KOEF.
URAIAN PEKERJAAN SAT. SATUAN UPAH KERJA BAHAN HARGA
ANALISIS
(Rp) (Rp) (Rp) (Rp)
I. PEKERJAAN PENDAHULUAN
1 Pengukuran dan pemasangan bouwplank per m'
Balok Kayu Meranti 0.0120 m3 3,499,900.00 41,998.80 41,998.80
Paku 0.0200 kg 25,000.00 500.00 500.00
Papan Kayu Meranti 0.0070 m3 3,619,200.00 25,334.40 25,334.40
Pekerja 0.1000 oh 170,000.00 17,000.00 17,000.00
Tukang 0.1000 oh 180,000.00 18,000.00 18,000.00
Kepala tukang 0.0100 oh 180,000.00 1,800.00 1,800.00
Mandor 0.0050 oh 200,000.00 1,000.00 1,000.00
JUMLAH ( UPAH DAN BAHAN) Rp. 105,633.20
OVERHEAD & PROFIT 10 % Rp. 10,563.32
JUMLAH 116,196.52
DI BULATKAN Rp. 116,100.00
PEKERJAAN STRUKTUR KAYU
1 Bh Pengadaan & Pemancangan Tiang Ulin 10/10 - 200
Balok Kayu Ulin 10/10 0.0220 m3 6,248,700.00 137,471.40 137,471.40
Pekerja 0.1250 oh 170,000.00 21,250.00 21,250.00
Tukang 0.1000 oh 180,000.00 18,000.00 18,000.00
Kepala tukang 0.0100 oh 180,000.00 1,800.00 1,800.00
Mandor 0.0130 oh 200,000.00 2,600.00 2,600.00
JUMLAH ( UPAH DAN BAHAN) Rp. 181,121.40
OVERHEAD & PROFIT 10 % Rp. 18,112.14
JUMLAH 199,233.54
DI BULATKAN Rp. 199,200.00
1 M3 Memasang Sunduk Ulin
Balok Kayu Ulin 5/10 1.1000 m3 6,248,700.00 6,873,570.00 6,873,570.00
Pekerja 0.2500 oh 170,000.00 42,500.00 42,500.00
Pekerja 0.2000 oh 170,000.00 34,000.00 34,000.00
Tukang 0.0200 oh 180,000.00 3,600.00 3,600.00
Kepala tukang 0.0250 oh 180,000.00 4,500.00 4,500.00
JUMLAH ( UPAH DAN BAHAN) Rp. 6,958,170.00
OVERHEAD & PROFIT 10 % Rp. 695,817.00
JUMLAH 7,653,987.00
DI BULATKAN Rp. 7,653,900.00
1 M3 Memasang Kalang Ulin
Balok Kayu Ulin 1.1000 m3 6,248,700.00 6,873,570.00 6,873,570.00
Pekerja 0.0200 oh 170,000.00 3,400.00 3,400.00
Tukang 0.0200 oh 180,000.00 3,600.00 3,600.00
Kepala tukang 0.0200 oh 180,000.00 3,600.00 3,600.00
Mandor 0.0100 oh 200,000.00 2,000.00 2,000.00
JUMLAH ( UPAH DAN BAHAN) Rp. 6,886,170.00
OVERHEAD & PROFIT 10 % Rp. 688,617.00
JUMLAH 7,574,787.00
DI BULATKAN Rp. 7,574,700.00
1 M3 Mengerjakan Sloof Kayu
Balok Kayu Ulin 1.1000 m3 6,248,700.00 6,873,570.00 6,873,570.00
Paku Ulin 3.0000 Kg 30,000.00 90,000.00 90,000.00
Baut Ǿ14 mm - 12 s/d 15 cm 40.0000 bh 11,000.00 440,000.00 440,000.00
Page 1 of 107
ANALISA HARGA HARGA JUMLAH
KODE
KOEF.
URAIAN PEKERJAAN SAT. SATUAN UPAH KERJA BAHAN HARGA
ANALISIS
(Rp) (Rp) (Rp) (Rp)
KOEF.
URAIAN PEKERJAAN SAT. SATUAN UPAH KERJA BAHAN HARGA
ANALISIS
(Rp) (Rp) (Rp) (Rp)
Page 3 of 107
ANALISA HARGA HARGA JUMLAH
KODE
KOEF.
URAIAN PEKERJAAN SAT. SATUAN UPAH KERJA BAHAN HARGA
ANALISIS
(Rp) (Rp) (Rp) (Rp)
KOEF.
URAIAN PEKERJAAN SAT. SATUAN UPAH KERJA BAHAN HARGA
ANALISIS
(Rp) (Rp) (Rp) (Rp)
KOEF.
URAIAN PEKERJAAN SAT. SATUAN UPAH KERJA BAHAN HARGA
ANALISIS
(Rp) (Rp) (Rp) (Rp)
KOEF.
URAIAN PEKERJAAN SAT. SATUAN UPAH KERJA BAHAN HARGA
ANALISIS
(Rp) (Rp) (Rp) (Rp)
KOEF.
URAIAN PEKERJAAN SAT. SATUAN UPAH KERJA BAHAN HARGA
ANALISIS
(Rp) (Rp) (Rp) (Rp)
Page 8 of 107
ANALISA HARGA HARGA JUMLAH
KODE
KOEF.
URAIAN PEKERJAAN SAT. SATUAN UPAH KERJA BAHAN HARGA
ANALISIS
(Rp) (Rp) (Rp) (Rp)
Page 9 of 107
ANALISA HARGA HARGA JUMLAH
KODE
KOEF.
URAIAN PEKERJAAN SAT. SATUAN UPAH KERJA BAHAN HARGA
ANALISIS
(Rp) (Rp) (Rp) (Rp)
1 m3 Lantai Kerja
Beton 1 Pc : 2 Ps : 3 Kr 1.0000 m3 2,510,000.00 2,510,000.00
Besi Polos 59.8500 Kg 21,900.00 1,310,715.00
JUMLAH ( UPAH DAN BAHAN) Rp. 3,820,715.00
DI BULATKAN Rp. 3,820,700.00
1 m2 Pasang Keramik warna ukuran 25 x 25 cm
Keramik 25 x 25 cm (warna) 16.0000 Lbr 6,875.00 110,000.00 110,000.00
Semen PC 10.0000 kg 2,530.00 25,300.00 25,300.00
Pasir Pasang 0.0420 m3 616,400.00 25,888.80 25,888.80
Semen warna 1.500 Kg 3,158.00 4,737.00 4,737.00
Pekerja 0.7000 Oh 170,000.00 119,000.00 119,000.00
Tukang 0.3500 Oh 180,000.00 63,000.00 63,000.00
Kepala Tukang 0.0350 Oh 180,000.00 6,300.00 6,300.00
Mandor 0.0350 Oh 200,000.00 7,000.00 7,000.00
JUMLAH ( UPAH DAN BAHAN) Rp. 361,225.80
OVERHEAD & PROFIT 10 % Rp. 36,122.58
JUMLAH 397,348.38
DI BULATKAN Rp. 397,300.00
Pasang Dinding Keramik 25x40 cm (warna)per m2
Keramik 25x40 cm (warna) 10.0000 lbr 6,875.00 68,750.00 68,750.00
Semen PC 9.3000 kg 2,530.00 23,529.00 23,529.00
Pasir Pasang 0.0180 m3 616,400.00 11,095.20 11,095.20
Semen warna 1.9400 kg 3,158.00 6,126.52 6,126.52
Pekerja 0.9000 oh 170,000.00 153,000.00 153,000.00
Tukang 0.4500 oh 180,000.00 81,000.00 81,000.00
Kepala Tukang 0.0045 oh 180,000.00 810.00 810.00
Mandor 0.0450 oh 200,000.00 9,000.00 9,000.00
JUMLAH ( UPAH DAN BAHAN) Rp. 353,310.72
OVERHEAD & PROFIT 10 % Rp. 35,331.07
JUMLAH 388,641.79
DI BULATKAN Rp. 388,600.00
PEKERJAAN PENGGANTUNG & PENGUNCI
1 buah Pasang Kunci Tanam biasa 2x Putar
Kunci tanam biasa 1.000 Bh 300,000.00 300,000.00 300,000.00
Pekerja 0.005 Oh 170,000.00 850.00 850.00
Tukang 0.500 Oh 180,000.00 90,000.00 90,000.00
Kepala Tukang 0.050 Oh 180,000.00 9,000.00 9,000.00
Mandor 0.005 Oh 200,000.00 1,000.00 1,000.00
JUMLAH ( UPAH DAN BAHAN) Rp. 400,850.00
OVERHEAD & PROFIT 10 % Rp. 40,085.00
JUMLAH 440,935.00
DI BULATKAN Rp. 440,900.00
1 Set Pasang Grendel Tanam Pintu
Grendel Tanam Pintu 1.000 Bh 53,200.00 53,200.00 53,200.00
Pekerja 0.010 Oh 170,000.00 1,700.00 1,700.00
Tukang 0.500 Oh 180,000.00 90,000.00 90,000.00
Kepala Tukang 0.010 Oh 180,000.00 1,800.00 1,800.00
Mandor 0.005 Oh 200,000.00 1,000.00 1,000.00
JUMLAH ( UPAH DAN BAHAN) Rp. 147,700.00
OVERHEAD & PROFIT 10 % Rp. 14,770.00
JUMLAH 162,470.00
DI BULATKAN Rp. 162,400.00
1 buah pasang kunci tanam KM/WC
Kunci tanam KM/WC 1.000 Bh 260,000.00 260,000.00 260,000.00
Pekerja 0.005 Oh 170,000.00 850.00 850.00
Tukang 0.500 Oh 180,000.00 90,000.00 90,000.00
Kepala tukang 0.005 Oh 180,000.00 900.00 900.00
Page 10 of 107
ANALISA HARGA HARGA JUMLAH
KODE
KOEF.
URAIAN PEKERJAAN SAT. SATUAN UPAH KERJA BAHAN HARGA
ANALISIS
(Rp) (Rp) (Rp) (Rp)
Page 11 of 107
ANALISA HARGA HARGA JUMLAH
KODE
KOEF.
URAIAN PEKERJAAN SAT. SATUAN UPAH KERJA BAHAN HARGA
ANALISIS
(Rp) (Rp) (Rp) (Rp)
KOEF.
URAIAN PEKERJAAN SAT. SATUAN UPAH KERJA BAHAN HARGA
ANALISIS
(Rp) (Rp) (Rp) (Rp)
Page 13 of 107
ANALISA HARGA HARGA JUMLAH
KODE
KOEF.
URAIAN PEKERJAAN SAT. SATUAN UPAH KERJA BAHAN HARGA
ANALISIS
(Rp) (Rp) (Rp) (Rp)
KOEF.
URAIAN PEKERJAAN SAT. SATUAN UPAH KERJA BAHAN HARGA
ANALISIS
(Rp) (Rp) (Rp) (Rp)
Page 15 of 107
ANALISA HARGA HARGA JUMLAH
KODE
KOEF.
URAIAN PEKERJAAN SAT. SATUAN UPAH KERJA BAHAN HARGA
ANALISIS
(Rp) (Rp) (Rp) (Rp)
KOEF.
URAIAN PEKERJAAN SAT. SATUAN UPAH KERJA BAHAN HARGA
ANALISIS
(Rp) (Rp) (Rp) (Rp)
Plamur 0.10 Kg
Cat Dasar 1 x 0.100 Kg 73,500.00 7,350.00 7,350.00
Cat Penutup 2 x 0.260 Kg 73,500.00 19,110.00 19,110.00
Pekerja 0.020 Oh 170,000.00 3,400.00 3,400.00
Tukang 0.063 Oh 180,000.00 11,340.00 11,340.00
Kepala tukang 0.006 Oh 180,000.00 1,134.00 1,134.00
Mandor 0.003 Oh 200,000.00 500.00 500.00
JUMLAH ( UPAH DAN BAHAN) Rp. 42,834.00
OVERHEAD & PROFIT 10 % Rp. 4,283.40
JUMLAH 47,117.40
DI BULATKAN Rp. 47,100.00
Page 17 of 107
ANALISA HARGA HARGA JUMLAH
KODE
KOEF.
URAIAN PEKERJAAN SAT. SATUAN UPAH KERJA BAHAN HARGA
ANALISIS
(Rp) (Rp) (Rp) (Rp)
Page 18 of 107
PERHITUNGAN VOLUME
UKURAN
1 ITEM PEKERJAAN SAT VOLUME
P L T N
1 Tongkat/Tiang 10/10 (Kayu Kelas I)
Jalur baris tongkat jumlah 7 bh 1.00 1.00 7.00 2.00 14.00
Jumlah baris tongkat jumlah 9 bh 1.00 1.00 9.00 2.00 18.00
Jumlah baris tongkat jumlah 11 bh 1.00 1.00 11.00 5.00 55.00
Jumlah baris tongkat jumlah 10 bh 1.00 1.00 10.00 1.00 10.00
97.00
2 Sunduk, Balok (Kayu Kelas I) 5/10 - 50 M3 0.50 0.05 0.10 97.00 0.25
3 Kalang, (Kayu Kelas I) 10/10 - 100 x 2 M3 1.00 0.05 0.10 97.00 0.49
4 Suai Tongkat, Balok (Kayu Kelas I) 5/10 - M3 1.50 0.05 0.10 16.00 0.12
Suai Tongkat, Balok (Kayu Kelas I) 5/10 - M3 2.00 0.05 0.10 64.00 0.64
0.76
BARIS A & B
BARIS c & d
BARIS e,f,g,h,i
Baris J
BARIS A & B
BARIS c & d
BARIS e,f,g,h,i
Baris J
baris 1, 12
baris 4,6,8,10
baris 1
baris 2
baris 3
baris 4
baris 5
baris 6
baris 7
baris 8
baris 9
baris 10
baris 11
baris 12
baris 1
baris 2
baris 3
baris 4
S1
S1.1
S2
S2.1
S3
S3.1
S4
S5
S6
S7
S8
S8.1
S9
S9.1
S10
S11
S12
S13
S13.1
S14
S15
S16
S16.1
S17
S17.1
S18
S18.1
S19
S20
S20.1
S21
S21.1
S21.2
S22
S23
S24
S24.1
S25
S25.1
S26
S26.1
S27
S28
S28.1
S29
S30
S31
S31.1
S32
S33
S33.1
S34
S35
S36
S36.1
S37
S38
S38.1
S39
S40
S40.1
S41
S42
S43
S43.1
S44
S45
S45.1
S46
S47
baris A
baris B
baris C
baris D
baris E
baris F
baris G
baris H
baris I
baris J
baris K
baris L
baris 1
baris 2
baris 3
baris 4
baris 5
baris 6
baris 7
baris 8
baris 9
baris 10
baris 11
baris 12
baris 13
baris 14
Bagian Dalam
Dalam + Teras
Teras
teras belakang
sebelah kanan
jendela
Bovenlight
jendela
layar
layar1
sebelah kiri
jendela
Bovenlight
jendela
layar
layar1
belakang
jendela
jendela
Pintu
Pintu
Bovenlight
Depan
jendela
jendela
jendela
Pintu
Depan
Piontu
Depan
pintu
pintu
Pintu
Void
Pintu
jendela
Pintu
jendela
Pintu
jendela
Pintu
Void
Pintu
Pintu
jendela
Pintu
jendela
Pintu
jendela
Pintu
Pintu
jendela
Pintu
Pintu
Pintu
Pintu
Pintu
Pintu
m3
m2
Jalusi
m3
m2
Jalusi
m3
m2
Jalusi
m3
m2
Jalusi
m3
m2
Jalusi
m3
m2
Jalusi
m3
m2
Jalusi
m3
m2
Jalusi
m3
m2
Jalusi
m3
m2
m3
m2
m2
m2 pengecatan
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
M3
M3
M3
M3
M3
M3
M3
M3
M3
M3
M3
M3
M3
M3
M3
M3
M3
M3
M3
M3
M3
M3
M3
M3
M3
M3
M3
M3
M3
M3
M3
M3
M3
M3
M3
M3
M3
M3
M3
M3
M3
M3
M3
M3
M3
M3
M3
M3
M3
M3
M3
M3
M3
M2
M2
M2
M2
M2
M2
M2
M1
M1
M1
M1
M1
M1
M1
M1
M1
M1
M1
M1
M1
M1
M1
M1
M1
M1
M1
Pekerjaan Lokasi divisi sub divisi Panjang
samping 4.00
2.50
teras 2.00
belakang 1.15
teras 2.00
depan teras
belakang 1.15
Saklar tuangan
ganda
terminal
panel pintu
jendela 1.00
0.52
kaca
TERALIS
0.10 2.00
0.10 0.02
0.20 0.02
0.10 3.82
0.05 3.82
0.05 0.10
0.05 0.10
0.05 0.10
0.05 0.10
0.10 0.10
0.05 0.10
0.10 0.10
0.10 0.10
7.10
8.10
3.90
3.90
3.90
3.90
1.32
1.40
2.76
2.76
0.25
0.05 0.10
0.05 0.07
0.05 0.10
0.05 0.10
0.05 0.10
0.05 0.10
0.05 0.10
0.05 0.10
0.05 0.10
0.05 0.10
0.05 0.10
0.05 0.10
0.05 0.10
0.10 0.10
0.04 0.09
0.04 0.09
0.04 0.09
0.05 0.10
0.05 0.10
0.05 0.10
0.05 0.10
0.04 0.09
0.04 0.09
0.04 0.09
0.04 0.09
8.10
8.10
8.14
0.96
0.96
8.14
8.10
8.10
0.96
0.96
6.55
0.12 0.06
0.12 0.06
0.10 0.02
0.12 0.06
0.12 0.06
0.12 0.06
0.10 0.02
0.12 0.06
0.12 0.06
0.12 0.06
0.12 0.06
0.10 0.02
0.12 0.06
0.12 0.06
0.12 0.06
0.12 0.06
0.10 0.02
0.12 0.06
1.20 1.94
0.07
0.07
0.52 0.86
0.66 1.00
1.32 2.06
0.07
0.07
0.66
0.20 0.05
0.10 0.10
0.10 0.10
0.20 0.05
Jumlah julah per titik Sub Volume Volume Total Satuan
36.00 0.72 M3
36.00 0.04 M3
72.00 0.14 M3
16.00 0.61 M3
7.00 0.13 M3
4.00 0.08
2.00 0.03
6.00 0.55 M3
19.00 0.77 M3
57.51 57.51 M2
16.04 16.04 M3
M3
1.00 16.20
1.00 9.36
2.00 12.29
2.00 12.29
1.00 9.36
1.00 12.10
9.92
2.00 25.60
2.00 23.30
1.00 18.06
2.00 133.62 M2
5.66 74.49 M
5.46
2.04
1.26
3.61
5.66
-
7.90
1.90
6.90 45.40
7.90
1.90
-
2.00 5.40 29.09
7.00 18.90
3.00 0.03
3.00 0.03
3.00 0.01
1.00 0.00
1.00 2.33 M2
8.00 5.28
2.00 0.03 0.14 M2
-
2.00 0.01
1.00 0.02
5.00 0.09
-
-
0.14
0.006 0.66
0.00859797979798 1.00
PEMERINTAH KABUPATEN KUTAI BARAT
DINAS PENDIDIKAN DAN KEBUDAYAAN
Alamat : Kompleks Perkantoran Pemkab Kutai Barat
SENDAWAR
REKAPITULASI
DINAS : DINAS PENDIDIKAN DAN KEBUDAYAAN
PEKERJAAN : PEMBANGUNAN RUANG LABORATORIUM KOMPUTER SDN 010 MUARA PAHU(DAK SD)
TAHUN ANGGARAN : 2022
LOKASI : KEC. MUARA PAHU
UKURAN : 103,14 M2
JUMLAH HARGA
NO. JENIS PEKERJAAN
(Rp.)
1 PEKERJAAN PENDAHULUAN 3,605,120.000
2 PEKERJAAN STRUKTUR KAYU 32,268,122.000
3 PEKERJAAN LANTAI DAN DINDING, 53,787,177.000
4 PEKERJAAN KUSEN, PINTU DAN JENDELA 9,252,133.000
5 PEKERJAAN RANGKA ATAP DAN PENUTUP ATAP 34,596,360.000
6 PEKERJAAN PLAFON 30,982,838.000
8 PEKERJAAN PENGGANTUNG, PENGUNCI DAN AKSESORIS 8,876,741.000
7 PEKERJAAN LISTRIK 4,937,500.000
9 PEKERJAAN PENGECATAN 23,664,926.000
10 PEKERJAAN LAIN-LAIN 5,229,942.000
A. JUMLAH 207,200,859.00
B. PPn ( 11% x A ) 22,792,094.49
C. TOTAL 229,992,953.49
D. DIBULATKAN 229,992,000.00
TERBILANG : DUA RATUS DUA PULUH SEMBILAN JUTA SEMBILAN RATUS SEMBILAN PULUH DUA RIBU RUPIAH
D
Sendawar, 2022 i
p
e
Dibuat Oleh
Mengetahui: r
Di Buat :
PT. ARISTA
PejabatGEMILANG
Pembuat KONSULINDO
komitmen i
PT. ARIESTA GEMILANG KONSULINDO
k
s
a
/
PAULUS PAGAPPONG, D
PAULUS PAGAPPONG, NGAMPUN,
ST S.IP, M.SIST Mi
Nip: Direktur
19621127 Cabang
199103 1 002 es
Direktur Cabang
ne
g
et
ut
aj
uh
ui
,,i
P
E
J
AJ
A
B
BA
T
A
PT
Page 54 ofE107
MP
B
E
U
HARGA PERKIRAAN SENDIRI
1 PEKERJAAN PENDAHULUAN
1.1 Papan Nama Kegiatan 1.00 Ls 350,000.00 350,000.00
1.2 Pembersihan Lokasi Dan Perataan 1.00 Ls 500,000.00 500,000.00
1.3 Pengukuran dan pemb. Bouplank 42.40 m¹ 26,300.00 1,115,120.00
1.4 Manajemen dan Keselamatan Kerja 1.00 Ls 1,640,000.00 1,640,000.00
JUMLAH (Rp.) 3,605,120.00
2 PEKERJAAN STRUKTUR KAYU
2.1 Tongkat/Tiang 10/10 (Kayu Kelas I) 36.00 ttk 153,800.00 5,536,800.00
2.2 Sunduk, Balok (Kayu Kelas I) 2/10 - 50 0.03 m³ 7,653,900.00 229,617.00
2.3 Kalang, (Kayu Kelas I) 2/20 - 50 x 2 0.14 m³ 8,052,300.00 1,127,322.00
2.4 Sloof, Balok (Kayu Kelas I) 10/10 0.54 m³ 11,342,700.00 6,125,058.00
2.5 Gelegar, Balok (Kayu Kelas I) 5/10 0.76 m³ 11,747,500.00 8,928,100.00
2.6 Kolom, Balok (Kayu Kelas II) 10/10 0.61 m³ 8,888,700.00 5,422,107.00
2.7 Kolom, Balok (Kayu Kelas II) 5/10 0.13 m³ 8,888,700.00 1,155,531.00
2.8 Ringbalk, Balok (Kayu Kelas II) 10/10 0.41 m³ 9,130,700.00 3,743,587.00
JUMLAH (Rp.) 32,268,122.00
3 PEKERJAAN LANTAI DAN DINDING,
3.1 Lantai Papan Bengkirai 2,5 / 20 57.51 m² 277,000.00 15,930,270.00
3.2 Lantai Papan Kayu Ulin 2 / 20 (Selasar) 16.03 m² 331,900.00 5,320,357.00
3.3 Dinding Luar, Papan Kayu Bengkirai (Ketam 2 Sisi) 133.58 m² 234,100.00 31,271,078.00
3.4 List Dinding Kayu Bengkirai 2 / 10 54.08 m 23,400.00 1,265,472.00
JUMLAH (Rp.) 53,787,177.00
4 PEKERJAAN KUSEN, PINTU DAN JENDELA
4.1 Kusen-Kusen + Jelusi Mati, Kayu Kelas II (Bengkirai) 0.33 m³ 11,773,300.00 3,885,189.00
4.2 Pintu Panel, Papan Kayu Kelas II (Bengkirai) 2.32 m² 536,800.00 1,245,376.00
4.4 Jendela Kaca, Papan Kayu Bengkirai 5.28 m² 780,600.00 4,121,568.00
JUMLAH (Rp.) 9,252,133.00
5 PEKERJAAN RANGKA ATAP DAN PENUTUP ATAP
5.1 Kuda-kuda, Nok dan Jurai, Balok Kayu Meranti 5/10 0.70 m³ 8,173,900.00 5,721,730.00
5.2 Pasangan Skor Angin, Balok Kayu Meranti 5/10 0.11 m³ 8,173,900.00 899,129.00
5.3 Pasangan Gording, Balok Kayu Meranti 5/7 0.63 m³ 8,532,900.00 5,375,727.00
5.4 Pekerjaan Lisplank Papan Kayu Bengkirai 2 x 2/20 45.84 m¹ 89,400.00 4,098,096.00
5.5 Pasangan Atap Soka 133.62 m² 131,900.00 17,624,478.00
5.6 Nok / Bubungan 10.20 m¹ 86,000.00 877,200.00
JUMLAH (Rp.) 34,596,360.00
Page 55 of 107
HARGA SATUAN JUMLAH HARGA
NO. JENIS PEKERJAAN VOLUME SAT.
(Rp.) (Rp.)
6 PEKERJAAN PLAFON
6.1 Pasang 1m² Pasang rangka langit-langit kayu Meranti 117.00 m² 174,600.00 20,428,200.00
6.2 Memasang 1m² Langit-langit GRC 117.00 m² 64,600.00 7,558,200.00
6.4 List plafond, kayu profil 1/4 cm 119.38 m¹ 25,100.00 2,996,438.00
JUMLAH (Rp.) 30,982,838.00
8 PEKERJAAN PENGGANTUNG, PENGUNCI DAN AKSESORIS
8.1 Teralis Pintu Dan Jendela 7.99 m2 615,900.00 4,921,041.00
8.2 Kunci tanam biasa 2 x Kali Putar 1.00 Bh 440,900.00 440,900.00
8.3 Grendel Tanam Pintu Kupu-Kupu 2.00 Bh 88,200.00 176,400.00
8.4 Ensel Pintu 5 inchi ( 3 Engsel untuk 1 Pintu) 6.00 Bh 70,800.00 424,800.00
8.5 Ensel Jendela 3 inchi ( 2 Engsel untuk 1 Jendela) 16.00 Bh 58,700.00 939,200.00
8.6 Kait / Hak Angin Jendela 16.00 Bh 61,700.00 987,200.00
8.7 Grendel Jendela 8.00 Bh 61,700.00 493,600.00
8.8 Pegangan / Handel Jendela 8.00 Bh 61,700.00 493,600.00
JUMLAH (Rp.) 8,876,741.00
7 PEKERJAAN LISTRIK
7.1 Instalasi Titik Lampu 8.00 Ttk 225,000.00 1,800,000.00
7.2 Instalasi Titik Saklar Ganda 1.00 Ttk 248,000.00 248,000.00
7.3 Instalasi Titik Saklar Tunggal 1.00 Ttk 237,000.00 237,000.00
7.4 Instalasi Titik Stop Kontak 7.00 Ttk 243,600.00 1,705,200.00
7.5 Instalasi Sekering Box / MCB (include MCB Box) 1.00 Bh 568,100.00 568,100.00
7.6 Lampu SL 18 W 8.00 Bh 47,400.00 379,200.00
JUMLAH (Rp.) 4,937,500.00
9 PEKERJAAN PENGECATAN
9.1 Cat Plafon ( Cat Air ) 117.00 m² 53,300.00 6,236,100.00
9.2 Cat List Plafon ( Cat Minyak ) 7.16 m² 59,600.00 426,736.00
9.3 Cat Kusen + Jelusi ( Cat Minyak ) 10.44 m² 59,600.00 622,224.00
9.4 Cat Pintu ( Cat Minyak ) 4.64 m² 59,600.00 276,544.00
9.5 Cat Daun Jendela ( Cat Minyak ) 3.40 m² 59,600.00 202,640.00
9.6 Cat Lisplang ( Cat Minyak ) 13.75 m² 59,600.00 819,500.00
9.7 Cat dinding Eksterior( Cat Minyak ) 133.58 m² 59,600.00 7,961,368.00
9.8 Cat dinding Dalam ( Cat Air ) 133.58 m² 53,300.00 7,119,814.00
JUMLAH (Rp.) 23,664,926.00
10 PEKERJAAN LAIN-LAIN
10.1 Pekerjaan Relling Teras, (Kayu Kelas II)
- Konstruksi Relling 0.28 m3 8,769,700.00 2,455,516.00
- Pengecatan (Cat Minyak) 16.35 m2 59,600.00 974,460.00
10.2 Pekerjaan Tangga, (kayu Kelas I)
- Konstruksi tangga 0.14 M3 12,856,900.00 1,799,966.00
JUMLAH (Rp.) 5,229,942.00
Page 56 of 107
PERHITUNGAN VOLUME
UKURAN
1 ITEM PEKERJAAN SAT VOLUME KETERANGAN
P L T N
1 Tongkat/Tiang 10/10 (Kayu Kelas I)
Jalur baris tipe 1 jumlah 6 (7ttk) Ttk 7.00 1.00 1.00 6.00 42.00 BARIS 1,2,3,9,10&11
Jalur baris tipe 2 jumlah 5 (8ttk) Ttk 8.00 1.00 1.00 5.00 40.00 BARIS 4,5,6,7,8
82.00
2 Sunduk, Balok (Kayu Kelas I) 5/10 - 50 M3 0.50 0.05 0.10 82.00 0.21
3 Kalang, (Kayu Kelas I) 5//10 - 50 x 2 M3 1.00 0.05 0.10 82.00 0.41
4 Suai Tongkat, Balok (Kayu Kelas I) 5/10 - 400 M3 4.00 0.05 0.10 20.00 0.40
Suai Tongkat, Balok (Kayu Kelas I) 5/10 - 300 M3 3.00 0.05 0.10 8.00 0.12
Suai Tongkat, Balok (Kayu Kelas I) 5/10 - 200 M3 2.00 0.05 0.10 4.00 0.04
0.520
9 Kolom, Balok (Kayu Kelas II) 5/10 M3 3.70 0.05 0.10 7.00 0.13
16 KUSEN
Pintu dan Jendela Type 1 2.4 0.05 0.14 4 0.07
2.8 0.05 0.14 2 0.04
0.7 0.05 0.14 2 0.01
0.25 0.05 0.14 1 0.002
16.85 0.12 m3
4.044 m2
23 LISTPLANK
1 Listplank 1 (2 bh) 3.78 2 7.56 M1
2 Listplank 2 (2 bh) 4.64 2 9.28 M1
3 Listplank 3 (2 bh) 1.51 2 3.02 M1
4 Listplank 4 (4 bh) 6.71 4 26.84 M1
5 Listplank 5 (1 bh) 14.9 1 14.90 M1
61.60
24 RANGKA PLAPON
1 Bidang 1 (1 bdg) 13.14 10.94 1 143.75 M2
2 Bidang 2 (2 bdg) 0.6 7.94 2 9.53 M2
3 Bidang 3 (6 bdg) 0.6 0.56 6 2.02 M2
4 Bidang 4 (4 bdg) 6.71 0.9 4 24.16 M2
5 Bidang 5 (2 bdg) 4.64 0.9 2 8.35 M2
187.8 M2
25 KACA MATI
2.30 0.68 1 2 3.13 M2
0.26 0.68 1 4 0.71 M2
0.91 0.31 1 4 1.13 M2
0.81 0.51 1 1 0.42 M2
5.39
26 LIST PLAFO
lisplang 61.60 1 61.60
dinding luar 48.60 1 48.60
wc + gudang 5.44 4 21.76
km tdr 1 9.44 1 9.44
km tdr 2 + arsip + g obat 10.43 3 31.29
Perawatan + kia 13.44 2 26.88
Lobby 20.44 1 20.44
R. Tamu 21.44 1 21.44
trs dpn 7.35 1 7.35
trs dpn 1 0.90 3 2.70
trs blkg 2.38 1 2.38
0.00
0.00
0.00
0.00
0.00
0.00
0.00
253.88
ENGGINEER'S ESTIMATE
PEKERJAAN PENDAHULUAN
Pengukuran dan pemasangan bouwplank per m'
Balok Kayu Meranti 0.0120 m3 Err:509 Err:509 Err:509
Paku 0.0200 kg 30,000.00 600.00 600.00
Papan Kayu Meranti 0.0070 m3 Err:509 Err:509 Err:509
Pekerja 0.1000 oh 100,000.00 10,000.00 10,000.00
Tukang Kayu 0.1000 oh 120,000.00 12,000.00 12,000.00
Kepala Tukang 0.0100 oh 150,000.00 1,500.00 1,500.00
Mandor 0.0050 oh 165,000.00 825.00 825.00
JUMLAH ( UPAH DAN BAHAN) Rp. Err:509
DI BULATKAN Rp. Err:509
PEKERJAAN STRUKTUR KAYU
1 m3 Pasang Struktur Kayu Ulin
Balok Kayu Ulin 1.1000 m3 4,800,000.00 5,280,000.00 5,280,000.00
Paku ulin 4.0000 Kg 36,000.00 144,000.00 144,000.00
Pekerja 5.0000 oh 100,000.00 500,000.00 500,000.00
Tukang Kayu 15.0000 oh 120,000.00 1,800,000.00 1,800,000.00
Kepala Tukang Kayu 1.5000 oh 150,000.00 225,000.00 225,000.00
Mandor 0.2500 oh 165,000.00 41,250.00 41,250.00
JUMLAH ( UPAH DAN BAHAN) Rp. 7,990,250.00
DI BULATKAN Rp. 7,990,200.00
1 m3 Pek. Konstruksi Gelagar & Pek. Tangga
Balok Kayu Ulin 1.100 m³ 4,800,000.00 5,280,000.00 5,280,000.00
Paku 10 cm 1.250 kg 30,000.00 37,500.00 37,500.00
Baut 20.000 Bh 7,000.00 140,000.00 140,000.00
Pekerja 7.000 oh 100,000.00 700,000.00 700,000.00
Tukang Kayu 21.000 oh 120,000.00 2,520,000.00 2,520,000.00
Kepala Tukang 2.100 oh 150,000.00 315,000.00 315,000.00
Mandor 0.350 oh 165,000.00 57,750.00 57,750.00
JUMLAH ( UPAH DAN BAHAN) Rp. 9,050,250.00
DI BULATKAN Rp. 9,050,200.00
PEKERJAAN LANTAI DAN DINDING
1 m2 Pasang Lantai Papan, Kayu Ulin (Halus)
Papan Kayu Ulin t ; 2,5 cm 0.0250 m3 5,400,000.00 135,000.00 135,000.00
Paku ulin 0.2500 Kg 36,000.00 9,000.00 9,000.00
Pekerja 0.2800 oh 100,000.00 28,000.00 28,000.00
Tukang Kayu 0.8000 oh 120,000.00 96,000.00 96,000.00
Kepala Tukang Kayu 0.0800 oh 150,000.00 12,000.00 12,000.00
Mandor 0.0140 oh 165,000.00 2,310.00 2,310.00
JUMLAH ( UPAH DAN BAHAN) Rp. 282,310.00
DI BULATKAN Rp. 282,300.00
1 m2 Pasang Lantai Papan, Kayu Ulin (Kasar)
Papan Kayu Ulin t ; 2,5 cm 0.0200 m3 5,400,000.00 108,000.00 108,000.00
Paku ulin 0.2500 Kg 36,000.00 9,000.00 9,000.00
Pekerja 0.2000 oh 100,000.00 20,000.00 20,000.00
Tukang Kayu 0.6000 oh 120,000.00 72,000.00 72,000.00
Kepala Tukang Kayu 0.0600 oh 150,000.00 9,000.00 9,000.00
Mandor 0.0140 oh 165,000.00 2,310.00 2,310.00
JUMLAH ( UPAH DAN BAHAN) Rp. 220,310.00
DI BULATKAN Rp. 220,300.00
Page 61 of 107
KODE ANALISA
HARGA HARGA JUMLAH
KOEF.
URAIAN PEKERJAAN SAT. SATUAN UPAH KERJA BAHAN HARGA
ANALISIS
(Rp) (Rp) (Rp) (Rp)
Page 62 of 107
KODE ANALISA
HARGA HARGA JUMLAH
KOEF.
URAIAN PEKERJAAN SAT. SATUAN UPAH KERJA BAHAN HARGA
ANALISIS
(Rp) (Rp) (Rp) (Rp)
Page 63 of 107
KODE ANALISA
HARGA HARGA JUMLAH
KOEF.
URAIAN PEKERJAAN SAT. SATUAN UPAH KERJA BAHAN HARGA
ANALISIS
(Rp) (Rp) (Rp) (Rp)
Page 65 of 107
KODE ANALISA
HARGA HARGA JUMLAH
KOEF.
URAIAN PEKERJAAN SAT. SATUAN UPAH KERJA BAHAN HARGA
ANALISIS
(Rp) (Rp) (Rp) (Rp)
PEKERJAAN LISTRIK
1 TITIK MENGERJAKAN INSTALASI LISTRIK
Kabel NYM (2x2,5) mm 16.0000 m 9,000.00 144,000.00 144,000.00
Klem Service Plastik 15.0000 Bh 600.00 9,000.00 9,000.00
Pipa Pvc 5/8" 1.0000 Btg - - -
Inbow Dos 1.0000 Bh 1,000.00 1,000.00 1,000.00
Las Dop 2.0000 Bh - - -
Isolasi 1.0000 Roll 4,000.00 4,000.00 4,000.00
T - Dos 5/8" 1.0000 Bh 1,000.00 1,000.00 1,000.00
Alat Bantu 1.0000 Ls 5,000.00 5,000.00 5,000.00
Tukang Instalatur 0.3000 oh 120,000.00 36,000.00 36,000.00
Pembantu Tukang 0.3000 oh 100,000.00 30,000.00 30,000.00
JUMLAH ( UPAH DAN BAHAN) Rp. 230,000.00
DI BULATKAN Rp. 230,000.00
1 titik memasang Sekering Kast /MCB
Sekring Kast 2 Group Outomatic 1.000 Bh 280,000.00 280,000.00 280,000.00
Kabel NYFGBY 4 X 6 mm 0.025 Roll 3,000,000.00 75,000.00 75,000.00
Pekerja 0.250 Oh 100,000.00 25,000.00 25,000.00
Tukang Listrik 0.350 Oh 120,000.00 42,000.00 42,000.00
JUMLAH ( UPAH DAN BAHAN) Rp. 422,000.00
DI BULATKAN Rp. 422,000.00
PEKERJAAN BETON DAN KERAMIK
1 m2 Membuat Beton Rangka Kawat Harmonika, 1 Pc : 3 Ps : 5 Kr (tebal, 5 cm)
Semen portland 10.000 Kg 2,100.00 21,000.00 21,000.00
Pasir beton 0.026 m3 300,000.00 7,800.00 7,800.00
Kerikil Beton 0.044 m3 360,000.00 15,840.00 15,840.00
Kawat Harmonika 1.100 m' 60,500.00 66,550.00 66,550.00
Pekerja 1.150 Oh 100,000.00 115,000.00 115,000.00
Tukang batu 0.020 Oh 120,000.00 2,400.00 2,400.00
Kepala tukang 0.002 Oh 150,000.00 300.00 300.00
Mandor 0.006 Oh 165,000.00 990.00 990.00
JUMLAH ( UPAH DAN BAHAN) Rp. 229,880.00
DI BULATKAN Rp. 229,800.00
1 m3 Membuat beton bertulang, 1 Pc : 2 Ps : 3 Kr
PC 336.0000 kg 2,100.00 705,600.00 705,600.00
Pasir beton 0.5400 m3 300,000.00 162,000.00 162,000.00
Kerikil beton 0.8100 m3 360,000.00 291,600.00 291,600.00
Tukang batu 0.3500 oh 120,000.00 42,000.00 42,000.00
Kepala tukang batu 0.0350 oh 150,000.00 5,250.00 5,250.00
Pekerja 2.0000 oh 100,000.00 200,000.00 200,000.00
Mandor 0.1000 oh 165,000.00 16,500.00 16,500.00
JUMLAH ( UPAH DAN BAHAN) Rp. 1,422,950.00
DI BULATKAN Rp. 1,422,900.00
1 kg Pembesian dengan besi polos
Besi beton polos 1.0500 kg 21,000.00 22,050.00 22,050.00
Kawat beton 0.0150 kg 30,000.00 450.00 450.00
Tukang besi 0.0070 oh 120,000.00 840.00 840.00
Kepala tukang besi 0.0007 oh 150,000.00 105.00 105.00
Pekerja 0.0070 oh 100,000.00 700.00 700.00
Mandor 0.0003 oh 165,000.00 49.50 49.50
JUMLAH ( UPAH DAN BAHAN) Rp. 24,194.50
DI BULATKAN Rp. 24,100.00
1 m3 Lantai Kerja
Beton 1 Pc : 2 Ps : 3 Kr 1.0000 m3 1,422,900.00 1,422,900.00
Besi Polos 59.8500 Kg 24,100.00 1,442,385.00
JUMLAH ( UPAH DAN BAHAN) Rp. 2,865,285.00
DI BULATKAN Rp. 2,865,200.00
Page 66 of 107
KODE ANALISA
HARGA HARGA JUMLAH
KOEF.
URAIAN PEKERJAAN SAT. SATUAN UPAH KERJA BAHAN HARGA
ANALISIS
(Rp) (Rp) (Rp) (Rp)
Page 67 of 107
KODE ANALISA
HARGA HARGA JUMLAH
KOEF.
URAIAN PEKERJAAN SAT. SATUAN UPAH KERJA BAHAN HARGA
ANALISIS
(Rp) (Rp) (Rp) (Rp)
Page 69 of 107
KODE ANALISA
HARGA HARGA JUMLAH
KOEF.
URAIAN PEKERJAAN SAT. SATUAN UPAH KERJA BAHAN HARGA
ANALISIS
(Rp) (Rp) (Rp) (Rp)
Page 70 of 107
KODE ANALISA
HARGA HARGA JUMLAH
KOEF.
URAIAN PEKERJAAN SAT. SATUAN UPAH KERJA BAHAN HARGA
ANALISIS
(Rp) (Rp) (Rp) (Rp)
Page 71 of 107
HARGA PERKIRAAN SENDIRI
KOEF.
URAIAN PEKERJAAN SAT. SATUAN UPAH KERJA BAHAN HARGA
ANALISIS
(Rp) (Rp) (Rp) (Rp)
I. PEKERJAAN PENDAHULUAN
1 Pengukuran dan pemasangan bouwplank per m'
Balok Kayu Meranti 0.0008 m3 3,499,900.00 2,694.92 2,694.92
Paku 0.0200 kg 25,000.00 500.00 500.00
Papan Kayu Meranti 0.0022 m3 3,619,200.00 7,962.24 7,962.24
Pekerja 0.0200 oh 170,000.00 3,400.00 3,400.00
Tukang 0.0400 oh 180,000.00 7,200.00 7,200.00
Kepala tukang 0.0080 oh 180,000.00 1,440.00 1,440.00
Mandor 0.0040 oh 200,000.00 800.00 800.00
JUMLAH ( UPAH DAN BAHAN) Rp. 23,997.16
OVERHEAD & PROFIT 10 % Rp. 2,399.72
JUMLAH 26,396.88
DI BULATKAN Rp. 26,300.00
II. PEKERJAAN STRUKTUR KAYU
1 1 Bh Pengadaan & Pemancangan Tiang Ulin 10/10
Balok Kayu Ulin 10/10 0.0154 m3 6,248,700.00 96,229.98 96,229.98
Pekerja 0.1250 oh 170,000.00 21,250.00 21,250.00
Tukang 0.1000 oh 180,000.00 18,000.00 18,000.00
Kepala tukang 0.0100 oh 180,000.00 1,800.00 1,800.00
Mandor 0.0130 oh 200,000.00 2,600.00 2,600.00
JUMLAH ( UPAH DAN BAHAN) Rp. 139,879.98
OVERHEAD & PROFIT 10 % Rp. 13,988.00
JUMLAH 153,867.98
DI BULATKAN Rp. 153,800.00
2 1 M3 Memasang Sunduk Ulin
Kayu Ulin 2/10 1.1000 m3 6,248,700.00 6,873,570.00 6,873,570.00
Pekerja 0.2500 oh 170,000.00 42,500.00 42,500.00
Pekerja 0.2000 oh 170,000.00 34,000.00 34,000.00
Tukang 0.0200 oh 180,000.00 3,600.00 3,600.00
Kepala tukang 0.0250 oh 180,000.00 4,500.00 4,500.00
JUMLAH ( UPAH DAN BAHAN) Rp. 6,958,170.00
OVERHEAD & PROFIT 10 % Rp. 695,817.00
JUMLAH 7,653,987.00
DI BULATKAN Rp. 7,653,900.00
3 1 M3 Memasang Kalang Ulin
Papan Kayu Ulin 1.1000 m3 6,643,400.00 7,307,740.00 7,307,740.00
Pekerja 0.0200 oh 170,000.00 3,400.00 3,400.00
Tukang 0.0200 oh 180,000.00 3,600.00 3,600.00
Kepala tukang 0.0200 oh 180,000.00 3,600.00 3,600.00
Mandor 0.0100 oh 200,000.00 2,000.00 2,000.00
JUMLAH ( UPAH DAN BAHAN) Rp. 7,320,340.00
OVERHEAD & PROFIT 10 % Rp. 732,034.00
JUMLAH 8,052,374.00
DI BULATKAN Rp. 8,052,300.00
Page 72 of 107
HARGA HARGA JUMLAH
ANALISA
KODE
KOEF.
URAIAN PEKERJAAN SAT. SATUAN UPAH KERJA BAHAN HARGA
ANALISIS
(Rp) (Rp) (Rp) (Rp)
Page 73 of 107
HARGA HARGA JUMLAH
ANALISA
KODE
KOEF.
URAIAN PEKERJAAN SAT. SATUAN UPAH KERJA BAHAN HARGA
ANALISIS
(Rp) (Rp) (Rp) (Rp)
Page 74 of 107
HARGA HARGA JUMLAH
ANALISA
KODE
KOEF.
URAIAN PEKERJAAN SAT. SATUAN UPAH KERJA BAHAN HARGA
ANALISIS
(Rp) (Rp) (Rp) (Rp)
Page 75 of 107
HARGA HARGA JUMLAH
ANALISA
KODE
KOEF.
URAIAN PEKERJAAN SAT. SATUAN UPAH KERJA BAHAN HARGA
ANALISIS
(Rp) (Rp) (Rp) (Rp)
Page 76 of 107
HARGA HARGA JUMLAH
ANALISA
KODE
KOEF.
URAIAN PEKERJAAN SAT. SATUAN UPAH KERJA BAHAN HARGA
ANALISIS
(Rp) (Rp) (Rp) (Rp)
Page 77 of 107
HARGA HARGA JUMLAH
ANALISA
KODE
KOEF.
URAIAN PEKERJAAN SAT. SATUAN UPAH KERJA BAHAN HARGA
ANALISIS
(Rp) (Rp) (Rp) (Rp)
Page 78 of 107
HARGA HARGA JUMLAH
ANALISA
KODE
KOEF.
URAIAN PEKERJAAN SAT. SATUAN UPAH KERJA BAHAN HARGA
ANALISIS
(Rp) (Rp) (Rp) (Rp)
Page 79 of 107
HARGA HARGA JUMLAH
ANALISA
KODE
KOEF.
URAIAN PEKERJAAN SAT. SATUAN UPAH KERJA BAHAN HARGA
ANALISIS
(Rp) (Rp) (Rp) (Rp)
Page 80 of 107
HARGA HARGA JUMLAH
ANALISA
KODE
KOEF.
URAIAN PEKERJAAN SAT. SATUAN UPAH KERJA BAHAN HARGA
ANALISIS
(Rp) (Rp) (Rp) (Rp)
JUMLAH 615,956.00
DI BULATKAN Rp. 615,900.00
Page 81 of 107
ANALISA HARGA MANAJEMEN KESELAMATAN KERJA
Kegiatan : PEMBANGUNAN RUANG LABORATORIUM KOMPUTER SDN 010 MUARA PAHU(DAK SD)
HARGA JUMLAH
No. URAIAN SATUAN VOLUME SATUAN HARGA Keterangan
(Rp.) (Rp.)
I. PENYIAPAN RKK
Penyusunan Dokumen RKK Laporan 1.00 150,000.00 150,000.00
Dituangkan dalam Penawaran
0.00
III. Asuransi dan Perizinan 0.00
1 Asuransi dan Perizinan Ls 1.00 460,000.00 460,000.00
0.00
IV. Alat Pelindung Diri 0.00
1 Helm bh 5.00 60,000.00 300,000.00
2 Rompi bh 5.00 25,000.00 125,000.00
3 Sarung Tangan Pasang 5.00 10,000.00 50,000.00
4 Safety Hardness bh 2.00 150,000.00 300,000.00
5 Police Line Roll 1.00 55,000.00 55,000.00
0.00
V. Personil 0.00
1 Petugas K3 0.00
0.00
VI. Fasilitas sarana kesehatan 0.00
1 Kotak dan Isi P3K Ls 1.00 200,000.00 200,000.00
0.00
2 Apar 6 Kg Bh - 500,000.00 0.00
TOTAL 1,640,000.00
BILL OF QUANTITY
DAFTAR HARGA SATUAN BAHAN & UPAH TENAGA KERJA
MASA PEMELIHARAAN
4 PEKERJAAN KUSEN, PINTU DAN JENDELA 9,252,133.00 4.4653 2.2 2.2
5 PEKERJAAN RANGKA ATAP DAN PENUTUP ATAP 34,596,360.00 16.6970 13.4 3.3
50
6 PEKERJAAN PLAFON 30,982,838.00 14.9530 3.7 11.2
12.5
25.5
15.7
11.2
0.9
3.5
2.6
2.6
2.6
4.8
9.5
8.6
BOBOT RENCANA (%)
100.0
12.1
17.0
29.5
55.0
70.7
81.9
91.4
0.9
4.3
6.9
9.5
BOBOT RENCANA KOMULATIF (%)
Dibuat Oleh
PT. ARISTA GEMILANG KONSULINDO
PAULUS PAGAPPONG, ST
Direktur Cabang
KEGIATAN
PEKERJAAN
LOKASI
TAHUN
5 Sloof, Balok Kayu Ulin 10/10 1.260 1.600 0.010 6.0000 0.0960
3.100 0.010 4.0000 0.1240
2.600 0.010 0.0000 -
13.000 0.010 8.0000 1.0400
1.2600
6 Balok, Balok Kayu Ulin 10/10 m3
7 Gelegar, Balok Kayu Ulin 5/10 & 10/10 2.331 m3 10.600 0.010 3.0000 0.3180
3.600 0.010 2.0000 0.0720
12.600 0.010 2.0000 0.2520
2.100 0.010 2.0000 0.0420
10.600 0.005 22.0000 1.1660
3.600 0.005 6.0000 0.1080
9.100 0.005 6.0000 0.2730
2.000 0.005 10.0000 0.1000
2.3310
8 Kolom, Balok Kayu Ulin 10/10 1.720 m3 4.0000 0.010 43.0000 1.7200
1.2000 0.010 0.0000 -
1.7200
9 Rangka Dinding, Balok Kayu Ulin 5/10 3.480
rangka vertikal penuh (4m) 4.0000 0.005 2.0000 26.0000 1.0400
rangka vertikal separuh
rangka horisontal penuh 46.450 0.005 2.0000 5.0000 2.3225
rangka horisontal separuh 5.200 0.005 2.0000 6.0000 0.3120 0.31
rangka vertikal partisi couple (dinding pembatas antar rumah) 4.0000 0.005 1.0000 6.0000 0.1200
rangka horisontal partisi couple (dinding pembatas antar rumah) 9.130 0.005 1.0000 5.0000 0.2283
4.0228
pengurang
atasjendela j2 1.150 0.005 2.0000 5.0000 0.0575
atas p1 2.700 0.005 2.0000 2.0000 0.0540
atas pj 4.200 0.005 2.0000 1.0000 0.0420
atas pj2 5.700 0.005 2.0000 1.0000 0.0570
atas p2 3.200 0.005 2.0000 1.0000 0.0320
bukaan teras dan void pintu 30.000 0.005 2.0000 1.0000 0.3000
0.5425
10 Ringbalk, Balok Kayu Ulin 10/10 1.253 m3 13.000 0.010 1.0000 0.1300
7.100 0.010 3.0000 0.2130
3.000 0.010 8.0000 0.2400
2.000 0.010 4.0000 0.0800
10.600 0.010 5.0000 0.5300
1.500 0.010 4.0000 0.0600
1.2530
11 Pekerjaan Tangga, Kayu Ulin
tiang 2.4100 0.015 3.0000 0.1085
anak tangga 0.9500 0.009 16.0000 0.1368
alas bordes 2.290 1.1000 0.0200 1.0000 0.0504
gelagar 1.100 0.010 3.0000 0.0330
tiang/tongkat 0.5000 0.010 6.0000 0.0300
sloef 2.290 0.010 2.0000 0.0458
0.4044
PENGURANGAN
- Ruang Tamu
PJ 3.2589 0.0000 2.0000 -
J2 2.0592 0.0000 2.0000 -
Bukaan Akses R. Tamu Ke R. Keluarga 1.7850 1.0000 2.0000 3.5700
- Ruang Tidur 1
J2 2.0592 0.0000 2.0000 -
P1 1.7850 0.0000 2.0000 -
- Ruang Tidur 2
J2 2.0592 0.0000 2.0000 -
P1 1.7850 0.0000 2.0000 -
- Ruang Keluarga
P1 1.7850 2.0000 2.0000 7.1400
P2 1.6800 1.0000 2.0000 3.3600
PJ2 3.9184 1.0000 2.0000 7.8368
Bukaan Akses R. Keluarga Ke dapur 1.7850 2.0000 2.0000 7.1400
- Dapur
J2 3.9184 0.0000 2.0000 -
Bukaan Akses R. Keluarga Ke dapur 1.7850 1.0000 2.0000 3.5700
- KM/WC
BV1 0.3000 0.0000 2.0000 -
P2 1.6800 0.0000 2.0000 -
Dinding Keramik warna 25/45 1.6000 5.7200 2.0000 18.3040
50.9208
5 List Dinding, kayu profil, Lebar 5 cm 257.900 m'
3.5000 35.0000 2.0000 245.0000
2.1500 3.0000 2.0000 12.9000
257.9000
PEKERJAAN PLAFON
1 Rangka langit-langit (60 x 120) m, kayu bengkirai 176.878 m2 13.140 1.0000 2.0000 26.2800
12.640 1.0000 2.0000 25.2800
Teras Depan 1.360 1.0000 2.0000 2.7200
R. Tamu 1.360 1.0000 2.0000 2.7200
2.860 2.860 2.0000 16.3592
R. Tidur 1 3.360 2.860 2.0000 19.2192
R. Tidur 2 3.360 2.860 2.0000 19.2192
R. Keluarga 5.360 3.360 2.0000 36.0192
KM/WC 1.860 1.3600 2.0000 5.0592
Dapur 2.860 2.860 2.0000 16.3592
Teras Belakang 1.980 1.930 2.0000 7.6428
176.8780
2 Langit2, Papan Kayu Meranti 176.878 m2
3 List plafond, kayu profil 205.500 m1
Luar 28.750 2.0000 57.5000
R. Tamu 13.500 2.0000 27.0000
R. Tidur 1 12.500 2.0000 25.0000
R. Tidur 2 12.500 2.0000 25.0000
R. Keluarga 17.500 2.0000 35.0000
KM/WC 6.500 2.0000 13.0000
Dapur 11.500 2.0000 23.0000
205.5000
PEKERJAAN LISTRIK
1 Instalasi kabel 35.000 ttk
2 Sekering Box / MCB 1.000 ttk 1.0000 1.0000
3 Stop Kontak 12.000 ttk 12.0000 12.0000
4 Saklar tunggal 8.000 ttk 8.0000 8.0000
5 Sakla ganda 4.000 ttk 4.0000 4.0000
6 Pas. Socket TV (Ruang ………...) 2.000 ttk 2.0000 2.0000
7 Lampu Down Light 23 Watt & Cap 20.000 Bh 20.0000 20.0000
PEKERJAAN FINISHING
1 Cat Plafon ( Cat Air )
2 Cat List ( Cat Minyak )
3 Cat Kusen ( Cat Minyak ) 43.531 M2
P1 2.560 0.2400 2.0000 4.0000 4.92
0.850 0.2400 2.0000 4.0000 1.63
P2 2.100 0.2400 2.0000 2.0000 2.02
0.800 0.2400 1.0000 2.0000 0.38
PJ1 2.560 0.2400 2.0000 2.0000 2.46
2.210 0.2400 1.0000 2.0000 1.06
1.370 0.2400 2.0000 2.0000 1.32
0.560 0.2400 1.0000 2.0000 0.27
PJ2 2.560 0.2400 2.0000 2.0000 2.46
1.840 0.2400 2.0000 2.0000 1.77
1.050 0.2400 1.0000 2.0000 0.50
1.760 0.2400 2.0000 2.0000 1.69
J2 1.760 0.2400 3.0000 10.0000 12.67
1.170 0.2400 3.0000 10.0000 8.42
BV1 0.600 0.2400 2.0000 2.0000 0.58
0.500 0.2400 2.0000 2.0000 0.48
BV2 0.500 0.2400 3.0000 1.0000 0.36
1.150 0.2400 2.0000 1.0000 0.55
43.5312
4 Cat Pintu ( Cat Minyak )
5 Cat Daun Jendela ( Cat Minyak ) 13.639 m²
PJ1 0.4600 1.6500 1.0000 2.0000 1.5180
PJ2 0.4600 1.2000 2.0000 2.0000 2.2080
J2 0.5200 1.2000 2.0000 10.0000 12.4800
16.2060
PENGURANGAN
PJ1 0.2950 1.4900 1.0000 2.0000 0.8791
PJ2 0.2950 1.0400 2.0000 2.0000 1.2272
J2 0.3500 1.0400 2.0000 10.0000 7.2800
9.3863
6 Cat Jalusi Mati ( Cat Minyak )
7 Cat Lisplang ( Cat Minyak )
8 Cat dinding Luar ( Cat Minyak ) 176.652
dinding keliling 3.4000 57.5100 195.5340
didning teras belakang dan depan 1.0000 8.9300 2.0000 17.8600
PENGURANGAN
J2 2.0592 10.0000 20.5920
BV1 0.3000 2.0000 0.6000
BV2 0.5750 2.0000 1.1500
pj 3.3400 2.0000 6.6800
pj2 3.8600 2.0000 7.7200
36.7420
PENGURANGAN
- Ruang Tamu
PJ 3.2589 1.0000 2.0000 6.5178
J2 2.0592 2.0000 2.0000 8.2368
Bukaan Akses R. Tamu Ke R. Keluarga 1.7850 1.0000 2.0000 3.5700
- Ruang Tidur 1
J2 2.0592 1.0000 2.0000 4.1184
P1 1.7850 1.0000 2.0000 3.5700
- Ruang Tidur 2
J2 2.0592 1.0000 2.0000 4.1184
P1 1.7850 1.0000 2.0000 3.5700
- Ruang Keluarga
P1 1.7850 2.0000 2.0000 7.1400
P2 1.6800 1.0000 2.0000 3.3600
PJ2 3.9184 1.0000 2.0000 7.8368
Bukaan Akses R. Keluarga Ke dapur 1.7850 2.0000 2.0000 7.1400
- Dapur
J2 3.9184 1.0000 2.0000 7.8368
Bukaan Akses R. Keluarga Ke dapur 1.7850 1.0000 2.0000 3.5700
- KM/WC
BV1 0.3000 1.0000 2.0000 0.6000
P2 1.6800 1.0000 2.0000 3.3600
0 1.6000 5.7200 2.0000 18.3040
92.8490
PEKERJAAN LAIN-LAIN
1 Pekerjaan Ralling, Besi Hollow 15.180 m1
1.400 7.0000 9.8000
1.880 2.0000 3.7600
0.810 2.0000 1.6200
2 Pas. Ornamen Pilar Depan 15.1800
BACK UP QUANTITY ARSITEKTUR
BACK UP QUANTITY MEKANIKAL ELEKTRIKAL
SANITARY LANTAI 1
1 CLOSET JONGKOK bh
3 KRAN AIR (ONDA) bh
4 KRAN WASTAFEL (ONDA) bh
5 WASHTAVEL bh
7 urinuoir bh
II PEKERJAAN PENERANGAN
LANTAI DASAR
1 Instalasi listrik dan stop kontak, NYM 3x2.5 mm2 ttk 15.0000
5 DOWN LIGTH PAR 38 18 W bh 21.0000
7 DOWN LIGTH PL 13 W bh 88.0000
9 Stop kontak bh 80.0000
10 Single Switch bh 5.0000
11 Doble Switch bh 80.0000
12 Grid Switch ( 6 gang ) bh 2.0000
LANTAI 1
1 Instalasi listrik dan stop kontak, NYM 3x2.5 mm2 ttk 46.0000
5 DOWN LIGTH PAR 38 18 W bh
7 DOWN LIGTH PL 13 W bh 178.0000
9 Stop kontak bh 164.0000
10 Single Switch bh 2.0000
11 Doble Switch bh 164.0000
12 Grid Switch ( 6 gang ) bh 2.0000
LOKASI
TAHUN
5 Sloof, Balok Kayu Ulin 10/10 0.688 4.600 0.010 1.0000 0.0460
7.600 0.010 7.0000 0.5320
6.200 0.010 1.0000 0.0620
1.600 0.010 3.0000 0.0480
0.6880
6 Balok, Balok Kayu Ulin 10/10 m3
7 Gelegar, Balok Kayu Ulin 5/10 & 10/10 1.200 m3 12.600 0.010 3.0000 0.3780
10.600 0.010 1.0000 0.1060
12.600 0.005 5.0000 0.3150
10.600 0.005 7.0000 0.3710
2.000 0.005 3.0000 0.0300
1.2000
8 Kolom, Balok Kayu Ulin 10/10 0.880 m3 4.0000 0.010 22.0000 0.8800
1.2000 0.010 0.0000 -
0.8800
9 Rangka Dinding, Balok Kayu Ulin 5/10 3.480
rangka vertikal penuh (4m) 4.0000 0.005 2.0000 26.0000 1.0400
rangka vertikal separuh
rangka horisontal penuh 46.450 0.005 2.0000 5.0000 2.3225
rangka horisontal separuh 5.200 0.005 2.0000 6.0000 0.3120 0.31
rangka vertikal partisi couple (dinding pembatas antar rumah) 4.0000 0.005 1.0000 6.0000 0.1200
rangka horisontal partisi couple (dinding pembatas antar rumah) 9.130 0.005 1.0000 5.0000 0.2283
4.0228
pengurang
atasjendela j2 1.150 0.005 2.0000 5.0000 0.0575
atas p1 2.700 0.005 2.0000 2.0000 0.0540
atas pj 4.200 0.005 2.0000 1.0000 0.0420
atas pj2 5.700 0.005 2.0000 1.0000 0.0570
atas p2 3.200 0.005 2.0000 1.0000 0.0320
bukaan teras dan void pintu 30.000 0.005 2.0000 1.0000 0.3000
0.5425
10 Ringbalk, Balok Kayu Ulin 10/10 1.253 m3 13.000 0.010 1.0000 0.1300
7.100 0.010 3.0000 0.2130
3.000 0.010 8.0000 0.2400
2.000 0.010 4.0000 0.0800
10.600 0.010 5.0000 0.5300
1.500 0.010 4.0000 0.0600
1.2530
11 Pekerjaan Tangga, Kayu Ulin
tiang 2.4100 0.015 3.0000 0.1085
anak tangga 0.9500 0.009 16.0000 0.1368
alas bordes 2.290 1.1000 0.0200 1.0000 0.0504
gelagar 1.100 0.010 3.0000 0.0330
tiang/tongkat 0.5000 0.010 6.0000 0.0300
sloef 2.290 0.010 2.0000 0.0458
0.4044
PENGURANGAN
- Ruang Tamu
PJ 3.2800 0.0000 1.0000 -
J2 2.0592 0.0000 1.0000 -
Bukaan Akses R. Tamu Ke R. Keluarga 1.7850 1.0000 1.0000 1.7850
- Ruang Tidur 1
J2 2.0592 0.0000 1.0000 -
P1 1.7850 0.0000 1.0000 -
- Ruang Tidur 2
J2 2.0592 0.0000 1.0000 -
P1 1.7850 0.0000 1.0000 -
- Ruang Keluarga
P1 1.7850 2.0000 1.0000 3.5700
P2 1.6800 1.0000 1.0000 1.6800
- KM/WC
Dinding Keramik warna 25/45 1.6000 1.9000 1.0000 3.0400
10.0750
5 List Dinding, kayu profil, Lebar 5 cm 257.900 m'
3.5000 35.0000 2.0000 245.0000
2.1500 3.0000 2.0000 12.9000
257.9000
5 Pekerjaan Lisplank Double, Balok Kayu Ulin 66.950 m² 3.200 4.0000 12.8000 Sambung Layang
2.250 1.0000 2.2500
1.650 2.0000 3.3000
2.150 4.0000 8.6000
12.500 2.0000 25.0000 Samp. Kiri & Kanan
15.000 1.0000 15.0000 Belakang
66.9500
6 Pasangan Atap Ex. Soka Jempol
7 Nok / Bubungan 10.000 4.0000 40.0000
2.750 1.0000 2.7500
4.500 2.0000 9.0000
51.7500
PEKERJAAN PLAFON
1 Rangka langit-langit (60 x 120) m, kayu bengkirai 176.878 m2 13.140 1.0000 2.0000 26.2800
12.640 1.0000 2.0000 25.2800
Teras Depan 1.360 1.0000 2.0000 2.7200
R. Tamu 1.360 1.0000 2.0000 2.7200
2.860 2.860 2.0000 16.3592
R. Tidur 1 3.360 2.860 2.0000 19.2192
R. Tidur 2 3.360 2.860 2.0000 19.2192
R. Keluarga 5.360 3.360 2.0000 36.0192
KM/WC 1.860 1.3600 2.0000 5.0592
Dapur 2.860 2.860 2.0000 16.3592
Teras Belakang 1.980 1.930 2.0000 7.6428
176.8780
2 Langit2, Papan Kayu Meranti 176.878 m2
3 List plafond, kayu profil 205.500 m1
Luar 28.750 2.0000 57.5000
R. Tamu 13.500 2.0000 27.0000
R. Tidur 1 12.500 2.0000 25.0000
R. Tidur 2 12.500 2.0000 25.0000
R. Keluarga 17.500 2.0000 35.0000
KM/WC 6.500 2.0000 13.0000
Dapur 11.500 2.0000 23.0000
205.5000
PEKERJAAN LISTRIK
1 Instalasi kabel 35.000 ttk
2 Sekering Box / MCB 1.000 ttk 1.0000 1.0000
3 Stop Kontak 12.000 ttk 12.0000 12.0000
4 Saklar tunggal 8.000 ttk 8.0000 8.0000
5 Sakla ganda 4.000 ttk 4.0000 4.0000
6 Pas. Socket TV (Ruang ………...) 2.000 ttk 2.0000 2.0000
7 Lampu Down Light 23 Watt & Cap 20.000 Bh 20.0000 20.0000
PEKERJAAN FINISHING
1 Cat Plafon ( Cat Air )
2 Cat List ( Cat Minyak )
3 Cat Kusen ( Cat Minyak ) 43.531 M2
P1 2.560 0.2400 2.0000 4.0000 4.92
0.850 0.2400 2.0000 4.0000 1.63
P2 2.100 0.2400 2.0000 2.0000 2.02
0.800 0.2400 1.0000 2.0000 0.38
PJ1 2.560 0.2400 2.0000 2.0000 2.46
2.210 0.2400 1.0000 2.0000 1.06
1.370 0.2400 2.0000 2.0000 1.32
0.560 0.2400 1.0000 2.0000 0.27
PJ2 2.560 0.2400 2.0000 2.0000 2.46
1.840 0.2400 2.0000 2.0000 1.77
1.050 0.2400 1.0000 2.0000 0.50
1.760 0.2400 2.0000 2.0000 1.69
J2 1.760 0.2400 3.0000 10.0000 12.67
1.170 0.2400 3.0000 10.0000 8.42
BV1 0.600 0.2400 2.0000 2.0000 0.58
0.500 0.2400 2.0000 2.0000 0.48
BV2 0.500 0.2400 3.0000 1.0000 0.36
1.150 0.2400 2.0000 1.0000 0.55
43.5312
4 Cat Pintu ( Cat Minyak )
5 Cat Daun Jendela ( Cat Minyak ) 13.639 m²
PJ1 0.4600 1.6500 1.0000 2.0000 1.5180
PJ2 0.4600 1.2000 2.0000 2.0000 2.2080
J2 0.5200 1.2000 2.0000 10.0000 12.4800
16.2060
PENGURANGAN
PJ1 0.2950 1.4900 1.0000 2.0000 0.8791
PJ2 0.2950 1.0400 2.0000 2.0000 1.2272
J2 0.3500 1.0400 2.0000 10.0000 7.2800
9.3863
6 Cat Jalusi Mati ( Cat Minyak )
7 Cat Lisplang ( Cat Minyak )
8 Cat dinding Luar ( Cat Minyak ) 176.652
dinding keliling 3.4000 57.5100 195.5340
didning teras belakang dan depan 1.0000 8.9300 2.0000 17.8600
PENGURANGAN
J2 2.0592 10.0000 20.5920
BV1 0.3000 2.0000 0.6000
BV2 0.5750 2.0000 1.1500
pj 3.3400 2.0000 6.6800
pj2 3.8600 2.0000 7.7200
36.7420
PENGURANGAN
- Ruang Tamu
P! 1.7850 1.0000 1.0000 1.7850
j1 1.3600 2.0000 1.0000 2.7200
vj.2 0.6600 2.0000
Bukaan Akses R. Tamu Ke R. Keluarga 1.7850 1.0000 1.0000 1.7850
- Ruang Tidur 1
J2 2.0592 1.0000 1.0000 2.0592
P1 1.7850 1.0000 1.0000 1.7850
- Ruang Tidur 2
J2 2.0592 1.0000 1.0000 2.0592
P1 1.7850 1.0000 1.0000 1.7850
- Ruang Keluarga
P1 1.7850 3.0000 1.0000 5.3550
P2 1.6800 1.0000 1.0000 1.6800
BV2 0.5750 1.0000 1.0000 0.5750
Bukaan Akses R. Keluarga Ke dapur 1.7850 1.0000 1.0000 1.7850
- KM/WC
BV1 0.3000 1.0000 1.0000 0.3000
P2 1.6800 1.0000 1.0000 1.6800
0 1.6000 5.7200 1.0000 9.1520
34.5054
PEKERJAAN LAIN-LAIN
1 Pekerjaan Ralling, Besi Hollow 15.180 m1
1.400 7.0000 9.8000
1.880 2.0000 3.7600
0.810 2.0000 1.6200
2 Pas. Ornamen Pilar Depan 15.1800
BACK UP QUANTITY ARSITEKTUR
BACK UP QUANTITY MEKANIKAL ELEKTRIKAL
II PEKERJAAN PENERANGAN
LANTAI DASAR
1 Instalasi listrik dan stop kontak, NYM 3x2.5 mm2 ttk 15.0000
5 DOWN LIGTH PAR 38 18 W bh 21.0000
7 DOWN LIGTH PL 13 W bh 88.0000
9 Stop kontak bh 80.0000
10 Single Switch bh 5.0000
11 Doble Switch bh 80.0000
12 Grid Switch ( 6 gang ) bh 2.0000
LANTAI 1
1 Instalasi listrik dan stop kontak, NYM 3x2.5 mm2 ttk 46.0000
5 DOWN LIGTH PAR 38 18 W bh
7 DOWN LIGTH PL 13 W bh 178.0000
9 Stop kontak bh 164.0000
10 Single Switch bh 2.0000
11 Doble Switch bh 164.0000
12 Grid Switch ( 6 gang ) bh 2.0000