Anda di halaman 1dari 4

A.

RENCANA ANGGARAN BIAYA RUKO 3 LANTAI

Harga Jumlah
N URAIAN PEKERJAAN Volume satuan
Satuan Harga
o
I PEKERJAAN PONDASI
1 Direlasi keet/gudang/los kerja 1.00 unit 600,000 Rp. 600,000
2 Uitzet/pasang bouwplank 16.00 m' 30,000 Rp. 480,000
3 Mobilisasi / Demobilisasi ls 2,500,000 Rp. 2,500,000
4 Galian Tanah 128.78 m
3 30,000 Rp. 3,863,400
5 Urugan tanah kembali 104.54 m
3 20,000 Rp. 2,090,800
6 Pasir Urug tebal 5 cm 2.53 m
3 125,000 Rp. 316,250
6 Lantai kerja (beton mutu Bo) t=5 cm 1.13 m
3 600,000 Rp. 675,000
7 Pasangan batu kali (di bwh sloof) 24.24 m
3 450,000 Rp. 10,908,000
Total Pekerjaan Fondasi 278.22 m
3 Rp. 21,433,450
II PEKERJAAN BETON
1 Pondasi tapak (1,5x1,5m) 3.38 m
3 3,350,000 Rp. 11,306,250
2 Pondasi tapak (1,5x2,3m) 1.13 m
3 3,350,000 Rp. 3,768,750
3 Pekerjaan Sloof 20/40 4.04 m
3 3,350,000 Rp. 13,534,000
4 Pekerjaan Sloof 15/30 0.20 m
3 3,350,000 Rp. 678,375
5 Balok B1 25/40 10.10 m
3 3,450,000 Rp. 34,845,000
6 Balok B2 20/40 0.72 m
3 3,450,000 Rp. 2,484,000
7 Balok B4 15/30 0.14 m
3 3,350,000 Rp. 452,250
8 Balok B5 15/15 (Ringbalk) 0.83 m
3 2,250,000 Rp. 1,873,125
9 Kolom K1 (35/35) 5.51 m
3 3,800,000 Rp. 20,947,500
10 Kolom K2 (30/30) 1.80 m
3 3,800,000 Rp. 6,840,000
11 Kolom K3 15/30 0.28 m
3 3,600,000 Rp. 1,004,400
12 Kolom KP 15/15 0.42 m
3 2,250,000 Rp. 941,625
13 Plat t=12cm 14.04 m
3 3,225,000 Rp. 45,279,000
14 Tangga Beton 2.38 3 4,200,000 Rp. 10,006,920
m
Total Pekerjaan Beton 44.96 m
3 Rp. 153,961,195
III PEKERJAAN DINDING
1 Pasangan bata (1pc:5 ps) 362.70 m
2 68,000 Rp. 24,663,600
2 Sopi sopi bata (1 pc :5 ps) 22.00 m
2 72,000 Rp. 1,584,000
3 Plester dinding bata (1pc:5ps)+acian 362.70 m
2 32,500 Rp. 11,787,750
Total Pekerjaan Dinding Rp. 38,035,350
IV PEKERJAAN LANTAI
1 Pasangan keramik lantai 30x30 189.00 m
2 72,000 Rp. 13,608,000
2 Pasangan keramik lt kamar mandi 20x20 9.00 m
2 74,000 Rp. 666,000
Pasangan keramik dinding kamar mandi 20x20 39.00 m
2 76,000 Rp. 2,964,000
3 Border keramik 10x20 3.90 m
2 148,000 Rp. 577,200
4 Border keramik teras 10x20 1.12 m
2 148,000 Rp. 165,760
5 Urugan Pasir padat t.5 cm 3.15 m
3 125,000 Rp. 393,750
Total Pekerjaan Lantai Rp. 18,374,710
V PEKERJAAN KUSEN,PINTU,JENDELA, BOVENLICH,
KACA
1 Jendela Muka lt.2+kaca (kusen alu 4/10) 1.00 unit 9,000,000 Rp. 9,000,000
2 Jendela Muka lt.3+kaca (kusen alu 4/10) 1.00 unit 9,000,000 Rp. 9,000,000
3 Pintu toilet+daun 3.00 unit 400,000 Rp. 1,200,000
Total Pekerjaan Kusen, Pintu, Jendela, Bovenlich, Kaca Rp. 19,200,000
VI PEKERJAAN ATAP & PLAFOND
1 Balok kayu uk. 8/12 Meranti 0.22 m
3 3,600,000 Rp. 777,600
2 Kaso 5/7 0.19 m
3 3,700,000 Rp. 699,300
3 papan lisplank 3/20,kayu Meranti 9.00 m' 95,000 Rp. 855,000
4 Asbes 63.00 m
2 65,000 Rp. 4,095,000
5 Asbes nok 4.50 m' 70,000 Rp. 315,000
6 Plafond Gypsum 162.00 m
2 65,000 Rp. 10,530,000
7 Lis profil Plafond Gypsum 111.00 m' 24,000 Rp. 2,664,000
8 Tripleks 4 mm plafond (Toilet) 9.00 m
2 67,000 Rp. 603,000
9 List Plafond Kayu (toilet) 21.00 m' 20,000 Rp. 420,000
Total Pekerjaan Atap & Plafond Rp. 20,958,900
VII PEKERJAAN PENGECATAN
1 Cat dinding 362.70 m
2 18,000 Rp. 6,528,600
2 Cat plafond 171.00 m
2 19,000 Rp. 3,249,000
3 Cat List plafond 132.00 m' 12,000 Rp. 1,584,000
Total Pekerjaan Pengecatan Rp. 11,361,600
VII PEKERJAAN INSTALASI AIR BERSIH & AIR KOTOR
I
1 Pipa PVC diameter 1/2" 2.00 m' 7,000 Rp. 14,000
Pipa PVC diameter 3/4" 23.00 m' 10,000 Rp. 230,000
2 Pipa PVC diameter 3'(air bekas) 22.50 m' 30,000 Rp. 675,000
3 Pipa PVC diameter 4'(dari kloset) 23.00 m' 50,000 Rp. 1,150,000
4 Septik tank + rembesan 1.00 unit 1,750,000 Rp. 1,750,000
5 Sumur Pantek 1.00 Ls 2,000,000 Rp. 2,000,000
6 Pompa LG250W 1.00 bh 2,000,000 Rp. 2,000,000
7 Bak kontrol 1.00 bh 280,000 Rp. 280,000
8 Biaya Penyambungan PAM Ls 2,000,000 Rp. 2,000,000
Total Pekerjaan Instalasi Air Bersih & Air Kotor Rp. 10,099,000
IX PEKERJAAN SANITAIR
1 Kloset jongkok merek Ex. KIA 3.00 bh 150,000 Rp. 450,000
2 Bak air fibre glass uk. 60x60x60 3.00 bh 200,000 Rp. 600,000
3 keran air merek SAN-EI 9.00 bh 100,000 Rp. 900,000
4 Roof Drain 2.00 bh 80,000 Rp. 160,000
5 Floor drain 3.00 bh 70,000 Rp. 210,000
Total Pekerjaan Sanitair Rp. 2,320,000
X PEKERJAAN LAIN-LAIN
1 Railing besi tangga+Void 10.70 m' 85,000 Rp. 909,500
2 Fin. Kolom depan 9.00 m
2 175,000 Rp. 1,575,000
3 Folding Gate 1.00 ls 6,000,000 Rp. 6,000,000
4 Parkir, Koral sikat motif 27.00 m
2 270,000 Rp. 7,290,000
Total Pekerjaan Lain-Lain Rp. 15,774,500
XI PEKERJAAN INSTALASI LISTRIK
1 Box MCB 2.00 bh 300,000 Rp. 600,000
2 Box meter 1.00 bh 500,000 Rp. 500,000
3 Titik lampu Termasuk Kabel NYM3x2.5 10.00 bh 170,000 Rp. 1,700,000
NYM 2x1.5 & Fitting+Inbow+Tee dus (Acessories)
4 Lampu tempel 2.00 bh 400,000 Rp. 800,000
5 Saklar dobel 4.00 bh 80,000 Rp. 320,000
6 Saklar Singel 4.00 bh 50,000 Rp. 200,000
7 Stop kontak 4.00 bh 50,000 Rp. 200,000
8 Biaya Penyambungan Daya Listrik Ls 2,500,000 Rp. 2,500,000
Total Pekerjaan Instalasi Listrik Rp. 6,820,000
Rekapitulasi RAB Ruko 3 Lantai :
I PEKERJAAN PERSIAPAN/ PONDASI Rp. 21,433,450
II PEKERJAAN BETON Rp. 153,961,195
III PEKERJAAN DINDING Rp. 38,035,350
IV PEKERJAAN LANTAI Rp. 18,374,710
V PEKERJAAN KUSEN,PINTU,JENDELA, BOVENLICH, KACA Rp. 19,200,000
VI PEKERJAAN ATAP & PLAFOND Rp. 20,958,900
VII PEKERJAAN PENGECATAN Rp. 11,361,600
VIII BIAYA PENYAMBUNGAN PAM ls Rp.2.000.000 Rp. 10,099,000
IX BIAYA PENYAMBUNGAN DAYA LISTRIK ls Rp.2.500.000 Rp. 2,320,000
X PEKERJAAN LAIN-LAIN Rp. 15,774,500
XI PEKERJAAN INSTALASI LISTRIK Rp. 6,820,000
TOTAL Rp. 318,338,705