JAWABAN :

Soal 1
Tarif overhead pabrik dibebankan
Tarif BOP jam tenaga kerja langsung = taksiran biaya overhead pabrik
taksiran jam tenaga kerja
= Rp. 100.000.000
1000

= Rp. 100.000

Pencatatan Dalam Jurnal


TGL KETERANGAN

DEBET KREDIT

1. Material Account Payable Rp. 25.000.000,00 Rp. 25.000.000,00


2. Work in process-Direct material Rp. 8.840.000,00 Rp. 8.840.000,00
3. Factory Overhead-Indirect material Rp. 3.100.000,00 Rp. 3.100.000,00
4. Work In Process Factory Overhead Rp. 7.400.000,00 Rp. 2.700.000,00
Rp. 10.100.000,00
Work In Process Factory Overhead Applied
Keterangan : - job #211
17 * 100.000 = 1.700.000
-job #212
20 * 100.000 = 2.000.000 3.700.000

Rp. 3.700.000,00 Rp. 3.700.000,00


5. Actualy Factory Overhead Depreciation Of machine Building Insurance
Rp. 3.400.000,00 Rp. 1.200.000,00 Rp. 2.200.000,00

Kartu Biaya job#212


Job#212 Status : Selesai / Belum Selesai
Bahan Langsung Tenaga Kerja Langsung Overhead Pabrik(dibebankan)
Tanggal Jumlah Tanggal Jumlah Tanggal Jumlah
Rp.8.840.000 Rp.3.100.000,00 Rp. 2.000.000,00
Jumlah Rp. 8.840.000,00 Rp.3.100.000,00 Rp. 2.000.000,00