V PEKERJAAN KAYU
5.1 1M3 Pekerjaan Kayu Kap 6/12
1.1000 M3 Kayu Kamper 6/12 2,960,600.00 3,256,660.00
24.0000 Tukang Kayu 40,000.00 960,000.00
2.4000 Kepala Tukang Kayu 43,000.00 103,200.00
8.0000 Pekerja 29,000.00 232,000.00
0.4000 Mandor 46,000.00 18,400.00
1,313,600.00 3,256,660.00 4,570,260.00
5.2 1M3 Pekerjaan Kayu Kap 8/12
1.1000 M3 Kayu Kamper 2,960,600.00 3,256,660.00
24.0000 Tukang Kayu 40,000.00 960,000.00
2.4000 Kepala Tukang Kayu 43,000.00 103,200.00
8.0000 Pekerja 29,000.00 232,000.00
0.4000 Mandor 46,000.00 18,400.00
1,313,600.00 3,256,660.00 4,570,260.00
1 2 3 4 5 6
IX PEKERJAAN LANTAI
9.1 1M2 Pek. Pasangan Lantai Keramik (Warna muda)
1.0000 M2 Keramik 30x30 (Warna Muda ) 35,000.00 35,000.00
0.0250 M3 Perekat G. 14 300,000.00 7,500.00
0.1600 Zak Semen 32,100.00 5,136.00
0.2500 Tukang Batu 38,000.00 9,500.00
0.0250 Kepala Tukang Batu 42,000.00 1,050.00
0.5000 Pekerja 29,000.00 14,500.00
0.0250 Mandor 46,000.00 1,150.00
26,200.00 47,636.00 73,836.00
a Pek. Pas. Keramik meja dapur 20 x 25 32,500.00 26,200.00 30,000.00 56,200.00
b Pek. Pas. Keramik 20 x 20 (Warna Muda) 28,500.00 26,200.00 28,500.00 54,700.00
c Pek. Pas. Keramik Dinding 20 x 25 (Warna Muda) 32,500.00 28,500.00 32,500.00 61,000.00
d Pek. Pas. Keramik 10 x 40 (Warna Muda) 8,750.00 26,200.00 8,750.00 34,950.00
1 2 3 4 5 6
1 2 3 4 5 6
12.4 1Bh Pemasangan Stop Kontak
1.0000 Bh Stop Kontak 12,500.00 12,500.00
1.0000 Tukang Listrik 35,000.00 35,000.00
0.5000 Pekerja 29,000.00 14,500.00
0.2500 Mandor 46,000.00 11,500.00
61,000.00 12,500.00 73,500.00
1Bh Pemasangan Saklar Tunggal 7,500.00 61,000.00 7,500.00 68,500.00
1Bh Pemasangan Saklar ganda 10,000.00 61,000.00 10,000.00 71,000.00
1 2 3 4 5 6
1Bh Pek. Pemasangan Bak Air Panjang 800,000.00 40,000.00 800,000.00 840,000.00
1Bh Pek. Pemasangan Floor drain 10,000.00 40,000.00 10,000.00 50,000.00
1 2 3 4 5 6
2.5000 m1 Pipa tanah 2II 5,000.00 12,500.00
1.8000 Tukang batu 38,000.00 68,400.00
2.8000 Pekerja 29,000.00 81,200.00
149,600.00 1,257,498.20 1,407,098.20
2,961,174.20
XVII PEKERJAAN LAIN-LAIN
17.1 1M2 Pekerjaan Tempelan paras krobokan
23.0000 bh paras krobokan 5,250.00 120,750.00
1.0000 Tukang Tempel 35,000.00 35,000.00
0.1000 Pekerja 29,000.00 2,900.00
37,900.00 120,750.00 158,650.00
17.2 1M Pekerjaan Pasangan paving
2
TGL
NO. URAIAN PEKERJAAN BOBOT DURASI PEKERJAAN
START
I PEKERJAAN PERSIAPAN
1 Pekerjaan pembersihan lokasi 1.99% 2 1-Mar
2 Pekerjaan pengukuran 1.21% 2 3-Mar
3 Pekerjaan bowplank 0.75% 3 4-Mar
II PEKERJAAN TANAH/PASIR
1 Pekerjaan galian tanah 1.03% 6 8-Mar
2 Pekerjaan urugan tanah kembali 0.89% 2 4-Apr
3 Pekerjaan urugan pasir 0.36% 1 13-Mar
IV PEKERJAAN BETON
Pekerjaan Beton Tak Bertulang
1 Pekerjaan beton cor 1 : 2 : 3 0.02% 1 8-Apr
2 Pekerjaan beton rabat 1 : 3 : 5 0.88% 3 5-Apr
Pekerjaan Beton Bertulang
1 Pekerjaan beton struktur (K 175) 11.09% 21 15-Mar
2 Pekerjaan beton praktis (K 125) 3.95% 9 15-Mar
V PEKERJAAN KAYU
1 Pekerjaan kayu kusen 6/12 kamper 4.28% 7
2 Pekerjaan kayu kap 8/12 kamper 0.00%
3 Pekerjaan kayu kap 6/12 kamper 4.89% 8
VI PEKERJAAN ATAP
1 Pekerjaan usuk/reng kamper 3.79% 4
2 Pekerjaan atap genteng plentong 1.76% 3
3 Pekerjaan bubungan genteng 0.75% 3
4 Pekerjaan papan listplank kamper 0.25% 1
5 Pekerjaan Talang Patahan Atap 0.28% 1
IX PEKERJAAN LANTAI
1 Pekerjaan lantai keramik 30/30 3.14% 6
3 Pekerjaan keramik meja dapur 20/20 0.02% 5
4 Pekerjaan keramik Dinding 20/20 0.43% 4
5 Pekerjaan keramik 20/20 0.14% 4
1 2
100.00%
TOT. HARGA SBLM PAJAK
1 - 7. 8 - 14. 15 - 21. 22 - 30. 1 - 7. 8 - 14. 15 - 21. 22 - 30.
TGL BULAN 1 BULAN 2
FINISH M1 M2 M3 M4 M5 M6 M7 M8
2-Mar 1.99%
5-Mar 1.21%
7-Mar 0.75%
13-Mar 1.03%
5-Apr 0.44% 0.44%
0.36%
15-Mar 1.73%
5-Apr 2.99% 2.99% 2.99% 2.99%
8-Apr 2.00%
26-Apr 3.20% 3.20% 3.20% 3.20%
8-Apr 0.02%
7-Apr 0.88%
2.14% 2.14%
2.44% 2.44%
3.79%
1.76%
0.37%
0.66%
1.30%
2.57%
0.66% 0.66%
3.14%
0.01%
0.53%
1.07%
1.15%
0.004%
0.15%
0.03%
0.08%
0.12%
0.13%
0.33%
0.78%
0.08%
0.07%
0.24%
0.16%
0.08%
0.25%
0.42% 0.42%
0.38%
2.69%
100.00%
80.00%
60.00%
40.00%
20.00%
0.00%
0 2 4 6 8 10 12 14
BULAN 3 BULAN 4 BULAN 5
M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19
0.37%
0.25%
0.28%
0.01%
0.43%
0.14%
0.11%
0.32%
0.10%
0.23%
0.54%
0.08%
0.05%
0.10%
0.09%
0.08%
0.13%
0.33%
0.78%
0.23%
0.04%
0.53%
0.42% 0.42%
0.58%
8% 4% 3% 1% 0% 0% 0% 0% 0% 0% 0%
92% 96% 98% 100% 100% 100% 100% 100% 100% 100% 100%
BULAN 5 BULAN 6 BULAN 7
M20 M21 M22 M23 M24 M25 M26 M27 M28
0% 0% 0% 0% 0% 0% 0% 0% 0%
100% 100% 100% 100% 100% 100% 100% 100% 100%
BULAN 8
M29 M30 M31 M32
0% 0% 0% 0% 0% 100%
100% 100% 100% 100% 100%
REKAPITULASI RENCANA ANGGARAN BIAYA
1 2 3
DIBULATKAN Rp 173,700,000.00
OLEH :
SARI KRISMONITA
17062063
1 2 3
JASA PEMBORONG 10 %
10% X 311624804,65 Rp 31,162,480.46
Rp 342,787,285.11
PPN 10 %
10% X 342787285,11 Rp 34,278,728.51
TOTAL COST Rp 377,066,013.63
DIBULATKAN Rp 377,000,000.00
4%
2%
29%
16%
9%
7%
6%
4%
4%
3%
1%
3%
2%
5%
5%
100%
DAFTAR KEBUTUHAN BAHAN, TENAGA, DAN DURASI
I. PEKERJAAN PERSIAPAN
1 1 M1 PASANGAN PAPAN BOUWPLANK 46.00
a. Kayu Meranti Papan (3/20) 0.006
b. Kayu Meranti (5/7) 0.004
c. Paku Reng/Usuk 0.02
d. Tukang Kayu 0.02
e. Pekerja 0.4
f. Kepala Tukang Kayu 0.15
g. Mandor 0.015
V. PEKERJAAN KAYU
1 PEKERJAAN KAYU KAP 6/12 2.02
a. Kayu Kamper 6/12 1.1
b. Tukang Kayu 24
c. Kepala Tukang Kayu 2.4
d. Pekerja 8
e. Mandor 0.4
M1 26.91 2.691
M3 0.276 lbr
M3 0.184 btg
Kg 0.92 kg
OH 0.92 oh
3
OH 18.4 oh
OH 6.9 oh
OH 0.69 oh
M2
M2
M3
OH 53.325 oh 55.1025 5.51025
9
OH 1.7775 oh
M3
M3 63.54 16.4145 1.64145
OH 15.885 oh 2
OH 0.5295 oh
M3
M3 10.08 M3 2.604 0.2604
OH 2.52 oh 1
OH 0.084 oh
M3
21.324 27.98775 2.798775
5.331 M3
5
26.655 oh
1.33275 oh
M3
M3 49.428 m3 203.1491 20.31491
Zak 112.0368 m3
M3 22.40736 sak
OH 49.428 oh 14
OH 4.9428 oh
OH 148.284 oh
OH 0.49428 oh
M3
Bh 2470 bh 24.225 2.4225
Zak 12.51568 sak
M3 1.2654 m3
OH 5.7 oh 3
3
OH 0.57 oh
OH 17.1 oh
OH 0.855 oh
M3
bh 18648.5 bh 182.8988 18.28988
Zak 44.7564 sak
M3 11.04565 m3
OH 43.035 oh 12
OH 4.3035 oh
OH 129.105 oh
OH 6.45525 oh
M3
M3 0.09234 m3 0.8436 0.08436
M3 0.05586 m3
Zak 0.0912 sak
OH 0.684 oh 1
OH 0.0342 oh
OH 0.114 oh
OH 0.0114 oh
M3
M3 3.6036 m3 27.126 2.7126
M3 2.1384 m3
Zak 14.38272 sak
OH 23.76 oh 4
OH 1.188 oh
OH 1.98 oh
OH 0.198 oh
M3
KG 450 kg
KG 11.25 kg
M3 2.25 lbr
M3 1.29375 btg
Kg 22.5 kg
KG 182.4 kg
KG 4.56 kg
M3 0.912 lbr
M3 0.5244 btg
Kg 9.12 kg
M3
M3 2.22035 btg 70.2438 7.02438
OH 48.444 oh
OH 4.8444 oh 3
OH 16.148 oh
OH 0.8074 oh
M3
M3 1.909 btg 64.906 6.4906
OH 43.16 oh
OH 4.316 oh 3
OH 16.6 oh
OH 0.83 oh
M3
M3 1.167495 btg 13.64301 1.364301
Kg 11.119 kg
OH 6.348949 oh
OH 0.311332 oh
1
OH 6.348949 oh
OH 0.633783 oh
M3
M3 0.66714 btg 10.21836 1.021836
Kg 16.6785 kg
OH 4.758932 oh
1
OH 0.233499 oh
OH 4.758932 oh
OH 0.466998 oh
M1
Bh 156.56 bh 25.0496 2.50496
Bh 1.1742 bh
OH 7.828 oh
OH 0.7828 oh
3
OH 15.656 oh
OH 0.7828 oh
M1
M3 0.03821 btg 8.971708 0.897171
Kg 0.7642 kg
OH 6.1136 oh
1
OH 0.61136 oh
OH 2.13976 oh
OH 0.106988 oh
M2
Bh 2557.37 bh 20.10315 2.010315
OH 16.6785 oh
OH 1.66785 oh 1
OH 1.66785 oh
OH 0.088952 oh
M1
Lb 0.12034 lbr 2.9538 0.29538
Bh 1.094 bh
OH 2.188 oh
1
OH 0.7658 oh
M2
Zak 7.25153 sak 29.66535 2.966535
M3 0.578094 m3
OH 7.6065 oh
3
OH 0.76065 oh
OH 20.284 oh
OH 1.0142 oh
M2
Zak 32.12916 sak 244.7936 24.47936
M3 8.185286 m3
OH 76.498 oh
OH 7.6498 oh
15
OH 152.996 oh
OH 7.6498 oh
M2
M3 1.2492 btg 45.55416 4.555416
Lb 13.874448 lbr
Kg 1.6656 kg
Kg 16.656 kg
7
OH 1.6656 oh
OH 0.16656 oh
7
OH 41.64 oh
OH 2.082 oh
M1
M3 0.06855 lbr 68.093 6.8093
Kg 1.828 kg
OH 45.7 oh
7
OH 18.28 oh
OH 1.828 oh
OH 2.285 oh
M2
M2 74.3 bh 59.44 5.944
M3 1.8575 bh
Zak 11.888 sak
OH 18.575 oh 6
OH 1.8575 oh
OH 37.15 oh
OH 1.8575 oh
M2
M2
M2
M2
M3 0.128 lbr 15.01 1.501
OH 10.4 oh
OH 1.04 oh 1
OH 3.4 oh
OH 0.17 oh
M2
M3 0.108 lbr 33.21 3.321
Lb 7.2 lbr
Kg 1.8 kg
Kg 0.72 kg
1
OH 9 oh
OH 0.45 oh
OH 21.6 oh
OH 2.16 oh
M2
M3 0.39552 lbr 4.7277 0.47277
M2 13.596 lbr
Lb 0.1854 kg
M' 0.1854 m
1
OH 2.472 oh
OH 0.2472 oh
OH 1.236 oh
OH 0.7725 oh
M2
M2 0.1188 lbr 0.06696 0.006696
Lb 0.00162 kg
M' 0.00162 m
OH 0.0216 oh 1
OH 0.00216 oh
OH 0.0108 oh
OH 0.0324 oh
BH
Bh 6 bh 2.244 0.2244
OH 2.04 oh 1
OH 0.204 oh
BH
BH
BH 15 bh 7.575 0.7575
OH 7.5 oh 1
OH 0.075 oh
BH
BH 24 bh 2.64 0.264
OH 2.4 oh 1
OH 0.24 oh
BH
BH
BH 28 bh 2.94 0.294
OH 2.8 oh 1
OH 0.14 oh
BH
BH 90 bh 11.25 1.125
OH 9 oh 1
OH 2.25 oh
BH
BH 24 bh 2.64 0.264
OH 2.4 oh 1
OH 0.24 oh
BH
BH 80 bh 4.8 0.48
OH 4 oh 1
OH 0.8 oh
BH
BH 2 bh 2 0.2
OH 2 oh 1
OH 0 oh
BH
BH 2 bh 2 0.2
1
OH 2 oh
BH
BH
BH
BH 1 bh 2 0.2
OH 1 oh 1
OH 1 oh
BH
M1
M1 34.056 m1 9.288 0.9288
OH 3.096 bh
1
OH 4.644 bh
OH 1.548 bh
M1
M1 51.524 m1 14.052 1.4052
OH 4.684 oh
1
OH 7.026 oh
OH 2.342 oh
UNIT
TTK
BH 2 bh 3.5 0.35
OH 2 oh
1
OH 1 oh
OH 0.5 oh
TTK
BH 2 bh 3.5 0.35
OH 2 oh
1
OH 1 oh
OH 0.5 oh
TTK
BH 7 bh 12.25 1.225
OH 7 oh
1
OH 3.5 oh
OH 1.75 oh
TTK
BH 0.5 bh 1.25 0.125
OH 0.5 oh
1
OH 0.5 oh
OH 0.25 oh
TTK
TTK
UNIT
Bh 1 bh 1.025 0.1025
OH 0.5 oh
OH 0.5 oh
1
OH 0.025 oh
LS
M2
KG 141.5213 klg 154.9085 15.49085
KG 95.6225 klg
LBR 191.245 lbr
OH 86.06025 oh 6
OH 8.606025 oh
OH 57.3735 oh
OH 2.868675 oh
M2
KG 29.3336 klg 32.1084 3.21084
KG 19.82 klg
LBR 39.64 lbr
OH 17.838 oh 1
OH 1.7838 oh
OH 11.892 oh
OH 0.5946 oh
M2
KG 1.085164 klg 3.09501 0.309501
KG 2.170328 klg
LBR 3.821 lbr
OH 1.71945 oh 1
OH 0.171945 oh
OH 1.1463 oh
OH 0.057315 oh
M2
Ltr 8.6688 ltr 10.54704 1.054704
Lbr 72.24 lbr
OH 5.418 oh
OH 0.57792 oh
1
OH 4.3344 oh
OH 0.21672 oh
M1
M2
M2
M2 17.5 m2 10.5 1.05
OH 8.75 oh 1
OH 1.75 oh
M2
M2 17.5 m2 20.545 2.0545
M3 0.385 lbr
M3 0.18375 btg
Kg 1.75 kg
1
OH 14 oh
OH 1.4 oh
OH 4.9 oh
OH 0.245 oh
157
5.233333
3
21
3
19
5 21
7
2 9
2
3
25
5
7
1
1
1
1
1
1
16
2
3
221
7.366667
REKAPITULASI VOLUME
PEKERJAAN RUMAH TINGGAL TIDAK BERTINGKAT
TYPE 130
I PEKERJAAN PERSIAPAN
1 Pek. Pembersihan Lokasi Ls 1.00
2 Pek. Pengukuran Ls 1.00
3 Pek. Pas. Papan Bowplank M1 45.50
IV PEKERJAAN BETON
1 Pek. Beton Rabat Lantai 1 : 3 :5 M3 6.50
2 Pek. Beton Cor 1 : 2 : 3 M3 0.15
3 Pek. Beton Praktis (k 125) M3 7.78
4 Pek. Beton Struktur (k 175) M3 7.54
V PEKERJAAN KAYU
1 Pek. Kayu Kusen Kamper 6/12 M3 1.46
2 Pek. Kayu Kap Kamper 8/12 M3 3.03
3 Pek. Kayu Kap Kamper 6/12 M3 0.43
VI PEKERJAAN ATAP
1 Pek. Usuk/Reng M2 322.36
2 Pek. Atap Genteng M2 322.36
3 Pek. Atap Bubungan M1 46.48
4 Pek. Lisplank Kamper M1 91.98
5 Pek. Talang Patahan Atap M1 8.30
6 Pek. Pas.Ornamen Ikut Celedu bh 5.00
7 Pek. Pas. Ornamen Murda bh 2.00
IX PEKERJAAN LANTAI
1 Pek. Keramik Lantai 40 x 40 M2 123.55
2 Pek. Keramik Lantai Km/Wc 20 x 20 M2 8.25
3 Pek. Keramik Dinding Km/Wc 25 x 20 M2 36.78
4 Pek. Plint Keramik 10 x 40 M1 131.19
5 Pek. Keramik Meja Dapur 25 x 20 M2 6.30
II PEKERJAAN TANAH/PASIR
1 Pekerjaan galian tanah 1.03% 1.03%
2 Pekerjaan urugan tanah kembali 0.89% 0.44% 0.44%
3 Pekerjaan urugan pasir 0.36% 0.36%
IV PEKERJAAN BETON
Pekerjaan Beton Tak Bertulang
1 Pekerjaan beton cor 1 : 2 : 3 0.02% 0.02%
2 Pekerjaan beton rabat 1 : 3 : 5 0.88% 0.88%
Pekerjaan Beton Bertulang
1 Pekerjaan beton struktur (K 175) 11.09% 3.70% 3.70% 3.70%
2 Pekerjaan beton praktis (K 125) 3.95% 1.97% 1.97%
V PEKERJAAN KAYU
1 Pekerjaan kayu kusen 6/12 kamper 4.28% 2.14% 2.14%
2 Pekerjaan kayu kap 8/12 kamper 0.00%
3 Pekerjaan kayu kap 6/12 kamper 4.89% 2.44% 2.44%
VI PEKERJAAN ATAP
1 Pekerjaan usuk/reng kamper 3.79% 3.79%
2 Pekerjaan atap genteng plentong 1.76% 1.76%
3 Pekerjaan bubungan genteng 0.75% 0.37% 0.37%
4 Pekerjaan papan listplank kamper 0.25% 0.25%
5 Pekerjaan Talang Patahan Atap 0.28% 0.28%