ANAI,ISA HARGA SATUAN PEKERIAAN PONDASI

Analisa Harga Satuan Pekeriaan Pondasi


Sesuai Permen PUPR Nomor 2B Tahun 2016

HARGA SATUAN
URAIAN SATUAN VOLUME HARGA (Rp)
{Rp)
Memasang 1m3 Pondasi Batu belah campuran 1 PC:4 PS
Bahan
Batrr belah 15/20 cm m3 7.200 430,000.00 516,000.00
Semen Portland kg 163.000 1,700.00 277.100.00
Pasir Pasang m3 0.520 352,300.00 183,196.00
Upah
Pekeria 0h 1.500 120,000.00 180,000.00
Tukang Batu oh 0.750 165,000.00 723,750.00
Kepala Tukang oh 0.075 170,000.00 n,754.0A
Mandor oh 0.075 180,000.00 13,500.00
Iumlah Rp L346,296.A0
Overhead & Profit (maksimal 15olo) Rp 195,944.40
Harga Satuan Pekeriaan Rp 1,5O2,24O.4O

Memasang 1 m3 Batu Kosqlrg {aanstamping)


Bahan
Batu belah 15/20 cm m3 t.200 430,000.00 516,000.00
Pasir Urue m3 0.432 113,600.00 49,075.20
Upah
Pekeria 0h 0,780 120,000.00 93,600,00
Tukang Batu oh 0.390 165,000.00 64,350.00
Kepala Tukang oh 0.039 170,000.00 6,630.00
Mandor oh 0.039 180,000.00 7,020.00
fumlah RD 736,675.20
Overhead & Profit (maksimal 15olo) Rp 110,501.28
Uarga Satuan Pekerjaan Rp 447,176.48