RENCANA ANGGARAN BIAYA

Pekerjaan : Pembangunan Gedung Baru dan Rehabilitasi Sarana dan Prasarana Balai Bibit Ikan
Lokasi : Jl. Bungan Ganyong Kel. Ladang Bambu
Kecamatan : Medan Tuntungan

NO URAIAN PEKERJAAN VOLUME SAT ANALISA

A PEKERJAAN PENDAHULUAN
1 Papan nama proyek 1.000 bh Taksir
2 Photo Dokumentasi - - "
3 P3K / Keamanan - - "
4 Gudang kerja / Sewa - - "
5 Pembongkaran / Pembersihan akhir - - "

B PEKERJAAN GEDUNG PASCA PANEN


a PEKERJAAN TANAH
1 Galian tanah pondasi 7.76 m3 A.1
2 Timbunan pasir bawah lantai 4.13 m3 A.18
3 Timbunan tanah 156.00 m3 A.18.a

b PEKERJAAN BATU / BETON


1 Pasangan batu kali dinding penahan / retainingwall 24.00 m3 G.31.J
2 Cor pondasi 1 : 3 : 5 + 20 % koral 5.82 m3 G.43.b
3 Cor sloof beton tulang 1 : 2 : 3 1.46 m3 Spl.V.a
4 Cor kolom praktis beton tulang 1 : 2 : 3 0.74 m3 Spl.V.a
5 Cor ring balok beton tulang 1 : 2 : 3 2.19 m3 Spl.V.a
6 Cor meja beton tulang 1 : 2 : 3 0.17 m3 Spl.V.a
7 Pasangan batu bata 1 : 4 10.57 m3 G.32.h
8 Plesteran batu batu 1 : 4 176.20 m2 G.50.q
9 Cor lantai beton 1 : 2 : 3 5.15 m2 Spl.I.b
10 Pas. Lantai keramik 40 x 40 cm 15.00 m2 G.69.f

c PEKERJAAN KAYU / ATAP


1 Pas. Kozen pintu / jendela kayu meranti 0.23 m3 F.27.a
2 Pas. Ventelasi /Jalusi kayu meranti 0.96 m2 F.34.c
3 Pas. Kuda-kuda / gording baja ringan (atap genteng metal) 143.00 m2 Taksir
4 Pas. Listplank kalsiboard 45.00 m' Taksir
5 Pas. Plafond gypsum + rangka furing 112.50 m2 F.1.g
6 Pas. Daun pintu panil kayu meranti 3.36 m2 F.33.a
7 Pas. Daun jendela kaca bingkai kayu meranti 2.88 m2 F.36.a
8 Pas. Atap genteng metal gording besi 143.00 m2 H.9.d
9 Pas. Rabung genteng metal 30.00 m' H.10.d
10 Pas. Pintu foldinggate / pintu lipat 6.60 m2 Taksir
11 Pas. Kawat harmonika rangka kayu meranti 49.50 m2 F.37.e

d PEKERJAAN LISTRIK
1 Pas. Instlasi listrik nyala 8.00 titik Taksir
2 Pas. Instalasi listrik stop kontak 2.00 titik "
3 Pas. Lampu SL 23 watt komplet 8.00 titik "
4 Bok zekering 1 group 1.00 titik "
5 Pas. MCB 4 A 1.00 titik "

e PEKERJAAN CAT
1 Cat tembok dinding 3 x cat setara paragon 176.20 m2 K23.a
2 Cat tembok plafond 3 x cat setara paragon 112.50 m2 K23.a
3 Cat kilat perkayuan baru 24.23 m2 K9+K23+K30

f PEKERJAAN SANITAIR
1 Pas. Instalasi air bersih 1.00 titik Taksir
2 Pas. Kran air lokal Ø ½" 1.00 bh "
3 Pas. Stop kran Ø 1" 8.00 bh "
4 Pas. Pipa PVC Ø 1" + aksesoris 30.00 m' "
5 Pas. Pipa PVC Ø 2" + aksesoris 14.00 m' "
6 Pas. Pipa air buangan PVC Ø 4 " + aksesoris 32.00 m' "
7 Pas. Wastafel komplet 1.00 set "
8 Pas. Bak kontrol 2.00 bh "

g PEKERJAAN PENGUNCI & PENGGANTUNG


1 Pas. Kunci tanam besar 2.00 bh Taksir
2 Pas. Engsel pintu nilon 2.00 set "
3 Pas. engsel jendela nilon 4.00 set "
4 Pas. Grendel jendela 4.00 bh "
5 Pas. Hak angin 4.00 bh "
6 Pas. Pegangan jendela 4.00 bh "
h PEKERJAAN TANGKI AIR
1 Cor pondasi beton tulang 1 : 2 : 3 0.20 m3 Spl.V.b
2 Cor kolom beton tulang 1 : 2 : 3 0.40 m3 Spl.V.b
3 Cor balok + lantai beton tulang 1 : 2 : 3 0.42 m3 Spl.V.b
4 Pas. Pompa air (sanyo sejenis) 1.00 bh Taksir
5 Pas. Pipa PVC Ø 3/4" + aksesoris 30.00 m' "
6 Pas. Tangki air fiberglass kapasitas 0,75 m3 1.00 set "

i PEKERJAAN KOLAM
1 Cor pondasi + lantai beton tulang 1 : 2 : 3 2.40 m3 Spl.V.b
2 Pas. Batu bata 1 : 2 2.88 m3 G.33.m
3 Plesteran batu bata 1 : 2 48.00 m2 G.50.h

C PEKERJAAN GUDANG PANGAN


a PEKERJAAN TANAH
1 Galian tanah pondasi 7.7600 m3 A.1
2 Timbunan pasir bawah lantai 4.0200 m3 A.18
3 Timbunan tanah 17.0600 m3 A.18.a

b PEKERJAAN BATU / BETON


1 Cor pondasi 1 : 3 : 5 + 20 % koral 7.08 m3 G.43.b
2 Cor sloof beton tulang 1 : 2 : 3 1.35 m3 Spl.V.a
3 Cor kolom praktis beton tulang 1 : 2 : 3 0.60 m3 Spl.V.a
4 Cor ring balok beton tulang 1 : 2 : 3 1.35 m3 Spl.V.a
5 Pas. Batu bata 1 : 4 17.22 m3 G.32.h
6 Plesteran batu bata 1 : 4 287.00 m2 G.50.q
7 Cor lantai rabat beton 1 : 3 : 5 # 5 cm 38.00 m2 G.67.b
8 Pas. Lantai keramik 40 x 40 cm 38.25 m2 G.69.f
9 Pas. Lantai keramik K.M 20 X 20 cm 4.00 m2 G.68.d
10 Pas. Dinding keramik K.M 20 X 25 cm 10.50 m2 G.68.f
11 Pas. Siku keramik (bon - bon) 4.00 m' Taksir

c PEKERJAAN KAYU / ATAP


1 Pas. Kozen pintu / jendela kayu meranti 0.24 m3 F.27.a
2 Pas. Ventelasi /Jalusi kayu meranti 0.96 m2 F.34.c
3 Pas. Kuda-kuda / gording baja ringan (atap genteng metal) 78.72 m2 Taksir
4 Pas. Listplank kalsiboard 34.00 m' Taksir
5 Pas. Plafond gypsum + rangka furing 64.00 m2 F.1.g
6 Pas. Daun pintu panil kayu meranti 5.04 m2 F.33.a
7 Pas. Daun jendela kaca bingkai kayu meranti 1.44 m2 F.36.a
8 Pas. Atap genteng metal gording besi 78.72 m2 H.9.d
9 Pas. Rabung genteng metal 20.00 m' H.10.d
10 Pas. Pintu fiberglass kamar mandi 1.00 set Taksir
11 Pas. Pintu foldinggate / pintu lipat 6.60 m2 Taksir

d PEKERJAAN LISTRIK
1 Pas. Instlasi listrik nyala 8.00 titik Taksir
2 Pas. Instalasi listrik stop kontak 2.00 titik "
3 Pas. Lampu SL 23 watt komplet 5.00 bh "
4 Pas. Exhaust fan 3.00 unit "
5 Bok zekering 1 group 1.00 set "
6 Pas. MCB 4 A 1.00 bh "

e PEKERJAAN CAT
1 Cat tembok dinding 3 x cat setara paragon 287.00 m2 K23.a
2 Cat tembok plafond 3 x cat setara paragon 64.00 m2 K23.a
3 Cat kilat perkayuan baru 17.46 m2 K9+K23+K30

f PEKERJAAN SANITAIR
1 Pembuatan sumur bor dangkal 1.00 bh Taksir
2 Pas. Pompa air (Daff sejenis) 1.00 bh "
3 Pas. Krangkeng pompa 1.00 bh "
4 Pas. Instalasi listrik stop kontak 1.00 titik "
5 Pas. Instalasi air bersih 1.00 titik "
6 Pas. Kran air lokal Ø ½" 1.00 bh "
7 Pas. stop air Ø 1" 1.00 bh "
8 Pas. Bak fiberglass 1.00 bh "
9 Pas. Saringan kamar mandi (floor drain) 1.00 bh "
10 Tempat sabun keramik 10 x 20 cm 1.00 bh "
11 Pas. Pipa PVC Ø 4" + aksesoris 6.00 m' "
g PEKERJAAN PENGUNCI & PENGGANTUNG
1 Pas. Kunci tanam besar 3.00 bh Taksir
2 Pas. Engsel pintu nilon 3.00 set "
3 Pas. engsel jendela nilon 2.00 set "
4 Pas. Grendel jendela 2.00 bh "
5 Pas. Hak angin 2.00 bh "
6 Pas. Pegangan jendela 2.00 bh "

h PEKERJAAN LAIN - LAIN


1 Lansir material ke lokasi 1.00 - Taksir
2 Cor perbaikain dinding parit 1 : 3 : 5 + 20 % koral 1.63 m3 G.43.b

D PEKERJAAN REHABILITASI BANGSAL PEMBENIHAN A


1 Penyisipan kuda- kuda / gording kayu meranti 1.08 m3 F.22.a
2 Pas. Polikarbonat tipis transparan 105.00 m2 Taksir
3 Pas. Rabung seng bjls 20 gording kayu 17.50 m' H.10.a
4 Cat perkayuan 2 x cat 88.00 m2 K23+K36

E PEKERJAAN REHABILITASI BANGSAL PEMBENIHAN B


1 Cor kolom praktis beton tulang 1 : 2 : 3 0.40 m3 Spl.V.a
2 Pas. Batu bata 1 : 4 4.20 m3 G.32.h
3 Plesteran batu bata 1 : 4 70.00 m2 G.50.q
4 Timbunan tanah 6.00 m3 A.18.a
5 Pas. Kozen pintu / jendela kayu meranti 0.05 m3 F.27.a
6 Pas. Rangka polikarbonat kayu meranti 0.95 m3 F.22.a
7 Pas. Daun pintu panil kayu meranti 3.36 m2 F.33.a
8 Pas. Kunci tanam besar 2.00 bh Taksir
9 Pas. Engsel pintu nilon 2.00 set "
10 Pas. Wastafel komplet 1.00 set "
11 Pas. Instalasi air bersih 1.00 titik "
12 Pas. Polikarbonat tebal / double 69.10 m' "
13 Cat perkayuan 2 x cat 74.72 m2 K23+K36

F PEKERJAAN HALAMAN
1 Pek. Pagar dan Plank nama
Pas. Pagar depan besi hollow + rel 8.00 m2 Taksir
Cor pondasi beton tulang 1 : 2 : 3 0.15 m3 Spl.V.b
Cor kolom beton tulang 1 : 2 : 3 0.14 m3 Spl.V.b
Cor balok beton tulang 1 : 2 : 3 0.12 m4 Spl.V.b
Pas. Batu bata 1 : 4 0.19 m3 G.32.h
Plesteran batu bata 1 : 4 3.20 m2 G.50.q
Pek. List Profil 5.60 m' Taksir
Pek. Pembuatan tulisan plank nama 1.00 ls Taksir

2 Pek. Conblock
Timbunan pasir bawah conblock 34.20 m3 A.18
Pas. Conblock 684.00 m2 G.67.a
Pas. Batu bata 1 : 4 kuncian conblock 3.03 m3 G.32.h
Plesteran batu bata 1 : 4 27.20 m2 G.50.q

3 Pek. Tangga
Galian tanah 3.00 m3 A.1
Pas. Batu bata 1 : 4 tangga 1.64 m3 G.32.h
Plesteran batu bata 1 : 4 tangga 31.20 m2 G.50.q
Cor lantai rabat beton 1 : 3 : 5 # 5 cm 52.00 m2 G.67.b

4 Pek. Saluran
Galian tanah 0.40 m3 A.1
Pas. Batu kali dinding penahan / retainingwall saluran 2.00 m3 G.31.J
Pemasangan sekat parit pelat besi 5.00 unit "

G PEKERJAAN PERALATAN PENDUKUNG OPERASIONAL GEDUNG


1 Mesin pembuat pelet apung 1.00 unit Taksir
2 Tabung gas oksigen 2.00 bh "
3 Instalasi aerasi ged. Pasca penen + hatchery indoor 1.00 set "
4 Hi - Blow 1.00 unit "
5 Hapa beserta rangka uk. 1 x 1 x 0,5 m 8.00 set "
6 Hapa beserta rangka uk. 1 x 2 x 0,5 m 4.00 set "
7 Hapa uk. 1 x 3 x 1 m 25.00 set "
REKAPITULASI :
A PEKERJAAN PENDAHULUAN
B PEKERJAAN GEDUNG PASCA PANEN
C PEKERJAAN GUDANG PANGAN
D PEKERJAAN REHABILITASI BANGSAL PEMBENIHAN A
E PEKERJAAN REHABILITASI BANGSAL PEMBENIHAN B
F PEKERJAAN HALAMAN
G PEKERJAAN PERALATAN PENDUKUNG OPERASIONAL GEDUNG

Diketahui Oleh :
CV. BARKAT: JAYA
Terbilang ………………………………………………………………………………………….

BUDI DARMAWAN
Direktur
AYA

ana Balai Bibit Ikan

HARGA SATUAN JUMLAH HARGA


(Rupiah) (Rupiah)

300,000.00 300,000.00
300,000.00 300,000.00
1,000,000.00 1,000,000.00
500,000.00 500,000.00
750,000.00 750,000.00
2,850,000.00

47,185.00 366,155.60
147,190.00 607,894.70
135,658.00 21,162,648.00
22,136,698.30

884,354.00 21,224,496.00
855,402.00 4,978,439.64
4,569,430.00 6,671,367.80
4,569,430.00 3,381,378.20
4,569,430.00 10,007,051.70
4,569,430.00 776,803.10
1,108,491.00 11,716,749.87
49,220.00 8,672,564.00
1,487,852.00 7,662,437.80
133,664.00 2,004,960.00
77,096,248.11

8,555,959.00 1,967,870.57
306,464.00 294,205.44
216,270.00 30,926,610.00
40,000.00 1,800,000.00
122,745.00 13,808,812.50
460,404.00 1,546,957.44
677,094.00 1,950,030.72
115,212.00 16,475,316.00
58,169.00 1,745,070.00
1,100,000.00 7,260,000.00
196,641.00 9,733,729.50
87,508,602.17

103,490.00 827,920.00
103,490.00 206,980.00
34,360.00 274,880.00
9,010.00 9,010.00
18,020.00 18,020.00
1,336,810.00

43,003.00 7,577,128.60
43,003.00 4,837,837.50
57,980.00 1,404,855.40
13,819,821.50

103,930.00 103,930.00
22,830.00 22,830.00
75,000.00 600,000.00
24,200.00 726,000.00
48,400.00 677,600.00
96,900.00 3,100,800.00
510,640.00 510,640.00
160,500.00 321,000.00
6,062,800.00

112,340.00 224,680.00
12,020.00 24,040.00
7,210.00 28,840.00
4,810.00 19,240.00
6,610.00 26,440.00
6,610.00 26,440.00
349,680.00
5,453,269.00 1,090,653.80
5,453,269.00 2,181,307.60
5,453,269.00 2,290,372.98
901,130.00 901,130.00
24,200.00 726,000.00
4,000,000.00 4,000,000.00
11,189,464.38

5,453,269.00 13,087,845.60
1,216,954.00 3,504,827.52
53,477.00 2,566,896.00
19,159,569.12

Jumlah 238,659,693.58

47,185.00 366,155.60
147,190.00 591,703.80
135,658.00 2,314,325.48
3,272,184.88

855,402.00 6,056,246.16
4,569,430.00 6,168,730.50
4,569,430.00 2,741,658.00
4,569,430.00 6,168,730.50
1,108,491.00 19,088,215.02
49,220.00 14,126,140.00
52,667.00 2,001,346.00
133,664.00 5,112,648.00
123,399.00 493,596.00
161,668.00 1,697,514.00
10,210.00 40,840.00
63,695,664.18

8,555,959.00 2,053,430.16
306,464.00 294,205.44
216,270.00 17,024,774.40
40,000.00 1,360,000.00
122,745.00 7,855,680.00
460,404.00 2,320,436.16
677,094.00 975,015.36
115,212.00 9,069,488.64
58,169.00 1,163,380.00
408,510.00 408,510.00
1,100,000.00 7,260,000.00
49,784,920.16

103,490.00 827,920.00
103,490.00 206,980.00
34,360.00 171,800.00
400,000.00 1,200,000.00
9,010.00 9,010.00
18,020.00 18,020.00
2,433,730.00

43,003.00 12,341,861.00
43,003.00 2,752,192.00
57,980.00 1,012,330.80
16,106,383.80

1,441,800.00 1,441,800.00
612,770.00 612,770.00
350,000.00 350,000.00
103,490.00 103,490.00
103,930.00 103,930.00
22,830.00 22,830.00
75,000.00 75,000.00
456,570.00 456,570.00
17,420.00 17,420.00
40,850.00 40,850.00
96,900.00 581,400.00
3,806,060.00
112,340.00 337,020.00
12,020.00 36,060.00
7,210.00 14,420.00
4,810.00 9,620.00
6,610.00 13,220.00
6,610.00 13,220.00
423,560.00

500,000.00 500,000.00
855,402.00 1,394,305.26
1,894,305.26

Jumlah 141,416,808.28

7,855,858.00 8,484,326.64
125,000.00 13,125,000.00
20,956.00 366,730.00
35,300.00 3,106,400.00
25,082,456.64

4,569,430.00 1,827,772.00
1,108,491.00 4,655,662.20
49,220.00 3,445,400.00
135,658.00 813,948.00
8,555,959.00 427,797.95
7,855,858.00 7,463,065.10
460,404.00 1,546,957.44
112,340.00 224,680.00
12,020.00 24,040.00
510,640.00 510,640.00
103,930.00 103,930.00
150,000.00 10,365,000.00
35,300.00 2,637,616.00
34,046,508.69

841,050.00 6,728,400.00
5,453,269.00 817,990.35
5,453,269.00 763,457.66
5,453,269.00 654,392.28
1,108,491.00 210,613.29
49,220.00 157,504.00
35,000.00 196,000.00
400,000.00 400,000.00
9,928,357.58

147,190.00 5,033,898.00
107,286.00 73,383,624.00
1,108,491.00 3,358,727.73
49,220.00 1,338,784.00
83,115,033.73

47,185.00 141,555.00
1,108,491.00 1,817,925.24
49,220.00 1,535,664.00
52,667.00 2,738,684.00
6,233,828.24

47,185.00 18,874.00
884,354.00 1,768,708.00
300,000.00 1,500,000.00
3,287,582.00

Jumlah 102,564,801.55

45,500,000.00 45,500,000.00
2,800,000.00 5,600,000.00
2,800,000.00 2,800,000.00
1,500,000.00 1,500,000.00
460,000.00 3,680,000.00
700,000.00 2,800,000.00
460,000.00 11,500,000.00
73,380,000.00
Rp 2,850,000.00
Rp 238,659,693.58
Rp 141,416,808.28
Rp 25,082,456.64
Rp 34,046,508.69
Rp 102,564,801.55
Rp 73,380,000.00
Jumlah Rp 618,000,268.74
PPn 10% Rp 61,800,026.87
Jumlah Rp 679,800,295.61
Dibulatkan Rp 679,800,000.00

Medan, 01 Juli 2010


PEMBANGUNAN GEDUNG BARU DAN REHABILITASI SARANA DAN PRASARANA BALAI BI
JL. BUNGAN GAYONG KEL. LADANG BAMBU KEC. MEDAN TUNTUNGAN

Anl A.1. 1 M3 Galian Tanah Biasa


Upah 0.75 - Pekerja @ Rp 59,470.00 =
0.025 - Mandor @ Rp 103,330.00 =
=

Anl A.18. 1 M3 Timbunan Pasir Timbun


Bahan 1.2000 M3 Pasir Timbun @ Rp 106,930.00 =
Upah 0.3000 - Pekerja @ Rp 59,470.00 =
0.0100 - Mandor @ Rp 103,330.00 =
=

Anl A.18.a. 1 M3 Timbunan Tanah Timbun


Bahan 1.2000 M3 Tanah Timbun/ Merah @ Rp 97,320.00 =
Upah 0.3000 - Pekerja @ Rp 59,470.00 =
0.0100 - Mandor @ Rp 103,330.00 =
=

Anl F.1.g. 1 M2 Plafond Gypsum + Rangka Furing


Bahan 0.3640 Lbr Papan Gypsum uk. 120x240 cm @ Rp 67,280.00 =
1.0000 M2 Rangka Furing @ Rp 83,750.00 =
0.1100 Kg Sekrup @ Rp 28,000.00 =
Upah 0.1000 - Pekerja @ Rp 59,470.00 =
0.0050 - Mandor @ Rp 103,330.00 =
0.0500 - Tukang Kayu @ Rp 88,910.00 =
0.0050 - Kepala Tukang @ Rp 103,330.00 =
Upah diambil ### x =

Anl F.8 Pekerjaan Cetakan Untuk 1 M3 Beton Cor


Bahan 0.4000 Ton Broti/ Ppn Kaya Sembarang @ Rp 6,367,950.00 =
4.0000 Kg Paku Biasa @ Rp 24,630.00 =

Upah 0.2000 - Pekerja @ Rp 59,470.00 =


0.0100 - Mandor @ Rp 103,330.00 =
0.5000 - Tukang Kayu @ Rp 88,910.00 =
0.0500 - Kepala Tukang @ Rp 103,330.00 =
membongkar/ menyiram cetakan
4.0000 - Pekerja @ Rp 59,470.00 =
Anl F.22.a. 1 M3 Kayu-kayu/ Gording Kayu Meranti
Bahan 0.8140 Ton Broti Kayu Meranti @ Rp 7,809,750.00 =
2.0000 Kg Paku Biasa @ Rp 24,630.00 =
Upah 8.0000 - Pekerja @ Rp 59,470.00 =
0.4000 - Mandor @ Rp 103,330.00 =
24.0000 - Tukang Kayu @ Rp 88,910.00 =
2.4000 - Kepala Tukang @ Rp 103,330.00 =
Upah diambil ### x =

Anl F.27.a. 1 M3 Kusen Kayu Meranti


Bahan 0.8140 Ton Broti Kayu Meranti @ Rp 7,809,750.00 =
1.0000 Kg Paku Biasa @ Rp 24,630.00 =

Upah 12.0000 - Pekerja @ Rp 59,470.00 =


0.6000 - Mandor @ Rp 103,330.00 =
36.0000 - Tukang Kayu @ Rp 88,910.00 =
3.6000 - Kepala Tukang @ Rp 103,330.00 =
Upah diambil ### x =

Anl F.33.a. 1 M2 Daun Pintu/ Jendela Panil Kayu Meranti


Bahan 0.0260 Ton Papan Kayu Meranti @ Rp 8,410,500.00 =
0.0500 Kg Paku Biasa @ Rp 24,630.00 =

Upah 1.3000 - Pekerja @ Rp 59,470.00 =


0.0650 - Mandor @ Rp 103,330.00 =
4.0000 - Tukang Kayu @ Rp 88,910.00 =
0.4000 - Kepala Tukang @ Rp 103,330.00 =
Upah diambil ### x =

Anl F.34.c. 1 M2 Ventilasi Jalusi Kayu Meranti


Bahan 0.0244 Ton Papan Kayu Meranti @ Rp 8,410,500.00 =
0.1000 Kg Paku Biasa @ Rp 24,630.00 =

Upah 0.3000 - Pekerja @ Rp 59,470.00 =


0.0150 - Mandor @ Rp 103,330.00 =
0.8000 - Tukang Kayu @ Rp 88,910.00 =
0.0800 - Kepala Tukang @ Rp 103,330.00 =
Upah diambil ### x =

Anl F.36.a. 1 M2 Daun Pintu/ Jendela Kaca Bingkai Kayu Meranti


Bahan 0.0220 Ton Papan Kayu Meranti @ Rp 8,410,500.00 =
0.8100 M2 Kaca Bening t = 5 mm @ Rp 158,600.00 =
0.0500 Kg Paku Biasa @ Rp 24,630.00 =
Upah 2.0000 - Pekerja @ Rp 59,470.00 =
0.1000 - Mandor @ Rp 103,330.00 =
6.0000 - Tukang Kayu @ Rp 88,910.00 =
0.6000 - Kepala Tukang @ Rp 103,330.00 =
Upah diambil ### x =

Anl F.36.a. 1 M2 Daun Pintu/ Jendela Kaca Bingkai Kayu Meranti


Bahan 0.0220 Ton Papan Kayu Meranti @ Rp 8,410,500.00 =
0.8100 M2 Kaca Bening t = 5 mm @ Rp 158,600.00 =
0.0500 Kg Paku Biasa @ Rp 24,630.00 =
Upah 2.0000 - Pekerja @ Rp 59,470.00 =
0.1000 - Mandor @ Rp 103,330.00 =
6.0000 - Tukang Kayu @ Rp 88,910.00 =
0.6000 - Kepala Tukang @ Rp 103,330.00 =
Upah diambil ### x =

Anl F.37.e. 1 M2 Pasangan Kawat Harmonika Rangka Kayu Meranti


Bahan 0.0140 Ton Broti Kayu Meranti @ Rp 7,809,750.00 =
1.0000 M2 Kawat Harmonika @ Rp 44,450.00 =
0.1000 Kg Paku Biasa @ Rp 24,630.00 =
Upah 1.0000 - Pekerja @ Rp 59,470.00 =
0.0050 - Mandor @ Rp 103,330.00 =
0.3000 - Tukang Kayu @ Rp 88,910.00 =
0.0300 - Kepala Tukang @ Rp 103,330.00 =
Upah diambil ### x =

Anl G.31.j 1 M3 Pasangan Batu Kali 1 : 4


Bahan 1.2000 M3 Batu Koral @ Rp 177,220.00 =
4.0720 Zak Semen Pc @ 40 kg @ Rp 60,080.00 =
0.5220 M3 Pasir Pasang @ Rp 144,180.00 =
Upah 3.6000 - Pekerja @ Rp 59,470.00 =
0.1800 - Mandor @ Rp 103,330.00 =
1.2000 - Tukang Batu @ Rp 88,910.00 =
0.1200 - Kepala Tukang @ Rp 103,330.00 =

Anl G.32.h 1 M3 Pasangan Batu Bata 1 : 4


Bahan 500.0000 Bh Batu Bata @ Rp 840.00 =
3.1662 Zak Semen Pc @ 40 kg @ Rp 60,080.00 =
0.4060 M3 Pasir Pasang @ Rp 144,180.00 =

Upah 4.5000 - Pekerja @ Rp 59,470.00 =


0.2250 - Mandor @ Rp 103,330.00 =
1.5000 - Tukang Batu @ Rp 88,910.00 =
0.1500 - Kepala Tukang @ Rp 103,330.00 =

Anl G.33.m 1 M3 Pasangan Batu Bata 1 : 2


Bahan 500.0000 Bh Batu Bata @ Rp 840.00 =
5.1467 Zak Semen Pc @ 40 kg @ Rp 60,080.00 =
0.3330 M3 Pasir Pasang @ Rp 144,180.00 =

Upah 4.5000 - Pekerja @ Rp 59,470.00 =


0.2250 - Mandor @ Rp 103,330.00 =
1.5000 - Tukang Batu @ Rp 88,910.00 =
0.1500 - Kepala Tukang @ Rp 103,330.00 =

Anl G.41 1 M3 Beton Cor 1 : 2 : 3


Bahan 8.5000 Zak Semen Pc @ 40 kg @ Rp 60,080.00 =
0.5400 M3 Pasir Pasang @ Rp 144,180.00 =
0.8200 M3 Batu Krikil (A) cor @ Rp 291,960.00 =

Upah 6.0000 - Pekerja @ Rp 59,470.00 =


0.3000 - Mandor @ Rp 103,330.00 =
1.0000 - Tukang Batu @ Rp 88,910.00 =
0.1000 - Kepala Tukang @ Rp 103,330.00 =
Upah diambil ### x =

Anl G.43.b 1 M3, Beton Cor 1 : 3 : 5 + 20% Batu Koral


Bahan 3.4490 Zak Semen Pc @ 40 kg @ Rp 60,080.00 =
0.4000 M3 Pasir pasang @ Rp 144,180.00 =
0.6500 M3 Krikil (A) cor @ Rp 291,960.00 =
0.2000 M3 Batu Koral @ Rp 177,220.00 =

Upah 6.0000 - Pekerja @ Rp 59,470.00 =


0.3000 - Mandor @ Rp 103,330.00 =
1.0000 - Tukang batu @ Rp 88,910.00 =
0.1000 - Kepala Tukang @ Rp 103,330.00 =
Upah diambil ### X =
Jumlah
Pembulatan

Anl G.50.h 1 M2, Plesteran Batu bata 1 : 2 Tebal 10 mm


Bahan 0.1760 Zak Semen Pc @ 40 kg @ Rp 60,080.00 =
0.0150 M3 Pasir pasang @ Rp 144,180.00 =

Upah 0.4000 - Pekerja @ Rp 59,470.00 =


0.0200 - Mandor @ Rp 103,330.00 =
0.1500 - Tukang batu @ Rp 88,910.00 =
0.0150 - Kepala Tukang @ Rp 103,330.00 =
Jumlah
Pembulatan

Anl G.50.q 1 M2, Plesteran Batu bata 1 : 4 Tebal 10 mm


Bahan 0.1085 Zak Semen Pc @ 40 kg @ Rp 60,080.00 =
0.0136 M3 Pasir pasang @ Rp 144,180.00 =

Upah 0.4000 - Pekerja @ Rp 59,470.00 =


0.0200 - Mandor @ Rp 103,330.00 =
0.1500 - Tukang batu @ Rp 88,910.00 =
0.0150 - Kepala Tukang @ Rp 103,330.00 =
Jumlah
Pembulatan

Anl l.2 100. Kg. Besi Beton


Bahan 110.0000 Kg Besi beton @ Rp 17,420.00 =
2.0000 Kg Kawat beton @ Rp 24,030.00 =

Upah 9.0000 - Pekerja @ Rp 59,470.00 =


9.0000 - Tukang besi @ Rp 88,910.00 =
3.0000 - Kepala Tukang @ Rp 103,330.00 =
Upah diambil ### X =
Jumlah
Pembulatan

Anl Spl.l.b 1 M3. Beton Cor 1 : 2 : 3 1/10 F8 (0,1)


Bahan 1.0000 M3 Beton Cor G.41 @ Rp 1,193,240.00 =
0.1000 F.8 Pekerjaan Cetakan @ Rp 2,946,128.00 =
Jumlah =

Anl Spl.V.a 1 M3. Beton Cor 1 : 2 : 3 + 20% Cetakan + 100 Kg Pembesian


Bahan 1.0000 M3 Beton Cor G.41 @ Rp 1,193,240.00 =
0.2000 F.8 Pekerjaan Cetakan @ Rp 2,946,128.00 =
1.0000 l.2 Pembesian 100 Kg @ Rp 2,786,965.00 =
Jumlah =

Anl Spl.V.b 1 M3. Beton Cor 1 : 2 : 3 + 20% Cetakan + 100 Kg Pembesian


Bahan 1.0000 M3 Beton Cor G.41 @ Rp 1,193,240.00 =
0.5000 F.8 Pekerjaan Cetakan @ Rp 2,946,128.00 =
1.0000 l.2 Pembesian 100 Kg @ Rp 2,786,965.00 =
Jumlah =

Anl G.67.a 1 M2. Pasangan Con Blok


Bahan 46.0000 Bh Con Blok @ Rp 1,680.00 =
0.0100 M3 Pasir pasang Utk Pengunci @ Rp 144,180.00 =

Upah 0.2500 - Pekerja @ Rp 59,470.00 =


0.0125 - Mandor @ Rp 103,330.00 =
0.1250 - Tukang batu @ Rp 88,910.00 =
0.0125 - Kepala Tukang @ Rp 103,330.00 =
Jumlah
Pembulatan

Anl G.67.b 1 M2. Cor Lantai Rabat Beton 1 : 3 : 5 # 5 Cm


Bahan 0.2838 Zak Semen Pc @ 40 kg @ Rp 60,080.00 =
0.0274 M3 Pasir pasang @ Rp 144,180.00 =
0.0459 M3 Krikil (A) cor @ Rp 291,960.00 =

Upah 0.3000 - Pekerja @ Rp 59,470.00 =


0.0150 - Mandor @ Rp 103,330.00 =
0.0500 - Tukang batu @ Rp 88,910.00 =
0.0050 - Kepala Tukang @ Rp 103,330.00 =
Upah diambil 1 X =
Jumlah
Pembulatan

Anl G.68.f 1 M2. Dinding keramik 20 x 25 cm


Bahan 20.0000 Bh Keramik 20 x 25 cm @ Rp 2,760.00 =
0.2640 Zak Semen Pc @ 40 kg @ Rp 60,080.00 =
0.0200 Zak Semen putih @ 40 kg @ Rp 137,570.00 =
0.0150 M3 Pasir pasang @ Rp 144,180.00 =

Upah 1.0000 - Pekerja @ Rp 59,470.00 =


0.0500 - Mandor @ Rp 103,330.00 =
0.5000 - Tukang batu @ Rp 88,910.00 =
0.0500 - Kepala Tukang @ Rp 103,330.00 =
Upah diambil 1 X =
Jumlah
Pembulatan

Anl G.69.d 1 M2. Dinding keramik 20 x 20 cm


Bahan 25.0000 Bh Keramik 20 x 20 cm @ Rp 2,400.00 =
0.2640 Zak Semen Pc @ 40 kg @ Rp 60,080.00 =
0.0100 Zak Semen putih @ 40 kg @ Rp 137,570.00 =
0.0230 M3 Pasir pasang @ Rp 144,180.00 =

Upah 0.5000 - Pekerja @ Rp 59,470.00 =


0.0250 - Mandor @ Rp 103,330.00 =
0.2500 - Tukang batu @ Rp 88,910.00 =
0.0250 - Kepala Tukang @ Rp 103,330.00 =
Upah diambil 1 X =
Jumlah
Pembulatan

Anl G.69.f 1 M2. Dinding keramik 40 x 40 cm


Bahan 6.5000 Bh Keramik 40 x 40 cm @ Rp 10,810.00 =
0.2640 Zak Semen Pc @ 40 kg @ Rp 60,080.00 =
0.0100 Zak Semen putih @ 40 kg @ Rp 137,570.00 =
0.0230 M3 Pasir pasang @ Rp 144,180.00 =

Upah 0.5000 - Pekerja @ Rp 59,470.00 =


0.0250 - Mandor @ Rp 103,330.00 =
0.2500 - Tukang batu @ Rp 88,910.00 =
0.0250 - Kepala Tukang @ Rp 103,330.00 =
Upah diambil 1 X =
Jumlah
Pembulatan

Anl H.9.d 1 M2. Atap Genteng Metal # 0,25 Gording Besi


Bahan 1.0000 Lbr Genteng Metal # 0.25 (16 daun) @ Rp 79,900.00 =
6.0000 Bh Baut seng + ring karet @ Rp 1,500.00 =

Upah 0.1000 - Pekerja @ Rp 59,470.00 =


0.0050 - Mandor @ Rp 103,330.00 =
0.2000 - Tukang batu @ Rp 88,910.00 =
0.0200 - Kepala Tukang @ Rp 103,330.00 =
Jumlah
Pembulatan

Anl H.10.a 1 M1. Rabung Seng BJLS 20 Gording Kayu


Bahan 0.6000 Lbr Rabung Seng BJLS 20 @ Rp 25,230.00 =
0.0500 Bh Paku Seng @ Rp 31,840.00 =

Upah 0.0250 - Pekerja @ Rp 59,470.00 =


0.0025 - Mandor @ Rp 103,330.00 =
0.0250 - Tukang batu @ Rp 88,910.00 =
0.0025 - Kepala Tukang @ Rp 103,330.00 =
Jumlah
Pembulatan

Anl H.10.d 1 M1. Rabung Genteng Metal # 0,35 Gording Besi


Bahan 1.2900 Lbr Rabung Genteng Metal BJLS @ Rp 34,840.00 =
6.0000 Bh Baut seng + ring karet @ Rp 1,500.00 =

Upah 0.0250 - Pekerja @ Rp 59,470.00 =


0.0025 - Mandor @ Rp 103,330.00 =
0.0250 - Tukang batu @ Rp 88,910.00 =
0.0025 - Kepala Tukang @ Rp 103,330.00 =
Jumlah
Pembulatan

Anl K9+K23+K30 1 M2. Pengecatan perkayuan baru dengan cat kilat warna 3 x cat
( 1 x Cat Dasar, 2 x Cat kilat ) Serta mendempul dan menggosok
Bahan 0.4250 Kg Cat setara bee brand @ Rp 49,260.00 =
0.0500 Ltr Minyak cat @ Rp 18,620.00 =
0.7500 Lbr Kertas pasir @ Rp 4,210.00 =
0.0500 Kg Dempul jadi @ Rp 18,620.00 =

Upah 0.1500 - Pekerja @ Rp 59,470.00 =


0.0075 - Mandor @ Rp 103,330.00 =
0.2250 - Tukang batu @ Rp 88,910.00 =
0.0225 - Kepala Tukang @ Rp 103,330.00 =
Upah diambil ### X =
Jumlah
Pembulatan

Anl K23 + K36 1 M2. Pengecatan perkayuan baru dengan cat kilat warna 3 x cat
( 1 x Cat Dasar, 2 x Cat kilat ) Serta mendempul dan menggosok
Bahan 0.2832 Kg Cat setara bee brand @ Rp 49,260.00 =

Upah 0.1000 - Pekerja @ Rp 59,470.00 =


0.0050 - Mandor @ Rp 103,330.00 =
0.1500 - Tukang batu @ Rp 88,910.00 =
0.0150 - Kepala Tukang @ Rp 103,330.00 =
Upah diambil ### X =
Jumlah
Pembulatan

Anl K23.a 1 M2. Pengecatan perkayuan baru dengan cat kilat warna 3 x cat ( setara Parago
( 1 x Cat Dasar, 2 x Cat kilat ) Serta mendempul dan menggosok
Bahan 0.4250 Kg Cat tembok Paragon @ Rp 16,820.00 =
0.7500 Lbr Kertas pasir @ Rp 4,210.00 =
0.0800 Kg Tepung dempul @ Rp 8,410.00 =

Upah 0.1500 - Pekerja @ Rp 59,470.00 =


0.0075 - Mandor @ Rp 103,330.00 =
0.2250 - Tukang batu @ Rp 88,910.00 =
0.0225 - Kepala Tukang @ Rp 103,330.00 =
Upah diambil ### X =
Jumlah
Pembulatan

Diketahui Oleh :
CV. BARKAT JAYA

BUDI DARMAWAN
Direktur
PRASARANA BALAI BIBIBT IKAN
DAN TUNTUNGAN

Rp 44,602.50
Rp 2,583.25
Rp 47,185.75 = Rp 47,185.00

Rp 128,316.00
Rp 17,841.00
Rp 1,033.30
Rp 147,190.30 = Rp 147,190.00

Rp 116,784.00
Rp 17,841.00
Rp 1,033.30
Rp 135,658.30 = Rp 135,658.00

Rp 24,489.92
Rp 83,750.00
Rp 3,080.00 = Rp 111,319.92
Rp 5,947.00
Rp 516.65
Rp 4,445.50
Rp 516.65
Rp 11,425.80 = Rp 11,425.80
Jumlah = Rp 122,745.72
Pembulatan = Rp 122,745.00

Rp 2,547,180.00
Rp 98,520.00 = Rp 2,645,700.00

Rp 11,894.00
Rp 1,033.30
Rp 44,455.00
Rp 5,166.50

Rp 237,880.00 = Rp 300,428.80
Jumlah = Rp 2,946,128.80
Pembulatan = Rp 2,946,128.00

Rp 6,357,136.50
Rp 49,260.00 = Rp 6,406,396.50
Rp 475,760.00
Rp 41,332.00
Rp 2,133,840.00
Rp 247,992.00
Rp 2,898,924.00 = Rp 1,449,462.00
Jumlah = Rp 7,855,858.50
Pembulatan = Rp 7,855,858.00

Rp 6,357,136.50
Rp 24,630.00 = Rp 6,381,766.50

Rp 713,640.00
Rp 61,998.00
Rp 3,200,760.00
Rp 371,988.00
Rp 4,348,386.00 = Rp 2,174,193.00
Jumlah = Rp 8,555,959.50
Pembulatan = Rp 8,555,959.00

Rp 218,673.00
Rp 1,231.50 = Rp 219,904.50

Rp 77,311.00
Rp 6,716.45
Rp 355,640.00
Rp 41,332.00
Rp 480,999.45 = Rp 240,499.73
Jumlah = Rp 460,404.23
Pembulatan = Rp 460,404.00

Rp 205,216.20
Rp 2,463.00 = Rp 207,679.20

Rp 17,841.00
Rp 1,549.95
Rp 71,128.00
Rp 8,266.40
Rp 98,785.35 = Rp 98,785.35
Jumlah = Rp 306,464.55
Pembulatan = Rp 306,464.00

Rp 185,031.00
Rp 128,466.00
Rp 1,231.50 = Rp 314,728.50
Rp 118,940.00
Rp 10,333.00
Rp 533,460.00
Rp 61,998.00
Rp 724,731.00 = Rp 362,365.50
Jumlah = Rp 677,094.00
Pembulatan = Rp 677,094.00

Rp 185,031.00
Rp 128,466.00
Rp 1,231.50 = Rp 314,728.50
Rp 118,940.00
Rp 10,333.00
Rp 533,460.00
Rp 61,998.00
Rp 724,731.00 = Rp 362,365.50
Jumlah = Rp 677,094.00
Pembulatan = Rp 677,094.00

Rp 109,336.50
Rp 44,450.00
Rp 2,463.00 = Rp 156,249.50
Rp 59,470.00
Rp 516.65
Rp 26,673.00
Rp 3,099.90
Rp 89,759.55 = Rp 40,391.80
Jumlah = Rp 196,641.30
Pembulatan = Rp 196,641.00

Rp 212,664.00
Rp 244,645.76
Rp 75,261.96 = Rp 532,571.72
Rp 214,092.00
Rp 18,599.40
Rp 106,692.00
Rp 12,399.60 = Rp 351,783.00
Jumlah = Rp 884,354.72
Pembulatan = Rp 884,354.00

Rp 420,000.00
Rp 190,225.30
Rp 58,537.08 = Rp 668,762.38

Rp 267,615.00
Rp 23,249.25
Rp 133,365.00
Rp 15,499.50 = Rp 439,728.75
Jumlah = Rp 1,108,491.13
Pembulatan = Rp 1,108,491.00

Rp 420,000.00
Rp 309,213.74
Rp 48,011.94 = Rp 777,225.68

Rp 267,615.00
Rp 23,249.25
Rp 133,365.00
Rp 15,499.50 = Rp 439,728.75
Jumlah = Rp 1,216,954.43
Pembulatan = Rp 1,216,954.00

Rp 510,680.00
Rp 77,857.20
Rp 239,407.20 = Rp 827,944.40

Rp 356,820.00
Rp 30,999.00
Rp 88,910.00
Rp 10,333.00
Rp 487,062.00 = Rp 365,296.50
Jumlah = Rp 1,193,240.90
Pembulatan = Rp 1,193,240.00

Rp 207,215.92
Rp 57,672.00
Rp 189,774.00
Rp 35,444.00 = Rp 490,105.92

Rp 356,820.00
Rp 30,999.00
Rp 88,910.00
Rp 10,333.00
Rp 487,062.00 = Rp 365,296.50
Jumlah = Rp 855,402.42
Pembulatan = Rp 855,402.00

Rp 10,574.08
Rp 2,162.70 = Rp 12,736.78

Rp 23,788.00
Rp 2,066.60
Rp 13,336.50
Rp 1,549.95 = Rp 40,741.05
Jumlah = Rp 53,477.83
Pembulatan = Rp 53,477.00

Rp 6,518.68
Rp 1,960.85 = Rp 8,479.53

Rp 23,788.00
Rp 2,066.60
Rp 13,336.50
Rp 1,549.95 = Rp 40,741.05
Jumlah = Rp 49,220.58
Pembulatan = Rp 49,220.00

Rp 1,916,200.00
Rp 48,060.00 = Rp 1,964,260.00

Rp 535,230.00
Rp 800,190.00
Rp 309,990.00
Rp 1,645,410.00 = Rp 822,705.00
Jumlah = Rp 2,786,965.00
Pembulatan = Rp 2,786,965.00

Rp 1,193,240.00
Rp 294,612.80
Rp 1,487,852.80 = Rp 1,487,852.00

Rp 1,193,240.00
Rp 589,225.60
Rp 2,786,965.00
Rp 4,569,430.60 = Rp 4,569,430.00
Rp 1,193,240.00
Rp 1,473,064.00
Rp 2,786,965.00
Rp 5,453,269.00 = Rp 5,453,269.00

Rp 77,280.00
Rp 1,441.80 = Rp 78,721.80

Rp 14,867.50
Rp 1,291.63
Rp 11,113.75
Rp 1,291.63 = Rp 28,564.50
Jumlah = Rp 107,286.30
Pembulatan = Rp 107,286.00

Rp 17,050.70
Rp 3,950.53
Rp 13,400.96 = Rp 34,402.20

Rp 17,841.00
Rp 1,549.95
Rp 4,445.50
Rp 516.65
Rp 24,353.10 = Rp 18,264.83
Jumlah = Rp 52,667.03
Pembulatan = Rp 52,667.00

Rp 55,200.00
Rp 15,861.12
Rp 2,751.40
Rp 2,162.70 = Rp 75,975.22

Rp 59,470.00
Rp 5,166.50
Rp 44,455.00
Rp 5,166.50
Rp 114,258.00 = Rp 85,693.50
Jumlah = Rp 161,668.72
Pembulatan = Rp 161,668.00

Rp 60,000.00
Rp 15,861.12
Rp 1,375.70
Rp 3,316.14 = Rp 80,552.96

Rp 29,735.00
Rp 2,583.25
Rp 22,227.50
Rp 2,583.25
Rp 57,129.00 = Rp 42,846.75
Jumlah = Rp 123,399.71
Pembulatan = Rp 123,399.00

Rp 70,265.00
Rp 15,861.12
Rp 1,375.70
Rp 3,316.14 = Rp 90,817.96

Rp 29,735.00
Rp 2,583.25
Rp 22,227.50
Rp 2,583.25
Rp 57,129.00 = Rp 42,846.75
Jumlah = Rp 133,664.71
Pembulatan = Rp 133,664.00

Rp 79,900.00
Rp 9,000.00 = Rp 88,900.00

Rp 5,947.00
Rp 516.65
Rp 17,782.00
Rp 2,066.60 = Rp 26,312.25
Jumlah = Rp 115,212.25
Pembulatan = Rp 115,212.00

Rp 15,138.00
Rp 1,592.00 = Rp 16,730.00

Rp 1,486.75
Rp 258.33
Rp 2,222.75
Rp 258.33 = Rp 4,226.15
Jumlah = Rp 20,956.15
Pembulatan = Rp 20,956.00

Rp 44,943.60
Rp 9,000.00 = Rp 53,943.60

Rp 1,486.75
Rp 258.33
Rp 2,222.75
Rp 258.33 = Rp 4,226.15
Jumlah = Rp 58,169.75
Pembulatan = Rp 58,169.00

Rp 20,935.50
Rp 931.00
Rp 3,157.50
Rp 931.00 = Rp 25,955.00

Rp 8,920.50
Rp 774.98
Rp 20,004.75
Rp 2,324.93
Rp 32,025.15 = Rp 32,025.15
Jumlah = Rp 57,980.15
Pembulatan = Rp 57,980.00

Rp 13,950.43 = Rp 13,950.43

Rp 5,947.00
Rp 516.65
Rp 13,336.50
Rp 1,549.95
Rp 21,350.10 = Rp 21,350.10
Jumlah = Rp 35,300.53
Pembulatan = Rp 35,300.00

a 3 x cat ( setara Paragon )


Rp 7,148.50
Rp 3,157.50
Rp 672.80 = Rp 10,978.80

Rp 8,920.50
Rp 774.98
Rp 20,004.75
Rp 2,324.93
Rp 32,025.15 = Rp 32,025.15
Jumlah = Rp 43,003.95
Pembulatan Rp 43,003.00

Medan, 01 Juli 2010

Dibuat Oleh :

....................................
Tenaga Ahli
PEMBANGUNAN GEDUNG BARU DAN REHABILITASI SARANA DAN PRASARANA BALAI BIBIT IKAN
JL. BUNGA GANYONG KEL. LADANG BAMBU KEC. MEDAN TUNTUNGAN

NO. NAMA BAHAN HARGA

A. DAFTAR PEKERJAAN
1 Pekerja Rp 59,470.00
2 Mandor Rp 103,330.00
3 Tukang Kayu Rp 88,910.00
4 Tukang Batu, Cat, Besi Rp 88,910.00
5 Kepala Tukang Rp 103,330.00

B. DAFTAR BAHAN
1 Tabah Timbun/ Merah Rp 97,320.00
2 Pasir Timbun Rp 106,930.00
3 Pasir Pasang Rp 144,180.00
4 Batu Krikil (A) Cor Rp 291,960.00
5 Batu Koral 15-20 cm Rp 177,220.00
6 Batu Bata Besar (Jumbo) Rp 840.00
7 Semen PC @ 40 Kg Rp 60,080.00
8 Semen Putih @ 40 Kg Rp 137,570.00
9 Broti/ Papan Kayu Sembarang Rp 6,367,950.00
10 Broti Kayu Meranti Rp 7,809,750.00
11 Papan Kayu Meranti Rp 8,410,500.00
12 Listplank Kalsiboard Rp 40,000.00
13 List Profil Rp 35,000.00
14 Papan Gypsum uk. 120 x 240 cm Rp 67,280.00
15 Paku Biasa Rp 24,630.00
16 Paku Seng Rp 31,840.00
17 Baut Seng + Ring Karet Rp 1,500.00
18 Skrup Rp 28,000.00
19 Besi Beton Rp 17,420.00
20 Pagar Depan Besi Hollow + Rel Rp 841,050.00
21 Pintu Harmonika Rp 1,441,800.00
22 Kawat Beton Rp 24,030.00
23 Kawat Harmonika Rp 44,450.00
24 Kuda-kuda/ Gording Baja Ringan (Atap Genteng Metal) Rp 216,270.00
25 Rangka Furing Rp 83,750.00
26 Sekat Parit Plat Besi Rp 300,000.00
27 Rabung Seng BJLS 20 L=30 cm Rp 25,230.00
28 Rabung Genteng Metal # 0,25 Rp 34,840.00
29 Genteng Metal # 0,25 (16 daun) Rp 79,900.00
30 Cat Minyak/ Perak (Setara Bee Brand) Rp 49,260.00
31 Minyak Cat Rp 18,620.00
32 Tepung Dempul Rp 8,410.00
33 Dempul Jadi Rp 18,620.00
34 Cat Tembok ( Setara Paragon ) Rp 16,820.00
35 Kertas Pasir Rp 4,210.00
36 Kaca Bening # = 5 mm Rp 158,600.00
37 Keramik 20 x 20 cm Rp 2,400.00
38 Keramik 20 x 25 cm Rp 2,760.00
39 Keramik 40 x 40 cm Rp 10,810.00
40 Siku Keramik (Bon-Bon) Rp 10,210.00
41 Tempat Sabun Keramik 10 x 20 cm Rp 40,850.00
42 Wastafel Komplet Standard Rp 510,640.00
43 Batu Con Blok K 125 Rp 1,680.00
44 Pipa PVC Ø ¾ " + aksesoris Rp 48,400.00
45 Pipa PVC Ø 1 " + aksesoris Rp 24,200.00
46 Pipa PVC Ø 2 " + aksesoris Rp 48,400.00
47 Pipa PVC Ø 4 " + aksesoris Rp 96,900.00
48 Pompa Air ( Sanyo Sejenis ) Rp 901,130.00
49 Pintu Fiber Glass Kamar Mandi Rp 408,510.00
50 Tangki Air Fiber Glass Kapasitas 0,75 m3 Rp 4,000,000.00
51 Instalasi Listrik Stop Kontak Rp 103,490.00
52 Instalasi Listrik Nyala Rp 103,490.00
53 Lampu SL 23 watt Rp 34,360.00
54 Box Zekering 1 group Rp 9,010.00
55 MCB 4 Amper Rp 18,020.00
56 Exhaust Fan Rp 400,000.00
57 Kran Air Lokal Uk ½" Rp 22,830.00
58 Stop Kran Ø 1" Rp 30,000.00
59 Instalasi Air Bersih Rp 103,930.00
60 Saringna Air Kamar Mandi (Floor Drain) Rp 17,420.00
61 Kunci Tanam Besar Rp 112,340.00
62 Engsel Pintu Nilon Uk 4" Rp 12,020.00
63 Engsel Jendela Nilon Uk 3" Rp 7,210.00
64 Grendel Jendela Rp 4,810.00
65 Hak Angin Rp 6,610.00
66 Pegangan Jendela Rp 6,610.00
67 Bak Kontrol Rp 150,000.00
68 Polikarbonat Tipis Transparan Rp 125,000.00
69 Polikarbonat Tebal/ Double Rp 150,000.00
70 Pembuatan Tulisan Plank Nama Rp 400,000.00
71 Mesin Pembuat Pelet Apung Rp 45,500,000.00
72 Tabung Gas Oksigen Rp 2,750,000.00
73 Instalasi Aerasi Ged. Pasca Panen + Hatchery Indoor Rp 2,750,000.00
74 Hi-Blow Rp 1,400,000.00
75 Hapa Beserta Rangka Uk. 1 x 1 x 0,5 m Rp 460,000.00
76 Hapa Beserta Rangka Uk. 1 x 2 x 0,5 m Rp 700,000.00
77 Hapa Uk. 1 x 3 x 1 m Rp 460,000.00

Medan, 01 Juli 2010


Diketahui Oleh : Dibuat Oleh :
CV. BARKAT JAYA

BUDI DARMAWAN ....................................


Direktur Tenaga Ahli
BUDI DARMAWAN ....................................
Direktur Tenaga Ahli
N REHABILITASI SARANA DAN PRASARANA BALAI BIBIT IKAN
KEL. LADANG BAMBU KEC. MEDAN TUNTUNGAN

SATUAN

Hari
Hari
Hari
Hari
Hari

M3
M3
M3
M3
M3
Bh
Zak
Zak
Ton
Ton
Ton
M'
M'
Lbr
Kg
Kg
Bh
Kg
Kg
M'

Kg



Unit
Lbr
Bh
Lbr
Kg
Ltr
Kg
Kg
Kg
Lbr

Bh
Bh
Bh
M'
Bh
Unit
Bh
M'
M'
M'
M'
Bh
Bh
Set
Ttk
Ttk
Bh
Set
Bh
Unit
Bh
Bh
Ttk
Bh
Bh
Set
Set
Bh
Bh
Bh
Bh
M'
M'

Unit
Bh
Set
Unit
Set
Set
Set

Medan, 01 Juli 2010


Dibuat Oleh :

....................................
Tenaga Ahli
....................................
Tenaga Ahli
JADWAL PELAKSANAAN
PEMBANGUNAN GEDUNG BARU DAN REHABILITASI SARANA DAN PRASARANA BALA
JL. BUNGA GANYONG KEL. LADANG BAMBU KEC. MEDAN TUNTUNGAN

MINGGU KE-
NO. URAIAN KEGIATAN
1 2 3 4 5 6

1 Pekerjaan Pendahuluan

2 Pekerjaan Gedung Pasca Panen

3 Pekerjaan Gudang Pangan

4 Pekerjaan Rehabilitasi Bangsal Pembenihan A

5 Pekerjaan Rehabilitasi Bangsal Pembenihan B

6 Pekerjaan Halaman

7 Pekerjaan Peralatan Pendukung Operasional Gedung

Diketahui Oleh :
CV. BARKAT JAYA

BUDI DARMAWAN
Direktur
L PELAKSANAAN
BILITASI SARANA DAN PRASARANA BALAI BIBIT IKAN
DANG BAMBU KEC. MEDAN TUNTUNGAN

MINGGU KE-
7 8 9 10 11 12

Medan, 01 Juli 2010


Dibuat Oleh :

....................................
Tenaga Ahli