BILL OF QUANTITY

PEMBANGUNAN RUMAH AMBROSSIA RESIDENCE


TYPE 47
Tambak Sawah - Sidoarjo

No. PEKERJAAN SPESIFIKASI VOL. SAT.

I PEKERJAAN RUMAH
A Pekerjaan Persiapan
1 Pengukuran dan Pasang Bowplank 40.00 m'

B Pekerjaan Tanah
1 Galian Pondasi 22.80 m3
2 Urugan Tanah Pondasi 7.41 m3
3 Urugan Tanah Lantai 18.24 m3
4 Urugan Tanah Taman 4.68 m3
5 Urugan Pasir Bawah Pondasi Tebal 5 Cm 1.71 m3
6 Urugan Pasir Bawah Lantai Tebal 7 Cm 2.28 m3
7 Pemadatan Tanah Pondasi & Lantai 53.70 m2

C Pekerjaan Pondasi
1 Pondasi Batu Kali Batu Kali Pas 1 : 4 15.39 m3
2 Plat Setempat Uk. 0,6 x 0,2 x 0,6 1.40 m3
3 Beton Sloof FB 1 Uk. 15 x 25 Cm 2.14 m3
4 Rollag Bata Camp. 1 : 4 18.00 m'

D Pekerjaan Dinding dan Beton


1 Pasangan Batu Alam 4.08 m2
2 Pasangan Bata Camp. 1 : 5 177.61 m2
3 Plester / Aci t=20 cm Camp. 1 : 2 Trasram 20.40 m2
4 Plester / Aci Camp. 1 : 5 332.96 m2
5 Benangan / Tali Air 88.47 m'
6 Beton Kolom Praktis ( kp ) Uk. 13 x 13 Cm 1.52 m3
7 Beton Ring Balok ( RB1 / RB . Gewel ) Uk. 13 x 15 Cm 1.11 m3
8 Beton Ring Balok Gantung ( RB3 ) Uk. 15 x 20 Cm 0.27 m3
9 Plat Beton & Canopy Beton Tebal 12 & 15 Cm 1.56 m3
10 Finishing Topi dan Canopy Beton 12.60 m2
11 Beton Meja Dapur Tebal 10 Cm 0.14 m3

E Pekerjaan Lantai Keramik


1 Keramik Lantai Uk. 60 x 60 Cm 35.30 m2
2 Keramik Teras Uk. 40 x 40 Cm 6.60 m2
3 Keramik Lantai KM Uk. 30 x 30 Cm 3.70 m2
4 Keramik Dinding KM Uk. 30 x 30 Cm 21.00 m2
5 Plint Lantai ( Siku L ) Uk. 3 Cm 51.00 m'
6 Keramik Dapur Uk. 20 x30 Cm 3.52 m2

F Pekerjaan Kusen , Pintu & Jendela


1 Daun Pintu Panel P1 3.00 bh
2 Daun Pintu KM P2 1.00 bh
3 Daun Pintu Panel PJ1 1.00 bh
4 Daun Jendela Kaca P3 1.00 bh
5 Daun Jendela Kaca J1 1.00 bh
6 Daun Jendela Kaca J2 2.00 bh
7 Daun Jendela Kaca J3 1.00 bh
8 Daun Jendela Kaca J4 1.00 bh
9 Daun Jendela Kaca J5 1.00 bh
10 Kusen Aluminium 4", Coating 67.35 m'

G Pekerjaan Plafond
1 Plafond Eternit + Rangka 13.42 m2
2 Plafond Gypsum 6mm + Rangka 35.30 m2
3 Tali Air 51.00 m'

H Pekerjaan Rangka Atap


1 Kuda - Kuda Galvalum 54.56 m2
2 Genteng Beton 62.20 m2
3 Genteng Nok 6.00 m'
4 Listplank 24.60 m'

I Pekerjaan Sanitasi & Instalasi Air


1 Bak MANDI Finish Keramik 20 x 20 Ex. Asia 1.00 bh
2 Closet Duduk Ex. INA 1.00 unit
3 Instalasi Air Bersih 1/2" + 3/4: Ex. Winlon 30.00 m'
4 Instalasi Air Kotor 4" Ex. Winlon 12.00 m'
5 Instalasi Air Kotor 3" Ex. Winlon 36.00 m'
6 Bak Kontrol 6.00 bh
7 Pas. KranTembok Ex. AER 3.00 bh
8 Zink Satu Sayap Ex. Royal 1 lubang 1.00 unit
9 Kran Zink Ex. AER 1.00 unit
10 Floor Drain Ex. Local 1.00 bh
11 Buat Tandon Air Bawah KAP. 1 M3 1.00 unit
12 Septic Tank + Rembesan 1.00 unit

J Pekerjaan Halaman Depan


1 Rabat Beton Car Port 15.00 m2

K Pekerjaan Pengecatan
1 Cat Dinding Dalam Catylac 246.75 m2
2 Cat Dinding Luar Mowilex 108.40 m2
3 Cat Plafond Catylac 48.72 m2
4 Cat Lisplank Mowilex 24.60 m'
5 Cat Daun Pintu dan Jendela Duco Nipe 2000 4.00 bh

L Pekerjaan Listrik
1 Instalasi Titik Lampu & Fitting NYM 2 x 2,5 12.00 titik
2 Instalasi Stop Kontak NYM 3 x 2,5 6.00 titik
3 Saklar Tunggal Broco 5.00 bh
4 Saklar Double Broco 2.00 bh
5 Stop Kontak Broco 6.00 bh
6 Lampu Taman 1.00 bh
7 Panel Box / Sekering 4 Group 1.00 lot
8 MCB 6A Phase = 1 Bh Broco 4.00 bh
9 Instalasi AC + stop kontak + Tanpa Refrigerant 2.00 titik
Pembuangan + sparing pipa

M Pekerjaan Lain - lain


1 Bak Sampah 1.00 ls
2 Pasangan Dinding Pagar Depan 12.00 m'
3 Pembersihan Akhir 1.00 ls
TOTAL
DIBULATKAN
Dibuat oleh

(………………………………………..)
E

HARGA
JUMLAH
SATUAN

46,000 1,840,000
1,840,000

78,000 1,778,400
12,500 92,625
120,000 2,188,800
240,000 1,123,200
560,000 957,600
560,000 1,276,800
14,500 778,650
8,196,075

540,000 8,310,600
1,860,000 2,604,000
1,960,000 4,194,400
90,000 1,620,000
16,729,000

135,000 550,800
86,000 15,274,460
36,000 734,400
33,000 10,987,680
9,500 840,465
2,245,000 3,412,400
2,670,000 2,963,700
2,670,000 720,900
962,000 1,500,720
37,500 472,500
962,000 134,680
37,592,705

235,000 8,295,500
115,000 759,000
90,000 333,000
105,000 2,205,000
75,000 3,825,000
105,000 369,600
15,787,100

1,250,000 3,750,000
1,150,000 1,150,000
1,450,000 1,450,000
950,000 950,000
850,000 850,000
235,000 470,000
800,000 800,000

3,665,000 3,665,000
125,000 8,418,750
21,503,750

125,000 1,677,500
105,000 3,706,500
21,000 1,071,000
6,455,000

135,000 7,365,600
102,000 6,344,400
260,000 1,560,000
85,000 2,091,000
17,361,000

90,000 90,000
2,450,000 2,450,000
32,500 975,000
68,000 816,000
57,500 2,070,000
225,000 1,350,000
35,000 105,000
265,000 265,000
165,000 165,000
95,000 95,000
1,850,000 1,850,000
2,650,000 2,650,000
12,881,000

82,500 1,237,500
1,237,500

16,500 4,071,375
45,000 4,878,000
18,500 901,320
23,500 578,100
1,200,000 4,800,000
15,228,795

180,000 2,160,000
185,000 1,110,000
40,000 200,000
45,000 90,000
40,000 240,000
265,000 265,000
225,000 225,000
65,000 260,000
950,000 1,900,000

6,450,000

650,000 650,000
135,000 1,620,000
200,000 200,000
2,470,000

TOTAL 163,731,925
DIBULATKAN 163,732,000
BILL OF QUANTITY
PEMBANGUNAN RUMAH AMBROSSIA RESIDENCE
TYPE 51
Tambak Sawah - Sidoarjo

No. PEKERJAAN SPESIFIKASI VOL. SAT.

I PEKERJAAN RUMAH
A Pekerjaan Persiapan
1 Pengukuran dan Pasang Bowplank 38.00 m'

B Pekerjaan Tanah
1 Galian Pondasi 18.28 m3
2 Urugan Tanah Pondasi 5.94 m3
3 Urugan Tanah Lantai 19.60 m3
4 Urugan Tanah Taman 4.68 m3
5 Urugan Pasir Bawah Pondasi Tebal 5 Cm 1.71 m3
6 Urugan Pasir Bawah Lantai Tebal 7 Cm 2.80 m3
7 Pemadatan Tanah Pondasi & Lantai 56.00 m2

C Pekerjaan Pondasi
1 Pondasi Batu Kali Batu Kali Pas 1 : 4 12.34 m3
2 Plat Setempat Uk. 0,75 x 0,2 x 0,75 1.40 m3
3 Beton Sloof FB 1 Uk. 15 x 25 Cm 1.71 m3
4 Rollag Bata Camp. 1 : 4 13.00 m'

D Pekerjaan Dinding dan Beton


1 Pasangan Batu Alam Ex. Paras 20 x 40 3.05 m2
2 Pasangan Bata Camp. 1 : 5 265.09 m2
3 Plester / Aci t=20 cm Camp. 1 : 2 Trasram 20.40 m2
4 Plester / Aci Camp. 1 : 5 430.94 m2
5 Benangan / Tali Air 88.47 m'
6 Beton Kolom Praktis ( kp ) Uk. 13 x 13 Cm 1.67 m3
7 Beton Ring Balok ( RB1 / RB . Gewel ) Uk. 13 x 15 Cm 0.82 m3
8 Beton Ring Balok Gantung ( RB3 ) Uk. 15 x 20 Cm 0.27 m3
9 Plat Beton & Canopy Beton Tebal 12 & 15 Cm 2.04 m3
10 Finishing Topi dan Canopy Beton 20.38 m2
11 Beton Meja Dapur Tebal 10 Cm 0.14 m3

E Pekerjaan Lantai Keramik


1 Keramik Lantai Uk. 60 x 60 Cm 38.44 m2
2 Keramik Teras Uk. 40 x 40 Cm 8.14 m2
3 Keramik Lantai KM Uk. 30 x 30 Cm 2.93 m2
4 Keramik Dinding KM Uk. 30 x 30 Cm 18.30 m2
5 Plint Lantai ( Siku L ) Uk. 3 Cm 42.00 m'
6 Keramik Dapur Uk. 20 x30 Cm 2.72 m2

F Pekerjaan Kusen , Pintu & Jendela


1 Daun Pintu Panel P1 2.00 bh
2 Daun Pintu KM P2 1.00 bh
3 Daun Pintu Panel PJ1 1.00 bh
4 Daun Jendela Kaca P3 1.00 bh
5 Daun Jendela Kaca J1 1.00 bh
6 Daun Jendela Kaca J2 1.00 bh
7 Daun Jendela Kaca J3 2.00 bh
8 Daun Jendela Kaca J4 1.00 bh
9 Kusen Aluminium 4", Coating 67.35 m'

G Pekerjaan Plafond
1 Plafond Eternit + Rangka Ex. Gyproc 10.42 m2
2 Plafond Gypsum 6mm + Rangka Tebal 0,3 Uk. 2 x 4 38.25 m2
3 Tali Air 42.00 m'

H Pekerjaan Rangka Atap


1 Kuda - Kuda Galvalum Ex. Platinum 57.80 m2
2 Genteng Beton Ex. Moenir Elabama 65.89 m2
3 Genteng Nok Ex. Moenir 6.00 m'
4 Listplank Ex. Nusaplank 22.80 m'

I Pekerjaan Sanitasi & Instalasi Air


1 Bak mandi Finish Keramik 20 x 20 Ex. Asia Tile 1.00 bh
2 Closet Duduk Ex. Ina 1.00 unit
3 Instalasi Air Bersih 1/2" + 3/4: PVC Winlon 30.00 m'
4 Instalasi Air Kotor 4" PVC Winlon 12.00 m'
5 Instalasi Air Kotor 3" PVC Winlon 36.00 m'
6 Bak Kontrol 6.00 bh
7 Pas. Kran Tembok Ex. AER 3.00 bh
8 Zink Satu Sayap Ex. Royal 1.00 unit
9 Kran Zink 1.00 unit
10 Floor Drain 1.00 bh
11 Buat Tandon Air Bawah KAP. 1 M3 1.00 unit
12 Septic Tank + Rembesan 1.00 unit

J Pekerjaan Halaman Depan


1 Rabat Beton Car Port 16.25 m2

K Pekerjaan Pengecatan
1 Cat Dinding Dalam Catylac 246.75 m2
2 Cat Dinding Luar Mowilex 108.40 m2
3 Cat Plafond Catylac 48.67 m2
4 Cat Lisplank Mowilex 22.80 m'
5 Cat Daun Pintu dan Jendela Duco Nipe 2000 4.00 bh
6 Cat Texture 2.94 m2

L Pekerjaan Listrik
1 Instalasi Titik Lampu & Fitting NYM 2 x 2,5 14.00 titik
2 Instalasi Stop Kontak NYM 3 x 2,5 4.00 titik
3 Saklar Tunggal Broco 5.00 bh
4 Saklar Double Broco 2.00 bh
5 Stop Kontak Broco 6.00 bh
6 Lampu Taman 1.00 bh
7 Panel Box / Sekering 4 Group Ex. Broco 1.00 lot
8 MCB 6A Phase = 1 Bh 4.00 bh
9 Instalasi AC Tanpa Refrigerant 2.00 titik

M Pekerjaan Lain - lain


1 Bak Sampah 1.00 ls
2 Pasangan Dinding Pagar Depan 14.00 m'
3 Pembersihan Akhir 1.00 ls
TOTAL
DIBULATKAN
Dibuat oleh

(………………………………………..)
HARGA
JUMLAH
SATUAN

46,000 1,748,000
1,748,000

78,000 1,425,840
12,500 74,250
120,000 2,352,000
240,000 1,123,200
560,000 957,600
560,000 1,568,000
14,500 812,000
8,312,890

540,000 6,663,600
1,860,000 2,604,000
1,960,000 3,351,600
90,000 1,170,000
13,789,200

135,000 411,750
86,000 22,797,740
36,000 734,400
33,000 14,221,020
9,500 840,465
2,245,000 3,749,150
2,670,000 2,189,400
2,670,000 720,900
962,000 1,962,480
37,500 764,250
962,000 134,680
48,526,235

235,000 9,033,400
115,000 936,100
90,000 263,700
105,000 1,921,500
75,000 3,150,000
105,000 285,600
15,590,300

1,250,000 2,500,000
1,150,000 1,150,000
1,450,000 1,450,000
1,050,000 1,050,000
850,000 850,000
235,000 235,000
800,000 1,600,000
2,673,000 2,673,000
95,000 6,398,250
17,906,250

125,000 1,302,500
105,000 4,016,250
21,000 882,000
6,200,750

135,000 7,803,000
102,000 6,720,780
260,000 1,560,000
85,000 1,938,000
18,021,780

90,000 90,000
2,450,000 2,450,000
32,500 975,000
68,000 816,000
57,500 2,070,000
225,000 1,350,000
35,000 105,000
265,000 265,000
165,000 165,000
95,000 95,000
1,850,000 1,850,000
2,650,000 2,650,000
12,881,000

82,500 1,340,625
1,340,625

16,500 4,071,375
45,000 4,878,000
18,500 900,395
23,500 535,800
1,200,000 4,800,000
95,000 279,300
15,464,870

180,000 2,520,000
185,000 740,000
40,000 200,000
45,000 90,000
40,000 240,000
265,000 265,000
225,000 225,000
65,000 260,000
950,000 1,900,000
6,440,000

650,000 650,000
135,000 1,890,000
250,000 250,000
2,790,000

TOTAL 169,011,900
DIBULATKAN 169,012,000
BILL OF QUANTITY
PEMBANGUNAN RUMAH AMBROSSIA RESIDENCE
TYPE 95 / 102
Tambak Sawah - Sidoarjo

No. PEKERJAAN SPESIFIKASI VOL. SAT.

A Pekerjaan Persiapan
1 Pengukuran dan Pasang Bowplank 49.00 m'

B Pekerjaan Tanah
1 Galian Pondasi 50.87 m3
2 Bor Strauss Pile Dia. 30 Cm Dalam 6 m dari Elv. Jalan 66.00 m'
3 Urugan Tanah Pondasi 16.96 m3
5 Urugan Pasir Bawah Pondasi Tebal 5 Cm 76.50 m2

C Pekerjaan Pondasi
1 Strauss Pile Dia. 30 Cm Dalam 6 m dari Elv. Jalan 4.66 m3
2 Pondasi Batu Kali Batu Kali Pas 1 : 4 33.91 m3
3 Beton Sloof S1 Uk. 15 x 25 Cm 0.76 m3
4 Beton Sloof S2 Uk. 20 x 30 Cm 2.56 m3
5 Plat Footing S3 Uk. 60 x 60 x 30 Cm 1.19 m3
6 Rollag Bata Camp. 1 : 4 12.00 m'

D Pekerjaan Dinding dan Beton


1 Pasangan Batu Alam 15.27 m2
2 Pasangan Bata Camp. 1 : 5 589.36 m2
3 Plester / Aci t=30 cm dari lantai Camp. 1 : 2 Trasram 37.68 m2
4 Plester / Aci Camp. 1 : 5 994.22 m2
5 Benangan / Tali Air 423.00 m'

Lantai 1
1 Beton Kolom (Kp) Uk. 13 x 15 Cm 0.45 m3
2 Beton Kolom (K1) Uk. 15 x 20 Cm 0.66 m3
3 Beton Kolom (K3) Uk. 15 x 25 Cm 0.36 m3
4 Beton Kolom (K4) Uk. 15 x 35 Cm 2.31 m3
Lantai 2
5 Beton Kolom (Kp) Uk. 13 x 15 Cm 0.27 m3
6 Beton Kolom (K1) Uk. 15 x 20 Cm 0.72 m3
7 Beton Kolom (K3) Uk. 15 x 25 Cm 2.34 m3
8 Beton Balok (D) Uk. 15 x 40 Cm 3.60 m3
9 Beton Balok (B) Uk. 15 x 30 Cm 0.31 m3
10 Beton Ring Balok (RB3) Uk. 15 x 20 Cm 1.80 m3
11 Beton Tangga 1.25 m3
12 Beton Meja Dapur Tebal 8 Cm 0.45 m3
13 Plat Beton Lantai 2 Tebal 10 Cm 6.18 m3
14 Plat Atap Beton Tebal 12 Cm 1.58 m3
15 Talang Beton Tebal 8 Cm 0.42 m3
16 Beton Ring Balok (RB2 / RB. Gewel) Uk. 15 x 20 Cm 1.20 m3
17 Beton Ring Balok (B. Latei) Uk. 15 x 25 Cm 0.94 m3
18 Finishing Topi dan Canopy Beton 12.00 m2

E Pekerjaan Lantai Keramik


1 Keramik Meja Dapur Granit Tile Uk. 60 x 60 Cm 4.56 m2
2 Granit Tile 60 x 60 Lantai 1 Utama Upah + Semen + Pasir 33.05 m2
3 Granit Tile 60 x 60 Lantai 2 Utama Upah + Semen + Pasir 29.80 m2
4 Keramik Lantai Dapur Platinum Uk. 40 x 40 Cm 5.25 m2
5 Keramik Teras Depan Platinum Uk. 40 x 40 Cm 6.24 m'
6 Keramik Lantai KM 1 Platinum Uk. 40 x 40 Cm 2.80 m2
7 Keramik Dinding KM 1 Platinum Uk. 20 x 33 Cm 13.42 m2
8 Keramik Lantai KM 2 Platinum Uk. 40 x 40 Cm 3.30 m2
9 Keramik Dinding KM 2 Platinum Uk. 20 x 33 Cm 20.73 m2
10 Keramik Lantai KM Utama Platinum Uk. 40 x 40 Cm 3.00 m2
11 Keramik Dindning KM Utama Platinum Uk. 20 x 33 Cm 19.53 m2
12 Keramik Plint Lantai Uk. 8 x 30 Cm 110.00 m'
13 Keramik Tangga Uk. 40 x 40 Cm 7.98 m2

F Pekerjaan Kusen , Pintu & Jendela


1 Kusen Alumunium Powder Coating Uk. 4" 119.93 m'
2 Daun Pintu P1 Panel - Fabrikasi 3.00 bh
3 Daun Pintu Kaca P2 Kaca 1.00 bh
4 Daun Pintu P2 Double Triplek 2.00 bh
5 Daun Pintu KM / WC P3 Pintu PVC 3.00 unit
6 Daun Jendela Kaca Besar J1 Alumunium + Kaca 5 mm 4.00 bh
7 Daun Jendela Kaca Sedang J2 Alumunium + Kaca 5 mm 12.00 bh
8 Kaca Mati Kaca Mati 5 mm 14.08 m2

G Pekerjaan Plafond
1 Plafond Calsiboard 4 mm (luar) Rangka Galvalum 24.00 m2
2 Plafond Gypsum 9 mm (dalam) Rangka Galvalum 91.63 m2
3 List Gypsum 142.20 m'

H Pekerjaan Rangka Atap


1 Kuda - Kuda Galvalum Galvalum A - Plus 59.20 m2
2 Genteng Beton Elabana GEP - Brown 59.20 m2
3 Genteng Nok Elabana GEP - Brown 8.00 m'
4 Listplank Nusaplank 27.60 m'
5 Atap Roof Top Rangka Hollow Galvalum 7.00 m'

I Pekerjaan Sanitasi & Instalasi Air


1 Kran Shower Onda 3.00 set
2 Closet Duduk Amstad 3.00 unit
3 Jet Spray Ex. China 3.00 set
4 Wastafel + Kran Wastafel Ex. China 3.00 set
5 Zink Satu Sayap 1.00 bh
6 Instalasi Air Bersih 1/2" + 3/4: westpex 65.00 m'
7 Instalasi Air Kotor 4" Trilliun D - Putih 38.00 m'
8 Instalasi Air Bekas dan Air Hujan 3" Trilliun D - Putih 36.00 m'
9 Bak Kontrol 6.00 bh
10 Pas. KranTembok 10.00 bh
11 Kran Zink 1.00 bh
12 Floor Drain dan Roof Drain 6.00 bh
13 Tandon Air Bawah KAP. 2 M3 1.00 unit
14 Tandon Air Atas 400 Liter 1.00 unit
15 Septic Tank + Rembesan 1.00 unit

J Pekerjaan Halaman Depan


1 Rabat Beton Car Port 19.25 m2
2 Batu Ampyangan 19.25 m2

K Pekerjaan Pengecatan
1 Cat Dinding Dalam Catylac 721.12 m2
2 Cat Dinding Luar Mowilex 273.10 m2
3 Cat Plafond Maxilite 115.63 m2
4 Cat Lisplank Emco 27.60 m2
5 Cat Duco Pintu Emco 14.08 m2

L Pekerjaan Listrik
1 Instalasi Titik Lampu Downlight NYM 2 x 2,5 16.00 titik
2 Instalasi Titik Lampu Pijar 2.00 titik
3 Instalasi Titik Lampu Spotlight Taman 1.00 titik
4 Instalasi Stop Kontak NYM 3 x 2,5 25.00 titik
5 Saklar Tunggal Broco 9.00 bh
6 Saklar Double Broco 2.00 bh
7 Stop Kontak Broco 25.00 bh
8 Instalasi Anthena 2.00 bh
9 Instalasi Telephone 2.00 bh
10 Ground Fudeng 1.00 unit
11 Panel Box / Sekering 4 Group 1.00 set

M Pekerjaan Lain - lain


1 Waterproofing Talang & Dak Beton Aquaproof 30.95 m2
2 Railing Tangga + Balkon Finsh. Cat Besi Hollow 2x4 & 4x4 9.70 m2
3 Pembersihan Akhir 1.00 ls
4 Pompa Air Shimizu P-135 - set
5 Bak Sampah 1.00 ls

TOTAL

Dibuat oleh

(………………………………………..)
NCE

HARGA
JUMLAH
SATUAN

46,000 2,254,000
2,254,000

78,000 3,967,860
34,000 2,244,000
12,500 212,000
28,000 2,142,000
8,565,860

1,360,000 6,337,600
540,000 18,311,400
1,960,000 1,489,600
2,180,000 5,580,800
1,860,000 2,213,400
90,000 1,080,000
35,012,800

135,000 2,061,450
86,000 50,684,960
36,000 1,356,480
33,000 32,809,260
9,500 4,018,500
90,930,650

2,245,000 1,010,250
2,465,000 1,626,900
2,670,000 961,200
2,835,000 6,548,850

2,245,000 606,150
2,465,000 1,774,800
2,670,000 6,247,800
3,185,000 11,466,000
2,835,000 878,850
2,670,000 4,806,000
2,560,000 3,200,000
962,000 432,900
2,409,000 14,887,620
2,560,000 4,044,800
962,000 404,040
2,670,000 3,204,000
2,670,000 2,509,800
96,200 1,154,400
65,764,360

235,000 1,071,600
235,000 7,766,750
235,000 7,003,000
95,000 498,750
115,000 717,600
90,000 252,000
105,000 1,409,100
90,000 297,000
105,000 2,176,650
90,000 270,000
105,000 2,050,650
75,000 8,250,000
115,000 917,700
32,680,800

95,000 11,393,350
635,000 1,905,000
655,000 655,000
475,000 950,000
425,000 1,275,000
850,000 3,400,000
650,000 7,800,000
97,000 1,365,760
28,744,110

125,000 3,000,000
105,000 9,621,150
32,000 4,550,400
17,171,550

135,000 7,992,000
102,000 6,038,400
260,000 2,080,000
85,000 2,346,000
450,000 3,150,000
21,606,400

135,000 405,000
2,450,000 7,350,000
115,000 345,000
425,000 1,275,000
265,000 265,000
32,500 2,112,500
68,000 2,584,000
57,500 2,070,000
225,000 1,350,000
35,000 350,000
165,000 165,000
95,000 570,000
2,325,000 2,325,000
1,650,000 1,650,000
2,650,000 2,650,000
25,466,500

82,500 1,588,125
160,000 3,080,000
4,668,125

16,500 11,898,480
45,000 12,289,500
18,500 2,139,155
23,500 648,600
350,000 4,928,000
31,903,735

215,000 3,440,000
180,000 360,000
295,000 295,000
185,000 4,625,000
40,000 360,000
45,000 90,000
40,000 1,000,000
35,000 70,000
45,000 90,000
435,000 435,000
225,000 225,000
10,990,000

32,500 1,005,875
575,000 5,577,500
300,000 300,000
-
650,000 650,000
7,533,375

TOTAL 383,292,265