JUMLAH Rp 484,994,923.23
DIBULATKAN Rp 484,994,000.00
Empat Ratus Delapan Puluh Empat Juta Sembilan Ratus Sembilan Puluh
Terbilang :
Empat Ribu Rupiah
PPKom
Rekapitulasi 1
ANALISA HARGA SATUAN PEKERJAAN KONSTRUKSI
10 1.00 m2 Memasang dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC : 5 PP
70.0000 bh Bata merah @ Rp. 725.00 50,750.00
9.6800 kg Portland Cement @ Rp. 950.00 9,196.00
0.0450 m3 Pasir Pasang @ Rp. 200,000.00 9,000.00
0.3000 oh Pekerja @ Rp. 63,000.00 18,900.00
0.1000 oh Tukang batu @ Rp. 75,000.00 7,500.00
0.0100 oh Kepala tukang @ Rp. 80,000.00 800.00
0.0150 oh Mandor @ Rp. 79,000.00 1,185.00
JUMLAH ( BELUM PPN ) 28,385.00 68,946.00 97,331.00
JASA 10 % 9,733.10
JUMLAH 107,064.10
DIBULATKAN 107,064.00
12 1.00 m3 Membuat lantai kerja beton mutu f’c = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87
230.0000 kg Portland Cement @ Rp. 950.00 218,500.00
0.6379 m3 Pasir beton @ Rp. 200,000.00 127,580.00
0.7607 m3 Koral beton @ Rp. 260,000.00 197,782.00
1.2000 oh Pekerja @ Rp. 63,000.00 75,600.00
0.2000 oh Tukang batu @ Rp. 75,000.00 15,000.00
0.0200 oh Kepala tukang @ Rp. 80,000.00 1,600.00
0.0600 oh Mandor @ Rp. 79,000.00 4,740.00
JUMLAH ( BELUM PPN ) 96,940.00 543,862.00 640,802.00
JASA 10 % 64,080.20
JUMLAH 704,882.20
DIBULATKAN 704,882.00
13 1.00 m3 Membuat beton mutu f’c = 19,3 MPa , slump (12 ± 2) cm, w/c = 0,58
371.0000 kg Portland Cement @ Rp. 950.00 352,450.00
0.4986 m3 Pasir beton @ Rp. 200,000.00 99,720.00
0.7756 m3 Koral beton @ Rp. 260,000.00 201,656.00
215.0000 Liter Air @ Rp. 38.00 8,170.00
1.6500 oh Pekerja @ Rp. 63,000.00 103,950.00
0.2750 oh Tukang batu @ Rp. 75,000.00 20,625.00
0.0280 oh Kepala tukang @ Rp. 80,000.00 2,240.00
0.0830 oh Mandor @ Rp. 79,000.00 6,557.00
JUMLAH ( BELUM PPN ) 141,542.00 653,826.00 795,368.00
JASA 10 % 79,536.80
JUMLAH 874,904.80
DIBULATKAN 874,904.00
14 1.00 m3 Membuat beton mutu f’c = 21,7 MPa (K 250), slump (12 ± 2) cm, w/c = 0,56
384.0000 kg Portland Cement @ Rp. 950.00 364,800.00
0.4943 m3 Pasir beton @ Rp. 200,000.00 98,860.00
0.7696 m3 Koral beton @ Rp. 260,000.00 200,096.00
215.0000 Liter Air @ Rp. 38.00 8,170.00
1.6500 oh Pekerja @ Rp. 63,000.00 103,950.00
0.2750 oh Tukang batu @ Rp. 75,000.00 20,625.00
0.0280 oh Kepala tukang @ Rp. 80,000.00 2,240.00
0.0830 oh Mandor @ Rp. 79,000.00 6,557.00
JUMLAH ( BELUM PPN ) 141,542.00 663,756.00 805,298.00
JASA 10 % 80,529.80
JUMLAH 885,827.80
DIBULATKAN 885,827.00
29 1.0000 m2 Memasang Bak Kontrol Pasangan Batu Bata Ukuran 60X60 cm,t=65cm
222.0000 bh Bata merah @ Rp. 725.00 160,950.00
114.0000 kg Portland Cement @ Rp. 950.00 108,300.00
0.1840 m3 Pasir Pasang @ Rp. 200,000.00 36,800.00
0.0330 m3 Batu Krikil @ Rp. 260,000.00 8,580.00
4.8500 kg Besi beton polos @ Rp. 8,250.00 40,012.50
0.1200 m3 Pasir beton @ Rp. 200,000.00 24,000.00
2.1600 oh Pekerja @ Rp. 63,000.00 136,080.00
0.7200 oh Tukang batu @ Rp. 75,000.00 54,000.00
0.0720 oh Kepala tukang @ Rp. 80,000.00 5,760.00
0.1080 oh Mandor @ Rp. 79,000.00 8,532.00
0.1000 oh Tukang Gali @ Rp. 63,000.00 6,300.00
JUMLAH ( BELUM PPN ) 210,672.00 378,642.50 589,314.50
JASA 10 % 58,931.45
JUMLAH 648,245.95
DIBULATKAN 648,245.00
Upah 6
DAFTAR HARGA SATUAN BAHAN BANGUNAN TERTINGGI
Bahan 7
B. PEKERJAAN PASANGAN
1 Membuat thrust block dengan beton mutu atau K225
2 Memasang Pipa Galvanis SCH 3 inch
3 Memasang Pipa Galvanis SCH 4 inch
4 Pengadaan dan Pemasangan Hydrant Pilar One Way dua setengah inchi
5 Pemasangan Dan Pengadaan Hydrant Box Outdoor
a Fire Hose satu setengah inchi x 30 mtr dengan Machino Coupling
b Hose rack satu setengah inchi
c Nozzle jet Machino coupling satu setengah inchi
d Hydrant Valve satu setengah inchi
e Hidrant Valve dua setengah inchi
6 Check Valve 4 inchi
7 Siamese Connection S11
8 Gate Valve 4 inchi
9 Pembuatan Bak kontrol untuk Gate Valve
Pipa Galvanis SCH 40 3" m1 170,167
Pipa Galvanis SCH 40 4" m1 242,000
Check Valve 4" merk Toyo, Kitz, Kokai bh 3,050,000
Gate Valve 4" merk Toyo, Kitz, Kokai bh 2,200,000
Hidran Pilar One Way 2.5" merk Gunnebo / unit 5,830,000
Siamese Connection S11 material Cooper bh 3,450,000
Hydran box Outdoor dengan kunci merk Gu unit 2,215,000
Fire Hose 1,5 x 30 mtr Machino Coupling unit 1,210,000
Hose rack 1,5” Material Copper unit 380,000
Nozzle Jet Machino cpl 1,5” Material Copp unit 435,000
Hydrant Valve 1.5" material Copper merk unit 460,000
Hidrant Valve 2,5" material Copper merk unit 970,000
KURVA-S TIME SCHEDULE
B. PEKERJAAN PASANGAN
1 Membuat thrust block dengan beton mutu atau K225 0.32% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05%
2 Memasang Pipa Galvanis SCH 3 inch 34.60% 5.77% 5.77% 5.77% 5.77% 5.77% 5.77%
3 Memasang Pipa Galvanis SCH 4 inch 32.57% 8.14% 8.14% 8.14% 8.14%
4 Pengadaan dan Pemasangan Hydrant Pilar One Way dua setengah inchi 1.25% 1.25%
5 Pemasangan Dan Pengadaan Hydrant Box Outdoor 6.91% 1.73% 1.73% 1.73% 1.73%
a Fire Hose satu setengah inchi x 30 mtr dengan Machino Coupling 3.65% 0.91% 0.91% 0.91% 0.91%
b Hose rack satu setengah inchi 0.95% 0.24% 0.24% 0.24% 0.24%
c Nozzle jet Machino coupling satu setengah inchi 1.27% 0.32% 0.32% 0.32% 0.32%
d Hydrant Valve satu setengah inchi 1.35% 0.34% 0.34% 0.34% 0.34%
e Hidrant Valve dua setengah inchi 3.02% 0.75% 0.75% 0.75% 0.75%
6 Check Valve 4 inchi 0.69% 0.17% 0.17% 0.17% 0.17%
7 Siamese Connection S11 0.78% 0.20% 0.20% 0.20% 0.20%
8 Gate Valve 4 inchi 1.50% 0.50% 0.50% 0.50%
9 Pembuatan Bak kontrol untuk Gate Valve 0.44% 0.11% 0.11% 0.11% 0.11%
0.17% 8.49% 9.26% 9.30% 0.00% 0.00% 9.17% 8.77% 11.45% 6.90% 11.45% 6.79% 11.40% 5.34% 0.87% 0.61%
0.17% 8.66% 17.92% 27.22% 27.22% 27.22% 36.39% 45.17% 56.62% 63.52% 74.97% 81.77% 93.17% 98.51% 99.39% 100.00%
Rincian 10
JADWAL PERALATAN
KEGIATAN : PENCEGAHAN BAHAYA KEBAKARAN
PEKERJAAN : KONSTRUKSI HIDRAN KAMPUNG PATHUK
LOKASI : KAMPUNG PATHUK, KELURAHAN NGAMPILAN, KECAMATAN NGAMPILAN
INSTANSI : DINAS KEBAKARAN KOTA YOGYAKARTA
TAHUN : 2017
MASA PELAKSANAAN
NO Daftar Peralatan Qty
1 2 3 4 Libur Lebaran 7 8 9 10 11 12
1 Stemper 1 ● ● ● ● ● ● ● ● ● ●
2 Mesin Las 1 ● ● ● ● ● ● ● ● ● ●
3 Gerinda 1 ● ● ● ● ● ● ● ● ● ●
4 Genset 1 ● ● ● ● ● ● ● ● ● ●
5 Alat Test Pipa 1
AGUS SUPRIYANTO, SE
Direktur
JADWAL PERSONIL
KEGIATAN : PENCEGAHAN BAHAYA KEBAKARAN
PEKERJAAN : KONSTRUKSI HIDRAN KAMPUNG PATHUK
LOKASI : KAMPUNG PATHUK, KELURAHAN NGAMPILAN, KECAMATAN NGAMPILAN
INSTANSI : DINAS KEBAKARAN KOTA YOGYAKARTA
TAHUN : 2017
MASA PELAKSANAAN
NO NAMA PERSONIL POSISI
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
4 xxxxxxxxxx Administrasi ● ● ● ● x x ● ● ● ● ● ● ● ● ●
5 xxxxxxxxxxxxx Drafter ● ● ● ● x x ● ● ● ● ● ● ● ● ●
AGUS SUPRIYANTO, SE
Direktur
16