NO. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA


( Rp ) ( Rp )
1 2 3 4 5 6=(4x5)

I. PEKERJAAN PENDAHULUAN
1 - Pek. Pembersihan Lahan Ls 1.00 500,000.00 500,000.00
2 - Pek. Pengukuran dan Pemasangan Bouwplank Ls 1.00 1,000,000.00 1,000,000.00

SUB - TOTAL. I 1,500,000.00

II. PEKERJAAN TANAH DAN PASIR


1 - Pek. Galian Tanah Pondasi M3 22.40 99,137.50 2,220,680.00
2 - Pek. Galian Tanah Ceker Ayam M3 40.00 99,137.00 3,965,480.00
3 - Pek. Urugan Pasir Bawah Pondasi M3 2.80 198,055.00 554,554.00
4 - Pek. Urugan Pasir Bawah Lantai M3 5.00 198,055.00 990,275.00
5 - Pek. Urugan Tanah Kembali M3 10.40 33,045.83 343,676.67

SUB - TOTAL. II 8,074,665.67

III. PEKERJAAN BATU, BETON DAN LANTAI


1 - Pek. Pondasi Batu Belah ad. 1:4 M3 12.00 988,801.00 11,865,612.00
2 - Pek. Balok Sloof 15/20 M3 1.20 5,626,163.84 6,751,396.61
3 - Pek. Kolom 12/12 M3 0.45 5,451,475.37 2,453,163.92
4 - Pek. Kolom Teras 15/20 M3 0.18 4,206,653.50 757,197.63
5 - Pek. Ring Balok 12/15 M3 1.20 5,920,881.12 7,105,057.34
6 - Pek. Plat Beton Lantai 1 + Teras M3 360,000.00 -
7 - Pek. Plat Beton Lantai 2 + Teras M3 8.00 874,386.86 6,995,094.86
8 - Pek. Dinding Batu Bata Pas.1/2 Bata Ad. 1:4 M2 68.00 117,166.50 7,967,322.00
9 - Pek. Plasteran Dinding Ad. 1:4 M2 136.00 79,766.28 10,848,214.08
10 - Pek. Lantai Beton Mutu K. 100 M3 8.00 874,386.86 6,995,094.86
11 - Pek. Pas. Keramik Lantai 40 x 40 M2 289,323.10 -
12 - Pek. Pas. Keramik Lantai KM/WC 20 x 20 M2 299,181.30 -
13 - Pek. Pas. Keramik Dinding KM/WC dan Dapur 20 x 25 M2 412,220.60 -
14 - Pek. Relief Dinding dan Teras Ls 2,000,000.00 -

SUB - TOTAL. III 61,738,153.29


IV. PEKERJAAN RANGKA ATAP BAJARINGAN
1 - Pek. Pasangan Atap Baja Ringan @ Tasso 75.65 M2 77.00 350,000.00 26,950,000.00

SUB - TOTAL. IV 26,950,000.00

V. PEKERJAAN KUSEN, PINTU DAN JENDELA


1 - Kusen PJ 1 Lbg 600,000.00 -
2 - Kusen P1 Lbg 5.00 450,000.00 2,250,000.00
3 - Kusen J1 Lbg 5.00 650,000.00 3,250,000.00
2 - Kusen JS Lbg 750,000.00 -
3 - Kusen V2 Lbg 400,000.00 -
4 - Kusen VS Lbg 500,000.00 -
5 - Kusen JM Lbg 750,000.00 -
3 - Pintu Panil Lbr 5.00 750,000.00 3,750,000.00
4 - Daun Jendela + Kaca 5 mm Lbr 5.00 300,000.00 1,500,000.00
5 - Daun Ventilasi + Kaca 5 mm Lbr 250,000.00 -
7 - Kusen Pintu PVC Lengkap Set 5.00 276,000.00 1,380,000.00

SUB - TOTAL. V 12,130,000.00

VI. PEKERJAAN KUNCI + ACCESSORIES


1 - Pek. Kunci Tanam 2 Slagg Bh 5.00 275,731.50 1,378,657.50
2 - Pek. Engsel Pintu Bh 10.00 82,691.40 826,914.00
3 - Pek. Grendel Pintu Bh 78,710.50 -
4 - Pek. Engsel Jendela Bh 34,955.25 -
5 - Pek. Grendel Jendela Bh 41,569.00 -
6 - Pek. Kait Angin Bh 78,710.50 -
7 - Pek. Tarikan Jendela Bh 27,225.00 -

SUB - TOTAL. VI 2,205,571.50

VII. PEKERJAAN INSTALASI LISTRIK


1 - Pek. Pasangan Instalasi Listrik Ttk 14.00 87,000.00 1,218,000.00
2 - Pek. Pitting Bh 8.00 18,000.00 144,000.00
3 - Pek. Box MCB Bh 1.00 50,000.00 50,000.00
4 - Pek. Stop Kontak Bh 10.00 29,000.00 290,000.00
5 - Pek. Sakelar Ganda Bh 2.00 25,000.00 50,000.00
6 - Pek. Sakelar Tunggal Bh 3.00 25,000.00 75,000.00
7 - Pek. Lampu LED 11 Watt Bh 46,000.00 -
8 - Pek. Lampu LED 5 Watt Bh 23,000.00 -

SUB - TOTAL. VII 1,827,000.00

VIII. PEKERJAAN SANITASI


1 - Pek. Pemasangan Kloset Jongkok Bh 5.00 864,457.00 4,322,285.00
2 - Pek. Pemasangan Floor drain Bh 2.00 29,000.00 58,000.00
3 - Pek. Pemasangan Kitcen Sink 1 Lob Bh 172,500.00 -
4 - Pek. Pemasangan Kran Air Bh 5.00 15,000.00 75,000.00
5 - Pek. Pemasangan Kran Angsa Bh 150,000.00 -
6 - Pek. Pemasangan Jaringan Air Bersih dan Kotor Ls 1.00 1,500,000.00 1,500,000.00
7 - Pek. Bak Fiber Bh 700,000.00 -
8 - Pek. Pembuatan Septic Tank Unit 1.00 3,500,000.00 3,500,000.00

SUB - TOTAL. VIII 9,455,285.00


REKAPITULASI
RENCANA ANGGARAN BIAYA ( RAB )
KOSKOSAN
KEGIATAN : PEMBANGUNAN KOS RNP 2
PEKERJAAN : PEMBUATAN KOS KOSAN PUTRA
LOKASI : CADIKA - RIMBO TENGAH - BUNGO

NO. URAIAN JUMLAH HARGA


( Rp )
1 2 3

I PEKERJAAN PENDAHULUAN 1,500,000.00


II PEKERJAAN TANAH DAN PASIR 8,074,665.67
III PEKERJAAN BATU, BETON DAN LANTAI 61,738,153.29
IV PEKERJAAN RANGKA ATAP BAJARINGAN 26,950,000.00
V PEKERJAAN KUSEN, PINTU DAN JENDELA 12,130,000.00
VI PEKERJAAN KUNCI + ACCESSORIES 2,205,571.50
VII PEKERJAAN INSTALASI LISTRIK 1,827,000.00
VIII PEKERJAAN SANITASI 9,455,285.00
IX PEKERJAAN PENGECATAN -
X PEKERJAAN SEMI MEZANINE -

A JUMLAH I s/d IX 123,880,675.46


B PEMBULATAN 124,000,000.00
C TERBILANG : SERATUS DUA PULUH EMPAT JUTA RUPIAH
ANALISA HARGA SATUAN PEKERJAAN (AHSP)
DIVISI 2. SITE WORK
A. 2.2.1.4. PENGUKURAN DAN PEMASANGAN 1 M' BOUWPLANK SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.1000 115,000.00 11,500.00
Tukang Kayu OH 0.1000 140,000.00 14,000.00
Kepala Tukang OH 0.0100 155,000.00 1,550.00
Mandor OH 0.0050 155,000.00 775.00
JUMLAH HARGA TENAGA 27,825.00
B BAHAN
Kayu Balok 5/7 M3 0.0120 1,900,000.00 22,800.00
Paku 2" - 3" Kg 0.0200 20,000.00 400.00
Kayu Papan 3/20 M3 0.0070 2,800,000.00 19,600.00
JUMLAH HARGA BAHAN 42,800.00
C PERALATAN

JUMLAH HARGA PERALATAN


D Jumlah (A+B+C) Rp. 70,625.00
E Overhead & Profit 10% 10% X D Rp. 7,062.50
F Harga Satuan Pekerjaan ( D + E ) Rp. 77,687.50

A. 2.2.1.5. 1 M2 PEMBERSIHAN LAPANGAN DAN PERATAAN SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.1000 115,000.00 11,500.00
Mandor OH 0.0500 155,000.00 7,750.00
JUMLAH HARGA TENAGA 19,250.00
B BAHAN
Kayu Balok 5/7 M3 0.0120 96,000.00 1,152.00
Paku 2" - 3" Kg 0.0200 80,000.00 1,600.00
Kayu Papan 3/20 M3 0.0070 65,000.00 455.00
JUMLAH HARGA BAHAN 3,207.00
C PERALATAN

JUMLAH HARGA PERALATAN


D Jumlah (A+B+C) Rp. 22,457.00
E Overhead & Profit 10% 10% X D Rp. 2,245.70
F Harga Satuan Pekerjaan ( D + E ) Rp. 24,702.70

A. 2.2.1.6. 1 M2 PEMBUATAN DIREKSI KEET DAN LOS BAHAN SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Ongkos Pasang Ls 0.1500 60,000.00 9,000.00
JUMLAH HARGA TENAGA 9,000.00
B BAHAN
Kayu / Papan Bekisting M3 0.0800 1,900,000.00 152,000.00
Paku 2" - 3" Kg 0.2500 20,000.00 5,000.00
Seng Gelombang BJLS 20 (bandar 11) Lbr 0.6200 66,000.00 40,920.00
Triplek T.3,6 mm Lbr 0.5000 65,000.00 32,500.00
Semen PC @ 50 kg (PCC) Zak 0.1000 76,000.00 7,600.00
Pasir Pasang/Beton M3 0.2500 120,000.00 30,000.00
Batu Bata Standar Bh 70.0000 450.00 31,500.00
JUMLAH HARGA BAHAN 299,520.00
C PERALATAN

JUMLAH HARGA PERALATAN


D Jumlah (A+B+C) Rp. 308,520.00
E Overhead & Profit 10% 10% X D Rp. 30,852.00
F Harga Satuan Pekerjaan ( D + E ) Rp. 339,372.00
A. 2.2.1.7. 1 M2 PAGAR PENGAMAN PROYEK SENG GELOMBANG BJLS 20 SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.2000 115,000.00 23,000.00
Tukang Kayu OH 0.4000 140,000.00 56,000.00
Kepala Tukang OH 0.0200 155,000.00 3,100.00
Mandor OH 0.0200 155,000.00 3,100.00
JUMLAH HARGA TENAGA 23,000.00
B BAHAN
Kayu Dolken Btg 1.2500 8,000.00 10,000.00
Semen PC @ 50 kg (PCC) Zak 1.5000 76,000.00 114,000.00
Seng Gelombang BJLS 20 (bandar 11) Lbr 1.2000 66,000.00 79,200.00
Pasir Pasang/Beton M3 0.0050 120,000.00 600.00
Sirtu M3 0.0090 120,000.00 1,080.00
Kayu / Papan Bekisting M3 0.0420 1,900,000.00 79,800.00
Paku 2" - 3" Kg 0.0600 20,000.00 1,200.00
JUMLAH HARGA BAHAN 285,880.00
C PERALATAN

JUMLAH HARGA PERALATAN


D Jumlah (A+B+C) Rp. 308,880.00
E Overhead & Profit 10% 10% X D Rp. 30,888.00
F Harga Satuan Pekerjaan ( D + E ) Rp. 339,768.00

A. 2.3.1.1. PENGGALIAN 1 M3 TANAH BIASA SEDALAM 1 M SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.7500 115,000.00 86,250.00
Mandor OH 0.0250 155,000.00 3,875.00
JUMLAH HARGA TENAGA 90,125.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA PERALATAN


D Jumlah (A+B+C) Rp. 90,125.00
E Overhead & Profit 10% 10% X D Rp. 9,012.50
F Harga Satuan Pekerjaan ( D + E ) Rp. 99,137.50

A. 2.3.1.9. PENGURUNGAN KEMBALI 1 M3 GALIAN TANAH SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.2500 115,000.00 28,750.00
Mandor OH 0.0083 155,000.00 1,291.67
JUMLAH HARGA TENAGA 30,041.67
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA PERALATAN


D Jumlah (A+B+C) Rp. 30,041.67
E Overhead & Profit 10% 10% X D Rp. 3,004.17
F Harga Satuan Pekerjaan ( D + E ) Rp. 33,045.83
A. 2.3.1.11. PENGURUGAN 1 M3 DENGAN PASIR URUG SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.3000 115,000.00 34,500.00
Mandor OH 0.0100 155,000.00 1,550.00
JUMLAH HARGA TENAGA 36,050.00
B BAHAN
Pasir Urug M3 1.2000 120,000.00 144,000.00

JUMLAH HARGA BAHAN 144,000.00


C PERALATAN

JUMLAH HARGA PERALATAN


D Jumlah (A+B+C) Rp. 180,050.00
E Overhead & Profit 10% 10% X D Rp. 18,005.00
F Harga Satuan Pekerjaan ( D + E ) Rp. 198,055.00

A. 2.3.1.16. TIMBUNAN 1 M3 DENGAN TANAH TIMBUNAN DI DATANGKAN SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.3000 115,000.00 34,500.00
Mandor OH 0.0300 155,000.00 4,650.00
JUMLAH HARGA TENAGA 39,150.00
B BAHAN
Tanah Timbunan M3 1.2500 48,000.00 60,000.00

JUMLAH HARGA BAHAN 60,000.00


C PERALATAN

JUMLAH HARGA PERALATAN


D Jumlah (A+B+C) Rp. 99,150.00
E Overhead & Profit 10% 10% X D Rp. 9,915.00
F Harga Satuan Pekerjaan ( D + E ) Rp. 109,065.00

DIVISI 3. PEKERJAAN STRUKTURAL


A. 3.2.1.2. PEMASANGAN 1 M3 PONDASI BATU BELAH CAMPURAN 1 SP : 4 PP SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 1.5000 115,000.00 172,500.00
Tukang Batu OH 0.7500 140,000.00 105,000.00
Kepala Tukang OH 0.0750 155,000.00 11,625.00
Mandor OH 0.0750 155,000.00 11,625.00
JUMLAH HARGA TENAGA 300,750.00
B BAHAN
Batu Belah M3 1.2000 240,000.00 288,000.00
Semen PC @ 50 kg (PCC)/Kg Kg 163.0000 1,520.00 247,760.00
Pasir Pasang/Beton M3 0.5200 120,000.00 62,400.00
JUMLAH HARGA BAHAN 598,160.00
C PERALATAN

JUMLAH HARGA PERALATAN


D Jumlah (A+B+C) Rp. 898,910.00
E Overhead & Profit 10% 10% X D Rp. 89,891.00
F Harga Satuan Pekerjaan ( D + E ) Rp. 988,801.00
A. 3.2.1.3. PEMASANGAN 1 M3 AANSTAMPANG BATU KOSONG SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.7800 115,000.00 89,700.00
Tukang Batu OH 0.3900 140,000.00 54,600.00
Kepala Tukang OH 0.0390 155,000.00 6,045.00
Mandor OH 0.0200 155,000.00 3,100.00
JUMLAH HARGA TENAGA 153,445.00
B BAHAN
Batu Belah M3 1.2000 240,000.00 288,000.00
Pasir Urug M3 0.3000 120,000.00 36,000.00
JUMLAH HARGA BAHAN 324,000.00
C PERALATAN

JUMLAH HARGA PERALATAN


D Jumlah (A+B+C) Rp. 477,445.00
E Overhead & Profit 10% 10% X D Rp. 47,744.50
F Harga Satuan Pekerjaan ( D + E ) Rp. 525,189.50

A. 3.2.1.5. PEMASANGAN 1 M3 BATU BRONJONG SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 1.5000 115,000.00 172,500.00
Kepala Tukang OH 0.2000 155,000.00 31,000.00
Mandor OH 0.0200 155,000.00 3,100.00
JUMLAH HARGA TENAGA 206,600.00
B BAHAN
Batu Kali Bulat M3 1.2000 175,000.00 210,000.00
Kawat Bronjong Kg 3.5000 24,500.00 85,750.00
JUMLAH HARGA BAHAN 295,750.00
C PERALATAN

JUMLAH HARGA PERALATAN


D Jumlah (A+B+C) Rp. 502,350.00
E Overhead & Profit 10% 10% X D Rp. 50,235.00
F Harga Satuan Pekerjaan ( D + E ) Rp. 552,585.00

DIVISI 4. PEKERJAAN ARSITEKTUR


A. 4.1.1.1. MEMBUAT 1 M3 BETON MUTU F'ç = 7,4 Mpa (K 100), SLUMP (12 ± 2) CM, w/c = 0,87 SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 1.6500 115,000.00 189,750.00
Tukang Batu OH 0.2750 140,000.00 38,500.00
Kepala Tukang OH 0.0280 155,000.00 4,340.00
Mandor OH 0.0830 155,000.00 12,865.00
JUMLAH HARGA TENAGA 245,455.00
B BAHAN
Semen PC @ 50 kg (PCC)/Kg Kg 247.0000 1,520.00 375,440.00
Pasir Pasang/Beton Kg 869.0000 85.71 74,485.71
Kerikil (Maks 30 mm) Kg 999.0000 89.29 89,196.43
Air Liter 215.0000 48.00 10,320.00
JUMLAH HARGA BAHAN 549,442.14
C PERALATAN

JUMLAH HARGA PERALATAN


D Jumlah (A+B+C) Rp. 794,897.14
E Overhead & Profit 10% 10% X D Rp. 79,489.71
F Harga Satuan Pekerjaan ( D + E ) Rp. 874,386.86
A. 4.1.1.2. MEMBUAT 1 M3 BETON MUTU F'ç = 9,8 Mpa (K 125), SLUMP (12 ± 2) CM, w/c = 0,78 SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 1.6500 115,000.00 189,750.00
Tukang Batu OH 0.2750 140,000.00 38,500.00
Kepala Tukang OH 0.0280 155,000.00 4,340.00
Mandor OH 0.0830 155,000.00 12,865.00
JUMLAH HARGA TENAGA 245,455.00
B BAHAN
Semen PC @ 50 kg (PCC)/Kg Kg 276.0000 1,520.00 419,520.00
Pasir Pasang/Beton Kg 828.0000 85.71 70,971.43
Kerikil (Maks 30 mm) Kg 1,012.0000 89.29 90,357.14
Air Liter 215.0000 48.00 10,320.00
JUMLAH HARGA BAHAN 591,168.57
C PERALATAN

JUMLAH HARGA PERALATAN


D Jumlah (A+B+C) Rp. 836,623.57
E Overhead & Profit 10% 10% X D Rp. 83,662.36
F Harga Satuan Pekerjaan ( D + E ) Rp. 920,285.93

A. 4.1.1.5. MEMBUAT 1 M3 BETON MUTU F'ç = 14,5 Mpa (K 175), SLUMP (12 ± 2) CM, w/c = 0,66 SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 1.6500 115,000.00 189,750.00
Tukang Batu OH 0.2750 140,000.00 38,500.00
Kepala Tukang OH 0.0280 155,000.00 4,340.00
Mandor OH 0.0830 155,000.00 12,865.00
JUMLAH HARGA TENAGA 245,455.00
B BAHAN
Semen PC @ 50 kg (PCC)/Kg Kg 326.0000 1,520.00 495,520.00
Pasir Pasang/Beton Kg 760.0000 85.71 65,142.86
Kerikil (Maks 30 mm) Kg 1,029.0000 89.29 91,875.00
Air Liter 215.0000 48.00 10,320.00
JUMLAH HARGA BAHAN 662,857.86
C PERALATAN

JUMLAH HARGA PERALATAN


D Jumlah (A+B+C) Rp. 908,312.86
E Overhead & Profit 10% 10% X D Rp. 90,831.29
F Harga Satuan Pekerjaan ( D + E ) Rp. 999,144.14

A. 4.1.1.7. MEMBUAT 1 M3 BETON MUTU F'ç = 19,3 Mpa (K 225), SLUMP (12 ± 2) CM, w/c = 0,58 SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 1.6500 115,000.00 189,750.00
Tukang Batu OH 0.2750 140,000.00 38,500.00
Kepala Tukang OH 0.0280 155,000.00 4,340.00
Mandor OH 0.0830 155,000.00 12,865.00
JUMLAH HARGA TENAGA 245,455.00
B BAHAN
Semen PC @ 50 kg (PCC)/Kg Kg 371.0000 1,520.00 563,920.00
Pasir Pasang/Beton Kg 698.0000 85.71 59,828.57
Kerikil (Maks 30 mm) Kg 1,047.0000 89.29 93,482.14
Air Liter 215.0000 48.00 10,320.00
JUMLAH HARGA BAHAN 727,550.71
C PERALATAN

JUMLAH HARGA PERALATAN


D Jumlah (A+B+C) Rp. 973,005.71
E Overhead & Profit 10% 10% X D Rp. 97,300.57
F Harga Satuan Pekerjaan ( D + E ) Rp. 1,070,306.29
A. 4.1.1.15. PEMBESIAN 1 KG DENGAN BESI POLOS ATAU BESI ULIR SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.0070 115,000.00 805.00
Tukang Besi OH 0.0070 140,000.00 980.00
Kepala Tukang OH 0.0007 155,000.00 108.50
Mandor OH 0.0004 155,000.00 62.00
JUMLAH HARGA TENAGA 1,955.50
B BAHAN
Besi Beton Polos Kg 1.0500 13,750.00 14,437.50
Kawat Beton Kg 0.0150 25,000.00 375.00
JUMLAH HARGA BAHAN 14,812.50
C PERALATAN

JUMLAH HARGA PERALATAN


D Jumlah (A+B+C) Rp. 16,768.00
E Overhead & Profit 10% 10% X D Rp. 1,676.80
F Harga Satuan Pekerjaan ( D + E ) Rp. 18,444.80

A. 4.1.1.19. PEMBESIAN 1 KG DENGAN BESI JARING KAWAT DILAS (WIREMESH) SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.0025 115,000.00 287.50
Tukang Besi OH 0.0025 140,000.00 350.00
Kepala Tukang OH 0.0025 155,000.00 387.50
Mandor OH 0.0001 155,000.00 15.50
JUMLAH HARGA TENAGA 1,040.50
B BAHAN
Besi Wiremesh M8 Kg 1.0200 53,000.00 54,060.00
Kawat Beton Kg 0.0050 25,000.00 125.00
JUMLAH HARGA BAHAN 54,185.00
C PERALATAN

JUMLAH HARGA PERALATAN


D Jumlah (A+B+C) Rp. 55,225.50
E Overhead & Profit 10% 10% X D Rp. 5,522.55
F Harga Satuan Pekerjaan ( D + E ) Rp. 60,748.05

A. PEMASANGAN 1 M2 WIREMESH M 8 SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.1000 115,000.00 11,500.00
Tukang Besi OH 0.0750 140,000.00 10,500.00
Mandor OH 0.0100 155,000.00 1,550.00
JUMLAH HARGA TENAGA 23,550.00
B BAHAN
Besi Wiremesh M8 M2 1.0100 53,000.00 53,530.00
Kawat Las Kg 0.1000 40,000.00 4,000.00

JUMLAH HARGA BAHAN 57,530.00


C PERALATAN
- -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 81,080.00
E Overhead & Profit 0% 10% X D Rp. 8,108.00
F Harga Satuan Pekerjaan ( D + E ) Rp. 89,188.00
A. 4.1.1.20. PEMASANGAN 1 M2 BEKISTING UNTUK PONDASI SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.5200 115,000.00 59,800.00
Tukang Kayu OH 0.2600 140,000.00 36,400.00
Kepala Tukang OH 0.0260 155,000.00 4,030.00
Mandor OH 0.0260 155,000.00 4,030.00
JUMLAH HARGA TENAGA 104,260.00
B BAHAN
Kayu / Papan Bekisting M3 0.0400 1,900,000.00 76,000.00
Paku Biasa Kg 0.3000 20,000.00 6,000.00
Minyak bekisting / Teak Oil Liter 0.1000 6,000.00 600.00
JUMLAH HARGA BAHAN 82,600.00
C PERALATAN

JUMLAH HARGA PERALATAN


D Jumlah (A+B+C) Rp. 186,860.00
E Overhead & Profit 10% 10% X D Rp. 18,686.00
F Harga Satuan Pekerjaan ( D + E ) Rp. 205,546.00

A. 4.1.1.21. PEMASANGAN 1 M2 BEKISTING UNTUK SLOOF SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.5200 115,000.00 59,800.00
Tukang Kayu OH 0.2600 140,000.00 36,400.00
Kepala Tukang OH 0.0260 155,000.00 4,030.00
Mandor OH 0.0260 155,000.00 4,030.00
JUMLAH HARGA TENAGA 104,260.00
B BAHAN
Kayu / Papan Bekisting M3 0.0450 1,900,000.00 85,500.00
Paku Biasa Kg 0.3000 20,000.00 6,000.00
Minyak bekisting / Teak Oil Liter 0.1000 6,000.00 600.00
JUMLAH HARGA BAHAN 92,100.00
C PERALATAN

JUMLAH HARGA PERALATAN


D Jumlah (A+B+C) Rp. 196,360.00
E Overhead & Profit 10% 10% X D Rp. 19,636.00
F Harga Satuan Pekerjaan ( D + E ) Rp. 215,996.00

A. 4.1.1.22. PEMASANGAN 1 M2 BEKISTING UNTUK KOLOM SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.6600 115,000.00 75,900.00
Tukang Kayu OH 0.3300 140,000.00 46,200.00
Kepala Tukang OH 0.0330 155,000.00 5,115.00
Mandor OH 0.0330 155,000.00 5,115.00
JUMLAH HARGA TENAGA 132,330.00
B BAHAN
Kayu / Papan Bekisting M3 0.0400 1,900,000.00 76,000.00
Paku Biasa Kg 0.4000 20,000.00 8,000.00
Minyak bekisting / Teak Oil Liter 0.2000 6,000.00 1,200.00
Balok Kayu Klas II M3 0.0150 2,800,000.00 42,000.00
Kayu Dolken Btg 2.0000 8,000.00 16,000.00
JUMLAH HARGA BAHAN 143,200.00
C PERALATAN

JUMLAH HARGA PERALATAN


D Jumlah (A+B+C) Rp. 275,530.00
E Overhead & Profit 10% 10% X D Rp. 27,553.00
F Harga Satuan Pekerjaan ( D + E ) Rp. 303,083.00
A. 4.1.1.23. PEMASANGAN 1 M2 BEKISTING UNTUK BALOK SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.6600 115,000.00 75,900.00
Tukang Kayu OH 0.3300 140,000.00 46,200.00
Kepala Tukang OH 0.0330 155,000.00 5,115.00
Mandor OH 0.0330 155,000.00 5,115.00
JUMLAH HARGA TENAGA 132,330.00
B BAHAN
Kayu / Papan Bekisting M3 0.0400 1,900,000.00 76,000.00
Paku Biasa Kg 0.4000 20,000.00 8,000.00
Minyak bekisting / Teak Oil Liter 0.2000 6,000.00 1,200.00
Balok Kayu Klas II M3 0.0180 2,800,000.00 50,400.00
Kayu Dolken Btg 2.0000 8,000.00 16,000.00
JUMLAH HARGA BAHAN 151,600.00
C PERALATAN

JUMLAH HARGA PERALATAN


D Jumlah (A+B+C) Rp. 283,930.00
E Overhead & Profit 10% 10% X D Rp. 28,393.00
F Harga Satuan Pekerjaan ( D + E ) Rp. 312,323.00

A. 4.1.1.24. PEMASANGAN 1 M2 BEKISTING UNTUK LANTAI (PLAT DAG) SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.6600 115,000.00 75,900.00
Tukang Kayu OH 0.3300 140,000.00 46,200.00
Kepala Tukang OH 0.0330 155,000.00 5,115.00
Mandor OH 0.0330 155,000.00 5,115.00
JUMLAH HARGA TENAGA 132,330.00
B BAHAN
Kayu / Papan Bekisting M3 0.0400 1,900,000.00 76,000.00
Paku Biasa Kg 0.4000 20,000.00 8,000.00
Minyak bekisting / Teak Oil Liter 0.2000 6,000.00 1,200.00
Balok Kayu Klas II M3 0.0150 2,800,000.00 42,000.00
Triplek T.2,6 mm Lbr 0.3500 55,000.00 19,250.00
Kayu Dolken Btg 6.0000 8,000.00 48,000.00
JUMLAH HARGA BAHAN 194,450.00
C PERALATAN

JUMLAH HARGA PERALATAN


D Jumlah (A+B+C) Rp. 326,780.00
E Overhead & Profit 10% 10% X D Rp. 32,678.00
F Harga Satuan Pekerjaan ( D + E ) Rp. 359,458.00

A. 4.1.1.26. PEMASANGAN 1 M2 BEKISTING UNTUK TANGGA SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.6600 115,000.00 75,900.00
Tukang Kayu OH 0.3300 140,000.00 46,200.00
Kepala Tukang OH 0.0330 155,000.00 5,115.00
Mandor OH 0.0330 155,000.00 5,115.00
JUMLAH HARGA TENAGA 132,330.00
B BAHAN
Kayu / Papan Bekisting M3 0.0300 1,900,000.00 57,000.00
Paku Biasa Kg 0.4000 20,000.00 8,000.00
Minyak bekisting / Teak Oil Liter 0.1500 6,000.00 900.00
Balok Kayu Klas II M3 0.0150 2,800,000.00 42,000.00
Triplek T.2,6 mm Lbr 0.3500 55,000.00 19,250.00
Kayu Dolken Btg 2.0000 8,000.00 16,000.00
JUMLAH HARGA BAHAN 143,150.00
C PERALATAN

JUMLAH HARGA PERALATAN


D Jumlah (A+B+C) Rp. 275,480.00
E Overhead & Profit 10% 10% X D Rp. 27,548.00
F Harga Satuan Pekerjaan ( D + E ) Rp. 303,028.00
A. 07.38 MEMBUAT 1 M3 PONDASI BETON BERTULANG (150Kg BESI + BEGISTING) SNI - 2008

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 3.9000 115,000.00 448,500.00
Tukang Batu OH 0.3500 140,000.00 49,000.00
Tukang Kayu OH 1.0400 140,000.00 145,600.00
Tukang Besi OH 1.0500 140,000.00 147,000.00
Kepala Tukang OH 0.2450 155,000.00 37,975.00
Mandor OH 0.1650 155,000.00 25,575.00
JUMLAH HARGA TENAGA 853,650.00
B BAHAN
Kayu / Papan Bekisting M3 0.2000 1,900,000.00 380,000.00
Paku Biasa Kg 1.5000 20,000.00 30,000.00
Minyak bekisting / Teak Oil Liter 0.4000 6,000.00 2,400.00
Besi Beton Polos Kg 150.0000 13,750.00 2,062,500.00
Kawat Beton Kg 2.2500 25,000.00 56,250.00
Semen PC @ 50 kg (PCC) Kg 323.0000 1,520.00 490,960.00
Pasir Pasang/Beton M3 0.5200 120,000.00 62,400.00
Batu Split Pecah Mesin 1/2, 3/5 M3 0.7800 400,000.00 312,000.00
JUMLAH HARGA BAHAN 3,396,510.00
C PERALATAN

JUMLAH HARGA PERALATAN


D Jumlah (A+B+C) Rp. 4,250,160.00
E Overhead & Profit 10% 10% X D Rp. 425,016.00
F Harga Satuan Pekerjaan ( D + E ) Rp. 4,675,176.00

A. 07.39 MEMBUAT 1 M3 SLOOF BETON BERTULANG (200Kg BESI + BEGISTING) SNI - 2008

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 5.6500 115,000.00 649,750.00
Tukang Batu OH 0.2750 140,000.00 38,500.00
Tukang Kayu OH 1.5600 140,000.00 218,400.00
Tukang Besi OH 1.4000 140,000.00 196,000.00
Kepala Tukang OH 0.3230 155,000.00 50,065.00
Mandor OH 0.2830 155,000.00 43,865.00
JUMLAH HARGA TENAGA 1,196,580.00
B BAHAN
Kayu / Papan Bekisting M3 0.2700 1,900,000.00 513,000.00
Paku Biasa Kg 2.0000 20,000.00 40,000.00
Minyak bekisting / Teak Oil Liter 0.6000 6,000.00 3,600.00
Besi Beton Polos Kg 210.0000 13,750.00 2,887,500.00
Kawat Beton Kg 3.0000 25,000.00 75,000.00
Semen PC @ 50 kg (PCC) Kg 6.7200 1,520.00 10,214.40
Pasir Pasang/Beton M3 0.5400 120,000.00 64,800.00
Batu Split Pecah Mesin 1/2, 3/5 M3 0.8100 400,000.00 324,000.00
JUMLAH HARGA BAHAN 3,918,114.40
C PERALATAN

JUMLAH HARGA PERALATAN


D Jumlah (A+B+C) Rp. 5,114,694.40
E Overhead & Profit 10% 10% X D Rp. 511,469.44
F Harga Satuan Pekerjaan ( D + E ) Rp. 5,626,163.84

A. 07.40 MEMBUAT 1 M3 KOLOM BETON BERTULANG (300Kg BESI + BEGISTING) SNI - 2008

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 7.0500 115,000.00 810,750.00
Tukang Batu OH 0.2750 140,000.00 38,500.00
Tukang Kayu OH 1.6500 140,000.00 231,000.00
Tukang Besi OH 2.1000 140,000.00 294,000.00
Kepala Tukang OH 0.4030 155,000.00 62,465.00
Mandor OH 0.3530 155,000.00 54,715.00
JUMLAH HARGA TENAGA 1,491,430.00
B BAHAN
Kayu / Papan Bekisting M3 0.4000 1,900,000.00 760,000.00
Paku Biasa Kg 4.0000 20,000.00 80,000.00
Minyak bekisting / Teak Oil Liter 2.0000 6,000.00 12,000.00
Besi Beton Polos Kg 315.0000 13,750.00 4,331,250.00
Kawat Beton Kg 4.5000 25,000.00 112,500.00
Semen PC @ 50 kg (PCC) Kg 6.7200 1,520.00 10,214.40
Pasir Pasang/Beton M3 0.5400 120,000.00 64,800.00
Batu Split Pecah Mesin 1/2, 3/5 M3 0.8100 400,000.00 324,000.00
Kayu 5/7 M3 0.1500 1,900,000.00 285,000.00
Triplek 9 mm Lbr 3.5000 105,000.00 367,500.00
Kayu Dolken Btg 20.0000 8,000.00 160,000.00
JUMLAH HARGA BAHAN 6,507,264.40
C PERALATAN

JUMLAH HARGA PERALATAN


D Jumlah (A+B+C) Rp. 7,998,694.40
E Overhead & Profit 10% 10% X D Rp. 799,869.44
F Harga Satuan Pekerjaan ( D + E ) Rp. 8,798,563.84

A. 07.40 MEMBUAT 1 M3 BALOK BETON BERTULANG (200Kg BESI + BEGISTING) SNI - 2008

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 6.3500 115,000.00 730,250.00
Tukang Batu OH 0.2750 140,000.00 38,500.00
Tukang Kayu OH 1.6500 140,000.00 231,000.00
Tukang Besi OH 1.4000 140,000.00 196,000.00
Kepala Tukang OH 0.3330 155,000.00 51,615.00
Mandor OH 0.3180 155,000.00 49,290.00
JUMLAH HARGA TENAGA 1,296,655.00
B BAHAN
Kayu / Papan Bekisting Kg 0.3200 1,900,000.00 608,000.00
Paku Biasa Kg 3.2000 20,000.00 64,000.00
Minyak bekisting / Teak Oil Kg 1.6000 6,000.00 9,600.00
Besi Beton Polos M3 210.0000 13,750.00 2,887,500.00
Kawat Beton M3 3.0000 25,000.00 75,000.00
Semen PC @ 50 kg (PCC) M3 6.7200 1,520.00 10,214.40
Pasir Pasang/Beton Lbr 0.5400 120,000.00 64,800.00
Batu Split Pecah Mesin 1/2, 3/5 Btg 0.8100 400,000.00 324,000.00
Kayu 5/7 Kg 0.1400 1,900,000.00 266,000.00
Triplek 9 mm Lobang 2.8000 105,000.00 294,000.00
Kayu Dolken M1 16.0000 8,000.00 128,000.00
JUMLAH HARGA BAHAN 4,731,114.40
C PERALATAN

JUMLAH HARGA PERALATAN


D Jumlah (A+B+C) Rp. 6,027,769.40
E Overhead & Profit 10% 10% X D Rp. 602,776.94
F Harga Satuan Pekerjaan ( D + E ) Rp. 6,630,546.34

A. 07.51 MEMBUAT 1 M3 BETON SLOOF uk. 15/20 (116.89 Kg Besi + Begisting) SNI - 2008

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.3500 115,000.00 40,250.00
Tukang Batu OH 1.0400 140,000.00 145,600.00
Tukang Kayu OH 1.0500 140,000.00 147,000.00
Tukang Besi OH 0.2450 140,000.00 34,300.00
Kepala Tukang OH 3.0000 155,000.00 465,000.00
Mandor OH 0.1225 155,000.00 18,987.50
JUMLAH HARGA TENAGA 851,137.50
B BAHAN
Kayu / Papan Bekisting M3 0.2900 1,900,000.00 551,000.00
Paku Biasa Kg 1.5000 20,000.00 30,000.00
Minyak bekisting / Teak Oil Liter 0.4000 6,000.00 2,400.00
Besi Beton Polos Kg 116.8900 13,750.00 1,607,237.50
Kawat Beton Kg 2.2500 25,000.00 56,250.00
Semen PC @ 50 kg (PCC) Kg 6.4600 1,520.00 9,819.20
Pasir Pasang/Beton M3 0.5200 120,000.00 62,400.00
Batu Split Pecah Mesin 1/2, 3/5 M3 0.7800 400,000.00 312,000.00
JUMLAH HARGA BAHAN 2,631,106.70
C PERALATAN

JUMLAH HARGA PERALATAN


D Jumlah (A+B+C) Rp. 3,482,244.20
E Overhead & Profit 10% 10% X D Rp. 348,224.42
F Harga Satuan Pekerjaan ( D + E ) Rp. 3,830,468.62

A. 07.53 MEMBUAT 1 M3 KOLOM PRAKTIS uk. 12/12 (208.864 Kg Besi + Begisting) SNI - 2008

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.3500 115,000.00 40,250.00
Tukang Batu OH 1.0400 140,000.00 145,600.00
Tukang Kayu OH 1.0500 140,000.00 147,000.00
Tukang Besi OH 0.2450 140,000.00 34,300.00
Kepala Tukang OH 3.0000 155,000.00 465,000.00
Mandor OH 0.1225 155,000.00 18,987.50
JUMLAH HARGA TENAGA 851,137.50
B BAHAN
Kayu / Papan Bekisting M3 0.4000 1,900,000.00 760,000.00
Paku Biasa Kg 1.5000 20,000.00 30,000.00
Minyak bekisting / Teak Oil Liter 0.4000 6,000.00 2,400.00
Besi Beton Polos Kg 208.8640 13,750.00 2,871,880.00
Kawat Beton Kg 2.2500 25,000.00 56,250.00
Semen PC @ 50 kg (PCC) Kg 6.4600 1,520.00 9,819.20
Pasir Pasang/Beton M3 0.5200 120,000.00 62,400.00
Batu Split Pecah Mesin 1/2, 3/5 M3 0.7800 400,000.00 312,000.00
JUMLAH HARGA BAHAN 4,104,749.20
C PERALATAN

JUMLAH HARGA PERALATAN


D Jumlah (A+B+C) Rp. 4,955,886.70
E Overhead & Profit 10% 10% X D Rp. 495,588.67
F Harga Satuan Pekerjaan ( D + E ) Rp. 5,451,475.37

A. 07.57 MEMBUAT 1 M3 KOLOM uk. 15/20 (116.889 Kg Besi + Begisting) SNI - 2008

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.3500 115,000.00 40,250.00
Tukang Batu OH 1.0400 140,000.00 145,600.00
Tukang Kayu OH 1.0500 140,000.00 147,000.00
Tukang Besi OH 0.2450 140,000.00 34,300.00
Kepala Tukang OH 3.0000 155,000.00 465,000.00
Mandor OH 0.1225 155,000.00 18,987.50
JUMLAH HARGA TENAGA 851,137.50
B BAHAN
Kayu / Papan Bekisting M3 0.4700 1,900,000.00 893,000.00
Paku Biasa Kg 1.5000 20,000.00 30,000.00
Minyak bekisting / Teak Oil Liter 0.4000 6,000.00 2,400.00
Besi Beton Polos Kg 116.8890 13,750.00 1,607,223.75
Kawat Beton Kg 2.2500 25,000.00 56,250.00
Semen PC @ 50 kg (PCC) Kg 6.4600 1,520.00 9,819.20
Pasir Pasang/Beton M3 0.5200 120,000.00 62,400.00
Batu Split Pecah Mesin 1/2, 3/5 M3 0.7800 400,000.00 312,000.00
JUMLAH HARGA BAHAN 2,973,092.95
C PERALATAN

JUMLAH HARGA PERALATAN


D Jumlah (A+B+C) Rp. 3,824,230.45
E Overhead & Profit 10% 10% X D Rp. 382,423.05
F Harga Satuan Pekerjaan ( D + E ) Rp. 4,206,653.50

A. 07.60 MEMBUAT 1 M3 KOLOM uk. 20/20 (91.334 Kg Besi + Begisting) SNI - 2008

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.3500 115,000.00 40,250.00
Tukang Batu OH 1.0400 140,000.00 145,600.00
Tukang Kayu OH 1.0500 140,000.00 147,000.00
Tukang Besi OH 0.2450 140,000.00 34,300.00
Kepala Tukang OH 3.0000 155,000.00 465,000.00
Mandor OH 0.1225 155,000.00 18,987.50
JUMLAH HARGA TENAGA 851,137.50
B BAHAN
Kayu / Papan Bekisting M3 0.4400 1,900,000.00 836,000.00
Paku Biasa Kg 1.5000 20,000.00 30,000.00
Minyak bekisting / Teak Oil Liter 0.4000 6,000.00 2,400.00
Besi Beton Polos Kg 91.3340 13,750.00 1,255,842.50
Kawat Beton Kg 2.2500 25,000.00 56,250.00
Semen PC @ 50 kg (PCC) Kg 6.4600 1,520.00 9,819.20
Pasir Pasang/Beton M3 0.5200 120,000.00 62,400.00
Batu Split Pecah Mesin 1/2, 3/5 M3 0.7800 400,000.00 312,000.00
JUMLAH HARGA BAHAN 2,564,711.70
C PERALATAN

JUMLAH HARGA PERALATAN


D Jumlah (A+B+C) Rp. 3,415,849.20
E Overhead & Profit 10% 10% X D Rp. 341,584.92
F Harga Satuan Pekerjaan ( D + E ) Rp. 3,757,434.12
A. 07.66 MEMBUAT 1 M3 BETON RING BALOK uk. 12/15 (217.79 Kg Besi + Begisting) SNI - 2008

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.3500 115,000.00 40,250.00
Tukang Batu OH 1.0400 140,000.00 145,600.00
Tukang Kayu OH 1.0500 140,000.00 147,000.00
Tukang Besi OH 0.2450 140,000.00 34,300.00
Kepala Tukang OH 3.0000 155,000.00 465,000.00
Mandor OH 0.1225 155,000.00 18,987.50
JUMLAH HARGA TENAGA 851,137.50
B BAHAN
Kayu / Papan Bekisting M3 0.5600 1,900,000.00 1,064,000.00
Paku Biasa Kg 1.5000 20,000.00 30,000.00
Minyak bekisting / Teak Oil Liter 0.4000 6,000.00 2,400.00
Besi Beton Polos Kg 217.7900 13,750.00 2,994,612.50
Kawat Beton Kg 2.2500 25,000.00 56,250.00
Semen PC @ 50 kg (PCC) Kg 6.4600 1,520.00 9,819.20
Pasir Pasang/Beton M3 0.5200 120,000.00 62,400.00
Batu Split Pecah Mesin 1/2, 3/5 M3 0.7800 400,000.00 312,000.00
JUMLAH HARGA BAHAN 4,531,481.70
C PERALATAN

JUMLAH HARGA PERALATAN


D Jumlah (A+B+C) Rp. 5,382,619.20
E Overhead & Profit 10% 10% X D Rp. 538,261.92
F Harga Satuan Pekerjaan ( D + E ) Rp. 5,920,881.12

A. 07.70 MEMBUAT 1 M3 BETON RING BALOK uk. 15/20 (116.889 Kg Besi + Begisting) SNI - 2008

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.3500 115,000.00 40,250.00
Tukang Batu OH 1.0400 140,000.00 145,600.00
Tukang Kayu OH 1.0500 140,000.00 147,000.00
Tukang Besi OH 0.2450 140,000.00 34,300.00
Kepala Tukang OH 3.0000 155,000.00 465,000.00
Mandor OH 0.1225 155,000.00 18,987.50
JUMLAH HARGA TENAGA 851,137.50
B BAHAN
Kayu / Papan Bekisting M3 0.3200 1,900,000.00 608,000.00
Paku Biasa Kg 1.5000 20,000.00 30,000.00
Minyak bekisting / Teak Oil Liter 0.4000 6,000.00 2,400.00
Besi Beton Polos Kg 116.8890 13,750.00 1,607,223.75
Kawat Beton Kg 2.2500 25,000.00 56,250.00
Semen PC @ 50 kg (PCC) Kg 6.4600 1,520.00 9,819.20
Pasir Pasang/Beton M3 0.5200 120,000.00 62,400.00
Batu Split Pecah Mesin 1/2, 3/5 M3 0.7800 400,000.00 312,000.00
JUMLAH HARGA BAHAN 2,688,092.95
C PERALATAN

JUMLAH HARGA PERALATAN


D Jumlah (A+B+C) Rp. 3,539,230.45
E Overhead & Profit 10% 10% X D Rp. 353,923.05
F Harga Satuan Pekerjaan ( D + E ) Rp. 3,893,153.50

A. 07.75 MEMBUAT 1 M3 PLAT BETON BERTULANG, TULANG 1 LAPIS DIA 10 MM JARAK 10 CM TEBAL 7-10 CM SNI - 2008

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 6.6497 115,000.00 764,715.50
Tukang Batu OH 0.2500 140,000.00 35,000.00
Tukang Kayu OH 4.0260 140,000.00 563,640.00
Tukang Besi OH 1.0073 140,000.00 141,022.00
Kepala Tukang OH 0.5192 155,000.00 80,476.00
Mandor OH 0.1294 155,000.00 20,057.00
JUMLAH HARGA TENAGA 1,604,910.50
B BAHAN
Kayu / Papan Bekisting Kg 0.2450 1,900,000.00 465,500.00
Paku Biasa M3 0.1500 20,000.00 3,000.00
Minyak bekisting / Teak Oil M3 1.4000 6,000.00 8,400.00
Besi Beton Polos Kg 137.3610 13,750.00 1,888,713.75
Kawat Beton Kg 1.9623 25,000.00 49,057.50
Semen PC @ 50 kg (PCC) Kg 232.0000 1,520.00 352,640.00
Pasir Pasang/Beton M3 0.5200 120,000.00 62,400.00
Balok Kayu M3 0.0700 1,900,000.00 133,000.00
Batu Split Pecah Mesin 1/2, 3/5 M3 0.7800 400,000.00 312,000.00
JUMLAH HARGA BAHAN 3,274,711.25
C PERALATAN

JUMLAH HARGA PERALATAN


D Jumlah (A+B+C) Rp. 4,879,621.75
E Overhead & Profit 10% 10% X D Rp. 487,962.18
F Harga Satuan Pekerjaan ( D + E ) Rp. 5,367,583.93

A. 07.78 MEMBUAT 1 M3 PLAT BETON BERTULANG, TULANG 2 LAPIS DIA 10 MM JARAK 10 CM TEBAL 12 CM SNI - 2008

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 6.6497 115,000.00 764,715.50
Tukang Batu OH 0.2500 140,000.00 35,000.00
Tukang Kayu OH 4.0260 140,000.00 563,640.00
Tukang Besi OH 1.0073 140,000.00 141,022.00
Kepala Tukang OH 0.5192 155,000.00 80,476.00
Mandor OH 0.1294 155,000.00 20,057.00
JUMLAH HARGA TENAGA 1,604,910.50
B BAHAN
Kayu / Papan Bekisting M3 0.2450 1,900,000.00 465,500.00
Paku Biasa M3 0.1500 20,000.00 3,000.00
Minyak bekisting / Teak Oil M3 1.4000 6,000.00 8,400.00
Besi Beton Polos Kg 349.5591 13,750.00 4,806,437.63
Kawat Beton Kg 4.9937 25,000.00 124,842.50
Semen PC @ 50 kg (PCC) M3 232.0000 1,520.00 352,640.00
Pasir Pasang/Beton M3 0.5200 120,000.00 62,400.00
Balok Kayu M3 0.0700 1,900,000.00 133,000.00
Batu Split Pecah Mesin 1/2, 3/5 M3 0.7800 400,000.00 312,000.00
JUMLAH HARGA BAHAN 6,268,220.13
C PERALATAN

JUMLAH HARGA PERALATAN


D Jumlah (A+B+C) Rp. 7,873,130.63
E Overhead & Profit 10% 10% X D Rp. 787,313.06
F Harga Satuan Pekerjaan ( D + E ) Rp. 8,660,443.69

A. 4.2.1.5. PENGERJAAN 10 CM PENGELASAN DENGAN LAS LISTRIK SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.0400 115,000.00 4,600.00
Tukang Besi Konstruksi OH 0.0200 140,000.00 2,800.00
Kepala Tukang OH 0.0020 155,000.00 310.00
Mandor OH 0.0020 155,000.00 310.00
JUMLAH HARGA TENAGA 8,020.00
B BAHAN
Kawat Las M3 0.4000 40,000.00 16,000.00
Solar Kg 0.3000 - -
Minyak Pelumas Oli Supremi Liter 0.0400 52,000.00 2,080.00
JUMLAH HARGA BAHAN 18,080.00
C PERALATAN
Sewa Alat Jam 0.1700 75,000.00 12,750.00

JUMLAH HARGA PERALATAN 12,750.00


D Jumlah (A+B+C) Rp. 38,850.00
E Overhead & Profit 10% 10% X D Rp. 3,885.00
F Harga Satuan Pekerjaan ( D + E ) Rp. 42,735.00
A. 4.4.1.2. PEMASANGAN 1 M2 DINDING BATA MERAH STANDAR TEBAL 1 BATU Ad. 1 SP : 3 PP SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.6000 115,000.00 69,000.00
Tukang Besi OH 0.2000 140,000.00 28,000.00
Kepala Tukang OH 0.0200 155,000.00 3,100.00
Mandor OH 0.0300 155,000.00 4,650.00
JUMLAH HARGA TENAGA 104,750.00
B BAHAN
Batu Bata Standar Bh 140.0000 450.00 63,000.00
Semen PC @ 50 kg (PCC)/Kg Kg 32.9500 1,520.00 50,084.00
Pasir Pasang/Beton M3 0.0910 120,000.00 10,920.00
JUMLAH HARGA BAHAN 124,004.00
C PERALATAN
- -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 228,754.00
E Overhead & Profit 10% 10% X D Rp. 22,875.40
F Harga Satuan Pekerjaan ( D + E ) Rp. 251,629.40

A. 4.4.1.3. PEMASANGAN 1 M2 DINDING BATA MERAH STANDAR TEBAL 1 BATU Ad. 1 SP : 4 PP SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.6000 115,000.00 69,000.00
Tukang OH 0.2000 140,000.00 28,000.00
Kepala Tukang OH 0.0200 155,000.00 3,100.00
Mandor OH 0.0300 155,000.00 4,650.00
JUMLAH HARGA TENAGA 104,750.00
B BAHAN
Batu Bata Standar Bh 140.0000 450.00 63,000.00
Semen PC @ 50 kg (PCC)/Kg Kg 26.5500 1,520.00 40,356.00
Pasir Pasang/Beton M3 0.0930 120,000.00 11,160.00
JUMLAH HARGA BAHAN 114,516.00
C PERALATAN
- -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 219,266.00
E Overhead & Profit 10% 10% X D Rp. 21,926.60
F Harga Satuan Pekerjaan ( D + E ) Rp. 241,192.60

A. 4.4.1.7. PEMASANGAN 1 M2 DINDING BATA MERAH STANDAR TEBAL 1/2 BATU Ad. 1 SP : 2 PP SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.3000 115,000.00 34,500.00
Tukang OH 0.1000 140,000.00 14,000.00
Kepala Tukang OH 0.0100 155,000.00 1,550.00
Mandor OH 0.0150 155,000.00 2,325.00
JUMLAH HARGA TENAGA 52,375.00
B BAHAN
Batu Bata Standar Bh 70.0000 450.00 31,500.00
Semen PC @ 50 kg (PCC)/Kg Kg 18.9500 1,520.00 28,804.00
Pasir Pasang/Beton M3 0.0380 120,000.00 4,560.00
JUMLAH HARGA BAHAN 64,864.00
C PERALATAN
- -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 117,239.00
E Overhead & Profit 10% 10% X D Rp. 11,723.90
F Harga Satuan Pekerjaan ( D + E ) Rp. 128,962.90
A. 4.4.1.7. PEMASANGAN 1 M2 DINDING BATA MERAH STANDAR TEBAL 1/2 BATU Ad. 1 SP : 4 PP SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.3000 115,000.00 34,500.00
Tukang OH 0.1000 140,000.00 14,000.00
Kepala Tukang OH 0.0100 155,000.00 1,550.00
Mandor OH 0.0150 155,000.00 2,325.00
JUMLAH HARGA TENAGA 52,375.00
B BAHAN
Batu Bata Standar Bh 70.0000 450.00 31,500.00
Semen PC @ 50 kg (PCC)/Kg Kg 11.5000 1,520.00 17,480.00
Pasir Pasang/Beton M3 0.0430 120,000.00 5,160.00
JUMLAH HARGA BAHAN 54,140.00
C PERALATAN
- -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 106,515.00
E Overhead & Profit 10% 10% X D Rp. 10,651.50
F Harga Satuan Pekerjaan ( D + E ) Rp. 117,166.50

A. 4.4.1.23. PEMASANGAN 1 M2 DINDING TERAWANG (ROOSTER) Ad. 1 SP : 4 PP SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.3000 115,000.00 34,500.00
Tukang OH 0.1000 140,000.00 14,000.00
Kepala Tukang OH 0.0100 155,000.00 1,550.00
Mandor OH 0.0150 155,000.00 2,325.00
JUMLAH HARGA TENAGA 52,375.00
B BAHAN
Batu Trawang 10x20 Bh 30.0000 6,000.00 180,000.00
Semen PC @ 50 kg (PCC)/Kg Kg 11.0000 1,520.00 16,720.00
Pasir Pasang/Beton M3 0.0350 120,000.00 4,200.00
JUMLAH HARGA BAHAN 200,920.00
C PERALATAN
- -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 253,295.00
E Overhead & Profit 10% 10% X D Rp. 25,329.50
F Harga Satuan Pekerjaan ( D + E ) Rp. 278,624.50

A. 4.4.2.4. PEMASANGAN 1 M2 PLESTERAN Ad. 1 SP : 4 PP TEBAL 15 MM SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.3000 115,000.00 34,500.00
Tukang OH 0.1500 140,000.00 21,000.00
Kepala Tukang OH 0.0150 155,000.00 2,325.00
Mandor OH 0.0150 155,000.00 2,325.00
JUMLAH HARGA TENAGA 60,150.00
B BAHAN
Semen PC @ 50 kg (PCC)/Kg Kg 6.2400 1,520.00 9,484.80
Pasir Pasang/Beton M3 0.0240 120,000.00 2,880.00
JUMLAH HARGA BAHAN 12,364.80
C PERALATAN
- -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 72,514.80
E Overhead & Profit 10% 10% X D Rp. 7,251.48
F Harga Satuan Pekerjaan ( D + E ) Rp. 79,766.28
A. 4.4.2.23. PEMASANGAN 1 M2 PLESTERAN CIPRAT Ad. 1 SP : 2 PP SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.3000 115,000.00 34,500.00
Tukang OH 0.1000 140,000.00 14,000.00
Kepala Tukang OH 0.0100 155,000.00 1,550.00
Mandor OH 0.0150 155,000.00 2,325.00
JUMLAH HARGA TENAGA 52,375.00
B BAHAN
Semen PC @ 50 kg (PCC)/Kg Kg 4.3200 1,520.00 6,566.40
Pasir Pasang/Beton M3 0.0060 120,000.00 720.00
JUMLAH HARGA BAHAN 7,286.40
C PERALATAN
- -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 59,661.40
E Overhead & Profit 10% 10% X D Rp. 5,966.14
F Harga Satuan Pekerjaan ( D + E ) Rp. 65,627.54

A. 4.4.2.27. PEMASANGAN 1 M2 ACIAN SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.2000 115,000.00 23,000.00
Tukang OH 0.1000 140,000.00 14,000.00
Kepala Tukang OH 0.0100 155,000.00 1,550.00
Mandor OH 0.0100 155,000.00 1,550.00
JUMLAH HARGA TENAGA 40,100.00
B BAHAN
Semen PC @ 50 kg (PCC)/Kg Kg 3.2500 1,520.00 4,940.00

JUMLAH HARGA BAHAN 4,940.00


C PERALATAN
- -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 45,040.00
E Overhead & Profit 10% 10% X D Rp. 4,504.00
F Harga Satuan Pekerjaan ( D + E ) Rp. 49,544.00

A. 4.4.3.13. PEMASANGAN 1 M2 LANTAI HOMOGENEOUS TILE/GRANIT UK. 60X60 SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.2400 115,000.00 27,600.00
Tukang OH 0.1200 140,000.00 16,800.00
Kepala Tukang OH 0.0120 155,000.00 1,860.00
Mandor OH 0.0120 155,000.00 1,860.00
JUMLAH HARGA TENAGA 48,120.00
B BAHAN
Keramik Polos 40 x 40 Cm Bh 3.1000 190,000.00 589,000.00
Semen PC @ 50 kg (PCC)/Kg Kg 9.6000 1,520.00 14,592.00
Pasir Pasang/Beton M3 0.0450 120,000.00 5,400.00
Semen Warna Kg 1.5000 15,000.00 22,500.00

JUMLAH HARGA BAHAN 631,492.00


C PERALATAN
- -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 679,612.00
E Overhead & Profit 10% 10% X D Rp. 67,961.20
F Harga Satuan Pekerjaan ( D + E ) Rp. 747,573.20
A. 4.4.3.34. PEMASANGAN 1 M2 LANTAI KERAMIK UKURAN 40CM X40 CM (POLOS) SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.7000 115,000.00 80,500.00
Tukang OH 0.3500 140,000.00 49,000.00
Kepala Tukang OH 0.0350 155,000.00 5,425.00
Mandor OH 0.0350 155,000.00 5,425.00
JUMLAH HARGA TENAGA 140,350.00
B BAHAN
Keramik Polos 40 x 40 Cm Bh 6.6300 12,500.00 82,875.00
Semen PC @ 50 kg (PCC)/Kg Kg 9.8000 1,520.00 14,896.00
Pasir Pasang/Beton M3 0.0450 120,000.00 5,400.00
Semen Warna Kg 1.3000 15,000.00 19,500.00
JUMLAH HARGA BAHAN 122,671.00
C PERALATAN
- -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 263,021.00
E Overhead & Profit 10% 10% X D Rp. 26,302.10
F Harga Satuan Pekerjaan ( D + E ) Rp. 289,323.10

A. 4.4.3.35. PEMASANGAN 1 M2 LANTAI KERAMIK UKURAN 30CM X30 CM (POLOS) SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.7000 115,000.00 80,500.00
Tukang OH 0.3500 140,000.00 49,000.00
Kepala Tukang OH 0.0350 155,000.00 5,425.00
Mandor OH 0.0350 155,000.00 5,425.00
JUMLAH HARGA TENAGA 140,350.00
B BAHAN
Keramik Polos 30 x 30 cm Bh 11.8700 6,818.18 80,931.82
Semen PC @ 50 kg (PCC)/Kg Kg 10.0000 1,520.00 15,200.00
Pasir Pasang/Beton M3 0.0450 120,000.00 5,400.00
Semen Warna Kg 1.5000 15,000.00 22,500.00
JUMLAH HARGA BAHAN 124,031.82
C PERALATAN
- -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 264,381.82
E Overhead & Profit 10% 10% X D Rp. 26,438.18
F Harga Satuan Pekerjaan ( D + E ) Rp. 290,820.00

A. 4.4.3.36. PEMASANGAN 1 M2 LANTAI KERAMIK UKURAN 20CM X20 CM SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.7000 115,000.00 80,500.00
Tukang OH 0.3500 140,000.00 49,000.00
Kepala Tukang OH 0.0350 155,000.00 5,425.00
Mandor OH 0.0350 155,000.00 5,425.00
JUMLAH HARGA TENAGA 140,350.00
B BAHAN
Keramik 20 x 20 cm Bh 26.5000 3,250.00 86,125.00
Semen PC @ 50 kg (PCC)/Kg Kg 10.4000 1,520.00 15,808.00
Pasir Pasang/Beton M3 0.0450 120,000.00 5,400.00
Semen Warna Kg 1.6200 15,000.00 24,300.00
JUMLAH HARGA BAHAN 131,633.00
C PERALATAN
- -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 271,983.00
E Overhead & Profit 10% 10% X D Rp. 27,198.30
F Harga Satuan Pekerjaan ( D + E ) Rp. 299,181.30
A. 4.4.3.37. PEMASANGAN 1 M2 LANTAI KERAMIK UKURAN 40CM X40 CM (KASAR) SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.7000 115,000.00 80,500.00
Tukang OH 0.3500 140,000.00 49,000.00
Kepala Tukang OH 0.0350 155,000.00 5,425.00
Mandor OH 0.0350 155,000.00 5,425.00
JUMLAH HARGA TENAGA 140,350.00
B BAHAN
Keramik Kasar 40 x 40 Cm Bh 6.6300 13,333.33 88,400.00
Semen PC @ 50 kg (PCC)/Kg Kg 9.8000 1,520.00 14,896.00
Pasir Pasang/Beton M3 0.0450 120,000.00 5,400.00
Semen Warna Kg 1.3000 15,000.00 19,500.00
JUMLAH HARGA BAHAN 128,196.00
C PERALATAN
- -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 268,546.00
E Overhead & Profit 10% 10% X D Rp. 26,854.60
F Harga Satuan Pekerjaan ( D + E ) Rp. 295,400.60

A. 4.4.3.37. PEMASANGAN 1 M' PLINT KERAMIK UKURAN 10CM X 25 CM SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.0900 115,000.00 10,350.00
Tukang OH 0.0900 140,000.00 12,600.00
Kepala Tukang OH 0.0350 155,000.00 5,425.00
Mandor OH 0.0050 155,000.00 775.00
JUMLAH HARGA TENAGA 29,150.00
B BAHAN
Plint Keramik 10x25 Bh 5.3000 10,000.00 53,000.00
Semen PC @ 50 kg (PCC)/Kg Kg 1.1400 1,520.00 1,732.80
Pasir Pasang/Beton M3 0.0030 120,000.00 360.00
Semen Warna Kg 0.0025 15,000.00 37.50
JUMLAH HARGA BAHAN 55,130.30
C PERALATAN
- -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 84,280.30
E Overhead & Profit 10% 10% X D Rp. 8,428.03
F Harga Satuan Pekerjaan ( D + E ) Rp. 92,708.33

A. 4.4.3.54.A. PEMASANGAN 1 M2 DINDING KERAMIK UKURAN 20CM X 25 CM SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.9000 115,000.00 103,500.00
Tukang OH 0.4500 140,000.00 63,000.00
Kepala Tukang OH 0.4500 155,000.00 69,750.00
Mandor OH 0.0450 155,000.00 6,975.00
JUMLAH HARGA TENAGA 243,225.00
B BAHAN
Keramik 20 x 20 cm Bh 26.5000 3,250.00 86,125.00
Semen PC @ 50 kg (PCC)/Kg Kg 9.3000 1,520.00 14,136.00
Pasir Pasang/Beton M3 0.0180 120,000.00 2,160.00
Semen Warna Kg 1.9400 15,000.00 29,100.00
JUMLAH HARGA BAHAN 131,521.00
C PERALATAN
- -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 374,746.00
E Overhead & Profit 10% 10% X D Rp. 37,474.60
F Harga Satuan Pekerjaan ( D + E ) Rp. 412,220.60
A. 4.4.3.54.B. PEMASANGAN 1 M2 DINDING KERAMIK UKURAN 30CM X 30 CM SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.9000 115,000.00 103,500.00
Tukang OH 0.4500 140,000.00 63,000.00
Kepala Tukang OH 0.4500 155,000.00 69,750.00
Mandor OH 0.0450 155,000.00 6,975.00
JUMLAH HARGA TENAGA 243,225.00
B BAHAN
Keramik Polos 30 x 30 cm Bh 11.8700 6,818.18 80,931.82
Semen PC @ 50 kg (PCC)/Kg Kg 10.0000 1,520.00 15,200.00
Pasir Pasang/Beton M3 0.0450 120,000.00 5,400.00
Semen Warna Kg 1.5000 15,000.00 22,500.00
JUMLAH HARGA BAHAN 124,031.82
C PERALATAN
- -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 367,256.82
E Overhead & Profit 10% 10% X D Rp. 36,725.68
F Harga Satuan Pekerjaan ( D + E ) Rp. 403,982.50

15.4. PEMASANGAN 1 M2 CONBLOK POLOS SNI - 2002

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.0940 115,000.00 10,810.00
Tukang OH 0.1880 140,000.00 26,320.00
Kepala Tukang OH 0.0188 155,000.00 2,914.00
Mandor OH 0.0157 155,000.00 2,433.50
JUMLAH HARGA TENAGA 42,477.50
B BAHAN
Conblok Polos T. 7 cm segi 6 Bh 42.0000 1,700.00 71,400.00
Pasir Pasang/Beton M3 0.0740 120,000.00 8,880.00
JUMLAH HARGA BAHAN 80,280.00
C PERALATAN
Alat Bantu / Perlengkapan Set 0.0600 19,000.00 1,140.00

JUMLAH HARGA PERALATAN 1,140.00


D Jumlah (A+B+C) Rp. 123,897.50
E Overhead & Profit 10% 10% X D Rp. 12,389.75
F Harga Satuan Pekerjaan ( D + E ) Rp. 136,287.25

15.5. PEMASANGAN 1 M2 BATU ALAM (DINDING) SNI - 2002

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.7600 115,000.00 87,400.00
Tukang OH 0.3800 140,000.00 53,200.00
Kepala Tukang OH 0.0380 155,000.00 5,890.00
Mandor OH 0.0380 155,000.00 5,890.00
JUMLAH HARGA TENAGA 152,380.00
B BAHAN
Batu Alam 10 x 20 M2 1.0600 127,000.00 134,620.00
Paku Biasa Kg 0.0060 20,000.00 120.00
Semen PC @ 50 kg (PCC)/Kg Zak 0.5250 76,000.00 39,900.00
Pasir Pasang/Beton M3 0.0700 120,000.00 8,400.00
Semen Warna Kg 0.3000 15,000.00 4,500.00
JUMLAH HARGA BAHAN 187,540.00
C PERALATAN
-

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 339,920.00
E Overhead & Profit 10% 10% X D Rp. 33,992.00
F Harga Satuan Pekerjaan ( D + E ) Rp. 373,912.00
15.9. PEMASANGAN 1 M2 BATU SIKAT SNI - 2002

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 1.2000 115,000.00 138,000.00
Tukang OH 1.1000 140,000.00 154,000.00
Kepala Tukang OH 0.0350 155,000.00 5,425.00
Mandor OH 0.0300 155,000.00 4,650.00
JUMLAH HARGA TENAGA 302,075.00
B BAHAN
Batu Sikat M3 0.2000 165,000.00 33,000.00
Semen PC @ 50 kg (PCC)/Kg Zak 0.5000 76,000.00 38,000.00
Pasir Pasang/Beton M3 0.0188 120,000.00 2,256.00
JUMLAH HARGA BAHAN 73,256.00
C PERALATAN
Alat Bantu / Perlengkapan - -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 375,331.00
E Overhead & Profit 10% 10% X D Rp. 37,533.10
F Harga Satuan Pekerjaan ( D + E ) Rp. 412,864.10

A. 4.2.1.18. PEMASANGAN 1 M' TALANG DATAR/JURAI SENG BJLS SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.2000 115,000.00 23,000.00
Tukang OH 0.2000 140,000.00 28,000.00
Kepala Tukang OH 0.0200 155,000.00 3,100.00
Mandor OH 0.0010 155,000.00 155.00
JUMLAH HARGA TENAGA 54,255.00
B BAHAN
Seng Plat Kwalitet I ( 90 x 180 ) M 1.0500 110,000.00 115,500.00
Paku Biasa Kg 0.0150 20,000.00 300.00
Kayu / Papan Klas II M3 0.0190 2,800,000.00 53,200.00
JUMLAH HARGA BAHAN 169,000.00
C PERALATAN
- -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 223,255.00
E Overhead & Profit 10% 10% X D Rp. 22,325.50
F Harga Satuan Pekerjaan ( D + E ) Rp. 245,580.50

A. 4.2.1.20. PEMASANGAN 1 M2 RANGKA BESI HOLLOW 1X40.40.2MM, MODUL 60X60 PLAFOND SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.3500 115,000.00 40,250.00
Tukang Besi OH 0.3500 140,000.00 49,000.00
Kepala Tukang OH 0.0350 155,000.00 5,425.00
Mandor OH 0.0180 155,000.00 2,790.00
JUMLAH HARGA TENAGA 97,465.00
B BAHAN
Rangka Metal Hollow 40.40.2 mm M' 4.0000 10,000.00 40,000.00
Accesories (Perkuatan Las dll) Ls 100%xrangka 40,000.00 40,000.00

JUMLAH HARGA BAHAN 80,000.00


C PERALATAN
- -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 177,465.00
E Overhead & Profit 10% 10% X D Rp. 17,746.50
F Harga Satuan Pekerjaan ( D + E ) Rp. 195,211.50
A. 4.5.1.5. PEMASANGAN 1 M2 LANGIT-LANGIT TRIPLEK T= 3, 4 & 6 MM dan GRC Board SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.1000 115,000.00 11,500.00
Tukang OH 0.1000 140,000.00 14,000.00
Kepala Tukang OH 0.0100 155,000.00 1,550.00
Mandor OH 0.0050 155,000.00 775.00
JUMLAH HARGA TENAGA 27,825.00
B BAHAN
Triplek T.3,6 mm Lbr 0.3750 65,000.00 24,375.00
Paku Triplek Kg 0.0300 28,000.00 840.00
JUMLAH HARGA BAHAN 25,215.00
C PERALATAN
- -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 53,040.00
E Overhead & Profit 10% 10% X D Rp. 5,304.00
F Harga Satuan Pekerjaan ( D + E ) Rp. 58,344.00

A. 4.5.1.7. PEMASANGAN 1 M2 LANGIT-LANGIT GYPSUM BOARD UK. (120X240X9)MM, TEBAL 9 MM SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.1000 115,000.00 11,500.00
Tukang OH 0.0500 140,000.00 7,000.00
Kepala Tukang OH 0.0050 155,000.00 775.00
Mandor OH 0.0050 155,000.00 775.00
JUMLAH HARGA TENAGA 20,050.00
B BAHAN
Gypsum Board T 9 mm Lbr 0.3640 65,000.00 23,660.00
Paku Sekrup Kg 0.1100 78,000.00 8,580.00
JUMLAH HARGA BAHAN 32,240.00
C PERALATAN
- -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 52,290.00
E Overhead & Profit 10% 10% X D Rp. 5,229.00
F Harga Satuan Pekerjaan ( D + E ) Rp. 57,519.00

A. 4.5.1.9. PEMASANGAN 1 M' LIST LANGIT-LANGIT KAYU PROFIL SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.0500 115,000.00 5,750.00
Tukang OH 0.0500 140,000.00 7,000.00
Kepala Tukang OH 0.0050 155,000.00 775.00
Mandor OH 0.0030 155,000.00 465.00
JUMLAH HARGA TENAGA 13,990.00
B BAHAN
Kayu List Profil Lbr 1.0500 20,000.00 21,000.00
Paku Biasa Kg 0.0100 20,000.00 200.00
JUMLAH HARGA BAHAN 21,200.00
C PERALATAN
- -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 35,190.00
E Overhead & Profit 10% 10% X D Rp. 3,519.00
F Harga Satuan Pekerjaan ( D + E ) Rp. 38,709.00
A. 4.5.1.11. PEMASANGAN 1 M' LIST GYPSUM SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.0500 115,000.00 5,750.00
Tukang OH 0.0500 140,000.00 7,000.00
Kepala Tukang OH 0.0050 155,000.00 775.00
Mandor OH 0.0030 155,000.00 465.00
JUMLAH HARGA TENAGA 13,990.00
B BAHAN
List Gypsum Lbr 1.0500 20,000.00 21,000.00
Paku Biasa Kg 0.0100 20,000.00 200.00
JUMLAH HARGA BAHAN 21,200.00
C PERALATAN
- -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 35,190.00
E Overhead & Profit 10% 10% X D Rp. 3,519.00
F Harga Satuan Pekerjaan ( D + E ) Rp. 38,709.00

A. 4.5.2.32. PEMASANGAN 1 M2 GENTENG METAL SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.2000 115,000.00 23,000.00
Tukang OH 0.1000 140,000.00 14,000.00
Kepala Tukang OH 0.0100 155,000.00 1,550.00
Mandor OH 0.0010 155,000.00 155.00
JUMLAH HARGA TENAGA 38,705.00
B BAHAN
Genteng Metal Setara Sakura Bh 1.0200 70,000.00 71,400.00
Paku Anti Karat Kg 0.2000 23,000.00 4,600.00
JUMLAH HARGA BAHAN 76,000.00
C PERALATAN
- -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 114,705.00
E Overhead & Profit 10% 10% X D Rp. 11,470.50
F Harga Satuan Pekerjaan ( D + E ) Rp. 126,175.50

A. 4.5.2.32. PEMASANGAN 1 M' NOK/BUBUNGAN GENTENG METAL SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.2500 115,000.00 28,750.00
Tukang OH 0.1500 140,000.00 21,000.00
Kepala Tukang OH 0.0150 155,000.00 2,325.00
Mandor OH 0.0130 155,000.00 2,015.00
JUMLAH HARGA TENAGA 54,090.00
B BAHAN
Bubungan Genteng Metal Bh 1.1000 25,000.00 27,500.00
Paku Anti Karat Kg 0.0500 23,000.00 1,150.00
JUMLAH HARGA BAHAN 28,650.00
C PERALATAN
- -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 82,740.00
E Overhead & Profit 10% 10% X D Rp. 8,274.00
F Harga Satuan Pekerjaan ( D + E ) Rp. 91,014.00
A. 4.5.2.38. PEMASANGAN 1 M2 ATAP SENG GELOMBANG WARNA SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.1200 115,000.00 13,800.00
Tukang OH 0.0600 140,000.00 8,400.00
Kepala Tukang OH 0.0060 155,000.00 930.00
Mandor OH 0.0060 155,000.00 930.00
JUMLAH HARGA TENAGA 24,060.00
B BAHAN
Seng Gelombang Warna Lbr 0.7000 80,000.00 56,000.00
Paku Seng Kg 0.0200 45,000.00 900.00
JUMLAH HARGA BAHAN 56,900.00
C PERALATAN
- -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 80,960.00
E Overhead & Profit 10% 10% X D Rp. 8,096.00
F Harga Satuan Pekerjaan ( D + E ) Rp. 89,056.00

A. 4.5.2.38. PEMASANGAN 1 M2 ATAP SENG GELOMBANG BJLS 20 SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.1200 115,000.00 13,800.00
Tukang OH 0.0600 140,000.00 8,400.00
Kepala Tukang OH 0.0060 155,000.00 930.00
Mandor OH 0.0060 155,000.00 930.00
JUMLAH HARGA TENAGA 24,060.00
B BAHAN
Seng Gelombang BJLS 20 (bandar 11) Lbr 0.7000 66,000.00 46,200.00
Paku Seng Kg 0.0200 45,000.00 900.00
JUMLAH HARGA BAHAN 47,100.00
C PERALATAN
- -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 71,160.00
E Overhead & Profit 10% 10% X D Rp. 7,116.00
F Harga Satuan Pekerjaan ( D + E ) Rp. 78,276.00

A. 4.5.2.38. PEMASANGAN 1 M2 ATAP SENG GELOMBANG ASBES T 4 MM SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.1400 115,000.00 16,100.00
Tukang OH 0.0700 140,000.00 9,800.00
Kepala Tukang OH 0.0070 155,000.00 1,085.00
Mandor OH 0.0035 155,000.00 542.50
JUMLAH HARGA TENAGA 27,527.50
B BAHAN
Atap Asbes Gel. 4 mm 90 x 180 Lbr 0.6200 55,000.00 34,100.00
Paku Anti Karat Kg 0.1200 45,000.00 5,400.00
JUMLAH HARGA BAHAN 39,500.00
C PERALATAN
- -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 67,027.50
E Overhead & Profit 10% 10% X D Rp. 6,702.75
F Harga Satuan Pekerjaan ( D + E ) Rp. 73,730.25
A. 4.5.2.39. PEMASANGAN 1 M' NOK SENG GELOMBANG SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.1500 115,000.00 17,250.00
Tukang OH 0.0700 140,000.00 9,800.00
Kepala Tukang OH 0.0070 155,000.00 1,085.00
Mandor OH 0.0060 155,000.00 930.00
JUMLAH HARGA TENAGA 29,065.00
B BAHAN
Seng Plat Kwalitet I ( 90 x 180 ) Lbr 0.3000 110,000.00 33,000.00
Paku Seng Kg 0.0400 45,000.00 1,800.00
JUMLAH HARGA BAHAN 34,800.00
C PERALATAN
- -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 63,865.00
E Overhead & Profit 10% 10% X D Rp. 6,386.50
F Harga Satuan Pekerjaan ( D + E ) Rp. 70,251.50

A. 4.6.1.1. PEMBUATAN DAN PEMASANGAN 1 M3 KUSEN PINTU DAN KUSEN JENDELA, KAYU KLAS II SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 6.0000 115,000.00 690,000.00
Tukang Kayu OH 18.0000 140,000.00 2,520,000.00
Kepala Tukang OH 1.8000 155,000.00 279,000.00
Mandor OH 0.3000 155,000.00 46,500.00
JUMLAH HARGA TENAGA 3,535,500.00
B BAHAN
Kayu / Papan Klas II M3 1.2000 2,800,000.00 3,360,000.00
Paku Biasa Kg 1.2500 20,000.00 25,000.00
Lem Kayu Kg 1.0000 20,000.00 20,000.00
JUMLAH HARGA BAHAN 3,405,000.00
C PERALATAN
- -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 6,940,500.00
E Overhead & Profit 10% 10% X D Rp. 694,050.00
F Harga Satuan Pekerjaan ( D + E ) Rp. 7,634,550.00

A. 4.6.1.5. PEMBUATAN DAN PEMASANGAN 1 M2 DAUN PINTU PANEL, KAYU KLAS II SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 1.0000 115,000.00 115,000.00
Tukang Kayu OH 3.0000 140,000.00 420,000.00
Kepala Tukang OH 0.3000 155,000.00 46,500.00
Mandor OH 0.0500 155,000.00 7,750.00
JUMLAH HARGA TENAGA 589,250.00
B BAHAN
Kayu / Papan Klas II M3 0.0400 2,800,000.00 112,000.00
Lem Kayu Kg 0.5000 20,000.00 10,000.00

JUMLAH HARGA BAHAN 122,000.00


C PERALATAN
- -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 711,250.00
E Overhead & Profit 10% 10% X D Rp. 71,125.00
F Harga Satuan Pekerjaan ( D + E ) Rp. 782,375.00
A. 4.6.1.6. PEMBUATAN DAN PEMASANGAN 1 M2 DAUN PINTU DAN JENDELA KACA, KAYU KLAS II SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.8000 115,000.00 92,000.00
Tukang Kayu OH 2.4000 140,000.00 336,000.00
Kepala Tukang OH 0.2400 155,000.00 37,200.00
Mandor OH 0.0400 155,000.00 6,200.00
JUMLAH HARGA TENAGA 471,400.00
B BAHAN
Kayu / Papan Klas II M3 0.0240 2,800,000.00 67,200.00
Lem Kayu Kg 0.3000 20,000.00 6,000.00

JUMLAH HARGA BAHAN 73,200.00


C PERALATAN
- -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 544,600.00
E Overhead & Profit 10% 10% X D Rp. 54,460.00
F Harga Satuan Pekerjaan ( D + E ) Rp. 599,060.00

A. 4.6.1.8. PEMBUATAN 1 M2 DAUN PINTU POLYWOOD RANGKAP + RANGKA, KAYU KLAS II (LEBAR MAX 90 M) SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.8000 115,000.00 92,000.00
Tukang Kayu OH 2.4000 140,000.00 336,000.00
Kepala Tukang OH 0.2400 155,000.00 37,200.00
Mandor OH 0.0400 155,000.00 6,200.00
JUMLAH HARGA TENAGA 471,400.00
B BAHAN
Kayu / Papan Klas II M3 0.0250 2,800,000.00 70,000.00
Lem Kayu Kg 0.5000 20,000.00 10,000.00
Paku Biasa Kg 0.0300 20,000.00 600.00
Polywood/Triplek T 4mm Lbr 1.0000 65,000.00 65,000.00
JUMLAH HARGA BAHAN 145,600.00
C PERALATAN
- -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 617,000.00
E Overhead & Profit 10% 10% X D Rp. 61,700.00
F Harga Satuan Pekerjaan ( D + E ) Rp. 678,700.00

A. 4.6.1.10. PEMBUATAN 1 M2 JALUSI KUSEN, KAYU KLAS II SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.6700 115,000.00 77,050.00
Tukang Kayu OH 2.0000 140,000.00 280,000.00
Kepala Tukang OH 0.2000 155,000.00 31,000.00
Mandor OH 0.3350 155,000.00 51,925.00
JUMLAH HARGA TENAGA 439,975.00
B BAHAN
Kayu / Papan Klas II M3 0.0600 2,800,000.00 168,000.00
Paku Biasa Kg 0.1500 20,000.00 3,000.00

JUMLAH HARGA BAHAN 171,000.00


C PERALATAN
- -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 610,975.00
E Overhead & Profit 10% 10% X D Rp. 61,097.50
F Harga Satuan Pekerjaan ( D + E ) Rp. 672,072.50
A. 4.6.1.13. PEMASANGAN 1 M3 KONSTRUKSI KUDA-KUDA KONVENSIONAL, KAYU KLAS II SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 4.0000 115,000.00 460,000.00
Tukang Kayu OH 12.0000 140,000.00 1,680,000.00
Kepala Tukang OH 1.2000 155,000.00 186,000.00
Mandor OH 0.2000 155,000.00 31,000.00
JUMLAH HARGA TENAGA 2,357,000.00
B BAHAN
Kayu / Papan Klas II M3 1.1000 2,800,000.00 3,080,000.00
Paku Biasa Kg 5.6000 20,000.00 112,000.00
Besi Strip Kg 15.0000 85,000.00 1,275,000.00
JUMLAH HARGA BAHAN 4,467,000.00
C PERALATAN
- -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 6,824,000.00
E Overhead & Profit 10% 10% X D Rp. 682,400.00
F Harga Satuan Pekerjaan ( D + E ) Rp. 7,506,400.00

A. 4.6.1.15. PEMASANGAN 1 M3 KONSTRUKSI GORDENG, KAYU KLAS II SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 6.7000 115,000.00 770,500.00
Tukang Kayu OH 20.1000 140,000.00 2,814,000.00
Kepala Tukang OH 2.0100 155,000.00 311,550.00
Mandor OH 0.3350 155,000.00 51,925.00
JUMLAH HARGA TENAGA 3,947,975.00
B BAHAN
Kayu / Papan Klas II M3 1.1000 2,800,000.00 3,080,000.00
Paku Biasa Kg 3.0000 20,000.00 60,000.00
Besi Strip Kg 15.0000 85,000.00 1,275,000.00
JUMLAH HARGA BAHAN 4,415,000.00
C PERALATAN
- -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 8,362,975.00
E Overhead & Profit 10% 10% X D Rp. 836,297.50
F Harga Satuan Pekerjaan ( D + E ) Rp. 9,199,272.50

7.1. PEMASANGAN 1 M2 RANGKA ATAP GENTENG, KAYU KLAS II SNI DT 91-2007

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.1000 115,000.00 11,500.00
Tukang OH 0.1000 140,000.00 14,000.00
Kepala Tukang OH 0.0100 155,000.00 1,550.00
Mandor OH 0.0050 155,000.00 775.00
JUMLAH HARGA TENAGA 27,825.00
B BAHAN
Kaso-kaso 5/7 klas II M3 0.0140 2,800,000.00 39,200.00
Reng 3/4 Klas II Kg 0.0160 2,800,000.00 44,800.00
Paku Biasa Kg 0.2500 20,000.00 5,000.00
JUMLAH HARGA BAHAN 89,000.00
C PERALATAN
- -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 116,825.00
E Overhead & Profit 10% 10% X D Rp. 11,682.50
F Harga Satuan Pekerjaan ( D + E ) Rp. 128,507.50
A. 4.6.1.20. PEMASANGAN 1 M2 RANGKA LANGIT-LANGIT (60X60)CM, KAYU KLAS II SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.2000 115,000.00 23,000.00
Tukang OH 0.3000 140,000.00 42,000.00
Kepala Tukang OH 0.0300 155,000.00 4,650.00
Mandor OH 0.0100 155,000.00 1,550.00
JUMLAH HARGA TENAGA 71,200.00
B BAHAN
Kaso-kaso 5/7 klas II M3 0.0163 2,800,000.00 45,640.00
Paku Biasa Kg 0.2500 20,000.00 5,000.00
JUMLAH HARGA BAHAN 50,640.00
C PERALATAN
- -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 121,840.00
E Overhead & Profit 10% 10% X D Rp. 12,184.00
F Harga Satuan Pekerjaan ( D + E ) Rp. 134,024.00

A. 4.6.1.21. PEMASANGAN 1 M' LISTPLANK (3X20)CM, KAYU KLAS II SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.1000 115,000.00 11,500.00
Tukang OH 0.2000 140,000.00 28,000.00
Kepala Tukang OH 0.0200 155,000.00 3,100.00
Mandor OH 0.0050 155,000.00 775.00
JUMLAH HARGA TENAGA 43,375.00
B BAHAN
Kayu / Papan Klas II M3 0.0108 2,800,000.00 30,240.00
Paku Biasa Kg 0.1000 20,000.00 2,000.00
JUMLAH HARGA BAHAN 32,240.00
C PERALATAN
- -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 75,615.00
E Overhead & Profit 10% 10% X D Rp. 7,561.50
F Harga Satuan Pekerjaan ( D + E ) Rp. 83,176.50

A. 4.6.1.23. PEMASANGAN 1 M2 RANGKA DINDING PEMISAH, KAYU KLAS II SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.1500 115,000.00 17,250.00
Tukang OH 0.4500 140,000.00 63,000.00
Kepala Tukang OH 0.0450 155,000.00 6,975.00
Mandor OH 0.0080 155,000.00 1,240.00
JUMLAH HARGA TENAGA 88,465.00
B BAHAN
Balok Kayu Klas II M3 0.0280 2,800,000.00 78,400.00
Paku Biasa Kg 0.1500 20,000.00 3,000.00
JUMLAH HARGA BAHAN 81,400.00
C PERALATAN
- -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 169,865.00
E Overhead & Profit 10% 10% X D Rp. 16,986.50
F Harga Satuan Pekerjaan ( D + E ) Rp. 186,851.50
A. 4.6.1.25. PEMASANGAN 1 M2 DINDING PEMISAH POLYWOOD/TRIPLEK RANGKAP+RANGKA, KAYU KLAS II SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.2000 115,000.00 23,000.00
Tukang OH 0.6000 140,000.00 84,000.00
Kepala Tukang OH 0.0600 155,000.00 9,300.00
Mandor OH 0.0100 155,000.00 1,550.00
JUMLAH HARGA TENAGA 117,850.00
B BAHAN
Balok Klas II M3 0.0280 2,800,000.00 78,400.00
Paku Biasa Kg 0.1500 20,000.00 3,000.00
Polywood/Triplek T. 4 mm Lbr 0.8600 65,000.00 55,900.00
Lem Kayu Kg 0.5600 20,000.00 11,200.00
JUMLAH HARGA BAHAN 148,500.00
C PERALATAN
- -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 266,350.00
E Overhead & Profit 10% 10% X D Rp. 26,635.00
F Harga Satuan Pekerjaan ( D + E ) Rp. 292,985.00

A. 4.6.1.26. PEMASANGAN 1 M2 DINDING LAMBRISERING DARI PAPAN, KAYU KLAS II SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.6000 115,000.00 69,000.00
Tukang OH 1.8000 140,000.00 252,000.00
Kepala Tukang OH 0.1800 155,000.00 27,900.00
Mandor OH 0.0300 155,000.00 4,650.00
JUMLAH HARGA TENAGA 353,550.00
B BAHAN
Papan Kayu Klas II M3 0.0070 2,800,000.00 19,600.00
Paku Biasa Kg 0.1000 20,000.00 2,000.00
Paku Sekrup Kg 0.1500 78,000.00 11,700.00
JUMLAH HARGA BAHAN 33,300.00
C PERALATAN
- -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 386,850.00
E Overhead & Profit 10% 10% X D Rp. 38,685.00
F Harga Satuan Pekerjaan ( D + E ) Rp. 425,535.00

A. 4.6.2.1. PEMASANGAN 1 BH KUNCI TANAM ANTIK SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.0600 115,000.00 6,900.00
Tukang OH 0.6000 140,000.00 84,000.00
Kepala Tukang OH 0.0600 155,000.00 9,300.00
Mandor OH 0.0030 155,000.00 465.00
JUMLAH HARGA TENAGA 100,665.00
B BAHAN
Kunci Tanam Antik 2 Slaag Bh 1.0000 150,000.00 150,000.00

JUMLAH HARGA BAHAN 150,000.00


C PERALATAN
- -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 250,665.00
E Overhead & Profit 10% 10% X D Rp. 25,066.50
F Harga Satuan Pekerjaan ( D + E ) Rp. 275,731.50
A. 4.6.2.5. PEMASANGAN 1 BH ENGSEL PINTU SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.0150 115,000.00 1,725.00
Tukang OH 0.1500 140,000.00 21,000.00
Kepala Tukang OH 0.0150 155,000.00 2,325.00
Mandor OH 0.0008 155,000.00 124.00
JUMLAH HARGA TENAGA 25,174.00
B BAHAN
Engsel Daun Pintu H - 5" Bh 1.0000 50,000.00 50,000.00

JUMLAH HARGA BAHAN 50,000.00


C PERALATAN
- -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 75,174.00
E Overhead & Profit 10% 10% X D Rp. 7,517.40
F Harga Satuan Pekerjaan ( D + E ) Rp. 82,691.40

A. 4.6.2.6. PEMASANGAN 1 BH ENGSEL JENDELA KUPU-KUPU SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.0100 115,000.00 1,150.00
Tukang OH 0.1000 140,000.00 14,000.00
Kepala Tukang OH 0.0100 155,000.00 1,550.00
Mandor OH 0.0005 155,000.00 77.50
JUMLAH HARGA TENAGA 16,777.50
B BAHAN
Engsel Daun Jendela H 3" Bh 1.0000 15,000.00 15,000.00

JUMLAH HARGA BAHAN 15,000.00


C PERALATAN
- -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 31,777.50
E Overhead & Profit 10% 10% X D Rp. 3,177.75
F Harga Satuan Pekerjaan ( D + E ) Rp. 34,955.25

A. 4.6.2.8. PEMASANGAN 1 BH SPRING KNIP (GRENDEL JENDELA) SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.0150 115,000.00 1,725.00
Tukang OH 0.1500 140,000.00 21,000.00
Kepala Tukang OH 0.0150 155,000.00 2,325.00
Mandor OH 0.0080 155,000.00 1,240.00
JUMLAH HARGA TENAGA 26,290.00
B BAHAN
Grendel Jendela Bh 1.0000 11,500.00 11,500.00

JUMLAH HARGA BAHAN 11,500.00


C PERALATAN
- -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 37,790.00
E Overhead & Profit 10% 10% X D Rp. 3,779.00
F Harga Satuan Pekerjaan ( D + E ) Rp. 41,569.00
A. 4.6.2.9. PEMASANGAN 1 BH KAIT ANGIN SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.0150 115,000.00 1,725.00
Tukang OH 0.1500 140,000.00 21,000.00
Kepala Tukang OH 0.0150 155,000.00 2,325.00
Mandor OH 0.0080 155,000.00 1,240.00
JUMLAH HARGA TENAGA 26,290.00
B BAHAN
Kait Angin / Hak Angin Bh 1.0000 10,000.00 10,000.00

JUMLAH HARGA BAHAN 10,000.00


C PERALATAN
- -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 36,290.00
E Overhead & Profit 10% 10% X D Rp. 3,629.00
F Harga Satuan Pekerjaan ( D + E ) Rp. 39,919.00

A. 4.6.2.11. PEMASANGAN 1 BH KUNCI SLOT (GRENDEL PINTU) SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.0200 115,000.00 2,300.00
Tukang OH 0.2000 140,000.00 28,000.00
Kepala Tukang OH 0.0200 155,000.00 3,100.00
Mandor OH 0.0010 155,000.00 155.00
JUMLAH HARGA TENAGA 33,555.00
B BAHAN
Grendel Pintu Bh 1.0000 38,000.00 38,000.00

JUMLAH HARGA BAHAN 38,000.00


C PERALATAN
- -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 71,555.00
E Overhead & Profit 10% 10% X D Rp. 7,155.50
F Harga Satuan Pekerjaan ( D + E ) Rp. 78,710.50

13.8. PEMASANGAN 1 BH TARIKAN JENDELA SNI - 2002

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Tukang OH 0.1000 140,000.00 14,000.00
Kepala Tukang OH 0.0100 155,000.00 1,550.00
JUMLAH HARGA TENAGA 15,550.00
B BAHAN
Tarikan Jendela (Handle) Bh 1.0000 9,200.00 9,200.00

JUMLAH HARGA BAHAN 9,200.00


C PERALATAN
- -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 24,750.00
E Overhead & Profit 10% 10% X D Rp. 2,475.00
F Harga Satuan Pekerjaan ( D + E ) Rp. 27,225.00
A. 4.6.2.16. PEMASANGAN 1 M2 KACA TEBAL 3 MM SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.0150 115,000.00 1,725.00
Tukang OH 0.1500 140,000.00 21,000.00
Kepala Tukang OH 0.0150 155,000.00 2,325.00
Mandor OH 0.0008 155,000.00 124.00
JUMLAH HARGA TENAGA 25,174.00
B BAHAN
Kaca Polos t = 3 mm M2 1.1000 85,000.00 93,500.00
Sealant Kg 0.0500 - -
JUMLAH HARGA BAHAN 93,500.00
C PERALATAN
- -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 118,674.00
E Overhead & Profit 10% 10% X D Rp. 11,867.40
F Harga Satuan Pekerjaan ( D + E ) Rp. 130,541.40

A. 4.6.2.17. PEMASANGAN 1 M2 KACA TEBAL 5 MM SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.0150 115,000.00 1,725.00
Tukang OH 0.1500 140,000.00 21,000.00
Kepala Tukang OH 0.0150 155,000.00 2,325.00
Mandor OH 0.0008 155,000.00 124.00
JUMLAH HARGA TENAGA 25,174.00
B BAHAN
Kaca Polos t = 5 mm M2 1.1000 130,000.00 143,000.00
Sealant Kg 0.0500 - -
JUMLAH HARGA BAHAN 143,000.00
C PERALATAN
- -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 168,174.00
E Overhead & Profit 10% 10% X D Rp. 16,817.40
F Harga Satuan Pekerjaan ( D + E ) Rp. 184,991.40

A. 4.6.2.25. PEMASANGAN 1 M2 ALUMUNIUM COMPOSITE PANEL (ACP) SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.6200 115,000.00 71,300.00
Kepala Tukang OH 0.0400 155,000.00 6,200.00
Mandor OH 0.0300 155,000.00 4,650.00
JUMLAH HARGA TENAGA 82,150.00
B BAHAN
Alumunium Composite Panel (ACP) M2 1.1000 949,000.00 1,043,900.00
Besi Hollow (panjang 6 M) M2 4.0000 10,000.00 40,000.00
Alat Bantu Alumunium Composite Panel Kg 1.0000 50,000.00 50,000.00
JUMLAH HARGA BAHAN 1,133,900.00
C PERALATAN
- -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 1,216,050.00
E Overhead & Profit 10% 10% X D Rp. 121,605.00
F Harga Satuan Pekerjaan ( D + E ) Rp. 1,337,655.00

A. 4.7.1.10. PENGECATAN 1 M2 TEMBOK BARU (1 PLAMUR : 1 CAT DASAR : 2 CAT PENUTUP) SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.0200 115,000.00 2,300.00
Tukang OH 0.0630 140,000.00 8,820.00
Kepala Tukang OH 0.0063 155,000.00 976.50
Mandor OH 0.0030 155,000.00 465.00
JUMLAH HARGA TENAGA 12,561.50
B BAHAN
Plamour Tembok Kg 0.1000 8,700.00 870.00
Cat Tembok KW 2 Kg 0.1000 13,000.00 1,300.00
Cat Tembok KW 1 Kg 0.2600 54,800.00 14,248.00
JUMLAH HARGA BAHAN 16,418.00
C PERALATAN
- -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 28,979.50
E Overhead & Profit 10% 10% X D Rp. 2,897.95
F Harga Satuan Pekerjaan ( D + E ) Rp. 31,877.45

A. 4.7.1.11. PENGECATAN 1 M2 TEMBOK LAMA (1 CAT DASAR : 2 CAT PENUTUP) SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.0280 115,000.00 3,220.00
Tukang OH 0.0420 140,000.00 5,880.00
Kepala Tukang OH 0.0042 155,000.00 651.00
Mandor OH 0.0030 155,000.00 465.00
JUMLAH HARGA TENAGA 10,216.00
B BAHAN
Cat Tembok KW 2 Kg 0.1200 13,000.00 1,560.00
Cat Tembok KW 1 Kg 0.1800 54,800.00 9,864.00

JUMLAH HARGA BAHAN 11,424.00


C PERALATAN
- -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 21,640.00
E Overhead & Profit 10% 10% X D Rp. 2,164.00
F Harga Satuan Pekerjaan ( D + E ) Rp. 23,804.00

9.9. PENGECATAN 1 M2 PLAFOND 2 LAPIS MENGGUNAKAN ROLL SNI - 2002

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.0600 115,000.00 6,900.00
Tukang OH 0.0400 140,000.00 5,600.00
Kepala Tukang OH 0.0040 155,000.00 620.00
Mandor OH 0.0030 155,000.00 465.00
JUMLAH HARGA TENAGA 13,585.00
B BAHAN
Plamour Tembok Kg 0.1000 8,700.00 870.00
Cat Tembok KW 2 Kg 0.4700 54,800.00 25,756.00
Amplas Kayu Lbr 0.5000 15,000.00 7,500.00
JUMLAH HARGA BAHAN 34,126.00
C PERALATAN
Alat Bantu / Perlengkapan Set 0.0100 19,000.00 190.00

JUMLAH HARGA PERALATAN 190.00


D Jumlah (A+B+C) Rp. 47,901.00
E Overhead & Profit 10% 10% X D Rp. 4,790.10
F Harga Satuan Pekerjaan ( D + E ) Rp. 52,691.10

9.13. PENGECATAN 1 M2 BIDANG KAYU 2 LAPIS SNI - 2002

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.1500 115,000.00 17,250.00
Tukang OH 0.1500 140,000.00 21,000.00
Kepala Tukang OH 0.0150 155,000.00 2,325.00
Mandor OH 0.0080 155,000.00 1,240.00
JUMLAH HARGA TENAGA 41,815.00
B BAHAN
Cat Kayu/Besi Kg 0.3000 80,000.00 24,000.00
Minyak Cat / Tinner Ltr 0.2000 34,000.00 6,800.00
Kuas Bh 0.0200 35,000.00 700.00
JUMLAH HARGA BAHAN 31,500.00
C PERALATAN

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 73,315.00
E Overhead & Profit 10% 10% X D Rp. 7,331.50
F Harga Satuan Pekerjaan ( D + E ) Rp. 80,646.50

DIVISI 5. PEKERJAAN MEKANIKAL


A. 5.1.1.1. PEMASANGAN 1 BH CLOSET DUDUK/MONOBLOCK SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 3.3000 115,000.00 379,500.00
Tukang OH 1.1000 140,000.00 154,000.00
Kepala Tukang OH 0.0100 155,000.00 1,550.00
Mandor OH 0.1600 155,000.00 24,800.00
JUMLAH HARGA TENAGA 559,850.00
B BAHAN
Kloset Duduk Lengkap Unit 1.0000 1,725,000.00 1,725,000.00
Perlengkapan Kg 6% x closet 103,500.00 103,500.00
JUMLAH HARGA BAHAN 1,828,500.00
C PERALATAN
- -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 2,388,350.00
E Overhead & Profit 10% 10% X D Rp. 238,835.00
F Harga Satuan Pekerjaan ( D + E ) Rp. 2,627,185.00

A. 5.1.1.2. PEMASANGAN 1 BH CLOSET JONGKOK PORSELEN SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 1.0000 115,000.00 115,000.00
Tukang OH 1.5000 140,000.00 210,000.00
Kepala Tukang OH 0.1500 155,000.00 23,250.00
Mandor OH 0.1600 155,000.00 24,800.00
JUMLAH HARGA TENAGA 373,050.00
B BAHAN
Kloset Jongkok Unit 1.0000 402,500.00 402,500.00
Semen PC @ 50 kg (PCC) Kg 6.0000 1,520.00 9,120.00
Pasir Pasang/Beton M3 0.0100 120,000.00 1,200.00
JUMLAH HARGA BAHAN 412,820.00
C PERALATAN
- -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 785,870.00
E Overhead & Profit 10% 10% X D Rp. 78,587.00
F Harga Satuan Pekerjaan ( D + E ) Rp. 864,457.00

A. 5.1.1.4. PEMASANGAN 1 BH URINOIR SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 1.0000 115,000.00 115,000.00
Tukang OH 1.0000 140,000.00 140,000.00
Kepala Tukang OH 0.1000 155,000.00 15,500.00
Mandor OH 0.0500 155,000.00 7,750.00
JUMLAH HARGA TENAGA 278,250.00
B BAHAN
Urinoir Lengkap Unit 1.0000 1,160,000.00 1,160,000.00
Semen PC @ 50 kg (PCC) Kg 6.0000 1,520.00 9,120.00
Pasir Pasang/Beton M3 0.0100 120,000.00 1,200.00
Perlengkapan % 30.0000 34,800.00
JUMLAH HARGA BAHAN 1,205,120.00
C PERALATAN
- -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 1,483,370.00
E Overhead & Profit 10% 10% X D Rp. 148,337.00
F Harga Satuan Pekerjaan ( D + E ) Rp. 1,631,707.00

A. 5.1.1.5. PEMASANGAN 1 BH WASHTAFEL SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 1.2000 115,000.00 138,000.00
Tukang OH 1.4500 140,000.00 203,000.00
Kepala Tukang OH 0.1500 155,000.00 23,250.00
Mandor OH 0.0600 155,000.00 9,300.00
JUMLAH HARGA TENAGA 373,550.00
B BAHAN
Washtafel Lengkap (American Standard) Unit 1.0000 550,000.00 550,000.00
Semen PC @ 50 kg (PCC) Kg 6.0000 1,520.00 9,120.00
Pasir Pasang/Beton M3 0.0100 120,000.00 1,200.00
Perlengkapan % 12.0000 6,600.00
JUMLAH HARGA BAHAN 566,920.00
C PERALATAN
- -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 940,470.00
E Overhead & Profit 10% 10% X D Rp. 94,047.00
F Harga Satuan Pekerjaan ( D + E ) Rp. 1,034,517.00

A. 5.1.1.6. PEMASANGAN 1 BH BATHCUIP PORSELEN SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.0750 115,000.00 8,625.00
Tukang OH 0.7500 140,000.00 105,000.00
Kepala Tukang OH 0.0750 155,000.00 11,625.00
Mandor OH 0.0030 155,000.00 465.00
JUMLAH HARGA TENAGA 125,715.00
B BAHAN
Bathcuip Lengkap Unit 1.0000 5,500,000.00 5,500,000.00
Perlengkapan % 20.0000 110,000.00
JUMLAH HARGA BAHAN 5,610,000.00
C PERALATAN
- -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 5,735,715.00
E Overhead & Profit 10% 10% X D Rp. 573,571.50
F Harga Satuan Pekerjaan ( D + E ) Rp. 6,309,286.50
A. 5.1.1.14. PEMASANGAN 1 BH FLOOR DRAIN SNI - 2013

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA


A TENAGA
Pekerja OH 0.0100 115,000.00 1,150.00
Tukang OH 0.1000 140,000.00 14,000.00
Kepala Tukang OH 0.0100 155,000.00 1,550.00
Mandor OH 0.0050 155,000.00 775.00
JUMLAH HARGA TENAGA 17,475.00
B BAHAN
Floor Drain Plastik Bh 1.0000 29,000.00 29,000.00

JUMLAH HARGA BAHAN 29,000.00


C PERALATAN
- -

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) Rp. 46,475.00
E Overhead & Profit 10% 10% X D Rp. 4,647.50
F Harga Satuan Pekerjaan ( D + E ) Rp. 51,122.50
HARGA SATUAN UPAH DAN BAHAN-BAHAN
ENGINEER'S ESTIMATE ( EE )

KEGIATAN : PERUMAHAN TABIR RESIDENCE


PEKERJAAN : PEMBANGUNAN RUMAH DAN RUKO
LOKASI : JALAN LINTAS SUMATERA ARAH BANGKO KEL. PASAR BARU RANTAU PANJANG TABIR

HARGA SATUAN ONGKOS KE ONGKOS LANSIR HARGA DI LOKASI


NAMA BAHAN / UPAH SAT LOKASI
No.
Rp. 0% Rp Rp
1 2 3 4 5 6 4

I. HARGA UPAH KERJA

1 Pekerja OH 115,000.00 115,000.00


2 Tukang OH 140,000.00 140,000.00
3 Kepala Tukang OH 155,000.00 155,000.00
4 Mandor OH 155,000.00 155,000.00

II. HARGA BAHAN - BAHAN

1 Alat Bantu / Perlengkapan Set 19,000.00 - 19,000.00


2 Alat Bantu Alumunium Composite Panel M2 50,000.00 - 50,000.00
3 Alumunium Composite Panel (ACP) M2 949,000.00 - 949,000.00
4 Amplas Kayu Lbr 15,000.00 - 15,000.00
5 Atap Asbes Gel. 4 mm 90 x 180 Lbr 55,000.00 - 55,000.00
6 Bathcuip Lengkap Unit 5,500,000.00 - 5,500,000.00
7 Bak Mandi 50x80 (TERASSO) Bh 1,700,000.00 - 1,700,000.00
8 Batu Alam 10 x 20 M2 127,000.00 - 127,000.00
9 Batu Bata Standar Bh 450.00 - 450.00
10 Batu Bata Besar Bh 550.00 - 550.00
11 Batu Belah M3 240,000.00 - 240,000.00
12 Batu Kali Bulat M3 175,000.00 - 175,000.00
13 Batu Trawang 10x20 Bh 6,000.00 - 6,000.00
14 Batu Sikat M3 165,000.00 - 165,000.00
15 Batu Split Pecah Mesin 1/2, 3/5 M3 400,000.00 - 400,000.00
16 Besi Beton Polos Kg 13,750.00 - 13,750.00
17 Besi Beton Ulir Kg 13,750.00 - 13,750.00
18 Besi Hollow (panjang 6 M) M 10,000.00 - 10,000.00
19 Besi Strip P 4 Meter Bh 85,000.00 - 85,000.00
20 Besi Wiremesh M8 M2 53,000.00 - 53,000.00
21 Besi Wiremesh m6 M2 31,000.00 - 31,000.00
22 Besi Wiremesh m5 M2 22,000.00 - 22,000.00
23 Bubungan Genteng Metal Bh 25,000.00 - 25,000.00
24 Cat Kayu/Besi Kg 80,000.00 - 80,000.00
25 Cat Tembok Exterior Kg 85,000.00 - 85,000.00
26 Cat TembokInterior Kg 71,000.00 - 71,000.00
27 Cat Tembok KW 1 Kg 54,800.00 - 54,800.00
28 Cat Tembok KW 2 Kg 13,000.00 - 13,000.00
29 Conblok Polos T. 7 cm segi 4 Bh 1,800.00 - 1,800.00
30 Conblok Polos T. 7 cm segi 6 Bh 1,700.00 - 1,700.00
31 Dempul Kg 60,000.00 - 60,000.00
32 Door Closer Bh 80,000.00 - 80,000.00
33 Engsel Daun Pintu H - 5" Bh 50,000.00 - 50,000.00
34 Engsel Daun Jendela H 3" Bh 15,000.00 - 15,000.00
35 Floor Drain Plastik Bh 29,000.00 - 29,000.00
36 Floor Drain Stainless Bh 115,000.00 - 115,000.00
37 Genteng Metal Setara Sakura Bh 70,000.00 - 70,000.00
38 Granit Tile 60x60 cm Bh 190,000.00 - 190,000.00
39 Grendel Jendela Bh 11,500.00 - 11,500.00
40 Grendel Pintu Bh 38,000.00 - 38,000.00
41 GRC Board Tebal 4 mm Lbr 65,000.00 - 65,000.00
42 Gypsum Board T 9 mm Lbr 65,000.00 - 65,000.00
43 Kaca Polos t = 3 mm M2 85,000.00 - 85,000.00
44 Kaca Polos t = 5 mm M2 130,000.00 - 130,000.00
45 Kaca Polos t = 12 mm M2 450,000.00 - 450,000.00
46 Kait Angin / Hak Angin Bh 10,000.00 - 10,000.00
47 Kawat Ayam M2 22,500.00 - 22,500.00
48 Kawat Beton Kg 25,000.00 - 25,000.00
HARGA SATUAN ONGKOS KE ONGKOS LANSIR HARGA DI LOKASI
NAMA BAHAN / UPAH SAT LOKASI
No.
Rp. 0% Rp Rp
1 2 3 4 5 6 4
49 Kawat Bronjong Kg 24,500.00 - 24,500.00
HARGA SATUAN ONGKOS KE ONGKOS LANSIR HARGA DI LOKASI
NAMA BAHAN / UPAH SAT LOKASI
No.
Rp. 0% Rp Rp
1 2 3 4 5 6 4
50 Kawat Las Kg 40,000.00 - 40,000.00
51 Kayu Cerucuk (Gelam) Btg 30,000.00 - 30,000.00
52 Kayu Dolken Btg 8,000.00 - 8,000.00
53 Kayu Klas I M3 4,000,000.00 - 4,000,000.00
54 Kayu / Papan Klas II M3 2,800,000.00 - 2,800,000.00
55 Kayu / Papan Bekisting M3 1,900,000.00 - 1,900,000.00
56 Kayu List Profil M 20,000.00 - 20,000.00
57 Kerikil M3 125,000.00 - 125,000.00
58 Kerikil (BJ) Kg 89.29 - 89.29
59 Kerikil Putih Tersaring M3 165,000.00 - 165,000.00
60 Keramik 20 x 25 cm Bh 2,400.00 - 2,400.00
61 Keramik 20 x 20 cm Bh 3,250.00 - 3,250.00
62 Keramik Polos 30 x 30 cm Bh 6,818.18 - 6,818.18
63 Keramik Polos 40 x 40 Cm Bh 12,500.00 - 12,500.00
64 Keramik Kasar 40 x 40 Cm Bh 13,333.33 - 13,333.33
65 Kloset Duduk Lengkap Unit 1,725,000.00 - 1,725,000.00
66 Kloset Jongkok Unit 402,500.00 - 402,500.00
67 Kran Plastik 1/2" Bh 12,000.00 - 12,000.00
68 Kran Plastik 1/4" Bh 15,000.00 - 15,000.00
69 Kran Stainless 1/2" Bh 80,000.00 - 80,000.00
70 Kran Stainless 1/4" Bh 90,000.00 - 90,000.00
71 Kran Angsa Bh 150,000.00 - 150,000.00
72 Kuas Bh 35,000.00 - 35,000.00
73 Kunci Tanam Antik 2 Slaag Bh 150,000.00 - 150,000.00
74 Kuku Keramik M 14,000.00 - 14,000.00
75 Lampu TL 10 Watt Bh 30,000.00 - 30,000.00
76 Lampu TL 2x40 Watt + BOX Bh 65,000.00 - 65,000.00
77 Lampu TL 100 Watt Bh 96,000.00 - 96,000.00
78 Lampu Pijar 15 s/d 75 Watt Bh 30,000.00 - 30,000.00
79 Lampu LED 5 Watt Bh 23,000.00 - 23,000.00
80 Lampu LED 11 Watt Bh 46,000.00 - 46,000.00
81 Lampu LED 18 Watt Bh 80,500.00 - 80,500.00
82 Lem Kayu Kg 20,000.00 - 20,000.00
83 Lisplank GRC Terpasang M1 50,000.00 - 50,000.00
84 List Gypsum M1 20,000.00 - 20,000.00
85 List PVC M1 50,000.00 - 50,000.00
86 MCB Bh 109,250.00 - 109,250.00
87 Minyak bekisting / Teak Oil Ltr 6,000.00 - 6,000.00
88 Minyak Cat / Tinner Ltr 34,000.00 - 34,000.00
89 Minyak Pelumas Oli Supremi Ltr 52,000.00 - 52,000.00
90 Paku Anti Karat Kg 23,000.00 - 23,000.00
91 Paku Beton Kg 25,000.00 - 25,000.00
92 Paku Biasa Kg 20,000.00 - 20,000.00
93 Paku Seng Kg 45,000.00 - 45,000.00
94 Paku Triplek Kg 28,000.00 - 28,000.00
95 Paku Sekrup Kg 78,000.00 - 78,000.00
96 Pasir Urug M3 120,000.00 - 120,000.00
97 Pasir Pasang/Beton M3 120,000.00 - 120,000.00
98 Pasir Pasang/Beton (BJ) Kg 85.71 - 85.71
99 Pitting Biasa Bh 18,000.00 - 18,000.00
100 Plamour Tembok Kg 8,700.00 - 8,700.00
101 Plint Granit Tile 10x60 cm Bh 20,000.00 - 20,000.00
102 Plint Keramik 10x25 Bh 10,000.00 - 10,000.00
103 Plasing Seng Plat + Pasang M 30,000.00 - 30,000.00
104 Rangka Canal Atap Baja Ringan Btg 140,000.00 - 140,000.00
105 Rangka Reng Atap Baja Ringan Btg 68,000.00 - 68,000.00
106 Rangka Plafond Metal Furing M2 20,000.00 - 20,000.00
107 Roster Beton 10x20 Bh 5,000.00 - 5,000.00
108 Sakelar Ganda Bh 25,000.00 - 25,000.00
109 Sakelar Tunggal Bh 25,000.00 - 25,000.00
110 Sealant Tb 55,000.00 - 55,000.00
111 Semen PC @ 50 kg (PCC) Zak 76,000.00 - 76,000.00
112 Semen PC @ 50 kg (PCC)/Kg Kg 1,520.00 - 1,520.00
113 Semen Warna Kg 15,000.00 - 15,000.00
114 Seng Gelombang BJLS 20 (bandar 11) Lbr 66,000.00 - 66,000.00
HARGA SATUAN ONGKOS KE ONGKOS LANSIR HARGA DI LOKASI
NAMA BAHAN / UPAH SAT LOKASI
No.
Rp. 0% Rp Rp
1 2 3 4 5 6 4
115 Seng Gelombang Warna Lbr 80,000.00 - 80,000.00
116 Seng Plat Kwalitet I ( 90 x 180 ) Lbr 110,000.00 - 110,000.00
117 Shower Set (american Standard) Set 2,200,000.00 - 2,200,000.00
118 Sirtu M3 120,000.00 - 120,000.00
119 Skring Grop Bh 75,000.00 - 75,000.00
120 Stop Kontak Bh 29,000.00 - 29,000.00
HARGA SATUAN ONGKOS KE ONGKOS LANSIR HARGA DI LOKASI
NAMA BAHAN / UPAH SAT LOKASI
No.
Rp. 0% Rp Rp
1 2 3 4 5 6 4
121 Tanah Timbunan M3 48,000.00 - 48,000.00
122 Tangki Air 1200 Unit 2,185,000.00 - 2,185,000.00
123 Tangki Air 500 Unit 1,035,000.00 - 1,035,000.00
124 Talang Air Plat M1 35,000.00 - 35,000.00
125 Tarikan Jendela (Handle) Bh 9,200.00 - 9,200.00
126 Tarikan Pintu (Handle) Bh 149,500.00 - 149,500.00
127 Triplek T.2,6 mm Lbr 55,000.00 - 55,000.00
128 Triplek T.3,6 mm Lbr 65,000.00 - 65,000.00
129 Triplek T.5 mm Lbr 87,500.00 - 87,500.00
130 Triplek T.9 mm Lbr 150,000.00 - 150,000.00
131 Triplek T.12 mm Lbr 200,000.00 - 200,000.00
132 Triplek Cor T.9 mm Lbr 105,000.00 - 105,000.00
133 Urinoir Lengkap Unit 1,160,000.00 - 1,160,000.00
134 Washtafel Lengkap (American Standard) Unit 550,000.00 - 550,000.00

III. HARGA LUMP SUM

1 AC 1/2 PK Unit 4,025,000.00 - 4,025,000.00


2 AC 1 PK Unit 5,520,000.00 - 5,520,000.00
3 AC 2 PK Unit 8,625,000.00 - 8,625,000.00
4 Air Unit 48.00 - 48.00
5 Box Sekering (MCB) Bh 50,000.00 - 50,000.00
6 Bak Kontrol 40x40x40 cm Unit 200,000.00 - 200,000.00
7 Daun Jendela Bingkai + kaca T 5 mm (type I) uk max. 80x130 Bh 300,000.00 - 300,000.00
8 Daun Jendela Bingkai + kaca T 5 mm (type II) uk max. 70x60 Bh 200,000.00 - 200,000.00
9 Daun Pintu Panil Standar Bh 750,000.00 - 750,000.00
10 Daun Pintu Panil + Kaca Kontrol T 5mm Exotic (1 Daun) Bh 900,000.00 - 900,000.00
11 Daun Pintu Panil + Kaca Kontrol T 5mm Exotic (2 Daun) Set 1,300,000.00 - 1,300,000.00
12 Daun Pintu Teakwood Finishing HVL + Kaca Kontrol (1 Daun) Bh 2,000,000.00 - 2,000,000.00
13 Daun Pintu Teakwood Finishing HVL + Kaca Kontrol (2 Daun) Set 3,500,000.00 - 3,500,000.00
14 Daun Pintu Temperet + Freamless + Accesories uk. 80x200 Bh 3,500,000.00 - 3,500,000.00
15 Exhaust Fan 12" Bh 518,000.00 - 518,000.00
16 Hand Rail Pipa Stainless Dia 1,5 " Set 1,000,000.00 - 1,000,000.00
17 Hydrant Kebakaran Dia 75mm / APAR Unit 949,000.00 - 949,000.00
18 Instalasi Titik Lampu Ttk 87,000.00 - 87,000.00
19 Kitchen Sink 1 Lobang Satinless Unit 172,500.00 - 172,500.00
20 Kitchen Sink 2 Lobang Satinless Unit 437,000.00 - 437,000.00
21 Kusen Freamless Rangka Alumunium + Kaca T 5mm + lis blur M2 550,000.00 - 550,000.00
22 Kusen dan Daun Jendela Alumunium + Kaca T 5 mm Lobang 1,500,000.00 - 1,500,000.00
23 Kusen dan Daun Pintu Alumunium + Kaca T 5 mm Lobang 1,500,000.00 - 1,500,000.00
24 Kusen Jendela Type I + Ventilasi uk max. 80x130 Lobang 400,000.00 - 400,000.00
25 Kusen Jendela Type II + Ventilasi uk max. 80x60 Lobang 300,000.00 - 300,000.00
26 Kusen Jendela Type III (3 rangkai) + Ventilasi uk max. 60x60 Lobang 550,000.00 - 550,000.00
27 Kusen Pintu (type I) + Ventilasi Lobang 450,000.00 - 450,000.00
28 Kusen Pintu (type II) Buka 2 + Ventilasi Lobang 600,000.00 - 600,000.00
29 Kusen Pintu (type III) Non Ventilasi Lobang 400,000.00 - 400,000.00
30 Kusen Pintu Alumunium Lengkap Unit 897,000.00 - 897,000.00
31 Kusen Pintu PVC Lengkap Unit 276,000.00 - 276,000.00
32 Ornamen Relief Semen M' 100,000.00 - 100,000.00
33 Pagar BRC T=1,6 M M' 285,000.00 - 285,000.00
34 Pagar BRC T=1,2 M M' 250,000.00 - 250,000.00
35 Pagar Stainless Bulat M' 823,000.00 - 823,000.00
36 Pagar Stainless Kotak M' 696,000.00 - 696,000.00
37 Papan Nama Kegiatan Unit 350,000.00 - 350,000.00
38 Pemasangan Bacdroop HVL M2 1,650,000.00 - 1,650,000.00
39 Pemasangan Dinding HVL + Rangka Terpasang M2 880,000.00 - 880,000.00
40 Pemasangan Interior Meja M' 1,980,000.00 - 1,980,000.00
41 Pemasangan Partisi Kaca + Rangka Freamless M2 633,000.00 - 633,000.00
42 Pintu Alumunium Slide Unit 2,587,000.00 - 2,587,000.00
43 Pintu Alumunium Swing Unit 2,875,000.00 - 2,875,000.00
44 Pitu Kaca Tempered T 12 mm Lengkap M2 3,000,000.00 - 3,000,000.00
45 Plafond PVC Terpasang Datar M2 275,000.00 - 275,000.00
46 Plafond PVC Terpasang Variasi M2 303,000.00 - 303,000.00
47 Rangka Kuda-kuda Baja Ringan Terpasang M2 275,000.00 - 275,000.00
48 Roster Kayu Klas II Lobang 70,000.00 - 70,000.00
HARGA SATUAN ONGKOS KE ONGKOS LANSIR HARGA DI LOKASI
NAMA BAHAN / UPAH SAT LOKASI
No.
Rp. 0% Rp Rp
1 2 3 4 5 6 4
49 Sewa Mesin Las Listrik Jam 75,000.00 - 75,000.00
50 Teralis Jendela Type I Bh 345,000.00 - 345,000.00
51 Teralis Jendela Type II Bh 300,000.00 - 300,000.00
52 Teralis Pintu Bh 1,380,000.00 - 1,380,000.00