A PEKERJAAN PERSIAPAN
1 Pembersihan Lokasi 1.00 Ls 650,000.00
2 Pengukuran dan Pemasangan Bowplank 52.00 m2 50,000.00
3 Pembuatan Bagan Bambu 1.00 Ls 8,500,000.00
4 Mobilisasi dan Demobilisasi 1.00 Ls 7,500,000.00
Sub Jumlah A
B PEKERJAAN TANAH
1 Galian Tanah Bore Pile dia. 60 cm 110.00 m1 350,000.00
2 Galian Tanah Pondasi Telapak 20.37 m3 65,000.00
3 Bobok Kepala Bore Pile 11.00 bh 85,000.00
4 Pek. Urugan Pasir Urug 1.74 m3 190,000.00
5 Pek. Lantai Kerja Beton T = 5 cm 1.74 m3 875,000.00
Sub Jumlah B
C PEKERJAAN BETON
1 Pek. Beton Bore Pile dia. 60 cm
. Pembesian U 24 785.30 kg 15,800.00
. Pembesian U 39 2,182.75 kg 15,800.00
. Cor Beton K-350 31.09 m3 1,204,000.00
650,000.00
2,600,000.00
8,500,000.00
7,500,000.00
19,250,000.00
38,500,000.00
1,323,920.00
935,000.00
329,840.00
1,519,000.00
42,607,760.00
21,407,762.75
34,487,481.60
37,427,544.00
2,322,560.00
13,100,749.07
16,721,152.00
21,481,200.00
29,505,090.64
18,806,480.00
195,260,020.06
264,000.00
5,940,000.00
6,204,000.00
254,321,780.06