2 POER PONDASI (P1) Pjg = 0.80 m 2 Beton 0.80 x 0.80 x 0.30 x 28.00 m3 5.38
L = 0.80 m Besi (Tul mmng / atas) 0.85 x 1.12 x 5.00 x 28.00 Kg 133.28
0.05 0.75 0.05 Tebal = 0.30 m Besi (Tul mmng / Bawah) 1.35 x 1.12 x 5.00 x 28.00 Kg 211.68
0.25 0.25 0.30 m Jml = 28.00 Ttk Besi (Tul mltg / atas) 0.85 x 1.12 x 5.00 x 28.00 Kg 133.28
0.75 Tul. Pokok (mmnjg) = f 14 - 18 Besi (Tul mmng / Bawah) 1.35 x 1.12 x 5.00 x 28.00 Kg 211.68
0.80 m Jumlah Tul mmnjg = 5.00 Bekisting 3.20 x 0.30 x 28.00 m2 26.88
Tul. Pokok (mltg) = f 14 - 18 Pasir Urug 0.80 x 0.80 x 0.05 x 28.00 m3 0.90
Jumlah Tul mltg = 5.00 Galian 1.30 x 1.30 x 0.50 x 28.00 m3 23.66 23.66
0.05 0.75 0.05 Tebal Pasir urug = 5.00 cm JML 5.38 23.66 689.92 26.88 - - 24.56
0.25 0.25 0.30 m
0.75 Kedalamn Galian = 0.50 m
0.80 m
PERHITUNGAN VOLUME
PROGRAM : PEMBANGUNAN RUMAH TINGGAL 2
PEKERJAAN : PEMBANGUNAN RUMAH TINGGAL 2 LANTAI, Dra. LILIS LESTARI
LOKASI : JL. KHR. MOCH. ROSYID. BOJONEGORO
3 KOLOM 20/15 (K1) Pjg = 4.00 3 Beton 4.00 x 0.20 x 0.15 x 15.00 m3 1.80
b = 0.20 m Besi (Tul Pokok) 4.55 x 0.62 x 6.00 x 15.00 Kg 252.66
h = 0.15 Besi (Tul bagi) 0.60 x 0.22 x 28.00 x 15.00 Kg 55.44
Jml = 15.00 Ttk Bekisting 0.70 x 4.00 x 15.00 m² 42.00
Tul. Pokok = f 10 Benangan 4.00 x 4.00 x 15.00 m' 240.00
Jumlah Tul Pokok = 6.00 Plesteran 0.70 x 4.00 m² 2.8
Tul. Bagi = f 6 - 15 CAT 0.70 x 4.00 m² 2.8
Jumlah Tul bagi = 28.00 1.80 308.10 42.00 2.80 240.00 2.80
tebal Poer = 0.30 m
Panjang Penyaluran (ke poer) = 0.30 m
4 KOLOM 15/15 (K2) Pjg = 4.50 4 Beton 4.50 x 0.15 x 0.15 x 19.00 m3 1.92
b = 0.15 m Besi (Tul Pokok) 5.05 x 0.62 x 4.00 x 19.00 Kg 236.80
h = 0.15 Besi (Tul bagi) 0.50 x 0.22 x 31.00 x 19.00 Kg 64.79
Jml = 19.00 Ttk Bekisting 0.60 x 4.50 x 19.00 m² 51.30
Tul. Pokok = f 10 Benangan 4.00 x 4.50 x 19.00 m' 342.00
Jumlah Tul Pokok = 4.00 Plesteran 0.60 x 4.50 m² 2.7
Tul. Bagi = f 6 - 15 CAT 0.60 x 4.50 m² 2.7
Jumlah Tul bagi = 31.00 1.92 301.59 51.30 2.70 342.00 2.70
tebal Poer = 0.30 m
Panjang Penyaluran (ke poer) = 0.30 m
5 KOLOM PRAKTIS (K3)
Pjg = 3.50 m 6 Beton 3.50 x 0.15 x 0.15 x 19.00 m3 1.50
b = 0.15 m Besi (Tul Pokok 1) 3.50 x 0.89 x 4.00 x 19.00 Kg 236.21
h = 0.15 m Besi (Tul Pokok 2) 0.15 x 0.62 x 6.00 x 19.00 Kg 10.55
Jml = 19.00 Ttk Besi (Tul bagi) 38.20 x 0.22 x 24.00 x 19.00 Kg 3,832.22
Tul. Pokok (1) = f 12 Bekisting 38.30 x 3.50 x 19.00 m² 2,546.95
Tul. Pokok (2) = f 10 Benangan 4.00 x 3.50 x 19.00 m' 266.00
Jumlah Tul Pokok (1) = 6.00 Plesteran 38.30 x 3.50 m² 134.05
Jumlah Tul Pokok (2) = 2.00 CAT 38.30 x 3.50 m² 134.05
Tul. Bagi = f 8 - 15 1.50 4,078.98 2,546.95 134.05 266.00 134.05
Jumlah Tul bagi = 2.00
tebal Poer = 0.30 m
Panjang Penyaluran (ke poer) = 0.30 m
6 KOLOM PRAKTIS Pjg = 3.50 m Beton 3.50 x 0.15 x 0.15 x 19.00 m3 1.50
b = 0.15 m Besi (Tul Pokok) 3.75 x 0.89 x 4.00 x 19.00 Kg 253.08
h = 0.15 m Besi (Tul bagi) 0.50 x 0.22 x 24.00 x 19.00 Kg 50.16
Jml = 19.00 Ttk Bekisting 0.60 x 0.62 x 19.00 m² 7.03
Tul. Pokok = f 12 Benangan 4.00 x 3.50 x 19.00 m' 266.00
Jumlah Tul Pokok = 4.00 Plesteran 0.60 x 3.50 m² 2.1
Tul. Bagi = f 6 - 15 CAT 0.60 x 3.50 m² 2.1
Jumlah Tul bagi = 24.00 1.50 303.24 7.03 2.10 266.00 2.10
tebal Poer = 0.30 m
Panjang Penyaluran (ke poer) = - m
PERHITUNGAN VOLUME
NAMA KEGIATAN : PEMBANGUNAN RUMAH TINGGAL 3
PEKERJAAN : PEMBANGUNAN RUMAH TINGGAL 2 LANTAI, Dra. LILIS LESTARI
LOKASI : JL. KHR. MOCH. ROSYID. BOJONEGORO
7 BALOK SLOOF 20/30 (S1) L = 1.00 m 7 Beton 1.00 x 0.25 x 0.40 x 52.77 m³ 5.28
(di hitung volume per m') b = 0.25 m Besi (Tul Pokok 1) 1.00 x 1.04 x 5.00 x 52.77 Kg 274.40
h = 0.40 m Besi (Tul Pokok 2) 0.25 x 0.40 x 4.00 x 52.77 Kg 20.84
Tul. Pokok (1) = f 13 Besi (Tul bagi) 1.20 x 0.22 x 8.00 x 52.77 Kg 111.45
Tul. Pokok (2) = f 8 Bekisting 1.05 x 1.00 x 52.77 m² 55.41
Jumlah Tul Pokok (1) = 5.00
Jumlah Tul Pokok (2) = 4.00 -
Tul. Bagi = f 6 - 15 5.28 406.70
Jumlah Tul bagi = 8.00
Panjang Total = 52.77 m
8 BALOK SLOOF 20/30 (S2) L = 1.00 m 8 Beton 1.00 x 0.20 x 0.30 x 21.66 m³ 1.30
(di hitung volume per m') b = 0.20 m Besi (Tul Pokok 1) 1.00 x 0.89 x 4.00 x 21.66 Kg 76.94
h = 0.30 m Besi (Tul Pokok 2) 0.20 x 0.40 x 3.00 x 21.66 Kg 5.13
Tul. Pokok (1) = f 12 Besi (Tul bagi) 0.90 x 0.22 x 8.00 x 21.66 Kg 34.31
Tul. Pokok (2) = f 8 Bekisting 0.80 x 1.00 x 21.66 m² 17.33
Jumlah Tul Pokok (1) = 4.00 -
Jumlah Tul Pokok (2) = 3.00
Tul. Bagi = f 6 - 15 1.30 116.38 17.33
Jumlah Tul bagi = 8.00
Panjang Total = 21.66 m
9 BALOK INDUK 25/40 (B1) L = 1.00 m 9 Beton 1.00 x 0.25 x 0.40 x 30 m³ 3.00
(di hitung volume per m') b = 0.25 m Besi (Tul Pokok 1) 1.00 x 0.89 x 6.00 x 30 Kg 159.84
h = 0.40 m Besi (Tul Pokok 2) 0.25 x 0.62 x 4.00 x 30 Kg 18.51
Tul. Pokok (1) = f 12 Besi (Tul bagi) 1.20 x 0.22 x 8.00 x 30 Kg 63.36
Tul. Pokok (2) = f 10 Bekisting 1.05 x 1.00 x 30 m2 31.50
Jumlah Tul Pokok (1) = 6.00 Plesteran 1.05 x 1.00 m2 1.05
Jumlah Tul Pokok (2) = 4.00 CAT 1.05 x 1.00 m2 1.05
Tul. Bagi = f 6 - 15 3.00 241.71 31.50 1.05 - 1.05
Jumlah Tul bagi = 6.00
Panjang Total = 30 m
10 BALOK 20/30 (B2) L = 1.00 m 10 Beton 1.00 x 0.20 x 0.30 x 3.12 m³ 0.19
(di hitung volume per m') b = 0.20 m Besi (Tul Pokok 1) 1.00 x 0.89 x 5.00 x 3.12 Kg 13.85
h = 0.30 m Besi (Tul Pokok 2) 0.20 x 0.62 x 2.00 x 3.12 Kg 0.77
Tul. Pokok (1) = f 12 Besi (Tul bagi) 0.90 x 0.22 x 8.00 x 3.12 Kg 4.94
Tul. Pokok (2) = f 10 Bekisting 0.80 x 1.00 x 3.12 m² 2.50
Jumlah Tul Pokok (1) = 5.00 Plesteran 0.80 x 1.00 m² 0.8
Jumlah Tul Pokok (2) = 2.00 CAT 0.80 x 1.00 m² 0.8
Tul. Bagi = f 6 - 15 0.19 19.56 2.50 0.8 0.8
Jumlah Tul bagi = 8.00
Panjang Total = 3.12 m
11 RING BALOK 15/20 L = 1.00 m 11 Beton 1.00 x 0.15 x 0.20 x 72.20 m³ 2.17
(di hitung volume per m') b = 0.15 Besi (Tul Pokok) 1.00 x 0.62 x 2.00 x 72.20 Kg 89.09
h = 0.20 m Besi (Tul bagi) 0.60 x 0.22 x 8.00 x 72.20 Kg 76.24
Tul. Pokok = f 10 Bekisting 0.55 x 1.00 x 72.20 m2 39.71
Jumlah Tul Pokok = 2.00 Plesteran 1.30 x 1.00 m² 1.3
Tul. Bagi = f 6 - 15 CAT 1.30 x 1.00 m² 1.3
Jumlah Tul bagi = 8.00 2.17 165.34 39.71 1.3 1.3
Panjang Total = 72.20 m
12 BALOK 15/25 ( B3) L = 1.00 m 12 Beton 1.00 x 0.15 x 25.00 x 8.25 m³ 30.94
(di hitung volume per m') b = 0.15 m Besi (Tul Pokok 1) 1.00 x 0.89 x 5.00 x 8.25 Kg 36.63
h = 25.00 m Besi (Tul Pokok 2) 0.15 x 0.62 x 2.00 x 8.25 Kg 1.53
Tul. Pokok (1) = f 12 Besi (Tul bagi) 50.20 x 0.22 x 8.00 x 8.25 Kg 728.90
Tul. Pokok (2) = f 10 Bekisting 50.15 x 1.00 x 8.25 m² 413.74
Jumlah Tul Pokok (1) = 5.00 Plesteran 50.15 x 1.00 m² 50.15
Jumlah Tul Pokok (2) = 2.00 CAT 50.15 x 1.00 m² 50.15
Tul. Bagi = f 6 - 15 30.94 767.06 413.74 50.15 50.15
Jumlah Tul bagi = 8.00
Panjang Total = 8.25 m
13 BALOK 15/20 ( B4) L = 1.00 m 13 Beton 1.00 x 0.15 x 0.20 x 22.50 m³ 0.68
(di hitung volume per m') b = 0.15 Besi (Tul Pokok) 1.00 x 0.62 x 4.00 x 22.50 Kg 55.53
h = 0.20 m Besi (Tul bagi) 0.60 x 0.22 x 8.00 x 22.50 Kg 23.76
Tul. Pokok = f 10 Bekisting 0.55 x 1.00 x 22.50 m2 12.38
Jumlah Tul Pokok = 4.00 Plesteran 1.30 x 1.00 m² 1.3
Tul. Bagi = f 6 - 15 CAT 1.30 x 1.00 m² 1.3
Jumlah Tul bagi = 8.00 0.68 79.29 12.38 1.3 1.3
Panjang Total = 22.50 m
Pekerjaan Pasangan keramik LEBAR PANJANG JUMLAH KOREKSI KRAMIK 40X40 VOLUME SATUAN
Pasangan keramik lantai 40x40 cm Lt.1 dan Lt.2 3 3.5 1 10.5
- Ruang Tamu Lt.1 3 3.5 1 10.5 M2
- Ruang Keluarga Lt.2 5.1 2.43 1 12.393 M2
- Ruang Tidur Lt.1 3 3 1 9 M2
- Ruang Tidur Lt.2 3 3 2 18 M2
- Ruang Santai 2.5 6.5 1 16.25 M2
- Ruang Teras Lt.1 3.4 2 1 6.8 M2
- Balkon Lt.2 3.4 2 1 6.8 M2
TOTAL 72.94 M2
Pekerjaan Pasangan keramik LEBAR PANJANG JUMLAH KOREKSI KRAMIK 30X30 VOLUME SATUAN
- Gudang Lt.1 2.5 4 1 10
- Ruang Kamar mandi/wc Lt.1 1.38 1.88 2 5.1888 M2
0.86 3.19 1 2.7434 M2
TOTAL 17.93 M2
Pekerjaan Pasangan keramik Dinding LEBAR PANJANG JUMLAH KOREKSI KUSEN VOLUME SATUAN
Pasangan keramik dinding km/wc 25x20 cm 1.5 2 2 6.00 M2
Pasangan keramik tangga 30x30 cm 8 1.5 1 12.00 M2
Pasangan Lis keramik dinding km/wc 10x20 cm 2.5 2.5 12 3.80 M1
TOTAL 21.80 M1
Pekerjaan Pasangan Plafon LEBAR PANJANG JUMLAH KOREKSI PLAFON VOLUME SATUAN
Pasangan Plafon Lt. 1 1.00 1.00 1 7.50 1.00 M2
Pasangan Rangka Plafon Lt. 1 1.00 1.00 1 - 1.00 M2
Pasangan Plafon Lt. 2 1.00 1.00 1 - 1.00 M2
Pasangan Rangka Plafon Lt. 2 1.00 1.00 1 - 1.00 M2
TOTAL 4.00 M2
Pekerjaan Pasangan Dinding PANJANG TINGGI JUMLAH KOREKSI KUSEN VOLUME SATUAN