I. PEKERJAAN PERSIAPAN
1. Mobilisasi dan Demobilisasi Peralatan
2. Pekerjaan Pembersihan
3. Pekerjaan Direksi Keet, Barak Kerja dan gudang
4. Papan nama kegiatan
5. Pekerjaan Sondir

II. B. PEKERJAAN PERKUATAN SALURAN


1. Pekerjaan Sheet Pile Beton
1.1 Pengadaan Sheet Pile Beton Precast
b. Pemancangan Sheet Pile Beton Precast
c. Pemotongan Sheet Pile Beton
Rencana Pekerja Kapasitas Pekerjaan per Hari yang Hari untuk 1
hari diperlukan pekerjaan
E F = 1/C G=ExF H = D/G
ANALISA HARGA SATUAN P
Proyek Pembangunan Sheet Pile Jakabaring - Pale

No. Uraian Satuan Harga


Upah :
1 Pekerja Org/hari Rp 95,000.00
2 Tukang Org/hari Rp 110,000.00
3 Kepala Tukang Org/hari Rp 135,000.00
4 Mandor Org/hari Rp 165,000.00
5 Operator Org/hari Rp 165,000.00
6 Pembantu Operator Org/hari Rp 95,000.00
7 Surveyor Org/hari Rp 165,000.00
8 Juru Gambar Org/hari Rp 110,000.00

Bahan :
1 CCSP W 450 B M' Rp 952,000.00
2 Tiang Pancang Persegi 400x400mm M' Rp 563,000.00
3 Besi Canal CNP 200x75x20 (3,2 mm) M' Rp 83,333.00
2 Semen portland zak Rp 67,000.00
3 Kerikil m3 Rp 435,000.00
4 Pasir beton m3 Rp 125,000.00
5 Pasir pasangan m 3
Rp 95,000.00
6 Besi polos kg Rp 12,000.00
7 Kawat ikat kg Rp 18,000.00
8 Papan kayu m3 Rp 1,400,000.00
9 Kaso 5/7 cm m3 Rp 1,600,000.00
10 Paku 5cm dan 7cm kg Rp 18,000.00
11 Minyak Begisting liter Rp 10,700.00
12 Bata Merah bh Rp 550.00
13 Sling Angkur dia 40 mm M' Rp 161,000.00
14 Accesoris Pemasangan Sing Angkur Ls Rp 375,000.00
15 Tanah Urug / bahan tanah timbunan m3 Rp 59,500.00
16 Plamur kg Rp 9,300.00
17 Cat Dasar kg Rp 33,000.00
18 Cat Penutup kg Rp 52,000.00
19 Bensin Liter Rp 9,240.00
20 Solar Liter Rp 9,130.00
21 Pelumas Liter Rp 23,500.00
Peralatan :
1 Mesin Gerinda Potong Jam Rp 120,000.00
2 Alat Bantu Jam Rp 10,000.00
A HARGA SATUAN PEKERJAAN
Sheet Pile Jakabaring - Palembang, Sumatera Selatan
No. Uraian Pekerjaan/Jenis kegiatan Analisa Volume

I. PEKERJAAN PERSIAPAN
Mobilisasi / Demobilisasi Ls 1.00 Ls
Pengukuran Ls 1.00 Ls
Direksi Keet, Barak Kerja, dan Gudang Ls 1.00 Unit
Papan Nama Kegiatan Ls 1.00 bh
Pekerjaan Sondir Ls 4 titik

II. PEKERJAAN PERKUATAN SALURAN


Pekerjaan Turap
1.1 Pengadaan Turap Beton Precast W.450 B.1000 Anal.01.TP 532.00 btg
1.2 Pemancangan Turap Beton Precast Alat 4681.60 M'
1.3 Pengadaan Tiang Pancang Persegi 400x400mm Anal.02.TP 133.00 btg
1.4 Pemancangan Tiang Pancang Persegi Alat 399.00 M'
1.5 Sling Angkur Baja + Aksesoris Anal.03.TP 133.00 Set
1.6 Pengadaan Besi Kanal C Anal.04.TP 107.00 btg
Pekerjaan Pile Cap
2.1 Pekerjaan Pembobokan Kepala Turap Anal.05.TP 532.00 btg
2.2 Beton AHSP 2016-B.05.a 85.12 M³
2.3 Pembesian AHSP 2016-B.17.a 9607.92 Kg
2.4 Bekisting AHSP 2016-B.05.a 851.20 M²
Galian Tanah Biasa AHSP 2016-T.06.a.1 344.74 M³
Urugan Tanah Kembali AHSP 2016-T.14.a.1 310.26 M³
Timbunan Tanah Didatangkan AHSP 2016-T.14.a.2 2109.27 M³
Beton Cor AHSP 2016-B.05.a 31.92 M³
Bekisting AHSP 2016-B.05.a 146.30 M²

PEKERJAAN PAGAR
Pembongkaran Pagar Ls 1.00 Ls
Pembuatan Pagar
2.2 Beton AHSP 2016-B.05.a 32.11 M³
2.3 Pembesian AHSP 2016-B.17.a 73.04 Kg
2.4 Bekisting AHSP 2016-B.05.a 446.40 M²
2.5 Pasangan Batu Bata AHSP 2016-P.02.a.1 18.43 M³
2.6 Plesteran 1PC:4PP AHSP 2016-P.04.c 275.04 M²
2.7 Pengecatan AHSP 2016-A.4.7.1.10 275.04 M²
2.8 Galian Tanah Biasa AHSP 2016-T.06.a.1 4.32 M³
2.9 Urugan Tanah Kembali AHSP 2016-T.14.a.1 1.44 M³

PEKERJAAN LAIN-LAIN
Administrasi dan Pelaporan Ls 1.00 Ls
Dokumentasi Ls 1.00 Ls
Harga Satuan Jumlah Harga
(Rp) (Rp)
DAFTAR UPAH DAN BAHAN

Program : Program Pembangunan Talud/Turap dan Bronjong


Kegiatan : Perkuatan Tebing Sungai Kota Palembang
Pekerjaan : Pembangunan Sheet Pile di Tepian Sungai Kawasan JSC
Lokasi : Kota Palembang
SKPD : Dinas Pengelolaan Sumber Daya Air Provinsi Sumatera Selatan
Tahun Anggaran : 2017

No. Uraian Satuan Harga


Upah :
1 Pekerja Org/hari Rp 93,983.50
2 Tukang Org/hari Rp 108,823.00
3 Kepala Tukang Org/hari Rp 133,555.50
4 Mandor Org/hari Rp 163,234.50
5 Operator Org/hari Rp 163,234.50
6 Pembantu Operator Org/hari Rp 93,983.50
7 Surveyor Org/hari Rp 163,234.50
8 Juru Gambar Org/hari Rp 108,823.00

Bahan :
1 CCSP W 450 B M' Rp 941,813.60
2 Tiang Pancang Persegi 400x400mm M' Rp 556,975.90
3 Besi Canal CNP 200x75x20 (3,2 mm) M' Rp 82,441.34
2 Semen portland zak Rp 66,283.10
3 Kerikil m3 Rp 430,345.50
4 Pasir beton m3 Rp 123,662.50
5 Pasir pasangan m 3
Rp 93,983.50
6 Besi polos kg Rp 11,871.60
7 Kawat ikat kg Rp 17,807.40
8 Papan kayu m3 Rp 1,385,020.00
9 Kaso 5/7 cm m3 Rp 1,582,880.00
10 Paku 5cm dan 7cm kg Rp 17,807.40
11 Minyak Begisting liter Rp 10,585.51
12 Bata Merah bh Rp 544.12
13 Sling Angkur dia 40 mm M' Rp 159,277.30
14 Accesoris Pemasangan Sing Angku Ls Rp 370,987.50
15 Tanah Urug / bahan tanah timbunan m3 Rp 58,863.35
16 Plamur kg Rp 9,200.49
17 Cat Dasar kg Rp 32,646.90
18 Cat Penutup kg Rp 51,443.60
19 Bensin Liter Rp 9,141.13
20 Solar Liter Rp 9,032.31
21 Pelumas Liter Rp 23,248.55
22 CRANE Unit Rp 1,088,230,000.00
23 PILE HAMMER Unit Rp 437,270,600.00
24 Las Listrik Unit Rp 24,732,500.00

Peralatan :
1 Mesin Gerinda Potong Jam Rp 118,716.00
2 Alat Bantu Jam Rp 9,893.00
No. Uraian Pekerjaan/Jenis kegiatan Analisa Volume

I. PEKERJAAN PERSIAPAN
1. Mobilisasi / Demobilisasi Ls 1.00
2. Pengukuran Ls 1.00
3. Direksi Keet, Barak Kerja, dan Gudang Ls 1.00
4. Papan Nama Kegiatan Ls 1.00
5. Pekerjaan Sondir Ls 4

II. PEKERJAAN PERKUATAN SALURAN


Pekerjaan Turap
1.1 Pengadaan Turap Beton Precast W.450 B.1000 L.12M Anal.01.TP 532.00
1.2 Pemancangan Turap Beton Precast Alat 4681.60
1.3 Pengadaan Tiang Pancang Persegi 400x400mm L.6M Anal.02.TP 133.00
1.4 Pemancangan Tiang Pancang Persegi Alat 399.00
1.5 Sling Angkur Baja + Aksesoris Anal.03.TP 133.00
1.6 Pengadaan Besi Kanal C Anal.04.TP 107.00
Pekerjaan Pile Cap
2.1 Pekerjaan Pembobokan Kepala Turap Anal.05.TP 532.00
2.2 Beton AHSP 2016-B.05.a 85.12
2.3 Pembesian AHSP 2016-B.17.a 9607.92
2.4 Bekisting AHSP 2016-B.05.a 851.20
Galian Tanah Biasa AHSP 2016-T.06.a.1 344.74
Urugan Tanah Kembali AHSP 2016-T.14.a.1 310.26
Timbunan Tanah Didatangkan AHSP 2016-T.14.a.2 2109.27
Beton Cor AHSP 2016-B.05.a 31.92
Bekisting AHSP 2016-B.05.a 146.30

PEKERJAAN LAIN-LAIN
Administrasi dan Pelaporan Ls 1.00
Dokumentasi Ls 1.00
Harga Satuan Jumlah Harga
Volume (Rp) (Rp)

Ls
Ls
Unit
bh
titik

btg
M'
btg
M'
Set
btg

btg

Kg





Ls
Ls
ANALISA BIAYA OPERASI ALAT BERAT

JENIS ALAT : CRANE DAN PILE HAMMER


SATUAN PEMBAYARAN : Rupiah per Jam

NO. URAIAN KODE SATUAN

1 2 3 4

A. URAIAN PERALATAN
1. Jenis Peralatan
2. Merk/Tipe
3. Tenaga Pw HP
4. Kapasitas Cp -
5. Umur Ekonomis A Tahun
6. Jam Operasi Dalam 1 Tahun W Jam
7. Harga Alat B Rp

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat C Rp

2. Faktor Angsuran Modal i x (1 + i )A


= D -
(1 + i )A - 1
3. Biaya Pasti Perjam :
a. Biaya Pengembalian (B - C) x D
= E Rp/jam
W
b. Asuransi, dll. B
= Px F Rp/jam
W
Biaya Pasti per Jam G = (E + F) G Rp/jam

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12% - 15%) x Pw x Ms H Rp/jam

2. Pelumas = (2.5% - 3%) x Pw x Mp I Rp/jam

3. Biaya Bengkel B J Rp/jam


= (6.5% - 8.75%) x
W
4. Perawatan dan Perbaikan B K Rp/jam
= (12.5% - 17.5%) x
W
5. Operator = (m orang/jam) x U1 M Rp/jam
6. Pembantu Operator = (n orang/jam) x U2 L Rp/jam
Biaya Operasi (per Jam) = P Rp/jam

D. BIAYA OPERASI ALAT / JAM = ( G + P ) S Rp/jam


E. LAIN - LAIN
1. Bahan Bakar Bensin (non subsidi) Mb Liter
2. Bahan Bakar Solar (non subsidi) Ms Liter
3. Minyak Pelumas Mp Liter
RASI ALAT BERAT

PERHITUNGAN PERHITUNGAN PERHITUNGAN PERHITUNGAN


BIAYA OPERASI BIAYA OPERASI BIAYA OPERASI KETERANGAN BIAYA OPERASI
PERALATAN PERALATAN PERALATAN PERALATAN
5 5 5 6 .........................

CRANE PILE HAMMER Las Listrik Excavator


KR-20 KR-80 T-250A
55.0 80.0 5.0 105.0
5.00 2.00 250.00 0.90
5.0 5.0 5.0 5.0
2,000 2,000 2,000 2,000
1,100,000,000 442,000,000 25,000,000 2,037,486,794

110,000,000 44,200,000 2,500,000 203,748,679

Suku Bunga
0.26380 0.26380 0.26380 0.2637974808
i = 10%

130,579.75 52,469.32 2,967.72 241,867.748

Asuransi
1,100 442 25 2037.486794
p = 0.2 %
131,679.75 52,911.32 2,992.72 243,905.234

18,356 106,800 6,675 12.00 % 35,043.8

6,463 47,000 2,938 2.50 % 12,337.5

12,375 13,813 781 6.25 % 22,921.73

27,500 27,625 1,563 12.50 % 50937.16985

23,319 23,319 23,319 23,319


13,426 13,426 13,426 13,426
101,439 231,983 48,702 157,985.6

233,118.93 284,894.25 51,694.40 401,890.809


9,240 9,240 9,240 9,240
11,125 11,125 11,125 11,125
23,500 23,500 23,500 23,500
0.10 1.4641
0.002

PERHITUNGAN PERHITUNGAN
BIAYA OPERASI BIAYA OPERASI
PERALATAN PERALATAN
1.61051

Dump Truck Concrete Mixer

120.0 6.0
3.50 125.00
5.0 4
2,000 2000
372,167,641 25,913,950

37,216,764 2,591,395

0.2637974808 0.31547

-647.85
44,179.599 3,678.793

372.167641 25.9140

44,551.766 3,704.7065

40,050.0 2,002.50

14,100.0 705.00

4,186.89 291.53

9,304.19 647.85

23,319 23,319
13,426 13,426
104,386.5 40,392.31

148,938.272 44,097.0158
9,240 9,240
11,125 11,125
23,500 23,500
ANALISA HARGA SATUAN PEKERJAAN
No. Uraian Koefisien Satuan

A. PEKERJAAN PERSIAPAN
1. Mobilisasi dan demobilisasi peralatan per 1 Ls
a. Pengangkutan
1. Bahan dan material 1.00 Ls
Total Biaya

2. Pengukuran per 1 Ls
a. Alat 1 Ls

3. Direksi Keet per 1 m2


a. Tenaga
1. Mandor
2. Pekerja
3. Tukang

b. Bahan
1. Kayu kelas
2. Paku Biasa
3. Seng Bergelombang
4. Kayu Papan
Total Biaya

4. Papan Nama Kegiatan


a. Bahan dan Material 1.00 buah
Total Biaya

5. Pekerjaan Sondir per 1 Ls 4 titik


a. Tenaga
1. Surveyor
b. Alat
1. Sondir Pile
Total Biaya

II PEKERJAAN PERKUATAN TEBING


1. Pekerjaan Turap
1.1 Pengadaan Turap Beton Precast
a. Bahan
1. CCSP W 450 B 12,000.00 M'
b. Peralatan
1. Handling di lokasi proyek 5460.00 Kg
Total Biaya
2. Pemancangan Turap Beton Precast
A. Tenaga Kerja
1. Pekerja 0.7881 jam
2. Tukang 0.2252 jam
3. Mandor 0.0788 jam
B. Peralatan
1. Pile Hammer + Crane + Alat bantu 0.1126 jam
Total Biaya

3. Pengadaan Tiang Pancang Persegi


A. Bahan
1. Tiang Pancang Persegi 400 mm x 400 mm 3000 M'
B. Peralatan
1. Handling di lokasi proyek 831.00 Kg
Total Biaya

4. Pemancangan Tiang Pancang Persegi


A. Tenaga
1. Pekerja 0.4719 jam
2. Tukang 0.1348 jam
3. Mandor 0.0472 jam
B. Peralatan
1. Pile Hammer + Crane + alat bantu 0.0674 jam
Total Biaya

5. Sling Angkur Baja + Aksesoris


A. Tenaga
1. Pekerja 3.000 jam
2. Mandor 0.375 jam
B. Bahan
1. Sling Angkur diameter 40 mm 12.000 M'
2. Accesoris 1.000 Ls
C. Peralatan
1. Alat Bantu 1.000 Ls
Total Biaya

6. Pengadaan Besi Canal C


A. Bahan
1. Besi Canal C 1 M'
B. Peralatan
1. Handling di lokasi proyek 9.27 Kg
Total Biaya

7. Pekerjaan Pembobokan Kepala Turap


A. Tenaga
1. Pekerja 0.750 jam
2. Tukang 0.150 jam
3. Mandor 0.050 jam
B. Peralatan
1. Mesin Gerinda Potong 0.550 jam
2. Alat Bantu 1.000 Ls
Total Biaya

8. Pekerjaan Beton
A. Tenaga
1. Tukang 0.275 O/H
2. Kepala Tukang 0.028 O/H
3. Pekerja 1.65 O/H
4. Mandor 0.165 O/H

B. Bahan
1. Semen Portland 6.520 Zak
2. Kerikil 0.572 m3
3. Pasir Beton 0.543 m3
Total Biaya

9. Pembesian
A. Tenaga
1. Tukang Besi 0.700 O/H
2. Kepala Tukang 0.070 O/H
3. Pekerja 0.700 O/H
4. Mandor 0.070 O/H
B. Bahan
1. Besi Polos 105.000 Kg
2. Kawat Ikat 1.500 Kg
Total Biaya

10. Bekisting
A. Tenaga
1. Tukang Kayu 0.15 O/H
2. Kepala Tukang 0.015 O/H
3. Pekerja 0.3 O/H
4. Mandor 0.03 O/H

B. Bahan
1. Papan Kayu 0.014 m3
2. Kaso 5/7 cm 0.003 m3
3. Paku 5 cm dan 7 cm 0.3 Kg
4. Minyak Begisting 0.2 Liter
Total Biaya

11. Pasangan Batu Bata


A. Tenaga
1. Pekerja 2.400 O/H
2. Tukang 1.200 O/H
3. Mandor 0.240 O/H

B. Bahan
1. Bata Merah 500.000 bh
2. Semen Portland 3.500 Zak
3. Pasir Pasangan 0.330 m3
Total Biaya

12. Plesteran 1PC : 4PP


A. Tenaga
1. Pekerja 0.3 O/H
2. Tukang 0.15 O/H
3. Kepala Tukang 0.015 O/H
4. Mandor 0.03 O/H

B. Bahan
1. Semen Portland 0.089 Zak
2. Pasir Pasangan 0.018 m3
Total Biaya

13. Timbunan tanah sebagai bahan pengisi


A. Tenaga
1. Pekerja 0.40 O/H
2. Mandor 0.04 O/H

B. Bahan
1. Tanah Timbunan 1.10 M3
Total Biaya

14. Pengecatan
A. Tenaga
1. Pekerja 0.02 O/H
2. Tukang 0.06 O/H
3. Kepala Tukang 0.01 O/H
4. Mandor 0.00 O/H

B. Bahan
1. Plamur 0.10 Kg
2. Cat Dasar 0.10 Kg
3. Cat Penutup 0.26 Kg
Total Biaya

15. Galian Tanah Biasa


A. Tenga
1. Pekerja 0.563 o/h
2. Mandor 0.0563 o/h
Total Biaya

16. Timbunan/Urugan Tanah Kembali


A. Tenaga
1. Pekerja 0.33 O/H
2. Mandor 0.033 O/H
Total Biaya

17.
ATUAN PEKERJAAN
Harga Satuan (Rp) Biaya Total (Rp)

Rp2,967,900,000.00 Rp2,967,900,000.00
Rp2,967,900,000.00

Rp1,187,160,000.00 Rp1,187,160,000.00
Rp1,187,160,000.00

Rp296,790.00 Rp296,790.00
Rp296,790.00

2,473,250.00 9,893,000.00

9,893,000.00

941,813.60 11,301,763,200

148.40 810,264.00
11,302,573,464
13,426.21 10,581.20
15,546.14 3,500.99
23,319.21 1,837.55

674,260.00 75,921.68
91,841.42

556,975.90 1,670,927,700.00

148.40 123,320.40
1,671,051,020.40

13,426.21 6,335.83
15,546.14 2,095.62
23,319.21 1,100.67

674,260.00 45,445.12
54,977.24

13,426.21 40,278.64
23,319.21 8,744.71

159,277.30 1,911,327.60
370,987.50 370,987.50

9,893.00 9,893.00
2,341,231.45

82441.34 82441.34

148.4 1375.668
83817.008
13,426.21 10,069.66
15,546.14 2,331.92
23,319.21 1,165.96

118,716.00 65,293.80
9,893.00 9,893.00
88,754.34

108,823.00 29,926.33
133,555.50 3,739.55
93,983.50 155,072.78
163,234.50 26,933.69

66,283.10 432,165.81
430,345.50 246,157.63
123,662.50 67,148.74
961,144.52

108,823.00 76,176.10
133,555.50 9,348.89
93,983.50 65,788.45
163,234.50 11,426.42

11,871.60 1,246,518.00
17,807.40 26,711.10
1,435,968.95

108,823.00 16,323.45
133,555.50 2,003.33
93,983.50 28,195.05
163,234.50 4,897.04

1,385,020.00 19,390.28
1,582,880.00 4,748.64
17,807.40 5,342.22
10,585.51 2,117.10
83,017.11

93,983.50 225,560.40
108,823.00 130,587.60
163,234.50 39,176.28

544.12 272,060.00
66,283.10 231,990.85
93,983.50 31,014.56
930,389.69

93,983.50 28,195.05
108,823.00 16,323.45
133,555.50 2,003.33
163,234.50 4,897.04

66,283.10 5,899.20
93,983.50 1,691.70
59,009.77

93983.50 37593.40
163234.50 6529.38

58863.35 64749.69
108872.47

93,983.50 1,879.67
108,823.00 6,855.85
133,555.50 841.40
163,234.50 489.70

9,200.49 920.05
32,646.90 3,264.69
51,443.60 13,375.34
27,626.70

93,983.50 52,912.71
163,234.50 9,190.10
62,102.81

93,983.50 31,014.56
163,234.50 5,386.74
36,401.29
Analisis Produktivitas Alat Berat
SatuanPembayaran : m3/jam

No. Uraian Kode Koefisien Satuan


per m' penetrasi pancang beton precast W.450 B.1000 L.12M
Crane 5T + Pile Hammer 2T
Kapasitas per jam continue V1 20.00
m/jam
Faktor Efisiensi Alat Fa 0.75

Waktu siklus per titik pemancangan


waktu membongkar dan reseting hammer pada posisi pancang T1 15.00 menit
Memasang tiang (termasuk sambungan) dan memancang T2 45.00 menit
Lain - lain (mengantur, menggeser dan menunggu) T3 16.00 menit
Ts1 76.00 menit

Kapsitas Produksi/jam
Va x Fa x T2 Q1 8.88 m/jam
Koefisien Alat/bh

Tenaga
Kebutuhan Tenaga
Produksi yang menentukan : Pile Driver Q1 8.88 m/jam
Produksi per hari m'/hari

Kebutuhan Tenaga
1. Pekerja orang
2. Tukang Pancang orang
3. Mandor orang

Koefisien tenaga per m3


1. Pekerja jam
2. Tukang Pancang jam
3. Mandor jam
Analisis Produ
Satuan

No.
Keterangan

Asumsi
Asumsi
Asumsi
Analisis Produktivitas Alat Berat
Pembayaran : m3/jam

Uraian Kode Koefisien Satuan Keterangan

per m' penetrasi pancang beton precast W.450 B.1000 L.12M


Crane 5T + Pile Hammer 2T
Kapasitas per jam continue V1 40.00
m/jam
Faktor Efisiensi Alat Fa 0.75

Waktu siklus per titik pemancangan


waktu membongkar dan reseting hammer pada posisi pancang T1 15.00 menit Asumsi
Memasang tiang (termasuk sambungan) dan memancang T2 22.50 menit Asumsi
Lain - lain (mengantur, menggeser dan menunggu) T3 8.00 menit Asumsi
Ts1 45.50 menit

Kapsitas Produksi/jam
Va x Fa x T2 Q1 14.84 m/jam
Koefisien Alat/bh

Tenaga
Kebutuhan Tenaga
Produksi yang menentukan : Pile Driver Q1 14.84 m/jam
Produksi per hari m'/hari

Kebutuhan Tenaga
1. Pekerja orang
2. Tukang Pancang orang
3. Mandor orang

Koefisien tenaga per m3


1. Pekerja jam
2. Tukang Pancang jam
3. Mandor jam
Produksivitas Kerja Aktual
1. Excavator
Diketahui
Model 215D LC
Kapasitas Bucket 0.93 m3
Waktu muat 1.00 menit
Waktu ayun bermuatan 0.10 menit
Waktu menumpahkan muatan 0.10 menit
Waktu ayun kosong 0.08 menit
Carry Factor 1.00
Faktor efisiensi kerja 0.83
Ditanya PKA Excavator

Penyelesaian :
a. Isi Aktual Bucket
kapasitas bucket x carry factor 0,93 x 1,00 0.93

b. Waktu Siklus
Waktu Muat 1.00 menit
Waktu ayun bermuatan 0.10 menit
Waktu menumpahkan muatan 0.10 menit
Waktu ayun kosong 0.08 menit
Total waktu siklus 1.28 menit

c. Produksi Kerja Kasar (PKK)


Isi aktual bucket x jumlah siklus/jam 0,93 m3 x (60 menit/jam /1,28 menit) 43.59375 m3/jam

d. Produksi Kerja Aktual Excavator


PKK x faktor efisiensi kerja 43,593 x 0,83 36.1828125 m3/jam
PERHITUNGAN VOLUME PEKERJAAN
Proyek Pembangunan Rumah Sakit Bunda Jakabaring - Palembang, Sumatera Selatan

NO Uraian Pekerjaan Uraian Perhitungan


1 PEKERJAAN PERSIAPAN
1.1 Pekerjaan Pembersihan
289 m Panjang = 289 m
Lebar = 5 m
14 m Luas = 289 x 5

= 1445 m2
1.2 Direksi Keet, Barak Kerja, dan Gudang
8m Panjang = 8 m
5m Lebar = 5 m
Luas = 8x 5

= 40 m2
1.3 Pemasangan Bowplank
Panjang = 289 m
Lebar = 2 m
2 (289 +
Keliling =
2)
= 582 m2
1.4 Pembuatan papan nama kerja
1.6 Mobilisasi / Demobilisasi
1.7 Pekerjaan sondir
II. PEKERJAAN STRUKTUR
2.1 Pengadaan Turap Beton Precast W.450 B.1000 L.12M
Jumlah = 532 buah
Panjang = 289 m
Lebar = 12 m
Tinggi = 1 m
p.l.t
Volume = .jumlah
pile cap

1,8 x 1,68
=
x 1 x 27

= m³
2.2 Pemancangan Turap Beton Precast
Jumlah = 4681.6 buah
Panjang = m
Lebar = m
Tinggi = m
p.l.t
Volume = .jumlah
pile cap

1,8 x 1,68
=
x 1 x 27

= m³
2.3 Pengadaan Tiang Pancang Persegi 400x400mm L.6M
Jumlah = 133 buah
Panjang = m
Lebar = m
Tinggi = m
p.l.t
Volume = .jumlah
pile cap

1,8 x 1,68
=
x 1 x 27

= m³
2.4 Pemancangan Tiang Pancang Persegi
Jumlah = 399 buah
Panjang = m
Lebar = m
Tinggi = m
p.l.t
Volume = .jumlah
pile cap

1,8 x 1,68
=
x 1 x 27

= m³
2.5 Sling Angkur Baja + Aksesoris
Jumlah = 133 buah
Panjang = m
Lebar = m
Tinggi = m
p.l.t
Volume = .jumlah
pile cap

1,8 x 1,68
=
x 1 x 27

= m³
2.6 Pengadaan Besi Kanal C
Jumlah = 107 buah
Panjang = m
Lebar = m
Tinggi = m
p.l.t
Volume = .jumlah
pile cap

1,8 x 1,68
=
x 1 x 27

= m³
III. PEKERJAAN PILE CAP
3.1 Pekerjaan Pembobokan Kepala Turap
Jumlah = 532 buah
Panjang = m
Lebar = m
Tinggi = m
p.l.t
Volume = .jumlah
pile cap

1,8 x 1,68
=
x 1 x 27

= m³
3.2 Beton
Jumlah = 85.12 buah
Panjang = 0.8 m
Lebar = 0.2 m

p.l.t
Volume = .jumlah
pile cap

1,8 x 1,68
=
x 1 x 27

= m³
3.3 Pembesian
Besi Ø 10" = 0,617 Kg/m' Jumlah = 9607.92 buah
1.80 Panjang = m
Lebar = m
Besi Ø 12" Tinggi = m
p.l.t
Volume = .jumlah
3.00 pile cap

1,8 x 1,68
=
x 1 x 27

= = m³
=

3.4 Bekisting
Jumlah = 851.20 buah
Panjang = m
Lebar = m
Tinggi = m
p.l.t
Volume = .jumlah
pile cap

1,8 x 1,68
=
x 1 x 27

= m³
3.5 Galian Tanah Biasa
Jumlah = 344.74 buah
Panjang = m
Lebar = m
Tinggi = m
p.l.t
Volume = .jumlah
pile cap

1,8 x 1,68
=
x 1 x 27

= m³
3.6 Urugan Tanah Kembali
Jumlah = 310.26 buah
Panjang = m
Lebar = m
Tinggi = m
p.l.t
Volume = .jumlah
pile cap

1,8 x 1,68
=
x 1 x 27

= m³
3.7 Timbunan Tanah Didatangkan
Jumlah = 310.26 buah
Panjang = m
Lebar = m
Tinggi = m
p.l.t
Volume = .jumlah
pile cap
1,8 x 1,68
=
x 1 x 27

= m³
3.8 Beton Cor
Jumlah = 2109.27 buah
Panjang = m
Lebar = m
Tinggi = m
p.l.t
Volume = .jumlah
pile cap

1,8 x 1,68
=
x 1 x 27

= m³
3.9 Bekisting
Jumlah = 31.92 buah
Panjang = m
Lebar = m
Tinggi = m
p.l.t
Volume = .jumlah
pile cap

1,8 x 1,68
=
x 1 x 27

= m³
ang, Sumatera Selatan

Volume Satuan

1445.00 m²

40.00 m²

582.00 m²
1.00 bh
1.00 Ls
4 Titik

1.1 Pengadaan Turap Beton Preca Anal.01.TP 532.00 btg


1.2 Pemancangan Turap Beton Pre Alat 4681.60 M'
1.3 Pengadaan Tiang Pancang Pe Anal.02.TP 133.00 btg
1.4 Pemancangan Tiang Pancang P Alat 399.00 M'
1.5 Sling Angkur Baja + Aksesori Anal.03.TP 133.00 Set

Anal.04.TP 107.00
1.6 Pengadaan Besi Kanal C btg

Pekerjaan Pile Cap


81.65 m³ 2.1 Pekerjaan Pembobokan Kepala Anal.05.TP 532.00 btg
2.2 Beton AHSP 2016-B.05.a 85.12 M³
2.3 Pembesian AHSP 2016-B.17.a 9607.92 Kg
2.4 Bekisting AHSP 2016-B.05.a 851.20 M²
Galian Tanah Biasa AHSP 2016-T.06.a.1 344.74 M³
Urugan Tanah Kembali AHSP 2016-T.14.a.1 310.26 M³
AHSP 2016-T.14.a.22109.27
Timbunan Tanah Didatangkan M³

AHSP 2016-B.05.a 31.92


Beton Cor M³
81.65 m³ Bekisting AHSP 2016-B.05.a 146.30 M²

81.65 m³

81.65 m³

81.65 m³
81.65 m³

81.65 m³
Pembobokan Kepala Turap

Beton
0.20 x 0.80

Pembesian Per 3 M'

Besi Ø 10" = 0.617


81.65 m³ 1.80 x 20.00

Besi Ø 12" = 0.888


3.00 x 12.00

0.617 x 36.00

0.888 x 36.00

81.65 m³ Bekisting
0.20 x 4.00

Galian Tanah Biasa


3.00 x 1.73

81.65 m³

81.65 m³

81.65 m³
81.65 m³

81.65 m³

81.65 m³
= 0 btg

x 0.00 =

kg/m'
=

kg/m'
=

x 0.00 =

x 0.00
=
x 4.00 x 0.00 =

x 0.50 x 0 =
- m3

36.00 m'

36.00 m'

- kg

- kg

- kg
- m2

- m3
TIME SCHEDULE
Program : Program Pembangunan Talud/Turap dan Bronjong
Kegiatan : Perkuatan Tebing Sungai Kota Palembang
Paket Kegiatan : Pembangunan Sheet Pile di Tepian Sungai Kawasan JSC
Lokasi : Kota Palembang
SKPD : Dinas Pengelolaan Sumber Daya Air Provinsi Sumatera Selatan
Tahun Anggaran : 2017

Waktu Pelaksanaan
Bobot
No Uraian Volume I II III IV
(%)
1 2 3 4 5 6 7 8 9 10 11 12 13

I. PEKERJAAN PERSIAPAN
1. Mobilisasi / Demobilisasi 1.00 Ls 0.275 0.137
2. Pengukuran 1.00 Ls 0.110 0.055
3. Direksi Keet, Barak Kerja, dan Gudang 1.00 Unit 0.642 0.642
4. Papan Nama Kegiatan 1.00 bh 0.003 0.003
5. Pekerjaan Sondir 1.00 titik 0.092 0.031 0.031 0.031

I. PEKERJAAN PERKUATAN SALURAN


1. Pekerjaan Turap
1.1 Pengadaan Turap Beton Precast W.450 B.1000 L.12M 532.00 Btg 65.675 3.127 3.127 3.127 3.127 3.127 3.127 3.127 3.127 3.127 3.127 3.127 3.127
1.2 Pemancangan Turap Beton Precast 4681.60 M' 4.382 0.209 0.209 0.209 0.209 0.209 0.209 0.209 0.209 0.209 0.209 0.209
1.3 Pengadaan Tiang Pancang Persegi 400x400mm L.6M 133.00 Btg 2.432 0.116 0.116 0.116 0.116 0.116 0.116 0.116 0.116 0.116 0.116 0.116 0.116
1.4 Pemancangan Tiang Pancang Persegi 399.00 M' 0.224 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011
1.5 Sling Angkur Baja + Aksesoris 133.00 Set 3.174 0.151 0.151 0.151 0.151 0.151 0.151 0.151 0.151 0.151 0.151 0.151
1.6 Pengadaan Besi Kanal C 107.00 Btg 0.548 0.026 0.026 0.026 0.026 0.026 0.026 0.026 0.026 0.026 0.026 0.026 0.026
2. Pekerjaan Pile Cap
2.1 Pekerjaan Pembobokan Kepala Turap 532.00 Btg 0.481 0.024 0.024 0.024 0.024 0.024 0.024 0.024 0.024 0.024 0.024
2.2 Beton 85.12 M³ 0.775 0.041 0.041 0.041 0.041 0.041 0.041 0.041 0.041 0.041
2.3 Pembesian 9607.92 Kg 15.937 0.839 0.839 0.839 0.839 0.839 0.839 0.839 0.839 0.839 0.839
2.4 Bekisting 851.20 M² 0.720 0.040 0.040 0.040 0.040 0.040 0.040 0.040 0.040 0.040
3. Galian Tanah Biasa 344.74 M³ 0.218 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022
4. Urugan Tanah Kembali 310.26 M³ 0.115 0.012
5. Timbunan Tanah Didatangkan 2109.27 M³ 2.341
6. Beton Cor 31.92 M³ 0.291
7. Bekisting 146.30 M² 0.124

IV. PEKERJAAN LAIN-LAIN


1. Administrasi dan Pelaporan 1.00 Ls 0.069 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.003
2. Dokumentasi 1.00 Ls 0.069 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.003

Jumlah 98.696 0.87 3.33 3.70 4.53 4.61 4.61 4.61 4.61 4.61 4.61 4.61 4.59 4.60
Rencana Per Minggu 0.873 3.33 3.70 4.53 4.61 4.61 4.61 4.61 4.61 4.61 4.61 4.59 4.60
Komulatif Rencana 0.873 4.20 7.90 12.43 17.04 21.65 26.26 30.87 35.48 40.09 44.71 49.29 53.90
Realisasi Per Minggu 0.837 0.033 3.279 4.202 3.498 3.289 3.315 3.312 4.173 4.154 4.154 4.154 4.154
Komulatif Realisasi 0.837 0.870 4.150 8.351 11.849 15.138 18.453 21.765 25.938 30.092 34.246 38.400 42.553
Deviasi 0.036 3.330 3.749 4.077 5.191 6.513 7.809 9.107 9.546 10.003 10.460 10.895 11.342

0.161 -35.323
16.8786677626846
elaksanaan Pemeliharaan
IV V VI (Bulan) Ket
14 15 16 17 18 19 20 21 22 23 24 1 2 3 4 5 6

0.137 100%
0.055

3.127 3.127 3.127 3.127 3.127 3.127 3.127 3.127 3.127


0.209 0.209 0.209 0.209 0.209 0.209 0.209 0.209 0.209 0.209
0.116 0.116 0.116 0.116 0.116 0.116 0.116 0.116 0.116
0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011
0.151 0.151 0.151 0.151 0.151 0.151 0.151 0.151 0.151 0.151
0.026 0.026 0.026 0.026 0.026 0.026 0.026 0.026 0.026

0.024 0.024 0.024 0.024 0.024 0.024 0.024 0.024 0.024 0.024
0.041 0.041 0.041 0.041 0.041 0.041 0.041 0.041 0.041 0.041 50%
0.839 0.839 0.839 0.839 0.839 0.839 0.839 0.839 0.839
0.040 0.040 0.040 0.040 0.040 0.040 0.040 0.040 0.040

0.012 0.012 0.012 0.012 0.012 0.012 0.012 0.012 0.012


0.234 0.234 0.234 0.234 0.234 0.234 0.234 0.234 0.234 0.234
0.036 0.036 0.036 0.036 0.036 0.036 0.036 0.036
0.015 0.015 0.015 0.015 0.015 0.015 0.015 0.015
0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.003
0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.003

0%

4.83 4.83 4.89 4.89 4.89 4.89 4.89 4.89 4.89 0.73 0.20
4.83 4.83 4.89 4.89 4.89 4.89 4.89 4.89 4.89 0.73 0.20
58.73 63.56 68.45 73.34 78.22 83.11 88.00 92.88 97.77 98.50 98.7 100

Palembang, 2017

Pejabat Pembuat Teknis Kerja


Dinas PSDA Prov. Sumsel

NUMERI, ST, MPSDA


NIP. 19750130199703 1 003