KODE
NO URAIAN VOL. SAT HARGA SATUAN JUMLAH HARGA
ANALISA
I PEKERJAAN PERSIAPAN
1 Uitzet & Pembuatan Bouwplank 258 M' SNI 03 Rp 17,500 Rp 4,515,000
Sub-01 Rp 4,515,000
II PEKERJAAN TANAH
1 Galian Tanah Pondasi 258 m3 T.07 Rp - Rp -
2 Pemadatan Tanah 309.6 m2 Ls Rp 65,000 Rp 20,124,000
3 Timbunan Kembali (0,25* Galian) 100.3 m3 T.14.c Rp 13,474 Rp 1,351,452
Sub-02 Rp 21,475,452
7 Balok Praktis
Begisting 51.6 m2 B.21 Rp 14,750 Rp 761,100
Pembesian
Tul. Utama D.10 mm 611.46 Kg B.17.a Rp 20,500 Rp 12,534,930
Beugel/Ring Ø 6mm (Space 150mm)
Cor Beton K225 (Site Mix) 7.74 m3 B.07 Rp 975,000 Rp 7,546,500
8 Balok Ring 15x25 cm
Begisting 64.5 m2 B.21 Rp 14,750 Rp 951,375
Pembesian
Tul. Utama D.10 mm 965.952 Kg B.17.a Rp 20,500 Rp 19,802,016
Beugel/Ring Ø 6mm (Space 150mm)
Cor Beton K225 (Site Mix) 9.675 m3 B.07 Rp 975,000 Rp 9,433,125
V PEKERJAAN ARSITEKTUR
5a PEKERJAAN PASANGAN
1 Pekerjaan Pasangan Bata 670.8 M2 D.4 Rp 144,115 Rp 96,672,342
2 Pekerjaan Plesteran 1341.6 m2 P.03.c Rp 67,655 Rp 90,765,948
4 Pekerjaaan Acian 0 m2 A.4.A.2.27 Rp 72,435 Rp -
5 Ornamen/benangan 0 M' @ Rp 15,000 Rp -
5C PEKERJAAN LAIN-LAIN
1 Pembersihan 1 Ls @ Rp 1,500,000 Rp 1,500,000
SUB-TOTAL Rp 188,938,290
TOTAL Rp 604,244,724
ProFit 5% Rp 30,212,236
TOTAL BIAYA Rp 634,456,960
DIBULATKAN Rp 634,456,000
HARGA PER M' Rp 2,459,132
Terbilang:
Enam Ratus Tiga Puluh Empat Juta Empat Ratus Lima Puluh Enam Ribu Rupiah
Note :
Pekerjaan pembuatan step utuk leveling tanah diluar pekerjaan ini
Terhitung pada RAB Site Leveling Step Diajukan Oleh :
Mahardicon Group