TARGET PEKERJAAN SELESAI

No. Nama Pekerjaan Mulai Selesai Keterangan

1 Pondasi Tapak 23-May 30-May

2 Sloof S1 31-May 6-Jun

3 Kolom "T" (RAM) 5-Jun 8-Jun


Kolom "I" Lantai I
4 9-Jun 26-Jun
Kolom "T" Lantai I

6 RAM Lantai 1-4 25-Jun 1-Aug

7 Plat Lantai I 25-Jun 11-Jul

8 Kolom Lantai II 11-Jul 20-Jul

9 Plat Lantai II 20-Jul 3-Aug

10 Dinding Bata Lantai I 11-Jul 18-Jul

11 Dinding Bata Lantai II 3-Aug 10-Aug

Ttd

Kamal Riza