REKAP HARGA ANGKUTAN BATU PECAH DAN PASIR

KEBUTUHAN PROYEK TOLL BANGKINANG - PANGKALAN

KAPASITAS JARAK
NO JENIS MATERIAL ARMADA ASAL TUJUAN TEMPUH
BAK (m3) (km)
1 BATU PECAH DT 4x6 20 Crusher BP 4 BP 1 80
2 BATU PECAH DT 4x6 20 Crusher BP 4 BP 2 50
3 BATU PECAH DT 4x6 20 Crusher BP 4 BP 3 20
4 BATU PECAH DT 4x6 20 Crusher BP 4 BP 4 -
5 PASIR DT 4x6 20 Bangkinang BP 1 5
6 PASIR DT 4x6 20 Bangkinang BP 2 20
7 PASIR DT 4x6 20 Bangkinang BP 3 50
8 PASIR DT 4x6 20 Bangkinang BP 4 80
ASIR
KALAN

HARSAT TOTAL
(Rp)
1,500 2,400,000
1,500 1,500,000
1,500 600,000
1,500 -
1,500 150,000
1,500 600,000
1,500 1,500,000
1,500 2,400,000