Harga Satuan Biaya Upah Biaya Bahan Jumlah Harga


No Uraian Pekerjaan
Rp Rp Rp Rp
A PEKERJAAN PENDAHULUAN
1 1 M' Mengukur dan Memasang Bowplank
0.012 M3 Kayu Meranti Uk. 2/20 cm 3,400,000.00 40,800.00
0.007 M3 Kayu Meranti Kasau Uk. 5/7 cm 3,400,000.00 23,800.00
0.050 Kg Paku Biasa 25,000.00 1,250.00
0.100 ltr Cat Kayu 60,000.00 6,000.00
0.040 Oh Tukang 175,000.00 7,000.00
0.056 Oh Pekerja 140,000.00 7,840.00
0.003 Oh Mandor 195,000.00 585.00
Jumlah 15,425.00 71,850.00 87,275.00
2 1 M2 Pembersihan Lahan
0.0500 Oh Pekerja 140,000.00 7,000.00
0.0050 Oh Mandor 195,000.00 975.00
Jumlah 7,975.00 7,975.00
C PEKERJAAN KAYU
1 1 M3 PAPAN KALANG ULIN MENERUS DAN SUNDUK ULIN
1.0000 M3 Balok Ulin Uk. 5/10 + Papan Ulin Uk. 2/20 6,100,000.00 6,100,000.00
1.0000 Kg Paku Ulin 32,000.00 32,000.00
5.0000 Oh Pekerja 110,000.00 550,000.00
8.0000 Oh Tukang Kayu 175,000.00 1,400,000.00
1.5000 Oh Kep. Tukang 185,000.00 277,500.00
0.2500 Oh Mandor 195,000.00 48,750.00
Jumlah 1,726,250.00 6,682,000.00 8,408,250.00
12 Pancang Ulin 10/10 - 3 m
0.0300 M3 Kayu Ulin 10/10 5,500,000.00 165,000.00
1.0000 Ls Alat Pancang 25,000.00 25,000.00
0.0160 Oh Tukang 175,000.00 2,800.00
0.0650 Oh Kep. Tukang 185,000.00 12,025.00
0.1630 Oh Pekerja 140,000.00 22,820.00
0.0330 Oh Mandor 195,000.00 6,435.00
Jumlah 69,080.00 165,000.00 234,080.00
3 1 Titik Tongkat Ulin Panjang 4 M Untuk Halaman
0.0400 M3 Kayu Ulin 10/10 5,500,000.00 220,000.00
0.0033 m3 Kayu Ulin 5/10 5,500,000.00 18,150.00
0.0044 m3 Papan Ulin 2/20 6,100,000.00 26,840.00
0.4000 Oh Tukang 175,000.00 70,000.00
0.0400 Oh Kep. Tukang 185,000.00 7,400.00
0.5000 Oh Pekerja 140,000.00 70,000.00
0.1000 Oh Mandor 195,000.00 19,500.00
Jumlah 166,900.00 264,990.00 431,890.00
4 1 Titik Tongkat Ulin Panjang 3 M Untuk Halaman
0.0300 M3 Kayu Ulin 10/10 5,500,000.00 165,000.00
0.0033 m3 Kayu Ulin 5/10 5,500,000.00 18,150.00
0.0044 m3 Papan Ulin 2/20 6,100,000.00 26,840.00
0.4000 Oh Tukang 175,000.00 70,000.00
0.0400 Oh Kep. Tukang 185,000.00 7,400.00
0.5000 Oh Pekerja 140,000.00 70,000.00
0.1000 Oh Mandor 195,000.00 19,500.00
Jumlah 166,900.00 209,990.00 376,890.00
5 1 Titik Tongkat Ulin Panjang 2 M Untuk Halaman
0.0200 M3 Kayu Ulin 10/10 5,500,000.00 110,000.00
0.0033 m3 Kayu Ulin 5/10 5,500,000.00 18,150.00
0.0044 m3 Papan Ulin 2/20 6,100,000.00 26,840.00
0.4000 Oh Tukang 175,000.00 70,000.00
0.0400 Oh Kep. Tukang 185,000.00 7,400.00
0.5000 Oh Pekerja 140,000.00 70,000.00
0.1000 Oh Mandor 195,000.00 19,500.00
Jumlah 166,900.00 154,990.00 321,890.00
6 1 M3 Memgerjakan Sloof / Suai / Ring Balk Ulin 10/10
1.1000 M3 Balok Kayu Ulin 5,500,000.00 6,050,000.00
0.0500 Kg Paku Ulin 32,000.00 1,600.00
4.0000 Oh Tukang kayu 175,000.00 700,000.00
1.3000 Oh Kepala Tukang 185,000.00 240,500.00
3.0000 Oh Pekerja 140,000.00 420,000.00
0.3000 Oh Mandor 195,000.00 58,500.00
Jumlah 1,419,000.00 6,051,600.00 7,470,600.00
7 1 M3 Mengerjakan Gelagar Kayu Ulin 5/10
1.1000 M3 Balok kayu ulin 5,500,000.00 6,050,000.00
1.0000 Kg Paku ulin 32,000.00 32,000.00
4.0000 Oh Tukang kayu 175,000.00 700,000.00
1.3000 Oh Kep. Tukang 185,000.00 240,500.00
3.0000 Oh Pekerja 140,000.00 420,000.00
0.3000 Oh Mandor 195,000.00 58,500.00
Jumlah 1,419,000.00 6,082,000.00 7,501,000.00
DAFTAR ANALISA UPAH DAN BAHAN
KEGIATAN : PENGEMBANGAN ENERGI BARU DAN TERBARUKAN
PEKERJAAN :: PENYUSUNAN
PENYUSUNAN PERENCANAAN
PERENCANAAN STUDY
STUDY KELAYAKAN
KELAYAKAN PLTS
PLTS TERPUSAT
TERPUSAT
LOKASI PEKERJAAN : DESA :MINTA, KECAMATAN
DESA MINTA, PENYINGGAHAN
KECAMATAN KABUPATEN
PENYINGGAHAN KUTAI BARAT
KABUPATEN KUTAI BARAT
TAHUN ANGGARAN : 2016 : -2016

Harga Satuan Biaya Upah Biaya Bahan Jumlah Harga


No Uraian Pekerjaan
Rp Rp Rp Rp
8 1 M3 Mengerjakan Suai Kayu Ulin 5/10
1.1000 M3 Kayu Ulin 5,500,000.00 6,050,000.00
1.0000 Kg Sekrup 25,000.00 25,000.00
4.0000 Oh Tukang 175,000.00 700,000.00
1.3000 Oh Kep. tukang 185,000.00 240,500.00
3.0000 Oh Pekerja 140,000.00 420,000.00
0.3000 Oh Mandor 195,000.00 58,500.00
Jumlah 1,419,000.00 6,075,000.00 7,494,000.00
9 1 M3 Tiang Pokok Kayu Ulin
1.1000 M3 Kayu Ulin 5,500,000.00 6,050,000.00
2.0000 Kg Paku Biasa 25,000.00 50,000.00
8.0000 Oh Tukang 175,000.00 1,400,000.00
2.6000 Oh Kep. tukang 185,000.00 481,000.00
6.0000 Oh Pekerja 140,000.00 840,000.00
0.6000 Oh Mandor 195,000.00 117,000.00
Jumlah 2,838,000.00 6,100,000.00 8,938,000.00
10 1M2 Mengerjakan Rangka Dinding Kayu Kapur
0.0189 M3 Kayu Kapur,Balok 4,000,000.00 75,600.00
0.1500 KG Paku Biasa 2" - 5" 25,000.00 3,750.00
0.4500 Oh Tukang Kayu 175,000.00 78,750.00
0.0450 Oh Kepala Tukang 185,000.00 8,325.00
0.1500 Oh Pekerja 140,000.00 21,000.00
0.0080 Oh Mandor 195,000.00 1,560.00
109,635.00 79,350.00 188,985.00
11 1M' Mengerjakan Tangga Ulin
0.0330 M3 Papan Ulin 6,100,000.00 201,300.00
0.0210 M3 Balok Ulin 5,500,000.00 115,500.00
0.1000 KG Paku Biasa 2" - 5" 25,000.00 2,500.00
0.1500 Oh Tukang Kayu 175,000.00 26,250.00
0.0150 Oh Kepala Tukang 185,000.00 2,775.00
0.1000 Oh Pekerja 140,000.00 14,000.00
0.0080 Oh Mandor 195,000.00 1,560.00
44,585.00 319,300.00 363,885.00
12 1 M2 Dinding Papan Kayu Kapur
0.0200 M3 Papan Kapur 4,000,000.00 80,000.00
0.2000 Kg Paku biasa 25,000.00 5,000.00
0.1500 Oh Tukang 175,000.00 26,250.00
0.0150 Oh Kep. tukang 185,000.00 2,775.00
0.0500 Oh Pekerja 140,000.00 7,000.00
0.0026 Oh Mandor 195,000.00 507.00
Jumlah 36,532.00 85,000.00 121,532.00
13 1 M2 Papan kayu ulin untuk lantai
0.0220 M3 Papan Ulin 6,100,000.00 134,200.00
0.2000 Kg Paku 32,000.00 6,400.00
0.3600 Oh Tukang 175,000.00 63,000.00
0.0360 Oh Kep. tukang 185,000.00 6,660.00
0.3600 Oh Pekerja 140,000.00 50,400.00
0.0350 Oh Mandor 195,000.00 6,825.00
Jumlah 126,885.00 140,600.00 267,485.00
14 1 M2 Dinding Partisi Plywood
0.4200 Lbr Plywood 9 mm 160,000.00 67,200.00
0.2000 Kg Paku 32,000.00 6,400.00
0.1500 Oh Tukang 175,000.00 26,250.00
0.0150 Oh Kep. tukang 185,000.00 2,775.00
0.0500 Oh Pekerja 140,000.00 7,000.00
0.0026 Oh Mandor 195,000.00 507.00
Jumlah 36,532.00 73,600.00 110,132.00
D PEKERJAAN BETON
1 1 M3 Lantai Cor Rabat (camp 1 : 3 : 5)
0.8700 M3 Kerikil / Koral 750,000.00 652,500.00
0.5200 M3 Pasir Pasang 530,000.00 275,600.00
218.0000 Kg Semen 2,100.00 457,800.00
0.2500 Oh Tukang 175,000.00 43,750.00
0.0250 Oh Kep. Tukang 185,000.00 4,625.00
1.6500 Oh Pekerja 140,000.00 231,000.00
0.0800 Oh Mandor 195,000.00 15,600.00
Jumlah 294,975.00 1,385,900.00 1,680,875.00
DAFTAR ANALISA UPAH DAN BAHAN
KEGIATAN : PENGEMBANGAN ENERGI BARU DAN TERBARUKAN
PEKERJAAN :: PENYUSUNAN
PENYUSUNAN PERENCANAAN
PERENCANAAN STUDY
STUDY KELAYAKAN
KELAYAKAN PLTS
PLTS TERPUSAT
TERPUSAT
LOKASI PEKERJAAN : DESA :MINTA, KECAMATAN
DESA MINTA, PENYINGGAHAN
KECAMATAN KABUPATEN
PENYINGGAHAN KUTAI BARAT
KABUPATEN KUTAI BARAT
TAHUN ANGGARAN : 2016 : -2016

Harga Satuan Biaya Upah Biaya Bahan Jumlah Harga


No Uraian Pekerjaan
Rp Rp Rp Rp
2 1 M3 Cor Beton K-225
0.7756 M3 Kerikil / Koral 750,000.00 581,700.00
0.4986 M3 Pasir Pasang 530,000.00 264,258.00
371.0000 Kg Semen 2,100.00 779,100.00
1.0000 Oh Tukang 175,000.00 175,000.00
0.1000 Oh Kep. Tukang 185,000.00 18,500.00
6.0000 Oh Pekerja 140,000.00 840,000.00
0.3000 Oh Mandor 195,000.00 58,500.00
Jumlah 1,092,000.00 1,625,058.00 2,717,058.00
4 1 M2 Pasang Bekesting Untuk Sloof
0.0450 M3 Kayu Bekisting 3,400,000.00 153,000.00
0.3000 Kg Paku Biasa 25,000.00 7,500.00
0.1000 Ltr Minyak Bekesting 10,000.00 1,000.00
0.0260 Oh Tukang 175,000.00 4,550.00
0.0260 Oh Kep. Tukang 185,000.00 4,810.00
0.3000 Oh Pekerja 140,000.00 42,000.00
0.0050 Oh Mandor 195,000.00 975.00
Jumlah 52,335.00 161,500.00 213,835.00
5 1 M2 Pasang Bekesting Untuk Kolom
0.0950 M3 Kayu Bekisting 3,400,000.00 323,000.00
0.4000 Kg Paku Biasa 25,000.00 10,000.00
0.2000 Ltr Minyak Bekesting 10,000.00 2,000.00
0.3500 Lbr Plywood 6 mm 125,000.00 43,750.00
0.3300 Oh Tukang 175,000.00 57,750.00
0.0330 Oh Kep. Tukang 185,000.00 6,105.00
0.3000 Oh Pekerja 140,000.00 42,000.00
0.0060 Oh Mandor 195,000.00 1,170.00
Jumlah 107,025.00 378,750.00 485,775.00
6 1 M2 Pasang Bekesting Untuk Balok
0.0980 M3 Kayu Bekisting 3,400,000.00 333,200.00
0.4000 Kg Paku Biasa 25,000.00 10,000.00
0.2000 Ltr Minyak Bekesting 10,000.00 2,000.00
0.3500 Lbr Plywood 6 mm 125,000.00 43,750.00
0.3300 Oh Tukang 175,000.00 57,750.00
0.0330 Oh Kep. Tukang 185,000.00 6,105.00
0.3200 Oh Pekerja 140,000.00 44,800.00
0.0060 Oh Mandor 195,000.00 1,170.00
Jumlah 109,825.00 388,950.00 498,775.00
7 1 M2 Pasang Bekesting Untuk Plat Lantai
0.0550 M3 Kayu Bekisting 3,400,000.00 187,000.00
0.4000 Kg Paku Biasa 25,000.00 10,000.00
0.2000 Ltr Minyak Bekesting 10,000.00 2,000.00
0.3500 Lbr Plywood 6 mm 125,000.00 43,750.00
6.0000 Btg Dolken Kayu Galam Dia 8 15,000.00 90,000.00
0.3300 Oh Tukang 175,000.00 57,750.00
0.0330 Oh Kep. Tukang 185,000.00 6,105.00
0.6600 Oh Pekerja 140,000.00 92,400.00
0.0330 Oh Mandor 195,000.00 6,435.00
Jumlah 162,690.00 332,750.00 495,440.00
8 1 Kg Pembesian Dengan Besi Polos
1.0500 Kg Besi Beton Polos 20,000.00 21,000.00
0.0150 Kg Kawat Beton 45,000.00 675.00
0.0070 Oh Tukang 175,000.00 1,225.00
0.0007 Oh Kep. Tukang 185,000.00 129.50
0.0070 Oh Pekerja 140,000.00 980.00
0.0003 Oh Mandor 195,000.00 58.50
Jumlah 2,393.00 21,675.00 24,068.00
9 1 Kg Pembesian Dengan Besi Ulir
1.0500 Kg Besi Beton Polos 20,000.00 21,000.00
0.0150 Kg Kawat Beton 45,000.00 675.00
0.0070 Oh Tukang 175,000.00 1,225.00
0.0007 Oh Kep. Tukang 185,000.00 129.50
0.0070 Oh Pekerja 140,000.00 980.00
0.0003 Oh Mandor 195,000.00 58.50
Jumlah 2,393.00 21,675.00 24,068.00
K PEKERJAAN KERAMIK LANTAI & DINDING
1 1 M2 Pasangan Lantai Keramik 30/30
1.0000 M2 Keramik 30/30 Ex. Ikad 95,000.00 95,000.00
14.1500 Kg Semen 2,100.00 29,715.00
2.0000 Kg Semen Warna 3,480.00 6,960.00
0.0390 M3 Pasir Pasang 530,000.00 20,670.00
0.4000 Oh Tukang 175,000.00 70,000.00
0.0400 Oh Kep. Tukang 185,000.00 7,400.00
0.6000 Oh Pekerja 140,000.00 84,000.00
0.0130 Oh Mandor 195,000.00 2,535.00
Jumlah 163,935.00 152,345.00 316,280.00