Subj: Monitoring the rest of OSP progress Project-5

Date: 1-Aug-18

Link Petasia-Tentena
NO URAIAN PEKERJAAN Total Scope Sisa Pekerjaan Current Pending Total
Achievement
1 Galian+Laying HDPE 159,366 30,366 30,366 0
2 Rektifikasi 108,000 61,878 57,470 4408
3 HH 166 89 88 1
4 Bridge 4,412 3,166 3,166 0
5 Pole 520 520 520 0
6 Pulling AC Cable 21,000 21,000 21,000 0
7 Pulling DC Cable 141,522 116,522 116,522 0

Link Wanggudu-Bungku
NO URAIAN PEKERJAAN Total Scope Sisa Pekerjaan Current Pending Total
Achievement
1 Galian+Laying HDPE 210,302 2,000 1,620 380
2 Rektifikasi 80,000 78,642 78,319 323
3 HH 213,302 50 33 17
4 Bridge 8,500 20 20 -
5 Pulling DC Cable 218,250 38,000 29,200 8,800

Link Kendari-Wanggudu
NO URAIAN PEKERJAAN Total Scope Sisa Pekerjaan Current Pending Total
Achievement
1 Rektifikasi Fiber Cut - 6 6 0
2 Penarikan Cable (Repair) - 2,000 2,000 0
3 Perapihan Cable turun ke bawah - 8 8 0
4 Perubahan titik HH due to PU - 5 5 0

Link Bungku-Petasia
NO URAIAN PEKERJAAN Total Scope Sisa Pekerjaan Current Pending Total
Achievement
1 Change DC to AC cable - 6,800 600 6200
2 Pending pole 9 meter - 16 16 0
3 Rektifikasi Fiber Cut - 5 5 0
Prepared by AP
Wk-29
15-Jul-18 16-Jul-18 17-Jul-18 18-Jul-18 19-Jul-18
Prog. MP Prog. MP Prog. MP Prog. MP Prog. MP

0 0 0 0 0

Wk-29
15-Jul-18 16-Jul-18 17-Jul-18 18-Jul-18 19-Jul-18
Prog. MP Prog. MP Prog. MP Prog. MP Prog. MP
46 13 110 13 0 13 157 30 41 24
0 20 0 20 0 20 0 0 0 0
2 17 1 17 2 17 2 17 0 17
0 0 0 0 0 0 0 6 0 0
0 12 1000 12 700 12 300 12 2000 24
62 62 62 65 65

Wk-29
15-Jul-18 16-Jul-18 17-Jul-18 18-Jul-18 19-Jul-18
Prog. MP Prog. MP Prog. MP Prog. MP Prog. MP

0 0 0 0 0

Wk-29
15-Jul-18 16-Jul-18 17-Jul-18 18-Jul-18 19-Jul-18
Prog. MP Prog. MP Prog. MP Prog. MP Prog. MP
0 0 0 0 0 0 0 0 1500 10
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 10
Wk-30
20-Jul-18 21-Jul-18 22-Jul-18 23-Jul-18 24-Jul-18
Prog. MP Prog. MP Prog. MP Prog. MP Prog. MP
0 0 0 0 0 0 0 0 0 0
1267 38 801 38 674 38 714 38 952 38
0 12 0 12 0 12 0 12 1 12
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 8
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
50 50 50 50 58

Wk-30
20-Jul-18 21-Jul-18 22-Jul-18 23-Jul-18 24-Jul-18
Prog. MP Prog. MP Prog. MP Prog. MP Prog. MP
0 0 0 0 0 0 0 0 26 18
188 24 0 24 135 24 0 24 0 6
2 7 0 17 2 17 5 17 1 17
0 0 0 0 0 0 0 0 0 0
1300 24 500 24 1500 24 1500 24 0 24
55 65 65 65 65

Wk-30
20-Jul-18 21-Jul-18 22-Jul-18 23-Jul-18 24-Jul-18
Prog. MP Prog. MP Prog. MP Prog. MP Prog. MP

0 0 0 0 0

Wk-30
20-Jul-18 21-Jul-18 22-Jul-18 23-Jul-18 24-Jul-18
Prog. MP Prog. MP Prog. MP Prog. MP Prog. MP
700 100 800 10 1500 10 700 10 1000 10
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 22
100 10 10 10 32
Wk-30
25-Jul-18 26-Jul-18 27-Jul-18 28-Jul-18 29-Jul-18
Prog. MP Prog. MP Prog. MP Prog. MP Prog. MP

0 0 0 0 0

Wk-30
25-Jul-18 26-Jul-18 27-Jul-18 28-Jul-18 29-Jul-18
Prog. MP Prog. MP Prog. MP Prog. MP Prog. MP

0 0 0 0 0

Wk-30
25-Jul-18 26-Jul-18 27-Jul-18 28-Jul-18 29-Jul-18
Prog. MP Prog. MP Prog. MP Prog. MP Prog. MP

0 0 0 0 0

Wk-30
25-Jul-18 26-Jul-18 27-Jul-18 28-Jul-18 29-Jul-18
Prog. MP Prog. MP Prog. MP Prog. MP Prog. MP

0 0 0 0 0
Wk-31
30-Jul-18 31-Jul-18 1-Aug-18 2-Aug-18 3-Aug-18
Prog. MP Prog. MP Prog. MP Prog. MP Prog. MP

0 0 0 0 0

Wk-31
30-Jul-18 31-Jul-18 1-Aug-18 2-Aug-18 3-Aug-18
Prog. MP Prog. MP Prog. MP Prog. MP Prog. MP

0 0 0 0 0

Wk-31
30-Jul-18 31-Jul-18 1-Aug-18 2-Aug-18 3-Aug-18
Prog. MP Prog. MP Prog. MP Prog. MP Prog. MP

0 0 0 0 0

Wk-31
30-Jul-18 31-Jul-18 1-Aug-18 2-Aug-18 3-Aug-18
Prog. MP Prog. MP Prog. MP Prog. MP Prog. MP

0 0 0 0 0
4-Aug-18
Prog. MP

4-Aug-18
Prog. MP

4-Aug-18
Prog. MP

4-Aug-18
Prog. MP

0
Total
No. Segment Pending Pekerjaan Pekerjaan

1. Fiber cut as follows:


Span HH31-HH32 by crazy man
Span HH55-HH56= 1 titk due to PU
Span HH68-HH69= 4 titik due to PU
Span HH69-HH70= 1 titik due to PU
1 Kendari-Wanggudu Span HH70-HH71= 3 titik due to PU
Span HH71-HH72= 2 titik due to PU
2. Perbaikan 3 buah HH akibat pekerjaan PU pada span
HH70-HH72.
3. Perbaikan slack support untuk span KU

Galian+Laying HDPE 210,302


Rektifikasi 80,000
HH 213
Bridge 8,500
2 Wanggudu-Bungku Pulling DC Cable 218,250
Fiber Cut:
HH67-HH68
HH95-HH96
HH155
Change DC to AC cable 6,800
3 Bungku-Petasia Pending pole 9 meter 16
Rektifikasi Fiber Cut
Galian+Laying HDPE 159,366
Rektifikasi 108,000
HH 166
4 Petasia-Tentena Bridge 4,412
Pole 520
Pulling AC Cable 21,000
Pulling DC Cable 114,522
Sisa Sisa Progress
Pekerjaan Pekerjaan Jumlah MP Blocking point
Terkini
Awal Update
Material HDPE, FO Cable and skill
Man Power

2,000 1,620 380 24 Adding Man Power and special


78,642 78,319 323 0 tools for open trenching
Medan galian berbatu
55 33 17 17
20 20 0 0
38,000 29,200 8,800 24

6,800 600 6200 10 Adding Man Power


16 16 0 0
5 5 0 0
30,366 30,366 0 0 Material HDPE, FO Cable, Pole
69,000 57,470 4,408 38 include accessories and adding
Man Power
89 88 1 12
3,166 3,166 0 0
520 520 0 8
21,000 21,000 0 0
116,522 116,522 0 0
Remarks

20/7: Plan joint survey with LTI, HTI and SI at 22 July to make sure
all problem at link KDW.
22/7: Done survey OSP problem at link KDW with LEN+partner, LTI,
HTI and SI
23/7: Berdasarkan hasil meeting dan koordinasi dengan
LEN+mitranya bahwa MP baru bisa berangkat di minggu depan dan
ditargetkan pekerjaan rektifikasi akan selesai di tanggal 14 Agustus
dan juga guna mengejar percepatan pensysteman secara
temporary bisa selesai di tanggal 7 Agusutus.

20/7: Meeting with new LEN's partner, base on information akan


ada penambahan MP 21 orang dan menggunakan alat guna
percepatan.
23/7: Belum ada realisasi penambahan MP

Penambahan MP sebanyak 25 orang per 24 Juli:


- Rectifikasi ATB : 3 org
- Penanaman tiang temporary : 22 org
20/7: Loading closure 34 pcs, tiang 7 m qty 80 pcs and OTB 2 pcs
from WH Kendri to PTE
23/7: loading closuer 10 pcs, duct cable 28 haspel (112.259 m),
aerial cable 1 haspel (1.029 m). Socket 60 batang.
90 roll HDPE dan Aerial Cable 8 haspel sudah tiba di Taripa
pengiriman via Palu.
Latest Activity PIC-Supervise

-Persapan mendatangkan MP dan perisapan APD, base camp di - PIC-LEN: Ahmad/Muh. Aghi
lokasi area kerja serta sewa transportasi darat. - PIC-LTI: Aulia Permana
- PIC Huawei: Teguh

-Progress HH: - PIC-LEN: Dafid/Agung/Ahmad


HH -154 - PIC-LTI: Aulia Permana
- PIC Huawei: Teguh
-On progress rectification
201-202

- Pulling cable 1000m/6200m - PIC-LEN: Lucky/Laila Aprian


- Rectifikasi ATB 1/1 done - PIC-LTI: Ardianto
- Temporary kabel HH 87 - HH 88 - PIC Huawei: Rahman
- Rectification trenching : - PIC-LEN: Rudy/Agus/Saleh
APD BCTR 5; rectification BCTR 0,6 to BCTR 1 - PIC-LTI: Ardianto
HH 98 - HH 99 = 562m - PIC Huawei: Rahman
HH 99 - HH 100 = 390 m
-Progress HH: Pengecoran HH 129
- Pembesian & begisting All HH Link PTE
- Drop Material Split HH
135,HH 136 & HH 137 - Pembesian
Marking Post dan Backcasting
- Pengecatan tiang T7 sebanyak 150 batang