Anda di halaman 1dari 2

RENCANA PEKERJAAN SISA

PAKET 2 - DESIGN & BUILD KONSTRUKSI APRON TIMUR DAN PEMINDAHAN SEWAGE TREATMENT PLANT (STP)

KONSTRUKSI APRON TIMUR


NO. URAIAN PEKERJAAN TARGET SELESAI
1 Pekerjaan Grounding Tiang AFL 29/08/2018
2 Pekerjaan Tiang Temporary AFL 28/08/2018
3 Pemasangan Panel di AFL Baru 30/08/2018
4 Penyambungan Panel ADP ke AFL 30/08/2018
5 Pemindahan Tiang AFL Eksisting ke Lokasi Baru 05/09/2018
6 Sistem Proteksi Penangkal Petir R100 TENTATIF
7 Pekerjaan Apron Edge Light 31/08/2018
8 FAT Panel TM 30/08/2018
9 Tiang AFL Baru On Site 12/09/2018
10 Pekerjaan Tiang AFL Baru 14/09/2018
11 Instalasi Selesai AFL Baru 15/09/2018
12 Normalisasi Saluran Sebelum Penyambungan Box Culvert 28/08/2018
13 Pembersihan Apron F dan Pemindahan Jalur Service Road Temporary 28/08/2018
14 Pekerjaan Saluran Sebelah Service Road Eksisting (Apron A,B,C, dan D) 03/09/2018
15 Pekerjaan Rigid Keseluruhan 10/09/2018
16 Pekerjaan Service Road 10/09/2018
17 Perbaikan Service Road Eksisting dengan Grooting TENTATIF
PEMINDAHAN SEWAGE TREATMENT PLANT (STP)
1 Ozonizer Sistem 30/08/2018
2 UV Sistem 30/08/2018
3 Polishing Sistem 30/08/2018
4 UF Sistem DALAM KONFIRMASI
5 Panel Sistem STP 29/08/2018
6 ACB Emergency DALAM KONFIRMASI
7 Tangki Recycling 05/09/2018
8 Pintu Baja SS- STP 31/08/2018
9 Kolam Indikator 29 AGUSTUS
10 Bongkaran Pos Security STP dan Pagar BRC DALAM KONFIRMASI
11 Jalan akses STP 05/09/2018
PEKERJAAN SUMP PIT 1
1 Waterproofing sump pit 1 28/08/2018
2 Cor Pelat Dudukan Bar Screen Sump Pit 1 28/08/2018
3 Pekerjaan Cor Pelat Atap Sump Pit 2 TENTATIF
4 Pemasangan tutup Manhole Sump Pit 1, 2, 3 30/08/2018
5 Finishing pelat atap sump pit 2 29/08/2018
6 Pembongkaran Sump Pit Eksisting 31/08/2018
PEKERJAAN SUBSTATION VVIP
1 Cubicle Inc/Out, GCB motorized 24 kV, 630 A, 16 kA , drawout type interface MPH1 08/09/2018
2 Cubicle Incomingt, GCB motorized 24 kV, 630 A, 16 kA , drawout type (24 kV) 08/09/2018
3 Cubicle Outgoing, GCB motorized 24 kV, 630 A, 16 kA , drawout type (24 kV) 08/09/2018
4 Areester 08/09/2018
5 Kabel Tegangan Menengah N2XSEFGbY 3X1C x 95 mm2 dari Cubicle Feeder Kelan 10/09/2018
(Termasuk relokasi dan penyambungan feeder existing)

6 LVMDP VVIP 4 cell 09/09/2018

Penangkal petir c/W: Air terminal, Tiang support, Kabel Coaxial 50 mm2 termasuk
7 28/09/2018
grounding
PEKERJAAN SUBSTATION STP
1 Cubicle Inc/Out, GCB motorized 24 kV, 630 A, 16 kA , drawout type 09/09/2018
2 Areester 09/09/2018
PEKERJAAN ELEKTRIKAL
1 Relokasi Apron Flood Light 05/09/2018
2 Apron Flood Light 17/09/2018
3 Kabel Tegangan Menengah N2XSEFGbY 3c x 50 mm2 02/09/2018
(dari Cubicle TM Outgoing ke ADP Panel) dari SS.VVIP
4 Kabel Tegangan Rendah NYFGbY 4c x 16 mm2 (Dari ADP Panel ke AFL Panel) 03/09/2018
5 Kabel Tegangan Rendah NYY 3 x 2.5 mm2 (Dari AFL Panel ke SNL Panel) 03/09/2018
6 Spot Number Light (SNL) 29/08/2018
7 Taxiway Edge Light 04/09/2018
8 Kabel FL2XCY 1x6 mm2 3,6/6 kV sesuai existing 01/09/2018
9 Kabel Sekunder NYYHY 2 X2,5mm2 1kV 01/09/2018
10 Kabel BC 1 x 50 mm2 01/09/2018
11 Kabel BC 1 x 16 mm2 01/09/2018
12 Pemasangan Apron Flood Light Panel (AFLP) 01/09/2018
PEKERJAAN SISTEM AIR KOTOR BUANGAN
1 Pel. Pompa Air kotor 1 set = 2 unit berikut aksesoris dan 29/08/2018
Perlengkapan sehingga dapat beroperasi normal @11 KW (SUMP PIT 1)
PEKERJAAN GSE
1 Dinding Penahan Tanah 05/09/2018
2 Pemasangan Paving Block 07/09/2018

Anda mungkin juga menyukai