Anda di halaman 1dari 4

REKAPITULASI

DAFTAR KUANTITAS DAN HARGA
PADA RUAS JALAN TOL SEMARANG TAHUN 2019
MATA PEMBAYARAN URAIAN PEKERJAAN  JUMLAH HARGA  
GUARDRAIL

BAB  1 UMUM            33.187.000,00

BAB  12 PEKERJAAN LAIN ‐ LAIN          882.102.000,00

TOTAL PEKERJAAN GUARDRAIL          915.289.000,00

PPN 10%            91.528.900,00

TOTAL + PPN 10%      1.006.817.900,00

PATOK KM

BAB 3 PEMBONGKARAN               7.050.000,00

BAB  12 PEKERJAAN LAIN ‐ LAIN          192.900.000,00

TOTAL PEKERJAAN PATOK KM          199.950.000,00

PPN 10%            19.995.000,00

TOTAL + PPN 10%          219.945.000,00

RAMBU

BAB 3 PEMBONGKARAN              1.527.000,00

BAB 12 PEKERJAAN LAIN‐LAIN                                     ‐


PASANG BARU                                     ‐
PENGGANTIAN PANEL                                     ‐
PENINGGIAN TIANG                                     ‐
PENGGANTIAN STICKER                                     ‐
LAIN‐LAIN                                     ‐

PENCAHAYAAN, LAMPU LALU LINTAS DAN PEKERJAAN 
BAB 13            38.350.000,00
LISTRIK

TOTAL PEKERJAAN RAMBU            39.877.000,00

PPN 10%              3.987.700,00

TOTAL + PPN 10%            43.864.700,00

TOTAL      1.155.116.000,00

PPN 10%          115.511.600,00

TOTAL + PPN 10%      1.270.627.600,00
DAFTAR KUANTITAS DAN HARGA
PEKERJAAN PENGADAAN DAN PERBAIKAN GUARDRAIL
PADA RUAS JALAN TOL SEMARANG TAHUN 2019
MATA PEMBAYARAN URAIAN PEKERJAAN SATUAN  KUANTITAS  HARGA SATUAN  JUMLAH HARGA  
a b c d e f=dxe

BAB  1 UMUM
SK 1.02 (2) Pengamanan Dan Pengaturan Lalu Lintas, Tipe B Lump sum                1,00       28.248.000,00            28.248.000,00
1.35 As Built Drawing Lump sum                1,00         4.939.000,00               4.939.000,00

TOTAL HARGA PENAWARAN UNTUK BAB 1            33.187.000,00
(Pindahkan ke Rekapitulasi)
BAB  12 PEKERJAAN LAIN ‐ LAIN
12.05 (1) Guardrail M'           840,00            788.000,00          661.920.000,00
12.05 (2) End Section Guardrail Buah             92,00            466.000,00            42.872.000,00
SK 2.01 Pengecatan Guardrail M`        8.865,50               20.000,00          177.310.000,00

TOTAL HARGA PENAWARAN UNTUK BAB 12          882.102.000,00
(Pindahkan ke Rekapitulasi)

TOTAL          915.289.000,00

PPN 10%            91.528.900,00

TOTAL + PPN 10%      1.006.817.900,00

1
DAFTAR KUANTITAS DAN HARGA
PEKERJAAN PENGADAAN DAN PEMASANGAN PATOK KILOMETER
PADA JALAN TOL SEMARANG TAHUN 2018

MATA 
URAIAN SATUAN  KUANTITAS  HARGA SATUAN  JUMLAH HARGA 
PEMBAYARAN

a b c d e f = d x e

BAB 3 PEMBONGKARAN

3.01 (4) a Pembongkaran Patok Kilometer buah           150,00              47.000,00                      7.050.000,00

TOTAL HARGA PENAWARAN UNTUK BAB 3                      7.050.000,00

(Pindahkan ke Rekapitulasi)

BAB 12 PEKERJAAN LAIN ‐ LAIN

12.09 (6) Kilometer Post, Tipe A buah           150,00        1.286.000,00                 192.900.000,00

TOTAL HARGA PENAWARAN UNTUK BAB 12                 192.900.000,00

(Pindahkan ke Rekapitulasi)

TOTAL         199.950.000,00

PPN 10%            19.995.000,00

TOTAL + PPN 10%         219.945.000,00
DAFTAR KUANTITAS DAN HARGA
PEKERJAAN PENGADAAN DAN PEMASANGAN RAMBU LALU LINTAS
PADA RUAS JALAN TOL SEMARANG TAHUN 2019

MATA PEMBAYARAN URAIAN SATUAN  KUANTITAS  HARGA SATUAN JUMLAH HARGA 

a b c d e f = d x e

BAB 3 PEMBONGKARAN
3.01 (4) Pembongkaran Rambu Lalu Lintas buah                      3,00                       509.000,00                 1.527.000,0

TOTAL HARGA PENAWARAN UNTUK BAB 3                 1.527.000,0
(Pindahkan ke Rekapitulasi)
BAB 12 PEKERJAAN LAIN ‐ LAIN
PASANG BARU
12.06 (1) Rambu Petunjuk, Peringatan & Larangan, Tipe A‐1 bh                      1,00                 15.302.000,00               15.302.000,0
12.06 (2) Rambu Petunjuk, Peringatan & Larangan, Tipe A‐2 bh                      2,00                 16.930.000,00               33.860.000,0
12.06 (3) Rambu Petunjuk, Peringatan & Larangan, Tipe A‐3 bh                      1,00                 19.284.000,00               19.284.000,0
12.06 (4) Rambu Petunjuk, Peringatan & Larangan, Tipe A‐4 bh                      8,00                 21.822.000,00            174.576.000,0
12.06 (5) Rambu Petunjuk, Peringatan & Larangan, Tipe B‐1 bh                      2,00                 42.489.000,00               84.978.000,0
12.07 (1) Rambu Petunjuk, Tipe A‐1 bh                    10,00                   1.639.000,00               16.390.000,0
12.07 (2) Rambu Petunjuk, Tipe A‐2 bh                      7,00                   2.663.000,00               18.641.000,0
12.07 (4) Rambu Petunjuk, Tipe C‐1 bh                      8,00                   1.360.000,00               10.880.000,0
12.07 (7) Rambu Masif bh                      7,00                   1.021.000,00                 7.147.000,0
PENGGANTIAN PANEL
12.06 (1) a Rambu Petunjuk, Peringatan & Larangan, Tipe A‐1 bh                      9,00                   8.417.000,00               75.753.000,0
12.06 (2) a Rambu Petunjuk, Peringatan & Larangan, Tipe A‐2 bh                      5,00                   9.870.000,00               49.350.000,0
12.06 (3) a Rambu Petunjuk, Peringatan & Larangan, Tipe A‐3 bh                      6,00                 10.760.000,00               64.560.000,0
12.06 (4) a Rambu Petunjuk, Peringatan & Larangan, Tipe A‐4 bh                      1,00                 14.741.000,00               14.741.000,0
12.06 (5) a Rambu Petunjuk, Peringatan & Larangan, Tipe B‐1 bh                      3,00                 21.785.000,00               65.355.000,0
12.06 (7) a Rambu Petunjuk, Peringatan & Larangan, Tipe C‐1 bh                      6,00                 41.530.000,00            249.180.000,0
12.07 (1) a Rambu Petunjuk, Tipe A‐1 bh                    20,00                   1.060.000,00               21.200.000,0
12.07 (2) a Rambu Petunjuk, Tipe A‐2 bh                    16,00                   2.159.000,00               34.544.000,0
12.07 (4) a Rambu Petunjuk, Tipe C‐1 bh                    15,00                   1.007.000,00               15.105.000,0
PENINGGIAN TIANG
12.06 (1) b Rambu Petunjuk, Peringatan & Larangan, Tipe A‐1 bh                      2,00                       831.000,00                 1.662.000,0
12.06 (2) b Rambu Petunjuk, Peringatan & Larangan, Tipe A‐2 bh                      3,00                       831.000,00                 2.493.000,0
12.06 (3) b Rambu Petunjuk, Peringatan & Larangan, Tipe A‐3 bh                      4,00                       831.000,00                 3.324.000,0
12.06 (4) b Rambu Petunjuk, Peringatan & Larangan, Tipe A‐4 bh                      1,00                       831.000,00                    831.000,0
12.07 (1) b Rambu Petunjuk, Tipe A‐1 bh                      4,00                       457.000,00                 1.828.000,0
12.07 (2) b Rambu Petunjuk, Tipe A‐2 bh                      2,00                       457.000,00                    914.000,0
PENGGANTIAN STICKER
12.06 (1) c Rambu Petunjuk, Peringatan & Larangan, Tipe A‐1 bh                      1,00                   2.609.000,00                 2.609.000,0
12.06 (2) c Rambu Petunjuk, Peringatan & Larangan, Tipe A‐2 bh                      1,00                   2.771.000,00                 2.771.000,0
12.06 (3) c Rambu Petunjuk, Peringatan & Larangan, Tipe A‐3 bh                      1,00                   3.699.000,00                 3.699.000,0
12.07 (1) c Rambu Petunjuk, Tipe A‐1 bh                    13,00                       517.000,00                 6.721.000,0
12.07 (2) c Rambu Petunjuk, Tipe A‐2 bh                    13,00                   1.142.000,00               14.846.000,0
12.07 (4) c Rambu Petunjuk, Tipe C‐1 bh                    14,00                       475.000,00                 6.650.000,0
LAIN‐LAIN
12.09 (1) Guide Post, Tipe A bh                  200,00                         63.440,00               12.688.000,0
12.09 (2) Guide Post, Tipe B bh                  200,00                         63.440,00               12.688.000,0
SK 2.02 (7) Pemindahan Rambu Petunjuk, Peringatan & Larangan, Tipe  C‐1 bh                      1,00                   7.540.000,00                 7.540.000,0
SK 2.03 Pengecatan Tiang Rambu m2                  100,00                         47.000,00                 4.700.000,0

TOTAL HARGA PENAWARAN UNTUK BAB 12         1.056.810.000,0
(Pindahkan ke Rekapitulasi)
BAB 13 PENCAHAYAAN, LAMPU LALU LINTAS DAN PEKERJAAN LISTRIK

13.01 (15) Kabel NYFGBY 4C ‐ 10 mm2 m                  230,00                         95.000,00               21.850.000,0


13.01 (6) Lampu Kedip (Flashing Light ) buah                      2,00                   8.250.000,00               16.500.000,0

TOTAL HARGA PENAWARAN UNTUK BAB 13              38.350.000,0
(Pindahkan ke Rekapitulasi)
TOTAL         1.096.687.000,0

PPN 10%            109.668.700,0

TOTAL + PPN 10%         1.206.355.700,0

Anda mungkin juga menyukai