RENCANA ANGGARAN BIAYA

PROGRAM :
PEKERJAAN : PERENCANAAN …………..
LOKASI :
TAHUN ANGGARAN : 2019

I. BIAYA LANGSUNG PERSONIL :

A. TENAGA AHLI

HARGA JUMLAH
NO. URAIAN SATUAN JUMLAH WAKTU SATUAN HARGA
(bulan) (Rp.) (Rp.)

1 Team Leader/Sipil Engineer Org 1.00 2.00 ### 34,000,000.00


2 Sipil/Struktur Engineer Org 1.00 2.00 ### 28,000,000.00
3 Ahli Pondasi / Geoteknik org 1.00 2.00 ### 28,000,000.00
4 Quantity Engineer Org 1.00 2.00 ### 24,000,000.00

JUMLAH (I.A) (dipindahkan ke rekapitulasi ) 114,000,000.00

B. STAF PENDUKUNG

HARGA JUMLAH
NO. URAIAN SATUAN JUMLAH WAKTU SATUAN HARGA
(bulan) (Rp.) (Rp.)

1 Draftman/ CAD Operator Org 2.00 2.00 4,000,000.00 16,000,000.00


2 Operator Computer/Sekretaris Org 1.00 2.00 2,000,000.00 4,000,000.00

JUMLAH (I.B) (dipindahkan ke rekapitulasi ) 20,000,000.00

II. BIAYA LANGSUNG NON PERSONIL :

A. BIAYA SURVEY DAN PENGUMPULAN DATA


JUMLAH
NO. URAIAN SATUAN JUMLAH HARGA SATUAN (Rp.) HARGA
(Rp.)

1 Pengukuran dan Pemetaan Unit 1.00 3,000,000.00 3,000,000.00


2 Pengadaan Data dan Literatur Unit 1.00 2,500,000.00 2,500,000.00

JUMLAH ( II. A) (dipindahkan ke rekapitulasi ) 5,500,000.00

B. BIAYA SOIL TEST (Pengujian Tanah)

JUMLAH
NO. URAIAN SATUAN JUMLAH HARGA SATUAN (Rp.) HARGA
(Rp.)

1 Pengujian dan Pengambilan Tanah (sondir) titik 2.00 ### 20,000,000.00


2 Pengujian Sampel di Laboraturium Paket 1.00 8,000,000.00 8,000,000.00

JUMLAH ( II. A) (dipindahkan ke rekapitulasi ) 28,000,000.00


C. BIAYA PERALATAN/PERLENGKAPAN

HARGA JUMLAH
NO. URAIAN SATUAN JUMLAH WAKTU SATUAN HARGA
(bulan) (Rp.) (Rp.)

1 Sewa Komputer Gambar Lengkap Unit 2.00 2.00 1,500,000.00 6,000,000.00


2 Sewa Computer Administrasi /Printer Unit 1.00 2.00 1,000,000.00 2,000,000.00
3 Biaya ATK ( Habis Pakai) Ls Ls Ls 2,500,000.00 2,500,000.00
4 Listrik,Komunikasi,Dokumentasi dan Internet Ls Ls Ls 1,250,000.00 1,250,000.00

JUMLAH ( II. B ) (dipindahkan ke rekapitulasi ) 11,750,000.00

D. BIAYA PENGADAAN DOKUMEN

HARGA JUMLAH
NO. URAIAN SATUAN JUMLAH SATUAN HARGA
(Rp.) (Rp.)

1 Laporan Perencanaan Lengkap (final Report) Exp 5.00 85,000.00 425,000.00


2 Gembar-Gambar Rencana dan Gambar Kerja Exp 5.00 120,000.00 600,000.00
3 Daftar Volume dan Biaya ( Engineer Estimate ) Exp 5.00 55,000.00 275,000.00
4 Rencana Kerja Dan Syarat Syarat (spesifikasi Teknis) Exp 5.00 55,000.00 275,000.00

JUMLAH ( II. C ) (dipindahkan ke rekapitulasi ) 1,575,000.00


REKAPITULASI
RENCANA ANGGARAN BIAYA
PROGRAM :
PEKERJAAN : PERENCANAAN …………..
LOKASI :
TAHUN ANGGARAN : 2019

NO. URAIAN JUMLAH HARGA


(Rp.)

I. BIAYA LANGSUNG PERSONIL

A. TENAGA AHLI 114,000,000.00


B. STAF PENDUKUNG 20,000,000.00

II. BIAYA LANGSUNG NON PERSONIL

A. BIAYA SURVEY DAN PENGUMPULAN DATA 5,500,000.00


B. BIAYA SOIL TEST (Pengujian Tanah) 28,000,000.00
C. BIAYA PERALATAN/PERLENGKAPAN 11,750,000.00
D. BIAYA PENGADAAN DOKUMEN 1,575,000.00

REAL COST PEKERJAAN 180,825,000.00


PPN 10 % 18,082,500.00
JUMLAH TOTAL 198,907,500.00
DIBULATKAN 198,907,000.00

Terbilang :
*** Seratus Sembilan Puluh Delapan Juta Sembilan Ratus Tujuh Ribu Rupiah ***

Ampana, …………. 2019


CV. ……………………..

………………………..
HARGA PERKIRAAN SENDIRI ( HPS )
KEGIATAN :
PEKERJAAN : PERENCANAAN …………..
LOKASI :
TAHUN ANGGARAN : 2019

A. BIAYA LANGSUNG PERSONIL


A.1. TENAGA AHLI
HARGA JUMLAH
WAKTU
NO. URAIAN SATUAN VOLUME SATUAN ( Rp HARGA ( Rp
(BULAN)
) )
1 2 3 4 5 6 7

1 Team Leader Org/Bln 1.00 1.50 4,500,000.00 6,750,000.00


2 Ahli Arsitek Org/Bln 1.00 1.50 3,750,000.00 5,625,000.00
3 Ahli Teknik Sipil Org/Bln 1.00 1.50 3,750,000.00 5,625,000.00
4 Ahli Estimasi Biaya Org/Bln 1.00 1.50 3,750,000.00 5,625,000.00
5 Mekanikal Elektrikal Org/Bln 1.00 1.00 3,750,000.00 3,750,000.00

JUMLAH A.1. ###

A.2. TENAGA PENUNJANG


HARGA JUMLAH
WAKTU
NO. URAIAN SATUAN VOLUME SATUAN ( Rp HARGA ( Rp
(BULAN)
) )
1 2 3 4 5 6 7

1 Asisten Arsitek Org/Bln 1.00 1.50 2,500,000.00 3,750,000.00


2 Asisten Struktur Org/Bln 1.00 1.50 2,500,000.00 3,750,000.00
3 Asisten Estimasi Biaya Org/Bln 1.00 1.50 2,500,000.00 3,750,000.00
4 Surveyor Org/Bln 2.00 0.50 2,000,000.00 2,000,000.00
5 Draftman Org/Bln 2.00 1.50 2,000,000.00 6,000,000.00
6 Sekretaris / Operator Komputer Org/Bln 1.00 1.50 1,000,000.00 1,500,000.00
7 Office Boy Org/Bln 1.00 1.50 750,000.00 1,125,000.00

JUMLAH A.2. ###

B. BIAYA LANGSUNG NON PERSONIL


B.1. BIAYA SURVEY DAN TRANSPORTASI
HARGA JUMLAH
WAKTU
NO. URAIAN SATUAN VOLUME SATUAN ( Rp HARGA ( Rp
(BULAN)
) )
1 2 3 4 5 6 7

1 Transportasi
- Sewa Kenderaan Roda 4 (empat) Unit 1.00 1.00 4,500,000.00 4,500,000.00
- Sewa Kenderaan Roda 2 (dua) Unit 2.00 1.50 700,000.00 2,100,000.00
2 Biaya Survey / Pengambilan Data Ls Ls Ls 1,500,000.00 1,500,000.00
JUMLAH B.1. 8,100,000.00

B.2. BIAYA PERALATAN DAN PERLENGK


HARGA JUMLAH
WAKTU
NO. URAIAN SATUAN VOLUME SATUAN ( Rp HARGA ( Rp
(BULAN)
) )
1 2 3 4 5 6 7

1 Sewa Meja Gambar Lengkap Unit 2.00 1.50 500,000.00 1,500,000.00


2 Sewa Lettering Set Lengkap Set 2.00 1.50 150,000.00 450,000.00
3 Kertas Kalkir (Bahan Gambar) Roll 2.00 - 149,000.00 298,000.00
4 Sewa Komputer + Printer Unit 1.00 1.50 1,100,000.00 1,650,000.00
5 Alat Tulis Kantor, Foto Copy Ls Ls Ls 1,580,089.65 1,580,089.65
6 Komunikasi dan Listrik Ls Ls Ls 1,800,000.00 1,800,000.00

JUMLAH B.2. 7,278,089.65

B.3. BIAYA PENGADAAN DOKUMEN


HARGA JUMLAH
WAKTU
NO. URAIAN SATUAN VOLUME SATUAN ( Rp HARGA ( Rp
(BULAN)
) )
1 2 3 4 5 6 7

1 Rencana Kerja dan Syarat-Syarat Exp 10.00 - 85,340.00 853,400.00


2 Gambar-Gambar Rencana Exp 10.00 - 100,172.50 1,001,724.98
3 Daftar Volume dan Biaya (EE) Exp 5.00 - 52,997.59 264,987.93
4 Laporan Pengawasan Berkala Exp 5.00 - 52,997.59 264,987.93

JUMLAH B.3. 2,385,100.83


REKAPITULASI
KEGIATAN :
PEKERJAAN : PERENCANAAN …………..
LOKASI :
TAHUN ANGGARAN : 2019

A. BIAYA LANGSUNG PERSONIL

A.1. TENAGA AHLI 27,375,000.00


A.2. TENAGA PENUNJANG 21,875,000.00
JUMLAH - A ###

B. BIAYA LANGSUNG NON PERSONIL

B.1. BIAYA SURVEY DAN TRANSPORTASI 8,100,000.00


B.2. BIAYA PERALATAN DAN PERLENGKAPAN 7,278,089.65
B.3. BIAYA PENGADAAN DOKUMEN 2,385,100.83
JUMLAH - B ###

TOTAL A + B ###
Pajak Pertambahan Nilai (PPN) 10 % 6,701,319.05
JUMLAH TOTAL ###
DIBULATKAN ###

Terbilang : Tujuh puluh juta empat ratus delapan puluh delapan ribu rupiah

Palu, Februari 2006

PANITIA

HARRY HERMANSYAH, SH.M.hum


Ketua