BILL OF QUANTITY / B.O.

Q
TAHUN ANGGARAN 2018

PROYEK
PERENCANAAN PEMBANGUNAN GEDUNG - D
DI AREA PERKANTORAN BADAN POM
Jl. PERCETAKAN NEGARA No. 23,
Kec. JOHAR BARU, JAKARTA PUSAT

PEKERJAAN :
PERSIAPAN,STRUKTUR,ARSITEKTUR & MEP

Disiapkan oleh :

GEDUNG ARKONIN, Jl. Bintaro Taman Timur, Bintaro Jaya - Jakarta Selatan 12330
Telp : 021 736.4176 Fax : 021 736.3829 E-mail : Arkonin@indo.net.id
Home Page : www.arkonin-id.com
BILL OF QUANTITY / B.O.Q
PROYEK : PERENCANAAN PEMBANGUNAN GEDUNG - D DI AREA PERKANTORAN BADAN POM
Jl. PERCETAKAN NEGARA No. 23 Kec. JOHAR BARU, JAKARTA PUSAT
PEKERJAAN : REKAP UTAMA

REKAPITULASI UTAMA
NO URAIAN PEKERJAAN TOTAL

<1> PEKERJAAN PERSIAPAN Rp. 807,344,931.15

<2> PEKERJAAN BANGUNAN GEDUNG D BPOM Rp. 72,204,483,215.92

<3> PEKERJAAN GWT & STP Rp. 1,056,563,816.07

SUB TOTAL ( a ) Rp. 74,068,391,963.14

PPN 10% Rp. 7,406,839,196.31

SUB TOTAL ( b ) Rp. 81,475,231,159.46

<3> PEKERJAAN PENYAMBUNGAN DAYA PLN 1500 KVA Rp. 1,687,500,000.00

<4> PEKERJAAN PENYAMBUNGAN TELEPON Rp. 25,000,000.00

<5> PEKERJAAN PENYAMBUNGAN PDAM Rp. 25,000,000.00

TOTAL BIAYA Rp. 83,212,731,159.46

PEMBULATAN Rp. 83,212,731,000.00

Jakarta, OKTOBER 2018

REKAPITULASI
BILL OF QUANTITY / B.O.Q
PROYEK : PERENCANAAN PEMBANGUNAN GEDUNG - D DI AREA PERKANTORAN BADAN POM
Jl. PERCETAKAN NEGARA No. 23 Kec. JOHAR BARU, JAKARTA PUSAT
PEKERJAAN : PERSIAPAN

HARGA
NO URAIAN PEKERJAAN SAT VOLUME JUMLAH (Rp)
SATUAN (Rp)

<1> PEKERJAAN PERSIAPAN

1 Pekerjaan Pengukuran Site m² 1,066.70 41,679.00 44,458,989.30


2 Papan Nama Proyek bh 1.00 2,500,000.00 2,500,000.00
3 Foto Proyek 3 phase, 5 set set 1.00 7,500,000.00 7,500,000.00
4 Kantor Direksikeet ( uk. 7 x 5 m ) m² 35.00 945,879.00 33,105,765.00
5 Bedeng Pekerja ( uk. 4 x 8 m ) m² 32.00 873,510.00 27,952,320.00
6 Administrasi dan Dokumentasi ls 1.00 5,000,000.00 5,000,000.00
Pekerjaan Pembuatan Gudang Semen Dan Peralatan ( uk. 4 x 7 m )
7 Material Penutup Dinding Triplek, Rangka Kayu, Penutup Atap Seng m² 28.00 674,327.50 18,881,170.00
Gelombang BJLS 30 lengkap Daun pintu dan jendela, Lantai dll
Instalasi Listrik Kerja Dengan Penyambungan Daya Sementara atau
8 Lot 1.00 7,500,000.00 7,500,000.00
sewa genset
Air Kerja, (pompa jet pump, tangki air 500 liter, menara tangki,
9 Lot 1.00 7,500,000.00 7,500,000.00
instalasi dll)
Sewa Mobile Cran 1 unit, Kap. 40 meter Boom Panjang Hydraulic
10 bln 8.00 50,000,000.00 400,000,000.00
Truck Crane, 30 Ton Hydraulic Boom Derek,
11 Asuransi CAR & TPL Lot 1.00 50,000,000.00 50,000,000.00
Bak Cuci ban mobil proyek keluar (termasuk fasilitas cuci ban mobil
12 Lot 1.00 5,000,000.00 5,000,000.00
proyek keluar)
13 Pekerjaan K 3 dan P3K Lot 1.00 15,000,000.00 15,000,000.00
14 Mobilisasi & Demobilisasi Peralatan Bored Pile Lot 1.00 150,000,000.00 150,000,000.00
Pagar Proyek Sementara Tinggi 195 cm, Dari seng Gelombang BJLS
30, Rangka Hollow Tiang 50/50, Horizontal & Vertkal Tambahan
15 m' 186.85 170,841.00 31,921,640.85
30/30 Lengkap Stud penguat Tiang setiap 6 m hollow 50/50 +
Pondasi Beton setempat
Pintu Pagar Tinggi 195 cm x 300 cm, Dari seng Gelombang BJLS 30,
16 Rangka Hollow Tiang 100/50, Rangka Daun Pintu hollow 40/60 + unit 2.00 512,523.00 1,025,046.00
40/40 Lengkap Ensel, Pengunci dan Pondasi Beton Setempat
SUB TOTAL PEKERJAAN PERSIAPAN <1> 807,344,931.15

PEK. PERSIAPAN
BILL OF QUANTITY / B.O.Q
PROYEK : PERENCANAAN PEMBANGUNAN GEDUNG - D DI AREA PERKANTORAN BADAN POM
Jl. PERCETAKAN NEGARA No. 23 Kec. JOHAR BARU, JAKARTA PUSAT
PEKERJAAN : SUB REKAP

SUB REKAPITULASI
NO URAIAN PEKERJAAN TOTAL

<2> GEDUNG - D BPOM

<2.1> PEKERJAAN STRUKTUR Rp. 28,110,989,181.78

<2.2> PEKERJAAN ARSITEKTUR Rp. 19,940,129,094.79

<2.3> PEKERJAAN MEKANIKAL Rp. 12,977,298,375.75

<2.4> PEKERJAAN ELEKTRIKAL Rp. 11,176,066,563.60

SUB TOTAL Rp. 72,204,483,215.92

SUB REKAP GEDUNG BPOM


BILL OF QUANTITY / B.O.Q
PROYEK : PERENCANAAN PEMBANGUNAN GEDUNG - D DI AREA PERKANTORAN BADAN POM
Jl. PERCETAKAN NEGARA No. 23 Kec. JOHAR BARU, JAKARTA PUSAT
PEKERJAAN : STRUKTUR

REKAPITULASI UTAMA
PEKERJAAN STRUKTUR GEDUNG D

I PEKERJAAN STRUKTUR
A PEKERJAAN BORED PILE Rp. 6,682,894,810.91
B PEKERJAAN STRUKTUR BAWAH Rp. 2,607,638,225.83
C PEKERJAAN STRUKTUR ATAS Rp. 18,489,107,279.26
C.1 LANTAI GROUND Rp. 1,928,110,494.56
C,2 LANTAI MEZZANINE Rp. 1,066,606,112.70
C,3 LANTAI 2 Rp. 2,018,362,123.63
C,4 LANTAI 3 Rp. 2,041,750,582.17
C,5 LANTAI 4 Rp. 2,018,362,123.63
C,6 LANTAI 5 Rp. 1,955,015,385.73
C,7 LANTAI 6 Rp. 1,955,015,385.73
C,8 LANTAI 7 Rp. 1,977,301,681.64
C,9 LANTAI 8 Rp. 1,889,476,445.37
C,10 LANTAI TRIBUN Rp. 836,024,877.86
C,11 LANTAI ATAP DAK Rp. 803,082,066.25
D RANGKA ATAP BAJA Rp. 331,348,865.78

SUB TOTAL Rp. 28,110,989,181.78

PEK. STR G. BPOM Page 5


BILL OF QUANTITY / B.O.Q
PROYEK : PERENCANAAN PEMBANGUNAN GEDUNG - D DI AREA PERKANTORAN BADAN POM
Jl. PERCETAKAN NEGARA No. 23 Kec. JOHAR BARU, JAKARTA PUSAT
PEKERJAAN : STRUKTUR

HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME JUMLAH (Rp)
(Rp)

<2> PEKERJAAN STRUKTUR GEDUNG D

I PEKERJAAN STRUKTUR

A PEKERJAAN BORED PILE


1 Pengeboran, Pabrikasi Besi Tulangan dan Pengecoran Bored Pile Diameter 80 cm
- Pengeboran kedalaman 12 M m' 2,826.00 375,000.00 1,059,750,000.00
- Perbaikan permukaan tanah , dengan Bentonate m' 2,826.00 25,000.00 70,650,000.00
- Pengadaan, Pembuatan Keranjang besi & Handling kg 181,134.37 20,586.98 3,729,008,746.83
- Pengadaan dan pengecoran Beton Mutu 'Fc = 33,2 Mpa m3 1,419.78 1,275,267.32 1,810,599,035.59
- Bobokan Kepala Bored Pile m3 39.44 125,000.00 4,929,800.00
2 Buang tanah / Lumpur bekas pengeboran ttk 157.00 40,507.50 6,359,677.50
3 Buang Bekas Bobokan Kepala Bored Pile m3 39.44 40,507.50 1,597,550.99
SUB TOTAL PEKERJAAN BORED PILE A 6,682,894,810.91

B PEKERJAAN STRUKTUR BAWAH


1 Pasang Bauwplank m' 186.80 41,679.00 7,785,637.20
2 Galian tanah pondasi, Sloof, Dinding beton, dll m3 1,316.50 56,925.00 74,941,785.27
3 Pemadatan tanah bawah Pondasi m2 1,038.10 66,550.00 69,085,555.00
4 Urug tanah kembali bekas galian m3 355.80 42,900.00 15,263,729.91
5 Buang tanah bekas galian keluar lokasi m3 960.70 40,507.50 38,915,656.52
6 Urug pasir padat tebal 7 cm, bawah pondasi m3 72.67 142,560.00 10,359,407.52
7 Beton Lantai Kerja tebal 5 cm m3 51.71 687,867.23 35,568,582.66
8 Beton Pile cap :
a Type PC-2
- Beton Mutu 'Fc = 29,5 Mpa m3 12.80 1,206,627.32 15,444,829.70
- Pembesian kg 2,044.15 13,086.98 26,751,692.83
- Bekisting m2 22.40 152,473.75 3,415,412.00
b Type PC-4
- Beton Mutu 'Fc = 29,5 Mpa m3 64.00 1,206,627.32 77,224,148.48
- Pembesian kg 7,900.10 13,086.98 103,388,421.67
- Bekisting m2 64.00 152,473.75 9,758,320.00
c Type PC-5
- Beton Mutu 'Fc = 29,5 Mpa m3 240.00 1,206,627.32 289,590,556.80
- Pembesian kg 27,640.36 13,086.98 361,728,735.21
- Bekisting m2 192.00 152,473.75 29,274,960.00
d Type PC-6
- Beton Mutu 'Fc = 29,5 Mpa m3 307.20 1,206,627.32 370,675,912.70
- Pembesian kg 35,206.77 13,086.98 460,750,110.10
- Bekisting m2 249.60 152,473.75 38,057,448.00
e Type PC-15
- Beton Mutu 'Fc = 29,5 Mpa m3 86.02 1,206,627.32 103,789,255.56
- Pembesian kg 8,070.92 13,086.98 105,623,877.66
- Bekisting m2 42.24 152,473.75 6,440,491.20
f Type PC-19
- Beton Mutu 'Fc = 29,5 Mpa m3 110.02 1,206,627.32 132,748,311.24
- Pembesian kg 11,120.64 13,086.98 145,535,514.11
- Bekisting m2 63.84 152,473.75 9,733,924.20
g Type Pondasi Genset
- Beton Mutu 'Fc = 29,5 Mpa m3 11.06 1,206,627.32 13,339,265.02
- Pembesian kg 2,040.82 13,086.98 26,708,131.09
- Bekisting m2 9.95 152,473.75 1,517,113.81
9 Beton Balok Sloof Type BS :
- Beton Mutu 'Fc = 29,5 Mpa m3 5.24 1,206,627.32 6,322,727.16
- Pembesian kg 1,021.33 13,086.98 13,366,058.52
- Bekisting m2 24.37 186,023.75 4,532,654.69
SUB TOTAL PEKERJAAN STRUKTUR BAWAH B 2,607,638,225.83

PEK. STR G. BPOM Page 6


HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME JUMLAH (Rp)
(Rp)

C PEKERJAAN STRUKTUR ATAS


C.1 LANTAI GROUND
1 Beton Balok :
a Type B 1
- Beton Mutu 'Fc = 29,5 Mpa m3 21.49 1,206,627.32 25,927,042.55
- Pembesian kg 3,346.21 13,086.98 43,791,788.94
- Bekisting m2 119.71 241,870.75 28,955,411.71
b Type B 2
- Beton Mutu 'Fc = 29,5 Mpa m3 26.26 1,206,627.32 31,690,859.93
- Pembesian kg 4,513.22 13,086.98 59,064,453.65
- Bekisting m2 146.33 241,870.75 35,392,463.11
c Type B 3
- Beton Mutu 'Fc = 29,5 Mpa m3 19.37 1,206,627.32 23,374,543.12
- Pembesian kg 3,388.11 13,086.98 44,340,175.27
- Bekisting m2 107.93 241,870.75 26,104,771.43
d Type B 4
- Beton Mutu 'Fc = 29,5 Mpa m3 8.24 1,206,627.32 9,946,470.32
- Pembesian kg 1,281.02 13,086.98 16,764,618.52
- Bekisting m2 45.93 241,870.75 11,108,252.81
e Type B 5
- Beton Mutu 'Fc = 29,5 Mpa m3 0.81 1,206,627.32 976,402.83
- Pembesian kg 109.08 13,086.98 1,427,524.27
- Bekisting m2 4.51 241,870.75 1,090,450.09
f Type B 6
- Beton Mutu 'Fc = 29,5 Mpa m3 3.30 1,206,627.32 3,983,318.11
- Pembesian kg 651.19 13,086.98 8,522,127.03
- Bekisting m2 22.95 241,870.75 5,551,223.96
g Type B 9
- Beton Mutu 'Fc = 29,5 Mpa m3 1.15 1,206,627.32 1,388,586.72
- Pembesian kg 195.06 13,086.98 2,552,771.39
- Bekisting m2 6.41 241,870.75 1,550,778.50
h Type B 10
- Beton Mutu 'Fc = 29,5 Mpa m3 0.62 1,206,627.32 747,505.62
- Pembesian kg 122.32 13,086.98 1,600,773.45
- Bekisting m2 4.31 241,870.75 1,041,737.32
i Type B a1
- Beton Mutu 'Fc = 29,5 Mpa m3 11.72 1,206,627.32 14,135,639.05
- Pembesian kg 2,342.25 13,086.98 30,652,969.95
- Bekisting m2 82.79 241,870.75 20,023,511.91
j Type B a2
- Beton Mutu 'Fc = 29,5 Mpa m3 10.28 1,206,627.32 12,398,095.71
- Pembesian kg 1,936.11 13,086.98 25,337,866.44
- Bekisting m2 72.61 241,870.75 17,562,235.16
k Type B a3
- Beton Mutu 'Fc = 29,5 Mpa m3 6.97 1,206,627.32 8,412,605.68
- Pembesian kg 1,545.52 13,086.98 20,226,228.86
- Bekisting m2 49.27 241,870.75 11,916,681.61
l Type B a4
- Beton Mutu 'Fc = 29,5 Mpa m3 0.85 1,206,627.32 1,022,616.65
- Pembesian kg 148.81 13,086.98 1,947,527.75
- Bekisting m2 5.99 241,870.75 1,448,563.92
m Type B a5
- Beton Mutu 'Fc = 29,5 Mpa m3 1.83 1,206,627.32 2,204,508.11
- Pembesian kg 382.98 13,086.98 5,012,082.49
- Bekisting m2 12.91 241,870.75 3,122,744.88
n Type B c1
- Beton Mutu 'Fc = 29,5 Mpa m3 3.41 1,206,627.32 4,115,081.81
- Pembesian kg 599.92 13,086.98 7,851,192.71
- Bekisting m2 19.00 241,870.75 4,595,737.75

PEK. STR G. BPOM Page 7


HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME JUMLAH (Rp)
(Rp)
2 Beton Kolom :
a Type K 1
- Beton Mutu 'Fc = 29,5 Mpa m3 104.16 1,206,627.32 125,682,301.65
- Pembesian kg 17,768.56 13,086.98 232,536,637.69
- Bekisting m2 260.40 210,273.25 54,755,154.30
b Type K 2
- Beton Mutu 'Fc = 29,5 Mpa m3 1.89 1,206,627.32 2,280,525.63
- Pembesian kg 375.72 13,086.98 4,917,013.12
- Bekisting m2 9.89 210,273.25 2,079,812.72
3 Beton Retaining Wall :
a Type W 1
- Beton Mutu 'Fc = 29,5 Mpa m3 10.55 1,206,627.32 12,732,934.79
- Pembesian kg 1,371.50 13,086.98 17,948,742.25
- Bekisting m2 70.35 292,685.25 20,590,407.34
b Type W 2
- Beton Mutu 'Fc = 29,5 Mpa m3 46.12 1,206,627.32 55,644,825.49
- Pembesian kg 5,974.07 13,086.98 78,182,545.31
- Bekisting m2 307.44 292,685.25 89,983,153.26
c Type W 3
- Beton Mutu 'Fc = 29,5 Mpa m3 19.09 1,206,627.32 23,033,308.91
- Pembesian kg 2,614.38 13,086.98 34,214,381.59
- Bekisting m2 127.26 292,685.25 37,247,124.92
d Type W 4
- Beton Mutu 'Fc = 29,5 Mpa m3 10.08 1,206,627.32 12,162,803.39
- Pembesian kg 1,317.89 13,086.98 17,247,224.98
- Bekisting m2 67.20 292,685.25 19,668,448.80
3 Beton Plat Lantai :
a Type Plat S1
- Beton Mutu 'Fc = 29,5 Mpa m3 83.72 1,206,627.32 101,018,619.62
- Pembesian kg 7,396.77 13,086.98 96,801,341.01
- Bekisting m2 644.00 268,105.75 172,659,727.65
b Type Plat S2
- Beton Mutu 'Fc = 29,5 Mpa m3 16.35 1,206,627.32 19,733,496.91
- Pembesian kg 1,444.92 13,086.98 18,909,672.01
- Bekisting m2 125.80 268,105.75 33,728,239.56
4 Tangga Beton :
4.1 Type Tangga Shaft Kebakaran #1 (as 3 / A'-B) :
a Type Balok Tangga
- Beton Mutu 'Fc = 29,5 Mpa m3 0.15 1,206,627.32 181,899.07
- Pembesian kg 29.64 13,086.98 387,930.13
- Bekisting m2 1.71 278,925.63 476,544.44
b Type Plat Tangga dan Anak Tangga
- Beton Mutu 'Fc = 29,5 Mpa m3 2.81 1,206,627.32 3,391,557.91
- Pembesian kg 259.91 13,086.98 3,401,457.16
- Bekisting m2 30.14 278,925.63 8,407,738.94
4.2 Type Tangga Shaft Kebakaran #2 (as 6' / C'-D) :
a Type Balok Tangga
- Beton Mutu 'Fc = 29,5 Mpa m3 0.14 1,206,627.32 172,668.37
- Pembesian kg 28.30 13,086.98 370,421.07
- Bekisting m2 1.62 278,925.63 452,361.59
b Type Plat Tangga dan Anak Tangga
- Beton Mutu 'Fc = 29,5 Mpa m3 2.34 1,206,627.32 2,824,394.80
- Pembesian kg 208.48 13,086.98 2,728,309.77
- Bekisting m2 27.01 278,925.63 7,533,697.59
4.3 Type Tangga Lantai Mezzanine :
a Type Balok Tangga
- Beton Mutu 'Fc = 29,5 Mpa m3 0.31 1,206,627.32 369,227.96
- Pembesian kg 60.07 13,086.98 786,159.72
- Bekisting m2 3.47 278,925.63 967,314.08
b Type Plat Tangga dan Anak Tangga
- Beton Mutu 'Fc = 29,5 Mpa m3 6.00 1,206,627.32 7,243,021.81
- Pembesian kg 490.69 13,086.98 6,421,640.98
- Bekisting m2 69.39 278,925.63 19,355,765.17
SUB TOTAL LANTAI GROUND C.1 1,928,110,494.56

PEK. STR G. BPOM Page 8


HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME JUMLAH (Rp)
(Rp)

C,2 LANTAI MEZZANINE


1 Beton Balok :
a Type B 1
- Beton Mutu 'Fc = 29,5 Mpa m3 16.12 1,206,627.32 19,445,281.91
- Pembesian kg 2,509.66 13,086.98 32,843,841.70
- Bekisting m2 89.79 241,870.75 21,716,558.79
b Type B 2
- Beton Mutu 'Fc = 29,5 Mpa m3 15.01 1,206,627.32 18,109,062.82
- Pembesian kg 2,578.99 13,086.98 33,751,116.37
- Bekisting m2 83.62 241,870.75 20,224,264.63
c Type B 3
- Beton Mutu 'Fc = 29,5 Mpa m3 1.62 1,206,627.32 1,959,562.77
- Pembesian kg 284.04 13,086.98 3,717,178.82
- Bekisting m2 9.05 241,870.75 2,188,446.55
d Type B 4 1.00
- Beton Mutu 'Fc = 29,5 Mpa m3 3.16 1,206,627.32 3,817,768.84
- Pembesian kg 472.70 13,086.98 6,186,161.47
- Bekisting m2 17.63 241,870.75 4,263,697.58
e Type B 6 1.00
- Beton Mutu 'Fc = 29,5 Mpa m3 0.79 1,206,627.32 950,219.01
- Pembesian kg 151.98 13,086.98 1,988,974.26
- Bekisting m2 5.48 241,870.75 1,324,242.36
f Type B 7 1.00
- Beton Mutu 'Fc = 29,5 Mpa m3 2.90 1,206,627.32 3,496,805.97
- Pembesian kg 412.19 13,086.98 5,394,259.50
- Bekisting m2 16.15 241,870.75 3,905,245.13
g Type B 8
- Beton Mutu 'Fc = 29,5 Mpa m3 5.22 1,206,627.32 6,296,784.67
- Pembesian kg 749.26 13,086.98 9,805,563.78
- Bekisting m2 32.16 241,870.75 7,779,288.93
h Type B 10
- Beton Mutu 'Fc = 29,5 Mpa m3 0.72 1,206,627.32 874,201.49
- Pembesian kg 143.05 13,086.98 1,872,090.98
- Bekisting m2 5.04 241,870.75 1,218,302.97
i Type B a1
- Beton Mutu 'Fc = 29,5 Mpa m3 3.20 1,206,627.32 3,855,174.29
- Pembesian kg 638.80 13,086.98 8,359,900.90
- Bekisting m2 22.58 241,870.75 5,460,957.79
j Type B a2
- Beton Mutu 'Fc = 29,5 Mpa m3 3.08 1,206,627.32 3,719,428.71
- Pembesian kg 581.11 13,086.98 7,605,032.35
- Bekisting m2 21.78 241,870.75 5,268,670.55
k Type B a5
- Beton Mutu 'Fc = 29,5 Mpa m3 0.92 1,206,627.32 1,109,493.82
- Pembesian kg 179.80 13,086.98 2,353,022.60
- Bekisting m2 6.50 241,870.75 1,571,627.76
l Type B a6
- Beton Mutu 'Fc = 29,5 Mpa m3 2.20 1,206,627.32 2,649,753.59
- Pembesian kg 394.47 13,086.98 5,162,358.61
- Bekisting m2 15.52 241,870.75 3,753,447.05
m Type B c1
- Beton Mutu 'Fc = 29,5 Mpa m3 0.94 1,206,627.32 1,138,573.54
- Pembesian kg 154.92 13,086.98 2,027,452.52
- Bekisting m2 5.26 241,870.75 1,271,562.91
2 Beton Plat Lantai Type S1 :
- Beton Mutu 'Fc = 29,5 Mpa m3 37.75 1,206,627.32 45,551,025.97
- Pembesian kg 3,335.33 13,086.98 43,649,382.80
- Bekisting m2 290.39 241,870.75 70,236,847.09

PEK. STR G. BPOM Page 9


HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME JUMLAH (Rp)
(Rp)
3 Beton Kolom :
a Type K-1
- Beton Mutu 'Fc = 29,5 Mpa m3 74.40 1,206,627.32 89,773,072.61
- Pembesian kg 13,009.44 13,086.98 170,254,153.23
- Bekisting m2 186.00 210,273.25 39,110,824.50
b Type K 2
- Beton Mutu 'Fc = 29,5 Mpa m3 1.35 1,206,627.32 1,628,946.88
- Pembesian kg 274.29 13,086.98 3,589,679.77
- Bekisting m2 7.07 210,273.25 1,485,580.51
4 Beton Retaining Wall :
a Type W 1
- Beton Mutu 'Fc = 29,5 Mpa m3 7.54 1,206,627.32 9,094,953.42
- Pembesian kg 1,010.50 13,086.98 13,224,365.27
- Bekisting m2 50.25 292,685.25 14,707,433.81
b Type W 2
- Beton Mutu 'Fc = 29,5 Mpa m3 32.94 1,206,627.32 39,746,303.92
- Pembesian kg 4,383.15 13,086.98 57,362,198.47
- Bekisting m2 219.60 292,685.25 64,273,680.90
c Type W 3
- Beton Mutu 'Fc = 29,5 Mpa m3 13.64 1,206,627.32 16,452,363.51
- Pembesian kg 1,915.78 13,086.98 25,071,792.98
- Bekisting m2 90.90 292,685.25 26,605,089.23
d Type W 4
- Beton Mutu 'Fc = 29,5 Mpa m3 7.20 1,206,627.32 8,687,716.70
- Pembesian kg 966.73 13,086.98 12,651,554.85
- Bekisting m2 48.00 292,685.25 14,048,892.00
5 Tangga Beton :
5.1 Type Tangga Shaft Kebakaran #1 (as 3 / A'-B) :
a Type Balok Tangga
- Beton Mutu 'Fc = 29,5 Mpa m3 0.15 1,206,627.32 181,899.07
- Pembesian kg 29.64 13,086.98 387,930.13
- Bekisting m2 1.71 278,925.63 476,544.44
b Type Plat Tangga dan Anak Tangga
- Beton Mutu 'Fc = 29,5 Mpa m3 2.86 1,206,627.32 3,446,507.71
- Pembesian kg 264.00 13,086.98 3,455,006.48
- Bekisting m2 30.45 278,925.63 8,492,420.76
5.2 Type Tangga Shaft Kebakaran #2 (as 6' / C'-D) :
a Type Balok Tangga
- Beton Mutu 'Fc = 29,5 Mpa m3 0.14 1,206,627.32 172,668.37
- Pembesian kg 28.30 13,086.98 370,421.07
- Bekisting m2 1.62 278,925.63 452,361.59
b Type Plat Tangga dan Anak Tangga
- Beton Mutu 'Fc = 29,5 Mpa m3 2.44 1,206,627.32 2,948,629.15
- Pembesian kg 218.18 13,086.98 2,855,335.07
- Bekisting m2 27.70 278,925.63 7,725,152.14
SUB TOTAL LANTAI MEZZANINE C,2 1,066,606,112.70

PEK. STR G. BPOM Page 10


HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME JUMLAH (Rp)
(Rp)

C,3 LANTAI 2
1 Beton Balok :
a Type B 1
- Beton Mutu 'Fc = 29,5 Mpa m3 21.49 1,206,627.32 25,927,042.55
- Pembesian kg 3,346.21 13,086.98 43,791,788.94
- Bekisting m2 119.71 241,870.75 28,955,411.71
b Type B 2
- Beton Mutu 'Fc = 29,5 Mpa m3 26.26 1,206,627.32 31,690,859.93
- Pembesian kg 4,513.22 13,086.98 59,064,453.65
- Bekisting m2 146.33 241,870.75 35,392,463.11
c Type B 3
- Beton Mutu 'Fc = 29,5 Mpa m3 18.36 1,206,627.32 22,153,194.94
- Pembesian kg 3,211.08 13,086.98 42,023,347.44
- Bekisting m2 102.29 241,870.75 24,740,765.52
d Type B 4
- Beton Mutu 'Fc = 29,5 Mpa m3 8.41 1,206,627.32 10,149,183.71
- Pembesian kg 1,256.62 13,086.98 16,445,335.45
- Bekisting m2 46.86 241,870.75 11,334,643.83
e Type B 6
- Beton Mutu 'Fc = 29,5 Mpa m3 23.60 1,206,627.32 28,481,231.26
- Pembesian kg 4,555.38 13,086.98 59,616,188.58
- Bekisting m2 164.10 241,870.75 39,691,957.56
f Type B 9
- Beton Mutu 'Fc = 29,5 Mpa m3 1.23 1,206,627.32 1,489,943.41
- Pembesian kg 209.30 13,086.98 2,739,105.06
- Bekisting m2 6.88 241,870.75 1,663,974.01
g Type B 10
- Beton Mutu 'Fc = 29,5 Mpa m3 3.79 1,206,627.32 4,573,720.86
- Pembesian kg 748.42 13,086.98 9,794,562.95
- Bekisting m2 26.35 241,870.75 6,374,019.87
h Type B a1
- Beton Mutu 'Fc = 29,5 Mpa m3 11.72 1,206,627.32 14,135,639.05
- Pembesian kg 2,342.25 13,086.98 30,652,969.95
- Bekisting m2 82.79 241,870.75 20,023,511.91
i Type B a2
- Beton Mutu 'Fc = 29,5 Mpa m3 10.20 1,206,627.32 12,307,598.66
- Pembesian kg 1,922.91 13,086.98 25,165,070.56
- Bekisting m2 72.08 241,870.75 17,434,043.66
j Type B a3
- Beton Mutu 'Fc = 29,5 Mpa m3 6.76 1,206,627.32 8,151,974.17
- Pembesian kg 1,497.64 13,086.98 19,599,598.70
- Bekisting m2 47.74 241,870.75 11,547,490.09
k Type B a4
- Beton Mutu 'Fc = 29,5 Mpa m3 0.87 1,206,627.32 1,049,765.77
- Pembesian kg 152.46 13,086.98 1,995,275.53
- Bekisting m2 6.15 241,870.75 1,487,021.37
l Type B a5
- Beton Mutu 'Fc = 29,5 Mpa m3 4.25 1,206,627.32 5,125,752.86
- Pembesian kg 890.48 13,086.98 11,653,709.04
- Bekisting m2 30.02 241,870.75 7,260,766.42
m Type B a7
- Beton Mutu 'Fc = 29,5 Mpa m3 0.48 1,206,627.32 579,181.11
- Pembesian kg 119.64 13,086.98 1,565,741.04
- Bekisting m2 3.39 241,870.75 820,425.58
n Type B c1
- Beton Mutu 'Fc = 29,5 Mpa m3 8.35 1,206,627.32 10,074,855.47
- Pembesian kg 1,468.78 13,086.98 19,221,885.61
- Bekisting m2 46.52 241,870.75 11,251,633.79
o Type B c2
- Beton Mutu 'Fc = 29,5 Mpa m3 0.95 1,206,627.32 1,148,709.21
- Pembesian kg 195.82 13,086.98 2,562,676.61
- Bekisting m2 5.30 241,870.75 1,282,882.46

PEK. STR G. BPOM Page 11


HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME JUMLAH (Rp)
(Rp)
2 Beton Plat Lantai :
a Type Plat S1
- Beton Mutu 'Fc = 29,5 Mpa m3 99.78 1,206,627.32 120,393,013.39
- Pembesian kg 9,863.25 13,086.98 129,080,128.93
- Bekisting m2 767.51 268,105.75 205,774,192.72
b Type Plat S2
- Beton Mutu 'Fc = 29,5 Mpa m3 23.92 1,206,627.32 28,867,545.06
- Pembesian kg 2,259.06 13,086.98 29,564,253.92
- Bekisting m2 184.03 268,105.75 49,340,037.38
3 Beton Kolom :
a Type K 1
- Beton Mutu 'Fc = 29,5 Mpa m3 83.33 1,206,627.32 100,545,841.32
- Pembesian kg 14,437.17 13,086.98 188,938,898.57
- Bekisting m2 208.32 210,273.25 43,804,123.44
b Type K 2
- Beton Mutu 'Fc = 29,5 Mpa m3 1.51 1,206,627.32 1,824,420.51
- Pembesian kg 304.72 13,086.98 3,987,879.77
- Bekisting m2 7.91 210,273.25 1,663,850.17
4 Beton Retaining Wall :
a Type W 1
- Beton Mutu 'Fc = 29,5 Mpa m3 8.44 1,206,627.32 10,186,347.84
- Pembesian kg 1,120.60 13,086.98 14,665,295.86
- Bekisting m2 56.28 292,685.25 16,472,325.87
b Type W 2
- Beton Mutu 'Fc = 29,5 Mpa m3 36.89 1,206,627.32 44,515,860.39
- Pembesian kg 4,860.43 13,086.98 63,608,302.52
- Bekisting m2 245.95 292,685.25 71,986,522.61
c Type W 3
- Beton Mutu 'Fc = 29,5 Mpa m3 15.27 1,206,627.32 18,426,647.13
- Pembesian kg 2,125.36 13,086.98 27,814,569.56
- Bekisting m2 101.81 292,685.25 29,797,699.93
d Type W 4
- Beton Mutu 'Fc = 29,5 Mpa m3 8.06 1,206,627.32 9,730,242.71
- Pembesian kg 1,072.08 13,086.98 14,030,255.89
- Bekisting m2 53.76 292,685.25 15,734,759.04
5 Tangga Beton :
5.1 Type Tangga Shaft Kebakaran #1 (as 3 / A'-B) :
a Type Balok Tangga
- Beton Mutu 'Fc = 29,5 Mpa m3 0.15 1,206,627.32 181,899.07
- Pembesian kg 29.64 13,086.98 387,930.13
- Bekisting m2 1.71 278,925.63 476,544.44
b Type Plat Tangga dan Anak Tangga
- Beton Mutu 'Fc = 29,5 Mpa m3 3.25 1,206,627.32 3,917,164.77
- Pembesian kg 293.73 13,086.98 3,844,101.67
- Bekisting m2 35.58 278,925.63 9,924,648.09
5.2 Type Tangga Shaft Kebakaran #2 (as 6' / C'-D) :
a Type Balok Tangga
- Beton Mutu 'Fc = 29,5 Mpa m3 0.14 1,206,627.32 172,668.37
- Pembesian kg 28.30 13,086.98 370,421.07
- Bekisting m2 1.62 278,925.63 452,361.59
b Type Plat Tangga dan Anak Tangga
- Beton Mutu 'Fc = 29,5 Mpa m3 2.80 1,206,627.32 3,381,060.25
- Pembesian kg 245.32 13,086.98 3,210,466.28
- Bekisting m2 32.62 278,925.63 9,098,470.37
SUB TOTAL LANTAI 2 C,3 2,018,362,123.63

PEK. STR G. BPOM Page 12


HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME JUMLAH (Rp)
(Rp)

C,4 LANTAI 3
1 Beton Balok :
a Type B 1
- Beton Mutu 'Fc = 29,5 Mpa m3 21.49 1,206,627.32 25,927,042.55
- Pembesian kg 3,346.21 13,086.98 43,791,788.94
- Bekisting m2 119.71 241,870.75 28,955,411.71
b Type B 2
- Beton Mutu 'Fc = 29,5 Mpa m3 26.26 1,206,627.32 31,690,859.93
- Pembesian kg 4,513.22 13,086.98 59,064,453.65
- Bekisting m2 146.33 241,870.75 35,392,463.11
c Type B 3
- Beton Mutu 'Fc = 29,5 Mpa m3 18.36 1,206,627.32 22,153,194.94
- Pembesian kg 3,211.08 13,086.98 42,023,347.44
- Bekisting m2 102.29 241,870.75 24,740,765.52
d Type B 4
- Beton Mutu 'Fc = 29,5 Mpa m3 8.41 1,206,627.32 10,149,183.71
- Pembesian kg 1,256.62 13,086.98 16,445,335.45
- Bekisting m2 46.86 241,870.75 11,334,643.83
e Type B 6
- Beton Mutu 'Fc = 29,5 Mpa m3 23.60 1,206,627.32 28,481,231.26
- Pembesian kg 4,555.38 13,086.98 59,616,188.58
- Bekisting m2 164.10 241,870.75 39,691,957.56
f Type B 9
- Beton Mutu 'Fc = 29,5 Mpa m3 1.23 1,206,627.32 1,489,943.41
- Pembesian kg 209.30 13,086.98 2,739,105.06
- Bekisting m2 6.88 241,870.75 1,663,974.01
g Type B 10
- Beton Mutu 'Fc = 29,5 Mpa m3 3.79 1,206,627.32 4,573,720.86
- Pembesian kg 748.42 13,086.98 9,794,562.95
- Bekisting m2 26.35 241,870.75 6,374,019.87
h Type B a1
- Beton Mutu 'Fc = 29,5 Mpa m3 11.72 1,206,627.32 14,135,639.05
- Pembesian kg 2,342.25 13,086.98 30,652,969.95
- Bekisting m2 82.79 241,870.75 20,023,511.91
i Type B a2
- Beton Mutu 'Fc = 29,5 Mpa m3 10.20 1,206,627.32 12,307,598.66
- Pembesian kg 1,922.91 13,086.98 25,165,070.56
- Bekisting m2 72.08 241,870.75 17,434,043.66
j Type B a3
- Beton Mutu 'Fc = 29,5 Mpa m3 6.76 1,206,627.32 8,151,974.17
- Pembesian kg 1,497.64 13,086.98 19,599,598.70
- Bekisting m2 47.74 241,870.75 11,547,490.09
k Type B a4
- Beton Mutu 'Fc = 29,5 Mpa m3 0.87 1,206,627.32 1,049,765.77
- Pembesian kg 152.46 13,086.98 1,995,275.53
- Bekisting m2 6.15 241,870.75 1,487,021.37
l Type B a5
- Beton Mutu 'Fc = 29,5 Mpa m3 4.25 1,206,627.32 5,125,752.86
- Pembesian kg 890.48 13,086.98 11,653,709.04
- Bekisting m2 30.02 241,870.75 7,260,766.42
m Type B a7
- Beton Mutu 'Fc = 29,5 Mpa m3 0.48 1,206,627.32 579,181.11
- Pembesian kg 119.64 13,086.98 1,565,741.04
- Bekisting m2 3.39 241,870.75 820,425.58
n Type B c1
- Beton Mutu 'Fc = 29,5 Mpa m3 8.35 1,206,627.32 10,074,855.47
- Pembesian kg 1,468.78 13,086.98 19,221,885.61
- Bekisting m2 46.52 241,870.75 11,251,633.79
o Type B c2
- Beton Mutu 'Fc = 29,5 Mpa m3 0.95 1,206,627.32 1,148,709.21
- Pembesian kg 195.82 13,086.98 2,562,676.61
- Bekisting m2 5.30 241,870.75 1,282,882.46

PEK. STR G. BPOM Page 13


HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME JUMLAH (Rp)
(Rp)
2 Beton Plat Lantai :
a Type Plat S1
- Beton Mutu 'Fc = 29,5 Mpa m3 99.78 1,206,627.32 120,393,013.39
- Pembesian kg 9,863.25 13,086.98 129,080,128.93
- Bekisting m2 767.51 292,685.25 224,639,236.72
b Type Plat S2
- Beton Mutu 'Fc = 29,5 Mpa m3 23.92 1,206,627.32 28,867,545.06
- Pembesian kg 2,259.06 13,086.98 29,564,253.92
- Bekisting m2 184.03 292,685.25 53,863,451.93
3 Beton Kolom :
a Type K 1
- Beton Mutu 'Fc = 29,5 Mpa m3 83.33 1,206,627.32 100,545,841.32
- Pembesian kg 14,437.17 13,086.98 188,938,898.57
- Bekisting m2 208.32 210,273.25 43,804,123.44
b Type K 2
- Beton Mutu 'Fc = 29,5 Mpa m3 1.51 1,206,627.32 1,824,420.51
- Pembesian kg 304.72 13,086.98 3,987,879.77
- Bekisting m2 7.91 210,273.25 1,663,850.17
4 Beton Retaining Wall :
a Type W 1
- Beton Mutu 'Fc = 29,5 Mpa m3 8.44 1,206,627.32 10,186,347.84
- Pembesian kg 1,120.60 13,086.98 14,665,295.86
- Bekisting m2 56.28 292,685.25 16,472,325.87
b Type W 2
- Beton Mutu 'Fc = 29,5 Mpa m3 36.89 1,206,627.32 44,515,860.39
- Pembesian kg 4,860.43 13,086.98 63,608,302.52
- Bekisting m2 245.95 292,685.25 71,986,522.61
c Type W 3
- Beton Mutu 'Fc = 29,5 Mpa m3 15.27 1,206,627.32 18,426,647.13
- Pembesian kg 2,125.36 13,086.98 27,814,569.56
- Bekisting m2 101.81 292,685.25 29,797,699.93
d Type W 4
- Beton Mutu 'Fc = 29,5 Mpa m3 8.06 1,206,627.32 9,730,242.71
- Pembesian kg 1,072.08 13,086.98 14,030,255.89
- Bekisting m2 53.76 292,685.25 15,734,759.04
5 Tangga Beton :
5.1 Type Tangga Shaft Kebakaran #1 (as 3 / A'-B) :
a Type Balok Tangga
- Beton Mutu 'Fc = 29,5 Mpa m3 0.15 1,206,627.32 181,899.07
- Pembesian kg 29.64 13,086.98 387,930.13
- Bekisting m2 1.71 278,925.63 476,544.44
b Type Plat Tangga dan Anak Tangga
- Beton Mutu 'Fc = 29,5 Mpa m3 3.25 1,206,627.32 3,917,164.77
- Pembesian kg 293.73 13,086.98 3,844,101.67
- Bekisting m2 35.58 278,925.63 9,924,648.09
5.2 Type Tangga Shaft Kebakaran #2 (as 6' / C'-D) :
a Type Balok Tangga
- Beton Mutu 'Fc = 29,5 Mpa m3 0.14 1,206,627.32 172,668.37
- Pembesian kg 28.30 13,086.98 370,421.07
- Bekisting m2 1.62 278,925.63 452,361.59
b Type Plat Tangga dan Anak Tangga
- Beton Mutu 'Fc = 29,5 Mpa m3 2.80 1,206,627.32 3,381,060.25
- Pembesian kg 245.32 13,086.98 3,210,466.28
- Bekisting m2 32.62 278,925.63 9,098,470.37
SUB TOTAL LANTAI 3 C,4 2,041,750,582.17

PEK. STR G. BPOM Page 14


HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME JUMLAH (Rp)
(Rp)

C,5 LANTAI 4
1 Beton Balok :
a Type B 1
- Beton Mutu 'Fc = 29,5 Mpa m3 21.49 1,206,627.32 25,927,042.55
- Pembesian kg 3,346.21 13,086.98 43,791,788.94
- Bekisting m2 119.71 241,870.75 28,955,411.71
b Type B 2
- Beton Mutu 'Fc = 29,5 Mpa m3 26.26 1,206,627.32 31,690,859.93
- Pembesian kg 4,513.22 13,086.98 59,064,453.65
- Bekisting m2 146.33 241,870.75 35,392,463.11
c Type B 3
- Beton Mutu 'Fc = 29,5 Mpa m3 18.36 1,206,627.32 22,153,194.94
- Pembesian kg 3,211.08 13,086.98 42,023,347.44
- Bekisting m2 102.29 241,870.75 24,740,765.52
d Type B 4
- Beton Mutu 'Fc = 29,5 Mpa m3 8.41 1,206,627.32 10,149,183.71
- Pembesian kg 1,256.62 13,086.98 16,445,335.45
- Bekisting m2 46.86 241,870.75 11,334,643.83
e Type B 6
- Beton Mutu 'Fc = 29,5 Mpa m3 23.60 1,206,627.32 28,481,231.26
- Pembesian kg 4,555.38 13,086.98 59,616,188.58
- Bekisting m2 164.10 241,870.75 39,691,957.56
f Type B 9
- Beton Mutu 'Fc = 29,5 Mpa m3 1.23 1,206,627.32 1,489,943.41
- Pembesian kg 209.30 13,086.98 2,739,105.06
- Bekisting m2 6.88 241,870.75 1,663,974.01
g Type B 10
- Beton Mutu 'Fc = 29,5 Mpa m3 3.79 1,206,627.32 4,573,720.86
- Pembesian kg 748.42 13,086.98 9,794,562.95
- Bekisting m2 26.35 241,870.75 6,374,019.87
h Type B a1
- Beton Mutu 'Fc = 29,5 Mpa m3 11.72 1,206,627.32 14,135,639.05
- Pembesian kg 2,342.25 13,086.98 30,652,969.95
- Bekisting m2 82.79 241,870.75 20,023,511.91
i Type B a2
- Beton Mutu 'Fc = 29,5 Mpa m3 10.20 1,206,627.32 12,307,598.66
- Pembesian kg 1,922.91 13,086.98 25,165,070.56
- Bekisting m2 72.08 241,870.75 17,434,043.66
j Type B a3
- Beton Mutu 'Fc = 29,5 Mpa m3 6.76 1,206,627.32 8,151,974.17
- Pembesian kg 1,497.64 13,086.98 19,599,598.70
- Bekisting m2 47.74 241,870.75 11,547,490.09
k Type B a4
- Beton Mutu 'Fc = 29,5 Mpa m3 0.87 1,206,627.32 1,049,765.77
- Pembesian kg 152.46 13,086.98 1,995,275.53
- Bekisting m2 6.15 241,870.75 1,487,021.37
l Type B a5
- Beton Mutu 'Fc = 29,5 Mpa m3 4.25 1,206,627.32 5,125,752.86
- Pembesian kg 890.48 13,086.98 11,653,709.04
- Bekisting m2 30.02 241,870.75 7,260,766.42
m Type B a7
- Beton Mutu 'Fc = 29,5 Mpa m3 0.48 1,206,627.32 579,181.11
- Pembesian kg 119.64 13,086.98 1,565,741.04
- Bekisting m2 3.39 241,870.75 820,425.58
n Type B c1
- Beton Mutu 'Fc = 29,5 Mpa m3 8.35 1,206,627.32 10,074,855.47
- Pembesian kg 1,468.78 13,086.98 19,221,885.61
- Bekisting m2 46.52 241,870.75 11,251,633.79
o Type B c2
- Beton Mutu 'Fc = 29,5 Mpa m3 0.95 1,206,627.32 1,148,709.21
- Pembesian kg 195.82 13,086.98 2,562,676.61
- Bekisting m2 5.30 241,870.75 1,282,882.46

PEK. STR G. BPOM Page 15


HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME JUMLAH (Rp)
(Rp)
2 Beton Plat Lantai :
a Type Plat S1
- Beton Mutu 'Fc = 29,5 Mpa m3 99.78 1,206,627.32 120,393,013.39
- Pembesian kg 9,863.25 13,086.98 129,080,128.93
- Bekisting m2 767.51 268,105.75 205,774,192.72
b Type Plat S2
- Beton Mutu 'Fc = 29,5 Mpa m3 23.92 1,206,627.32 28,867,545.06
- Pembesian kg 2,259.06 13,086.98 29,564,253.92
- Bekisting m2 184.03 268,105.75 49,340,037.38
3 Beton Kolom :
a Type K 1
- Beton Mutu 'Fc = 29,5 Mpa m3 83.33 1,206,627.32 100,545,841.32
- Pembesian kg 14,437.17 13,086.98 188,938,898.57
- Bekisting m2 208.32 210,273.25 43,804,123.44
b Type K 2
- Beton Mutu 'Fc = 29,5 Mpa m3 1.51 1,206,627.32 1,824,420.51
- Pembesian kg 304.72 13,086.98 3,987,879.77
- Bekisting m2 7.91 210,273.25 1,663,850.17
4 Beton Retaining Wall :
a Type W 1
- Beton Mutu 'Fc = 29,5 Mpa m3 8.44 1,206,627.32 10,186,347.84
- Pembesian kg 1,120.60 13,086.98 14,665,295.86
- Bekisting m2 56.28 292,685.25 16,472,325.87
b Type W 2
- Beton Mutu 'Fc = 29,5 Mpa m3 36.89 1,206,627.32 44,515,860.39
- Pembesian kg 4,860.43 13,086.98 63,608,302.52
- Bekisting m2 245.95 292,685.25 71,986,522.61
c Type W 3
- Beton Mutu 'Fc = 29,5 Mpa m3 15.27 1,206,627.32 18,426,647.13
- Pembesian kg 2,125.36 13,086.98 27,814,569.56
- Bekisting m2 101.81 292,685.25 29,797,699.93
d Type W 4
- Beton Mutu 'Fc = 29,5 Mpa m3 8.06 1,206,627.32 9,730,242.71
- Pembesian kg 1,072.08 13,086.98 14,030,255.89
- Bekisting m2 53.76 292,685.25 15,734,759.04
5 Tangga Beton :
5.1 Type Tangga Shaft Kebakaran #1 (as 3 / A'-B) :
a Type Balok Tangga
- Beton Mutu 'Fc = 29,5 Mpa m3 0.15 1,206,627.32 181,899.07
- Pembesian kg 29.64 13,086.98 387,930.13
- Bekisting m2 1.71 278,925.63 476,544.44
b Type Plat Tangga dan Anak Tangga
- Beton Mutu 'Fc = 29,5 Mpa m3 3.25 1,206,627.32 3,917,164.77
- Pembesian kg 293.73 13,086.98 3,844,101.67
- Bekisting m2 35.58 278,925.63 9,924,648.09
5.2 Type Tangga Shaft Kebakaran #2 (as 6' / C'-D) :
a Type Balok Tangga
- Beton Mutu 'Fc = 29,5 Mpa m3 0.14 1,206,627.32 172,668.37
- Pembesian kg 28.30 13,086.98 370,421.07
- Bekisting m2 1.62 278,925.63 452,361.59
b Type Plat Tangga dan Anak Tangga
- Beton Mutu 'Fc = 29,5 Mpa m3 2.80 1,206,627.32 3,381,060.25
- Pembesian kg 245.32 13,086.98 3,210,466.28
- Bekisting m2 32.62 278,925.63 9,098,470.37
SUB TOTAL LANTAI 4 C,5 2,018,362,123.63

PEK. STR G. BPOM Page 16


HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME JUMLAH (Rp)
(Rp)

C,6 LANTAI 5
1 Beton Balok :
a Type B 1
- Beton Mutu 'Fc = 29,5 Mpa m3 21.49 1,206,627.32 25,927,042.55
- Pembesian kg 3,346.21 13,086.98 43,791,788.94
- Bekisting m2 119.71 241,870.75 28,955,411.71
b Type B 2
- Beton Mutu 'Fc = 29,5 Mpa m3 26.26 1,206,627.32 31,690,859.93
- Pembesian kg 4,513.22 13,086.98 59,064,453.65
- Bekisting m2 146.33 241,870.75 35,392,463.11
c Type B 3
- Beton Mutu 'Fc = 29,5 Mpa m3 18.36 1,206,627.32 22,153,194.94
- Pembesian kg 3,211.08 13,086.98 42,023,347.44
- Bekisting m2 102.29 241,870.75 24,740,765.52
d Type B 4
- Beton Mutu 'Fc = 29,5 Mpa m3 8.41 1,206,627.32 10,149,183.71
- Pembesian kg 1,256.62 13,086.98 16,445,335.45
- Bekisting m2 46.86 241,870.75 11,334,643.83
e Type B 6
- Beton Mutu 'Fc = 29,5 Mpa m3 23.60 1,206,627.32 28,481,231.26
- Pembesian kg 4,555.38 13,086.98 59,616,188.58
- Bekisting m2 164.10 241,870.75 39,691,957.56
f Type B 9
- Beton Mutu 'Fc = 29,5 Mpa m3 1.23 1,206,627.32 1,489,943.41
- Pembesian kg 209.30 13,086.98 2,739,105.06
- Bekisting m2 6.88 241,870.75 1,663,974.01
g Type B 10
- Beton Mutu 'Fc = 29,5 Mpa m3 3.79 1,206,627.32 4,573,720.86
- Pembesian kg 748.42 13,086.98 9,794,562.95
- Bekisting m2 26.35 241,870.75 6,374,019.87
h Type B a1
- Beton Mutu 'Fc = 29,5 Mpa m3 11.72 1,206,627.32 14,135,639.05
- Pembesian kg 2,342.25 13,086.98 30,652,969.95
- Bekisting m2 82.79 241,870.75 20,023,511.91
i Type B a2
- Beton Mutu 'Fc = 29,5 Mpa m3 10.20 1,206,627.32 12,307,598.66
- Pembesian kg 1,922.91 13,086.98 25,165,070.56
- Bekisting m2 72.08 241,870.75 17,434,043.66
j Type B a3
- Beton Mutu 'Fc = 29,5 Mpa m3 6.76 1,206,627.32 8,151,974.17
- Pembesian kg 1,497.64 13,086.98 19,599,598.70
- Bekisting m2 47.74 241,870.75 11,547,490.09
k Type B a4
- Beton Mutu 'Fc = 29,5 Mpa m3 0.87 1,206,627.32 1,049,765.77
- Pembesian kg 152.46 13,086.98 1,995,275.53
- Bekisting m2 6.15 241,870.75 1,487,021.37
l Type B a5
- Beton Mutu 'Fc = 29,5 Mpa m3 4.25 1,206,627.32 5,125,752.86
- Pembesian kg 890.48 13,086.98 11,653,709.04
- Bekisting m2 30.02 241,870.75 7,260,766.42
m Type B a7
- Beton Mutu 'Fc = 29,5 Mpa m3 0.48 1,206,627.32 579,181.11
- Pembesian kg 119.64 13,086.98 1,565,741.04
- Bekisting m2 3.39 241,870.75 820,425.58
n Type B c1
- Beton Mutu 'Fc = 29,5 Mpa m3 8.51 1,206,627.32 10,267,433.19
- Pembesian kg 1,496.86 13,086.98 19,589,305.96
- Bekisting m2 47.41 241,870.75 11,466,705.26
o Type B c2
- Beton Mutu 'Fc = 29,5 Mpa m3 0.98 1,206,627.32 1,182,494.77
- Pembesian kg 201.58 13,086.98 2,638,049.45
- Bekisting m2 5.46 241,870.75 1,320,614.30

PEK. STR G. BPOM Page 17


HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME JUMLAH (Rp)
(Rp)
2 Beton Plat Lantai :
a Type Plat S1
- Beton Mutu 'Fc = 29,5 Mpa m3 99.78 1,206,627.32 120,393,013.39
- Pembesian kg 9,863.25 13,086.98 129,080,128.93
- Bekisting m2 767.51 268,105.75 205,774,192.72
b Type Plat S2
- Beton Mutu 'Fc = 29,5 Mpa m3 24.11 1,206,627.32 29,089,347.30
- Pembesian kg 2,276.42 13,086.98 29,791,409.28
- Bekisting m2 185.45 268,105.75 49,719,138.91
3 Beton Kolom :
a Type K 2
- Beton Mutu 'Fc = 29,5 Mpa m3 1.51 1,206,627.32 1,824,420.51
- Pembesian kg 304.72 13,086.98 3,987,879.77
- Bekisting m2 7.91 210,273.25 1,663,850.17
b Type K 3
- Beton Mutu 'Fc = 29,5 Mpa m3 63.80 1,206,627.32 76,980,409.76
- Pembesian kg 11,988.70 13,086.98 156,895,777.40
- Bekisting m2 286.18 210,273.25 60,175,914.58
4 Beton Retaining Wall :
a Type W 5
- Beton Mutu 'Fc = 29,5 Mpa m3 8.44 1,206,627.32 10,186,347.84
- Pembesian kg 877.68 13,086.98 11,486,177.18
- Bekisting m2 56.28 292,685.25 16,472,325.87
b Type W 6
- Beton Mutu 'Fc = 29,5 Mpa m3 36.89 1,206,627.32 44,515,860.39
- Pembesian kg 3,798.82 13,086.98 49,715,079.40
- Bekisting m2 245.95 292,685.25 71,986,522.61
c Type W 7
- Beton Mutu 'Fc = 29,5 Mpa m3 15.27 1,206,627.32 18,426,647.13
- Pembesian kg 1,685.93 13,086.98 22,063,686.22
- Bekisting m2 101.81 292,685.25 29,797,699.93
d Type W 8
- Beton Mutu 'Fc = 29,5 Mpa m3 8.06 1,206,627.32 9,730,242.71
- Pembesian kg 840.03 13,086.98 10,993,485.81
- Bekisting m2 53.76 292,685.25 15,734,759.04
5 Tangga Beton :
5.1 Type Tangga Shaft Kebakaran #1 (as 3 / A'-B) :
a Type Balok Tangga
- Beton Mutu 'Fc = 29,5 Mpa m3 0.15 1,206,627.32 181,899.07
- Pembesian kg 29.64 13,086.98 387,930.13
- Bekisting m2 1.71 278,925.63 476,544.44
b Type Plat Tangga dan Anak Tangga
- Beton Mutu 'Fc = 29,5 Mpa m3 3.25 1,206,627.32 3,917,164.77
- Pembesian kg 293.73 13,086.98 3,844,101.67
- Bekisting m2 35.58 278,925.63 9,924,648.09
5.2 Type Tangga Shaft Kebakaran #2 (as 6' / C'-D) :
a Type Balok Tangga
- Beton Mutu 'Fc = 29,5 Mpa m3 0.14 1,206,627.32 172,668.37
- Pembesian kg 28.30 13,086.98 370,421.07
- Bekisting m2 1.62 278,925.63 452,361.59
b Type Plat Tangga dan Anak Tangga
- Beton Mutu 'Fc = 29,5 Mpa m3 2.80 1,206,627.32 3,381,060.25
- Pembesian kg 245.32 13,086.98 3,210,466.28
- Bekisting m2 32.62 278,925.63 9,098,470.37
SUB TOTAL LANTAI 5 C,6 1,955,015,385.73

PEK. STR G. BPOM Page 18


HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME JUMLAH (Rp)
(Rp)

C,7 LANTAI 6
1 Beton Balok :
a Type B 1
- Beton Mutu 'Fc = 29,5 Mpa m3 21.49 1,206,627.32 25,927,042.55
- Pembesian kg 3,346.21 13,086.98 43,791,788.94
- Bekisting m2 119.71 241,870.75 28,955,411.71
b Type B 2
- Beton Mutu 'Fc = 29,5 Mpa m3 26.26 1,206,627.32 31,690,859.93
- Pembesian kg 4,513.22 13,086.98 59,064,453.65
- Bekisting m2 146.33 241,870.75 35,392,463.11
c Type B 3
- Beton Mutu 'Fc = 29,5 Mpa m3 18.36 1,206,627.32 22,153,194.94
- Pembesian kg 3,211.08 13,086.98 42,023,347.44
- Bekisting m2 102.29 241,870.75 24,740,765.52
d Type B 4
- Beton Mutu 'Fc = 29,5 Mpa m3 8.41 1,206,627.32 10,149,183.71
- Pembesian kg 1,256.62 13,086.98 16,445,335.45
- Bekisting m2 46.86 241,870.75 11,334,643.83
e Type B 6
- Beton Mutu 'Fc = 29,5 Mpa m3 23.60 1,206,627.32 28,481,231.26
- Pembesian kg 4,555.38 13,086.98 59,616,188.58
- Bekisting m2 164.10 241,870.75 39,691,957.56
f Type B 9
- Beton Mutu 'Fc = 29,5 Mpa m3 1.23 1,206,627.32 1,489,943.41
- Pembesian kg 209.30 13,086.98 2,739,105.06
- Bekisting m2 6.88 241,870.75 1,663,974.01
g Type B 10
- Beton Mutu 'Fc = 29,5 Mpa m3 3.79 1,206,627.32 4,573,720.86
- Pembesian kg 748.42 13,086.98 9,794,562.95
- Bekisting m2 26.35 241,870.75 6,374,019.87
h Type B a1
- Beton Mutu 'Fc = 29,5 Mpa m3 11.72 1,206,627.32 14,135,639.05
- Pembesian kg 2,342.25 13,086.98 30,652,969.95
- Bekisting m2 82.79 241,870.75 20,023,511.91
i Type B a2
- Beton Mutu 'Fc = 29,5 Mpa m3 10.20 1,206,627.32 12,307,598.66
- Pembesian kg 1,922.91 13,086.98 25,165,070.56
- Bekisting m2 72.08 241,870.75 17,434,043.66
j Type B a3
- Beton Mutu 'Fc = 29,5 Mpa m3 6.76 1,206,627.32 8,151,974.17
- Pembesian kg 1,497.64 13,086.98 19,599,598.70
- Bekisting m2 47.74 241,870.75 11,547,490.09
k Type B a4
- Beton Mutu 'Fc = 29,5 Mpa m3 0.87 1,206,627.32 1,049,765.77
- Pembesian kg 152.46 13,086.98 1,995,275.53
- Bekisting m2 6.15 241,870.75 1,487,021.37
l Type B a5
- Beton Mutu 'Fc = 29,5 Mpa m3 4.25 1,206,627.32 5,125,752.86
- Pembesian kg 890.48 13,086.98 11,653,709.04
- Bekisting m2 30.02 241,870.75 7,260,766.42
m Type B a7
- Beton Mutu 'Fc = 29,5 Mpa m3 0.48 1,206,627.32 579,181.11
- Pembesian kg 119.64 13,086.98 1,565,741.04
- Bekisting m2 3.39 241,870.75 820,425.58
n Type B c1
- Beton Mutu 'Fc = 29,5 Mpa m3 8.51 1,206,627.32 10,267,433.19
- Pembesian kg 1,496.86 13,086.98 19,589,305.96
- Bekisting m2 47.41 241,870.75 11,466,705.26
o Type B c2
- Beton Mutu 'Fc = 29,5 Mpa m3 0.98 1,206,627.32 1,182,494.77
- Pembesian kg 201.58 13,086.98 2,638,049.45
- Bekisting m2 5.46 241,870.75 1,320,614.30

PEK. STR G. BPOM Page 19


HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME JUMLAH (Rp)
(Rp)
2 Beton Plat Lantai :
a Type Plat S1
- Beton Mutu 'Fc = 29,5 Mpa m3 99.78 1,206,627.32 120,393,013.39
- Pembesian kg 9,863.25 13,086.98 129,080,128.93
- Bekisting m2 767.51 268,105.75 205,774,192.72
b Type Plat S2
- Beton Mutu 'Fc = 29,5 Mpa m3 24.11 1,206,627.32 29,089,347.30
- Pembesian kg 2,276.42 13,086.98 29,791,409.28
- Bekisting m2 185.45 268,105.75 49,719,138.91
3 Beton Kolom :
a Type K 2
- Beton Mutu 'Fc = 29,5 Mpa m3 1.51 1,206,627.32 1,824,420.51
- Pembesian kg 304.72 13,086.98 3,987,879.77
- Bekisting m2 7.91 210,273.25 1,663,850.17
b Type K 3
- Beton Mutu 'Fc = 29,5 Mpa m3 63.80 1,206,627.32 76,980,409.76
- Pembesian kg 11,988.70 13,086.98 156,895,777.40
- Bekisting m2 286.18 210,273.25 60,175,914.58
4 Beton Retaining Wall :
a Type W 5
- Beton Mutu 'Fc = 29,5 Mpa m3 8.44 1,206,627.32 10,186,347.84
- Pembesian kg 877.68 13,086.98 11,486,177.18
- Bekisting m2 56.28 292,685.25 16,472,325.87
b Type W 6
- Beton Mutu 'Fc = 29,5 Mpa m3 36.89 1,206,627.32 44,515,860.39
- Pembesian kg 3,798.82 13,086.98 49,715,079.40
- Bekisting m2 245.95 292,685.25 71,986,522.61
c Type W 7
- Beton Mutu 'Fc = 29,5 Mpa m3 15.27 1,206,627.32 18,426,647.13
- Pembesian kg 1,685.93 13,086.98 22,063,686.22
- Bekisting m2 101.81 292,685.25 29,797,699.93
d Type W 8
- Beton Mutu 'Fc = 29,5 Mpa m3 8.06 1,206,627.32 9,730,242.71
- Pembesian kg 840.03 13,086.98 10,993,485.81
- Bekisting m2 53.76 292,685.25 15,734,759.04
5 Tangga Beton :
5.1 Type Tangga Shaft Kebakaran #1 (as 3 / A'-B) :
a Type Balok Tangga
- Beton Mutu 'Fc = 29,5 Mpa m3 0.15 1,206,627.32 181,899.07
- Pembesian kg 29.64 13,086.98 387,930.13
- Bekisting m2 1.71 278,925.63 476,544.44
b Type Plat Tangga dan Anak Tangga
- Beton Mutu 'Fc = 29,5 Mpa m3 3.25 1,206,627.32 3,917,164.77
- Pembesian kg 293.73 13,086.98 3,844,101.67
- Bekisting m2 35.58 278,925.63 9,924,648.09
5.2 Type Tangga Shaft Kebakaran #2 (as 6' / C'-D) :
a Type Balok Tangga
- Beton Mutu 'Fc = 29,5 Mpa m3 0.14 1,206,627.32 172,668.37
- Pembesian kg 28.30 13,086.98 370,421.07
- Bekisting m2 1.62 278,925.63 452,361.59
b Type Plat Tangga dan Anak Tangga
- Beton Mutu 'Fc = 29,5 Mpa m3 2.80 1,206,627.32 3,381,060.25
- Pembesian kg 245.32 13,086.98 3,210,466.28
- Bekisting m2 32.62 278,925.63 9,098,470.37
SUB TOTAL LANTAI 6 C,7 1,955,015,385.73

PEK. STR G. BPOM Page 20


HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME JUMLAH (Rp)
(Rp)

C,8 LANTAI 7
1 Beton Balok :
a Type B 1
- Beton Mutu 'Fc = 29,5 Mpa m3 21.84 1,206,627.32 26,352,740.67
- Pembesian kg 3,401.15 13,086.98 44,510,809.71
- Bekisting m2 121.68 241,870.75 29,430,832.86
b Type B 2
- Beton Mutu 'Fc = 29,5 Mpa m3 26.66 1,206,627.32 32,163,857.84
- Pembesian kg 4,580.59 13,086.98 59,946,012.66
- Bekisting m2 148.51 241,870.75 35,920,708.82
c Type B 3
- Beton Mutu 'Fc = 29,5 Mpa m3 19.81 1,206,627.32 23,903,287.21
- Pembesian kg 3,464.76 13,086.98 45,343,172.66
- Bekisting m2 110.37 241,870.75 26,695,274.68
d Type B 4
- Beton Mutu 'Fc = 29,5 Mpa m3 8.36 1,206,627.32 10,081,612.58
- Pembesian kg 1,248.25 13,086.98 16,335,845.86
- Bekisting m2 46.55 241,870.75 11,259,180.16
e Type B 6
- Beton Mutu 'Fc = 29,5 Mpa m3 23.61 1,206,627.32 28,483,765.18
- Pembesian kg 4,555.79 13,086.98 59,621,492.51
- Bekisting m2 164.12 241,870.75 39,695,488.87
f Type B 9
- Beton Mutu 'Fc = 29,5 Mpa m3 1.28 1,206,627.32 1,540,621.76
- Pembesian kg 216.42 13,086.98 2,832,271.90
- Bekisting m2 7.11 241,870.75 1,720,571.77
g Type B 10
- Beton Mutu 'Fc = 29,5 Mpa m3 3.79 1,206,627.32 4,573,720.86
- Pembesian kg 748.42 13,086.98 9,794,562.95
- Bekisting m2 26.35 241,870.75 6,374,019.87
h Type B a1
- Beton Mutu 'Fc = 29,5 Mpa m3 11.72 1,206,627.32 14,135,639.05
- Pembesian kg 2,342.25 13,086.98 30,652,969.95
- Bekisting m2 82.79 241,870.75 20,023,511.91
i Type B a2
- Beton Mutu 'Fc = 29,5 Mpa m3 10.20 1,206,627.32 12,307,598.66
- Pembesian kg 1,922.91 13,086.98 25,165,070.56
- Bekisting m2 72.08 241,870.75 17,434,043.66
j Type B a3
- Beton Mutu 'Fc = 29,5 Mpa m3 6.76 1,206,627.32 8,151,974.17
- Pembesian kg 1,497.64 13,086.98 19,599,598.70
- Bekisting m2 47.74 241,870.75 11,547,490.09
k Type B a4
- Beton Mutu 'Fc = 29,5 Mpa m3 0.88 1,206,627.32 1,058,815.47
- Pembesian kg 153.78 13,086.98 2,012,476.18
- Bekisting m2 6.20 241,870.75 1,499,840.52
l Type B a5
- Beton Mutu 'Fc = 29,5 Mpa m3 4.25 1,206,627.32 5,125,752.86
- Pembesian kg 890.48 13,086.98 11,653,709.04
- Bekisting m2 30.02 241,870.75 7,260,766.42
m Type B a7
- Beton Mutu 'Fc = 29,5 Mpa m3 0.48 1,206,627.32 579,181.11
- Pembesian kg 119.64 13,086.98 1,565,741.04
- Bekisting m2 3.39 241,870.75 820,425.58
n Type B c1
- Beton Mutu 'Fc = 29,5 Mpa m3 8.57 1,206,627.32 10,335,004.32
- Pembesian kg 1,506.71 13,086.98 19,718,225.38
- Bekisting m2 47.72 241,870.75 11,542,168.94
o Type B c2
- Beton Mutu 'Fc = 29,5 Mpa m3 0.98 1,206,627.32 1,182,494.77
- Pembesian kg 201.58 13,086.98 2,638,049.45
- Bekisting m2 5.46 241,870.75 1,320,614.30

PEK. STR G. BPOM Page 21


HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME JUMLAH (Rp)
(Rp)
2 Beton Plat Lantai :
a Type Plat S1
- Beton Mutu 'Fc = 29,5 Mpa m3 99.78 1,206,627.32 120,393,013.39
- Pembesian kg 9,863.25 13,086.98 129,080,128.93
- Bekisting m2 767.51 268,105.75 205,774,192.72
b Type Plat S2
- Beton Mutu 'Fc = 29,5 Mpa m3 24.11 1,206,627.32 29,089,347.30
- Pembesian kg 2,276.42 13,086.98 29,791,409.28
- Bekisting m2 185.45 268,105.75 49,719,138.91
3 Beton Kolom :
a Type K 2
- Beton Mutu 'Fc = 29,5 Mpa m3 1.51 1,206,627.32 1,824,420.51
- Pembesian kg 304.72 13,086.98 3,987,879.77
- Bekisting m2 7.91 210,273.25 1,663,850.17
b Type K 3
- Beton Mutu 'Fc = 29,5 Mpa m3 63.80 1,206,627.32 76,980,409.76
- Pembesian kg 11,988.70 13,086.98 156,895,777.40
- Bekisting m2 286.18 210,273.25 60,175,914.58
4 Beton Retaining Wall :
a Type W 5
- Beton Mutu 'Fc = 29,5 Mpa m3 8.44 1,206,627.32 10,186,347.84
- Pembesian kg 877.68 13,086.98 11,486,177.18
- Bekisting m2 56.28 292,685.25 16,472,325.87
b Type W 6
- Beton Mutu 'Fc = 29,5 Mpa m3 36.89 1,206,627.32 44,515,860.39
- Pembesian kg 3,798.82 13,086.98 49,715,079.40
- Bekisting m2 245.95 292,685.25 71,986,522.61
c Type W 7
- Beton Mutu 'Fc = 29,5 Mpa m3 15.27 1,206,627.32 18,426,647.13
- Pembesian kg 1,685.93 13,086.98 22,063,686.22
- Bekisting m2 101.81 292,685.25 29,797,699.93
d Type W 8
- Beton Mutu 'Fc = 29,5 Mpa m3 8.06 1,206,627.32 9,730,242.71
- Pembesian kg 840.03 13,086.98 10,993,485.81
- Bekisting m2 53.76 292,685.25 15,734,759.04
5 Tangga Beton :
5.1 Type Tangga Shaft Kebakaran #1 (as 3 / A'-B) :
a Type Balok Tangga
- Beton Mutu 'Fc = 29,5 Mpa m3 0.15 1,206,627.32 181,899.07
- Pembesian kg 29.64 13,086.98 387,930.13
- Bekisting m2 1.71 278,925.63 476,544.44
b Type Plat Tangga dan Anak Tangga
- Beton Mutu 'Fc = 29,5 Mpa m3 3.25 1,206,627.32 3,917,164.77
- Pembesian kg 293.73 13,086.98 3,844,101.67
- Bekisting m2 35.58 278,925.63 9,924,648.09
5.2 Type Tangga Shaft Kebakaran #2 (as 6' / C'-D) :
a Type Balok Tangga
- Beton Mutu 'Fc = 29,5 Mpa m3 0.14 1,206,627.32 172,668.37
- Pembesian kg 28.30 13,086.98 370,421.07
- Bekisting m2 1.62 278,925.63 452,361.59
b Type Plat Tangga dan Anak Tangga
- Beton Mutu 'Fc = 29,5 Mpa m3 2.80 1,206,627.32 3,381,060.25
- Pembesian kg 245.32 13,086.98 3,210,466.28
- Bekisting m2 32.62 278,925.63 9,098,470.37
5.3 Type Tangga Area GYM (as 7 / C) :
Type Plat Tangga dan Anak Tangga
- Beton Mutu 'Fc = 29,5 Mpa m3 2.01 1,206,627.32 2,428,940.80
- Pembesian kg 181.18 13,086.98 2,371,037.75
- Bekisting m2 23.98 278,925.63 6,688,636.61
SUB TOTAL LANTAI 7 C,8 1,977,301,681.64

PEK. STR G. BPOM Page 22


HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME JUMLAH (Rp)
(Rp)

C,9 LANTAI 8
1 Beton Balok :
a Type B 1
- Beton Mutu 'Fc = 29,5 Mpa m3 9.10 1,206,627.32 10,980,308.61
- Pembesian kg 1,417.15 13,086.98 18,546,170.71
- Bekisting m2 50.70 241,870.75 12,262,847.03
b Type B 2
- Beton Mutu 'Fc = 29,5 Mpa m3 7.62 1,206,627.32 9,189,673.67
- Pembesian kg 1,308.74 13,086.98 17,127,432.19
- Bekisting m2 42.43 241,870.75 10,263,059.66
c Type B 3
- Beton Mutu 'Fc = 29,5 Mpa m3 17.86 1,206,627.32 21,555,190.44
- Pembesian kg 3,124.40 13,086.98 40,888,967.01
- Bekisting m2 99.53 241,870.75 24,072,912.01
d Type B 4
- Beton Mutu 'Fc = 29,5 Mpa m3 8.36 1,206,627.32 10,081,612.58
- Pembesian kg 1,248.25 13,086.98 16,335,845.86
- Bekisting m2 46.55 241,870.75 11,259,180.16
e Type B 6
- Beton Mutu 'Fc = 29,5 Mpa m3 23.61 1,206,627.32 28,483,765.18
- Pembesian kg 4,555.79 13,086.98 59,621,492.51
- Bekisting m2 164.12 241,870.75 39,695,488.87
f Type B 9
- Beton Mutu 'Fc = 29,5 Mpa m3 1.28 1,206,627.32 1,540,621.76
- Pembesian kg 216.42 13,086.98 2,832,271.90
- Bekisting m2 7.11 241,870.75 1,720,571.77
g Type B 10
- Beton Mutu 'Fc = 29,5 Mpa m3 3.79 1,206,627.32 4,573,720.86
- Pembesian kg 748.42 13,086.98 9,794,562.95
- Bekisting m2 26.35 241,870.75 6,374,019.87
h Type B 11
- Beton Mutu 'Fc = 29,5 Mpa m3 31.70 1,206,627.32 38,245,259.53
- Pembesian kg 5,488.80 13,086.98 71,831,813.91
- Bekisting m2 176.59 241,870.75 42,712,439.48
i Type B a1
- Beton Mutu 'Fc = 29,5 Mpa m3 5.33 1,206,627.32 6,425,290.48
- Pembesian kg 1,064.66 13,086.98 13,933,168.16
- Bekisting m2 37.63 241,870.75 9,101,596.32
j Type B a2
- Beton Mutu 'Fc = 29,5 Mpa m3 4.08 1,206,627.32 4,923,039.47
- Pembesian kg 769.16 13,086.98 10,066,028.22
- Bekisting m2 28.83 241,870.75 6,973,617.46
k Type B a3
- Beton Mutu 'Fc = 29,5 Mpa m3 6.62 1,206,627.32 7,989,079.49
- Pembesian kg 1,467.72 13,086.98 19,207,954.86
- Bekisting m2 46.79 241,870.75 11,316,745.40
l Type B a4
- Beton Mutu 'Fc = 29,5 Mpa m3 0.88 1,206,627.32 1,058,815.47
- Pembesian kg 153.78 13,086.98 2,012,476.18
- Bekisting m2 6.20 241,870.75 1,499,840.52
m Type B a5
- Beton Mutu 'Fc = 29,5 Mpa m3 4.74 1,206,627.32 5,713,983.67
- Pembesian kg 992.67 13,086.98 12,991,087.37
- Bekisting m2 33.46 241,870.75 8,094,011.15
n Type B a7
- Beton Mutu 'Fc = 29,5 Mpa m3 0.48 1,206,627.32 579,181.11
- Pembesian kg 119.64 13,086.98 1,565,741.04
- Bekisting m2 3.39 241,870.75 820,425.58
o Type B a8
- Beton Mutu 'Fc = 29,5 Mpa m3 12.51 1,206,627.32 15,094,907.77
- Pembesian kg 2,624.39 13,086.98 34,345,319.35
- Bekisting m2 88.40 241,870.75 21,382,341.78

PEK. STR G. BPOM Page 23


HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME JUMLAH (Rp)
(Rp)
p Type B c1
- Beton Mutu 'Fc = 29,5 Mpa m3 8.57 1,206,627.32 10,335,004.32
- Pembesian kg 1,506.71 13,086.98 19,718,225.38
- Bekisting m2 47.72 241,870.75 11,542,168.94
q Type B c2
- Beton Mutu 'Fc = 29,5 Mpa m3 0.98 1,206,627.32 1,182,494.77
- Pembesian kg 201.58 13,086.98 2,638,049.45
- Bekisting m2 5.46 241,870.75 1,320,614.30
2 Beton Plat Lantai :
a Type Plat S1
- Beton Mutu 'Fc = 29,5 Mpa m3 99.78 1,206,627.32 120,393,013.39
- Pembesian kg 9,863.25 13,086.98 129,080,128.93
- Bekisting m2 767.51 268,105.75 205,774,192.72
b Type Plat S2
- Beton Mutu 'Fc = 29,5 Mpa m3 24.11 1,206,627.32 29,089,347.30
- Pembesian kg 2,276.42 13,086.98 29,791,409.28
- Bekisting m2 185.45 268,105.75 49,719,138.91
3 Beton Kolom :
a Type K 2
- Beton Mutu 'Fc = 29,5 Mpa m3 1.62 1,206,627.32 1,954,736.26
- Pembesian kg 325.01 13,086.98 4,253,346.44
- Bekisting m2 8.48 210,273.25 1,782,696.61
b Type K 3
- Beton Mutu 'Fc = 29,5 Mpa m3 46.31 1,206,627.32 55,872,878.05
- Pembesian kg 8,657.36 13,086.98 113,298,687.39
- Bekisting m2 207.71 210,273.25 43,676,067.03
4 Beton Retaining Wall :
a Type W 5
- Beton Mutu 'Fc = 29,5 Mpa m3 9.05 1,206,627.32 10,913,944.11
- Pembesian kg 936.72 13,086.98 12,258,805.79
- Bekisting m2 60.30 292,685.25 17,648,920.58
b Type W 6
- Beton Mutu 'Fc = 29,5 Mpa m3 39.53 1,206,627.32 47,695,564.70
- Pembesian kg 4,054.23 13,086.98 53,057,596.64
- Bekisting m2 263.52 292,685.25 77,128,417.08
c Type W 7
- Beton Mutu 'Fc = 29,5 Mpa m3 16.36 1,206,627.32 19,742,836.21
- Pembesian kg 1,799.66 13,086.98 23,552,135.23
- Bekisting m2 109.08 292,685.25 31,926,107.07
d Type W 8
- Beton Mutu 'Fc = 29,5 Mpa m3 8.64 1,206,627.32 10,425,260.04
- Pembesian kg 896.54 13,086.98 11,733,045.60
- Bekisting m2 57.60 292,685.25 16,858,670.40
5 Tangga Beton :
5.1 Type Tangga area Prefunction (as 1 / D ) :
Type Plat Tangga dan Anak Tangga
- Beton Mutu 'Fc = 29,5 Mpa m3 3.62 1,206,627.32 4,365,577.64
- Pembesian kg 314.51 13,086.98 4,115,964.29
- Bekisting m2 41.40 278,925.63 11,547,521.08
SUB TOTAL LANTAI 8 C,9 1,889,476,445.37

PEK. STR G. BPOM Page 24


HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME JUMLAH (Rp)
(Rp)

C,10 LANTAI TRIBUN


1 Beton Balok :
a Type B 1
- Beton Mutu 'Fc = 29,5 Mpa m3 12.74 1,206,627.32 15,372,432.06
- Pembesian kg 1,984.01 13,086.98 25,964,639.00
- Bekisting m2 70.98 241,870.75 17,167,985.84
b Type B 2
- Beton Mutu 'Fc = 29,5 Mpa m3 11.42 1,206,627.32 13,784,510.50
- Pembesian kg 1,963.11 13,086.98 25,691,148.28
- Bekisting m2 63.65 241,870.75 15,394,589.50
c Type B 4
- Beton Mutu 'Fc = 29,5 Mpa m3 6.70 1,206,627.32 8,084,885.69
- Pembesian kg 1,001.03 13,086.98 13,100,428.67
- Bekisting m2 37.33 241,870.75 9,029,228.59
d Type B 6
- Beton Mutu 'Fc = 29,5 Mpa m3 12.20 1,206,627.32 14,719,526.01
- Pembesian kg 2,354.29 13,086.98 30,810,537.32
- Bekisting m2 84.81 241,870.75 20,513,396.93
e Type B 10
- Beton Mutu 'Fc = 29,5 Mpa m3 4.52 1,206,627.32 5,447,922.35
- Pembesian kg 891.47 13,086.98 11,666,653.93
- Bekisting m2 31.39 241,870.75 7,592,322.84
f Type B 11
- Beton Mutu 'Fc = 29,5 Mpa m3 10.86 1,206,627.32 13,105,420.65
- Pembesian kg 1,880.84 13,086.98 24,614,452.84
- Bekisting m2 60.51 241,870.75 14,636,179.57
g Type B 12
- Beton Mutu 'Fc = 29,5 Mpa m3 3.64 1,206,627.32 4,392,123.44
- Pembesian kg 760.40 13,086.98 9,951,396.34
- Bekisting m2 20.28 241,870.75 4,905,138.81
h Type B a1
- Beton Mutu 'Fc = 29,5 Mpa m3 4.26 1,206,627.32 5,140,232.38
- Pembesian kg 851.73 13,086.98 11,146,534.53
- Bekisting m2 30.10 241,870.75 7,281,277.06
i Type B a2
- Beton Mutu 'Fc = 29,5 Mpa m3 2.50 1,206,627.32 3,020,791.50
- Pembesian kg 471.96 13,086.98 6,176,544.52
- Bekisting m2 17.69 241,870.75 4,279,032.19
j Type B a4
- Beton Mutu 'Fc = 29,5 Mpa m3 0.88 1,206,627.32 1,058,815.47
- Pembesian kg 153.68 13,086.98 2,011,191.45
- Bekisting m2 6.20 241,870.75 1,499,840.52
k Type B a5
- Beton Mutu 'Fc = 29,5 Mpa m3 2.90 1,206,627.32 3,493,186.09
- Pembesian kg 606.86 13,086.98 7,941,969.79
- Bekisting m2 20.46 241,870.75 4,948,191.80
l Type B a8
- Beton Mutu 'Fc = 29,5 Mpa m3 4.27 1,206,627.32 5,147,472.15
- Pembesian kg 1,124.59 13,086.98 14,717,513.47
- Bekisting m2 30.15 241,870.75 7,291,532.38
m Type B c1
- Beton Mutu 'Fc = 29,5 Mpa m3 4.56 1,206,627.32 5,500,289.98
- Pembesian kg 801.87 13,086.98 10,494,040.84
- Bekisting m2 25.40 241,870.75 6,142,743.06
n Type B c2
- Beton Mutu 'Fc = 29,5 Mpa m3 0.87 1,206,627.32 1,054,109.63
- Pembesian kg 184.01 13,086.98 2,408,071.45
- Bekisting m2 4.87 241,870.75 1,177,233.31

PEK. STR G. BPOM Page 25


HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME JUMLAH (Rp)
(Rp)
2 Beton Plat Lantai :
a Type Plat S1
- Beton Mutu 'Fc = 29,5 Mpa m3 30.25 1,206,627.32 36,503,471.28
- Pembesian kg 2,810.42 13,086.98 36,779,958.81
- Bekisting m2 232.71 268,105.75 62,391,264.43
b Type Plat S3
- Beton Mutu 'Fc = 29,5 Mpa m3 16.08 1,206,627.32 19,402,386.31
- Pembesian kg 1,580.43 13,086.98 20,682,985.05
- Bekisting m2 107.20 268,105.75 28,740,668.29
c Type Plat S4
- Beton Mutu 'Fc = 29,5 Mpa m3 4.64 1,206,627.32 5,595,854.86
- Pembesian kg 482.76 13,086.98 6,317,810.52
- Bekisting m2 42.16 268,105.75 11,303,338.42
3 Beton Kolom :
a Type K 2
- Beton Mutu 'Fc = 29,5 Mpa m3 1.62 1,206,627.32 1,954,736.26
- Pembesian kg 325.01 13,086.98 4,253,346.44
- Bekisting m2 8.48 210,273.25 1,782,696.61
b Type K 3
- Beton Mutu 'Fc = 29,5 Mpa m3 39.69 1,206,627.32 47,891,038.33
- Pembesian kg 7,420.60 13,086.98 97,113,160.62
- Bekisting m2 178.04 210,273.25 37,436,628.88
SUB TOTAL LANTAI TRIBUN C,10 836,024,877.86

PEK. STR G. BPOM Page 26


HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME JUMLAH (Rp)
(Rp)

C,11 LANTAI ATAP DAK


1 Beton Balok :
a Type B 1
- Beton Mutu 'Fc = 29,5 Mpa m3 10.92 1,206,627.32 13,176,370.33
- Pembesian kg 1,700.58 13,086.98 22,255,404.86
- Bekisting m2 60.84 241,870.75 14,715,416.43
b Type B 2
- Beton Mutu 'Fc = 29,5 Mpa m3 20.94 1,206,627.32 25,271,602.59
- Pembesian kg 3,599.03 13,086.98 47,100,438.52
- Bekisting m2 116.69 241,870.75 28,223,414.08
c Type B 3
- Beton Mutu 'Fc = 29,5 Mpa m3 6.78 1,206,627.32 8,176,106.72
- Pembesian kg 1,185.12 13,086.98 15,509,608.18
- Bekisting m2 37.75 241,870.75 9,131,104.55
d Type B 4
- Beton Mutu 'Fc = 29,5 Mpa m3 6.28 1,206,627.32 7,578,102.22
- Pembesian kg 938.28 13,086.98 12,279,256.79
- Bekisting m2 34.99 241,870.75 8,463,251.04
e Type B 5
- Beton Mutu 'Fc = 29,5 Mpa m3 0.83 1,206,627.32 996,674.17
- Pembesian kg 110.94 13,086.98 1,451,885.93
- Bekisting m2 4.60 241,870.75 1,113,089.19
f Type B 6
- Beton Mutu 'Fc = 29,5 Mpa m3 25.21 1,206,627.32 30,424,745.89
- Pembesian kg 4,866.24 13,086.98 63,684,303.94
- Bekisting m2 175.30 241,870.75 42,400,474.59
g Type B a1
- Beton Mutu 'Fc = 29,5 Mpa m3 2.97 1,206,627.32 3,583,683.14
- Pembesian kg 593.81 13,086.98 7,771,175.48
- Bekisting m2 20.99 241,870.75 5,076,383.30
h Type B a2
- Beton Mutu 'Fc = 29,5 Mpa m3 2.04 1,206,627.32 2,461,519.73
- Pembesian kg 384.58 13,086.98 5,033,014.11
- Bekisting m2 14.42 241,870.75 3,486,808.73
i Type B a3
- Beton Mutu 'Fc = 29,5 Mpa m3 1.91 1,206,627.32 2,298,625.04
- Pembesian kg 428.81 13,086.98 5,611,836.63
- Bekisting m2 13.46 241,870.75 3,256,064.04
j Type B a4
- Beton Mutu 'Fc = 29,5 Mpa m3 0.85 1,206,627.32 1,022,616.65
- Pembesian kg 148.81 13,086.98 1,947,527.75
- Bekisting m2 5.99 241,870.75 1,448,563.92
k Type B a5
- Beton Mutu 'Fc = 29,5 Mpa m3 3.55 1,206,627.32 4,287,750.18
- Pembesian kg 744.90 13,086.98 9,748,459.29
- Bekisting m2 25.11 241,870.75 6,073,713.15
l Type B c1
- Beton Mutu 'Fc = 29,5 Mpa m3 8.63 1,206,627.32 10,416,089.68
- Pembesian kg 1,518.53 13,086.98 19,872,928.68
- Bekisting m2 48.09 241,870.75 11,632,725.35
2 Beton Plat Lantai :
Type Plat S4
- Beton Mutu 'Fc = 29,5 Mpa m3 42.53 1,206,627.32 51,320,598.96
- Pembesian kg 4,608.79 13,086.98 60,315,173.48
- Bekisting m2 386.66 268,105.75 103,664,964.98
3 Beton Kolom :
Type K 3
- Beton Mutu 'Fc = 29,5 Mpa m3 26.46 1,206,627.32 31,927,358.89
- Pembesian kg 5,123.51 13,086.98 67,051,227.39
- Bekisting m2 118.69 268,105.75 31,822,007.68
SUB TOTAL LANTAI ATAP DAK C,11 803,082,066.25

SUB TOTAL PEKERJAAN STRUKTUR ATAS C 18,489,107,279.26

PEK. STR G. BPOM Page 27


HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME JUMLAH (Rp)
(Rp)

D RANGKA ATAP BAJA


1 Baut angkur M22, Panjang Baut 90cm bh 72.00 175,000.00 12,600,000.00
2 Grouting ukuran 250 x 250mm, tebal 50mm m2 1.13 2,500,000.00 2,812,500.00
3 Base Plate ukuran 250 x 250 mm, tebal 25 mm kg 220.78 25,982.00 5,736,338.44
4 Balok & Kolom Baja WF 150 x 75 x 5 x 7mm kg 8,210.45 28,281.00 232,199,679.89
5 Baut HTB M16 bh 216.00 3,200.00 691,200.00
6 Plate tebal 8 mm kg 37.52 25,982.00 974,718.63
7 Plate tebal 10 mm kg 108.62 25,982.00 2,822,278.51
8 Stiffener kg 309.09 25,982.00 8,030,873.81
9 Balok Gording Baja C 150 x 50 x 20 x 2,3mm kg 1,663.71 28,281.00 47,051,292.01
10 Trakstang Ø12 kg 106.99 28,281.00 3,025,677.85
11 Pekerjaan Pengecatan Anti Karat m2 482.27 31,941.25 15,404,306.64
SUB TOTAL RANGKA ATAP BAJA D 331,348,865.78

SUB TOTAL PEKERJAAN STRUKTUR I 28,110,989,181.78

PEK. STR G. BPOM Page 28


BILL OF QUANTITY / B.O.Q
PROYEK : PERENCANAAN PEMBANGUNAN GEDUNG - D DI AREA PERKANTORAN BADAN POM
Jl. PERCETAKAN NEGARA No. 23 Kec. JOHAR BARU, JAKARTA PUSAT
PEKERJAAN : FINISHING ARSITEKTUR

REKAPITULASI UTAMA
PEKERJAAN GEDUNG BPOM ARSITEKTUR
I PEKERJAAN LANTAI SATU Rp. 1,295,410,842.66
A PEKERJAAN DINDING DAN LAPISAN Rp. 778,050,946.96
B PEKERJAAN LANTAI Rp. 245,906,747.88
C PEKERJAAN PLAFOND Rp. 46,967,590.69
D PEKERJAAN PINTU & JENDELA Rp. 75,023,000.00
E PEKERJAAN SANITAIR Rp. 60,969,298.91
F PEKERJAAN TANGGA Rp. 88,493,258.21
II PEKERJAAN LANTAI MEZZANINE Rp. 725,682,541.36
A PEKERJAAN DINDING DAN LAPISAN Rp. 406,847,490.94
B PEKERJAAN LANTAI Rp. 126,773,529.44
C PEKERJAAN PLAFOND Rp. 165,986,761.56
D PEKERJAAN PINTU & JENDELA Rp. 14,100,000.00
E PEKERJAAN TANGGA Rp. 11,974,759.42
III PEKERJAAN LANTAI DUA Rp. 1,744,383,256.95
A PEKERJAAN DINDING DAN LAPISAN Rp. 939,514,820.12
B PEKERJAAN LANTAI Rp. 378,391,055.32
C PEKERJAAN PLAFOND Rp. 284,785,392.07
D PEKERJAAN PINTU & JENDELA Rp. 57,862,000.00
E PEKERJAAN SANITAIR Rp. 64,380,591.77
F PEKERJAAN TANGGA Rp. 19,449,397.67
IV PEKERJAAN LANTAI TIGA Rp. 1,744,383,256.95
A PEKERJAAN DINDING DAN LAPISAN Rp. 939,514,820.12
B PEKERJAAN LANTAI Rp. 378,391,055.32
C PEKERJAAN PLAFOND Rp. 284,785,392.07
D PEKERJAAN PINTU & JENDELA Rp. 57,862,000.00
E PEKERJAAN SANITAIR Rp. 64,380,591.77
F PEKERJAAN TANGGA Rp. 19,449,397.67
V PEKERJAAN LANTAI EMPAT Rp. 1,744,383,256.95
A PEKERJAAN DINDING DAN LAPISAN Rp. 939,514,820.12
B PEKERJAAN LANTAI Rp. 378,391,055.32
C PEKERJAAN PLAFOND Rp. 284,785,392.07
D PEKERJAAN PINTU & JENDELA Rp. 57,862,000.00
E PEKERJAAN SANITAIR Rp. 64,380,591.77
F PEKERJAAN TANGGA Rp. 19,449,397.67
VI PEKERJAAN LANTAI LIMA Rp. 2,826,421,617.37
A PEKERJAAN DINDING DAN LAPISAN Rp. 2,009,483,819.45
B PEKERJAAN LANTAI Rp. 380,149,943.26
C PEKERJAAN PLAFOND Rp. 276,286,594.33
D PEKERJAAN PINTU & JENDELA Rp. 70,868,000.00
E PEKERJAAN SANITAIR Rp. 70,183,862.65
F PEKERJAAN TANGGA Rp. 19,449,397.67

PEK. ARS G. BPOM Page 29


VII PEKERJAAN LANTAI ENAM Rp. 2,826,421,617.37
A PEKERJAAN DINDING DAN LAPISAN Rp. 2,009,483,819.45
B PEKERJAAN LANTAI Rp. 380,149,943.26
C PEKERJAAN PLAFOND Rp. 276,286,594.33
D PEKERJAAN PINTU & JENDELA Rp. 70,868,000.00
E PEKERJAAN SANITAIR Rp. 70,183,862.65
F PEKERJAAN TANGGA Rp. 19,449,397.67
VIII PEKERJAAN LANTAI TUJUH Rp. 2,413,973,712.52
A PEKERJAAN DINDING DAN LAPISAN Rp. 1,592,024,263.35
B PEKERJAAN LANTAI Rp. 379,666,422.58
C PEKERJAAN PLAFOND Rp. 277,914,837.80
D PEKERJAAN PINTU & JENDELA Rp. 67,882,000.00
E PEKERJAAN SANITAIR Rp. 63,760,169.27
F PEKERJAAN TANGGA Rp. 32,726,019.52
IX PEKERJAAN LANTAI DELAPAN Rp. 1,831,863,417.23
A PEKERJAAN DINDING DAN LAPISAN Rp. 1,369,097,220.29
B PEKERJAAN LANTAI Rp. 226,388,344.91
C PEKERJAAN PLAFOND Rp. 106,411,980.52
D PEKERJAAN PINTU & JENDELA Rp. 40,766,000.00
E PEKERJAAN SANITAIR Rp. 63,760,169.27
F PEKERJAAN TANGGA Rp. 25,439,702.24
VI PEKERJAAN LANTAI TRIBUN DAN PENUTUP ATAP Rp. 2,008,889,075.41
VII PEKERJAAN FASADE Rp. 778,316,500.00

TOTAL Rp. 19,940,129,094.79

PEK. ARS G. BPOM Page 30


BILL OF QUANTITY / B.O.Q
PROYEK : PERENCANAAN PEMBANGUNAN GEDUNG - D DI AREA PERKANTORAN BADAN POM
Jl. PERCETAKAN NEGARA No. 23 Kec. JOHAR BARU, JAKARTA PUSAT
PEKERJAAN : FINISHING ARSITEKTUR

HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME JUMLAH (Rp)
(Rp)

<2.2> PEKERJAAN GEDUNG BPOM ARSITEKTUR

I PEKERJAAN LANTAI SATU


A PEKERJAAN DINDING DAN LAPISAN

1 Dinding pasangan Light Concrete block tebal 100 mm m2 841.25 375,000.00 315,467,475.00
2 Beton Kolom & Ring Balok Praktis m3 10.09 5,138,399.75 51,871,935.83
Plester + aci permukaan Light Concrete Block tebal 15 mm,
3 m2 1,682.49 71,579.20 120,431,517.26
menggunakan Semen Instan
Plester + aci permukaan Beton tebal 15 mm, menggunakan Semen
4 m2 328.54 71,579.20 23,516,344.05
Instan
5 Dinding Homogeneous Tile 60 x 60cm, area toilet,Mushola dll m2 112.62 315,102.03 35,487,893.48
6 Dinding Granit 60 x 120 cm area Lobby & Lift m2 141.22 315,102.03 44,497,574.31
7 Dinding Kaca Sun Energy Glass 8mm (KC1) m2 122.40 600,000.00 73,437,000.00
8 Dinding Kaca Tempered Clear Glass 8 mm (KC5) m2 38.68 766,260.55 29,635,126.77
9 ACP pembungkus Kolom m2 85.05 650,000.00 55,282,500.00
10 Cat tembok untuk dinding dalam m2 822.54 24,553.93 20,196,663.24
11 Cat tembok untuk dinding luar m2 335.06 24,553.93 8,226,917.02
SUB TOTAL PEKERJAAN DINDING DAN LAPISAN A 778,050,946.96

B PEKERJAAN LANTAI

1 Lantai Homogenius Tile uk. 120 x 120 cm m2 363.27 438,515.76 159,299,620.14


1 Lantai Homogenius Tile uk. 60 x 60cm m2 78.86 292,343.84 23,054,235.22
2 Lantai Homogenius Tile uk. 60 x 60cm area Toilet m2 41.58 292,343.84 12,155,656.87
3 Lantai Homogenius Tile 30 x 30 cm m2 16.04 221,673.65 3,555,645.35
4 Lantai Keramik Tile uk. 30 x 30cm m2 52.28 221,673.65 11,588,655.07
5 Lantai Floor Hardener 3kg m2 390.43 42,190.50 16,472,436.92
6 Plint Homogenius Tile 10cm m' 153.38 128,964.00 19,780,498.32
SUB TOTAL PEKERJAAN LANTAI B 245,906,747.88

C PEKERJAAN PLAFOND

1 Plafond Gypsum board tebal 9mm + Water Resistance m2 41.58 129,329.75 5,377,531.01
2 Plafond Akustik Tile tebal 9mm m2 90.68 178,178.00 16,157,181.04
3 Plafond Calcium Silicate m2 59.54 147,933.50 8,807,664.72
4 Plafond Beton Expose finish aci m2 112.80 43,422.50 4,898,058.00
5 List Plafond m' 182.66 23,256.75 4,248,077.96
6 Cat Plafond m2 304.60 24,553.93 7,479,077.97
SUB TOTAL PEKERJAAN PLAFOND C 46,967,590.69

PEK. ARS G. BPOM Page 31


HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME JUMLAH (Rp)
(Rp)

D PEKERJAAN PINTU & JENDELA

1 Pintu Type PG1, Uk. 2400 x 900 mm Unit 1.00 1,728,000.00 1,728,000.00
2 Pintu Type PG2, Uk. 2400 x 1800 mm Unit 2.00 3,456,000.00 6,912,000.00
3 Pintu Type PG3, Uk. 3000 x 1800 mm Unit 2.00 4,320,000.00 8,640,000.00
4 Pintu Type PS1, Uk. 2400 x 1000 mm Unit 2.00 4,320,000.00 8,640,000.00
5 Pintu Type PS2, Uk. 2400 x 900 mm Unit 2.00 1,728,000.00 3,456,000.00
6 Pintu Type PS3, Uk. 2400 x 800 mm Unit 2.00 1,536,000.00 3,072,000.00
7 Pintu Type PD1, Uk. 2400 x 1470mm Unit 3.00 2,850,000.00 8,550,000.00
8 Pintu Type PD2, Uk. 2400 x 1000mm Unit 2.00 2,600,000.00 5,200,000.00
9 Pintu Type PB1, Uk. 2400 x 1000 mm Unit 3.00 1,800,000.00 5,400,000.00
10 Pintu Type PB3, Uk. 2400 x 2400mm Unit 2.00 3,750,000.00 7,500,000.00
11 Pintu Type PB4, Uk. 2400 x 1900 mm Unit 2.00 3,400,000.00 6,800,000.00
12 Jendela, Uk. 650 x 650 mm (R.GWT) Unit 1.00 700,000.00 700,000.00
13 Jendela, Uk. 650 x 650 mm (R.Kapasitor) Unit 1.00 700,000.00 700,000.00
14 Jendela, Uk. 650 x 650 mm (R.Trafo) Unit 1.00 700,000.00 700,000.00
15 Jendela, Uk. 650 x 650 mm (R.MV) Unit 1.00 700,000.00 700,000.00
16 Jendela, Uk. 650 x 650 mm (R.Genset) Unit 1.00 700,000.00 700,000.00
17 Jendela, Uk. 350 x 350 mm (R.Pompa STP) Unit 1.00 575,000.00 575,000.00
18 Jendela, Uk. 200 x 200 mm (R.Bakpel) Unit 1.00 500,000.00 500,000.00
19 Jendela, Uk. 300 x 300 mm (R.Toilet Difabel) Unit 1.00 500,000.00 500,000.00
20 Jendela, Uk. 300 x 300 mm (R.Pantry) Unit 1.00 550,000.00 550,000.00
21 Jendela, Uk. 300 x 300 mm (R.Laktasi) Unit 1.00 550,000.00 550,000.00
22 Jendela, Uk. 450 x 450 mm (R.Toilet Pria) Unit 1.00 650,000.00 650,000.00
23 Jendela, Uk. 450 x 450 mm (R.Toilet Wanita) Unit 1.00 650,000.00 650,000.00
24 Jendela, Uk. 450 x 450 mm (R.Panel) Unit 1.00 650,000.00 650,000.00
25 Jendela, Uk. 700 x 700 mm (R.LVMDP) Unit 1.00 1,000,000.00 1,000,000.00
SUB TOTAL PEKERJAAN PINTU & JENDELA D 75,023,000.00

PEK. ARS G. BPOM Page 32


HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME JUMLAH (Rp)
(Rp)
E PEKERJAAN SANITAIR

1 Closet Duduk set 6.00 3,177,982.50 19,067,895.00


2 Closet Duduk Difable set 1.00 3,177,982.50 3,177,982.50
3 Closet Duduk Jongkok set 2.00 669,817.50 1,339,635.00
4 Grab Barr set 1.00 400,000.00 400,000.00
5 Jet Spray unit 9.00 300,000.00 2,700,000.00
6 Wastafel unit 5.00 727,292.50 3,636,462.50
7 Wastafel Difabel unit 1.00 727,292.50 727,292.50
8 Floor Drain bh 13.00 65,422.50 850,492.50
9 Kitchen zink bh 2.00 377,767.50 755,535.00
10 Kran Kitchen zink bh 2.00 96,511.25 193,022.50
11 Kaca cermin tebal 6 mm, Bevel tepi + Rangka m2 4.73 390,142.50 1,843,423.31
12 Meja Wastafel Beton Lapis Granit L= 60 cm m' 4.28 949,146.26 4,062,345.99
13 Meja Pantry Beton Lapis Homogenius Tile, Lebar 60 cm m' 4.45 949,146.26 4,223,700.86
14 Paper Holder bh 9.00 105,000.00 945,000.00
15 Robe Hook bh 11.00 150,000.00 1,650,000.00
16 Urinal (moslem Type) set 4.00 2,587,500.00 10,350,000.00
17 Partisi Pembates Urinoir unit 2.00 1,750,000.00 3,500,000.00
18 Hand Dryer unit 2.00 250,000.00 500,000.00
19 Soap Dispenser, Type Initial Healthcear unit 3.00 150,000.00 450,000.00
20 Kran tempat Wudhu / Janitor unit 1.00 96,511.25 96,511.25
21 Shower Spray unit 2.00 250,000.00 500,000.00
SUB TOTAL PEKERJAAN SANITAIR E 60,969,298.91

F PEKERJAAN TANGGA

1 Tangga Type T #1
- Antrade & Optrade, Floor Hardener m2 17.60 42,190.50 742,388.26
- Anti slip / Step Nozing m' 25.65 95,000.00 2,436,750.00
- Hand Railling m' 7.81 550,000.00 4,295,500.00
Bahan : Hand Ralling Besi Pipa Ø 2" Finish Cat
Ralling Besi Pipa Ø 1,5" Finish Cat
Tiang Ralling Besi Pipa Ø 1,5" Finish Cat
- Plester + acian permukan beton, campuran 1 pc : 3 psr m2 16.18 110,488.07 1,787,542.29
- Cat Tembok m2 16.99 27,226.93 462,518.29

2 Tangga Type T #2
- Antrade & Optrade, Floor Hardener m2 17.60 42,190.50 742,388.26
- Anti slip / Step Nozing m' 25.65 95,000.00 2,436,750.00
- Hand Railling m' 7.81 550,000.00 4,295,500.00
Bahan : Hand Ralling Besi Pipa Ø 2" Finish Cat
Ralling Besi Pipa Ø 1,5" Finish Cat
Tiang Ralling Besi Pipa Ø 1,5" Finish Cat
- Plester + acian permukan beton, campuran 1 pc : 3 psr m2 16.18 110,488.07 1,787,542.29
- Cat Tembok m2 16.99 27,226.93 462,518.29
3 Tangga LT. Mezzanine
Antrade & Optrade, Homogenius Tile uk. 120 x 120 cm (HT1/
- m2 36.92 438,515.76 16,187,809.28
Polished)
- Anti slip / Step Nozing m' 65.55 95,000.00 6,227,250.00
- Hand Railling m' 44.58 550,000.00 24,519,000.00
Bahan : Hand Ralling pipa Stainless Steel Ø 2" hairline
Ralling Plat Stainlees Steel 5mm
Kaca Tempered tebal 10 mm + Acc.
- Plester + acian permukan beton, campuran 1 pc : 3 psr m2 158.98 110,488.07 17,564,951.42
- Cat Tembok m2 166.92 27,226.93 4,544,849.84
SUB TOTAL PEKERJAAN TANGGA F 88,493,258.21

SUB TOTAL PEKERJAAN LANTAI SATU I 1,295,410,842.66

PEK. ARS G. BPOM Page 33


HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME JUMLAH (Rp)
(Rp)

II PEKERJAAN LANTAI MEZZANINE


A PEKERJAAN DINDING DAN LAPISAN

1 Dinding pasangan Light Concrete block tebal 100 mm m2 456.50 375,000.00 171,185,700.00
2 Beton Kolom & Ring Balok Praktis m3 5.48 5,138,399.75 28,147,857.86
Plester + aci permukaan Light Concrete Block tebal 15 mm,
3 m2 912.99 71,579.20 65,351,122.44
menggunakan Semen Instan
Plester + aci permukaan Beton tebal 15 mm, menggunakan Semen
4 m2 328.54 71,579.20 23,516,344.05
Instan
5 Dinding Granit 60 x 120 cm area Lobby & Lift m2 141.22 315,102.03 44,497,574.31
6 Dinding Kaca Sun Energy Glass 8mm (KC1) m2 139.62 400,000.00 55,846,000.00
7 Cat tembok untuk dinding dalam m2 657.67 24,553.93 16,148,407.70
8 Cat tembok untuk dinding luar m2 87.75 24,553.93 2,154,484.59
SUB TOTAL PEKERJAAN DINDING DAN LAPISAN A 406,847,490.94

B PEKERJAAN LANTAI

1 Lantai Homogenius Tile uk. 120 x 120 cm m2 260.04 438,515.76 114,031,638.23


2 Lantai Homogenius Tile uk. 60 x 60 cm m2 7.71 292,343.84 2,253,971.01
3 Lantai Keramik Tile uk. 30 x 30cm m2 22.64 221,673.65 5,018,691.44
4 Lantai Floor Hardener 3kg m2 21.73 42,190.50 916,799.57
5 Plint Homogenius Tile 10cm m' 35.30 128,964.00 4,552,429.20
SUB TOTAL PEKERJAAN LANTAI B 126,773,529.44

C PEKERJAAN PLAFOND

1 Plafond Accoustic Metal Ceiling m2 297.46 178,178.00 53,000,827.88


2 Plafond Hollow Metal Ceilling m2 446.27 178,178.00 79,515,496.06
3 Plafond Beton Expose finish aci m2 108.28 43,422.50 4,701,788.30
4 List Plafond m' 337.47 23,256.75 7,848,455.42
5 Cat Plafond m2 852.01 24,553.93 20,920,193.90
SUB TOTAL PEKERJAAN PLAFOND C 165,986,761.56

PEK. ARS G. BPOM Page 34


HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME JUMLAH (Rp)
(Rp)

D PEKERJAAN PINTU & JENDELA

1 Pintu Type PD1, Uk. 2400 x 1470mm Unit 1.00 2,850,000.00 2,850,000.00
2 Pintu Type PD2, Uk. 2400 x 1000mm Unit 2.00 2,600,000.00 5,200,000.00
3 Pintu Type PB1, Uk. 2400 x 1000 mm Unit 3.00 1,800,000.00 5,400,000.00
4 Jendela, Uk. 450 x 450 mm (R.Panel) Unit 1.00 650,000.00 650,000.00
SUB TOTAL PEKERJAAN PINTU & JENDELA D 14,100,000.00

E PEKERJAAN TANGGA

1 Tangga Type T #1
- Antrade & Optrade, Floor Hardener m2 17.60 42,190.50 742,388.26
- Anti slip / Step Nozing m' 25.65 95,000.00 2,436,750.00
- Hand Railling m' 7.81 550,000.00 4,295,500.00

PEK. ARS G. BPOM Page 35


HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME JUMLAH (Rp)
(Rp)
Bahan : Hand Ralling Besi Pipa Ø 2" Finish Cat
Ralling Besi Pipa Ø 1,5" Finish Cat
Tiang Ralling Besi Pipa Ø 1,5" Finish Cat
- Plester + acian permukan beton, campuran 1 pc : 3 psr m2 16.18 110,488.07 1,787,542.29
- Cat Tembok m2 16.99 27,226.93 462,518.29

2 Tangga Type T #2
- Antrade & Optrade, Floor Hardener m2 17.60 42,190.50 742,388.26
- Anti slip / Step Nozing m' 25.65 95,000.00 2,436,750.00
- Hand Railling m' 7.81 550,000.00 4,295,500.00
Bahan : Hand Ralling Besi Pipa Ø 2" Finish Cat
Ralling Besi Pipa Ø 1,5" Finish Cat
Tiang Ralling Besi Pipa Ø 1,5" Finish Cat
- Plester + acian permukan beton, campuran 1 pc : 3 psr m2 16.18 110,488.07 1,787,542.29
- Cat Tembok m2 16.99 27,226.93 462,518.29
SUB TOTAL PEKERJAAN TANGGA E 11,974,759.42

SUB TOTAL PEKERJAAN LANTAI MEZZANINE II 725,682,541.36

PEK. ARS G. BPOM Page 36


HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME JUMLAH (Rp)
(Rp)

III PEKERJAAN LANTAI DUA


A PEKERJAAN DINDING DAN LAPISAN

1 Dinding pasangan Light Concrete block tebal 100 mm m2 970.20 375,000.00 363,825,000.00
2 Beton Kolom & Ring Balok Praktis m3 11.64 5,138,399.75 59,823,305.25
Plester + aci permukaan Light Concrete Block tebal 15 mm,
3 m2 1,940.40 71,579.20 138,892,279.68
menggunakan Semen Instan
Plester + aci permukaan Beton tebal 15 mm, menggunakan Semen
4 m2 396.58 71,579.20 28,386,592.82
Instan
5 Dinding Granit 60 x 120 cm area Lobby & Lift m2 99.99 315,102.03 31,506,421.78
6 Dinding Kaca Sun Energy Glass 8mm (KC1) m2 388.33 400,000.00 155,332,800.00
7 Dinding Kaca Tempered Clear Glass 8 mm (KC5) m2 69.72 700,920.55 48,868,180.75
8 Dinding Homogenius Tile 60 x 60 cm area Toilet m2 154.67 292,343.84 45,215,652.36
9 Dinding Partisi Kaca 12mm tempered Clear Glass m2 54.57 766,260.55 41,816,370.73
10 Cat tembok untuk dinding dalam m2 679.08 24,553.93 16,674,082.78
11 Cat tembok untuk dinding luar m2 373.63 24,553.93 9,174,133.97
SUB TOTAL PEKERJAAN DINDING DAN LAPISAN A 939,514,820.12

B PEKERJAAN LANTAI

1 Lantai Homogenius Tile uk. 120 x 120 cm m2 533.75 438,515.76 234,057,786.90


2 Lantai Homogenius Tile uk. 60 x 60cm m2 75.23 292,343.84 21,993,027.08
3 Lantai Homogenius Tile uk. 60 x 60cm area Toilet m2 46.88 292,343.84 13,705,079.22
4 Lantai Keramik Tile uk. 30 x 30cm m2 222.95 221,673.65 49,422,140.27
5 Lantai Karpet m2 57.53 68,334.75 3,931,298.17
6 Screed Perataan Lantai tebal 3 cm di Area Karpet m2 57.53 134,131.14 7,716,564.48
7 Lantai Floor Hardener 3kg m2 34.36 42,190.50 1,449,665.58
8 Lantai Parquet m2 53.81 412,513.75 22,197,364.89
9 Waterprofing Coating area Toilet, Janitor, dll m2 46.88 90,000.00 4,219,200.00
10 Scred Plindung Waterprofing m2 46.88 75,919.03 3,559,084.13
11 Plint Homogenius Tile 10cm m' 125.15 128,964.00 16,139,844.60
SUB TOTAL PEKERJAAN LANTAI B 378,391,055.32

C PEKERJAAN PLAFOND

1 Plafond Gypsum board tebal 9mm m2 144.64 129,329.75 18,706,255.04


1 Plafond Calsiboard tebal + Water Resistance m2 46.88 221,900.25 10,402,683.72
2 Plafond Akustik Tile tebal 9mm m2 591.28 370,334.25 218,971,235.34
3 Plafond Akustik Metal Celing m2 31.17 178,178.00 5,553,808.26
4 Plafond Beton Expose finish aci m2 61.65 43,422.50 2,676,997.13
5 List Plafond m' 332.80 23,256.75 7,739,846.40
6 Cat Plafond m2 844.45 24,553.93 20,734,566.19
SUB TOTAL PEKERJAAN PLAFOND C 284,785,392.07

PEK. ARS G. BPOM Page 37


HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME JUMLAH (Rp)
(Rp)

D PEKERJAAN PINTU & JENDELA

1 Pintu Type PG1, Uk. 2400 x 900 mm Unit 9.00 1,728,000.00 15,552,000.00
2 Pintu Type PG2, Uk. 2400 x 1800 mm Unit 2.00 3,456,000.00 6,912,000.00
3 Pintu Type PS1, Uk. 2400 x 1000 mm Unit 1.00 4,320,000.00 4,320,000.00
4 Pintu Type PS2, Uk. 2400 x 900 mm Unit 2.00 1,728,000.00 3,456,000.00
5 Pintu Type PS3, Uk. 2400 x 800 mm Unit 2.00 1,536,000.00 3,072,000.00
6 Pintu Type PS4, Uk. 2400 x 800 mm Unit 1.00 2,850,000.00 2,850,000.00
7 Pintu Type PD1, Uk. 2400 x 1470mm Unit 2.00 2,850,000.00 5,700,000.00
8 Pintu Type PD2, Uk. 2400 x 1000mm Unit 2.00 2,600,000.00 5,200,000.00
9 Pintu Type PB1, Uk. 2400 x 1000 mm Unit 2.00 1,800,000.00 3,600,000.00
10 Pintu Type PB2, Uk. 2400 x 1900 mm Unit 1.00 3,750,000.00 3,750,000.00
11 Jendela, Uk. 450 x 450 mm (R.Toilet Pria) Unit 1.00 650,000.00 650,000.00
12 Jendela, Uk. 450 x 450 mm (R.Toilet Wanita) Unit 1.00 650,000.00 650,000.00
13 Jendela, Uk. 300 x 300 mm (R.Toilet Difabel) Unit 1.00 500,000.00 500,000.00
14 Jendela, Uk. 450 x 450 mm (R.Panel) Unit 1.00 650,000.00 650,000.00
15 Jendela, Uk. 200 x 200 mm (R.Bakpel) Unit 1.00 500,000.00 500,000.00
16 Jendela, Uk. 300 x 300 mm (R.Pantry) Unit 1.00 500,000.00 500,000.00
SUB TOTAL PEKERJAAN PINTU & JENDELA D 57,862,000.00

E PEKERJAAN SANITAIR

1 Closet Duduk set 7.00 3,177,982.50 22,245,877.50


2 Closet Duduk Difable unit 1.00 3,177,982.50 3,177,982.50
3 Closet Duduk Jongkok unit 2.00 669,817.50 1,339,635.00
4 Grab Barr bh 1.00 400,000.00 400,000.00
5 Jet Spray bh 10.00 300,000.00 3,000,000.00
6 Wastafel bh 6.00 727,292.50 4,363,755.00
7 Wastafel Difabel m2 1.00 727,292.50 727,292.50
8 Floor Drain m' 15.00 65,422.50 981,337.50
9 Kitchen zink m' 1.00 377,767.50 377,767.50
10 Kran Kitchen zink bh 1.00 96,511.25 96,511.25
11 Kaca cermin tebal 6 mm, Bevel tepi + Rangka bh 5.93 390,142.50 2,311,594.31
12 Meja Wastafel Beton Lapis Granit L= 60 cm set 4.98 949,146.26 4,726,748.37
13 Meja Pantry Beton Lapis Homogenius Tile, Lebar 60 cm unit 2.25 949,146.26 2,135,579.09
14 Paper Holder unit 10.00 105,000.00 1,050,000.00
15 Robe Hook unit 12.00 150,000.00 1,800,000.00
16 Urinal (moslem Type) unit 4.00 2,587,500.00 10,350,000.00
17 Partisi Pembates Urinoir m2 2.00 1,750,000.00 3,500,000.00
18 Hand Dryer unit 2.00 250,000.00 500,000.00
19 Soap Dispenser, Type Initial Healthcear unit 3.00 150,000.00 450,000.00
20 Kran tempat Wudhu / Janitor unit 1.00 96,511.25 96,511.25
21 Shower Spray set 3.00 250,000.00 750,000.00
SUB TOTAL PEKERJAAN SANITAIR E 64,380,591.77

PEK. ARS G. BPOM Page 38


HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME JUMLAH (Rp)
(Rp)

F PEKERJAAN TANGGA

1 Tangga Type T #1
- Antrade & Optrade, Floor Hardener m2 17.60 42,190.50 742,388.26
- Anti slip / Step Nozing m' 25.65 95,000.00 2,436,750.00
- Hand Railling m' 7.81 550,000.00 4,295,500.00
Bahan : Hand Ralling Besi Pipa Ø 2" Finish Cat
Ralling Besi Pipa Ø 1,5" Finish Cat
Tiang Ralling Besi Pipa Ø 1,5" Finish Cat
- Plester + acian permukan beton, campuran 1 pc : 3 psr m2 16.18 110,488.07 1,787,542.29
- Cat Tembok m2 16.99 27,226.93 462,518.29

2 Tangga Type T #02


- Antrade & Optrade, Floor Hardener m2 17.60 42,190.50 742,388.26
- Anti slip / Step Nozing m' 25.65 95,000.00 2,436,750.00
- Hand Railling m' 7.81 550,000.00 4,295,500.00
Bahan : Hand Ralling Besi Pipa Ø 2" Finish Cat
Ralling Besi Pipa Ø 1,5" Finish Cat
Tiang Ralling Besi Pipa Ø 1,5" Finish Cat
- Plester + acian permukan beton, campuran 1 pc : 3 psr m2 16.18 110,488.07 1,787,542.29
- Cat Tembok m2 16.99 27,226.93 462,518.29
SUB TOTAL PEKERJAAN TANGGA F 19,449,397.67

SUB TOTAL PEKERJAAN LANTAI DUA III 1,744,383,256.95

PEK. ARS G. BPOM Page 39


HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME JUMLAH (Rp)
(Rp)

IV PEKERJAAN LANTAI TIGA


A PEKERJAAN DINDING DAN LAPISAN

1 Dinding pasangan Light Concrete block tebal 100 mm m2 970.20 375,000.00 363,825,000.00
2 Beton Kolom & Ring Balok Praktis m3 11.64 5,138,399.75 59,823,305.25
Plester + aci permukaan Light Concrete Block tebal 15 mm,
3 m2 1,940.40 71,579.20 138,892,279.68
menggunakan Semen Instan
Plester + aci permukaan Beton tebal 15 mm, menggunakan Semen
4 m2 396.58 71,579.20 28,386,592.82
Instan
5 Dinding Granit 60 x 120 cm area Lobby & Lift m2 99.99 315,102.03 31,506,421.78
6 Dinding Kaca Sun Energy Glass 8mm (KC1) m2 388.33 400,000.00 155,332,800.00
7 Dinding Kaca Tempered Clear Glass 8 mm (KC5) m2 69.72 700,920.55 48,868,180.75
8 Dinding Homogenius Tile 60 x 60 cm area Toilet m2 154.67 292,343.84 45,215,652.36
9 Dinding Partisi Kaca 12mm tempered Clear Glass m2 54.57 766,260.55 41,816,370.73
10 Cat tembok untuk dinding dalam m2 679.08 24,553.93 16,674,082.78
11 Cat tembok untuk dinding luar m2 373.63 24,553.93 9,174,133.97
SUB TOTAL PEKERJAAN DINDING DAN LAPISAN A 939,514,820.12

B PEKERJAAN LANTAI

1 Lantai Homogenius Tile uk. 120 x 120 cm m2 533.75 438,515.76 234,057,786.90


2 Lantai Homogenius Tile uk. 60 x 60cm m2 75.23 292,343.84 21,993,027.08
3 Lantai Homogenius Tile uk. 60 x 60cm area Toilet m2 46.88 292,343.84 13,705,079.22
4 Lantai Keramik Tile uk. 30 x 30cm m2 222.95 221,673.65 49,422,140.27
5 Lantai Karpet m2 57.53 68,334.75 3,931,298.17
6 Screed Perataan Lantai tebal 3 cm di Area Karpet m2 57.53 134,131.14 7,716,564.48
7 Lantai Floor Hardener 3kg m2 34.36 42,190.50 1,449,665.58
8 Lantai Parquet m2 53.81 412,513.75 22,197,364.89
9 Waterprofing Coating area Toilet, Janitor, dll m2 46.88 90,000.00 4,219,200.00
10 Scred Plindung Waterprofing m2 46.88 75,919.03 3,559,084.13
11 Plint Homogenius Tile 10cm m' 125.15 128,964.00 16,139,844.60
SUB TOTAL PEKERJAAN LANTAI B 378,391,055.32

C PEKERJAAN PLAFOND

1 Plafond Gypsum board tebal 9mm m2 144.64 129,329.75 18,706,255.04


1 Plafond Calsiboard tebal + Water Resistance m2 46.88 221,900.25 10,402,683.72
2 Plafond Akustik Tile tebal 9mm m2 591.28 370,334.25 218,971,235.34
3 Plafond Akustik Metal Celing m2 31.17 178,178.00 5,553,808.26
4 Plafond Beton Expose finish aci m2 61.65 43,422.50 2,676,997.13
5 List Plafond m' 332.80 23,256.75 7,739,846.40
6 Cat Plafond m2 844.45 24,553.93 20,734,566.19
SUB TOTAL PEKERJAAN PLAFOND C 284,785,392.07

PEK. ARS G. BPOM Page 40


HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME JUMLAH (Rp)
(Rp)

D PEKERJAAN PINTU & JENDELA

1 Pintu Type PG1, Uk. 2400 x 900 mm Unit 9.00 1,728,000.00 15,552,000.00
2 Pintu Type PG2, Uk. 2400 x 1800 mm Unit 2.00 3,456,000.00 6,912,000.00
3 Pintu Type PS1, Uk. 2400 x 1000 mm Unit 1.00 4,320,000.00 4,320,000.00
4 Pintu Type PS2, Uk. 2400 x 900 mm Unit 2.00 1,728,000.00 3,456,000.00
5 Pintu Type PS3, Uk. 2400 x 800 mm Unit 2.00 1,536,000.00 3,072,000.00
6 Pintu Type PS4, Uk. 2400 x 800 mm Unit 1.00 2,850,000.00 2,850,000.00
7 Pintu Type PD1, Uk. 2400 x 1470mm Unit 2.00 2,850,000.00 5,700,000.00
8 Pintu Type PD2, Uk. 2400 x 1000mm Unit 2.00 2,600,000.00 5,200,000.00
9 Pintu Type PB1, Uk. 2400 x 1000 mm Unit 2.00 1,800,000.00 3,600,000.00
10 Pintu Type PB2, Uk. 2400 x 1900 mm Unit 1.00 3,750,000.00 3,750,000.00
11 Jendela, Uk. 450 x 450 mm (R.Toilet Pria) Unit 1.00 650,000.00 650,000.00
12 Jendela, Uk. 450 x 450 mm (R.Toilet Wanita) Unit 1.00 650,000.00 650,000.00
13 Jendela, Uk. 300 x 300 mm (R.Toilet Difabel) Unit 1.00 500,000.00 500,000.00
14 Jendela, Uk. 450 x 450 mm (R.Panel) Unit 1.00 650,000.00 650,000.00
15 Jendela, Uk. 200 x 200 mm (R.Bakpel) Unit 1.00 500,000.00 500,000.00
16 Jendela, Uk. 300 x 300 mm (R.Pantry) Unit 1.00 500,000.00 500,000.00
SUB TOTAL PEKERJAAN PINTU & JENDELA D 57,862,000.00

E PEKERJAAN SANITAIR

1 Closet Duduk set 7.00 3,177,982.50 22,245,877.50


2 Closet Duduk Difable unit 1.00 3,177,982.50 3,177,982.50
3 Closet Duduk Jongkok unit 2.00 669,817.50 1,339,635.00
4 Grab Barr bh 1.00 400,000.00 400,000.00
5 Jet Spray bh 10.00 300,000.00 3,000,000.00
6 Wastafel bh 6.00 727,292.50 4,363,755.00
7 Wastafel Difabel m2 1.00 727,292.50 727,292.50
8 Floor Drain m' 15.00 65,422.50 981,337.50
9 Kitchen zink m' 1.00 377,767.50 377,767.50
10 Kran Kitchen zink bh 1.00 96,511.25 96,511.25
11 Kaca cermin tebal 6 mm, Bevel tepi + Rangka bh 5.93 390,142.50 2,311,594.31
12 Meja Wastafel Beton Lapis Granit L= 60 cm set 4.98 949,146.26 4,726,748.37
13 Meja Pantry Beton Lapis Homogenius Tile, Lebar 60 cm unit 2.25 949,146.26 2,135,579.09
14 Paper Holder unit 10.00 105,000.00 1,050,000.00
15 Robe Hook unit 12.00 150,000.00 1,800,000.00
16 Urinal (moslem Type) unit 4.00 2,587,500.00 10,350,000.00
17 Partisi Pembates Urinoir m2 2.00 1,750,000.00 3,500,000.00
18 Hand Dryer unit 2.00 250,000.00 500,000.00
19 Soap Dispenser, Type Initial Healthcear unit 3.00 150,000.00 450,000.00
20 Kran tempat Wudhu / Janitor unit 1.00 96,511.25 96,511.25
21 Shower Spray set 3.00 250,000.00 750,000.00
SUB TOTAL PEKERJAAN SANITAIR E 64,380,591.77

PEK. ARS G. BPOM Page 41


HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME JUMLAH (Rp)
(Rp)

F PEKERJAAN TANGGA

1 Tangga Type T #1
- Antrade & Optrade, Floor Hardener m2 17.60 42,190.50 742,388.26
- Anti slip / Step Nozing m' 25.65 95,000.00 2,436,750.00
- Hand Railling m' 7.81 550,000.00 4,295,500.00
Bahan : Hand Ralling Besi Pipa Ø 2" Finish Cat
Ralling Besi Pipa Ø 1,5" Finish Cat
Tiang Ralling Besi Pipa Ø 1,5" Finish Cat
- Plester + acian permukan beton, campuran 1 pc : 3 psr m2 16.18 110,488.07 1,787,542.29
- Cat Tembok m2 16.99 27,226.93 462,518.29

2 Tangga Type T #02


- Antrade & Optrade, Floor Hardener m2 17.60 42,190.50 742,388.26
- Anti slip / Step Nozing m' 25.65 95,000.00 2,436,750.00
- Hand Railling m' 7.81 550,000.00 4,295,500.00
Bahan : Hand Ralling Besi Pipa Ø 2" Finish Cat
Ralling Besi Pipa Ø 1,5" Finish Cat
Tiang Ralling Besi Pipa Ø 1,5" Finish Cat
- Plester + acian permukan beton, campuran 1 pc : 3 psr m2 16.18 110,488.07 1,787,542.29
- Cat Tembok m2 16.99 27,226.93 462,518.29
SUB TOTAL PEKERJAAN TANGGA F 19,449,397.67

SUB TOTAL PEKERJAAN LANTAI TIGA IV 1,744,383,256.95

PEK. ARS G. BPOM Page 42


HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME JUMLAH (Rp)
(Rp)

V PEKERJAAN LANTAI EMPAT


A PEKERJAAN DINDING DAN LAPISAN

1 Dinding pasangan Light Concrete block tebal 100 mm m2 970.20 375,000.00 363,825,000.00
2 Beton Kolom & Ring Balok Praktis m3 11.64 5,138,399.75 59,823,305.25
Plester + aci permukaan Light Concrete Block tebal 15 mm,
3 m2 1,940.40 71,579.20 138,892,279.68
menggunakan Semen Instan
Plester + aci permukaan Beton tebal 15 mm, menggunakan Semen
4 m2 396.58 71,579.20 28,386,592.82
Instan
5 Dinding Granit 60 x 120 cm area Lobby & Lift m2 99.99 315,102.03 31,506,421.78
6 Dinding Kaca Sun Energy Glass 8mm (KC1) m2 388.33 400,000.00 155,332,800.00
7 Dinding Kaca Tempered Clear Glass 8 mm (KC5) m2 69.72 700,920.55 48,868,180.75
8 Dinding Homogenius Tile 60 x 60 cm area Toilet m2 154.67 292,343.84 45,215,652.36
9 Dinding Partisi Kaca 12mm tempered Clear Glass m2 54.57 766,260.55 41,816,370.73
10 Cat tembok untuk dinding dalam m2 679.08 24,553.93 16,674,082.78
11 Cat tembok untuk dinding luar m2 373.63 24,553.93 9,174,133.97
SUB TOTAL PEKERJAAN DINDING DAN LAPISAN A 939,514,820.12

B PEKERJAAN LANTAI

1 Lantai Homogenius Tile uk. 120 x 120 cm m2 533.75 438,515.76 234,057,786.90


2 Lantai Homogenius Tile uk. 60 x 60cm m2 75.23 292,343.84 21,993,027.08
3 Lantai Homogenius Tile uk. 60 x 60cm area Toilet m2 46.88 292,343.84 13,705,079.22
4 Lantai Keramik Tile uk. 30 x 30cm m2 222.95 221,673.65 49,422,140.27
5 Lantai Karpet m2 57.53 68,334.75 3,931,298.17
6 Screed Perataan Lantai tebal 3 cm di Area Karpet m2 57.53 134,131.14 7,716,564.48
7 Lantai Floor Hardener 3kg m2 34.36 42,190.50 1,449,665.58
8 Lantai Parquet m2 53.81 412,513.75 22,197,364.89
9 Waterprofing Coating area Toilet, Janitor, dll m2 46.88 90,000.00 4,219,200.00
10 Scred Plindung Waterprofing m2 46.88 75,919.03 3,559,084.13
11 Plint Homogenius Tile 10cm m' 125.15 128,964.00 16,139,844.60
SUB TOTAL PEKERJAAN LANTAI B 378,391,055.32

C PEKERJAAN PLAFOND

1 Plafond Gypsum board tebal 9mm m2 144.64 129,329.75 18,706,255.04


1 Plafond Calsiboard tebal + Water Resistance m2 46.88 221,900.25 10,402,683.72
2 Plafond Akustik Tile tebal 9mm m2 591.28 370,334.25 218,971,235.34
3 Plafond Akustik Metal Celing m2 31.17 178,178.00 5,553,808.26
4 Plafond Beton Expose finish aci m2 61.65 43,422.50 2,676,997.13
5 List Plafond m' 332.80 23,256.75 7,739,846.40
6 Cat Plafond m2 844.45 24,553.93 20,734,566.19
SUB TOTAL PEKERJAAN PLAFOND C 284,785,392.07

PEK. ARS G. BPOM Page 43


HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME JUMLAH (Rp)
(Rp)

D PEKERJAAN PINTU & JENDELA

1 Pintu Type PG1, Uk. 2400 x 900 mm Unit 9.00 1,728,000.00 15,552,000.00
2 Pintu Type PG2, Uk. 2400 x 1800 mm Unit 2.00 3,456,000.00 6,912,000.00
3 Pintu Type PS1, Uk. 2400 x 1000 mm Unit 1.00 4,320,000.00 4,320,000.00
4 Pintu Type PS2, Uk. 2400 x 900 mm Unit 2.00 1,728,000.00 3,456,000.00
5 Pintu Type PS3, Uk. 2400 x 800 mm Unit 2.00 1,536,000.00 3,072,000.00
6 Pintu Type PS4, Uk. 2400 x 800 mm Unit 1.00 2,850,000.00 2,850,000.00
7 Pintu Type PD1, Uk. 2400 x 1470mm Unit 2.00 2,850,000.00 5,700,000.00
8 Pintu Type PD2, Uk. 2400 x 1000mm Unit 2.00 2,600,000.00 5,200,000.00
9 Pintu Type PB1, Uk. 2400 x 1000 mm Unit 2.00 1,800,000.00 3,600,000.00
10 Pintu Type PB2, Uk. 2400 x 1900 mm Unit 1.00 3,750,000.00 3,750,000.00
11 Jendela, Uk. 450 x 450 mm (R.Toilet Pria) Unit 1.00 650,000.00 650,000.00
12 Jendela, Uk. 450 x 450 mm (R.Toilet Wanita) Unit 1.00 650,000.00 650,000.00
13 Jendela, Uk. 300 x 300 mm (R.Toilet Difabel) Unit 1.00 500,000.00 500,000.00
14 Jendela, Uk. 450 x 450 mm (R.Panel) Unit 1.00 650,000.00 650,000.00
15 Jendela, Uk. 200 x 200 mm (R.Bakpel) Unit 1.00 500,000.00 500,000.00
16 Jendela, Uk. 300 x 300 mm (R.Pantry) Unit 1.00 500,000.00 500,000.00
SUB TOTAL PEKERJAAN PINTU & JENDELA D 57,862,000.00

E PEKERJAAN SANITAIR

1 Closet Duduk set 7.00 3,177,982.50 22,245,877.50


2 Closet Duduk Difable unit 1.00 3,177,982.50 3,177,982.50
3 Closet Duduk Jongkok unit 2.00 669,817.50 1,339,635.00
4 Grab Barr bh 1.00 400,000.00 400,000.00
5 Jet Spray bh 10.00 300,000.00 3,000,000.00
6 Wastafel bh 6.00 727,292.50 4,363,755.00
7 Wastafel Difabel m2 1.00 727,292.50 727,292.50
8 Floor Drain m' 15.00 65,422.50 981,337.50
9 Kitchen zink m' 1.00 377,767.50 377,767.50
10 Kran Kitchen zink bh 1.00 96,511.25 96,511.25
11 Kaca cermin tebal 6 mm, Bevel tepi + Rangka bh 5.93 390,142.50 2,311,594.31
12 Meja Wastafel Beton Lapis Granit L= 60 cm set 4.98 949,146.26 4,726,748.37
13 Meja Pantry Beton Lapis Homogenius Tile, Lebar 60 cm unit 2.25 949,146.26 2,135,579.09
14 Paper Holder unit 10.00 105,000.00 1,050,000.00
15 Robe Hook unit 12.00 150,000.00 1,800,000.00
16 Urinal (moslem Type) unit 4.00 2,587,500.00 10,350,000.00
17 Partisi Pembates Urinoir m2 2.00 1,750,000.00 3,500,000.00
18 Hand Dryer unit 2.00 250,000.00 500,000.00
19 Soap Dispenser, Type Initial Healthcear unit 3.00 150,000.00 450,000.00
20 Kran tempat Wudhu / Janitor unit 1.00 96,511.25 96,511.25
21 Shower Spray set 3.00 250,000.00 750,000.00
SUB TOTAL PEKERJAAN SANITAIR E 64,380,591.77

PEK. ARS G. BPOM Page 44


HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME JUMLAH (Rp)
(Rp)

F PEKERJAAN TANGGA

1 Tangga Type T #1
- Antrade & Optrade, Floor Hardener m2 17.60 42,190.50 742,388.26
- Anti slip / Step Nozing m' 25.65 95,000.00 2,436,750.00
- Hand Railling m' 7.81 550,000.00 4,295,500.00
Bahan : Hand Ralling Besi Pipa Ø 2" Finish Cat
Ralling Besi Pipa Ø 1,5" Finish Cat
Tiang Ralling Besi Pipa Ø 1,5" Finish Cat
- Plester + acian permukan beton, campuran 1 pc : 3 psr m2 16.18 110,488.07 1,787,542.29
- Cat Tembok m2 16.99 27,226.93 462,518.29

2 Tangga Type T #02


- Antrade & Optrade, Floor Hardener m2 17.60 42,190.50 742,388.26
- Anti slip / Step Nozing m' 25.65 95,000.00 2,436,750.00
- Hand Railling m' 7.81 550,000.00 4,295,500.00
Bahan : Hand Ralling Besi Pipa Ø 2" Finish Cat
Ralling Besi Pipa Ø 1,5" Finish Cat
Tiang Ralling Besi Pipa Ø 1,5" Finish Cat
- Plester + acian permukan beton, campuran 1 pc : 3 psr m2 16.18 110,488.07 1,787,542.29
- Cat Tembok m2 16.99 27,226.93 462,518.29
SUB TOTAL PEKERJAAN TANGGA F 19,449,397.67

SUB TOTAL PEKERJAAN LANTAI EMPAT V 1,744,383,256.95

PEK. ARS G. BPOM Page 45


HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME JUMLAH (Rp)
(Rp)

VI PEKERJAAN LANTAI LIMA


A PEKERJAAN DINDING DAN LAPISAN

1 Dinding pasangan Light Concrete block tebal 100 mm m2 1,137.37 375,000.00 426,513,600.00
2 Beton Kolom & Ring Balok Praktis m3 13.65 5,138,399.75 70,131,116.02
Plester + aci permukaan Light Concrete Block tebal 15 mm,
3 m2 2,274.74 71,579.20 162,824,012.14
menggunakan Semen Instan
Plester + aci permukaan Beton tebal 15 mm, menggunakan Semen
4 m2 396.58 71,579.20 28,386,592.82
Instan
5 Dinding Granit 60 x 120 cm area Lobby & Lift m2 166.54 315,102.03 52,478,352.48
6 Dinding Kaca Sun Energy Glass 8mm (KC1) m2 397.66 400,000.00 159,062,400.00
7 Dinding Kaca Tempered Clear Glass 8 mm (KC5) m2 19.08 700,920.55 13,376,367.78
8 Dinding Homogenius Tile 60 x 60 cm area Toilet m2 154.67 292,343.84 45,215,652.36
9 Dinding Partisi Kaca 12mm tempered Clear Glass m2 79.37 766,260.55 60,819,632.37
10 Cladding Façade System m2 533.95 1,800,000.00 961,102,800.00
11 Cat tembok untuk dinding dalam m2 893.33 24,553.93 21,934,713.18
12 Cat tembok untuk dinding luar m2 311.09 24,553.93 7,638,580.30
SUB TOTAL PEKERJAAN DINDING DAN LAPISAN A 2,009,483,819.45

B PEKERJAAN LANTAI

1 Lantai Homogenius Tile uk. 120 x 120 cm m2 474.22 438,515.76 207,952,943.71


2 Lantai Homogenius Tile uk. 60 x 60cm m2 117.89 292,343.84 34,464,415.30
3 Lantai Homogenius Tile uk. 60 x 60cm area Toilet m2 51.10 292,343.84 14,938,770.22
4 Lantai Keramik Tile uk. 30 x 30cm m2 221.81 221,673.65 49,169,432.31
5 Lantai Karpet m2 74.85 68,334.75 5,114,856.04
6 Screed Perataan Lantai tebal 3 cm di Area Karpet m2 74.85 134,131.14 10,039,715.83
7 Lantai Floor Hardener 3kg m2 45.82 42,190.50 1,933,168.71
8 Lantai Parquet m2 34.67 412,513.75 14,301,851.71
9 Waterprofing Coating area Toilet, Janitor, dll m2 51.10 90,000.00 4,599,000.00
10 Scred Plindung Waterprofing m2 51.10 75,919.03 3,879,462.43
11 Plint Homogenius Tile 10cm m' 261.75 128,964.00 33,756,327.00
SUB TOTAL PEKERJAAN LANTAI B 380,149,943.26

C PEKERJAAN PLAFOND

1 Plafond Gypsum board tebal 9mm m2 157.17 129,329.75 20,326,756.81


1 Plafond Calsiboard tebal + Water Resistance m2 55.39 221,900.25 12,291,054.85
2 Plafond Akustik Tile tebal 9mm m2 526.07 370,334.25 194,821,738.90
3 Plafond Akustik Metal Celing m2 30.96 178,178.00 5,516,390.88
4 Plafond Beton Expose finish aci m2 253.36 43,422.50 11,001,524.60
5 List Plafond m' 310.09 23,256.75 7,211,685.61
6 Cat Plafond m2 1,022.95 24,553.93 25,117,442.69
SUB TOTAL PEKERJAAN PLAFOND C 276,286,594.33

PEK. ARS G. BPOM Page 46


HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME JUMLAH (Rp)
(Rp)

D PEKERJAAN PINTU & JENDELA

1 Pintu Type PG1, Uk. 2400 x 900 mm Unit 11.00 1,728,000.00 19,008,000.00
2 Pintu Type PG2, Uk. 2400 x 1800 mm Unit 2.00 3,456,000.00 6,912,000.00
3 Pintu Type PS1, Uk. 2400 x 1000 mm Unit 1.00 4,320,000.00 4,320,000.00
4 Pintu Type PS2, Uk. 2400 x 900 mm Unit 2.00 1,728,000.00 3,456,000.00
5 Pintu Type PS3, Uk. 2400 x 800 mm Unit 2.00 1,536,000.00 3,072,000.00
6 Pintu Type PS4, Uk. 2400 x 800 mm Unit 2.00 2,850,000.00 5,700,000.00
7 Pintu Type PD1, Uk. 2400 x 1470mm Unit 2.00 2,850,000.00 5,700,000.00
8 Pintu Type PD2, Uk. 2400 x 1000mm Unit 2.00 2,600,000.00 5,200,000.00
9 Pintu Type P1, Uk. 2400 x 800mm Unit 2.00 2,850,000.00 5,700,000.00
10 Pintu Type PB1, Uk. 2400 x 1000 mm Unit 2.00 1,800,000.00 3,600,000.00
11 Pintu Type PB2, Uk. 2400 x 1900 mm Unit 1.00 3,750,000.00 3,750,000.00
12 Jendela, Uk. 300 x 300 mm (R.Toilet 1) Unit 1.00 500,000.00 500,000.00
13 Jendela, Uk. 300 x 300 mm (R.Toilet 2) Unit 1.00 500,000.00 500,000.00
14 Jendela, Uk. 450 x 450 mm (R.Toilet Pria) Unit 1.00 650,000.00 650,000.00
15 Jendela, Uk. 450 x 450 mm (R.Toilet Wanita) Unit 1.00 650,000.00 650,000.00
16 Jendela, Uk. 300 x 300 mm (R.Toilet Difabel) Unit 1.00 500,000.00 500,000.00
17 Jendela, Uk. 450 x 450 mm (R.Panel) Unit 1.00 650,000.00 650,000.00
18 Jendela, Uk. 200 x 200 mm (R.Bakpel) Unit 1.00 500,000.00 500,000.00
19 Jendela, Uk. 300 x 300 mm (R.Pantry) Unit 1.00 500,000.00 500,000.00
SUB TOTAL PEKERJAAN PINTU & JENDELA D 70,868,000.00

E PEKERJAAN SANITAIR

1 Closet Duduk set 8.00 3,177,982.50 25,423,860.00


2 Closet Duduk Difable unit 1.00 3,177,982.50 3,177,982.50
3 Closet Duduk Jongkok unit 2.00 669,817.50 1,339,635.00
4 Grab Barr bh 1.00 400,000.00 400,000.00
5 Jet Spray bh 11.00 300,000.00 3,300,000.00
6 Wastafel bh 7.00 727,292.50 5,091,047.50
7 Wastafel Difabel m2 1.00 727,292.50 727,292.50
8 Floor Drain m' 16.00 65,422.50 1,046,760.00
9 Kitchen zink m' 1.00 377,767.50 377,767.50
10 Kran Kitchen zink bh 1.00 96,511.25 96,511.25
11 Kaca cermin tebal 6 mm, Bevel tepi + Rangka bh 7.13 390,142.50 2,779,765.31
12 Meja Wastafel Beton Lapis Granit L= 60 cm set 5.68 949,146.26 5,391,150.76
13 Meja Pantry Beton Lapis Homogenius Tile, Lebar 60 cm unit 2.25 949,146.26 2,135,579.09
14 Paper Holder unit 10.00 105,000.00 1,050,000.00
15 Robe Hook unit 12.00 150,000.00 1,800,000.00
16 Urinal (moslem Type) unit 4.00 2,587,500.00 10,350,000.00
17 Partisi Pembates Urinoir m2 2.00 1,750,000.00 3,500,000.00
18 Hand Dryer unit 2.00 250,000.00 500,000.00
19 Soap Dispenser, Type Initial Healthcear unit 4.00 150,000.00 600,000.00
20 Kran tempat Wudhu / Janitor unit 1.00 96,511.25 96,511.25
21 Shower Spray set 4.00 250,000.00 1,000,000.00
SUB TOTAL PEKERJAAN SANITAIR E 70,183,862.65

PEK. ARS G. BPOM Page 47


HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME JUMLAH (Rp)
(Rp)

F PEKERJAAN TANGGA

1 Tangga Type T #1
- Antrade & Optrade, Floor Hardener m2 17.60 42,190.50 742,388.26
- Anti slip / Step Nozing m' 25.65 95,000.00 2,436,750.00
- Hand Railling m' 7.81 550,000.00 4,295,500.00
Bahan : Hand Ralling Besi Pipa Ø 2" Finish Cat
Ralling Besi Pipa Ø 1,5" Finish Cat
Tiang Ralling Besi Pipa Ø 1,5" Finish Cat
- Plester + acian permukan beton, campuran 1 pc : 3 psr m2 16.18 110,488.07 1,787,542.29
- Cat Tembok m2 16.99 27,226.93 462,518.29

2 Tangga Type T #02


- Antrade & Optrade, Floor Hardener m2 17.60 42,190.50 742,388.26
- Anti slip / Step Nozing m' 25.65 95,000.00 2,436,750.00
- Hand Railling m' 7.81 550,000.00 4,295,500.00
Bahan : Hand Ralling Besi Pipa Ø 2" Finish Cat
Ralling Besi Pipa Ø 1,5" Finish Cat
Tiang Ralling Besi Pipa Ø 1,5" Finish Cat
- Plester + acian permukan beton, campuran 1 pc : 3 psr m2 16.18 110,488.07 1,787,542.29
- Cat Tembok m2 16.99 27,226.93 462,518.29
SUB TOTAL PEKERJAAN TANGGA F 19,449,397.67

SUB TOTAL PEKERJAAN LANTAI LIMA VI 816,937,797.92

PEK. ARS G. BPOM Page 48


HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME JUMLAH (Rp)
(Rp)

VII PEKERJAAN LANTAI ENAM


A PEKERJAAN DINDING DAN LAPISAN

1 Dinding pasangan Light Concrete block tebal 100 mm m2 1,137.37 375,000.00 426,513,600.00
2 Beton Kolom & Ring Balok Praktis m3 13.65 5,138,399.75 70,131,116.02
Plester + aci permukaan Light Concrete Block tebal 15 mm,
3 m2 2,274.74 71,579.20 162,824,012.14
menggunakan Semen Instan
Plester + aci permukaan Beton tebal 15 mm, menggunakan Semen
4 m2 396.58 71,579.20 28,386,592.82
Instan
5 Dinding Granit 60 x 120 cm area Lobby & Lift m2 166.54 315,102.03 52,478,352.48
6 Dinding Kaca Sun Energy Glass 8mm (KC1) m2 397.66 400,000.00 159,062,400.00
7 Dinding Kaca Tempered Clear Glass 8 mm (KC5) m2 19.08 700,920.55 13,376,367.78
8 Dinding Homogenius Tile 60 x 60 cm area Toilet m2 154.67 292,343.84 45,215,652.36
9 Dinding Partisi Kaca 12mm tempered Clear Glass m2 79.37 766,260.55 60,819,632.37
10 Cladding Façade System m2 533.95 1,800,000.00 961,102,800.00
11 Cat tembok untuk dinding dalam m2 893.33 24,553.93 21,934,713.18
12 Cat tembok untuk dinding luar m2 311.09 24,553.93 7,638,580.30
SUB TOTAL PEKERJAAN DINDING DAN LAPISAN A 2,009,483,819.45

B PEKERJAAN LANTAI

1 Lantai Homogenius Tile uk. 120 x 120 cm m2 474.22 438,515.76 207,952,943.71


2 Lantai Homogenius Tile uk. 60 x 60cm m2 117.89 292,343.84 34,464,415.30
3 Lantai Homogenius Tile uk. 60 x 60cm area Toilet m2 51.10 292,343.84 14,938,770.22
4 Lantai Keramik Tile uk. 30 x 30cm m2 221.81 221,673.65 49,169,432.31
5 Lantai Karpet m2 74.85 68,334.75 5,114,856.04
6 Screed Perataan Lantai tebal 3 cm di Area Karpet m2 74.85 134,131.14 10,039,715.83
7 Lantai Floor Hardener 3kg m2 45.82 42,190.50 1,933,168.71
8 Lantai Parquet m2 34.67 412,513.75 14,301,851.71
9 Waterprofing Coating area Toilet, Janitor, dll m2 51.10 90,000.00 4,599,000.00
10 Scred Plindung Waterprofing m2 51.10 75,919.03 3,879,462.43
11 Plint Homogenius Tile 10cm m' 261.75 128,964.00 33,756,327.00
SUB TOTAL PEKERJAAN LANTAI B 380,149,943.26

C PEKERJAAN PLAFOND

1 Plafond Gypsum board tebal 9mm m2 157.17 129,329.75 20,326,756.81


1 Plafond Calsiboard tebal + Water Resistance m2 55.39 221,900.25 12,291,054.85
2 Plafond Akustik Tile tebal 9mm m2 526.07 370,334.25 194,821,738.90
3 Plafond Akustik Metal Celing m2 30.96 178,178.00 5,516,390.88
4 Plafond Beton Expose finish aci m2 253.36 43,422.50 11,001,524.60
5 List Plafond m' 310.09 23,256.75 7,211,685.61
6 Cat Plafond m2 1,022.95 24,553.93 25,117,442.69
SUB TOTAL PEKERJAAN PLAFOND C 276,286,594.33

PEK. ARS G. BPOM Page 49


HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME JUMLAH (Rp)
(Rp)

D PEKERJAAN PINTU & JENDELA

1 Pintu Type PG1, Uk. 2400 x 900 mm Unit 11.00 1,728,000.00 19,008,000.00
2 Pintu Type PG2, Uk. 2400 x 1800 mm Unit 2.00 3,456,000.00 6,912,000.00
3 Pintu Type PS1, Uk. 2400 x 1000 mm Unit 1.00 4,320,000.00 4,320,000.00
4 Pintu Type PS2, Uk. 2400 x 900 mm Unit 2.00 1,728,000.00 3,456,000.00
5 Pintu Type PS3, Uk. 2400 x 800 mm Unit 2.00 1,536,000.00 3,072,000.00
6 Pintu Type PS4, Uk. 2400 x 800 mm Unit 2.00 2,850,000.00 5,700,000.00
7 Pintu Type PD1, Uk. 2400 x 1470mm Unit 2.00 2,850,000.00 5,700,000.00
8 Pintu Type PD2, Uk. 2400 x 1000mm Unit 2.00 2,600,000.00 5,200,000.00
9 Pintu Type P1, Uk. 2400 x 800mm Unit 2.00 2,850,000.00 5,700,000.00
10 Pintu Type PB1, Uk. 2400 x 1000 mm Unit 2.00 1,800,000.00 3,600,000.00
11 Pintu Type PB2, Uk. 2400 x 1900 mm Unit 1.00 3,750,000.00 3,750,000.00
12 Jendela, Uk. 300 x 300 mm (R.Toilet 1) Unit 1.00 500,000.00 500,000.00
13 Jendela, Uk. 300 x 300 mm (R.Toilet 2) Unit 1.00 500,000.00 500,000.00
14 Jendela, Uk. 450 x 450 mm (R.Toilet Pria) Unit 1.00 650,000.00 650,000.00
15 Jendela, Uk. 450 x 450 mm (R.Toilet Wanita) Unit 1.00 650,000.00 650,000.00
16 Jendela, Uk. 300 x 300 mm (R.Toilet Difabel) Unit 1.00 500,000.00 500,000.00
17 Jendela, Uk. 450 x 450 mm (R.Panel) Unit 1.00 650,000.00 650,000.00
18 Jendela, Uk. 200 x 200 mm (R.Bakpel) Unit 1.00 500,000.00 500,000.00
19 Jendela, Uk. 300 x 300 mm (R.Pantry) Unit 1.00 500,000.00 500,000.00
SUB TOTAL PEKERJAAN PINTU & JENDELA D 70,868,000.00

E PEKERJAAN SANITAIR

1 Closet Duduk set 8.00 3,177,982.50 25,423,860.00


2 Closet Duduk Difable unit 1.00 3,177,982.50 3,177,982.50
3 Closet Duduk Jongkok unit 2.00 669,817.50 1,339,635.00
4 Grab Barr bh 1.00 400,000.00 400,000.00
5 Jet Spray bh 11.00 300,000.00 3,300,000.00
6 Wastafel bh 7.00 727,292.50 5,091,047.50
7 Wastafel Difabel m2 1.00 727,292.50 727,292.50
8 Floor Drain m' 16.00 65,422.50 1,046,760.00
9 Kitchen zink m' 1.00 377,767.50 377,767.50
10 Kran Kitchen zink bh 1.00 96,511.25 96,511.25
11 Kaca cermin tebal 6 mm, Bevel tepi + Rangka bh 7.13 390,142.50 2,779,765.31
12 Meja Wastafel Beton Lapis Granit L= 60 cm set 5.68 949,146.26 5,391,150.76
13 Meja Pantry Beton Lapis Homogenius Tile, Lebar 60 cm unit 2.25 949,146.26 2,135,579.09
14 Paper Holder unit 10.00 105,000.00 1,050,000.00
15 Robe Hook unit 12.00 150,000.00 1,800,000.00
16 Urinal (moslem Type) unit 4.00 2,587,500.00 10,350,000.00
17 Partisi Pembates Urinoir m2 2.00 1,750,000.00 3,500,000.00
18 Hand Dryer unit 2.00 250,000.00 500,000.00
19 Soap Dispenser, Type Initial Healthcear unit 4.00 150,000.00 600,000.00
20 Kran tempat Wudhu / Janitor unit 1.00 96,511.25 96,511.25
21 Shower Spray set 4.00 250,000.00 1,000,000.00
SUB TOTAL PEKERJAAN SANITAIR E 70,183,862.65

PEK. ARS G. BPOM Page 50


HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME JUMLAH (Rp)
(Rp)

F PEKERJAAN TANGGA

1 Tangga Type T #1
- Antrade & Optrade, Floor Hardener m2 17.60 42,190.50 742,388.26
- Anti slip / Step Nozing m' 25.65 95,000.00 2,436,750.00
- Hand Railling m' 7.81 550,000.00 4,295,500.00
Bahan : Hand Ralling Besi Pipa Ø 2" Finish Cat
Ralling Besi Pipa Ø 1,5" Finish Cat
Tiang Ralling Besi Pipa Ø 1,5" Finish Cat
- Plester + acian permukan beton, campuran 1 pc : 3 psr m2 16.18 110,488.07 1,787,542.29
- Cat Tembok m2 16.99 27,226.93 462,518.29

2 Tangga Type T #02


- Antrade & Optrade, Floor Hardener m2 17.60 42,190.50 742,388.26
- Anti slip / Step Nozing m' 25.65 95,000.00 2,436,750.00
- Hand Railling m' 7.81 550,000.00 4,295,500.00
Bahan : Hand Ralling Besi Pipa Ø 2" Finish Cat
Ralling Besi Pipa Ø 1,5" Finish Cat
Tiang Ralling Besi Pipa Ø 1,5" Finish Cat
- Plester + acian permukan beton, campuran 1 pc : 3 psr m2 16.18 110,488.07 1,787,542.29
- Cat Tembok m2 16.99 27,226.93 462,518.29
SUB TOTAL PEKERJAAN TANGGA F 19,449,397.67

SUB TOTAL PEKERJAAN LANTAI ENAM VII 2,826,421,617.37

PEK. ARS G. BPOM Page 51


HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME JUMLAH (Rp)
(Rp)

VIII PEKERJAAN LANTAI TUJUH


A PEKERJAAN DINDING DAN LAPISAN

1 Dinding pasangan Light Concrete block tebal 100 mm m2 1,194.50 375,000.00 447,938,100.00
2 Beton Kolom & Ring Balok Praktis m3 14.33 5,138,399.75 73,653,920.67
Plester + aci permukaan Light Concrete Block tebal 15 mm,
3 m2 2,389.00 71,579.20 171,002,937.85
menggunakan Semen Instan
Plester + aci permukaan Beton tebal 15 mm, menggunakan Semen
4 m2 396.58 71,579.20 28,386,592.82
Instan
5 Dinding Granit 60 x 120 cm area Lobby & Lift m2 174.92 315,102.03 55,116,386.68
6 Dinding Kaca Sun Energy Glass 8mm (KC1) m2 358.05 400,000.00 143,220,000.00
7 Dinding Kaca Tempered Clear Glass 8 mm (KC5) m2 63.27 700,920.55 44,348,645.04
8 Dinding Homogenius Tile 60 x 60 cm area Toilet m2 154.67 292,343.84 45,215,652.36
9 Dinding Partisi Kaca 12mm tempered Clear Glass m2 66.72 766,260.55 51,121,838.85
10 Cladding Façade System m2 278.08 1,800,000.00 500,547,600.00
11 Cat tembok untuk dinding dalam m2 1,013.98 24,553.93 24,897,243.05
12 Cat tembok untuk dinding luar m2 267.79 24,553.93 6,575,346.02
SUB TOTAL PEKERJAAN DINDING DAN LAPISAN A 1,592,024,263.35

B PEKERJAAN LANTAI

1 Lantai Homogenius Tile uk. 120 x 120 cm m2 465.42 438,515.76 204,094,005.02


2 Lantai Homogenius Tile uk. 60 x 60cm m2 116.11 292,343.84 33,944,043.26
3 Lantai Homogenius Tile uk. 60 x 60cm area Toilet m2 51.10 292,343.84 14,938,770.22
4 Lantai Keramik Tile uk. 30 x 30cm m2 216.70 221,673.65 48,036,679.96
5 Lantai Karpet m2 40.79 68,334.75 2,787,374.45
6 Screed Perataan Lantai tebal 3 cm di Area Karpet m2 40.79 134,131.14 5,471,209.20
7 Lantai Floor Hardener 3kg m2 45.82 42,190.50 1,933,168.71
8 Lantai Parquet m2 78.38 412,513.75 32,332,827.73
9 Waterprofing Coating area Toilet, Janitor, dll m2 51.10 90,000.00 4,599,000.00
10 Scred Plindung Waterprofing m2 51.10 75,919.03 3,879,462.43
11 Plint Homogenius Tile 10cm m' 214.40 128,964.00 27,649,881.60
SUB TOTAL PEKERJAAN LANTAI B 379,666,422.58

C PEKERJAAN PLAFOND

1 Plafond Gypsum board tebal 9mm m2 156.86 129,329.75 20,286,664.59


1 Plafond Calsiboard tebal + Water Resistance m2 55.39 221,900.25 12,291,054.85
2 Plafond Akustik Tile tebal 9mm m2 533.72 370,334.25 197,654,795.91
3 Plafond Akustik Metal Celing m2 30.87 178,178.00 5,500,354.86
4 Plafond Beton Expose finish aci m2 248.25 43,422.50 10,779,635.63
5 List Plafond m' 267.98 23,256.75 6,232,343.87
6 Cat Plafond m2 1,025.09 24,553.93 25,169,988.10
SUB TOTAL PEKERJAAN PLAFOND C 277,914,837.80

PEK. ARS G. BPOM Page 52


HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME JUMLAH (Rp)
(Rp)

D PEKERJAAN PINTU & JENDELA

1 Pintu Type PG1, Uk. 2400 x 900 mm Unit 7.00 1,728,000.00 12,096,000.00
2 Pintu Type PG2, Uk. 2400 x 1800 mm Unit 3.00 3,456,000.00 10,368,000.00
3 Pintu Type PS1, Uk. 2400 x 1000 mm Unit 2.00 4,320,000.00 8,640,000.00
4 Pintu Type PS2, Uk. 2400 x 900 mm Unit 2.00 1,728,000.00 3,456,000.00
5 Pintu Type PS3, Uk. 2400 x 800 mm Unit 2.00 1,536,000.00 3,072,000.00
6 Pintu Type PS4, Uk. 2400 x 800 mm Unit 1.00 2,850,000.00 2,850,000.00
7 Pintu Type PD1, Uk. 2400 x 1470mm Unit 2.00 2,850,000.00 5,700,000.00
8 Pintu Type PD2, Uk. 2400 x 1000mm Unit 2.00 2,600,000.00 5,200,000.00
9 Pintu Type P1, Uk. 2400 x 800mm Unit 2.00 2,850,000.00 5,700,000.00
10 Pintu Type PB1, Uk. 2400 x 1000 mm Unit 2.00 1,800,000.00 3,600,000.00
11 Jendela, Uk. 300 x 300 mm (R.Toilet 1) Unit 1.00 3,750,000.00 3,750,000.00
12 Jendela, Uk. 450 x 450 mm (R.Toilet Pria) Unit 1.00 500,000.00 500,000.00
13 Jendela, Uk. 450 x 450 mm (R.Toilet Wanita) Unit 1.00 650,000.00 650,000.00
14 Jendela, Uk. 300 x 300 mm (R.Toilet Difabel) Unit 1.00 650,000.00 650,000.00
15 Jendela, Uk. 450 x 450 mm (R.Panel) Unit 1.00 500,000.00 500,000.00
16 Jendela, Uk. 200 x 200 mm (R.Bakpel) Unit 1.00 650,000.00 650,000.00
17 Jendela, Uk. 300 x 300 mm (R.Pantry) Unit 1.00 500,000.00 500,000.00
SUB TOTAL PEKERJAAN PINTU & JENDELA D 67,882,000.00

E PEKERJAAN SANITAIR

1 Closet Duduk set 7.00 3,177,982.50 22,245,877.50


2 Closet Duduk Difable unit 1.00 3,177,982.50 3,177,982.50
3 Closet Duduk Jongkok unit 2.00 669,817.50 1,339,635.00
4 Grab Barr bh 1.00 400,000.00 400,000.00
5 Jet Spray bh 9.00 300,000.00 2,700,000.00
6 Wastafel bh 6.00 727,292.50 4,363,755.00
7 Wastafel Difabel m2 1.00 727,292.50 727,292.50
8 Floor Drain m' 14.00 65,422.50 915,915.00
9 Kitchen zink m' 1.00 377,767.50 377,767.50
10 Kran Kitchen zink bh 1.00 96,511.25 96,511.25
11 Kaca cermin tebal 6 mm, Bevel tepi + Rangka bh 5.93 390,142.50 2,311,594.31
12 Meja Wastafel Beton Lapis Granit L= 60 cm set 4.98 949,146.26 4,726,748.37
13 Meja Pantry Beton Lapis Homogenius Tile, Lebar 60 cm unit 2.25 949,146.26 2,135,579.09
14 Paper Holder unit 9.00 105,000.00 945,000.00
15 Robe Hook unit 11.00 150,000.00 1,650,000.00
16 Urinal (moslem Type) unit 4.00 2,587,500.00 10,350,000.00
17 Partisi Pembates Urinoir m2 2.00 1,750,000.00 3,500,000.00
18 Hand Dryer unit 2.00 250,000.00 500,000.00
19 Soap Dispenser, Type Initial Healthcear unit 3.00 150,000.00 450,000.00
20 Kran tempat Wudhu / Janitor unit 1.00 96,511.25 96,511.25
21 Shower Spray set 3.00 250,000.00 750,000.00
SUB TOTAL PEKERJAAN SANITAIR E 63,760,169.27

PEK. ARS G. BPOM Page 53


HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME JUMLAH (Rp)
(Rp)

F PEKERJAAN TANGGA
1 Tangga Type T #1
- Antrade & Optrade, Floor Hardener m2 17.60 42,190.50 742,388.26
- Anti slip / Step Nozing m' 25.65 95,000.00 2,436,750.00
- Hand Railling m' 7.81 550,000.00 4,295,500.00
Bahan : Hand Ralling Besi Pipa Ø 2" Finish Cat
Ralling Besi Pipa Ø 1,5" Finish Cat
Tiang Ralling Besi Pipa Ø 1,5" Finish Cat
- Plester + acian permukan beton, campuran 1 pc : 3 psr m2 16.18 110,488.07 1,787,542.29
- Cat Tembok m2 16.99 27,226.93 462,518.29

2 Tangga Type T #02


- Antrade & Optrade, Floor Hardener m2 17.60 42,190.50 742,388.26
- Anti slip / Step Nozing m' 25.65 95,000.00 2,436,750.00
- Hand Railling m' 7.81 550,000.00 4,295,500.00
Bahan : Hand Ralling Besi Pipa Ø 2" Finish Cat
Ralling Besi Pipa Ø 1,5" Finish Cat
Tiang Ralling Besi Pipa Ø 1,5" Finish Cat
- Plester + acian permukan beton, campuran 1 pc : 3 psr m2 16.18 110,488.07 1,787,542.29
- Cat Tembok m2 16.99 27,226.93 462,518.29

3 Tangga area GYM

- Antrade & Optrade, Lantai Keramik 30 x 30cm m2 10.54 281,581.85 2,967,872.70

- Anti slip / Step Nozing m' 20.00 95,000.00 1,900,000.00


- Hand Railling m' 11.88 550,000.00 6,534,000.00
Bahan : Hand Ralling pipa Stainless Steel Ø 2" hairline
Ralling Plat Stainlees Steel 5mm
Kaca Tempered tebal 10 mm + Acc.
- Plester + acian permukan beton, campuran 1 pc : 3 psr m2 13.48 110,488.07 1,489,379.18
- Cat Tembok m2 14.15 27,226.93 385,369.97
SUB TOTAL PEKERJAAN TANGGA F 32,726,019.52

SUB TOTAL PEKERJAAN LANTAI TUJUH VIII 2,413,973,712.52

PEK. ARS G. BPOM Page 54


HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME JUMLAH (Rp)
(Rp)

IX PEKERJAAN LANTAI DELAPAN


A PEKERJAAN DINDING DAN LAPISAN

1 Dinding pasangan Light Concrete block tebal 100 mm m2 849.11 375,000.00 318,415,800.00
2 Beton Kolom & Ring Balok Praktis m3 10.19 5,138,399.75 52,356,725.35
Plester + aci permukaan Light Concrete Block tebal 15 mm,
3 m2 1,698.22 71,579.20 121,557,057.23
menggunakan Semen Instan
Plester + aci permukaan Beton tebal 15 mm, menggunakan Semen
4 m2 474.34 71,579.20 33,952,591.41
Instan
5 Dinding Granit 60 x 120 cm area Lobby & Lift m2 141.25 315,102.03 44,507,531.53
6 Dinding Kaca Sun Energy Glass 8mm (KC1) m2 391.69 400,000.00 156,676,800.00
7 Dinding Kaca Tempered Clear Glass 8 mm (KC5) m2 37.10 700,920.55 26,001,348.72
8 Dinding Homogenius Tile 60 x 60 cm area Toilet m2 154.67 292,343.84 45,215,652.36
9 Cladding Façade System m2 306.05 1,800,000.00 550,890,000.00
10 Cat tembok untuk dinding dalam m2 396.35 24,553.93 9,731,851.94
11 Cat tembok untuk dinding luar m2 398.79 24,553.93 9,791,861.74

SUB TOTAL PEKERJAAN DINDING DAN LAPISAN A 1,369,097,220.29

B PEKERJAAN LANTAI

1 Lantai Homogenius Tile uk. 60 x 60cm m2 228.78 292,343.84 66,882,423.72


2 Lantai Homogenius Tile uk. 60 x 60cm area Toilet m2 43.09 292,343.84 12,597,096.07
3 Lantai Keramik Tile uk. 30 x 30cm m2 30.10 221,673.65 6,672,376.87
4 Lantai Karpet m2 323.21 68,334.75 22,086,474.55
5 Screed Perataan Lantai tebal 3 cm di Area Karpet m2 323.21 134,131.14 43,352,525.76
6 Lantai Floor Hardener 3kg m2 296.00 42,190.50 12,488,388.00
7 Lantai Parquet m2 80.50 412,513.75 33,207,356.88
8 Waterprofing Coating area Toilet, Janitor, dll m2 43.09 90,000.00 3,878,100.00
9 Scred Plindung Waterprofing m2 43.09 75,919.03 3,271,351.00
10 Plint Homogenius Tile 10cm m' 170.22 128,964.00 21,952,252.08
SUB TOTAL PEKERJAAN LANTAI B 226,388,344.91

C PEKERJAAN PLAFOND

1 Plafond Gypsum board tebal 9mm m2 385.64 129,329.75 49,874,724.79


1 Plafond Calsiboard tebal + Water Resistance m2 55.39 221,900.25 12,291,054.85
2 Plafond Akustik Tile tebal 9mm m2 46.92 370,334.25 17,376,083.01
3 Plafond Akustik Metal Celing m2 30.87 178,178.00 5,500,354.86
4 Plafond Beton Expose finish aci m2 61.65 43,422.50 2,676,997.13
5 List Plafond m' 190.91 23,256.75 4,439,946.14
6 Cat Plafond m2 580.47 24,553.93 14,252,819.75
SUB TOTAL PEKERJAAN PLAFOND C 106,411,980.52

PEK. ARS G. BPOM Page 55


HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME JUMLAH (Rp)
(Rp)

D PEKERJAAN PINTU & JENDELA

1 Pintu Type PG1, Uk. 2400 x 900 mm Unit 3.00 1,728,000.00 5,184,000.00
2 Pintu Type PG2, Uk. 2400 x 1800 mm Unit 1.00 3,456,000.00 3,456,000.00
3 Pintu Type PS1, Uk. 2400 x 1000 mm Unit 1.00 4,320,000.00 4,320,000.00
4 Pintu Type PS2, Uk. 2400 x 900 mm Unit 3.00 1,728,000.00 5,184,000.00
5 Pintu Type PS3, Uk. 2400 x 800 mm Unit 2.00 1,536,000.00 3,072,000.00
6 Pintu Type PD1, Uk. 2400 x 1470mm Unit 2.00 2,850,000.00 5,700,000.00
7 Pintu Type PD2, Uk. 2400 x 1000mm Unit 2.00 2,600,000.00 5,200,000.00
8 Pintu Type PB1, Uk. 2400 x 1000 mm Unit 2.00 2,850,000.00 5,700,000.00
9 Jendela, Uk. 450 x 450 mm (R.Toilet Wanita) Unit 1.00 650,000.00 650,000.00
10 Jendela, Uk. 300 x 300 mm (R.Toilet Difabel) Unit 1.00 650,000.00 650,000.00
11 Jendela, Uk. 450 x 450 mm (R.Panel) Unit 1.00 500,000.00 500,000.00
12 Jendela, Uk. 200 x 200 mm (R.Bakpel) Unit 1.00 650,000.00 650,000.00
13 Jendela, Uk. 300 x 300 mm (R.Pantry) Unit 1.00 500,000.00 500,000.00
SUB TOTAL PEKERJAAN PINTU & JENDELA D 40,766,000.00

E PEKERJAAN SANITAIR

1 Closet Duduk set 7.00 3,177,982.50 22,245,877.50


2 Closet Duduk Difable unit 1.00 3,177,982.50 3,177,982.50
3 Closet Duduk Jongkok unit 2.00 669,817.50 1,339,635.00
4 Grab Barr bh 1.00 400,000.00 400,000.00
5 Jet Spray bh 9.00 300,000.00 2,700,000.00
6 Wastafel bh 6.00 727,292.50 4,363,755.00
7 Wastafel Difabel m2 1.00 727,292.50 727,292.50
8 Floor Drain m' 14.00 65,422.50 915,915.00
9 Kitchen zink m' 1.00 377,767.50 377,767.50
10 Kran Kitchen zink bh 1.00 96,511.25 96,511.25
11 Kaca cermin tebal 6 mm, Bevel tepi + Rangka bh 5.93 390,142.50 2,311,594.31
12 Meja Wastafel Beton Lapis Granit L= 60 cm set 4.98 949,146.26 4,726,748.37
13 Meja Pantry Beton Lapis Homogenius Tile, Lebar 60 cm unit 2.25 949,146.26 2,135,579.09
14 Paper Holder unit 9.00 105,000.00 945,000.00
15 Robe Hook unit 11.00 150,000.00 1,650,000.00
16 Urinal (moslem Type) unit 4.00 2,587,500.00 10,350,000.00
17 Partisi Pembates Urinoir m2 2.00 1,750,000.00 3,500,000.00
18 Hand Dryer unit 2.00 250,000.00 500,000.00
19 Soap Dispenser, Type Initial Healthcear unit 3.00 150,000.00 450,000.00
20 Kran tempat Wudhu / Janitor unit 1.00 96,511.25 96,511.25
21 Shower Spray set 3.00 250,000.00 750,000.00
SUB TOTAL PEKERJAAN SANITAIR E 63,760,169.27

PEK. ARS G. BPOM Page 56


HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME JUMLAH (Rp)
(Rp)

F PEKERJAAN TANGGA

1 Tangga Type T #1
- Antrade & Optrade, Floor Hardener m2 17.60 42,190.50 742,388.26
- Anti slip / Step Nozing m' 25.65 95,000.00 2,436,750.00
- Hand Railling m' 7.81 550,000.00 4,295,500.00
Bahan : Hand Ralling Besi Pipa Ø 2" Finish Cat
Ralling Besi Pipa Ø 1,5" Finish Cat
Tiang Ralling Besi Pipa Ø 1,5" Finish Cat
- Plester + acian permukan beton, campuran 1 pc : 3 psr m2 16.18 110,488.07 1,787,542.29
- Cat Tembok m2 16.99 27,226.93 462,518.29
2 Tangga Area Prefuntion
- Antrade & Optrade, Floor Hardener m2 21.02 42,190.50 886,844.31
- Anti slip / Step Nozing m' 36.00 95,000.00 3,420,000.00
- Hand Railling m' 14.27 550,000.00 7,848,500.00
Bahan : Hand Ralling Besi Pipa Ø 2" Finish Cat
Ralling Besi Pipa Ø 1,5" Finish Cat
Tiang Ralling Besi Pipa Ø 1,5" Finish Cat
- Plester + acian permukan beton, campuran 1 pc : 3 psr m2 25.60 110,488.07 2,827,942.15
- Cat Tembok m2 26.87 27,226.93 731,716.94
SUB TOTAL PEKERJAAN TANGGA F 25,439,702.24

SUB TOTAL PEKERJAAN LANTAI DELAPAN IX 1,831,863,417.23

PEK. ARS G. BPOM Page 57


HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME JUMLAH (Rp)
(Rp)

VI PEKERJAAN LANTAI TRIBUN DAN PENUTUP ATAP

1 Dinding pasangan Light Concrete block tebal 100 mm m2 856.54 375,000.00 321,201,300.00
2 Beton Kolom & Ring Balok Praktis m3 10.28 5,138,399.75 52,814,741.75
Plester + aci permukaan Light Concrete Block tebal 15 mm,
3 m2 1,713.07 71,579.20 122,620,437.83
menggunakan Semen Instan
4 Dinding Granit 60 x 120 cm area Lobby & Lift m2 18.66 315,102.03 5,878,543.47
5 Dinding Kaca Sun Energy Glass 8mm (KC1) m2 343.73 400,000.00 137,491,200.00
6 Dinding Homogenius Tile 60 x 60 cm area Toilet m2 103.20 292,343.84 30,169,884.29
7 Cladding Façade System m2 470.25 1,500,000.00 705,375,000.00
8 Cat tembok untuk dinding dalam m2 558.55 24,553.93 13,714,597.60
9 Cat tembok untuk dinding Luar m2 177.45 24,553.93 4,357,094.88
10 Lantai Homogenius Tile uk. 60 x 60cm m2 282.89 292,343.84 82,701,148.90
11 Lantai Homogenius Tile uk. 60 x 60cm area Toilet m2 47.40 292,343.84 13,857,098.02
12 Lantai Floor Hardener 3kg m2 63.40 42,190.50 2,674,877.70
13 Plint Homogenius Tile 10cm m' 178.91 128,964.00 23,072,949.24
14 Plafond Gypsum board tebal 9mm m2 626.42 129,329.75 81,014,742.00
15 Plafond Calsiboard tebal + Water Resistance m2 47.40 221,900.25 10,518,071.85
16 Plafond Akustik Metal Celing m2 29.99 178,178.00 5,343,558.22
17 Plafond Beton Expose + aci m2 111.93 43,422.50 4,860,280.43
18 List Plafond m' 183.51 23,256.75 4,267,846.19
19 Cat Plafond m2 815.74 24,553.93 20,029,622.86
20 Pintu Type PD1, Uk. 2400 x 1470mm Unit 1.00 2,850,000.00 2,850,000.00
21 Pintu Type PD2, Uk. 2400 x 1000mm Unit 1.00 2,600,000.00 2,600,000.00
22 Pintu Type P1, Uk. 2400 x 800mm Unit 2.00 2,850,000.00 5,700,000.00
23 Pintu Type PB1, Uk. 2400 x 1000 mm Unit 1.00 1,800,000.00 1,800,000.00
24 Closet Duduk set 4.00 3,177,982.50 12,711,930.00
25 Jet Spray bh 4.00 300,000.00 1,200,000.00
26 Wastafel bh 4.00 727,292.50 2,909,170.00
27 Floor Drain m' 4.00 65,422.50 261,690.00
28 Kitchen zink m' 1.00 377,767.50 377,767.50
29 Kran Kitchen zink bh 1.00 96,511.25 96,511.25
30 Kaca cermin tebal 6 mm, Bevel tepi + Rangka bh 4.73 390,142.50 1,843,423.31
31 Meja Wastafel Beton Lapis Granit L= 60 cm set 3.40 949,146.26 3,227,097.28
32 Paper Holder unit 4.00 105,000.00 420,000.00
33 Robe Hook unit 4.00 150,000.00 600,000.00
34 Urinal (moslem Type) unit 2.00 2,587,500.00 5,175,000.00
35 Partisi Pembates Urinoir m2 1.00 1,750,000.00 1,750,000.00
36 Tangga Type T #1 -
- Antrade & Optrade, Floor Hardener m2 17.60 42,190.50 742,388.26
- Anti slip / Step Nozing m' 25.65 95,000.00 2,436,750.00
- Hand Railling m' 7.81 550,000.00 4,295,500.00
Bahan : Hand Ralling Besi Pipa Ø 2" Finish Cat
Ralling Besi Pipa Ø 1,5" Finish Cat
Tiang Ralling Besi Pipa Ø 1,5" Finish Cat
- Plester + acian permukan beton, campuran 1 pc : 3 psr m2 16.18 110,488.07 1,787,542.29
- Cat Tembok m2 16.99 27,226.93 462,518.29
35 Atap Metal System + Rangka dan Insulation m2 449.80 233,998.00 105,252,300.40
36 Waterprofing Membrane untuk Atap Dak Beton m2 597.31 190,000.00 113,488,900.00
37 Scred Plindung Waterprofing m2 597.31 151,838.06 90,694,391.62
38 Roof drain Ø 4" Cast iron bh 13.00 326,400.00 4,243,200.00
PEKERJAAN LANTAI TRIBUN DAN PENUTUP
SUB TOTAL VI 2,008,889,075.41
ATAP

PEK. ARS G. BPOM Page 58


HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME JUMLAH (Rp)
(Rp)

VII PEKERJAAN FASADE

ALUMINIUM COMPOSITE PANEL FIN. PVDF KETEBALAN 55um STANDARD AL


1 SHEET @0,5mm ALLOY 3003 H14 STANDARD CORE 3,0mm BAHAN FIRE m2 1,197.41 650,000.00 778,316,500.00
RETARDANT DAN NON COMBUSTIBLE.

SUB TOTAL PEKERJAAN FASADE VII 778,316,500.00

PEK. ARS G. BPOM Page 59


BILL OF QUANTITY / B.O.Q
PROYEK : PERENCANAAN PEMBANGUNAN GEDUNG - D DI AREA PERKANTORAN BADAN POM
Jl. PERCETAKAN NEGARA No. 23 Kec. JOHAR BARU, JAKARTA PUSAT
PEKERJAAN : MEKANIKAL & ELEKTRIKAL

REKAPITULASI
PEKERJAAN MEKANIKAL & ELEKTRIKAL
0

<2.3> MEKANIKAL Rp. 12,977,298,375.75

<2.3.1> PEKERJAAN INSTALASI AIR CONDITIONING Rp. 7,874,755,777.50

<2.3.2> PEKERJAAN INSTALASI PLUMBING Rp. 591,883,718.25

<2.3.3> PEKERJAAN INSTALASI FIRE HYDRANT Rp. 505,557,420.00

<2.3.4> PEKERJAAN INSTALASI FIRE SPRINKLER Rp. 868,601,460.00

<2.3.5> PEKERJAAN ELEVATOR Rp. 3,136,500,000.00

<2.4> ELEKTRIKAL Rp. 11,176,066,563.60

<2.4.1> PEKERJAAN INSTALASI LISTRIK Rp. 3,889,932,350.00

<2.4.2> PEKERJAAN INSTALASI SOUND SYSTEM Rp. 246,000,276.10

<2.4.3> PEKERJAAN INSTALASI FIRE ALARM (TYPE SEMI ADDRESS Rp. 624,067,450.00

<2.4.4> PEKERJAAN INSTALASI SECURITY SYSTEM Rp. 177,020,000.00

<2.4.5> PEKERJAAN INSTALASI TELEPON Rp. 1,056,829,187.50

<2.4.6> PEKERJAAN INSTALASI DATA Rp. 1,199,458,800.00

<2.4.7> PEKERJAAN INSTALASI BUILDING AUTOMATION SYSTEM Rp. 322,150,000.00

<2.4.8> PEKERJAAN INSTALASI TRANSFORMATOR DAYA Rp. 3,660,608,500.00

TOTAL PEKERJAAN MEKANIKAL & ELEKTRIKAL Rp. 24,153,364,939.35

PEK. (M & E) G. BPOM


BILL OF QUANTITY / B.O.Q
PROYEK : PERENCANAAN PEMBANGUNAN GEDUNG - D DI AREA PERKANTORAN BADAN POM
Jl. PERCETAKAN NEGARA No. 23 Kec. JOHAR BARU, JAKARTA PUSAT
PEKERJAAN : STRUKTUR

REKAPITULASI UTAMA
PEKERJAAN STRUKTUR GWT & STP

I PEKERJAAN STRUKTUR GWT Rp. 522,580,992.97


A PEKERJAAN BORED PILE Rp. 127,487,784.67
B PEKERJAAN STRUKTUR BAWAH & ATAS Rp. 395,093,208.30
II PEKERJAAN STRUKTUR STP Rp. 533,982,823.10
A PEKERJAAN BORED PILE Rp. 127,487,784.67
B PEKERJAAN STRUKTUR BAWAH & ATAS Rp. 406,495,038.43

SUB TOTAL Rp. 1,056,563,816.07

PEK. GWT & STP Page 61


BILL OF QUANTITY / B.O.Q
PROYEK : PERENCANAAN PEMBANGUNAN GEDUNG - D DI AREA PERKANTORAN BADAN POM
Jl. PERCETAKAN NEGARA No. 23 Kec. JOHAR BARU, JAKARTA PUSAT
PEKERJAAN : STRUKTUR

HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME JUMLAH (Rp)
(Rp)

<3> PEKERJAAN STRUKTUR GWT & STP

I PEKERJAAN STRUKTUR GWT

A PEKERJAAN BORED PILE


1 Pengeboran, Pabrikasi Besi Tulangan dan Pengecoran Bored Pile Diameter 60 cm
- Pengeboran kedalaman 12 M m' 72.00 375,000.00 27,000,000.00
- Perbaikan permukaan tanah , dengan Bentonate m' 72.00 25,000.00 1,800,000.00
- Pengadaan, Pembuatan Keranjang besi & Handling kg 3,514.66 20,586.98 72,356,303.20
- Pengadaan dan pengecoran Beton Mutu 'Fc = 33,2 Mpa m3 20.35 1,275,267.32 25,948,119.21
- Bobokan Kepala Bored Pile m3 0.85 125,000.00 105,975.00
2 Buang tanah / Lumpur bekas pengeboran ttk 6.00 40,507.50 243,045.00
3 Buang Bekas Bobokan Kepala Bored Pile m3 0.85 40,507.50 34,342.26
SUB TOTAL PEKERJAAN BORED PILE A 127,487,784.67

B PEKERJAAN STRUKTUR BAWAH & ATAS


1 Pasang Bauwplank m' 36.40 41,679.00 1,517,115.60
2 Galian tanah pondasi, Sloof, Dinding beton, dll m3 227.57 56,925.00 12,954,308.40
3 Pemadatan tanah bawah Pondasi m2 79.20 66,550.00 5,270,760.00
4 Urug tanah kembali bekas galian m3 209.42 42,900.00 8,984,289.60
5 Buang tanah bekas galian keluar lokasi m3 18.14 40,507.50 734,968.08
6 Urug pasir padat tebal 7 cm, bawah pondasi m3 5.54 142,560.00 790,352.64
7 Beton Lantai Kerja tebal 5 cm m3 3.96 687,867.23 2,723,954.23
8 Beton Pile cap :
a Type PC-1
- Beton Mutu 'Fc = 29,5 Mpa m3 8.64 1,206,627.32 10,425,260.04
- Pembesian kg 1,802.37 13,086.98 23,587,555.43
- Bekisting m2 28.80 152,473.75 4,391,244.00
9 Beton Sloof Balok :
a Type TB 1
- Beton Mutu 'Fc = 29,5 Mpa m3 2.96 1,206,627.32 3,574,633.44
- Pembesian kg 579.95 13,086.98 7,589,845.35
- Bekisting m2 20.94 186,023.75 3,894,407.21
b Type TB 2
- Beton Mutu 'Fc = 29,5 Mpa m3 1.26 1,206,627.32 1,520,350.42
- Pembesian kg 304.99 13,086.98 3,991,356.20
- Bekisting m2 8.90 186,023.75 1,656,355.47
10 Beton Kolom :
a Type K 1
- Beton Mutu 'Fc = 29,5 Mpa m3 1.28 1,206,627.32 1,544,482.97
- Pembesian kg 629.61 13,086.98 8,239,743.72
- Bekisting m2 9.60 210,273.25 2,018,623.20
b Type K 2
- Beton Mutu 'Fc = 29,5 Mpa m3 0.96 1,206,627.32 1,158,362.23
- Pembesian kg 419.74 13,086.98 5,493,162.48
- Bekisting m2 15.07 210,273.25 3,169,238.42
11 Beton Plat Lantai Bawah Type S1 :
- Beton Mutu 'Fc = 29,5 Mpa m3 5.87 1,206,627.32 7,081,937.07
- Pembesian kg 595.06 13,086.98 7,787,547.36
- Bekisting m2 29.35 268,105.75 7,867,831.34
12 Dinding Beton :
- Beton Mutu 'Fc = 29,5 Mpa m3 25.68 1,206,627.32 30,986,189.58
- Pembesian kg 5,126.31 13,086.98 67,087,874.75
- Bekisting m2 256.80 292,685.25 75,161,572.20

PEK. GWT & STP Page 62


HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME JUMLAH (Rp)
(Rp)
13 Beton Kolom Lantai Atas :
a Type K 1
- Beton Mutu 'Fc = 29,5 Mpa m3 1.34 1,206,627.32 1,621,707.12
- Pembesian kg 659.16 13,086.98 8,626,448.13
- Bekisting m2 10.08 210,273.25 2,119,554.36
b Type K 2
- Beton Mutu 'Fc = 29,5 Mpa m3 1.01 1,206,627.32 1,216,280.34
- Pembesian kg 439.44 13,086.98 5,750,965.42
- Bekisting m2 15.83 210,273.25 3,327,700.35
14 Beton Plat Lantai Atas Type S2 :
- Beton Mutu 'Fc = 29,5 Mpa m3 4.80 1,206,627.32 5,797,602.95
- Pembesian kg 601.83 13,086.98 7,876,188.34
- Bekisting m2 36.96 268,105.75 9,909,188.52
15 Beton Balok :
a Type B 1
- Beton Mutu 'Fc = 29,5 Mpa m3 2.25 1,206,627.32 2,714,911.47
- Pembesian kg 391.97 13,086.98 5,129,642.96
- Bekisting m2 15.90 241,870.75 3,845,744.93
b Type B 2
- Beton Mutu 'Fc = 29,5 Mpa m3 1.32 1,206,627.32 1,592,748.06
- Pembesian kg 228.54 13,086.98 2,990,845.44
- Bekisting m2 10.69 241,870.75 2,586,082.06
15 Beton Plat Lantai Dak Type S3 :
- Beton Mutu 'Fc = 29,5 Mpa m3 4.07 1,206,627.32 4,905,664.03
- Pembesian kg 303.31 13,086.98 3,969,423.87
- Bekisting m2 36.96 268,105.75 9,909,188.52
SUB TOTAL PEKERJAAN STRUKTUR BAWAH & ATAS B 395,093,208.30

SUB TOTAL PEKERJAAN STRUKTUR GWT I 522,580,992.97

PEK. GWT & STP Page 63


HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME JUMLAH (Rp)
(Rp)

II PEKERJAAN STRUKTUR STP

A PEKERJAAN BORED PILE


1 Pengeboran, Pabrikasi Besi Tulangan dan Pengecoran Bored Pile Diameter 60 cm
- Pengeboran kedalaman 12 M m' 72.00 375,000.00 27,000,000.00
- Perbaikan permukaan tanah , dengan Bentonate m' 72.00 25,000.00 1,800,000.00
- Pengadaan, Pembuatan Keranjang besi & Handling kg 3,514.66 20,586.98 72,356,303.20
- Pengadaan dan pengecoran Beton Mutu 'Fc = 33,2 Mpa m3 20.35 1,275,267.32 25,948,119.21
- Bobokan Kepala Bored Pile m3 0.85 125,000.00 105,975.00
2 Buang tanah / Lumpur bekas pengeboran ttk 6.00 40,507.50 243,045.00
3 Buang Bekas Bobokan Kepala Bored Pile m3 0.85 40,507.50 34,342.26
SUB TOTAL PEKERJAAN BORED PILE A 127,487,784.67

B PEKERJAAN STRUKTUR BAWAH & ATAS


1 Pasang Bauwplank m' 46.20 41,679.00 1,925,569.80
2 Galian tanah pondasi, Sloof, Dinding beton, dll m3 325.71 56,925.00 18,540,836.82
3 Pemadatan tanah bawah Pondasi m2 103.02 66,550.00 6,855,981.00
4 Urug tanah kembali bekas galian m3 304.70 42,900.00 13,071,801.60
5 Buang tanah bekas galian keluar lokasi m3 21.00 40,507.50 850,754.72
6 Urug pasir padat tebal 7 cm, bawah pondasi m3 7.21 142,560.00 1,028,057.18
7 Beton Lantai Kerja tebal 5 cm m3 5.15 687,867.23 3,543,204.10
8 Beton Pile cap :
a Type PC-1
- Beton Mutu 'Fc = 29,5 Mpa m3 8.64 1,206,627.32 10,425,260.04
- Pembesian kg 1,802.37 13,086.98 23,587,555.43
- Bekisting m2 28.80 152,473.75 4,391,244.00
9 Beton Sloof Balok :
a Type TB 1
- Beton Mutu 'Fc = 29,5 Mpa m3 3.70 1,206,627.32 4,459,694.57
- Pembesian kg 723.55 13,086.98 9,469,052.63
- Bekisting m2 26.12 186,023.75 4,858,642.71
b Type TB 2
- Beton Mutu 'Fc = 29,5 Mpa m3 3.03 1,206,627.32 3,656,080.78
- Pembesian kg 733.42 13,086.98 9,598,261.33
- Bekisting m2 21.41 186,023.75 3,983,140.54
10 Beton Plat Lantai Bawah Type S1 :
- Beton Mutu 'Fc = 29,5 Mpa m3 10.16 1,206,627.32 12,259,333.57
- Pembesian kg 949.40 13,086.98 12,424,786.28
- Bekisting m2 50.80 268,105.75 13,619,772.10
11 Dinding Beton :
- Beton Mutu 'Fc = 29,5 Mpa m3 31.23 1,206,627.32 37,677,662.04
- Pembesian kg 6,366.70 13,086.98 83,320,787.65
- Bekisting m2 312.26 292,685.25 91,392,725.42
12 Beton Plat Lantai Atas Type S2 :
- Beton Mutu 'Fc = 29,5 Mpa m3 7.26 1,206,627.32 8,765,423.50
- Pembesian kg 902.25 13,086.98 11,807,661.29
- Bekisting m2 55.88 268,105.75 14,981,749.31
SUB TOTAL PEKERJAAN STRUKTUR BAWAH & ATAS B 406,495,038.43

SUB TOTAL PEKERJAAN STRUKTUR STP II 533,982,823.10

SUB TOTAL PEKERJAAN STRUKTUR GWT & STP I 1,056,563,816.07

PEK. GWT & STP Page 64


NO URAIAN

1 PEKERJAAN PERSIAPAN
2 PEKERJAAN STRUKTUR
2.1 PEKERJAAN BORED PILE
2.2 PEKERJAAN STRUKTUR BAWAH
2.3 PEKERJAAN STRUKTUR ATAS
2.3.1 LANTAI GROUND
2.3.2 LANTAI MEZZANINE
2.3.3 LANTAI 2
2.3.4 LANTAI 3
2.3.5 LANTAI 4
2.3.6 LANTAI 5
2.3.7 LANTAI 6
2.3.8 LANTAI 7
2.3.9 LANTAI 8
2.3.10 LANTAI TRIBUN
2.3.11 LANTAI ATAP DAK
2.4 RANGKA ATAP BAJA
3 PEKERJAAN ARSITEKTUR
3.1 PEKERJAAN LANTAI SATU
3.1.1 PEKERJAAN DINDING DAN LAPISAN
3.1.2 PEKERJAAN LANTAI
3.1.3 PEKERJAAN PLAFOND
3.1.4 PEKERJAAN PINTU & JENDELA
3.1.5 PEKERJAAN SANITAIR
3.1.6 PEKERJAAN TANGGA
3.2 PEKERJAAN LANTAI MEZZANINE
3.2.1 PEKERJAAN DINDING DAN LAPISAN
3.2.2 PEKERJAAN LANTAI
3.2.3 PEKERJAAN PLAFOND
3.2.4 PEKERJAAN PINTU & JENDELA
3.2.5 PEKERJAAN TANGGA
3.3 PEKERJAAN LANTAI DUA
3.3.1 PEKERJAAN DINDING DAN LAPISAN
3.3.2 PEKERJAAN LANTAI
3.3.3 PEKERJAAN PLAFOND
3.3.4 PEKERJAAN PINTU & JENDELA
3.3.5 PEKERJAAN SANITAIR
3.3.6 PEKERJAAN TANGGA
3.4 PEKERJAAN LANTAI TIGA
3.4.1 PEKERJAAN DINDING DAN LAPISAN
3.4.2 PEKERJAAN LANTAI
3.4.3 PEKERJAAN PLAFOND
3.4.4 PEKERJAAN PINTU & JENDELA
3.4.5 PEKERJAAN SANITAIR
3.4.6 PEKERJAAN TANGGA
3.5 PEKERJAAN LANTAI EMPAT
3.5.1 PEKERJAAN DINDING DAN LAPISAN
3.5.2 PEKERJAAN LANTAI
3.5.3 PEKERJAAN PLAFOND
3.5.4 PEKERJAAN PINTU & JENDELA
3.5.5 PEKERJAAN SANITAIR
3.5.6 PEKERJAAN TANGGA
3.6 PEKERJAAN LANTAI LIMA
3.6.1 PEKERJAAN DINDING DAN LAPISAN
3.6.2 PEKERJAAN LANTAI
3.6.3 PEKERJAAN PLAFOND
3.6.4 PEKERJAAN PINTU & JENDELA
3.6.5 PEKERJAAN SANITAIR
3.6.6 PEKERJAAN TANGGA
3.7 PEKERJAAN LANTAI ENAM
3.7.1 PEKERJAAN DINDING DAN LAPISAN
3.7.2 PEKERJAAN LANTAI
3.7.3 PEKERJAAN PLAFOND
3.7.4 PEKERJAAN PINTU & JENDELA
3.7.5 PEKERJAAN SANITAIR
3.7.6 PEKERJAAN TANGGA
3.8 PEKERJAAN LANTAI TUJUH
3.8.1 PEKERJAAN DINDING DAN LAPISAN
3.8.2 PEKERJAAN LANTAI
3.8.3 PEKERJAAN PLAFOND
3.8.4 PEKERJAAN PINTU & JENDELA
3.8.5 PEKERJAAN SANITAIR
3.8.6 PEKERJAAN TANGGA
3.9 PEKERJAAN LANTAI DELAPAN
3.9.1 PEKERJAAN DINDING DAN LAPISAN
3.9.2 PEKERJAAN LANTAI
3.9.3 PEKERJAAN PLAFOND
3.9.4 PEKERJAAN PINTU & JENDELA
3.9.5 PEKERJAAN SANITAIR
3.9.6 PEKERJAAN TANGGA
3.10 PEKERJAAN LANTAI TRIBUN DAN PENUTUP ATAP
3.11 PEKERJAAN FASADE
4 MEKANIKAL
4.1 PEKERJAAN INSTALASI AIR CONDITIONING
4.2 PEKERJAAN INSTALASI PLUMBING
4.3 PEKERJAAN INSTALASI FIRE HYDRANT
4.4 PEKERJAAN INSTALASI FIRE SPRINKLER
4.5 PEKERJAAN ELEVATOR
5 ELEKTRIKAL
5.1 PEKERJAAN INSTALASI LISTRIK
5.2 PEKERJAAN INSTALASI SOUND SYSTEM
5.3 PEKERJAAN INSTALASI FIRE ALARM (TYPE SEMI ADDRESSABLE)
5.4 PEKERJAAN INSTALASI SECURITY SYSTEM
5.5 PEKERJAAN INSTALASI TELEPON
5.6 PEKERJAAN INSTALASI DATA
5.7 PEKERJAAN INSTALASI BUILDING AUTOMATION SYSTEM
5.8 PEKERJAAN INSTALASI TRANSFORMATOR DAYA
6 PEKERJAAN GWT & STP
6.1 PEKERJAAN STRUKTUR GWT
6.1.1 PEKERJAAN BORED PILE
6.1.2 PEKERJAAN STRUKTUR BAWAH & ATAS
6.2 PEKERJAAN STRUKTUR STP
6.2.1 PEKERJAAN BORED PILE
6.2.2 PEKERJAAN STRUKTUR BAWAH & ATAS
7 PEKERJAAN PENYAMBUNGAN DAYA PLN 1500 KVA
8 PEKERJAAN PENYAMBUNGAN TELEPON
9 PEKERJAAN PENYAMBUNGAN PDAM
1 2
Bobot
% 1 2 3 4 5 6 7

1-7 8-14 15-21 22-28 29-35 36-42 43-49


807,344,931.15 1.065% 0.025% 0.025% 0.025% 0.025% 0.025% 0.025% 0.025%

6,682,894,810.91 8.816% 1.469% 1.469% 1.469% 1.469%


2,607,638,225.83 3.440% 0.430%

1,928,110,494.56 2.543%
1,066,606,112.70 1.407%
2,018,362,123.63 2.663%
2,041,750,582.17 2.693%
2,018,362,123.63 2.663%
1,955,015,385.73 2.579%
1,955,015,385.73 2.579%
1,977,301,681.64 2.608%
1,889,476,445.37 2.493%
836,024,877.86 1.103%
803,082,066.25 1.059%
331,348,865.78 0.437%

778,050,946.96 1.026%
245,906,747.88 0.324%
46,967,590.69 0.062%
75,023,000.00 0.099%
60,969,298.91 0.080%
88,493,258.21 0.117%

406,847,490.94 0.537%
126,773,529.44 0.167%
165,986,761.56 0.219%
14,100,000.00 0.019%
11,974,759.42 0.016%

939,514,820.12 1.239%
378,391,055.32 0.499%
284,785,392.07 0.376%
57,862,000.00 0.076%
64,380,591.77 0.085%
19,449,397.67 0.026%

939,514,820.12 1.239%
378,391,055.32 0.499%
284,785,392.07 0.376%
57,862,000.00 0.076%
64,380,591.77 0.085%
19,449,397.67 0.026%

939,514,820.12 1.239%
378,391,055.32 0.499%
284,785,392.07 0.376%
57,862,000.00 0.076%
64,380,591.77 0.085%
19,449,397.67 0.026%

2,009,483,819.45 2.651%
380,149,943.26 0.501%
276,286,594.33 0.364%
70,868,000.00 0.093%
70,183,862.65 0.093%
19,449,397.67 0.026%
0.000%
2,009,483,819.45 2.651%
380,149,943.26 0.501%
276,286,594.33 0.364%
70,868,000.00 0.093%
70,183,862.65 0.093%
19,449,397.67 0.026%
0.000%
1,592,024,263.35 2.100%
379,666,422.58 0.501%
277,914,837.80 0.367%
67,882,000.00 0.090%
63,760,169.27 0.084%
32,726,019.52 0.043%

1,369,097,220.29 1.806%
226,388,344.91 0.299%
106,411,980.52 0.140%
40,766,000.00 0.054%
63,760,169.27 0.084%
25,439,702.24 0.034%
2,008,889,075.41 2.650%
778,316,500.00 1.027%

7,874,755,777.50 10.388%
591,883,718.25 0.781%
505,557,420.00 0.667%
868,601,460.00 1.146%
3,136,500,000.00 4.138%

3,889,932,350.00 5.131%
246,000,276.10 0.325%
624,067,450.00 0.823%
177,020,000.00 0.234%
1,056,829,187.50 1.394%
1,199,458,800.00 1.582%
322,150,000.00 0.425%
3,660,608,500.00 4.829%

127,487,784.67 0.168%
395,093,208.30 0.521%
0.000%
127,487,784.67 0.168%
406,495,038.43 0.536%
1,687,500,000.00 2.226%
25,000,000.00 0.033%
25,000,000.00 0.033%
75,805,891,963.14 100.00% 0.025% 0.025% 0.025% 1.494% 1.494% 1.494% 1.924%
0.000% 0.025% 0.050% 0.074% 1.568% 3.062% 4.557% 6.481%
2 3 4 5

8 9 10 11 12 13 14 15 16 17 18

50-56 57-63 64-70 71-77 78-84 85-91 92-98 99-105 106-112 113-119 120-126
0.025% 0.025% 0.025% 0.025% 0.025% 0.025% 0.025% 0.025% 0.025% 0.025% 0.025%

1.469% 1.469%
0.430% 0.430% 0.430% 0.430% 0.430% 0.430% 0.430%

0.509% 0.509% 0.509% 0.509% 0.509%


1.924% 1.924% 0.455% 0.455% 0.455% 0.963% 0.963% 0.533% 0.533% 0.533% 0.025%
8.405% ### ### ### ### ### ### ### ### ### ###
BULAN KE
5 6 7 8
MINGGU KE
19 20 21 22 23 24 25 26 27 28 29
HARI KE
127-133 134-140 141-147 `148-154 155-161 162-168 169-175 176-182 183-189 190-196 197-203
0.025% 0.025% 0.025% 0.025% 0.025% 0.025% 0.025% 0.025% 0.025% 0.025% 0.025%
0.025% 0.025% 0.025% 0.025% 0.025% 0.025% 0.025% 0.025% 0.025% 0.025% 0.025%
### ### ### ### ### ### ### ### ### ### ###
8 9 10

30 31 32 33 34 35 36 37 38 39 40

204-210 211-217 218-224 225-231 232-238 239-245 246-252 253-259 260-266 267-273 274-280
0.025% 0.025% 0.025% 0.025% 0.025% 0.025% 0.025% 0.025% 0.025% 0.025% 0.025%
0.025% 0.025% 0.025% 0.025% 0.025% 0.025% 0.025% 0.025% 0.025% 0.025% 0.025%
### ### ### ### ### ### ### ### ### ### ###
11

41 42 43

281-287 288-294 295-300


0.025% 0.025% 0.025% 1.065% 0.000%
0.000% 0.000%
8.816% 0.000%
3.440% 0.000%
0.000% 0.000%
2.543% 0.000%
0.000% -1.407%
0.000% -2.663%
0.000% -2.693%
0.000% -2.663%
0.000% -2.579%
0.000% -2.579%
0.000% -2.608%
0.000% -2.493%
0.000% -1.103%
0.000% -1.059%
0.000% -0.437%
0.000% 0.000%
0.000% 0.000%
0.000% -1.026%
0.000% -0.324%
0.000% -0.062%
0.000% -0.099%
0.000% -0.080%
0.000% -0.117%
0.000% 0.000%
0.000% -0.537%
0.000% -0.167%
0.000% -0.219%
0.000% -0.019%
0.000% -0.016%
0.000% 0.000%
0.000% -1.239%
0.000% -0.499%
0.000% -0.376%
0.000% -0.076%
0.000% -0.085%
0.000% -0.026%
0.000% 0.000%
0.000% -1.239%
0.000% -0.499%
0.000% -0.376%
0.000% -0.076%
0.000% -0.085%
0.000% -0.026%
0.000% 0.000%
0.000% -1.239%
0.000% -0.499%
0.000% -0.376%
0.000% -0.076%
0.000% -0.085%
0.000% -0.026%
0.000% 0.000%
0.000% -2.651%
0.000% -0.501%
0.000% -0.364%
0.000% -0.093%
0.000% -0.093%
0.000% -0.026%
0.000% 0.000%
0.000% -2.651%
0.000% -0.501%
0.000% -0.364%
0.000% -0.093%
0.000% -0.093%
0.000% -0.026%
0.000% 0.000%
0.000% -2.100%
0.000% -0.501%
0.000% -0.367%
0.000% -0.090%
0.000% -0.084%
0.000% -0.043%
0.000% 0.000%
0.000% -1.806%
0.000% -0.299%
0.000% -0.140%
0.000% -0.054%
0.000% -0.084%
0.000% -0.034%
0.000% -2.650%
0.000% -1.027%
0.000% 0.000%
0.000% -10.388%
0.000% -0.781%
0.000% -0.667%
0.000% -1.146%
0.000% -4.138%
0.000% 0.000%
0.000% -5.131%
0.000% -0.325%
0.000% -0.823%
0.000% -0.234%
0.000% -1.394%
0.000% -1.582%
0.000% -0.425%
0.000% -4.829%
0.000% 0.000%
0.000% 0.000%
0.000% -0.168%
0.000% -0.521%
0.000% 0.000%
0.000% -0.168%
0.000% -0.536%
0.000% -2.226%
0.000% -0.033%
0.000% -0.033%
0.025% 0.025% 0.025% 15.864% -84.136%
### ### ###