Date: 1-Aug-18
Link Petasia-Tentena
NO URAIAN PEKERJAAN Total Scope Sisa Pekerjaan Current Pending Total
Achievement
1 Galian+Laying HDPE 159,366 30,366 30,366 0
2 Rektifikasi 108,000 61,878 57,470 4408
3 HH 166 89 88 1
4 Bridge 4,412 3,166 3,166 0
5 Pole 520 520 520 0
6 Pulling AC Cable 21,000 21,000 21,000 0
7 Pulling DC Cable 141,522 116,522 116,522 0
Link Wanggudu-Bungku
NO URAIAN PEKERJAAN Total Scope Sisa Pekerjaan Current Pending Total
Achievement
1 Galian+Laying HDPE 210,302 2,000 1,620 380
2 Rektifikasi 80,000 78,642 78,319 323
3 HH 213,302 50 33 17
4 Bridge 8,500 20 20 -
5 Pulling DC Cable 218,250 38,000 29,200 8,800
Link Kendari-Wanggudu
NO URAIAN PEKERJAAN Total Scope Sisa Pekerjaan Current Pending Total
Achievement
1 Rektifikasi Fiber Cut - 6 6 0
2 Penarikan Cable (Repair) - 2,000 2,000 0
3 Perapihan Cable turun ke bawah - 8 8 0
4 Perubahan titik HH due to PU - 5 5 0
Link Bungku-Petasia
NO URAIAN PEKERJAAN Total Scope Sisa Pekerjaan Current Pending Total
Achievement
1 Change DC to AC cable - 6,800 600 6200
2 Pending pole 9 meter - 16 16 0
3 Rektifikasi Fiber Cut - 5 5 0
Prepared by AP
Wk-29
15-Jul-18 16-Jul-18 17-Jul-18 18-Jul-18 19-Jul-18
Prog. MP Prog. MP Prog. MP Prog. MP Prog. MP
0 0 0 0 0
Wk-29
15-Jul-18 16-Jul-18 17-Jul-18 18-Jul-18 19-Jul-18
Prog. MP Prog. MP Prog. MP Prog. MP Prog. MP
46 13 110 13 0 13 157 30 41 24
0 20 0 20 0 20 0 0 0 0
2 17 1 17 2 17 2 17 0 17
0 0 0 0 0 0 0 6 0 0
0 12 1000 12 700 12 300 12 2000 24
62 62 62 65 65
Wk-29
15-Jul-18 16-Jul-18 17-Jul-18 18-Jul-18 19-Jul-18
Prog. MP Prog. MP Prog. MP Prog. MP Prog. MP
0 0 0 0 0
Wk-29
15-Jul-18 16-Jul-18 17-Jul-18 18-Jul-18 19-Jul-18
Prog. MP Prog. MP Prog. MP Prog. MP Prog. MP
0 0 0 0 0 0 0 0 1500 10
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 10
Wk-30
20-Jul-18 21-Jul-18 22-Jul-18 23-Jul-18 24-Jul-18
Prog. MP Prog. MP Prog. MP Prog. MP Prog. MP
0 0 0 0 0 0 0 0 0 0
1267 38 801 38 674 38 714 38 952 38
0 12 0 12 0 12 0 12 1 12
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 8
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
50 50 50 50 58
Wk-30
20-Jul-18 21-Jul-18 22-Jul-18 23-Jul-18 24-Jul-18
Prog. MP Prog. MP Prog. MP Prog. MP Prog. MP
0 0 0 0 0 0 0 0 26 18
188 24 0 24 135 24 0 24 0 6
2 7 0 17 2 17 5 17 1 17
0 0 0 0 0 0 0 0 0 0
1300 24 500 24 1500 24 1500 24 0 24
55 65 65 65 65
Wk-30
20-Jul-18 21-Jul-18 22-Jul-18 23-Jul-18 24-Jul-18
Prog. MP Prog. MP Prog. MP Prog. MP Prog. MP
0 0 0 0 0
Wk-30
20-Jul-18 21-Jul-18 22-Jul-18 23-Jul-18 24-Jul-18
Prog. MP Prog. MP Prog. MP Prog. MP Prog. MP
700 100 800 10 1500 10 700 10 1000 10
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 22
100 10 10 10 32
Wk-30
25-Jul-18 26-Jul-18 27-Jul-18 28-Jul-18 29-Jul-18
Prog. MP Prog. MP Prog. MP Prog. MP Prog. MP
0 0 0 0 0
Wk-30
25-Jul-18 26-Jul-18 27-Jul-18 28-Jul-18 29-Jul-18
Prog. MP Prog. MP Prog. MP Prog. MP Prog. MP
0 0 0 0 0
Wk-30
25-Jul-18 26-Jul-18 27-Jul-18 28-Jul-18 29-Jul-18
Prog. MP Prog. MP Prog. MP Prog. MP Prog. MP
0 0 0 0 0
Wk-30
25-Jul-18 26-Jul-18 27-Jul-18 28-Jul-18 29-Jul-18
Prog. MP Prog. MP Prog. MP Prog. MP Prog. MP
0 0 0 0 0
Wk-31
30-Jul-18 31-Jul-18 1-Aug-18 2-Aug-18 3-Aug-18
Prog. MP Prog. MP Prog. MP Prog. MP Prog. MP
0 0 0 0 0
Wk-31
30-Jul-18 31-Jul-18 1-Aug-18 2-Aug-18 3-Aug-18
Prog. MP Prog. MP Prog. MP Prog. MP Prog. MP
0 0 0 0 0
Wk-31
30-Jul-18 31-Jul-18 1-Aug-18 2-Aug-18 3-Aug-18
Prog. MP Prog. MP Prog. MP Prog. MP Prog. MP
0 0 0 0 0
Wk-31
30-Jul-18 31-Jul-18 1-Aug-18 2-Aug-18 3-Aug-18
Prog. MP Prog. MP Prog. MP Prog. MP Prog. MP
0 0 0 0 0
4-Aug-18
Prog. MP
4-Aug-18
Prog. MP
4-Aug-18
Prog. MP
4-Aug-18
Prog. MP
0
Total
No. Segment Pending Pekerjaan Pekerjaan
20/7: Plan joint survey with LTI, HTI and SI at 22 July to make sure
all problem at link KDW.
22/7: Done survey OSP problem at link KDW with LEN+partner, LTI,
HTI and SI
23/7: Berdasarkan hasil meeting dan koordinasi dengan
LEN+mitranya bahwa MP baru bisa berangkat di minggu depan dan
ditargetkan pekerjaan rektifikasi akan selesai di tanggal 14 Agustus
dan juga guna mengejar percepatan pensysteman secara
temporary bisa selesai di tanggal 7 Agusutus.
-Persapan mendatangkan MP dan perisapan APD, base camp di - PIC-LEN: Ahmad/Muh. Aghi
lokasi area kerja serta sewa transportasi darat. - PIC-LTI: Aulia Permana
- PIC Huawei: Teguh