PAKET 2 - DESIGN & BUILD KONSTRUKSI APRON TIMUR DAN PEMINDAHAN SEWAGE TREATMENT PLANT (STP)
Penangkal petir c/W: Air terminal, Tiang support, Kabel Coaxial 50 mm2 termasuk
7 28/09/2018
grounding
PEKERJAAN SUBSTATION STP
1 Cubicle Inc/Out, GCB motorized 24 kV, 630 A, 16 kA , drawout type 09/09/2018
2 Areester 09/09/2018
PEKERJAAN ELEKTRIKAL
1 Relokasi Apron Flood Light 05/09/2018
2 Apron Flood Light 17/09/2018
3 Kabel Tegangan Menengah N2XSEFGbY 3c x 50 mm2 02/09/2018
(dari Cubicle TM Outgoing ke ADP Panel) dari SS.VVIP
4 Kabel Tegangan Rendah NYFGbY 4c x 16 mm2 (Dari ADP Panel ke AFL Panel) 03/09/2018
5 Kabel Tegangan Rendah NYY 3 x 2.5 mm2 (Dari AFL Panel ke SNL Panel) 03/09/2018
6 Spot Number Light (SNL) 29/08/2018
7 Taxiway Edge Light 04/09/2018
8 Kabel FL2XCY 1x6 mm2 3,6/6 kV sesuai existing 01/09/2018
9 Kabel Sekunder NYYHY 2 X2,5mm2 1kV 01/09/2018
10 Kabel BC 1 x 50 mm2 01/09/2018
11 Kabel BC 1 x 16 mm2 01/09/2018
12 Pemasangan Apron Flood Light Panel (AFLP) 01/09/2018
PEKERJAAN SISTEM AIR KOTOR BUANGAN
1 Pel. Pompa Air kotor 1 set = 2 unit berikut aksesoris dan 29/08/2018
Perlengkapan sehingga dapat beroperasi normal @11 KW (SUMP PIT 1)
PEKERJAAN GSE
1 Dinding Penahan Tanah 05/09/2018
2 Pemasangan Paving Block 07/09/2018