
3 Anyelir 1 Tangkai 13,750
4 Apple blossom 1 Tangkai 11,000
5 Aster (Asteraceae sp) 1 Tangkai 15,125
6 Anggrek Dendrobium 1 Tangkai 68,750
7 Gladiol 1 Tangkai 13,750
8 Golden shower 1 Tangkai 55,000
9 Krisan (Chrysanthemum llini) 1 Tangkai 16,500
10 Mawar 1 Tangkai 5,500
PARYADI, S.Hut
A. PEKERJAAN PERSIAPAN (P.Ps)
1m2 Membersihkan Lapangan dan Perataan (P.Ps. 03)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 70,000.00 0.100 7,000.00
2 Mandor OH 75,000.00 0.050 3,750.00
Jumlah 10,750.00
B Jumlah A 10,750.00
C Harga Satuan 10,750.00
Acuan : ABK Bangunan Gedung dan Perumahan - 6.8
Pekerjaan Persiapan 72
LAMPIRAN 2 : KEPUTUSAN WALIKOTA PONTIANAK
NOMOR : ………………… TAHUN 2010
TANGGAL : ……………-…………2010
TENTANG
DAFTAR HARGA SATUAN TANAMAN HIAS
DI KOTA PONTIANAK TAHUN 2010
Periode : Januari 2010
I. RUMPUT (LAWN)
1 Rumput gajah ( Axonopus sp )
a. Tandur 100 Titik/M2 M2 9,000
b. Lempeng, jarak lempeng + 2 cm 25 x 25 cm M2 31,000
2 Rumput golf (Tifton grass) Tandur 100 Titik/M2 M2 10,250
3 Rumput manila (Zoysia matrela),jrk lempeng 2 cm 25 x 25 cm M2 9,000
4 Rumput manila (Zoysia matrela) Tandur 100 Titik/M2 M2 5,000
II PENUTUP TANAH
1 Anggrek tanah (Sphatoglotis plicata), rumpun 35 - 40 2 btg, 3 anakan Polybag 8,000
2 Bayam merah (Alteanthera ficoidea), rumpun 20 - 25 1 btg/rumpun Polybag 2,000
3 Beludru coklat (Episcia reptans) 7 - 10 Tajuk 10 - 15 Polybag 3,000
4 Beludru Hijau (Episcia reptans) 7 - 10 Tajuk 10 - 15 Polybag 3,000
5 Botan (Centaurea candisina) 25 - 30 1 btg Polybag 4,500
6 Cendrawasih (Phyllantus sp) 15 - 20 Tajuk 20 - 25 Polybag 12,017
7 Cocor bebek (Kalanchoe pinnata) 15 - 20 1 btg Polybag 5,000
8 Crossandra 20 - 40 Tajuk 20 - 25 Polybag 11,000
9 Dinding ari (Hemigraphis colorata) 7 - 10 3 s/d 4 btg/rpn Polybag 10,000
10 Dracaena Tricolor 30 Polybag 17,500
11 Gandarusa 15 3 s/d 4 btg/rpn Polybag 3,500
12 Jengger ayam air mancur daun besar 15 - 20 dia. 1 btg Polybag 6,000
13 Jengger ayam air mancur daun kecil 15 - 20 dia. 1 btg Polybag 6,000
14 Jengger ayam a.m. protol besar 20 - 25 dia. Btg 1 cm Polybag 6,000
15 Jengger ayam a.m. protol kecil 20 - 25 dia. Btg 1 cm Polybag 7,000
16 Kembang coklat putih (Zyphyranthes sp) 15 - 20 Tajuk 15 - 20 Polybag 3,250
17 Kembang coklat merah muda (Zyphyranthes sp) 15 - 20 Tajuk 15 - 20 Polybag 3,250
18 Krokot (Althernantera amoenna) 10 5 btg/rpn Polybag 1,000
19 Lili paris bintang (Chlorophytum sp) 10 - 12 1 btg/rpn Polybag 3,250
20 Lili paris kasar (Ophiopogon jaburan) 20 - 25 5 s/d 7 btg/rpn Polybag 5,000
21 Lili paris kasar (Ophiopogon jaburan) 25-35 5 s/d 7 btg/rpn Polybag 10,658
22 Lili paris kucai (Chlorophytum sp) 10 3 s/d 5 btg/rpn Polybag 3,500
21 Lili paris umbi (Chlorophytum sp) 10 3 s/d 5 btg/rpn Polybag 3,250
22 Lili paris brazil (Chlorophytum sp) 15 - 20 3 s/d 5 btg/rpn Polybag 4,500
24 Mirten perak (Malphigia sp) 20 - 25 3 s/d 5 btg/rpn Polybag 12,000
25 Mirten rebah (Malphigia sp) 10 - 15 Tajuk 10 - 15 Polybag 17,500
26 Mirten tegak (Malphigia sp) 30 - 35 3 btg/rpn Polybag 20,000
27 Nanas kerang (Rhoeo discolor) 3-5 1 btg Polybag 3,250
28 Nanas merah (Ananas sp) 15-20 Tajuk 20 - 25 Polybag 4,500
28 Nanas merah (Ananas sp) 30-40 Tajuk 20 - 25 Polybag 7,500
29 Seruni rambat (Wedelia trilobata) 10 3 s/d 5 btg/rpn Polybag 11,996
30 Sutra bombai banci (Portulacca sp) 7 - 10 3 s/d 5 btg/rpn Polybag 1,500
31 Sutra bombai ungu (Portulacca sp) 7 - 10 3 s/d 5 btg/rpn Polybag 2,500
32 Tagetes (Tagetes erecta) 20 - 25 Tajuk 15 - 20 Polybag 2,500
33 Nanas kerang (Rhoeo discolor) 20 1 btg Polybag 5,000
34 Katis kodok hijau (Sansiviera sp) isi 10 10 10 btg/pot Polybag 4,750
35 Katis kodok kuning (Sansiviera sp) isi 10 10 10 btg/pot Polybag 6,250
NO JENIS BAHAN PERTAMANAN UKURAN
TINGGI DIAMETER UNIT HARGA BAHAN
(cm) (cm)
1 2 3 4 5 6
36 Pedang-pedangan strip kuning (Sansiviera sp) 30 - 35 5 s/d 7 btg/rpn Polybag 6,750
37 Pedang-pedangan strip hijau (Sansiviera sp) 30 - 35 5 s/d 7 btg/rpn Polybag 5,250
38 Pandan Kuning Africa 30 Polybag 10,000
39 Pangkas kuning kecil (Duranta repens) 10 3 s/d 5 btg/rpn Polybag 2,000
40 Pangkas kuning sedang (Duranta repens) 15 3 s/d 5 btg/rpn Polybag 3,250
41 Lantana Warna-Warni 15 3 s/d 5 btg/rpn Polybag 6,000
42 Taiwan Beauty bunga ungu (Cuphea sp) 25 Tajuk 15 Polybag 10,500
44 Taiwan Beauty bunga ungu (Cuphea sp) 16 Tajuk 15 Polybag 4,000
45 Cover Crop (Kacang-kacangan) 7-10 10 btg / rpn Polybag 1,500
III PERDU
1 Agave putih (Agave sp) 40 dia. Tajuk 30 Polybag 55,000
2 Agave biasa (Agave sp) 50 dia. Tajuk 40 Polybag 37,500
3 Aglonema (Aglaonema sp) 40 3 btg Polybag 30,000
4 Bilawan (Plumbago aphylia) 10 - 15 3 btg Polybag 40,000
5 Bougenvil berbunga bentukan penuh 60 dia.Tajuk 60 Polybag 125,000
6 Bougenvil hawai (Bougainvillea sp) 60 dia.Tajuk 60 Polybag 150,000
7 Bougenvil Biasa 60 dia.Tajuk 60 Polybag 50,000
8 Dendron biasa (Phillodendron sp) 15 - 20 1 btg Polybag 20,000
9 Dendrose lokal Jkt Merah 20 - 40 dia.Tajuk 10-15 Polybag 17,500
10 Balanceng india (Dieffenbachia sp) 30 3 daun/btg Polybag 22,500
11 Dracena tricolor (Dracena sp) 30 dia. Tajuk 30 Polybag 15,000
12 Kacapiring (Gardenia sp) 50 dia. Tajuk 30 Polybag 12,500
13 Pisang-pisangan (Heliconia sp) bunga
kuning / merah 50 2 s/d 3 btg/rpn Polybag 5,000
14 Spatiphylum lokal (Spatiphylum sp) 15 - 20 3 bth/pot Polybag 11,000
15 Spatiphylum luar (Spatiphylum sp) 15 - 20 3 btg Polybag 25,000
16 Beringin putih kecil (Ficus hybrida) ex Jkt 30 diaTajuk 15 -20 Polybag 145,000
17 Kamboja jepang (Adenium cutanium) bercabang 30 dia.Tajuk 15-20 Polybag 27,500
18 Kamboja putih 100 dia. Btg 3 Polybag 100,000
19 Kamboja rantai 100 dia. Btg 3 Polybag 90,000
20 Kana (Canna hibrida) 40 2 s/d 3 btg/rpn Polybag 10,000
21 Kastuba (Euphorbia pulcherima) 25 - 30 dia. Tajuk 30 Polybag 35,000
22 Kembang sepatu putih (Hibiscus mutabilis) 30 1 btg/pot Polybag 27,500
23 Lusiana 50 - 75 dia. Btg 1,5 Polybag 22,500
24 Mawar putih (Rosa Hybrida) 25 dia.Tajuk15 -20 Polybag 5,000
25 Mawar merah (Rosa Hybrida) 30 dia.Tajuk 15-20 Polybag 5,000
26 Melati costa (Jasminum sp) 50 2 anakan/rpn Polybag 22,500
27 Melati Gambir (Jasminum sp) 50 2 anakan/rpn Polybag 22,500
28 Melati Malaysia Polybag 22,500
29 Oleander (Nerium indicum) 30 1 rpn Polybag 11,000
30 Pepayungan (Cyperus altemifolius) 60 5 anakan/pot Polybag 8,500
31 Pandan hijau jepang (Pandanus sp) 50 1 rpn Polybag 35,000
32 Pandan kuning afrika 50 1 rpn Polybag 37,500
33 Pangkas Hijau 10 3 s/d 5 btg/rpn Polybag 1,500
33 Pangkas Hijau 20-40 3 s/d 5 btg/rpn Polybag 2,250
34 Variegata Polybag 15,000
34 Sambang darah 50 dia. Tajuk 30 Polybag 40,000
35 Siklok Polybag 92,500
36 Wali songo daun kecil (Scheffera sp) 50 1 btg/pot Polybag 20,000
37 Soka bangkok (Ixora sp) 20 1 btg/pot Polybag 6,500
38 Soka jepang bunga orange (Ixora sp) 20 1 btg/pot Polybag 4,000
39 Soka philipina (Ixora sp) 20 1 btg/pot Polybag 4,000
40 Soka siantan (Ixora tricia) 20 1 btg/pot Polybag 4,000
NO JENIS BAHAN PERTAMANAN UKURAN
TINGGI DIAMETER UNIT HARGA BAHAN
(cm) (cm)
1 2 3 4 5 6
41 Soka singapura (Ixora cocineae) bunga
putih, pink 30 1 btg/pot Polybag 4,000
42 Soka jawa/hawai (Ixora sp) 30 1 btg/pot Polybag 5,000
43 Terang bulan daun putih/kuning (Thitonia sp) 20 3 s/d 5 btg/rpn Polybag 6,000
44 Tombak raja (Yucca gloriosa) 40 3 s/d 5 btg/rpn Polybag 52,500
45 Tapak dara 10 - 15 3 s/d 5 btg/rpn Polybag 3,500
46 Pangkas Hijau 3-5 3 s/d 5 btg/rpn Polybag 1,500
47 Pangkas Hijau 20 4 s/d 7 btg/rpn Polybag 2,500
48 Bayam Merah 10 - 15 3 s/d 5 btg/rpn Polybag 2,000
49 Soka Merah 20 1 btg/pot Polybag 6,500
50 Bawang-bawangan 15-20 f5 s/d 7 btg/rpn Polybag 5,050
51 Bawang-bawangan 20-25 f5 s/d 7 btg/rpn Polybag 6,000
52 Veberia Polybag 7,500
53 Vinolia 20-30 5 s/d 10btg/rpn Polybag 6,000
54 Vinolia 10-15 2 s/d 4 btg/rpn Polybag 5,750
55 Vinolia 35-40 12sd 20 btg/rpn Polybag 6,500
56 Variegata Polybag 15,000
57 Aires Polybag 4,950
58 Ketela Merah 10 1sd 2 btg/rpn Polybag 3,650
59 Kana Presiden 15 - 20 1sd 2 btg/rpn Polybag 5,000
IV TANAMAN PAGAR
1 Kedondong laut (Nothopanax sp) 30-65 3 s/d 4 btg/rpn Polybag 6,000
2 Kedondong laut (Nothopanax sp) 60 - 75 3 s/d 4 btg/rpn Polybag 8,750
3 Kemuning (Murraya paniculata) 75 1 btg/rpn Polybag 35,000
4 Lantana pagar (Lantana camara) 30 1rpn Polybag 17,500
5 Mangkokan (Nothopanax sp) 50 3 s/d 4 btg/rpn Polybag 15,000
6 Mirten pagar (Malphigia sp) 50 3 s/d 4 btg/rpn Polybag 15,000
7 The-tehan tinggi (Durantha repens) 30 3 s/d 4 btg/rpn Polybag 13,500
8 The-tehan tinggi (Durantha repens) 50 3 s/d 4 btg/rpn Polybag 23,500
9 The-tehan tinggi (Durantha repens) 70 3 s/d 4 btg/rpn Polybag 30,000
10 Krokot 15 Polybag 1,008
V TANAMAN MERAMBAT
1 Air mata pengantin ( Antigonon leptapus) 30 dia. Tajuk 430 Polybag 40,000
2 Air mata pengantin ( Antigonon leptapus) 50 dia. Tajuk 40 Polybag 47,500
2 Alamanda (Alamanda cathartica) 30 dia. Tajuk 20 Polybag 12,500
3 Alamanda (Alamanda cathartica) 50 dia. Tajuk 40 Polybag 15,000
4 Arabidea (Arabidea sp) 40 dia. Tajuk 30 Polybag 50,000
5 Flame of irian (Orange) 40 dia. Tajuk 30 Polybag 35,000
6 Kembang kelinci (Ipomea sp) 40 dia. Tajuk 30 Polybag 40,000
7 Kembang sungsang (Gloriosa superba) 30 dia. Tajuk 20 Polybag 40,000
8 Lantana rambut ungu (Lantana sp) 20 3 s/d 4 btg/rpn Polybag 7,500
9 Pasiflora 60 dia. Tajuk 40 Polybag 20,000
10 Sirih Gading daun strip kuning (Scindapsus sp) 30 3 s/d 4 btg/rpn Polybag 10,000
11 Sthephanot bunga putih
(Sthepanothis floribunda) 30 dia. Tajuk 40 Polybag 30,000
12 Nona Makan Sirih 30 Polybag 15,000
13 Ubi rambat Kuning 30 Polybag 2,500
VI TANAMAN HIAS
1 Anjuang hijau (Dracaena sp) 60 dia. Tajuk 40 Polybag 10,000
2 Anjuang kribo (Dracaerna sp) 60 dia. Tajuk 40 Polybag 11,000
3 Anjuang kuning (Dracaerna sp) 60 dia. Tajuk 40 Polybag 12,500
NO JENIS BAHAN PERTAMANAN UKURAN
TINGGI DIAMETER UNIT HARGA BAHAN
(cm) (cm)
1 2 3 4 5 6
4 Anjuang merah (Cordelyne terminalis) 40 dia. Tajuk 20 Polybag 8,000
5 Anjuang merah (Cordelyne terminalis) 60 dia. Tajuk 40 Polybag 11,000
6 Anjuang merah (Cordelyne terminalis) 80 dia. Tajuk 50 Polybag 15,000
7 Anjuang suji (Dracaena sp) 60 dia. Tajuk 40 Polybag 13,500
8 Azalea (Azalea sp) 50 dia. Tajuk 40 Polybag 25,000
9 Bakung kecil (Hymenochalys sp) 20 dia. Tajuk 40 Polybag 5,500
10 Beringin bonsai (Ficus benjamina) 100 - 200 dia. Tajuk 100 Polybag 225,000
11 Beringin bonsai bentukan (Ficus benjamina) 100 - 200 dia. Tajuk 100 Polybag 375,000
12 Beringin bonsai putih (Ficus benjamina) 250 dia. Tajuk 100 Polybag 1,000,000
13 Bonsai serut 151 - 200 dia. Tajuk 100 Polybag 2,500,000
14 Nusa indah merah/putih (Nussaenda sp) 50 dia. Tajuk 40 Polybag 20,000
15 Rambusa 50 Polybag 30,000
16 Pakis kelabang kuning (Neprolephis sp) 40 5 s/d 7 btg/rpn Polybag 10,000
17 Pakis krol (Neprolephis sp) 40 5 s/d 7 btg/rpn Polybag 12,500
18 Pakis monyet (Alsophila glauca) 150 - 200 dia. Tajuk 40 Polybag 200,000
19 Pisang kipas (Ravanela madagaskariensis) 200 - 250 dia. Btg 10 Polybag 475,000
20 Puring bor (Codiaeum sp) 75 dia. Tajuk 30 Polybag 20,000
21 Puring buntut (Codiaeum sp) 75 dia. Tajuk 30 Polybag 20,000
22 Puring gelatik (Codiaeum sp) 75 dia. Tajuk 30 Polybag 20,000
23 Puring jet (Codiaeum sp) 40 dia. Tajuk 20 Polybag 14,500
24 Puring jet (Codiaeum sp) 75 dia. Tajuk 30 Polybag 30,000
25 Puring ketapang (Codiaeum sp) 50 dia. Tajuk 30 Polybag 20,000
26 Puring nuri (Codiaeum sp) 60 dia. Tajuk 30 Polybag 20,000
27 Puring Kuning 20 dia. Tajuk 30 Polybag 7,500
28 Siklok dia. Btg 5 Polybag 100,000
29 Sikas/Pakis haji halus (Cycas revoluta) 80 dia. Btg 7,5 Polybag 900,000
30 Sikas diameter tajuk daun (Cycas sp) 100 dia. Btg 10 Polybag 1,000,000
31 Sikas medan (Cycas sp) 100 dia. Btg 10 Polybag 1,350,000
32 Sikas/pakis haji kasar (Cycas rumpi) 50 - 100 dia. Btg 7,5 Polybag 125,000
33 Kamboja kuning (Bali) tinggi (Plumeria sp) 150 - 200 dia. Btg 3 Polybag 400,000
34 Kamboja orange tinggi (Plumeria sp) 150 - 200 dia. Btg 3 Polybag 300,000
35 Lidah Buaya Besar 10-25 2-3 btg/pot Polybag 40,000
36 Lidah Buaya Kecil 50 5-7 btg/pot Polybag 15,000
VII PALEM
1 Kelapa gading (Cocos capitata) 200 - 250 dia. Btg 20 Phn 450,000
2 Kelapa sawit (Elais guineensis) 200 - 250 dia. Btg 40 Phn 450,000
3 Kelapa sayur (Cocos nucifera) 200 - 250 dia. btg 30 Phn 175,000
4 Kurma (Phoenix daetilifera) 100 dia. btg 30 Phn 400,000
5 Kurma (Phoenix daetilifera) >200 dia. Btg 40 Phn 3,500,000
6 Lontar (Borassus flabefiter) 300 dia. Btg 25 Phn 400,000
7 Palm anggur (Lalania loglgessu) 100 dia. Btg 15 Phn 150,000
8 Palm alexander 150 dia. Btg 10 Phn 125,000
9 Palm botol 150 - 200 dia. btg 30 Phn 300,000
10 Palm camedoria 100 3 s/d 5 btg/rpn Phn 110,000
11 Palm camedoria 200 3 s/d 5 btg/rpn Phn 300,000
12 Palm ekor tupai 50-75 Phn 45,000
13 Palm ekor tupai 200 dia. Btg 15 Phn 225,000
14 Palm jepang (Ptychosperma macarthurii) 100 - 150 5 s/d 7 btg/rpn Rmp 110,000
15 Palm jepang (Ptychosperma macarthurii) 150 - 250 5 s/d 7 btg/rpn Rmp 250,000
16 Palm kol (Licuala grandis) 100 dia. Btg 10 Phn 65,000
18 Palm kuning (Chrysalidocarpus lutescens) 50 - 100 3 s/d 5 btg/rpn Phn 42,500
19 Palm kuning (Chrysalidocarpus lutescens) 100 - 150 5 s/d 7 btg/rpn Rmp 125,000
20 Palm korembusa 50 dia. Btg 5 Phn 40,000
NO JENIS BAHAN PERTAMANAN UKURAN
TINGGI DIAMETER UNIT HARGA BAHAN
(cm) (cm)
1 2 3 4 5 6
21 Palm korembusa 100 dia. Btg 7 Phn 60,000
22 Palm korembusa >200 dia. Btg 10 Phn 70,000
23 Palm merah (Cyrtotachis lakka) 150 - 200 3 s/d 5 btg/rpn Phn 110,000
24 Palm merah (Cyrtotachis lakka) 300 - 350 5 s/d 7 btg/rpn Rmp 325,000
25 Palm phoeniks (Phoenix sp) 75 - 100 dia. Btg 8 Phn 175,000
26 Palm phoeniks (Phoenix sp) 150 - 200 dia. Btg 10 Phn 375,000
26 Palm putri 50 Phn 45,000
27 Palm putri 100-150 dia. Btg 10 Phn 140,000
28 Palm putri 150 - 200 dia. Btg 10 Phn 300,000
29 Palm pigni (Phoenix canariensis) 100 - 150 dia. Btg 10 Phn 8,000,000
30 Palm raja (Oredoxa regia) 100 - 200 dia. Btg 20 Phn 150,000
31 Palm raja (Super oredoxa regia) 200 - 300 dia. Btg 25 Phn 425,000
32 Palm ratu 100 - 150 dia. Btg 10 Phn 80,000
33 Palm sadeng (Livistonia rotundifolta) 50 dia. Btg 5 Phn 62,500
34 Palm saderi (Caroutamiti) 150 dia. Btg 8 Phn 70,000
35 Palm seledri tunggal tinggi 150 dia. Btg 8 Phn 150,000
36 Palm seledri tunggal putih 200 dia. Btg 8 Phn 400,000
37 Palm udang 50 3 s/d 5 btg/rpn Phn 35,000
38 Palm waregu (Rhapis excelsa) 150 5 s/d 7 btg/rpn Rmp 50,000
39 Pinang sirih (Areca catechu) 200 dia. Btg 10 Phn 250,000
X BUNGA POTONG
1 Amarilis (Amarylidaceae) 1 Tangkai 17,875
2 Anggrek macan (Arrachnis sp) 1 Tangkai 275,000
3 Anyelir 1 Tangkai 13,750
4 Apple blossom 1 Tangkai 11,000
5 Aster (Asteraceae sp) 1 Tangkai 15,125
6 Anggrek Dendrobium 1 Tangkai 68,750
7 Gladiol 1 Tangkai 13,750
8 Golden shower 1 Tangkai 55,000
9 Krisan (Chrysanthemum llini) 1 Tangkai 16,500
10 Mawar 1 Tangkai 5,500
TERTANDA
PARYADI, S.Hut
Membuat 1m3 Beton Mutu f'c = 19,3 Mpa (K 225), slump (12 ± 2) cm, w/c = 0,58 (P.BB. 04)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 60,000.00 1.650 99,000.00
2 Tukang Batu OH 70,000.00 0.275 19,250.00
3 Kepala Tukang OH 75,000.00 0.028 2,100.00
4 Mandor OH 75,000.00 0.083 6,225.00
Jumlah 126,575.00
B BAHAN
1 Semen Portland Kg 2,047.41 371.000 759,589.41
2 Pasir Kg 104.32 698.000 72,813.36
3 Batu pecah 1-2 cm (Kerikil) Kg 538.78 1,047.000 564,104.13
4 Air Liter 0.00 0.000 0.00
Jumlah 1,396,506.90
C Jumlah A + B 1,523,081.90
D Harga Satuan 1,523,081.90
Acuan : SNI DT 91-0008-2007
Pekerjaan Tanah 84
No. URAIAN PEKERJAAN SATUAN KUANTITAS
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 48,400.00 1.200 58,080.00
2 Mandor OH 66,550.00 0.0450 2,994.75
Jumlah 61,074.75
B Jumlah A 61,074.75
C Harga Satuan 61,074.75
Acuan : SNI DT-91-0006-2007
Jumlah 0.00
C Jumlah A + B 10,557.25
D Harga Satuan 10,557.25
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
Pekerjaan Tanah 85
No. URAIAN PEKERJAAN SATUAN KUANTITAS
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 70,950.00 0.250 17,737.50
2 Mandor OH 98,230.00 0.0083 818.58
Jumlah 18,556.08
B Jumlah A 18,556.08
C Harga Satuan 18,556.08
Acuan : SNI DT-91-0006-2007
Pekerjaan Tanah 86
DAFTAR HARGA SATUAN BAHAN DAN UPAH
HARGA BELUM
TERMASUK
NO. TENAGA KERJA SATUAN KODE
KEUNTUNGAN
(OVERHEAD) (Rp)
A. UPAH
1 Mandor Lapangan Org/hari L.061 75,000.00
2 Mekanik Org/hari L.071 75,000.00
3 Kepala Tukang Org/hari L.073 75,000.00
4 Tukang Batu / Kayu / Gali / Besi / Cor / Semen / Cat / Listrik / Pancang Org/hari L.079 70,000.00
5 Operator terlatih Org/hari L.081 65,000.00
6 Operator semi terlatih Org/hari L.082 60,000.00
7 Sopir Org/hari L.091 65,000.00
8 Pekerja / Buruh Lapangan Tak terlatih Org/hari L.101 60,000.00
9 Pekerja / Buruh Lapangan terlatih Org/hari L.106 70,000.00
HARGA BELUM
JARAK ONGKOS
TERMASUK
NO. MATERIAL SATUAN KODE ANGKUT RATA- ANGKUT PER
KEUNTUNGAN
RATA (KM) UNIT (Rp)
(OVERHEAD) (Rp)
A. BAHAN PENGISI
1 Batu pecah 1/2 cm M³ - - 727,354.90
2 Pasir urug M³ - - 131,369.70
3 Pasir Ayak untuk beton M³ 146,043.98
4 Semen PC Zak - - 102,370.54
5 Semen PC Kg - - 2,047.41
6 Timbunan Pilihan (Tanah Datang) M³ 192,163.13
B. BAHAN KAYU
1 Ky klas III uk. 4/6 - 4 M ( tdk ketam) M³ - - 1,850,000.00
2 Papan mal klas III M³ - - 1,531,714.80
6 Kayu bulat dia 8 - 10 cm,4 m Btg 6,987.75
C. BAHAN PENGANTUNG
1 Paku campuran 1" - 5 " Kg - - 22,780.07
D. BAHAN BAKAR
1 Minyak Diesel / Solar Lt 7,267.26
MUHAMMAD KHALID, ST
Direktur
1 Mandor Lapangan
2 Mekanik
3 Kepala Tukang
4 Tukang Batu / Kayu / Gali / Besi / Cor / Semen / Cat / Listrik / Pancang
5 Operator terlatih
6 Operator semi terlatih
7 Sopir
8 Pekerja / Buruh Lapangan Tak terlatih
9 Pekerja / Buruh Lapangan terlatih
Harga Bahan
Keterangan
Wilayah II Wilayah III
491,708.01 540,878.81
336,000.48 369,600.53
237,094.36 260,803.80
461,806.93 507,987.62
499,903.14 549,893.45
318,851.04 350,736.14
396,098.12 435,707.93
271,963.23 299,159.55 Wilayah II :
343,378.04 377,715.84 Kecamatan Kuala Mandor B, Teluk Pakedai
471,393.62 518,532.98
574,602.68 632,062.95 Kecamatan Sungai Raya :
626,102.40 688,712.64
727,354.90 800,090.39
819,523.32 901,475.65
640,427.29 704,470.02
181,500.00 199,650.00
341,002.20 375,102.42
426,252.75 468,878.03
511,503.30 562,653.63 Wilayah III :
593,958.75 653,354.63 Kec. Batu Ampar dan Terentang, Termasuk :
131,369.70 144,506.67 Kecamatan Sungai Raya :
146,043.98 160,648.37 - Desa Pulau Limbung
192,163.13 211,379.44 - Desa Gunung Tamang
16,491.09 18,140.20 Kecamatan Sungai Kakap :
11,979.00 13,176.90 - Desa Tanjung Saleh
219,764.74 241,741.21 - Desa Sepuk Laut
102,370.54 112,607.59 Kecamatan Sungai Ambawang :
62,610.24 68,871.26 - Desa Simpang Kanan
21,941.54 24,135.69 - Desa Pasak
4,052.90 4,458.18 - Desa Pasak Piang
5,310.69 5,841.76 - Desa Puguk
6,288.98 6,917.87 - Desa Bengkarek
7,267.26 7,993.99 - Desa Teluk Bakung
7,686.53 8,455.18 Kecamatan Teluk Pakedai :
9,782.85 10,761.14 - Desa Kuala Karang
15,792.32 17,371.55 - Desa Sungai Nibung
357,074.03 392,781.43 Kecamatan Kubu :
310,882.20 341,970.42 - Desa Dabong
540,572.34 594,629.57
668,448.17 735,292.98 Catatan :
2,124,953.60 2,337,448.96
1,308,106.80 1,438,917.48 Wilayah I :
1,648,130.72 1,812,943.79 Kecamatan Sungai Raya, Sungai Kakap,
2,298,969.75 2,528,866.73 Rasau Jaya dan Sungai Ambawang
1,012,965.20 1,114,261.72
1,272,119.89 1,399,331.88 Wilayah II :
1,603,269.36 1,763,596.30 Kecamatan Kuala Mandor B, Teluk Pakedai
2,423,211.95 2,665,533.14 dan Kubu, termasuk :
3,600,787.58 3,960,866.33 Kecamatan Sungai Raya :
542,808.42 597,089.26 - Desa Sungai Bulan
602,546.69 662,801.36 - Desa Tebang Kacang
956,553.10 1,052,208.41 - Desa Sungai Asam
27,811.25 30,592.37 Kecamatan Sungai Ambawang :
29,348.55 32,283.41 - Desa Lingga
29,348.55 32,283.41 - Desa Pancaroba
9,782.85 10,761.14
27,671.49 30,438.64 Wilayah III :
29,628.06 32,590.87 Kec. Batu Ampar dan Terentang, Termasuk :
26,413.70 29,055.06 Kecamatan Sungai Raya :
137,239.41 150,963.35 - Desa Pulau Limbung
3,662,699.04 4,028,968.94 - Desa Gunung Tamang
12,436,797.45 13,680,477.20 Kecamatan Sungai Kakap :
7,267.26 7,993.99 - Desa Tanjung Saleh
7,267.26 7,993.99 - Desa Sepuk Laut
55,203.23 60,723.55 Kecamatan Sungai Ambawang :
73,231.62 80,554.78 - Desa Simpang Kanan
27,951.00 30,746.10 - Desa Pasak
31,864.14 35,050.55 - Desa Pasak Piang
46,817.93 51,499.72 - Desa Puguk
87,207.12 95,927.83 - Desa Bengkarek
65,405.34 71,945.87 - Desa Teluk Bakung
31,305.12 34,435.63 Kecamatan Teluk Pakedai :
43,324.05 47,656.46 - Desa Kuala Karang
81,756.68 89,932.34 - Desa Sungai Nibung
25,575.17 28,132.68 Kecamatan Kubu :
65,405.34 71,945.87 - Desa Dabong
49,054.01 53,959.41
59,954.90 65,950.38 Catatan :
98,340.94 108,175.03
98,108.01 107,918.81 Wilayah I :
19,565.70 21,522.27 Kecamatan Sungai Raya, Sungai Kakap,
5,590.20 6,149.22 Rasau Jaya dan Sungai Ambawang
7,686.53 8,455.18
122,635.01 134,898.51 Wilayah II :
19,845.21 21,829.73 Kecamatan Kuala Mandor B, Teluk Pakedai
27,322.10 30,054.31 dan Kubu, termasuk :
36,755.57 40,431.12 Kecamatan Sungai Raya :
63,309.02 69,639.92 - Desa Sungai Bulan
83,853.00 92,238.30 - Desa Tebang Kacang
118,512.24 130,363.46 - Desa Sungai Asam
170,501.10 187,551.21 Kecamatan Sungai Ambawang :
280,907.55 308,998.31 - Desa Lingga
448,194.29 493,013.71 - Desa Pancaroba
621,700.12 683,870.13
17,888.64 19,677.50 Wilayah III :
24,527.00 26,979.70 Kec. Batu Ampar dan Terentang, termasuk :
32,702.67 35,972.94 Kecamatan Sungai Raya :
41,507.24 45,657.96 - Desa Pulau Limbung
53,805.68 59,186.24 - Desa Gunung Tamang
72,952.11 80,247.32 Kecamatan Sungai Kakap :
93,216.59 102,538.24 - Desa Tanjung Saleh
148,140.30 162,954.33 - Desa Sepuk Laut
233,390.85 256,729.94 Kecamatan Sungai Ambawang :
294,883.05 324,371.36 - Desa Simpang Kanan
152,332.95 167,566.25 - Desa Pasak
320,737.73 352,811.50 - Desa Pasak Piang
468,878.03 515,765.83 - Desa Puguk
762,084.02 838,292.42 - Desa Bengkarek
1,006,236.00 1,106,859.60 - Desa Teluk Bakung
40,878.34 44,966.17 Kecamatan Teluk Pakedai :
49,054.01 53,959.41 - Desa Kuala Karang
4,891.43 5,380.57 - Desa Sungai Nibung
13,898,634.75 15,288,498.23 Kecamatan Kubu :
16,351,335.00 17,986,468.50 - Desa Dabong
9,810,801.00 10,791,881.10
12,263,501.25 13,489,851.38 Catatan :
5,722,967.25 6,295,263.98
7,358,100.75 8,093,910.83 Wilayah I :
19,621,602.00 21,583,762.20 Kecamatan Sungai Raya, Sungai Kakap,
17,986,468.50 19,785,115.35 Rasau Jaya dan Sungai Ambawang
11,445,934.50 12,590,527.95
7,358,100.75 8,093,910.83 Wilayah II :
6,540,534.00 7,194,587.40 Kecamatan Kuala Mandor B, Teluk Pakedai
1,531,714.80 1,684,886.28 dan Kubu, termasuk :
981,145.98 1,079,260.58 Kecamatan Sungai Raya :
27,671.49 30,438.64 - Desa Sungai Bulan
22,780.07 25,058.07 - Desa Tebang Kacang
27,671.49 30,438.64 - Desa Sungai Asam
40,878.34 44,966.17 Kecamatan Sungai Ambawang :
40,176.24 44,193.86 - Desa Lingga
26,134.19 28,747.60 - Desa Pancaroba
32,702.67 35,972.94
2,125,673.55 2,338,240.91 Wilayah III :
2,370,244.80 2,607,269.28 Kec. Batu Ampar dan Terentang, termasuk :
209,213.24 230,134.56 Kecamatan Sungai Raya :
327,026.70 359,729.37 - Desa Pulau Limbung
40,878.34 44,966.17 - Desa Gunung Tamang
981,080.10 1,079,188.11 Kecamatan Sungai Kakap :
40,878.34 44,966.17 - Desa Tanjung Saleh
163,513.35 179,864.69 - Desa Sepuk Laut
187,970.48 206,767.52 Kecamatan Sungai Ambawang :
24,457.13 26,902.84 - Desa Simpang Kanan
35,917.04 39,508.74 - Desa Pasak
35,917.04 39,508.74 - Desa Pasak Piang
69,178.73 76,096.60 - Desa Puguk
147,162.02 161,878.22 - Desa Bengkarek
245,270.03 269,797.03 - Desa Teluk Bakung
286,148.36 314,763.20 Kecamatan Teluk Pakedai :
286,148.36 314,763.20 - Desa Kuala Karang
89,932.34 98,925.58 - Desa Sungai Nibung
122,635.01 134,898.51 Kecamatan Kubu :
32,702.67 35,972.94 - Desa Dabong
40,878.34 44,966.17
4,052.90 4,458.18 Catatan :
4,052.90 4,458.18
60,374.16 66,411.58 Wilayah I :
98,108.01 107,918.81 Kecamatan Sungai Raya, Sungai Kakap,
63,728.28 70,101.11 Rasau Jaya dan Sungai Ambawang
102,999.44 113,299.38
148,822.44 163,704.68 Wilayah II :
195,657.00 215,222.70 Kecamatan Kuala Mandor B, Teluk Pakedai
165,190.41 181,709.45 dan Kubu, termasuk :
98,108.01 107,918.81 Kecamatan Sungai Raya :
114,459.35 125,905.28 - Desa Sungai Bulan
98,108.01 107,918.81 - Desa Tebang Kacang
81,756.68 89,932.34 - Desa Sungai Asam
26,134.19 28,747.60 Kecamatan Sungai Ambawang :
10,900.89 11,990.98 - Desa Lingga
13,695.99 15,065.59 - Desa Pancaroba
73,231.62 80,554.78
69,458.24 76,404.06 Wilayah III :
58,557.35 64,413.08 Kec. Batu Ampar dan Terentang, termauk :
38,432.63 42,275.89 Kecamatan Sungai Raya :
171,619.14 188,781.05 - Desa Pulau Limbung
138,986.35 152,884.98 - Desa Gunung Tamang
122,774.10 135,051.51 Kecamatan Sungai Kakap :
236,884.73 260,573.20 - Desa Tanjung Saleh
196,216.02 215,837.62 - Desa Sepuk Laut
212,567.36 233,824.09 Kecamatan Sungai Ambawang :
376,080.71 413,688.78 - Desa Simpang Kanan
784,864.08 863,350.49 - Desa Pasak
245,270.03 269,797.03 - Desa Pasak Piang
327,026.70 359,729.37 - Desa Puguk
572,296.73 629,526.40 - Desa Teluk Bakung
490,540.05 539,594.06 Kecamatan Teluk Pakedai :
564,051.18 620,456.30 - Desa Kuala Karang
572,296.73 629,526.40 - Desa Sungai Nibung
57,229.67 62,952.64 Kecamatan Kubu :
65,405.34 71,945.87 - Desa Dabong
81,756.68 89,932.34
65,405.34 71,945.87
81,756.68 89,932.34 Catatan :
98,108.01 107,918.81
106,283.68 116,912.05 Wilayah I :
73,581.01 80,939.11 Kecamatan Sungai Raya, Sungai Kakap,
294,324.03 323,756.43 Rasau Jaya dan Sungai Ambawang
89,932.34 98,925.58
12,158.69 13,374.55 Wilayah II :
24,527.00 26,979.70 Kecamatan Kuala Mandor B, Teluk Pakedai
138,986.35 152,884.98 dan Kubu, termasuk :
81,756.68 89,932.34 Kecamatan Sungai Raya :
220,743.02 242,817.32 - Desa Sungai Bulan
98,108.01 107,918.81 - Desa Tebang Kacang
9,810.80 10,791.88 - Desa Sungai Asam
2,375.84 2,613.42 Kecamatan Sungai Ambawang :
1,677.06 1,844.77 - Desa Lingga
2,795.10 3,074.61 - Desa Pancaroba
4,192.65 4,611.92
130,810.68 143,891.75 Wilayah III :
327,026.70 359,729.37 Kec. Batu Ampar dan Terentang, termauk :
24,527.00 26,979.70 Kecamatan Sungai Raya :
13,067.09 14,373.80 - Desa Pulau Limbung
65,405.34 71,945.87 - Desa Gunung Tamang
16,351.34 17,986.47 Kecamatan Sungai Kakap :
40,878.34 44,966.17 - Desa Tanjung Saleh
327,026.70 359,729.37 - Desa Sepuk Laut
4,891.43 5,380.57 Kecamatan Sungai Ambawang :
71,874.00 79,061.40 - Desa Simpang Kanan
- Desa Pasak
- Desa Pasak Piang
- Desa Puguk
- Desa Teluk Bakung
Kecamatan Teluk Pakedai :
- Desa Kuala Karang
- Desa Sungai Nibung
Kecamatan Kubu :
- Desa Dabong
75,000.00
75,000.00
75,000.00
70,000.00
65,000.00
60,000.00
65,000.00
60,000.00
70,000.00
44,700.73 49,170.80
30,545.50 33,600.05
21,554.03 23,709.44
41,982.45 46,180.69
45,445.74 49,990.31
28,986.46 31,885.10
39,609.81
27,196.32
34,337.80
42,853.97 47,139.36
57,460.27
56,918.40 62,610.24
66,123.17 72,735.49
74,502.12 81,952.33
58,220.66 64,042.73
16,500.00 18,150.00
31,000.20 34,100.22
42,625.28
51,150.33
59,395.88
13,136.97
14,604.40
19,216.31
1,649.11
1,197.90
21,976.47
10,237.05
6,261.02
2,194.15
405.29
531.07
628.90
726.73
768.65
978.29
1,579.23
35,707.40
31,088.22
54,057.23
66,844.82
212,495.36
130,810.68
164,813.07
229,896.98
101,296.52
127,211.99
160,326.94
242,321.19
360,078.76
54,280.84
60,254.67
95,655.31
2,781.12
2,934.86
2,934.86
978.29
2,767.15
2,962.81
2,641.37
13,723.94
366,269.90
1,243,679.75
726.73
726.73
5,520.32
7,323.16
2,795.10
3,186.41
4,681.79
8,720.71
6,540.53
3,130.51
4,332.41
8,175.67
2,557.52
6,540.53
4,905.40
5,995.49
9,834.09
9,810.80
1,956.57
559.02
768.65
12,263.50
1,984.52
2,732.21
3,675.56
6,330.90
8,385.30
11,851.22
17,050.11
28,090.76
44,819.43
62,170.01
1,788.86
2,452.70
3,270.27
4,150.72
5,380.57
7,295.21
9,321.66
14,814.03
23,339.09
29,488.31
15,233.30
32,073.77
46,887.80
76,208.40
100,623.60
4,087.83
4,905.40
489.14
1,389,863.48
1,635,133.50
981,080.10
1,226,350.13
572,296.73
735,810.08
1,962,160.20
1,798,646.85
1,144,593.45
735,810.08
654,053.40
153,171.48
98,114.60
2,767.15
2,278.01
2,767.15
4,087.83
4,017.62
2,613.42
3,270.27
212,567.36
237,024.48
20,921.32
32,702.67
4,087.83
98,108.01
4,087.83
16,351.34
18,797.05
2,445.71
3,591.70
3,591.70
6,917.87
14,716.20
24,527.00
28,614.84
28,614.84
8,993.23
12,263.50
3,270.27
4,087.83
405.29
405.29
6,037.42
9,810.80
6,372.83
10,299.94
14,882.24
19,565.70
16,519.04
9,810.80
11,445.93
9,810.80
8,175.67
2,613.42
1,090.09
1,369.60
7,323.16
6,945.82
5,855.73
3,843.26
17,161.91
13,898.63
12,277.41
23,688.47
19,621.60
21,256.74
37,608.07
78,486.41
24,527.00
32,702.67
57,229.67
49,054.01
56,405.12
57,229.67
5,722.97
6,540.53
8,175.67
6,540.53
8,175.67
9,810.80
10,628.37
7,358.10
29,432.40
8,993.23
1,215.87
2,452.70
13,898.63
8,175.67
22,074.30
9,810.80
981.08
237.58
167.71
279.51
419.27
13,081.07
32,702.67
2,452.70
1,306.71
6,540.53
1,635.13
4,087.83
32,702.67
489.14
7,187.40
-
-
-
-
-
-
-
-
-
-
RENCANA ANGGARAN BIAYA
HARGA JUMLAH
VOLUME CODE
NO URAIAN PEKERJAAN SATUAN HARGA
JUMLAH SAT ANALISA ( Rp ) ( Rp )
1 2 3 4 5 6
I PEKERJAAN PENDAHULUAN
1 Pembersihan Lokasi 216.00 M2 P. Ps. 03 10,750.00 2,322,000.00
SUB JUMLAH 2,322,000.00
II PEKERJAAN RABAT BETON
1 Bekisting 17.80 M2 P. BB. 12 276,239.88 4,917,069.94
2 Pasir Urug 34.70 M3 P. T. 13 176,393.64 6,120,506.52
3 Plastik 68.25 M2 10,000.00 682,500.00
3 Cor Beton 34.70 M3 P. BB. 04 1,523,081.90 52,847,895.63
SUB JUMLAH 64,567,972.09
III PEKERJAAN TIMBUNAN TANAH DATANG
1 Timbunan Tanah t 50cm 93.00 M3 P. T. 11 338,325.25 31,464,248.24
2 Pekerjaan Pemadatan Timbunan Tanah 93.00 P. T. 12 33,750.00 3,138,750.00
SUB JUMLAH 31,464,248.24
IV PEKERJAAN PLESTERAN
1 Plesteran Dinding Pagar 86.70 M2 P. Pls. 03 73,003.49 6,329,402.71
Dibuat Oleh :
Konsultan Perencana
PT. QUADRAN KONSULINDO
MUHAMMAD KHALID, ST
Direktur
REKAPITULASI RENCANA ANGGARAN BIAYA
NO. JUMLAH
URAIAN PEKERJAAN
(Rp.)
1 2 3
JUMLAH 115,454,839.47
PPN 10 % 11,545,483.95
DIBULATKAN 127,000,000.00
Terbilang : " TUJUH PULUH EMPAT JUTA TUJUH RATUS SEMBILAN PULUH ENAM RIBU "
Dibuat Oleh :
Mengetahui / Menyetujui Konsultan Perencana
KABID URAIS KANTOR KEMENAG KUBU RAYA PT. QUADRAN KONSULINDO
Rekapitulasi 110
HARGA SATUAN
NO KODE ANALISA URAIAN PEKERJAAN HAL
(Rp)
1 2 3 4 5
8 P. Pls. 08 Memasang 1m2 Plesteran 1PC : 3PP, tebal 15 mm (P.Pls. 08) 50,167.12
G. PEKERJAAN KAYU
1m3 Pek. Membuat Kayu Sandaran Jembatan, Balok Pemikul, Balok Air Pada Barau, Topangan
1 P. K. 01 12,393,645.00
Angin dan Balok Tarahan Kayu-kayu Penahan Menggunakan Kayu Belian Uk. 9/9 (P.K. 01)
1m3 Pek. Membuat Kayu Sandaran Jembatan, Balok Pemikul, Balok Air Pada Barau, Topangan
2 P. K. 02 10,802,374.00
Angin dan Balok Tarahan Kayu-kayu Penahan Menggunakan Kayu Belian Uk. 10/10 (P.K. 02)
1m3 Pek. Membuat Kayu Sandaran Jembatan, Balok Pemikul, Balok Air Pada Barau,
3 P. K. 03 Topangan Angin dan Balok Tarahan Kayu-kayu Penahan Menggunakan Kayu Belian 11,036,025.00
Uk. 12/12 - 15/15 (P.K. 03)
1m3 Pek. Membuat Kayu Sandaran Jembatan, Balok Pemikul, Balok Air Pada Barau,
4 P. K. 04 Topangan Angin dan Balok Tarahan Kayu-kayu Penahan Menggunakan Kayu Belian 10,215,887.00
Uk. 18/18 - 20/20 (P.K. 04)
5 P. K. 05 1m3 Pekerjaan Rangka Badan Kayu Belian Uk. 7/7 (P.K. 05) 16,284,741.00
6 P. K. 06 1m3 Pekerjaan Rangka Badan Kayu Belian Uk. 8/8 (P.K. 06) 15,260,193.80
7 P. K. 07 1m3 Pekerjaan Rangka Badan Kayu Kelas I Uk. 7/7 (P.K. 07) 8,787,427.00
8 P. K. 08 1m3 Pekerjaan Rangka Badan Kayu Kelas I Uk. 8/8 (P.K. 08) 7,842,530.40
9 P. K. 09 1m1 Melancip Tiang / Batang (P.K. 09) 27,747.50
10 P. K. 10 Membuat Puting dan Lobang / Pasang (P.K. 10) 40,293.00
11 P. K. 11 1 m1 Memancang Tiang ke Dalam Tanah (P.K. 11) 57,322.30
12 P. K. 12 Membuat dan Memasang 1m3 Kusen Pintu dan Kusen Jendela, Kayu Kelas I (P.K. 12) 7,654,010.90
13 P. K. 12.a Membuat dan Memasang 1m3 Kusen Pintu dan Kusen Jendela Kayu Belian (P.K. 12.a) 14,900,303.50
14 P. K. 13 Membuat dan Memasang 1m3 Kusen Pintu dan Kusen Jendela, Kayu Kelas II (P.K. 13) 5,229,604.00
15 P. K. 14 Membuat dan Memasang 1m2 Daun Pintu Panel, Kayu Kelas I (P.K. 14) 565,892.50
16 P. K. 15 Membuat dan Memasang 1m2 Daun Pintu Panel, Kayu Kelas II (P.K. 15) 516,638.90
17 P. K. 16 Membuat dan Memasang 1m2 Pintu dan Jendela Jalusi Kayu Kelas I (P.K. 16) 772,775.23
18 P. K. 17 Membuat dan Memasang 1m2 Pintu dan Jendela Jalusi Kayu Kelas II (P.K. 17) 415,340.34
Membuat 1m2 Daun Pintu Kayu Lapis (Plywood) Rangkap, Rangka Tertutup Kayu Kelas II
19 P.K. 18 455,680.75
(Lebar sampai 90 cm) (P.K. 18)
20 P. K. 19 Membuat 1m2 Pintu Plywood Rangkap, Rangka Expose Kayu Kelas I (P.K. 19) 516,321.00
21 P. K. 20 Membuat 1m2 Pintu Plywood Rangkap, Rangka Expose Kayu Kelas II (P.K. 20) 484,798.70
22 P. K. 21 Membuat 1m2 Jalusi Kusen, Kayu Kelas I (P.K. 21) 645,917.25
23 P. K. 22 Membuat 1m2 Jalusi Kusen, Kayu Kelas II (P.K. 22) 572,036.85
1m2 Pemasangan Ventilasi Kaca
24 P. K. 23 174,041.20
Setiap luas 1 m2 bidang daun ventilasi, luas kacanya adalah 0.60 m2 (P.K. 23)
25 P. K. 24 Memasang 1m3 Konstruksi Kuda-kuda Konvensional, Kayu Kelas I Bentang 6 m (P.K. 24) 6,800,442.00
26 P. K. 25 Memasang 1m3 Konstruksi Kuda-kuda Konvensional, Kayu Kelas II Bentang 6 m (P.K. 25) 5,298,117.80
27 P. K. 26 Memasang 1m3 Konstruksi Kuda-kuda Expose, Kayu Kelas I (P.K. 26) 7,947,073.75
28 P. K. 27 Memasang 1m3 Konstruksi Gordeng, Kayu Kelas II (P.K. 27) 4,722,123.00
29 P. K. 28 Memasang 1m2 Rangka Atap Genteng Keramik, Kayu Kelas II (P.K. 28) 78,135.75
30 P. K. 29 Memasang 1m2 Rangka Atap Genteng Beton, Kayu Kelas II (P.K. 29) 98,348.25
31 P. K. 30 Memasang 1m3 Konstruksi Gordeng, Kayu Kelas I (P.K. 30) 6,340,994.00
32 P. K. 30.a Memasang 1m3 Konstruksi Gordeng, Kayu Belian (P.K. 30.a) 13,857,756.00
33 P. K. 31 Memasang 1m2 Rangka Atap Sirap, Kayu Kelas II (P.K. 31) 632,932.30
34 P. K. 32 1m2 Pemasangan Rangka Atap Seng (P.K. 32) 53,212.18
35 P. K. 33 1m2 Pasang Kasau + Reng Atap Genteng Metal Kayu Kelas II (P.K. 33) 60,462.14
36 P. K. 34 Memasang 1m2 Rangka Langit-langit (50 x 100) cm, Kayu Kelas II atau III (P.K. 34) 65,587.50
37 P. K. 35 Memasang 1m2 Rangka Langit-langit (60 x 60) cm, Kayu Kelas II atau III (P.K. 35) 97,956.62
38 P. K. 36 1m2 Pasang Rangka Langit-langit (30 x 60)cm Kayu Kelas II (P.K. 36) 110,849.28
39 P. K. 37 1m2 Pasang Rangka Langit-langit (30 x 30)cm Kayu Kelas II (P.K. 37) 141,168.45
40 P. K. 38 Memasang 1m1 Lisplank Ukuran (3 x 20) cm, Kayu Kelas I (P.K. 38) 102,368.75
41 P. K. 39 Memasang 1m1 Lisplank Ukuran (3 x 20) cm, Kayu Kelas II (P.K. 39) 89,070.28
42 P. K. 40 1m1 Pasang Lisplank Ukuran 2 x (3 x 20cm) Kayu Kelas I (P.K. 40) 139,950.25
43 P. K. 41 1m1 Pasang Lisplank Ukuran 2 x (2 x 20cm) Kayu Belian (P.K. 41) 165,766.66
44 P. K. 42 1m1 Pasang Lisplank Ukuran 2 x (2 x 20cm) Kayu Kelas I (P.K. 42) 64,946.02
45 P. K. 43 1m1 Pasang Lisplank Ukuran 2 x (2 x 20cm) Kayu Kelas II (P.K. 43) 71,851.21
46 P. K. 44 1m2 Pasang Rangka Dinding Pemisah Kayu Kelas I (P.K. 44) 178,895.20
47 P. K. 45 Memasang 1m2 Rangka Dinding Pemisah (60x120) cm Kayu Kelas II (P.K. 45) 117,182.12
48 P. K. 46 Memasang 1m2 Dinding Pemisah Plywood Rangkap, Rangka Kayu Kelas II (P.K. 46) 263,506.38
50 P. K. 47 Memasang 1m2 Dinding Lambriziring dari Papan Kayu Kelas I (P.K. 47) 216,843.00
49 P. K. 47.a Memasang 1m2 Dinding Lambriziring dari Papan Kayu Belian (P.K. 47.a) 283,274.09
51 P. K. 48 Memasang 1m2 Dinding Lambriziring dari Plywood ukuran (120 x 240) cm (P.K. 48) 51,127.45
52 P. K. 49 1m1 Pasang List Plafond, Kayu Profil (P.K. 49) 16,423.14
53 P. K. 50 1m2 Pemasangan Lantai Papan Kayu Belian (P.K. 50) 564,416.38
54 P. K. 51 1m2 Pemasangan Lantai Papan Kayu Kelas I (P.K. 51) 320,241.25
H. PEKERJAAN PENUTUP ATAP
1 P. PA. 01 1m2 Pasang Atap Genteng Metal Type PRIMA 0.35 (P.PA. 01) 148,761.25
2 P. PA. 02 1m2 Pasang Atap Genteng Metal Type ROYAL 0.35 (P.PA. 02) 139,709.35
3 P. PA. 03 1m2 Pasang Atap Genteng Metal Kualitas A 0.35 (P.PA. 03) 207,628.66
4 P. PA. 04 1m2 Pasang Atap Genteng Metal Stone Type CLASSIC 0.35 (P.PA. 04) 164,627.65
5 P. PA. 05 1m2 Pasang Atap Genteng Metal Stone Type PRIMA 0.35 (P.PA. 05) 184,181.25
6 P. PA. 06 1m2 Pasang Atap Sirap Belian (P.PA. 06) 359,535.55
7 P. PA. 07 1m1 Pekerjaan Bumbungan dengan Seng Datar Color 0.35 / 10 m1 (P.PA. 07) 96,932.58
8 P. PA. 08 1m1 Pasang Nok / Bumbungan Genteng Metal 1/2 Lingkaran 0.35 (P.PA. 08) 202,833.40
9 P. PA. 09 1m1 Pasang Nok / Bumbungan Genteng Metal Kotak 0.35 (P.PA. 09) 109,443.40
10 P. PA. 10 1m1 Pasang Nok / Bumbungan Genteng Metal Stone Kotak 0.35 (P.PA. 10) 125,283.40
11 P. PA. 11 1m1 Pasang Bumbungan Atap Sirap (P.PA. 11) 90,345.53
Rekapitulasi 111
HARGA SATUAN
NO KODE ANALISA URAIAN PEKERJAAN HAL
(Rp)
1 2 3 4 5
12 P. PA. 12 1m2 Pasang Atap Seng Gelombang BJLS 30 (P.PA. 12) 93,281.44
13 P. PA. 13 1m2 Pasang Atap Metal Supersheet 0.35 (polos) (P.PA. 13) 177,113.20
14 P. PA. 14 1m2 Pasang Zincalume Gelombang Persegi 0.30 (Polos) (P.PA. 14) 159,725.20
15 P. PA. 15 1m2 Pasang Zincalume Gelombang Persegi 0.30 (Colour) (P.PA. 15) 174,162.70
16 P. PA. 16 1m2 Pasang Zincalume Gelombang Persegi 0.35 (Polos) (P.PA. 16) 174,162.70
17 P. PA. 17 1m2 Pasang Zincalume Gelombang Persegi 0.35 (Colour) (P.PA. 17) 188,600.20
18 P. PA. 18 1m1 Pekerjaan Bubungan Atap Seng BJLS 30 / 10m1 (P.PA. 18) 66,218.90
19 P. PA. 19 1m2 Pasang Aluminium Foil / Sealation (P.PA. 19) 68,900.15
I. PEKERJAAN PLAFOND
1 P. Pf. 01 Memasang 1 m2 langit-langit tripleks ukuran (120 x 240) cm, tebal 3 mm (P.Pf. 01) 35,441.85
2 P. Pf. 02 Memasang 1 m2 langit-langit tripleks ukuran (120 x 240) cm, tebal 6 mm (P.Pf. 02) 62,666.85
3 P. Pf. 03 Memasang 1 m2 langit-langit gypsum board ukuran (120 x 240 x 9) mm, tebal 9 mm (P.Pf. 03) 40,214.90
4 P. Pf. 04 Memasang 1 m' list langit-langit kayu profil (P.Pf. 04) 11,614.90
5 P. Pf. 05 1m2 Langit-langit GRC (P.Pf. 05) 49,957.52
6 P. Pf. 06 1m2 Pekerjaan Plafond Renglat Kayu Kelas I (P.Pf. 06) 155,393.06
J. PEKERJAAN SANITASI
1 P. Snt. 01 Pemasangan 1 Buah Kloset Duduk / Monoblok (P.Snt. 01) 2,044,284.55
2 P. Snt. 02 Pemasangan Kloset Jongkok INA (P.Snt. 02) 532,058.01
3 P. Snt. 03 Memasang 1m1 Pipa Galvanis Ø 1/2" (P.Snt. 03) 41,940.07
4 P. Snt. 04 Memasang 1m1 Pipa Galvanis Ø 3/4" (P. Snt. 04) 48,845.32
5 P. Snt. 05 Memasang 1m1 Pipa Galvanis Ø 1" (P.Snt. 05) 59,927.82
6 P. Snt. 06 Memasang 1m1 Pipa Galvanis Ø 11/2" (P.Snt. 06) 98,463.05
7 P. Snt. 07 Memasang 1m1 Pipa Galvanis Ø 3" (P.Snt. 07) 176,381.55
8 P. Snt. 08 Memasang 1m1 Pipa Galvanis Ø 4" (P.Snt. 08) 220,728.92
9 P. Snt. 09 Memasang 1m1 Pipa PVC Tipe AW Ø 1/2" (P.Snt. 09) 12,796.74
10 P. Snt. 10 Memasang 1m1 Pipa PVC Tipe AW Ø 3/4" (P.Snt. 10) 20,994.65
11 P. Snt. 11 Memasang 1m1 Pipa PVC Tipe AW Ø 1" (P.Snt. 11) 21,662.74
12 P. Snt. 12 Memasang 1m1 Pipa PVC Tipe AW Ø 2" (P.Snt. 12) 40,431.34
13 P. Snt. 13 Memasang 1m1 Pipa PVC Tipe AW Ø 3" (P.Snt. 13) 58,654.81
14 P. Snt. 14 Memasang 1m1 Pipa PVC Tipe AW Ø 4" (P.Snt. 14) 112,778.43
15 P. Snt. 15 Memasang 1 Buah Kran Air Ø 3/4" atau Ø 1/2" (P.Snt. 15) 64,605.00
K. PEKERJAAN BESI DAN ALUMINIUM
1 P. BA. 01 Memasang 1 kg besi profil (P.BA 01) 42,804.69
2 P. BA. 02 Memasang 1 Kg rangka kuda-kuda baja IWF (P. BA 02) 42,804.69
Rekapitulasi 112
HARGA SATUAN
NO KODE ANALISA URAIAN PEKERJAAN HAL
(Rp)
1 2 3 4 5
3 P. BA. 03 Mengerjakan 100 kg pekerjaan perakitan (P. BA 03) 68,209.30
4 P. BA. 04 Mengerjakan 10 cm pengelasan dengan las listrik (P. BA 04) 60,355.20
5 P. BA. 05 Memasang 1m kusen pintu alluminium (P. BA 05) 104,768.62
6 P. BA. 06 Memasang 1m' talang 1/2 lingkaran D-15 cm, seng plat bjls 30 lebar 45 cm (P. BA 06) 57,847.90
7 P. BA. 07 1m2 Pasang Kawat Harmonika (P.BA. 07) 53,652.86
8 P. BA. 08 1m2 Pasang Kawat Kassa (P.BA. 08) 38,527.86
9 P. BA. 09 1m2 Pasang Jendela Nako (P.BA. 09) 259,545.55
10 P. BA. 10 1m2 Pasang Talang Datar Seng BJLS 30 / Talang Sembunyi (P.BA. 10) 123,926.62
11 P. BA. 11 1m2 Pasang Talang Miring Seng BJLS 30 / Jurai Dalam (P.BA. 11) 173,813.79
12 P. BA. 12 10m1 Talang Cucuran Atap 1/2 Lingkaran Ø 15cm BJLS 30 (P.BA. 12) 80,940.75
13 P. BA. 13 10m1 Pemasangan Pipa Pembuangan dari Talang Atap Ø 8cm BJLS 30 (P.BA. 13) 54,680.18
L. PEKERJAAN KUNCI DAN KACA
1 P. KK. 01 1 Buah Pemasangan Kunci Tanam Antik (P.KK. 01) 222,416.65
2 P. KK. 02 1 Buah Pemasangan Kunci Tanam Biasa (P.KK. 02) 99,819.00
3 P. KK. 03 1 Buah Pemasangan Kunci Silinder (P.KK. 03) 138,091.39
4 P. KK. 04 1 Buah Pemasangan Engsel Pintu (P.KK. 04) 25,681.75
5 P. KK. 04.a 1 Buah Pemasangan Engsel Jendela (P.KK. 04.a) 23,698.75
6 P. KK. 05 1 Buah Pemasangan Kait Angin (P.KK. 05) 20,722.75
7 P. KK. 06 1 Buah Pemasangan Door Closer (P.KK. 06) 159,913.88
8 P. KK. 07 1 Buah Pemasangan Slot Pintu (P.KK. 07) 28,292.00
9 P. KK. 07.a 1 Buah Pemasangan Slot Jendela (P.KK. 07.a) 26,307.00
10 P. KK. 08 1 Buah Pemasangan Door Stoper (P.KK. 08) 29,232.78
11 P. KK. 09 1 m2 Pemasangan Kaca Tebal 5mm (P.KK. 09) 368,377.95
12 P. KK. 10 1 m2 Pemasangan Kaca Tebal 12mm (P.KK. 10) 488,304.44
13 P. KK. 11 1 m2 Pemasangan Kaca Cermin, Tebal 3mm (P.KK. 11) 183,274.16
14 P. KK. 12 1 m2 Pemasangan Kaca Patri (P.KK. 12) 1,160,349.16
M. PEKERJAAN PENUTUP LANTAI DAN DINDING
1 P. LD. 01 Memasang 1m2 Lantai Keramik ukuran (20 x 20) cm (P.LD. 01) 201,543.68
2 P. LD. 02 Memasang 1m2 Lantai Keramik ukuran (30 x 30) cm (P.LD. 02) 204,170.31
P. LD. 02.a Memasang 1m2 Lantai Keramik ukuran (60 x 60) cm (P.LD. 02.a) 496,008.65
3 P. LD. 03 1m2 Pasang Lantai Keramik 40 x 40cm Polos (P.LD. 03) 204,364.00
4 P. LD. 04 1m2 Pasang Lantai Keramik 40 x 40cm Anti Gores (P.LD. 04) 182,265.29
5 P. LD. 05 Memasang 1 m2 lantai marmer ukuran (100 x 100) cm (P.LD. 05) 558,409.45
6 P. LD. 06 Memasang 1 m2 dinding keramik ukuran (20 x 20) cm (P.LD. 06) 155,077.04
7 P. LD. 07 1m2 Pasang Dinding Keramik 20 x 25cm (P.LD. 07) 204,582.74
8 P. LD. 07.a 1m2 Pasang Dinding Keramik 30 x 30cm (P.LD. 07.a) 126,520.91
9 P. LD. 07.b 1m2 Pasang Dinding Keramik 40 x 40cm (P.LD. 07.b) 157,290.91
10 P. LD. 08 Memasang 1 m2 Floor Hardener (P.LD. 08) 55,515.90
11 P. LD. 09 1m2 Pemasangan Paving Block (P.LD. 09) 137,515.00
12 P. LD. 10 1m2 Pemasangan Paving Stone (P.LD. 10) 206,910.00
N. PEKERJAAN PENGECATAN
1 P. Ct. 01 1m2 Mengikis / Mengerok Permukaan Cat Tembok Lama (P.Ct. 01) 19,086.38
2 P. Ct. 02 1m2 Mengerok Karat Cat Lama Permukaan Baja dengan Cara Manual (P.Ct. 02) 8,443.88
3 P. Ct. 03 1m2 Pengecatan Bidang Kayu Lama (P.Ct. 03) 25,554.10
4 P. Ct. 04 1m2 Pengecatan Bidang Kayu Baru (1Lapis Plamir, 1Lapis Cat Dasar, 2Lapis Cat Penutup) (P.Ct. 04) 46,969.14
5 P. Ct. 05 1m2 Pengecatan Bidang Kayu Baru (1Lapis Plamir, 1Lapis Cat Dasar, 3Lapis Cat Penutup) (P.Ct. 05) 43,563.58
6 P. Ct. 06 1m2 Pelaburan Bidang Kayu dengan Teak Oil (P.Ct. 06) 25,946.53
7 P. Ct. 07 1m2 Pelaburan Bidang Kayu dengan Politur (P.Ct. 07) 29,922.70
8 P. Ct. 08 1m2 Pekerjaan Melamic (P.Ct. 08) 56,136.96
9 P. Ct. 09 1m2 Pelaburan Bidang Kayu Dengan Cat Residu dan Ter (P.Ct. 09) 15,304.30
10 P. Ct. 10 1m2 Pelaburan Bidang Kayu Dengan Vernis (P.Ct. 10) 25,096.78
1m2 Pengecatan Tembok Baru (1 Lapis Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup)
11 P. Ct. 11 26,196.27
Dengan Cat Mutu Baik. (P.Ct. 11)
1m2 Pengecatan Tembok Lama (1 Lapis Cat Dasar, 2 Lapis Cat Penutup)
12 P. Ct. 12 16,014.94
Dengan Cat Mutu Baik. (P.Ct. 12)
13 P. Ct. 13 1m2 Pengecatan Permukaan Baja dengan Meni Besi (P.Ct. 13) 20,752.60
14 P. Ct. 14 1m2 Pengecatan Permukaan Baja dengan Meni Besi dan Perancah (P.Ct. 14) 43,734.30
15 P. Ct. 15 1m2 Pengecatan Atap Seng (P.Ct. 15) 28,744.73
O. PEKERJAAN MEKANIKAL ELEKRIKAL
1 P. ME. 01
P. PEKERJAAN BONGKARAN
1 P. Bkr. 01 1m3 Pekerjaan Bongkaran Beton Bertulang (P.Bkr. 01) 344,843.95
2 P. Bkr. 02 1m2 Pekerjaan Bongkaran Dinding Tembok Plesteran Simpai (P. Bkr. 02) 75,861.50
3 P. Bkr. 03 1m2 Pekerjaan Bongkaran Lantai Ubin / Keramik (P.Bkr. 03) 2,586.38
4 P. Bkr. 04 1m2 Pekerjaan Bongkaran Atap Genteng / Sirap (P.Bkr. 04) 816.75
5 P. Bkr. 05 1m2 Pekerjaan Bongkaran Atap Seng (P.Bkr. 05) 12,006.50
6 P. Bkr. 06 1m2 Pekerjaan Bongkaran Rangka Atap Kayu (P.Bkr. 06) 51,727.50
7 P. Bkr. 07 1m3 Pekerjaan Bongkaran Rangka Badan Kayu (P.Bkr. 07) 406,560.00
Rekapitulasi 113
REKAPITULASI ANALISA BIAYA KONSTRUKSI (ABK)
HARGA SATUAN
NO. KODE ANALISA URAIAN PEKERJAAN HAL
(Rp.)
1 2 3 4 5
A. PEKERJAAN PERSIAPAN
1 P. Ps. 03 1m2 Membersihkan Lapangan dan Perataan (P.Ps. 03) 10,750.00
B. PEKERJAAN TANAH
1 P. T. 11 1m3 Menimbun dengan Tanah Peniraman (P.T. 11) 277,628.91
2 P. T. 13 Mengurug 1m3 Pasir Urug (P.T. 13) 176,393.64
x 2.3 5.29
y 5 25
r 30.29 5.503635
HITUNGAN RAB
TA RENCANA HASIL PERHITUNGAN
Koefisien
Tinggi VOLUME Sat. KETERANGAN
Data Sat-
- - - 175.50 M2
- - - 57.00 M'
0.80 - - 28.32 M3
- 0.016 m3 0.79 M3
- - - 98.00 Bh
- 0.003 m3 0.25 M3
- - - 0.753 M3
- - - 46.410 M3
- - - 8.840 M3
- - - 110.500 M2
0.50 - - 22.50 M2
- - - 0.335 M3
- - - 1.882 M3
- - - 0.502 M3
0.25 - - 0.88 M3
4.000 Unit
- - - 1.676 M3
- - - 0.288 M3
- - - 0.652 M3
- - - 4.00 Bh
- - - 8.00 Bh
- - - 76.00 Bh
6.000 Unit
- - - 0.320 M3
- - - 0.120 M3
- - - 24.00 Bh
3.000 Unit
- - - 0.529 M3
- - - 0.060 M3
- - - 0.060 M3
- - - 12.00 Bh
- - - 0.120 M3
- - - 12.00 Bh
- - - 12.30 M'
- - - 10.20 M2
- - - 244.00 M'
- - - 179.43 M2
- - - 4.42 M2
- - - 145.00 M2
- - - 92.96 M'
- - - 6.00 Titik
- - - 10.00 Titik
- - - 7.00 Titik
- - - 6.00 Titik
- - - 1.00 Titik
- - - 2.00 Unit
1.80 - - 2.16 M2
- - - 3.54 M2
- - - 4.00 Bh
- - - 6.00 Bh
- - - 4.00 Bh
- - - 1.00 Unit
- - - 5.00 Unit
0.60 - - 3.00 M2
- - - 10.00 Bh
- - - 15.00 Bh
- - - 10.00 Bh
- - - 5.00 Unit
- - - 8.00 Bh
- - - 8.00 Bh
- - - 16.00 Bh
- - - 16.00 Bh
- - - 8.00 Bh
- - - 8.00 Bh
- - - 8.00 Bh
- - - 16.00 Bh
- - - 16.00 Bh
- - - 8.00 Bh
- - - 2.00 Unit
0.60 - - 2.40 M2
- - - 4.00 Bh
- - - 6.00 Bh
- - - 4.00 Bh
- - - 2.00 Unit
0.60 - - 1.20 M2
- - - 1.00 Unit
- - - 0.28 M3
- - - 14.11 M2
N
ERANGAN