PEK : GANTI AC SPLIT OFFICE PT SSP 09/07/19

LOKASI : SUNTER AGUNG Jakarta 19-03-09

NO ITEM PEKERJAAN VOL SAT UNIT PRICE TOTAL PRICE

A Ganti AC office direksi


1 Bgk Indoor AC lama 10 set 100,000 1,000,000
2 Ganti instalasi pipa baru 2,5 PK 10 set 800,000 8,000,000
drain baru 10 lot 100,000 1,000,000
3 Pasang AC split baru 10 lot 200,000 2,000,000

SUB TOTAL INSTALASI AC 12,000,000

B Ruang direksi
1 Psg kembali AC ex direksi 4 set 900,000 3,600,000
tambahan utk R staff
2 Remote AC 1 set 400,000 400,000

SUB TOTAL INSTALASI AC 4,000,000

Ditawarkan oleh :

Ir Siswandi K

TOTAL PENAWARAN HARGA 16,000,000

'file:///conversion/tmp/scratch/427385983.xls'#$AC OFFICE SSP


PEK : REPAIR AC RT BUDGET 09/07/19
LOKASI : JL CISANGGIRI Jakarta 23-03-09

NO ITEM PEKERJAAN VOL SAT UNIT PRICE TOTAL PRICE

1 Material
kbl eterna nym 3 x2,5 mm 50 m 5,000 250,000
teedos 20 bh 600 12,000
isolasi kbl 2 rol 5,000 10,000

2 Upah kerja
1 komeng/ tajab 6/2/09 2 org 65,000 130,000

TOTAL PENAWARAN HARGA 402,000

'file:///conversion/tmp/scratch/427385983.xls'#$anggaran
PEK : PEK AC R LOBBY 09/07/19
LOKASI : TWIN HOTEL SLIPI Jakarta 26-01-10

NO ITEM PEKERJAAN VOL SAT UNIT PRICE TOTAL PRICE

1 Pek instalasi AC
1 konek AC split floor 5 PK 4 unit 250,000 1,000,000

2 Pek panel AC
1 panel AC
isi mccb 63 amp/acc 1 set 495,000 495,000
2 kbl power nyy 4x16 mm 1.5 m 70,000 105,000
3 upah panel AC 1 unit 200,000 200,000

Ditagih oleh :

Ir siswandi K

TOTAL PENAGIHAN 1,800,000

'file:///conversion/tmp/scratch/427385983.xls'#$pen hrg
PEK : PEK AC R LOBBY anggaran kerja 09/07/19
LOKASI : TWIN HOTEL SLIPI Jakarta 3-07-10

NO ITEM PEKERJAAN VOL SAT UNIT PRICE TOTAL PRICE

1 material kerja/ alat


lak ban lem 3 rol 6,500 19,500
alat kerja 1 lot 40,000 40,000

2 Upah kerja
udin/agus ac/agus k selasa 03/07/10 3 org 65,000 195,000
lembur jumat 3 org 60,000 180,000
udin/agus k 2 org 60,000 120,000

mcb 16 amp 3 bh 150,000 450,000


rel mcb 1 bh 30,000 30,000
bus bar nol 1 bh 20,000 20,000
-

1 Biaya lain
tlp 1 lot 50,000 50,000
transport:
blazer 1 trip 35,000 35,000
zebra 1 trip 30,000 30,000

TOTAL PENGELUARAN 1,169,500

'file:///conversion/tmp/scratch/427385983.xls'#$ang kerja
PEK : PEK AC R LOBBY 09/07/19
LOKASI : TWIN HOTEL SLIPI Jakarta 28-08-10

NO ITEM PEKERJAAN VOL SAT UNIT PRICE TOTAL PRICE

1 Pek instalasi AC
1 Instalasi AC split floor 5 PK 7 unit 575,000 4,025,000
kbl power/ drain AC

2 Instalasi AC cassete 5 PK 4 unit 575,000 2,300,000


kbl power/ drain AC/ pindah indoor

3 alat kerja 1 lot 450,000 450,000


perak/ las
transport 1 lot 200,000 200,000

4 kabel tray 250 mm + tutup 1 bh 700,000 700,000


kerja

Ditagih oleh :

Ir siswandi K

TOTAL PENAGIHAN 7,675,000

'file:///conversion/tmp/scratch/427385983.xls'#$AC MOI
PEK : PENGADAAN MED FILTER 09/07/19
LOKASI : RS KARYA MEDIKA CIBITUNG Jakarta 1-7-19

NO ITEM PEKERJAAN VOL SAT UNIT PRICE TOTAL PRICE

1 Indoor unit AC
pengadaan MED FILTER 8 bh 1,850,000 14,800,000
merk : AAF
type : medium
uk : 24 x 12 x 12 in

2 Indoor unit AC
pengadaan pre filter 8 bh 250,000 2,000,000
merk : AAF
type : pre washable
uk : 24 x 12 x 2 in

3 biaya bongkar/ psg filter 2 AC 200,000 400,000


transport tkg

utk AC R OK 1 dan 2

dp : rp 12 juta

di transfer ke rek mandiri an siswandi kartarahardja

no rek 118 009808 139 0

Ditawarkan oleh :

Ir siswandi K

TOTAL PENAWARAN HARGA 17,200,000