Anda di halaman 1dari 3

REKAPITULASI BIAYA

BANTUAN TEKNIS (BANTEK) PERENCANAAN DAN PEMANTAUAN


BALAI BESAR PELAKSANAAN JALAN NASIONAL XIII MAKASSAR
PROV. SULAWESI SELATAN

NO. JENIS BIAYA JUMLAH

I. BIAYA LANGSUNG PERSONIL 2,366,564,200

II. BIAYA LANGSUNG NON PERSONIL 875,830,000

TOTAL 3,242,394,200

PPN (10%) 324,239,420

TOTAL BIAYA 3,566,633,620

DIBULATKAN 3,566,633,000

TERBILANG: tiga milyar lima ratus enam puluh enam enam juta enam ratus tiga puluh tiga ribu rupiah
RENCANA ANGGARAN BIAYA

BANTUAN TEKNIS (BANTEK) PERENCANAAN DAN PEMANTAUAN


BALAI BESAR PELAKSANAAN JALAN NASIONAL XIII MAKASSAR
PROV. SULAWESI SELATAN
####### 3,566,633,000.00
Jml. Jml. Hrg. Sat. Jumlah
No Kualifikas Sat. Vol.
Org Bln. (Rp.) (Rp.)

I BIAYA LANGSUNG PERSONIL


1.1 Biaya Tenaga Ahli
Bidang Perencanaan dan Pemantauan
1 Ketua Tim / Ahli Jalan S2 Sipil / SKA Ahli Madya 1 11.00 OB 11.00 29,780,000.00 327,580,000
2 Ahli Teknik Jalan S1 Sipil / SKA Ahli Muda 1 11.00 OB 11.00 18,177,000.00 199,947,000
3 Ahli Teknik Jembatan S1 Sipil / SKA Ahli Muda 1 11.00 OB 11.00 18,177,000.00 199,947,000
4 Ahli Transportasi S1 Sipil / SKA Ahli Muda 1 11.00 OB 11.00 18,177,000.00 199,947,000

Bidang Pembangunan dan Pengujian


6 Ahli Teknik Jalan S1 Sipil / SKA Ahli Muda 1 11.00 OB 11.00 18,177,000.00 199,947,000
7 Ahli Teknik Jembatan S1 Sipil / SKA Ahli Muda 1 11.00 OB 11.00 18,177,000.00 199,947,000

Bidang Preservasi dan Peralatan


8 Ahli Teknik Jalan S1 Sipil / SKA Ahli Muda 1 11.00 OB 11.00 18,177,000.00 199,947,000
9 Ahli Teknik Jembatan S1 Sipil / SKA Ahli Muda 1 11.00 OB 11.00 18,177,000.00 199,947,000
Sub Total 1.1 88.00 1,727,209,000

1.2 Biaya Tenaga Penunjang / Pendukung


Bidang Perencanaan dan Pemantauan
1 Staf Teknik / Administrasi Teknik 1 S1 Sipil 1 11.00 OB 11.00 6,458,000 71,038,000
2 Staf Teknik / Administrasi Teknik 2 S1 Sipil 1 11.00 OB 11.00 6,458,000 71,038,000
3 Staf Informasi dan Teknologi S1 Informatika / IT 1 11.00 OB 11.00 5,687,000 62,557,000
4 Sekretaris / Staf Teknik / Administrasi Teknik 1 11.00 OB 11.00 5,687,000 62,557,000
5 Office Boy - 1 11.00 OB 11.00 3,711,400 40,825,400
6 Driver - 1 11.00 OB 11.00 4,289,800 47,187,800

Bidang Pembangunan dan Pengujian


7 Staf Teknik / Administrasi Teknik 3 S1 Sipil 1 11.00 OB 11.00 6,458,000 71,038,000
8 Staf Teknik / Administrasi Teknik 4 S1 Sipil 1 11.00 OB 11.00 6,458,000 71,038,000

Bidang Preservasi dan Peralatan


9 Staf Teknik / Administrasi Teknik 5 S1 Sipil 1 11.00 OB 11.00 6,458,000 71,038,000
10 Staf Teknik / Administrasi Teknik 6 S1 Sipil 1 11.00 OB 11.00 6,458,000 71,038,000
Sub Total 1.2 110.00 639,355,200
Total Biaya I Langsung Personil 2,366,564,200

II BIAYA LANGSUNG NON PERSONIL


2.1 Biaya Kantor
1 Sewa Komputer Laptop ( 11 Unit ) Unit Bln 163.00 850,000 138,550,000
2 Sewa Mobil unit 11.00 5,890,000 64,790,000
3 Safety Tools (Helm, Rompi dan Baju Seragam dll) Ls 1.00 1,852,000 1,852,000
Sub Total 2.1 205,192,000

2.2 Biaya Perjalanan Dinas


a. Koordinasi (Makassar - Jakarta)
Tiket Pesawat PP 3 Org OT 3.00 3,600,000 10,800,000
Biaya Taxi PP 3 Org OT 3.00 716,000 2,148,000
Hotel (Jakarta) 10 hari x 3 Org OH 30.00 610,000 18,300,000
Jml. Jml. Hrg. Sat. Jumlah
No Kualifikas Sat. Vol.
Org Bln. (Rp.) (Rp.)
b. Prov. Sulsel
Biaya BBM Hari 30.00 280,000 8,400,000
Sewa Mobil (termasuk sopir) 30 hari x 1 Mobil UH 30.00 700,000 21,000,000
Hotel 29 hari x 6 Org OH 174.00 350,000 60,900,000

b. Prov. Sulbar
Tiket Pesawat PP 10 Org OT 10.00 1,600,000 16,000,000
Biaya Taxi PP 10 Org OT 10.00 834,000 8,340,000
Transportasi Darat PP (Makassar - Sulbar / Sulsel) 12 Org OT 12.00 400,000 4,800,000
Biaya BBM Hari 10.00 280,000 2,800,000
Sewa Mobil (termasuk sopir) 10 hari x 1 Mobil UH 10.00 700,000 7,000,000
Hotel 9 hari x 3 Org OH 27.00 350,000 9,450,000
Sub Total 2.2 169,938,000

2.3 Biaya Pelaporan


1 Laporan Bulanan ( 11 Lap. x 3 Dok) Dok 33.00 100,000 3,300,000
2 Laporan Pendahuluan ( 1 Lap. x 3 Dok) Dok 3.00 150,000 450,000
3 Laporan Khusus / Teknis Ls 1.00 750,000 750,000
4 Laporan Khusus / Teknis Ls 1.00 750,000 750,000
5 Laporan Khusus / Teknis Ls 1.00 750,000 750,000
6 Laporan Akhir + Executiv Summary ( 1 Lap. x 3 Dok) Dok 3.00 300,000 900,000
7 Hardisk 4 Tera Unit 3.00 2,000,000 6,000,000
Sub Total 2.3 12,900,000

2.4 Biaya Pembahasan (2x)


1 Honor Pembahas / Pakar 15 jam x 2 Org OJ 30.00 900,000 27,000,000
2 Konsumsi Makan 2 kali x 20 Org OH 40.00 48,000 1,920,000
3 Konsumsi Kudapan 2 kali x 20 Org OH 40.00 19,000 760,000
4 Penggandaan Materi 2 kali x 20 Org Set 40.00 35,000 1,400,000

Sub Total 2.4 31,080,000

2.5 Biaya Pengujian


1 Sondir (termasuk laporan + rekomendasi) Ttk. 11.00 5,500,000 60,500,000
2 Hand Boring (termasuk laporan + rekomendasi) Ttk. 12.00 8,250,000 99,000,000
3 Bor Mesin (termasuk laporan + rekomendasi) Ttk. 8.00 27,500,000 220,000,000
4 Geolistrik (termasuk laporan + rekomendasi) Lokasi 9.00 5,500,000 49,500,000
5 Traffic Counting (termasuk laporan) 3 hari x 3 Org ( 8 Titik ) OH 72.00 385,000 27,720,000

36.00 456,720,000

Total Biaya II Non Personil 875,830,000

TOTAL BIAYA 3,242,394,200