RENCANA ANGGARAN BIAYA

Instansi : Pondok Pesantren Haji Ya'qub


Nama Paket : Pembangunan Asrama Santri ( 2 Kamar )

HARGA JUMLAH
NO. URAIAN PEKERJAAN VOLUME SAT. SATUAN HARGA
(Rp.) (Rp.)
1 2 3 4 6 7
I PEKERJAAN PERSIAPAN
1 Pembersihan Lapangan 84.00 m2 7,000.00 588,000.00
2 Pengukuran dan Pemasangan Bowplank 84.00 m2 51,900.00 4,359,600.00
Sub Jumlah 4,947,600.00
II PEKERJAAN STRUKTUR BAWAH
A PEKERJAAN TANAH DAN PONDASI
1 Pondasi Tapak Type P1 = 12 Unit
Galian Tanah Pondasi 21.60 m3 63,000.00 1,360,800.00
Urugan Kembali Bekas Galian 4.32 m3 35,000.00 151,200.00
Urugan Pasir Alas Pondasi t = 5 cm 0.43 m3 169,800.00 73,353.60
Pasangan Batu Kosong t = 10 cm 0.86 m3 365,268.00 315,591.55
Plat Pondasi Tapak Ukuran 120 x 20 cm
- Pembesian 10-10 plat 10 - 10 212.49 kg 14,575.00 3,097,111.71
- Beton K-225 4.32 m3 950,668.50 4,106,887.92
Kolom K1 dibawah sloof Ukuran 30x40
- Beton K-225 1.80 m3 950,668.50 1,711,203.30
- Pembesian 12D16 205.16 kg 15,100.00 3,097,867.68
- sengkang Ø8-10 cm 75.25 Kg 14,575.00 3,097,111.71
- Bekisting 16.80 m2 168,128.00 4,106,887.92
2 Pondasi Tapak Type P2 = 7 Unit
Galian Tanah Pondasi 6.00 m3 63,000.00 378,000.00
Urugan Kembali Bekas Galian 1.50 m3 35,000.00 52,500.00
Urugan Pasir Alas Pondasi t = 5 cm 0.15 m3 169,800.00 25,470.00
Pasangan Batu Kosong t = 10 cm 0.30 m3 365,268.00 109,580.40
Plat Pondasi Tapak Ukuran 80 x 80 cm
- Pembesian Ø8-10 plat Ø8-10 67.23 kg 14,575.00 979,852.76
- Beton K-225 0.90 m3 950,668.50 855,601.65
Kolom K2 dibawah sloof Ukuran 30x30
- Beton K-225 1.45 m3 950,668.50 1,377,518.66
- Pembesian 8D16 117.78 kg 15,100.00 1,778,405.52
- sengkang Ø8-10 cm 31.70 Kg 14,575.00 462,009.28
- Bekisting 7.20 m2 168,128.00 1,210,521.60

4 Pondasi Menerus
Galian Tanah Pondasi Menerus 42.24 m3 52,500.00 2,217,600.00
Urugan Kembali Bekas Galian 13.73 m3 35,000.00 480,480.00
Urugan Pasir Alas Pondasi T = 5 cm 3.30 m3 169,800.00 560,340.00
Pasangan Batu Kosong Pondasi T =10 cm 6.60 m3 365,268.00 2,410,768.80
Pasangan Batu Gunung 1 : 4 33.00 m3 743,690.00 24,541,770.00
Sub Jumlah 58,558,434.06
III PEKERJAAN LANTAI I
PEKERJAAN PASANGAN DAN
A
PLESTERAN
1 Pasangan Dinding Bata 1 : 4 139.87 m2 216,678.50 30,307,428.49
2 Plesteran Dinding Bata 1 : 4 279.75 m2 65,008.00 18,185,701.96
3 Plesteran 1 : 3 (Kolom dan Balok) 103.95 m2 50,766.20 5,277,146.49
Sub Jumlah 53,770,276.95
B PEKERJAAN BETON BERTULANG
Sloof Beton 25/40 cm (Pondasi
1
Menerus)
- Beton K-225 4.30 m3 950,668.50 4,087,874.55
- Pembesian 8D16 543.52 kg 15,100.00 8,207,152.00
- Pembesian 4-Ø12 153.08 Kg 14,575.00 2,231,141.00
- sengkang Ø8-10cm 196.21 Kg 14,575.00 2,859,746.18
- Bekisting 34.40 m2 49,321.00 1,696,642.40
2 Sloof Beton15/20 cm (Selasar Depan)
- Beton K-225 0.29 m3 950,668.50 270,940.52
- Pembesian 4-Ø12 33.82 m3 14,575.00 492,926.50
- sengkang Ø8-10cm 21.12 m3 14,575.00 307,802.14
- Bekisting 3.80 m2 49,321.00 187,419.80
3 Kolom Beton 30/40 cm (K1)
- Beton K-225 2.88 m3 950,668.50 2,737,925.28
- Pembesian 12D16 524.29 kg 15,100.00 7,916,772.96
- sengkang Ø8-10 cm 138.46 Kg 14,575.00 2,017,987.46
- Bekisting 33.60 m2 114,999.55 3,863,984.95
4 Kolom Beton 30/30 cm (K2)
- Beton K-225 1.08 m3 950,668.50 1,026,721.98
- Pembesian 8D16 174.76 kg 15,100.00 2,638,924.32
- sengkang 8-10 cm 58.33 Kg 14,575.00 850,097.08
- Bekisting 14.40 m2 114,999.55 1,655,993.55
5 Balok Lantai 25/50 cm (B1)
- Beton K-225 6.75 m3 950,668.50 6,417,012.38
- Pembesian 10D16 948.00 kg 15,100.00 14,314,800.00
- sengkang 8-10 cm 320.58 Kg 14,575.00 4,672,453.50
- Bekisting 72.00 m2 151,437.00 10,903,464.00
6 Balok Lantai 15/30 cm (B2)
- Beton K-225 0.28 m3 950,668.50 267,375.52
- Pembesian 8D16 158.00 kg 15,100.00 2,385,800.00
- sengkang 8-10 cm 37.54 Kg 14,575.00 547,109.06
- Bekisting 5.63 m2 151,437.00 851,833.13
7 Plat Lantai T = 12 cm
- Beton K-225 13.80 m3 950,668.50 13,119,225.30
- Pembesian Ø10-10,Ø10-10 1,140.80 kg 15,100.00 17,226,080.00
- Bekisting 92.00 m2 341,040.00 31,375,680.00
Sub Jumlah 145,130,885.53
C PEKERJAAN LANTAI
1 Rabat Beton Lantai T = 5 cm 2.52 m3 807,650.00 2,035,278.00
2 Lantai Keramik 50 x 50 cm (polished) 72.00 m2 131,625.00 9,477,000.00
3 Lantai Keramik 50 x 50 cm (unpolished) 12.00 m2 131,625.00 1,579,500.00
Sub Jumlah 13,091,778.00
PEKERJAAN KOSEN PINTU DAN
D
JENDELA
KOSEN
1 Kusen Pintu P1 (2 Unit) 2.00 Ls 650,000.00 1,300,000.00
2 Kusen Jendela P1 (4 Unit) 8.00 Ls 450,000.00 3,600,000.00
DAUN PINTU DAN JENDELA
1 Pintu Type A (2 Unit)
Daun Pintu kayu Ukuran 9 x 200 cm 2.00 Ls 900,000.00 1,800,000.00
2 Jendela Type B (4 Unit)
Daun Jendela Kaca 5 mm Ukuran 60 x
4.00 ls 300,000.00 1,200,000.00
88 cm
Sub Jumlah 7,900,000.00
PEKERJAAN PENGUNCI DAN
E
PENGGANTUNG
1 Kunci Tanam 2 Slaag 2.00 Set 350,000.00 700,000.00
2 Engsel Pintu 4 Inchi 12.00 Bh 50,000.00 600,000.00
3 Slot Pintu 2.00 Bh 50,000.00 100,000.00
4 Engsel Jendela 3 Inchi 8.00 Bh 20,000.00 160,000.00
5 Grendel Jendela 4.00 Bh 16,000.00 64,000.00
6 Hak Angin Jendela 8.00 Bh 20,000.00 160,000.00
7 Tarikan/Pegangan Jendela 4.00 Bh 20,000.00 80,000.00
Sub Jumlah 1,864,000.00
F PEKERJAAN PENGECATAN
1 Cat Tembok 3 x (L/D) 231.91 M2 28,970.00 6,718,406.70
2 Cat Langit- Langit Plat Beton 76.36 M2 28,970.00 2,212,149.20
3 Cat Mengkilat Kosen Pintu/Jendela 16.00 M2 40,000.00 640,000.00
4 Cat Mengkilat Daun Pintu/Jendela/Jalusi 19.00 M2 40,000.00 760,000.00
Sub Jumlah 10,330,555.90
G PEKERJAAN INSTALASI LISTRIK
1 Box Zekering/Panel MCB 1.00 Unit 165,000.00 165,000.00
2 Armatur
Lampu 10 Watt setara Philips 3.00 Bh 42,000.00 126,000.00
Lampu15 Watt Setara Philips 12.00 Bh 52,000.00 624,000.00
Instalasi titik penerangan, instalasi
termasuk kabel NYA 2,5 mm dalam
3 15.00 Ttk 185,000.00 2,775,000.00
pipa PVC fitting lampu dan kelengkapan
instalasi terpasang
Instalasi titik kontak, instalasi termasuk
kabel NYA 2,5 mm dalam pipa PVC,
4 3.00 Bh 185,000.00 555,000.00
kotak stop kontak dan kelengkapan
instalasi terpasang
5 Saklar Tunggal 3.00 Bh 16,000.00 48,000.00
6 Saklar ganda 3.00 Bh 21,000.00 63,000.00
7 Stop Kontak 3.00 Bh 20,000.00 60,000.00
Sub Jumlah 4,416,000.00
Sub Total A+B+C+D+E+F+G 236,503,496.38
TOTAL I+II+III 300,009,530.44
TOTAL BIAYA 300,009,530.44
DIBULATKAN 300,000,000.00
TERBILANG : TIGA RATUS JUTA RUPIAH

Kediri, 22 Agustus 2022


Pengurus
Pondok Pesantren Haji Ya'qub

Miftahudin Muhamad Mundakir


Ketua Bendahara
REKAPITULASI

Instansi : Pondok Pesantren Haji Ya'qub


Nama Paket : Pembangunan Asrama Santri ( 2 Kamar )

TOTAL
NO URAIAN PEKERJAAN JUMLAH
(Rp)
1 2 3
I PEKERJAAN PERSIAPAN Rp. 4,947,600.00
II PEKERJAAN STRUKTUR BAWAH
A PEKERJAAN TANAH DAN PONDASI Rp. 58,558,434.06
III PEKERJAAN LANTAI 1
A PEKERJAAN PASANGAN DAN PLESTERAN Rp. 53,770,276.95
B PEKERJAAN BETON BERTULANG Rp. 145,130,885.53
C PEKERJAAN LANTAI Rp. 13,091,778.00
D PEKERJAAN KOSEN PINTU DAN JENDELA Rp. 7,900,000.00
E PEKERJAAN PENGUNCI DAN PENGGANTUNG Rp. 1,864,000.00
F PEKERJAAN PENGECATAN Rp. 10,330,555.90
G PEKERJAAN INSTALASI LISTRIK Rp. 4,416,000.00
TOTAL I +II+III Rp. 300,009,530.44
TOTAL BIAYA Rp. 300,009,530.44
DIBULATKAN Rp. 300,000,000.00
TERBILANG : TIGA RATUS JUTA RUPIAH

Kediri, 22 Agustus 2022


Pengurus
Pondok Pesantren Haji Ya'qub

Miftahudin Muhamad Mundakir


Ketua Bendahara