Anda di halaman 1dari 1

1.

Volume Batukali Samping Atas


- Beton 5.7 mᶾ
- Batukali 35.2 mᶾ

2. Volume batukali samping belakang


- Beton 1.455 mᶾ
- Batukali 9.24 mᶾ

3. Volume batukali samping bawah


- Beton 68.415 mᶾ
- Batukali 90.675 mᶾ

A. REKAPITULASI Volume lokasi


1. Beton = 75.665 mᶾ
2. Batukali = 135.115 mᶾ

B. REKAP BAHAN
1. Semen 670 zak
2. Pasir 60 mᶾ
3. Kerikil 81 mᶾ
4. Batukali 176 mᶾ
5. Besi 10 186 btg
6. Besi 6 161 btg

C. RENCANA ANGGARAN BAHAN


1. Semen 670 x 70.000 = 46.900.000
2. Pasir 60 x 125.000 = 7.500.000
3. Kerikil 81 x 350.000 = 28.350.000
4. Batukali 176 x 137.500 = 24.200.000
5. Besi 10 186 x 60.000 = 11.160.000
6. Besi 6 161 x 30.000 = 4.830.000 +
122.940.000

D. ONGKOS KERJA
- Cor beton 76 mᶾ x 125.000 = 9.500.000
- Pas Batukali 134 mᶾ x 250.000 = 33.750.000 +
43.250.000