ID TaskTask Name Duration Start Finish Predecessors

Mode Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018


Dec Jan Feb Mar Apr May
0 JADWAL RENCANA KONSTRUKSI POLRES BANDARA 365 days? Mon 01/01/18 Tue 01/01/19
1 ÙMUM 365 days Mon 01/01/18 Tue 01/01/19
2 MULAI 0 days Mon 01/01/18 Mon 01/01/18 01/01
3 Bongkaran Bangunan Exsiting 41 days Mon 01/01/18 Sun 11/02/18 2
4 Bongkaran Pagar Exsiting 14 days Mon 01/01/18 Mon 15/01/18 2 Bongkaran Pagar Exsiting
5 Pek. Pembersihan Site 35 days Mon 01/01/18 Mon 05/02/18 2 Pek. Pembersihan Site
6 Penyediaan Listrik untuk bekerja 365 days Mon 01/01/18 Tue 01/01/19 2
7 Penyediaan Air untuk bekerja 365 days Mon 01/01/18 Tue 01/01/19 2
8 Pek. Pembuatan Kantor Direksi Keet, dari bangunan semi 21 days Sun 11/02/18 Sun 04/03/18 3 Pek. Pembuatan Kantor D
permanen, dinding papan rangka kayu finish cat, lantai flooraci,
plafond multipleks dicat, atap asbes gelombang, dilengkapi fasilitas
Ac Split, perlengkapan kerja dan Toilet.

9 Pek. Pembuatan Kantor Pemborong, dari bangunan konstruksi 21 days Sun 11/02/18 Sun 04/03/18 3 Pek. Pembuatan Kantor P
kayu, dinding tripleks rangka kayu finish cat, lantai floor aci, plafond
trpleks dicat, atap asbes gelombang, dilengkapi perlengkapan kerja
dan Toilet.

10 Tugu Patok dasar (kolom beton 20/20) 7 days Mon 05/02/18 Mon 12/02/18 5 Tugu Patok dasar (kolom beto
11 Papan Nama Proyek 1 day Mon 01/01/18 Tue 02/01/18 2 Papan Nama Proyek
12 Pembuatan pagar proyek sementara (seng glmbg rgk. Kayu) 7 days Mon 05/02/18 Mon 12/02/18 5 Pembuatan pagar proyek sem
13 Pas. Papan patok ukur (bouwplank) 7 days Mon 05/02/18 Mon 12/02/18 5 Pas. Papan patok ukur (bouwp
14 Biaya Mobilisasi / Demobilisasi Alat berat 365 days Mon 01/01/18 Tue 01/01/19 2
15 PEKERJAAN STRUKTUR : 207 days Thu 08/02/18 Mon 03/09/18

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 1
ID TaskTask Name Duration Start Finish Predecessors
Mode Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Dec Jan Feb Mar Apr May
16 PEKERJAAN PONDASI : 51 days Thu 08/02/18 Sat 31/03/18
17 Pekerjaan Struktur Bawah: 51 days Thu 08/02/18 Sat 31/03/18
18 Mobilisasi (alat pancang) 7 days Thu 08/02/18 Thu 15/02/18 3FS-3 days
19 Demobilisasi (alat pancang) 7 days Sat 17/03/18 Sat 24/03/18 22 Demobilisasi (alat pan
20 Mobilisasi (alat loading test) 7 days Sat 10/03/18 Sat 17/03/18 22FS-7 days Mobilisasi (alat loading
21 Demobilisasi (alat loading test) 7 days Sat 24/03/18 Sat 31/03/18 24;25 Demobilisasi (alat lo
22 Pondasi Tiang Pancang 30 days Thu 15/02/18 Sat 17/03/18 18
23 Pengadaan & Penyambungan 30 days Fri 16/02/18 Sun 18/03/18 22SS+1 day Pengadaan & Penyamb
24 Pengujian Beban - PDA Test 1 day Sat 17/03/18 Sun 18/03/18 20 Pengujian Beban - PDA
25 Pekerjaan Pile Cap 14 days Sat 10/03/18 Sat 24/03/18 22FS-7 days
26 Pekerjaan Kolom Pedestal 7 days Sat 17/03/18 Sat 24/03/18 25FS-7 days
27 PEKERJAAN LANTAI DASAR : 79 days Sat 17/03/18 Mon 04/06/18
28 Pekerjaan Tie Beam 21 days Sat 17/03/18 Sat 07/04/18 26FS-7 days
29 Pekerjaan Pelat Lantai 21 days Mon 19/03/18 Mon 09/04/18 28SS+2 days
30 Pekerjaan Kolom 14 days Mon 09/04/18 Mon 23/04/18 29
31 Pekerjaan Tangga 14 days Mon 21/05/18 Mon 04/06/18 34
32 PEKERJAAN LANTAI DUA : 63 days Mon 16/04/18 Mon 18/06/18
33 Pekerjaan Balok 21 days Mon 16/04/18 Mon 07/05/18 30FS-7 days
34 Pekerjaan Pelat Lantai 21 days Mon 30/04/18 Mon 21/05/18 33FS-7 days
35 Pekerjaan Kolom 14 days Mon 21/05/18 Mon 04/06/18 34
36 Pekerjaan Tangga 14 days Mon 04/06/18 Mon 18/06/18 31
37 PEKERJAAN LANTAI TIGA : 35 days Mon 28/05/18 Mon 02/07/18
Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 2
ID TaskTask Name Duration Start Finish Predecessors
Mode Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Dec Jan Feb Mar Apr May
38 Pekerjaan Balok 21 days Mon 28/05/18 Mon 18/06/18 35FS-7 days
39 Pekerjaan Pelat Lantai 21 days Mon 28/05/18 Mon 18/06/18 35FS-7 days
40 Pekerjaan Kolom 14 days Mon 18/06/18 Mon 02/07/18 39
41 Pekerjaan Tangga 14 days Mon 18/06/18 Mon 02/07/18 36
42 PEKERJAAN LANTAI EMPAT : 35 days Mon 25/06/18 Mon 30/07/18
43 Pekerjaan Balok 21 days Mon 25/06/18 Mon 16/07/18 40FS-7 days
44 Pekerjaan Pelat Lantai 21 days Mon 25/06/18 Mon 16/07/18 40FS-7 days
45 Pekerjaan Kolom 14 days Mon 16/07/18 Mon 30/07/18 44
46 Pekerjaan Tangga 14 days Mon 02/07/18 Mon 16/07/18 41
47 PEKERJAAN LANTAI LIMA : 35 days Mon 09/07/18 Mon 13/08/18
48 Pekerjaan Balok 21 days Mon 09/07/18 Mon 30/07/18 44FS-7 days
49 Pekerjaan Pelat Lantai 21 days Mon 09/07/18 Mon 30/07/18 44FS-7 days
50 Pekerjaan Kolom 14 days Mon 30/07/18 Mon 13/08/18 49
51 Pekerjaan Tangga 14 days Mon 16/07/18 Mon 30/07/18 46
52 PEKERJAAN LANTAI ATAP : 26 days Mon 06/08/18 Sat 01/09/18
53 Pekerjaan Balok 14 days Mon 06/08/18 Mon 20/08/18 50FS-7 days
54 Pekerjaan Pelat Lantai 14 days Mon 06/08/18 Mon 20/08/18 50FS-7 days
55 Pekerjaan Balok Dak Atap Tangga 7 days Sat 25/08/18 Sat 01/09/18 57FS-2 days
56 Pekerjaan Dak Atap Tangga 7 days Sat 25/08/18 Sat 01/09/18 57FS-2 days
57 Pekerjaan Kolom 7 days Mon 20/08/18 Mon 27/08/18 54
58 Pekerjaan Waterproofing Integral 7 days Mon 20/08/18 Mon 27/08/18 54
59 PEKERJAAN RUANG POS JAGA 21 days Mon 12/02/18 Mon 05/03/18 13 PEKERJAAN RUANG POS

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 3
ID TaskTask Name Duration Start Finish Predecessors
Mode Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Dec Jan Feb Mar Apr May
60 PEKERJAAN BANGUNAN RUMAH POMPA, PANEL & GENSET 28 days Mon 12/02/18 Mon 12/03/18 13 PEKERJAAN BANGUNAN
61 PEKERJAAN PAGAR 14 days Mon 12/02/18 Mon 26/02/18 13 PEKERJAAN PAGAR
62 PEKERJAAN PERKERASAN 14 days Mon 20/08/18 Mon 03/09/18 54
63 PEKERJAAN SALURAN 14 days Mon 20/08/18 Mon 03/09/18 54
64 PEKERJAAN ARSITEKTUR 174 days Mon 28/05/18 Sun 18/11/18
65 PEKERJAAN LANTAI DASAR 86 days Mon 28/05/18 Wed 22/08/18

72 PEKERJAAN LANTAI DUA : 83 days Mon 18/06/18 Sun 09/09/18

79 PEKERJAAN LANTAI TIGA : 97 days Mon 02/07/18 Sun 07/10/18


80 Pekerjaan Dinding 30 days Mon 23/07/18 Wed 22/08/18 44FS+7 days

81 Pekerjaan Lantai 30 days Wed 15/08/18 Fri 14/09/18 80FS-7 days

82 Pekerjaan Plafond 30 days Fri 07/09/18 Sun 07/10/18 81FS-7 days

83 Pekerjaan Kosen, Pintu, Jendela dan Partisi 21 days Fri 07/09/18 Fri 28/09/18 81FS-7 days

84 Pekerjaan Tangga 7 days Mon 02/07/18 Mon 09/07/18 41

85 Pekerjaan Sanitari & Fitting 7 days Fri 07/09/18 Fri 14/09/18 81FS-7 days

86 PEKERJAAN LANTAI EMPAT 97 days Mon 16/07/18 Sun 21/10/18

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 4
ID TaskTask Name Duration Start Finish Predecessors
Mode Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Dec Jan Feb Mar Apr May
93 PEKERJAAN LANTAI LIMA : 104 days Mon 30/07/18 Sun 11/11/18
100 PEKERJAAN LANTAI ATAP 90 days Mon 20/08/18 Sun 18/11/18

101 Pekerjaan Dinding 30 days Mon 20/08/18 Wed 19/09/18 54

102 Pekerjaan Lantai 30 days Wed 19/09/18 Fri 19/10/18 101

103 Pekerjaan Plafond 30 days Fri 19/10/18 Sun 18/11/18 102

104 Pekerjaan Kosen, Pintu, Jendela dan Partisi 21 days Wed 19/09/18 Wed 10/10/18 101

105 Pekerajaan Waterproofing Atap Beton 7 days Fri 19/10/18 Fri 26/10/18 102

106 PEKERJAAN BANGUNAN POS JAGA (ENTRY) 30 days Sun 07/10/18 Tue 06/11/18 79

107 PEKERJAAN BANGUNAN RUMAH POMPA, PANEL & GENSET 30 days Sun 07/10/18 Tue 06/11/18 79

108 PEKERJAAN EXTERIOR / LANDSCAPE 30 days Sun 07/10/18 Tue 06/11/18 79

109 PEKERJAAN PAGAR 30 days Sun 07/10/18 Tue 06/11/18 79

110 MEP 365 days? Mon 01/01/18 Tue 01/01/19


111 Pekerjaan Listrik Arus Kuat 218 days Mon 28/05/18 Tue 01/01/19
112 Pekerjaan Tegangan Menengah dan Penyambungan PLN 21 days Mon 03/12/18 Mon 24/12/18
Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 5
ID TaskTask Name Duration Start Finish Predecessors
Mode Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Dec Jan Feb Mar Apr May
113 Pengadaan dan Pemasangan PDTM 21 days Mon 03/12/18 Mon 24/12/18 117FS-15
days
114 Pengadaan dan Pemasangan Transformator & PDTR 21 days Mon 03/12/18 Mon 24/12/18 113SS

115 Instalsi Pengkabelan 21 days Mon 03/12/18 Mon 24/12/18 113SS

116 Pekerjaan Panel-panel 21 days Tue 04/12/18 Tue 25/12/18 113FS-20


days
117 Pekerjaan Kabel-Kabel Utama 84 days Tue 25/09/18 Tue 18/12/18 139FS-29
days
118 Pekerjaan Kabel Ladder dan Kabel Tray ( Arus Kuat & Arus 105 days Mon 28/05/18 Mon 10/09/18
Lemah )
119 Lantai 1 21 days Mon 28/05/18 Mon 18/06/18 34FS+7 days

120 Lantai 2 21 days Mon 25/06/18 Mon 16/07/18 39FS+7 days

121 Lantai 3 21 days Mon 23/07/18 Mon 13/08/18 44FS+7 days

122 Lantai 4 21 days Mon 06/08/18 Mon 27/08/18 49FS+7 days

123 Lantai 5 14 days Mon 27/08/18 Mon 10/09/18 54FS+7 days


124 Pekerjaan Lampu / Titik Nyala / Stop Kontak 158 days Wed 27/06/18 Sun 02/12/18
125 Lantai 1 88 days Wed 27/06/18 Sun 23/09/18

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 6
ID TaskTask Name Duration Start Finish Predecessors
Mode Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Dec Jan Feb Mar Apr May
126 Lampu, Saklar dan Stop Kontak 14 days Sun 09/09/18 Sun 23/09/18 75

127 Instalasi Lampu, Saklar dan Stop Kontak 28 days Wed 27/06/18 Wed 25/07/18 66

128 Lantai 2 88 days Wed 25/07/18 Sun 21/10/18

129 Lampu, Saklar dan Stop Kontak 14 days Sun 07/10/18 Sun 21/10/18 82

130 Instalasi Lampu, Saklar dan Stop Kontak 28 days Wed 25/07/18 Wed 22/08/18 73

131 Lantai 3 74 days Wed 22/08/18 Sun 04/11/18

132 Lampu, Saklar dan Stop Kontak 14 days Sun 21/10/18 Sun 04/11/18 89

133 Instalasi Lampu, Saklar dan Stop Kontak 28 days Wed 22/08/18 Wed 19/09/18 80

134 Lantai 4 81 days Wed 05/09/18 Sun 25/11/18

135 Lampu, Saklar dan Stop Kontak 14 days Sun 11/11/18 Sun 25/11/18 96

136 Instalasi Lampu, Saklar dan Stop Kontak 28 days Wed 05/09/18 Wed 03/10/18 87

137 Lantai 5 67 days Wed 26/09/18 Sun 02/12/18

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 7
ID TaskTask Name Duration Start Finish Predecessors
Mode Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Dec Jan Feb Mar Apr May
138 Lampu, Saklar dan Stop Kontak 14 days Sun 18/11/18 Sun 02/12/18 103

139 Instalasi Lampu, Saklar dan Stop Kontak 28 days Wed 26/09/18 Wed 24/10/18 94

140 Bangunan Utilitas dan Pos Jaga 21 days Tue 06/11/18 Tue 27/11/18
143 Taman / Site 49 days Sun 14/10/18 Sun 02/12/18
147 Pekerjaan Instalasi Penangkal Petir 14 days Tue 04/12/18 Tue 18/12/18 117FS-14
days
148 Testing & Commissioning 7 days Tue 25/12/18 Tue 01/01/19 152;161;170;179;187;197;206;215;243;247;259;276;116;113

149 Pekerjaan Diesel Generator Set 35 days Tue 06/11/18 Tue 11/12/18
150 Diesel Generator Set & Panel Kontrol Genset 21 days Tue 06/11/18 Tue 27/11/18 107

151 Instalasi dan Peralatan Penunjang 28 days Tue 06/11/18 Tue 04/12/18 107

152 Testing & Commissioning 7 days Tue 04/12/18 Tue 11/12/18 150;151

153 Pekerjaan Fire Alarm 197 days Mon 28/05/18 Tue 11/12/18
154 Peralatan Utama Dan Kabel Utama 21 days Mon 30/07/18 Mon 20/08/18 67

155 Pekerjaan Instalasi Fire Alarm dalam Bangunan 197 days Mon 28/05/18 Tue 11/12/18

156 Lantai 1 21 days Mon 28/05/18 Mon 18/06/18 34FS+7 days

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 8
ID TaskTask Name Duration Start Finish Predecessors
Mode Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Dec Jan Feb Mar Apr May
157 Lantai 2 21 days Mon 25/06/18 Mon 16/07/18 39FS+7 days

158 Lantai 3 21 days Mon 23/07/18 Mon 13/08/18 44FS+7 days

159 Lantai 4 21 days Mon 06/08/18 Mon 27/08/18 49FS+7 days

160 Lantai 5 21 days Mon 27/08/18 Mon 17/09/18 54FS+7 days


161 Bangunan Utilitas 21 days Tue 06/11/18 Tue 27/11/18 107

162 Testing & Commissioning 14 days Tue 27/11/18 Tue 11/12/18 161;160

163 Pekerjaan Sound System ( Peralatan Utama ) 204 days Mon 28/05/18 Tue 18/12/18
164 Pekerjaan Instalasi Sound System Pada Bangunan 204 days Mon 28/05/18 Tue 18/12/18

165 Lantai 1 21 days Mon 28/05/18 Mon 18/06/18 34FS+7 days

166 Lantai 2 21 days Mon 25/06/18 Mon 16/07/18 39FS+7 days

167 Lantai 3 21 days Mon 23/07/18 Mon 13/08/18 44FS+7 days

168 Lantai 4 21 days Mon 06/08/18 Mon 27/08/18 49FS+7 days

169 Lantai 5 21 days Mon 27/08/18 Mon 17/09/18 54FS+7 days

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 9
ID TaskTask Name Duration Start Finish Predecessors
Mode Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Dec Jan Feb Mar Apr May
170 Bangunan Utilitas, Parkir dan Halaman 21 days Tue 06/11/18 Tue 27/11/18 107

171 Testing & Commissioning 21 days Tue 27/11/18 Tue 18/12/18 170;169

172 Pekerjaan Telepon ( Peralatan Utama ) 204 days Mon 28/05/18 Tue 18/12/18
173 Pekerjaan Instalasi Telepon dalam Bangunan 204 days Mon 28/05/18 Tue 18/12/18

174 Lantai 1 21 days Mon 28/05/18 Mon 18/06/18 34FS+7 days

175 Lantai 2 21 days Mon 25/06/18 Mon 16/07/18 39FS+7 days

176 Lantai 3 21 days Mon 23/07/18 Mon 13/08/18 44FS+7 days

177 Lantai 4 21 days Mon 06/08/18 Mon 27/08/18 49FS+7 days

178 Lantai 5 21 days Mon 27/08/18 Mon 17/09/18 54FS+7 days


179 Bangunan Utilitas 21 days Tue 06/11/18 Tue 27/11/18 107

180 Testing & Commissioning 21 days Tue 27/11/18 Tue 18/12/18 179;178

181 Pekerjaan MATV ( Peralatan Utama ) 126 days Mon 28/05/18 Mon 01/10/18
182 Pekerjaan Instalasi MATV dalam bangunan 126 days Mon 28/05/18 Mon 01/10/18

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 10
ID TaskTask Name Duration Start Finish Predecessors
Mode Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Dec Jan Feb Mar Apr May
183 Lantai 1 21 days Mon 28/05/18 Mon 18/06/18 34FS+7 days

184 Lantai 2 21 days Mon 25/06/18 Mon 16/07/18 39FS+7 days

185 Lantai 3 21 days Mon 23/07/18 Mon 13/08/18 44FS+7 days

186 Lantai 4 21 days Mon 06/08/18 Mon 27/08/18 49FS+7 days

187 Lantai 5 21 days Mon 27/08/18 Mon 17/09/18 54FS+7 days


188 Testing & Commissioning 14 days Mon 17/09/18 Mon 01/10/18 187

189 Pekerjaan CCTV & Acces Control ( Peralatan Utama ) 351 days Mon 01/01/18 Tue 18/12/18
190 Pekerjaan Instalasi CCTV & Acces Control pada Bangunan 1 day Mon 01/01/18 Tue 02/01/18 Pekerjaan Instalasi CCTV & Acces Cont

191 Lantai 1 28 days Mon 28/05/18 Mon 25/06/18 34FS+7 days

192 Lantai 2 28 days Mon 25/06/18 Mon 23/07/18 39FS+7 days

193 Lantai 3 28 days Mon 23/07/18 Mon 20/08/18 44FS+7 days

194 Lantai 4 28 days Mon 06/08/18 Mon 03/09/18 49FS+7 days

195 Lantai 5 28 days Mon 27/08/18 Mon 24/09/18 54FS+7 days

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 11
ID TaskTask Name Duration Start Finish Predecessors
Mode Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Dec Jan Feb Mar Apr May
196 Bangunan Utilitas 28 days Tue 06/11/18 Tue 04/12/18 107

197 Parkir dan Halaman 28 days Tue 06/11/18 Tue 04/12/18 108

198 Testing & Commissioning 14 days Tue 04/12/18 Tue 18/12/18 195;196;197

199 Pekerjaan Data ( Peralatan Utama ) 204 days Mon 28/05/18 Tue 18/12/18
200 Pekerjaan Jaringan Instalasi Data 204 days Mon 28/05/18 Tue 18/12/18

201 Lantai 1 28 days Mon 28/05/18 Mon 25/06/18 34FS+7 days

202 Lantai 2 28 days Mon 25/06/18 Mon 23/07/18 39FS+7 days

203 Lantai 3 28 days Mon 23/07/18 Mon 20/08/18 44FS+7 days

204 Lantai 4 28 days Mon 06/08/18 Mon 03/09/18 49FS+7 days

205 Lantai 5 28 days Mon 27/08/18 Mon 24/09/18 54FS+7 days


206 Bangunan Utilitas 28 days Tue 06/11/18 Tue 04/12/18 107

207 Testing and Commissioning 14 days Tue 04/12/18 Tue 18/12/18 205;206

208 Pekerjaan BAS ( Peralatan Utama ) 204 days Mon 28/05/18 Tue 18/12/18

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 12
ID TaskTask Name Duration Start Finish Predecessors
Mode Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Dec Jan Feb Mar Apr May
209 Pekerjaan Instalasi BAS 204 days Mon 28/05/18 Tue 18/12/18

210 Lantai 1 28 days Mon 28/05/18 Mon 25/06/18 34FS+7 days

211 Lantai 2 28 days Mon 25/06/18 Mon 23/07/18 39FS+7 days

212 Lantai 3 28 days Mon 23/07/18 Mon 20/08/18 44FS+7 days

213 Lantai 4 28 days Mon 06/08/18 Mon 03/09/18 49FS+7 days

214 Lantai 5 28 days Mon 27/08/18 Mon 24/09/18 54FS+7 days


215 Bangunan Utilitas 28 days Tue 06/11/18 Tue 04/12/18 107

216 Testing and Commissioning 14 days Tue 04/12/18 Tue 18/12/18 214;215

217 PEKERJAAN PLUMBING 206 days? Mon 28/05/18 Thu 20/12/18


218 Air Bersih 176 days Mon 28/05/18 Tue 20/11/18
219 Peralatan Utama ( pompa & filter ) 14 days Tue 06/11/18 Tue 20/11/18 107

220 Pemipaan Utama dan Katub-Katub 21 days Mon 28/05/18 Mon 18/06/18 34FS+7 days

221 Pekerjaan instalasi pipa air bersih dalam bangunan 119 days Mon 28/05/18 Mon 24/09/18
222 Lantai 1 28 days Mon 28/05/18 Mon 25/06/18 34FS+7 days

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 13
ID TaskTask Name Duration Start Finish Predecessors
Mode Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Dec Jan Feb Mar Apr May
223 Lantai 2 28 days Mon 25/06/18 Mon 23/07/18 39FS+7 days

224 Lantai 3 28 days Mon 23/07/18 Mon 20/08/18 44FS+7 days

225 Lantai 4 28 days Mon 06/08/18 Mon 03/09/18 49FS+7 days

226 Lantai 5 28 days Mon 27/08/18 Mon 24/09/18 54FS+7 days


227 Air Kotor, Bekas dan Vent 28 days Mon 28/05/18 Mon 25/06/18
228 Peralatan Utama STP 28 days Mon 28/05/18 Mon 25/06/18 34FS+7 days

229 Pekerjaan Instalasi Pipa Air Bekas, Kotor & Vent dalam 119 days Mon 28/05/18 Mon 24/09/18
bangunan
230 Lantai 1 28 days Mon 28/05/18 Mon 25/06/18 34FS+7 days

231 Lantai 2 28 days Mon 25/06/18 Mon 23/07/18 39FS+7 days

232 Lantai 3 28 days Mon 23/07/18 Mon 20/08/18 44FS+7 days

233 Lantai 4 28 days Mon 06/08/18 Mon 03/09/18 49FS+7 days

234 Lantai 5 28 days Mon 27/08/18 Mon 24/09/18 54FS+7 days


235 Air Siram Taman 28 days Tue 06/11/18 Tue 04/12/18
236 Distribution Pump 14 days Tue 06/11/18 Tue 20/11/18 108

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 14
ID TaskTask Name Duration Start Finish Predecessors
Mode Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Dec Jan Feb Mar Apr May
237 Instalasi Siram Taman 28 days Tue 06/11/18 Tue 04/12/18 108

238 Katub - katub dan kelengkapannya : 14 days Tue 06/11/18 Tue 20/11/18 108

239 Instalasi Saluran dan Air Hujan 165 days Mon 28/05/18 Fri 09/11/18
240 Roof Drain : 14 days Fri 26/10/18 Fri 09/11/18 105;241

241 Instalasi Pemipaan Air Hujan 49 days Mon 28/05/18 Mon 16/07/18 34FS+7 days

242 Pekerjaan Elektrikal Plumbing 21 days Tue 20/11/18 Tue 11/12/18


243 Panel - Panel 14 days Tue 20/11/18 Tue 04/12/18 221;219

244 Pekerjaan Testing & Commissioning 7 days Tue 04/12/18 Tue 11/12/18 243

245 Pekerjaan Sumur Dalam 139 days Mon 28/05/18 Sun 14/10/18
246 Pompa Deep Well 7 days Sun 07/10/18 Sun 14/10/18 108SS

247 Intalasi Pipa dan Pengkabelan Listrik & Kontrol 21 days Mon 28/05/18 Mon 18/06/18 34FS+7 days

248 Testing Commissioning 7 days Mon 25/06/18 247


Mon 18/06/18
249 Pekerjaan Fire Hydrant, Fire Sprinkler dan Extinguisher 206 days? Mon 28/05/18 Thu 20/12/18
250
251 Peralatan Utama 28 days Mon 28/05/18 Mon 25/06/18 34FS+7 days

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 15
ID TaskTask Name Duration Start Finish Predecessors
Mode Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Dec Jan Feb Mar Apr May
252 Site Plan 60 days Sun 07/10/18 Thu 06/12/18 108SS
253 Instalasi Fire Hydrant & Sprinkler dalam Bangunan 119 days Mon 28/05/18 Mon 24/09/18
254 Lantai 1 28 days Mon 28/05/18 Mon 25/06/18 34FS+7 days
255 Lantai 2 28 days Mon 25/06/18 Mon 23/07/18 39FS+7 days
256 Lantai 3 28 days Mon 23/07/18 Mon 20/08/18 44FS+7 days
257 Lantai 4 28 days Mon 06/08/18 Mon 03/09/18 49FS+7 days
258 Lantai 5 28 days Mon 27/08/18 Mon 24/09/18 54FS+7 days
259 Fire Extinguisher 21 days Mon 24/09/18 Mon 15/10/18 258
260 Testing & Commissioning 14 days Thu 06/12/18 Thu 20/12/18 259;258;252;251
261 Pekerjaan Tata Udara 200 days Mon 28/05/18 Fri 14/12/18
262 Peralatan Utama AC FAN 200 days Mon 28/05/18 Fri 14/12/18
263 Lantai 1 21 days Mon 28/05/18 Mon 18/06/18 34FS+7 days
264 Lantai 2 21 days Mon 25/06/18 Mon 16/07/18 39FS+7 days
265 Lantai 3 21 days Mon 06/08/18 Mon 27/08/18 44FS+7 days;49FS+7 days
266 Lantai 4 21 days Mon 06/08/18 Mon 27/08/18 49FS+7 days
267 Lantai 5 21 days Mon 27/08/18 Mon 17/09/18 54FS+7 days
268 Bangunan Utilitas 14 days Tue 06/11/18 Tue 20/11/18 107
269 Testing & Commissioning 14 days Fri 30/11/18 Fri 14/12/18 277
270 Pekerjaan Instalasi Pemipaan dan Drain 183 days Mon 28/05/18 Tue 27/11/18

271 lantai 1 21 days Mon 28/05/18 Mon 18/06/18 34FS+7 days


272 Lantai 2 21 days Mon 25/06/18 Mon 16/07/18 39FS+7 days

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 16
ID TaskTask Name Duration Start Finish Predecessors
Mode Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Dec Jan Feb Mar Apr May
273 Lantai 3 21 days Mon 06/08/18 Mon 27/08/18 44FS+7 days;49FS+7 days
274 Lantai 4 21 days Mon 06/08/18 Mon 27/08/18 49FS+7 days
275 Lantai 5 21 days Mon 27/08/18 Mon 17/09/18 54FS+7 days
276 Bangunan Utilitas 21 days Tue 06/11/18 Tue 27/11/18 107
277 Pekerjaan Pemasangan Grille dan Diffuser 10 days Tue 20/11/18 Fri 30/11/18 267;268

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 17
Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul

ihan Site

mbuatan Kantor Direksi Keet, dari bangunan semi permanen, dinding papan rangka kayu finish cat, lantai flooraci, plafond multipleks dicat, atap asbes gelombang, dilengkapi fasilit

mbuatan Kantor Pemborong, dari bangunan konstruksi kayu, dinding tripleks rangka kayu finish cat, lantai floor aci, plafond trpleks dicat, atap asbes gelombang, dilengkapi perleng

dasar (kolom beton 20/20)

pagar proyek sementara (seng glmbg rgk. Kayu)


patok ukur (bouwplank)

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 18
Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul

mobilisasi (alat pancang)


lisasi (alat loading test)
emobilisasi (alat loading test)

adaan & Penyambungan


ujian Beban - PDA Test

Pekerjaan Tangga

Pekerjaan Tangga

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 19
Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
Pekerjaan Balok

Pekerjaan Tangga

Pekerjaan Balok

Pekerjaan Kolom
Pekerjaan Tangga

Pekerjaan Balok

Pekerjaan Tangga

Pekerjaan Balok

Pekerjaan Balok Dak Atap Tangga


Pekerjaan Dak Atap Tangga
Pekerjaan Kolom
Pekerjaan Waterproofing Integral
AAN RUANG POS JAGA

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 20
Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
JAAN BANGUNAN RUMAH POMPA, PANEL & GENSET
AN PAGAR
PEKERJAAN PERKERASAN
PEKERJAAN SALURAN

Pekerjaan Dinding

Pekerjaan Lantai

Pekerjaan Plafond

Pekerjaan Kosen, Pintu, Jendela dan Partisi

Pekerjaan Tangga

Pekerjaan Sanitari & Fitting

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 21
Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul

Pekerjaan Dinding

Pekerjaan Lantai

Pekerjaan Plafond

Pekerjaan Kosen, Pintu, Jendela dan Partisi

Pekerajaan Waterproofing Atap Beton

PEKERJAAN BANGUNAN POS JAGA (ENTRY)

PEKERJAAN BANGUNAN RUMAH POMPA, PANEL & GENSET

PEKERJAAN EXTERIOR / LANDSCAPE

PEKERJAAN PAGAR

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 22
Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul

Pengadaan dan Pemasangan Transformator & PDTR

Instalsi Pengkabelan

Lantai 1

Lantai 2

Lantai 3

Lantai 4

Lantai 5

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 23
Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
Lampu, Saklar dan Stop Kontak

Instalasi Lampu, Saklar dan Stop Kontak

Lampu, Saklar dan Stop Kontak

Instalasi Lampu, Saklar dan Stop Kontak

Lampu, Saklar dan Stop Kontak

Instalasi Lampu, Saklar dan Stop Kontak

Lampu, Saklar dan Stop Kontak

Instalasi Lampu, Saklar dan Stop Kontak

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 24
Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
Lampu, Saklar dan Stop Kontak

Pekerjaan Instalasi Penangkal Petir

Diesel Generator Set & Panel Kontrol Genset

Instalasi dan Peralatan Penunjang

Testing & Commissioning

Peralatan Utama Dan Kabel Utama

Lantai 1

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 25
Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
Lantai 2

Lantai 3

Lantai 4

Lantai 5
Bangunan Utilitas

Testing & Commissioning

Lantai 1

Lantai 2

Lantai 3

Lantai 4

Lantai 5

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 26
Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
Bangunan Utilitas, Parkir dan Halaman

Testing & Commissioning

Lantai 1

Lantai 2

Lantai 3

Lantai 4

Lantai 5
Bangunan Utilitas

Testing & Commissioning

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 27
Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
Lantai 1

Lantai 2

Lantai 3

Lantai 4

Lantai 5
Testing & Commissioning

CTV & Acces Control pada Bangunan

Lantai 1

Lantai 2

Lantai 3

Lantai 4

Lantai 5

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 28
Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
Bangunan Utilitas

Parkir dan Halaman

Testing & Commissioning

Lantai 1

Lantai 2

Lantai 3

Lantai 4

Lantai 5
Bangunan Utilitas

Testing and Commissioning

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 29
Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul

Lantai 1

Lantai 2

Lantai 3

Lantai 4

Lantai 5
Bangunan Utilitas

Testing and Commissioning

Peralatan Utama ( pompa & filter )

Pemipaan Utama dan Katub-Katub

Lantai 1

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 30
Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
Lantai 2

Lantai 3

Lantai 4

Lantai 5

Peralatan Utama STP

Lantai 1

Lantai 2

Lantai 3

Lantai 4

Lantai 5

Distribution Pump

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 31
Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
Instalasi Siram Taman

Katub - katub dan kelengkapannya :

Roof Drain :

Instalasi Pemipaan Air Hujan

Panel - Panel

Pekerjaan Testing & Commissioning

Pompa Deep Well

Intalasi Pipa dan Pengkabelan Listrik & Kontrol

Testing Commissioning

Peralatan Utama

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 32
Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
Site Plan

Lantai 1
Lantai 2
Lantai 3
Lantai 4
Lantai 5
Fire Extinguisher
Testing & Commissioning

Lantai 1
Lantai 2
Lantai 3
Lantai 4
Lantai 5
Bangunan Utilitas
Testing & Commissioning

lantai 1
Lantai 2

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 33
Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
Lantai 3
Lantai 4
Lantai 5
Bangunan Utilitas
Pekerjaan Pemasangan Grille dan Diffuser

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 34
Qtr 3, 2020 Qtr 4, 2020 Qtr 1, 2021 Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 35
Qtr 3, 2020 Qtr 4, 2020 Qtr 1, 2021 Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 36
Qtr 3, 2020 Qtr 4, 2020 Qtr 1, 2021 Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 37
Qtr 3, 2020 Qtr 4, 2020 Qtr 1, 2021 Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 38
Qtr 3, 2020 Qtr 4, 2020 Qtr 1, 2021 Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 39
Qtr 3, 2020 Qtr 4, 2020 Qtr 1, 2021 Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 40
Qtr 3, 2020 Qtr 4, 2020 Qtr 1, 2021 Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 41
Qtr 3, 2020 Qtr 4, 2020 Qtr 1, 2021 Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 42
Qtr 3, 2020 Qtr 4, 2020 Qtr 1, 2021 Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 43
Qtr 3, 2020 Qtr 4, 2020 Qtr 1, 2021 Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 44
Qtr 3, 2020 Qtr 4, 2020 Qtr 1, 2021 Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 45
Qtr 3, 2020 Qtr 4, 2020 Qtr 1, 2021 Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 46
Qtr 3, 2020 Qtr 4, 2020 Qtr 1, 2021 Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 47
Qtr 3, 2020 Qtr 4, 2020 Qtr 1, 2021 Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 48
Qtr 3, 2020 Qtr 4, 2020 Qtr 1, 2021 Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 49
Qtr 3, 2020 Qtr 4, 2020 Qtr 1, 2021 Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 50
Qtr 3, 2020 Qtr 4, 2020 Qtr 1, 2021 Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 51
Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 52
Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 53
Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 54
Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 55
Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 56
Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 57
Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 58
Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 59
Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 60
Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 61
Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 62
Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 63
Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 64
Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 65
Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 66
Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 67
Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: JADWAL RENCANA KO
Summary Manual Summary Rollup Critical
Date: Wed 25/07/18
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 68