PERKIRAAN KEUNTUNGAN

PROYEK : RUMAH BERSUBSIDI BUKIT INDAH HA


KELURAHAN : TANI AMAN - LAO JANAN ILIR SAM

NO URAIAN QTY UNIT


UNIT PRICE (Rp)TOTAL PRICE
I TRIWULAN KE - I SEBANYAK 240 UNIT RUMAH
A HARGA JUAL RUMAH
Penjualan 240 Unit Rumah 240.00 Unit ### 32,400,000,

TOTAL PENJUALAN
B PENGELUARAN
1. Biaya Pembangunan Rumah All In 24240.00 Unit ### 24,436,319,
2. Pembuatan Jalan Masuk 1.00 Ls ### 1,600,000,
3. Peralatan Kantor 1.00 Ls 26,000,000.00 26,000,
4. Pengeluaran Rutin Tipa Bulan 3.00 Bln 61,000,000.00 183,000,

TOTAL PENGELUARAN
C KEUNTUNGAN TRIWULAN PERTAMA
( Rp. 32.400.000.000 - Rp. 26.245.319.040) 6,154,680,

TOTAL KEUNTUNGAN TRIWULAN PERTAMA 6,154,680,9

II TRIWULAN KE - II SAMPAI DENGAN KE - TERAKHIR DENGAN TARGET 24


A HARGA JUAL RUMAH
Penjualan 240 Unit Rumah 240.00 Unit ### 32,400,000,

TOTAL PENJUALAN
B PENGELUARAN
1. Biaya Pembangunan Rumah All In 24240.00 Unit ### 24,436,319,
2. Pengeluaran Rutin Tipa Bulan 3.00 Bln 61,000,000.00 183,000,

TOTAL PENGELUARAN
C KEUNTUNGAN TRIWULAN PERTAMA
( Rp. 32.400.000.000 - Rp. 26.245.319.040) 7,780,680,

TOTAL KEUNTUNGAN TRIWULAN PERTAMA 7,780,680,9


PERKIRAAN KEUNTUNGAN
PROYEK : RUMAH BERSUBSIDI BUKIT INDAH HA
KELURAHAN : TANI AMAN - LAO JANAN ILIR SAM

NO URAIAN QTY UNIT


UNIT PRICE (Rp)TOTAL PRICE
AAN KEUNTUNGAN
RUMAH BERSUBSIDI BUKIT INDAH HARMONI
N : TANI AMAN - LAO JANAN ILIR SAMARINDA

TOTAL PRICE (Rp) REMARKS

32,400,000,000.00

###

24,436,319,040.00
1,600,000,000.00
26,000,000.00
183,000,000.00

###

6,154,680,960.00

6,154,680,960.00

32,400,000,000.00

###

24,436,319,040.00
183,000,000.00

###

7,780,680,960.00

7,780,680,960.00

Bontang, 02 Janu
Hormat Kami
AAN KEUNTUNGAN
RUMAH BERSUBSIDI BUKIT INDAH HARMONI
N : TANI AMAN - LAO JANAN ILIR SAMARINDA

TOTAL PRICE (Rp) REMARKS

Zul Rahmat
Estimator
RINCIAN PENGELUARAN
NON FISIK BANGUNAN

NO URAIAN VOL UNITHARGA SATUAN


I PERALATAN KANTOR
1. Meja Kantor 5.00 Unit 500,000
2. Laptop 3.00 Unit 5,000,000
3. Printer 2.00 Unit 2,000,000
4. Pasang Lampu PLN 1.00 Ls 4,500,000

II PENGELUARAN RUTIN TIAP BULAN


1. Sewa 1 Unit Mobil AVANZA 1.00 Unit 6,000,000
2. BBM 1.00 Ls 2,000,000
3. Gaji Karyawan
a. Project Manager 1.00 Org 7,500,000
b. Supervisor 1.00 Org 5,000,000
c. Keuangan 1.00 Org 4,000,000
d. Administrasi 1.00 Org 3,000,000
e. Purchasing 1.00 Org 3,000,000
f. Pergudangan 1.00 Org 3,000,000
g. SATPAM 6.00 Org 3,000,000
h. Humas 1.00 Org 3,500,000
i. Operation Kantor 1.00 Org 5,000,000

Bontang, 02
Hormat Kam

Zul Rahmat
Estimator
N PENGELUARAN
K BANGUNAN

JUMLAH/BLN

Rp 2,500,000
Rp 15,000,000
Rp 4,000,000
Rp 4,500,000

Rp 26,000,000

Rp 6,000,000
Rp 3,000,000

Rp 7,500,000
Rp 5,000,000
Rp 4,000,000
Rp 3,000,000
Rp 3,000,000
Rp 3,000,000
Rp 18,000,000
Rp 3,500,000
Rp 5,000,000

Rp 61,000,000

Bontang, 02 Januari 2018


Hormat Kami

Zul Rahmat
Estimator
RENCANA PENGGUNAAN MODAL

NO URAIAN VOL UNITHARGA SATUAN

1. Biaya Pembuatan Jalan Masuk Proyek ± 1 KM 1.00 Ls ###


2. Inventaris Kantor 1.00 Ls 26,000,000
3. Pengeluaran Rutin 3 Bulan Awal 3.00 Bln 61,000,000
4 Modal Pembangunan 240 Unit Pertama 240.00 Unit 101,817,996

Bontang, 02
Hormat Kam

Zul Rahmat
Estimator
ANA PENGGUNAAN MODAL

JUMLAH/BLN

Rp1,600,000,000
Rp 26,000,000
Rp 183,000,000
###

###

Bontang, 02 Januari 2018


Hormat Kami

Zul Rahmat
Estimator
7,780,680,960.00 9 70,026,128,640
6,154,680,960.00 1 6,154,680,960

76,180,809,600
7,618,080,960