Jumlah Luas = A1 + A2 + A3 + A4 + A5
A1 + A6 + A7
A2
= 1015 m + 4084 m +
A3
A4 A5
6193,4004 m + 4893,
3877 m + 898,865 m +
A6 2054, 487 m + 304,8255
m
A7
= 19443,9656 m

Total Luas = Jumlah Luas + (0,2 x


Jumlah Luas)
= 19443,9656 m + (0,2 x
19443,9656 m) m²
= 23332, 75872
- Saluran Inlet
Saluran T1-T2
SALURAN T1-T2
150 150

P x l = 188,14 m x 4,6 m
= 865,444 m²
140

160

Saluran T3 – T4
150 SALURAN T3-T4 150

P x l = 224,47 m x 4,4 m
= 987,668 m²
120

140

Saluran T5 – T2
150 150
SALURAN T5-T2 P x l = 479,5 m x 4,5 m
= 2157,75 m²
125

150

Saluran T2 – T4
SALURAN T2-T4
150 150

100
P x l = 119,72 m x 4,1 m
= 490,852
110

Saluran T6 – T4
150 150 P x l = 191,01 m x 4,75 m
SALURAN T6-T4
= 907,2975 m²
140

175

Saluran T2 – T7
P x l = 151,05 m x 5,05 m
SALURAN T2-T7
= 762,8025 m²
170

205

Saluran T4 - T8
SALURAN T4-T8

P x l = 173,09 m x 5,20 m
= 900,068 m²
180

220

Saluran T9 – T7
SALURAN T9-T7

P x l = 363,08 m x 4,75 m
= 1724,63 m²
145

175

Saluran T11 – T10


SALURAN T11-T10

P x l = 422, 43 m x 4,6 m
= 1943,178 m²
130

160

Saluran T12 – T10


P x l = 372,54 m x 4,9 m
SALURAN T12-T10 = 1825,446

155

190

Saluran T8 – T7
SALURAN T8-T7

P x l = 115,44 m x 5,3m
= 611,832 m²
0
18

230

Saluran T7 – T10
P x l = 268,8 m x 6,65 m
SALURAN T7-T10

= 1787,52 m²
270

365

Saluran T10 – T13


SALURAN T10-T13
P x l = 46,599 m x 7,25 m
= 337,84275 m²
300

425
Total Luas Saluran Inlet = 15302,33075

Saluran Outlet
SALURAN OUTLET

P x l = 46,67 m x 6 m
= 280,02 m²
265

260

II. Direksi Keet

P x l = 6m x 3m
= 18 m²
6m

3m
III. Pekerjaan Bowplank
1. Kolam
A1

A2

A3
A4 A5

A6

A7


2. Saluran
Saluran T1 – T2
Jumlah Patok = (P.saluran x 2) + (l.
Saluran x 2)
=(188,14 m x 2) + (1,6 m x
2)
P= 188,14 m

l = 1,6 m m³


Papan BP = (2xP.Saluran) +
(2xl.Saluran)
= (188,14 m x 2) + (2 x 1,6
m)
Saluran T3-T4 Jumlah Patok
= (P. Saluran x 2) + (L. Saluran x 2)
= (224,47 m x 2) + (1,4 m x 2)

P= 224,47 m = 301,16 buah x 1 m

= 76 x 0,04 m x 0,06 m x 4 m
=0,7296 m³

Papan Bowplank
L = 1,4 m = (P. Saluran x 2) + (L. Saluran x 2)
= (224,47 m x 2) + (1,4 m x 2)

=112,935 ≈ 113 keping


= 113 x 0,02 m x 0,2 m x 3m m³
=1,536

Saluran T5-T2 Jumlah Patok


= (P. Saluran x 2) + (L. Saluran x 2)
= (479,5 m x 2) + (1,5 m x 2)

P= 479,5 m = 642 buah x 1 m

=161 x 0,04 m x 0,06 m x 4 m


=1,5456 m³

Papan Bowplank
L = 1,5 m = (P. Saluran x 2) + (L. Saluran x 2)
= (479,5 m x 2) + (1,5 m x 2)

=241 keping
= 241 x 0,02 m x 0,2 m x 3m

=2,892
Saluran T2-T4 Jumlah Patok
= (P. Saluran x 2) + (L. Saluran x 2)
= (119,72 m x 2) + (1,1 m x 2)

P= 119,72 m = 161,3 ≈ 162 buah x 1 m

= 41 x 0,04 m x 0,06 m x 1m
= 0,3936 m³

Papan Bowplank
L = 1,1 m = (P. Saluran x 2) + (L. Saluran x 2)
= (119,72 m x 2) + (1,1 m x 2)

=61 keping
= 61 x 0,02 m x 0,2 m x 3m

=0,732

Saluran T6-T4 Jumlah Patok


= (P. Saluran x 2) + (L. Saluran x 2)
= (191,01 m x 2) + (1,75 m x 2)

P= 191,01 m = 257,01 ≈ 257 buah x 1 m

= 65 x 0,04 m x 0,06 m x 1m
= 0,624 m³

Papan Bowplank
L = 1,75 m = (P. Saluran x 2) + (L. Saluran x 2)
= (191,01m x 2) + (1,75 m x 2)
= 96,38 keping ≈ 97 keping m³
= 97 x 0,02 m x 0,2 m x 3m
= 1,164

Saluran T2-T7 Jumlah Patok


= (P. Saluran x 2) + (L. Saluran x 2)
= (151,05 m x 2) + (2,05 m x 2)

P= 151,05 m = 204,13 ≈ 205 buah x 1 m

= 52 x 0,04 m x 0,06 m x 1m
= 0,4992 m³

Papan Bowplank
L = 2,05 m = (P. Saluran x 2) + (L. Saluran x 2)
= (151,05m x 2) + (2,05 m x 2)

= 76,55 keping ≈ 77 keping


= 77 x 0,02 m x 0,2 m x 3m m³
= 0,924

Saluran T4-T8 Jumlah Patok


= (P. Saluran x 2) + (L. Saluran x 2)
= (173,09 m x 2) + (2,2 m x 2)

P= 173,09 m = 233,72 ≈ 234 buah x 1 m

= 59 x 0,04 m x 0,06 m x 1m
= 0,5664 m³

Papan Bowplank
L = 2,2 m = (P. Saluran x 2) + (L. Saluran x 2)
= (173,09 m x 2) + (2,2 m x 2)

= 87,645 keping ≈ 88 keping


= 88 x 0,02 m x 0,2 m x 3m m³
= 1,056
Saluran T9-T7 Jumlah Patok
= (P. Saluran x 2) + (L. Saluran x 2)
= (363,08 m x 2) + (1,75 m x 2)

P= 363,08 m = 486,44 ≈ 487 buah x 1 m

= 122 x 0,04 m x 0,06 m x 1m


= 1,1712 m³

Papan Bowplank
L = 1,75 m = (P. Saluran x 2) + (L. Saluran x 2)
= (363,08 m x 2) + (1,75 m x 2)

= 182.415 keping ≈ 183 keping


= 183 x 0,02 m x 0,2 m x 3m

= 2,196

Saluran T11-T10 Jumlah Patok


= (P. Saluran x 2) + (L. Saluran x 2)
= (422,43 m x 2) + (2,6 m x 2)

P= 422,43 m = 565,373 ≈ 566 buah x 1 m

= 142 x 0,04 m x 0,06 m x 1m


= 1,3632 m³

Papan Bowplank
L = 1,6 m = (P. Saluran x 2) + (L. Saluran x 2)
= (422,43 m x 2) + (1,6 m x 2)

= 212,015 keping ≈ 212 keping


= 212 x 0,02 m x 0,2 m x 3m m³
= 2,544

Saluran T12-T10 Jumlah Patok


= (P. Saluran x 2) + (L. Saluran x 2)
= (372,54 m x 2) + (1,9 m x 2)

P= 372,54 m = 499,253 ≈ 500 buah x 1 m

= 125 x 0,04 m x 0,06 m x 1m



= 1,2

L = 1,9 m Papan Bowplank


= (P. Saluran x 2) + (L. Saluran x 2)
= (372,54 m x 2) + (1,9 m x 2)

= 187,22 keping ≈ 188 keping


= 188 x 0,02 m x 0,2 m x 3m m³
= 2,256

Saluran T8-T7 Jumlah Patok


= (P. Saluran x 2) + (L. Saluran x 2)
= (115,44 m x 2) + (2,3 m x 2)

P= 115,44 m = 157 buah x 1 m

= 40 x 0,04 m x 0,06 m x 1m
= 0,384 m³

Papan Bowplank
L = 2,3 m = (P. Saluran x 2) + (L. Saluran x 2)
= (115,44 m x 2) + (2,3 m x 2)

= 58,87 keping ≈ 59 keping


= 59 x 0,02 m x 0,2 m x 3m
= 0,708 m³

Saluran T7-T10 Jumlah Patok


= (P. Saluran x 2) + (L. Saluran x 2)
= (268,68 m x 2) + (3,65 m x 2)

P= 268,8 m = 363,26 ≈ 364 buah x 1 m

= 91 x 0,04 m x 0,06 m x 1m
= 0,8736 m³

Papan Bowplank
L = 3,65 m = (P. Saluran x 2) + (L. Saluran x 2)
= (268,68 m x 2) + (3,65 m x 2)

= 136,225 keping ≈ 137 keping


= 137 x 0,02 m x 0,2 m x 3m m³
= 1,644

Saluran T10-T13 Jumlah Patok


= (P. Saluran x 2) + (L. Saluran x 2)
= (46,559 m x 2) + (4,25 m x 2)

P= 46,559 m = 67,7986 ≈ 68 buah x 1 m

= 17 x 0,04 m x 0,06 m x 1m
= 0,1632 m³

Papan Bowplank
L = 4,25 m = (P. Saluran x 2) + (L. Saluran x 2)
= (46,559 m x 2) + (4,25 m x 2)

= 25,4245 keping ≈ 26 keping


= 26 x 0,02 m x 0,2 m x 3m

= 0,312

Total Kayu = 10,1283 m³


Total Papan = 18,924 m³

Saluran Outlet Jumlah Patok


= (P. Saluran x 2) + (L. Saluran x 2)
= (46,67 m x 2) + (3 m x 2)

P= 46,67 m = 66,226 ≈ 63 buah x 1 m

= 17 x 0,04 m x 0,06 m x 1m
= 0,1632 m³

Papan Bowplank
L=3m = (P. Saluran x 2) + (L. Saluran x 2)
= (46,67m x 2) + (3 m x 2)

= 24,835 keping ≈ 25 keping


= 25 x 0,02 m x 0,2 m x 3m

= 0,3
IV. Pekerjaan Galian
1. Kolam
Volume
A1
= Luas Kolam x t
= 19443,9656 m² x 4,1 m
A2

A3
A4 A5
= 79720,25896

2. Saluran Inlet A6

Saluran T1-T2 A7

SALURAN T1-T2
150 POTONGAN KOLAM A4
150
Volume
=PxLxt
75

= 188,14 m x 1,6 m x 1,5 m


= 451,536 m³
140

410,76
410

Saluran T3-T4 Volume


150 SALURAN T3-T4 150
=PxLxt
100
160
= 224,47 m x 1,4 m x 1,3 m
478,55
= 408,535 m³
120

140

Saluran T5-T2 Volume


150
SALURAN T5-T2
150
=PxLxt
= 479,5 m x 1,5 m x 1,35 m
= 970,9875 m³
125

150

Saluran T2-T4 Volume


150
SALURAN T2-T4
150 =PxLxt
= 119,72 m x 1,1 m x 1,1 m
= 144,8612 m³
100

110
Saluran T6-T4 Volume
150 150 =PxLxt
SALURAN T6-T4
= 191,01 m x 1,75 m x 1,5 m
= 501,40125 m³
140

175

Saluran T2-T7 Volume


=PxLxt
SALURAN T2-T7 = 151,05 m x 2,05 m x 1,8 m
= 557,3745 m³
170

205

Saluran T4-T8 Volume


SALURAN T4-T8 =PxLxt
= 173,09 m x 2,2 m x 1,9 m
= 723,5162 m³
180

220

Saluran T9-T7 Volume


SALURAN T9-T7
=PxLxt
= 363,08 m x 1,75 m x 1,55 m
= 984,8545 m³
145

175

Saluran T11-T10 Volume


SALURAN T11-T10
=PxLxt
= 422,43 m x 1,6 m x 1,4 m
= 946,2432 m³
130

160

Saluran T12-T10 Volume


SALURAN T12-T10 =PxLxt
= 372,54 m x 1,9 m x 1,55 m
= 1097,1303 m³
155

190
Saluran T8-T7 Volume
SALURAN T8-T7 =PxLxt
= 115,44 m x 2,3 m x 1,9 m
= 504,4728 m³
0
18

230

Saluran T7-T10 Volume


SALURAN T7-T10
=PxLxt
= 268,8 m x 3,65m x 2,9 m
= 2845,248 m³
270

365

Saluran T10-T13 Volume


SALURAN T10-T13
=PxLxt
= 46,599 m x 4,25 m x 3,2 m
= 633,7464 m³
300

425
Total Volume Saluran Inlet
=10769,90685 m³
3. Saluran Outlet Volume
SALURAN OUTLET
=PxLxt
= 46,64 m x 3 m x 2,75 m
= 385,0275 m³
265

260

V. Pekerjaan Pasir Urug


1. Kolam Volume
= Panjang Keliling x l x t
= 1047,2208 m x 1m x 0,1 m
= 104,72208
L=1 m ; t=0,1 m m³

2. Saluran Inlet Volume


Saluran T1-T2 =Pxlxt
L = 188,14 m x 1,6 m x 0,1 m
= = 30,1024 m³
1,6 m; t = 0,1 m
Saluran T3-T4
L Volume
= =Pxlxt
1,4 = 224,47 m x 1,4 m x 0,1 m
m; t = 0,1 m = 31,4258 m³
Saluran T5-T2 Volume
=Pxlxt
= 479,5 m x 1,5 m x 0,1 m
= 71,925 m³
L = 1,5 m; t = 0,1 m

Saluran T2-T4 Volume


=Pxlxt
= 119,72 m x 1,1 m x 0,1 m
= 13,1692 m³
L = 1,1 m; t = 0,1 m
Saluran T6-T4 Volume
=Pxlxt
= 191,01 m x 1,75 m x 0,1 m
= 33,42675 m³
L = 1,75 m; t = 0,1 m

Saluran T2-T7 Volume


=Pxlxt
= 151,05 m x 2,05 m x 0,1 m
= 30,96525 m³
L = 2,05 m; t = 0,1 m
Saluran T4-T8 Volume
=Pxlxt
= 173,09 m x 2,2 m x 0,1 m
= 38,0798 m³
L = 2,2 m; t = 0,1 m
Saluran T9-T7 Volume
=Pxlxt
= 363,08 m x 1,75 m x 0,1 m
= 63,539 m³
L = 1,75 m; t = 0,1 m
Saluran T11-T10 Volume
=Pxlxt
= 422,43 m x 1,6 m x 0,1 m
= 67,5888 m³
L = 1,6 m; t = 0,1 m
Saluran T12-T10 Volume
=Pxlxt
= 372,54 m x 1,9 m x 0,1 m
= 70,7826 m³
L = 1,9 m; t = 0,1 m
Saluran T8-T7 Volume
=Pxlxt
= 115,44 m x 2,3 m x 0,1 m
= 26,5512 m³
L = 2,3 m; t = 0,1 m
Saluran T7-T10 Volume
=Pxlxt
= 268,8 m x 3,65 m x 0,1 m
= 98,112 m³
L = 3,65 m; t = 0,1 m
Saluran T10-T13 Volume
=Pxlxt
= 46,599 m x 4,25 m x 0,1 m
= 19,804575 m³
L = 4,25 m; t = 0,1 m

Total Volume Pasir Urug Saluran Inlet


=565,472375 m³
Saluran Outlet Volume
=Pxlxt
= 46,67 m x 3 m x 0,1 m
= 14,001 m³
L = 3 m; t = 0,1 m

VI. Pekerjaan Lantai Kerja Tidak Ada Lantai Kerja

VII. Pekerjaan Dinding


1. Dinding Kolam Dinding Kolam
75
POTONGAN KOLAM A4 = Panjang Keliling x l x t
= 1047,2208 m x 1m x 4,1 m
= 4293,60528

410

2. Dinding Saluran =Volume 1 - Volume 2


Saluran T1-T2
100
= (P x L x t) – (P x L1 x t1)
= (188,14m x 1,6m x 1,5m) – (188,14 m
478,55

SALURAN T1-T2

x 1,2 m x 1,2 m)
55

=180,61

140
65

120
160
Saluran T3-T4 =Volume 1 - Volume 2
SALURAN T3-T4 = (P x L x t) – (P x L1 x t1)
= (224,47m x 1,4m x 1,2m) – (224,47 m
x 1 m x 1 m)
50 =152,63

120
50

100
140
Saluran T5-T2 =Volume 1 - Volume 2
SALURAN T5-T2 = (P x L x t) – (P x L1 x t1)
= (479,5m x 1,5m x 1,25m) – (479,5m x
50

1,1m x 1,05 m)
=345,24
125


55

110
150

Saluran T2-T4 =Volume 1 - Volume 2


SALURAN T2-T4 = (P x L x t) – (P x L1 x t1)
= (119,72m x 1,1m x 1m) – (119,72 m x
0,7 m x 0,8 m)
40

=64,64

100
40

70
110
Saluran T6-T4 =Volume 1 - Volume 2
SALURAN T6-T4 = (P x L x t) – (P x L1 x t1)
= (191,01m x 1,75m x 1,4m) – (191,01
55

m x 1,35 m x 1,2 m)
140

=158,53

65

135
175

Saluran T2-T7 =Volume 1 - Volume 2


= (P x L x t) – (P x L1 x t1)
= (151,05m x 2,05m x 1,7m) – (151,05
65

SALURAN T2-T7
m x 1,65 m x 1,5 m)
=152,56
170


85

165
205
Saluran T4-T8 =Volume 1 - Volume 2
SALURAN T4-T8
= (P x L x t) – (P x L1 x t1)
= (173,09m x 2,2m x 1,8m) – (173,09 m
65
x 1,8 m x 1,6 m)
=186,94

180
95

180
220

Saluran T9-T7 =Volume 1 - Volume 2


SALURAN T9-T7 = (P x L x t) – (P x L1 x t1)
= (363,08m x 1,75m x 1,45m) – (363,08
m x 1,35 m x 1,25 m)
=308,61
55


145
70

135
175

Saluran T11-T10 =Volume 1 - Volume 2


SALURAN T11-T10 = (P x L x t) – (P x L1 x t1)
= (422,43m x 1,6m x 1,3m) – (422,43 m
50

x 1,2 m x 1,1 m)
=321,05
130


60

120
160

Saluran T12-T10 =Volume 1 - Volume 2


SALURAN T12-T10 = (P x L x t) – (P x L1 x t1)
= (372,54m x 1,9m x 1,55m) – (372,54
60

m x 1,5 m x 1,35 m)
155

=342,80
75


150
190

Saluran T8-T7 =Volume 1 - Volume 2


SALURAN T8-T7 = (P x L x t) – (P x L1 x t1)
= (115,44m x 2,3m x 1,8m) – (115,44 m
65

x 1,9 m x 1,6 m)
=126,99

95

190
230
Saluran T7-T10 (Batu Kali) =Volume 1 - Volume 2
SALURAN T7-T10
= (P x L x t) – (P x L1 x t1)
= (268,8m x 3,65m x 2,8m) – (268,8 m x
85
2,85 m x 2,30 m)
=985,15

270
145

285
365

Saluran T10-T13 (Batu Kali) =Volume 1 - Volume 2


SALURAN T10-T13
= (P x L x t) – (P x L1 x t1)
90

= (46,599m x 4,25m x 3,1m) – (46,599


m x 3,45 m x 2,6 m)
=195,95
300


170

345
425
Total Volume Dinding Batu Bata
=2340,6 m³

Total Volume Dinding Batu Kali m³


=1181,1
Saluran Outlet =Volume 1 - Volume 2
SALURAN OUTLET
= (P x L x t) – (P x L1 x t1)
= (46,67 m x 3m x 2,65m) – (46,67 m x
2,6 m x 2,25 m)
=98,007
265

260

VIII. Pekerjaan Plesteran


1. Plesteran Kolam Plesteran Kolam
75
= Panjang Keliling x (L1+L2)
= 1047,2208 m x (0,75+4,176)
= 1047,2208 m x 4,926 m
= 5158,6097

410,76
410

100

2. Plesteran Saluran
Saluran T1-T2 = Panjang Saluran x (2a+2b+c)
= 188,14 m x (2x0,2m+2x1,1m+1,2m)
= 714,932 m²
SALURAN T1-T2

55
140
65

120
160

Saluran T3-T4
SALURAN T3-T4 = Panjang Saluran x (2a+2b+c)
= 224,47 m x (2x0,2m+2x1m+1m)
= 763,198
50


120
50

100
140
Saluran T5-T2
SALURAN T5-T2 = Panjang Saluran x (2a+2b+c)
= 479,5 m x (2x0,2m+2x1,05m+1,1m)
50

= 1726,2 m²
125
55

110
150

Saluran T2-T4
SALURAN T2-T4 = Panjang Saluran x (2a+2b+c)
= 119,72 m x (2x0,2m+2x0,8m+0,7m)
= 323,244 m²
40
100
40

70
110
Saluran T6-T4
SALURAN T6-T4 = Panjang Saluran x (2a+2b+c)
= 191,01 m x (2x0,2m+2x1,2m+1,35m)
55

= 792,6915 m²
140
65

135
175
Saluran T2-T7
= Panjang Saluran x (2a+2b+c)
= 151,05 m x (2x0,2m+2x1,5m+1,65m)
65
SALURAN T2-T7

170 = 762,8025 m²
85

165
205

Saluran T4-T8
SALURAN T4-T8
= Panjang Saluran x (2a+2b+c)
= 173,09 m x (2x0,2m+2x1,6m+1,8m)
65

= 934,686 m²
180
95

180
220

Saluran T9-T7
SALURAN T9-T7 = Panjang Saluran x (2a+2b+c)
= 363,08 m x
(2x0,2m+2x1,25m+1,35m)
= 1543,09
55


145
70

135
175

Saluran T11-T10
SALURAN T11-T10 = Panjang Saluran x (2a+2b+c)
= 422,43 m x (2x0,2m+2x1,1m+1,2m)
50

= 1605,234 m²
130
60

120
160

Saluran T12-T10
SALURAN T12-T10 = Panjang Saluran x (2a+2b+c)
= 372,54 m x (2x0,2m+2x1,35m+1,5m)
60

= 1713,684 m²
155
75

150
190
Saluran T8-T7
SALURAN T8-T7 = Panjang Saluran x (2a+2b+c)
= 115,44 m x (2x0,2m+2x1,6m+1,9m)
65 = 634,92 m²
95

Total Luas Plesteran Saluran Inlet


190
230 =11223,682 m²
Saluran T7-T10 Batu Kali
SALURAN T7-T10
85
270
145

285
365

Saluran T10-T13 Batu Kali


SALURAN T10-T13
90
300
170

345
425

Saluran Outlet Batu Kali


SALURAN OUTLET
265

260

IX. Pekerjaan Timbunan/Tepi


Kolam/Saluran
1. Kolam =P.Keliling Kolam x L x t
=1047,2208 m x 1,5 m x 0,15
=235,62468

L=1,5m;t=0,15m
2. Saluran
- Saluran Inlet =(2xP.Saluran Inlet Total) x L x t
=6231,738 m x 1,5 m x 0,15
=1402,14105 m³
L=1,5m;t=0,15m

- Saluran Outlet
=(2xP.Saluran Outlet) x L x t
=(2x46,67)m x 1,5 m x 0,15
=21,0015 m³
L=1,5m;t=0,15m

X. Pekerjaan Gorong-Gorong
1. Galian Gorong-Gorong = P x L x t x Jumlah Titik
= 6m x 1,2 m x 1,1 m x 13
10

=102,96 m³
80
20

20 80 20
2. Pasir Urug
= P x L x t x Jumlah Titik
= 6m x 1,2 m x 0,2 m x 13
=18,72 m³
L=1,2m;t=0,2m

3. Gorong-Gorong
60 = (Vol.1-Vol.2) x Jumlah Titik
= (πr² x P – πr1² x P) x 13
= ( π x 0,4² x 6m – π x 0,3² x 6m) x 13
10 10 = 17,153 m³

4. Timbunan Gorong-Gorong
=Vol. Galian Gorong-Gorong – Vol.
Pasir – Vol. Gorong-Gorong
= 102,96 – 18,72 – 17,153
= 67,087

10
80
20
20 80 20

Tabel 3.1 Hasil Perhitungan Volume Pekerjaan


No. Uraian Pekerjaan Volume Satuan
I. Pekerjaan Persiapan
1. Pembersihan Kolam 23332, 75872 m²
2. Pembersihan Saluran Inlet 15302,33075 m²
3. Pembersihan Saluran Outlet 280,02 m²

II. Pembuatan Direksi Keet 18 m²

III. Pekerjaan Bowplank


1. Kolam 168 m³
2. Saluran Inlet
-Kayu 10,1283 m³
-Papan 18,924 m³
3. Saluran Outlet
-Kayu 0,1632 m³
-Papan 0,3 m³

IV. Pekerjaan Galian


1. Kolam 79720,25896 m³
2. Saluran Inlet 10769,90685 m³
3. Saluran Outlet 385,0275 m³

V. Pekerjaan Pasir Urug


1. Kolam 104,72208 m³
2. Saluran Inlet 565,472375 m³
3. Saluran Outlet 14,001 m³

VI. Pekerjaan Lantai Kerja - -

VII. Pekerjaan Dinding


1. Pasangan Batu Kali Kolam 4293,60528 m³
2. Pasangan Batu Bata Saluran Inlet 2340,6 m³
3. Pasangan Batu Kali Saluran Outlet 1181,1 m³
4. Pasangan Batu Kali Saluran Outlet 98,007 m³

VIII. Pekerjaan Plesteran


1. Plesteran Kolam 5158,6097 m²
2. Plesteran Saluran Inlet 11223,682 m²
3. Plesteran Saluran Outlet - m²

IX. Pekerjaan Timbunan Tepi


Kolam/Saluran
1. Timbunan Tepi Kolam 235,62468 m³
2. Timbunan Tepi Saluran Inlet 1402,14105 m³
3. Timbunan Tepi Saluran Outlet 21,0015 m³

X. Pekerjaan Gorong-Gorong
1. Galian Gorong-Gorong 102,96 m³
2. Pasir Urug 18,72 m³
3. Gorong-Gorong 17,153 m³
4. Timbunan Gorong-Gorong 67,087 m³