ANALISA HARGA SATUAN PEKERJAA

KODE
JENIS & URAIAN PEKERJAN KOEFISIEN
ANALISA
1 2 3
Q3 - 013 Lapis Resap Pengikat
L.007a Pekerja 0.030
L.009a Mandor 0.006
M.009 Aspal Penetrasi 60/70 0.629
M.009d Kerosene / Minyak Tanah 0.489
E.03 Aphalt Sprayer 0.003
E.05 Compressor 4000-6000 L/M 0.003
E.08 Dump Truck 3 - 4 M3 0.003
JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN D
OVERHEAD & PROFIT E
HARGA SATUAN PEKERJAAN ( D + E )
Q3 - 014 Lapis Perekat
L.007a Pekerja 0.030
L.009a Mandor 0.006
M.009 Aspal Penetrasi 60/70 0.872
M.009d Kerosene / Minyak Tanah 0.253
E.03 Aphalt Sprayer 0.003
E.05 Compressor 4000-6000 L/M 0.006
E.08 Dump Truck 3 - 4 M3 0.003
JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN D
OVERHEAD & PROFIT E
HARGA SATUAN PEKERJAAN ( D + E )
Q3 - 015 Lapis Penetrasi Makadam (Leveling)
ANALISA HARGA SATUAN PEKERJAA

KODE
JENIS & URAIAN PEKERJAN KOEFISIEN
ANALISA
1 2 3
L.007a Pekerja 0.714
L.009a Mandor 0.071
M.111 Agregat Pokok Lapen 1.822
M.009 Aspal Penetrasi 60/70 80.000
M.005a Kayu Bakar 0.300
E.16 Three Wheel Roller 6 - 8 T 0.046
E.03 Aphalt Sprayer 0.292
Ls.022 Alat bantu 1.000
JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN D
OVERHEAD & PROFIT E
HARGA SATUAN PEKERJAAN ( D + E )
Q3 - 016 Lapis Penetrasi Makadam Sheet
L.007a Pekerja 1.045
L.009a Mandor 0.039
M.111 Agregat Pokok Lapen 0.049
M.112 Agregat Pengunci Lapen 0.015
M.001h3 Batu pecah 0,2 - 0,5 cm 0.010
M.009 Aspal Penetrasi 60/70 4.500
M.005a Kayu Bakar 0.050
E.16 Three Wheel Roller 6 - 8 T 0.003
E.03 Aphalt Sprayer 0.012
Ls.005 Alat bantu 1.000
JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN D
ANALISA HARGA SATUAN PEKERJAA

KODE
JENIS & URAIAN PEKERJAN KOEFISIEN
ANALISA
1 2 3
OVERHEAD & PROFIT E
HARGA SATUAN PEKERJAAN ( D + E )
Q3 - 017 Latasir ( Sand Sheet )
L.007a Pekerja 1.166
L.009a Mandor 0.056
M.005a Kayu Bakar 0.018
M.001h3 Batu pecah 02 - 0,5 cm 0.020
M.009 Aspal penetrasi 60/70 2.500
E.16 Three Wheel Roller 6 - 8 T 0.002
Ls.003 Alat bantu 1.000
JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN D
OVERHEAD & PROFIT E
HARGA SATUAN PEKERJAAN ( D + E )
ANALISA HARGA SATUAN PEKERJAA

KODE
JENIS & URAIAN PEKERJAN KOEFISIEN
ANALISA
1 2 3
Q3 - 022 Acuan (Begisting) utk Jbt / gorong-gorong
L.007a Pekerja 2.450
L.005a Tukang 1.400
L.009a Mandor 0.350
M.005 Kayu Perancah 0.030
M.006 Paku Biasa ( 2" - 5") 0.200
Ls.009 Alat bantu 1.000
JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN D
OVERHEAD & PROFIT E
HARGA SATUAN PEKERJAAN ( D + E )
Q2 - 024 Membongkar 1 m3 pasangan batu
L.007 Pekerja 2.000
L.009 Mandor 0.100
JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN D
OVERHEAD & PROFIT E
HARGA SATUAN PEKERJAAN ( D + E )
ANALISA HARGA SATUAN PEKERJAAN

JENIS & URAIAN PEKERJAN KOEFISIEN SAT HRG SAT(Rp)

2 3 4 5
Resap Pengikat LITER
a 0.030 Jam
r 0.006 Jam
Penetrasi 60/70 0.629 Kg
ne / Minyak Tanah 0.489 Ltr
Sprayer 0.003 Jam
essor 4000-6000 L/M 0.003 Jam
Truck 3 - 4 M3 0.003 Jam
AH HARGA TENAGA, BAHAN DAN PERALATAN D
HEAD & PROFIT E
A SATUAN PEKERJAAN ( D + E )
Perekat LITER
a 0.030 Jam
r 0.006 Jam
Penetrasi 60/70 0.872 Kg
ne / Minyak Tanah 0.253 Ltr
Sprayer 0.003 Jam
essor 4000-6000 L/M 0.006 Jam
Truck 3 - 4 M3 0.003 Jam
AH HARGA TENAGA, BAHAN DAN PERALATAN D
HEAD & PROFIT E
A SATUAN PEKERJAAN ( D + E )
Penetrasi Makadam (Leveling) M3
ANALISA HARGA SATUAN PEKERJAAN

JENIS & URAIAN PEKERJAN KOEFISIEN SAT HRG SAT(Rp)

2 3 4 5
a 0.714 Jam
r 0.071 Jam
at Pokok Lapen 1.822 M3
Penetrasi 60/70 80.000 Kg
Bakar 0.300 M3
Wheel Roller 6 - 8 T 0.046 Jam
Sprayer 0.292 Jam
ntu 1.000 Ls
AH HARGA TENAGA, BAHAN DAN PERALATAN D
HEAD & PROFIT E
A SATUAN PEKERJAAN ( D + E )
Penetrasi Makadam Sheet M2
a 1.045 Jam
r 0.039 Jam
at Pokok Lapen 0.049 M3
at Pengunci Lapen 0.015 M3
ecah 0,2 - 0,5 cm 0.010 M3
Penetrasi 60/70 4.500 Kg
Bakar 0.050 M3
Wheel Roller 6 - 8 T 0.003 Jam
Sprayer 0.012 Jam
ntu 1.000 Ls
AH HARGA TENAGA, BAHAN DAN PERALATAN D
ANALISA HARGA SATUAN PEKERJAAN

JENIS & URAIAN PEKERJAN KOEFISIEN SAT HRG SAT(Rp)

2 3 4 5
HEAD & PROFIT E
A SATUAN PEKERJAAN ( D + E )
r ( Sand Sheet ) M2
a 1.166 Jam
r 0.056 Jam
Bakar 0.018 M3
ecah 02 - 0,5 cm 0.020 M3
penetrasi 60/70 2.500 Kg
Wheel Roller 6 - 8 T 0.002 Jam
ntu 1.000 Ls
AH HARGA TENAGA, BAHAN DAN PERALATAN D
HEAD & PROFIT E
A SATUAN PEKERJAAN ( D + E )
ANALISA HARGA SATUAN PEKERJAAN

JENIS & URAIAN PEKERJAN KOEFISIEN SAT HRG SAT(Rp)

2 3 4 5
(Begisting) utk Jbt / gorong-gorong M2
a 2.450 Jam
g 1.400 Jam
r 0.350 Jam
Perancah 0.030 M3
Biasa ( 2" - 5") 0.200 Kg
ntu 1.000 Set
AH HARGA TENAGA, BAHAN DAN PERALATAN D
HEAD & PROFIT E
A SATUAN PEKERJAAN ( D + E )
ongkar 1 m3 pasangan batu M3
a 2.000 OH
r 0.100 OH
AH HARGA TENAGA, BAHAN DAN PERALATAN D
HEAD & PROFIT E
A SATUAN PEKERJAAN ( D + E )
ANALISA HARGA SATUAN PEKERJAA

KODE
JENIS & URAIAN PEKERJAN KOEFISIEN
ANALISA
1 2 3
Q3 - 007 Mengurug 1 M3 Sirtu
L.007a Pekerja 0.071
L.009a Mandor 0.018
M.001d Sirtu 1.200
E.13 Motor Grader 0.006
E.19 Vibratory Roller 0.010
E.23 Water Tank Truck 2000-4500L 0.007
Ls.008 Alat bantu 1.000
JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN D
OVERHEAD & PROFIT E
HARGA SATUAN PEKERJAAN ( D + E )
ANALISA HARGA SATUAN PEKERJAAN

JENIS & URAIAN PEKERJAN KOEFISIEN SAT HRG SAT(Rp)

2 3 4 5
urug 1 M3 Sirtu M3
a 0.071 Jam
r 0.018 Jam
1.200 M3
Grader 0.006 Jam
ry Roller 0.010 Jam
Tank Truck 2000-4500L 0.007 Jam
ntu 1.000 Ls
AH HARGA TENAGA, BAHAN DAN PERALATAN D
HEAD & PROFIT E
A SATUAN PEKERJAAN ( D + E )
ANALISA HARGA SATUAN PEKERJAA

KODE
JENIS & URAIAN PEKERJAN KOEFISIEN
ANALISA
1 2 3
G. PEKERJAAN BETON
G2 - 001 Cetakan Beton
M.005 Kayu Tahun 0.040
M.006 Paku Biasa ( 2" - 5") 0.400
L.002 Tukang Kayu 0.500
L.006 Kepala Tukang 0.050
L.007 Pekerja 0.200
L.009 Mandor 0.010
L.007 Pekerja Bongkar / Siram 0.400
JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN D
OVERHEAD & PROFIT (10%) E
HARGA SATUAN PEKERJAAN ( D + E )
G1 - 002 Memasang Bekisting untuk Pondasi
M.005 Kayu Tahun 0.040
M.006 Paku Biasa (2" - 5") 0.300
L.007 Pekerja 0.300
L.002 Tukang Kayu 0.260
L.006 Kepala Tukang 0.026
L.009 Mandor 0.005
JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN D
OVERHEAD & PROFIT (10%) E
HARGA SATUAN PEKERJAAN ( D + E )
G1 - 003 Memasang Bekisting untuk Sloof
ANALISA HARGA SATUAN PEKERJAA

KODE
JENIS & URAIAN PEKERJAN KOEFISIEN
ANALISA
1 2 3
M.005 Kayu Tahun 0.045
M.006 Paku Biasa (2" - 5") 0.300
L.007 Pekerja 0.300
L.002 Tukang Kayu 0.260
L.006 Kepala Tukang 0.026
L.009 Mandor 0.005
G1 - 009 Pembesian dengan Besi Beton Polos
M.003 Besi Beton Polos 1.050
M.003a Kawat bindrat 0.015
L.007 Pekerja 0.007
L.003 Tukang Besi 0.007
L.006 Kepala Tukang 0.001
L.009 Mandor 0.000
JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN D
OVERHEAD & PROFIT (10%) E
HARGA SATUAN PEKERJAAN ( D + E )
G1 - 010 Pembesian dengan Besi Beton Ulir
M.003b Besi Beton Ulir 1.050
M.003a Kawat bindrat 0.015
L.007 Pekerja 0.007
L.003 Tukang Besi 0.007
L.006 Kepala Tukang 0.001
L.009 Mandor 0.000
ANALISA HARGA SATUAN PEKERJAA

KODE
JENIS & URAIAN PEKERJAN KOEFISIEN
ANALISA
1 2 3
Membuat Beton Tumbuk 1 Portland Cement : 3 Ps : 5
G1 - 011
Kerikil
M.002a Portland Cement 218.000
M.001 Pasir Beton 0.520
M.001h Koral Beton ( Batu pecah 2/3 cm ) 0.870
L.007 Pekerja 1.650
L.001 Tukang Batu 0.250
L.006 Kepala Tukang 0.025
L.009 Mandor 0.080
Membuat Lantai Kerja Beton Tumbuk 1 Portland Cement :
G1 - 012
3 Ps : 5 Kerikil tebal 5 cm
M.002a Portland Cement 10.000
M.001 Pasir Beton 0.026
M.001h Koral Beton ( Batu pecah 2/3 cm ) 0.044
L.007 Pekerja 1.150
L.001 Tukang Batu 0.020
L.006 Kepala Tukang 0.002
L.009 Mandor 0.006

G1 - 013 Membuat Beton Cor 1 Portland Cement : 2 Ps : 2,5 Kerikil

M.002a Portland Cement 352.000


M.001 Pasir Beton 0.560
M.001h Koral Beton ( Batu pecah 2/3 cm ) 0.700
L.007 Pekerja 1.650
L.001 Tukang Batu 0.250
ANALISA HARGA SATUAN PEKERJAA

KODE
JENIS & URAIAN PEKERJAN KOEFISIEN
ANALISA
1 2 3
L.006 Kepala Tukang 0.025
L.009 Mandor 0.080

G1 - 014 Membuat Beton Cor 1 Portland Cement : 2 Ps : 3 Kerikil

M.002a Portland Cement 336.000


M.001 Pasir Beton 0.540
M.001h Koral Beton ( Batu pecah 2/3 cm ) 0.810
L.007 Pekerja 2.000
L.001 Tukang Batu 0.350
L.006 Kepala Tukang 0.035
L.009 Mandor 1.000
G3 - 018 Beton K-125
L.007a Pekerja 5.301
L.005a Tukang 1.767
L.009a Mandor 0.442
M.002a Portland Cement 50 kg 256.250
M.001 Pasir Beton 0.427
M.100 Agregat Kasar Beton 0.712
E.06 Concrete Mixer 0,125 M3 0.442
E.20 Concrete Vibrator 0.442
E.23 Water Tank Truck 2000-4500L 0.046
Ls.010 Alat bantu 1.000
JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN D
OVERHEAD & PROFIT E
ANALISA HARGA SATUAN PEKERJAA

KODE
JENIS & URAIAN PEKERJAN KOEFISIEN
ANALISA
1 2 3
HARGA SATUAN PEKERJAAN ( D + E )
G3 - 019 Beton K-250
L.007a Pekerja 5.301
L.005a Tukang 1.767
L.009a Mandor 0.442
M.002a Portland Cement 50 kg 354.808
M.001 Pasir Beton 0.444
M.100 Agregat Kasar Beton 0.641
E.06 Concrete Mixer 0,125 M3 0.442
E.20 Concrete Vibrator 0.442
E.23 Water Tank Truck 2000-4500L 0.053
Ls.010 Alat bantu 1.000
JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN D
OVERHEAD & PROFIT E
HARGA SATUAN PEKERJAAN ( D + E )
G3- 035 Beton CYCLOP
L.007a Pekerja 4.819
L.005a Tukang 1.606
L.009a Mandor 0.803
M.002a Portland Cement 50 kg 187.690
M.001 Pasir Beton 0.280
M.100 Agregat Kasar Beton 0.618
M.001f Batu Belah 0.540
ANALISA HARGA SATUAN PEKERJAA

KODE
JENIS & URAIAN PEKERJAN KOEFISIEN
ANALISA
1 2 3
E.06 Concrete Mixer 0,125 M3 0.803
E.20 Concrete Vibrator 0.803
E.23 Water Tank Truck 2000-4500L 0.058
Ls.010 Alat bantu 1.000
JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN D
OVERHEAD & PROFIT E
HARGA SATUAN PEKERJAAN ( D + E )
ANALISA HARGA SATUAN PEKERJAAN

JENIS & URAIAN PEKERJAN KOEFISIEN SAT HRG SAT(Rp)

2 3 4 5
ETON
an Beton M2
ahun 0.040 M3
Biasa ( 2" - 5") 0.400 Kg
g Kayu 0.500 OH
Tukang 0.050 OH
a 0.200 OH
dor 0.010 OH
a Bongkar / Siram 0.400 OH
AH HARGA TENAGA, BAHAN DAN PERALATAN D
HEAD & PROFIT (10%) E
A SATUAN PEKERJAAN ( D + E )
sang Bekisting untuk Pondasi M2
ahun 0.040 M3
Biasa (2" - 5") 0.300 Kg
a 0.300 OH
g Kayu 0.260 OH
Tukang 0.026 OH
dor 0.005 OH
AH HARGA TENAGA, BAHAN DAN PERALATAN D
HEAD & PROFIT (10%) E
A SATUAN PEKERJAAN ( D + E )
sang Bekisting untuk Sloof M2
ANALISA HARGA SATUAN PEKERJAAN

JENIS & URAIAN PEKERJAN KOEFISIEN SAT HRG SAT(Rp)

2 3 4 5
ahun 0.045 M3
Biasa (2" - 5") 0.300 Kg
a 0.300 OH
g Kayu 0.260 OH
Tukang 0.026 OH
dor 0.005 OH
esian dengan Besi Beton Polos Kg
eton Polos 1.050 Kg
bindrat 0.015 Kg
a 0.007 OH
g Besi 0.007 OH
Tukang 0.001 OH
dor 0.000 OH
AH HARGA TENAGA, BAHAN DAN PERALATAN D
HEAD & PROFIT (10%) E
A SATUAN PEKERJAAN ( D + E )
esian dengan Besi Beton Ulir Kg
eton Ulir 1.050 Kg
bindrat 0.015 Kg
a 0.007 OH
g Besi 0.007 OH
Tukang 0.001 OH
dor 0.000 OH
ANALISA HARGA SATUAN PEKERJAAN

JENIS & URAIAN PEKERJAN KOEFISIEN SAT HRG SAT(Rp)

2 3 4 5
uat Beton Tumbuk 1 Portland Cement : 3 Ps : 5
M3

d Cement 218.000 Kg
Beton 0.520 M3
Beton ( Batu pecah 2/3 cm ) 0.870 M3
a 1.650 OH
g Batu 0.250 OH
Tukang 0.025 OH
dor 0.080 OH
uat Lantai Kerja Beton Tumbuk 1 Portland Cement :
M3
5 Kerikil tebal 5 cm
d Cement 10.000 Kg
Beton 0.026 M3
Beton ( Batu pecah 2/3 cm ) 0.044 M3
a 1.150 OH
g Batu 0.020 OH
Tukang 0.002 OH
dor 0.006 OH

uat Beton Cor 1 Portland Cement : 2 Ps : 2,5 Kerikil M3

d Cement 352.000 Kg
Beton 0.560 M3
Beton ( Batu pecah 2/3 cm ) 0.700 M3
a 1.650 OH
g Batu 0.250 OH
ANALISA HARGA SATUAN PEKERJAAN

JENIS & URAIAN PEKERJAN KOEFISIEN SAT HRG SAT(Rp)

2 3 4 5
Tukang 0.025 OH
dor 0.080 OH

uat Beton Cor 1 Portland Cement : 2 Ps : 3 Kerikil M3

d Cement 336.000 Kg
Beton 0.540 M3
Beton ( Batu pecah 2/3 cm ) 0.810 M3
a 2.000 OH
g Batu 0.350 OH
Tukang 0.035 OH
dor 1.000 OH
K-125 M3
a 5.301 Jam
g 1.767 Jam
r 0.442 Jam
d Cement 50 kg 256.250 kg
Beton 0.427 M3
at Kasar Beton 0.712 M3
ete Mixer 0,125 M3 0.442 Jam
ete Vibrator 0.442 Jam
Tank Truck 2000-4500L 0.046 Jam
ntu 1.000 Ls
AH HARGA TENAGA, BAHAN DAN PERALATAN D
HEAD & PROFIT E
ANALISA HARGA SATUAN PEKERJAAN

JENIS & URAIAN PEKERJAN KOEFISIEN SAT HRG SAT(Rp)

2 3 4 5
A SATUAN PEKERJAAN ( D + E )
K-250 M3
a 5.301 Jam
g 1.767 Jam
r 0.442 Jam
d Cement 50 kg 354.808 kg
Beton 0.444 M3
at Kasar Beton 0.641 M3
ete Mixer 0,125 M3 0.442 Jam
ete Vibrator 0.442 Jam
Tank Truck 2000-4500L 0.053 Jam
ntu 1.000 Ls
AH HARGA TENAGA, BAHAN DAN PERALATAN D
HEAD & PROFIT E
A SATUAN PEKERJAAN ( D + E )
CYCLOP M3
a 4.819 Jam
g 1.606 Jam
r 0.803 Jam
d Cement 50 kg 187.690 kg
Beton 0.280 M3
at Kasar Beton 0.618 M3
elah 0.540 M3
ANALISA HARGA SATUAN PEKERJAAN

JENIS & URAIAN PEKERJAN KOEFISIEN SAT HRG SAT(Rp)

2 3 4 5
ete Mixer 0,125 M3 0.803 Jam
ete Vibrator 0.803 Jam
Tank Truck 2000-4500L 0.058 Ls
ntu 1.000 Ls
AH HARGA TENAGA, BAHAN DAN PERALATAN D
HEAD & PROFIT E
A SATUAN PEKERJAAN ( D + E )
A.4.2.1 HARGA SATUAN PEKERJAAN BESI

A.4.2.1.1. Pemasangan 1 kg besi profil


Harga Satuan
No Uraian Kode Satuan Koefisien (Rp)

A TENAGA
Pekerja L.01 OH 0.06
Tukang Las L.03 OH 0.06
Kepala tukang L.03 OH 0.006
Mandor L.04 OH 0.003
JUMLAH TENAGA KERJA
B BAHAN
Besi Profil Kg 1.0
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Maksimal 15 %) xD
F Harga Satuan Pekerjaan (D+E)

A.4.2.1.1.B Pemasangan 1 kg Besi plat baja


Harga Satuan
No Uraian Kode Satuan Koefisien (Rp)

A TENAGA
Pekerja L.01 OH 0.06
Tukang Las L.03 OH 0.06
Kepala tukang L.03 OH 0.006
Mandor L.04 OH 0.003
JUMLAH TENAGA KERJA
B BAHAN
Besi plat baja Kg 1.0
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Maksimal 15 %) xD
F Harga Satuan Pekerjaan (D+E)

A.4.2.1.2. Pemasangan 1 kg rangka baja IWF


Harga Satuan
No Uraian Kode Satuan Koefisien (Rp)

A TENAGA
Pekerja L.01 OH 0.06
Tukang Las L.03 OH 0.06
Kepala tukang L.03 OH 0.006
Mandor L.04 OH 0.003
JUMLAH TENAGA KERJA
B BAHAN
Besi Baja IWF Kg 1.0
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Maksimal 15 %) xD
F Harga Satuan Pekerjaan (D+E)

A.4.2.1.5. Pengerjaan 1 cm pengelasan dengan las listrik


Harga Satuan
No Uraian Kode Satuan Koefisien (Rp)

A TENAGA
Pekerja L.01 OH 0.004
Tukang Las L.03 OH 0.002
Kepala tukang L.03 OH 0.0002
Mandor L.04 OH 0.0002
JUMLAH TENAGA KERJA
B BAHAN
Kawat las listrik Kg 0.04
Solar Liter 0.03
Minyak pelumas Liter 0.004
JUMLAH HARGA BAHAN
C PERALATAN
Sewa alat las Jam 0.017
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Maksimal 15 %) xD
F Harga Satuan Pekerjaan (D+E)
Jumlah
Harga
(Rp)

-
-
-
-
-

-
-

-
-

-
-
-

Jumlah
Harga
(Rp)

-
-
-
-
-

-
-

-
-

-
-
-

Jumlah
Harga
(Rp)

-
-
-
-
-
-
-

-
-

-
-
-

Jumlah
Harga
(Rp)

-
-
-
-
-

-
-
-
-

-
-

-
-
-
KATEGORI I (MUDAH)

A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING

A.4.4.1.9 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP :4PP
Harga Satuan
No Uraian Kode Satuan Koefisien (Rp)

A TENAGA
Pekerja L.01 OH 0.3
Tukang Batu L.02 OH 0.1
Kepala Tukang L.03 OH 0.01
Mandor L.04 OH 0.015
JUMLAH TENAGA KERJA
B BAHAN
Bata merah bh 70
PC Kg 11.5
Pasir Pasang m3 0.043
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Maksimal 15 %) xD
F Harga Satuan Pekerjaan (D+E)

27
KATEGORI I (MUDAH)

Jumlah
Harga
(Rp)

-
-
-
-
-

-
-
-
-

-
-

28
KATEGORI I (MUDAH)

A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN

29
KATEGORI I (MUDAH)

A.4.4.2.4. Pemasangan 1 m2 plesteran 1SP : 4PP tebal 15 mm


Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L.01 OH 0.3 -
Tukang Batu L.03 OH 0.15 -
Kepala Tukang L.03 OH 0.015 -
Mandor L.04 OH 0.015 -
JUMLAH TENAGA KERJA -
B BAHAN
PC Kg 6.24 -
Pasir Pasang m3 0.024 -
JUMLAH HARGA BAHAN -
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit (Maksimal 15 %) xD
Harga Satuan
F -
Pekerjaan (D+E)

30
A.5.1.1 HARGA SATUAN PEKERJAAN PEMASANGAN PIPA

A.5.1.1.29. Pemasangan 1 m’ pipa PVC tipe AW diameter 2”


Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L.01 OH 0.054 -
Tukang batu L.02 0.09 -
Kepala tukang L.03 0.009 -
Mandor L.04 OH 0.003 -
JUMLAH TENAGA KERJA -
B BAHAN
Pipa PVC 2” tipe AW M 1.2 -
Perlengkapan (35% x
Ls 35% -
pipa)
JUMLAH HARGA BAHAN -
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) -
E Overhead & Profit (Maksimal 15 %) xD
Harga Satuan
F -
Pekerjaan (D+E)