B. REKAP BAHAN
1. Semen 670 zak
2. Pasir 60 mᶾ
3. Kerikil 81 mᶾ
4. Batukali 176 mᶾ
5. Besi 10 186 btg
6. Besi 6 161 btg
D. ONGKOS KERJA
- Cor beton 76 mᶾ x 125.000 = 9.500.000
- Pas Batukali 134 mᶾ x 250.000 = 33.750.000 +
43.250.000