NO Description QTY

I. PEKERJAAN PERSIAPAN AWAL REVISI


1 Pembersihan site dan Buangan Puing 1.00
2 Biaya kost tenaga 3.00
3 Biaya kipem 6.00
4 Biaya mobilisasi alat 1.00
5 Pagar pengaman proyek 1.00

Sub total Pek. I


II. PEKERJAAN AREA TERAS DEPAN
1 Bongkar Kanopi Kaca Existing 25.73
2 Bobok Plat Beton Kantilever 14.36
3 Pekerjaan Penambahan Planter Box 4.20
4 Pekerjaan fin. Texture planter box sisi dalam 15.80
5 Pekerjaan texture planter box 17.00
6 Pek. Kolom Besi Hollow 50 x 50, 2mm include cat 31.46
7 Pek. Balok Hollow 50 x 50, 2Mm include cat 47.04
8 Strukur Rangka Kayu Canopy kayu bengkirai 50.40
9 Finishing Rangka Kayu Canopy kayu bengkirai 50.40
10 Atap Alderon 50.40
11 Lapisan Anyaman Rotan 50.40
12 Finshing Lapisan Anyaman Rotan 50.40
14 Pekerjaan Toping Meja Makan Teras Depan 55 x 864 cm ex. Bengkirai 8.64
15 Pekerjaan Finishing Toping Meja Makan Teras Depan 55 x 1000 cm ex. Bengkirai 1.00
16 Pekerjaan Finishing Toping Meja Makan Teras Depan 55 x 864 cm ex. Bengkirai 1.00
18 Papan Nama Depan uk. 1.00 x 3.90 1.00
19 Finshing papan nama 7.80
20 Kayu kerepyak depan uk. 77 x 1935 cm 19.35
21 Finishing kerepyak depan uk. 77 x 1935 cm 19.35

Sub total Pek. II


III. PEKERJAAN AREA KITCHEN
1 Bongkaran Tembok 78.37
- Penyekat kitchen dengan tempat cuci piring
- Penyekat restaurant dengan kitchen
- Penyekat kitchen existing dengan kitchen baru
NO Description QTY

2 Bongkaran Kaca Depan Existing 2.00


3 Bobok Tembok Ventilating Van ( untuk exhausfan baru ) include perapian 6.00
4 Bobok Lantai Kitchen 73.65 52.18
5 Pekerjaan Pasangan Keramik Lantai 30x30 Asia Tiles 73.65 52.18
6 Pekerjaan Pas. Batako Untuk Dinding meja kitchen ( sisi selatan ) 5.96
9 Pekerjaan Pas. Keramik Dinding 30 x 60 Cm Untuk meja kitchen
( sisi selatan ) sisi dalam 5.96
10 Pekerjaan Cat Dinding Dalam 25.20
11 Pekerjaan Cat Dinding Luar 18.90
25.28
13 Pekerjaan Pasangan Keramik Dinding Motif Bata Sisi Dalam
30 x 60 Cm,T=242 Cm
14 Pekerjaan Cat Minyak Balok Beton Expose 35.70
15 Pekerjaan Toping Meja Counter Belakang 60 x 275 cm ex. Bengkirai 2.75
16 Pekerjaan Finishing Toping Meja Counter Depan 50 x 275 cm ex. Bengkirai 1.00
17 Pekerjaan Finishing Toping Meja Counter Depan 50 x 293 cm ex. Bengkirai 1.00
18 Pekerjaan Finishing Toping Meja Counter Belakang 60 x 275 cm ex. Bengkirai 1.00
19 Pekerjaan Kusen Kayu Uk. 5/14cm ex. Bengkirai
a Pekerjaan Kusen Pintu P1, Kitchen to Garden 5.82
b Pekerjaan Kusen Jendela J1 area meja counter belakang 8.05
20 Pekerjaan Daun Pintu dan Jendela Kayu ex. Bengkirai
a Pekerjaan Daun Pintu P1-1, Kitchen to Garden ( 81 x 216 cm ) 1.84
b Pekerjaan Daun Pintu P1-2, Kitchen to Garden ( 51 x 216 cm ) 1.16
c Pekerjaan Daun Jendela J1 area meja counter belakang 4.00
21 Pekerjaan Finishing Polituran Kusen, Pintu, dan Jendela
a Pekerjaan Finshing Polituran Kusen Pintu P1, Kitchen to Garden 6.11
b Pekerjaan Finshing Polituran Kusen Kayu P4, kitchen to restorant 1.89
c Pekerjaan Finshing Polituran Kusen Jendela J1 area meja counter belakang 8.45
f Pekerjaan Finishing Polituran Daun Pintu P1, Kitchen to Garden 5.87
g Pekerjaan Finishing Polituran Daun Pintu P4, kitchen to restorant 1.17
h Pekerjaan Finishing Polituran Daun Jendela J1 area meja counter belakang 5.04
22 Pekerjaan fix glass J3 -
23 Pekerjaan fix glass J4 -
24 Pekerjaan Acessories Pintu dan Jendela :
a Kuncian ( mortise + silinder ) 1.00
b Pull Handle pemasangan (SBO) 2.00
c Rel + Roda untuk jendela lipat 1.00
d Grendel 3.00
f Engsel pintu 6.00
g Engsel Jendela 4.00
25 Cover rel di jendela 1.00
26 Pek. Gutter 8.00
Sub total Pek. III
IV. PEKERJAAN AREA RESTORANT
1 Pekerjaan Bobok Batu alam dinding meja counter 11.01
2 Pekerjaan Bongkar Toping Meja Bar dan counter + trali 10.01
3 Pekerjaan Ring balok praktis di Dinding Meja Bar & Counter 10.01
4 Pekerjaan Pasangan Tegel Dinding sisi restorant, teras depan dan garden 18.23
5 Pekerjaan Pasangan Tegel Dinding sisi restorant, teras depan dan garden 18.23
NO Description QTY
6
Pekerjaan Pas. Keramik Dinding 30 x 60 Cm Meja Bar & Counter sisi dalam
( sisi kitchen ) 10.01
8
Pekerjaan Toping Table Bar & Counter 60 x 4365 mm ex. Bengkirai
include rangka 4.37
9
Pekerjaan Toping Table Bar & Counter 60 x 3100 mm ex. Bengkirai include
rangka 3.10
10 Pekerjaan Finishing Toping Table Bar & Counter 60 x 436,5 cm ex. Bengkirai 1.00

11 Pekerjaan Finsishing Toping Table Bar & Counter 60 x 310 cm ex. Bengkirai 1.00

12 Pasangan Industrial Ventilating Van 16" 6.00


Sub total Pek. IV
V. PEKERJAAN AREA GARDEN
1 Bobok Lantai 30.19
2 Pekerjaan Batu Candi Untuk Lantai 30 x 30 cm 30.00
5 Pekerjaan Lantai Rabatan Gas Storage 5.36
6 Pekerjaan Roster Custom 20 x 20 Cm 9.91
7 Pekerjaan Bongkar Tembok Steward Area 3.52
8 Pekerjaan Bongkar Spandek Steward Area 15.75
9 Pasangan Tegel Mix 20 x 20 Cm dinding counter table steward area 2.26
10 Pekerjaan Pas. Tembok Batako Menuju Gang 9.78
11 Pekerjaan Plester Tembok Menuju Gang 19.55
12 Pek. Finishing Dinding Texture 19.55
13 Pekerjaan Kusen Pintu P2 To Gang ex. Bengkirai (material eksisting) 5.67
14 Pekerjaan Daun Pintu Besi 1.00
15 Pekerjaan Finishing Polituran Kusen Pintu P2 To Gang 5.67
Sub total Pek. V
VI. PEKERJAAN AREA TOILET
1 Pekerjaan Bongkar Lantai Toilet 13.79
2 Pekerjaan Kuras Septic tank existing 1.00
3 Pekerjaan Bongkar Tembok 9.92
4 Pekerjaan Bongkar Closet + Urinoir 4.00
5 Pekerjaan Bongkar Wastafel 2.00
6 Pekerjaan Urugan Septictank existing 1.00
7 Pekerjaan Bongkar paving jalan 28.00
8 Pekerjaan Finishing Lantai Keramik Roman 32.94 22.00
9 Pekerjaan Pasangan Batako Dinding Toilet Pria 8.57
10 Pekerjaan Pasangan Batako Dinding Luar 10.43
11 Pekerjaan Bongkar Atap meliputi : 16.70
a Bongkar atap spandek / trimdek
b Bongkar reng, usuk dan balok kayu struktur atap
c Bongkar kolom kayu struktur atap
12 Pekerjaan Pasang Atap Kembali
a Pek. Struktur sendi finish acian 2.00
b Pek. Kolom kayu struktur atap ( matrial existing ) 2.00
c Pek. Balok, usuk, reng dan penutup atap( matrial existing ) 16.70
13 Pekerjaan Tambahan Fin. Dinding Paras Jogja include finsh coating 10.43
14 Pekerjaan Dinding Tegel Multicolour uk. 20 x 20 cm 49.10 12.35
15 Pekerjaan Poles Dinding Tegel Multicolour uk. 20 x 20 cm 12.35
NO Description QTY

16 Pekerjaan keramik Dinding Roman 36.75


17 Tambahan Lavatory + meja vanity 2.00
18 Tambahan Urinoir Toto 2.00 2.00
20 Pasangan Cermin Wastafel Toilet 2.00
21 Pekerjaan pasang kusen Pintu P3 ( 3 unit ) matrial kusen existing 14.81
22 Pekerjaan daun pintu P3 ( 3 unit ) kombinasi tegel 20 x 20 cm 4.41
23 Pekerjaan finishing polituran kusen Pintu P3 ( 3 unit ) 14.81
24 Pekerjaan polituran daun pintu P3 ( 3 unit ) 8.82
25 Acesories Pintu P3:
a Kuncian ( mortise + silinder ) 3.00
b Pull Handle pemasangan (SBO) 3.00
c Engsel pintu pivot 3.00
Sub total Pek. VI
VII PEKERJAAN MEP
VII.1 INSTALASI LISTRIK
1 Pekerjaan instalasi lampu gantung teras 7.00
2 Pekerjaan instalasi lampu dinding tempel kolom resto 4.00
3 Pekerjaan instalasi lampu gantung counter kitchen 8.00
4 Pekerjaan instalasi lampu kitchen 6.00
4 Pekerjaan instalasi lampu spot light teras 11.00
5 Pekerjaan instalasi stop kontak 32.00
6 Pekerjaan instalasi stop kontak teras depan 12.00
7 Pek. Instalasi exhaust fan dinding 6.00
8 Pek. Instalasi kabel power 4 x 6 mm2 50.00

VII.2 INSTAL ACESSORIES LISTRIK


1 Saklar Tunggal 5.00
2 Saklar Double 3.00
3 Socket Stop Kontak 32.00
4 Socket Stop Kontak outbow 12.00
5 Lampu gantung teras + bohlam 6.00
6 Lampu dinding tempel kolom resto + bohlam 4.00
7 Lampu gantung counter kitchen + bohlam 8.00
8 lampu Spotlight Teras 11.00
9 Lampu dinding tempel teras belakang 8.00
10 Box Panel Panel 40 x 60 cm include instalasi MCB 8 group 2.00
11 Lampu kitchen (eksisting) + bohlam baru philips 18W 6.00
12 Exhaust Fan dinding 6.00

VII.3 PEKERJAAN PLUMBING


1 Pek. Saluran Air Kotor WC 4" 28.00
2 Pek. Saluran Air Kotor Kitchen 4" 4.00
3 Pek. Saluran Kitchen Zink 2" 24.00
4 Pek. Saluran Air Floor Drain Toilet 3" 28.00
5 Pek. Saluran Air Kotor Urinoir 2" 28.00
6 Pek. Saluran Wastafel 1 1/2" 8.00
7 Pek. Pipa PVC Saluran air bersih 1/2" 24.00

Sub total Pek. VI


NO Description QTY

TOTAL

DIBULATKAN
HARGA SATUAN JUMLAH
SAT ( Rp ) ( Rp )
REVISI
ls 4,725,000.00 4,725,000.00 Perubahan Harga Satuan
bln 1,800,000.00 5,400,000.00
org 150,000.00 900,000.00
ls 4,050,000.00 4,050,000.00
ls 1,601,250.00 1,601,250.00 Perubahan Harga Satuan

16,676,250.00

m2 52,500.00 1,350,562.50 Perubahan Harga Satuan


m2 250,000.00 3,591,000.00 Perubahan Harga Satuan
m' 304,500.00 1,278,900.00 Perubahan Harga Satuan
m2 52,500.00 829,631.25 Perubahan Finishing
m2 52,500.00 892,500.00 Perubahan Finishing
m' 168,000.00 5,284,944.00 Perubahan Harga Satuan
m' 168,000.00 7,902,720.00 Perubahan Harga Satuan
m2 673,148.00 33,926,659.20
m2 117,075.00 5,900,580.00 Perubahan Harga Satuan
m2 279,681.82 14,095,963.64 Perubahan matrial
m2 101,850.00 5,133,240.00 Perubahan Harga Satuan
m2 55,000.00 2,772,000.00 Perubahan Harga Satuan
m' 2,011,994.38 17,383,631.46
unit 1,344,000.00 1,344,000.00
unit 979,918.78 979,918.78
unit 4,787,475.00 4,787,475.00
m2 147,000.00 1,146,600.00 Perubahan Harga Satuan
m' 1,134,486.00 21,952,304.10 -15%
m' 148,750.00 2,878,312.50 -15%

133,430,942.43

m2 20,000.00 1,567,440.00 Perubahan Harga Satuan


HARGA SATUAN JUMLAH
SAT ( Rp ) ( Rp )
unit 131,250.00 262,500.00 Perubahan Harga Satuan
unit 157,500.00 945,000.00
m2 36,750.00 1,917,615.00 Perubahan volume dan harga satuan
m2 200,633.21 10,469,041.03 Perubahan volume dan spesifikasi matrial uk. 30 x 30 cm
m' 258,278.12 1,540,370.69

m2 250,000.00 1,491,000.00 Perubahan spesifikasi matrial


m2 42,474.85 1,070,366.25
m2 48,277.85 912,451.39
m2 250,000.00 6,320,737.50
Perubahan spesifikasi matrial
m2 89,656.35 3,200,731.70 Balok tidak ditutup dengan plafond spandek
m' 2,011,994.38 5,532,984.55
unit 1,323,084.00 1,323,084.00
unit 1,456,553.00 1,456,553.00
unit 1,381,114.00 1,381,114.00

m' 203,105.00 1,182,071.10


m' 203,105.00 1,634,995.25

m2 1,885,975.00 3,464,686.95
m2 2,060,065.00 2,382,835.98
unit 1,189,615.00 4,758,460.00

m' 94,500.00 577,489.50 Perubahan Harga Satuan


m' - Item pekerjaan dihilangkan
m' 94,500.00 798,761.25 Perubahan Harga Satuan
m2 147,000.00 862,816.50 Perubahan Harga Satuan
m2 - Item pekerjaan dihilangkan
m2 - - Perubahan Harga Satuan
m2 421,297.80 -
m2 421,297.80 -

set 522,270.00 522,270.00


psg 35,000.00 70,000.00
set 899,465.00 899,465.00
psg 116,060.00 348,180.00
pcs 95,749.50 574,497.00
pcs 89,946.50 359,786.00
unit 522,270.00 522,270.00
m' 319,165.00 2,553,320.00
60,902,893.64

m2 29,015.00 319,372.46
m' 40,621.00 406,474.04
m' 158,755.51 1,588,586.97
m2 75,439.00 1,374,988.93
m2 75,439.00 1,374,988.93
HARGA SATUAN JUMLAH
SAT ( Rp ) ( Rp )

m2 250,000.00 2,501,625.00 Perubahan spesifikasi matrial

m' 2,011,994.38 8,782,355.48

m' 2,011,994.38 6,237,182.58


unit 1,706,082.00 1,706,082.00

unit 1,323,084.00 1,323,084.00

unit 1,160,600.00 6,963,600.00


32,578,340.40

m2 36,750.00 1,109,390.63 Perubahan Harga Satuan


m2 398,177.78 11,945,333.33 150000
m2 125,000.00 669,375.00
m2 1,083,136.89 10,736,052.90
m2 20,000.00 70,350.00 Perubahan Harga Satuan
m2 15,750.00 248,062.50
m' 1,079,935.40 2,437,954.16
m2 99,522.61 972,883.28
m2 65,429.87 1,279,219.47
m2 52,500.00 1,026,427.50 Perubahan Harga Satuan
m' 55,000.00 311,850.00 matral existing hanya pemasangan
unit 2,160,000.00 2,160,000.00
m' 94,500.00 535,815.00 Perubahan Harga Satuan
33,502,713.76

m2 36,750.00 506,653.88 Perubahan Harga Satuan


unit 577,500.00 577,500.00
m2 20,000.00 198,450.00 Perubahan Harga Satuan
unit 98,651.00 394,604.00
unit 58,030.00 116,060.00
unit 500,000.00 500,000.00 Perubahan Harga Satuan
m' 29,015.00 812,420.00
m2 383,869.60 8,445,131.14 Perubahan volume
m2 99,522.61 852,709.73
m2 99,522.61 1,037,672.50
m2 110,000.00 1,836,450.00 Perubahan Harga Satuan

titik 1,769,915.00 3,539,830.00


unit 435,225.00 870,450.00
m2 226,317.00 3,778,362.32
m2 336,956.13 3,513,273.06
m2 1,155,374.40 14,268,873.82 Perubahan Volume
m2 68,250.00 842,887.50
HARGA SATUAN JUMLAH
SAT ( Rp ) ( Rp )
m2 250,000.00 9,187,000.00 Perubahan spesifikasi matrial
unit 3,468,310.00 6,936,620.00
unit 3,597,860.00 7,195,720.00
unit 650,000.00 1,300,000.00
m' 55,000.00 814,275.00 Matrial existing
m2 1,305,675.00 5,758,026.75
m' 104,454.00 1,546,441.47
m2 162,484.00 1,433,108.88

set 450,000.00 1,350,000.00 Perubahan Harga Satuan


psg 35,000.00 105,000.00
psg 390,000.00 1,170,000.00
78,887,520.04

titik 226,143.75 1,583,006.25 Perubahan Harga Satuan


titik 226,143.75 904,575.00 Perubahan Harga Satuan
titik 226,143.75 1,809,150.00
titik 226,144.75 1,356,868.50
titik 275,100.00 3,026,100.00 Perubahan Harga Satuan
titik 281,426.25 9,005,640.00 Perubahan Harga Satuan
titik 288,776.25 3,465,315.00 Perubahan Harga Satuan
titik 281,426.25 1,688,557.50 Perubahan Harga Satuan
m' 61,425.00 3,071,250.00 Perubahan Harga Satuan

titik 85,575.00 427,875.00 Perubahan Harga Satuan


titik 91,350.00 274,050.00 Perubahan Harga Satuan
titik 105,000.00 3,360,000.00 Perubahan Harga Satuan
titik 210,000.00 2,520,000.00 Perubahan Harga Satuan
titik 415,000.00 2,490,000.00 Perubahan Harga Satuan
titik 675,000.00 2,700,000.00
titik 415,000.00 3,320,000.00
titik 295,100.00 3,246,100.00
titik 204,750.00 1,638,000.00 Perubahan Harga Satuan
unit 1,480,500.00 2,961,000.00 Box Matrial existing
titik 96,000.00 576,000.00
titik 985,000.00 5,910,000.00

m' 132,365.63 3,706,237.50 Perubahan Harga Satuan


m' 132,365.63 529,462.50 Perubahan Harga Satuan
m' 73,565.63 1,765,575.00 Perubahan Harga Satuan
m' 96,022.50 2,688,630.00 Perubahan Harga Satuan
m' 73,565.63 2,059,837.50 Perubahan Harga Satuan
m' 55,387.50 443,100.00 Perubahan Harga Satuan
m' 45,858.75 1,100,610.00 Perubahan Harga Satuan

67,626,939.75
HARGA SATUAN JUMLAH
SAT ( Rp ) ( Rp )

423,605,600.02

423,600,000.00

Sanur, 04 Mei 2018


Dibuat oleh :
PT. WISMAKARMA ALAM KARYA

A A Ngr. Arya Putra Damar, ST


Direktur Utama
al uk. 30 x 30 cm
9,425,000.00
776,900,000.00
PEKERJAAN TAMBAHAN OOPS RESTAURANT UBUD

NO PEKERJAAN VOLUME SATUAN

I. ELECTRICAL
1 LAMPU RESTO BESAR EXC. INSTALASI 3 PCS
2 LAMPU RESTO KECIL EXC. INSTALASI 6 PCS
3 LAMPU TERAS EXC. INSTALASI 6 PCS
4 LAMPU SPOTLIGHT RESTO EXC. INSTALASI 5 PCS
5 LAMPU KOLOM RESTO EXC. INSTALASI 4 PCS
6 LAMPU SPOTLIGHT TERAS DEPAN 11 PCS
7 BOHLAM + FITTING + INSTALASI BARU 15 PCS
8 LAMPU COUNTER EXC. INSTALASI 8 PCS
9 LAMPU SPOTLIGHT GARDEN 2 PCS
10 LAMPU GANTUNG GARDEN (EKSISTING) 3 PCS
11 LAMPU SPOTLIGHT TOILET 6 PCS
12 LAMPU TOILET CEWEK 2 PCS
13 STOP KONTAK RESTO dan bar 44 PCS
14 SAKLAR DOUBLE 5 PCS
15 LED STRIP BAR 15 M'
16 LED STRIP BAR 3 M'
17 LAMPU KITCHEN (MATERIAL EKSISTING) 6 PCS
18 PEK. PEMINDAHAN PANEL RESTO 1 PCS
19 PEK. INSTALASI ULANG LISTRIK LT.2
20 STOP KONTAK CCTV 16 TITIK
21 STOP KONTAK OUTBOW GARDEN 1 PCS
22 SAKLAR OUTBOW GARDEN DAN TOILET 2 PCS
23 STOP KONTAK KIPAS RESTO 5 PCS
24 SPOT LIGHT KANOPI LT. 2 3 PCS

II. ARSITEKTURAL
1 PEK. TEXTURE KOLOM 56 M2
2 PEK. TEXTURE TERAS BELAKANG
3 PEK. CAT TEXTURE TERAS BLKG
4 PEK. TEXTURE DINDING TERAS DEPAN 3 M2
5 PEK. CAT DINDING PATUNG BUDDHA 2 M2
6 PEK. TEXTURE PLANTER BOX (LUAR+DALAM)
7 PEK. PENUTUP BAK KONTROL PLAT BESI
8 PEK. PENUTUP ATAP ALDERON RUANG GAS 3.75 M2
9 PEK. DINDING RUANG GAS 6.125 M2
10 PEK. CAT DINDING RUANG GAS EX. VINILEX 12.25 M2
11 PEK. PANEL KAYU COUNTER TABLE RESTO 12 M'
12 PINTU BESI GARDEN 1 PCS
13 TEMPAT TISU TOILET 3 PCS
14 PAS. KANOPI TERAS LT. 2 12 M2
15 PAS. ALDERON KANOPI LT. 2 12 M2
16 CAT DINDING LUAR LT. 2 LS
17 PEK. PAS. DINDING KALSIBOARD 2 M2
18 PEK. SERVICE ATAP GYPSUM LS

III. PLUMBING
1 PEK. MAIN LIPE PIPA BARU 60 M'
2 PAS. POMPA PRESSURE SIMIZU 1 PCS
3 CLOSET AMERICAN STANDARD 2 PCS
HARGA KETERANGAN

2,600,000.00 TDK TERMASUK BOHLAM, FITTING, TALI SELING, INSTALASI


500,000.00 TDK TERMASUK BOHLAM, FITTING, TALI SELING, INSTALASI
225,000.00 TDK TERMASUK BOHLAM, FITTING, INSTALASI

300,000.00 TDK TERMASUK BOHLAM, FITTING, INSTALASI

225,000.00 TDK TERMASUK BOHLAM, FITTING, INSTALASI

BOHLAM BARU

400,000.00 TDK TERMASUK BOHLAM, FITTING, INSTALASI

BOHLAM BARU

MATERIAL BARU

HARGA DI PAK DAMAR

PAPAN KAYU TEBAL 3.5 CM


HARGA DI PAK DAMAR
BELUM TERPASANG
MATERIAL EKSISTING

700,000.00
1,800,000.00 TOILET CEWEK
General Contractor - Architectural - Interior

Jl. Tk Balian 104, Renon - Denpasar - Bali


Ph : 0361-223371 Fax : 0361-244582

RENCANA ANGGARAN BIAYA


Proyek : Renovasi Restorant OOPS
Lokasi : Jl. Raya Ubud, Gianyar
Tahun : 2018

HARGA SATUAN JUMLAH


NO Description QTY ( Rp ) ( Rp )

1 Pekerjaan Awal (Tahap 1) 1 325,500,000.00 423,600,000.00


2 Pekerjaan Tambahan (Tahap 2) 1 214,600,000.00 382,600,000.00

TOTAL 806,200,000.00