DAFTAR KUANTITAS DAN HARGA
PADA RUAS JALAN TOL SEMARANG TAHUN 2019
MATA PEMBAYARAN URAIAN PEKERJAAN JUMLAH HARGA
GUARDRAIL
TOTAL PEKERJAAN GUARDRAIL 915.289.000,00
PPN 10% 91.528.900,00
TOTAL + PPN 10% 1.006.817.900,00
PATOK KM
TOTAL PEKERJAAN PATOK KM 199.950.000,00
PPN 10% 19.995.000,00
TOTAL + PPN 10% 219.945.000,00
RAMBU
PENCAHAYAAN, LAMPU LALU LINTAS DAN PEKERJAAN
BAB 13 38.350.000,00
LISTRIK
TOTAL PEKERJAAN RAMBU 39.877.000,00
PPN 10% 3.987.700,00
TOTAL + PPN 10% 43.864.700,00
TOTAL 1.155.116.000,00
PPN 10% 115.511.600,00
TOTAL + PPN 10% 1.270.627.600,00
DAFTAR KUANTITAS DAN HARGA
PEKERJAAN PENGADAAN DAN PERBAIKAN GUARDRAIL
PADA RUAS JALAN TOL SEMARANG TAHUN 2019
MATA PEMBAYARAN URAIAN PEKERJAAN SATUAN KUANTITAS HARGA SATUAN JUMLAH HARGA
a b c d e f=dxe
BAB 1 UMUM
SK 1.02 (2) Pengamanan Dan Pengaturan Lalu Lintas, Tipe B Lump sum 1,00 28.248.000,00 28.248.000,00
1.35 As Built Drawing Lump sum 1,00 4.939.000,00 4.939.000,00
TOTAL HARGA PENAWARAN UNTUK BAB 1 33.187.000,00
(Pindahkan ke Rekapitulasi)
BAB 12 PEKERJAAN LAIN ‐ LAIN
12.05 (1) Guardrail M' 840,00 788.000,00 661.920.000,00
12.05 (2) End Section Guardrail Buah 92,00 466.000,00 42.872.000,00
SK 2.01 Pengecatan Guardrail M` 8.865,50 20.000,00 177.310.000,00
TOTAL HARGA PENAWARAN UNTUK BAB 12 882.102.000,00
(Pindahkan ke Rekapitulasi)
TOTAL 915.289.000,00
PPN 10% 91.528.900,00
TOTAL + PPN 10% 1.006.817.900,00
1
DAFTAR KUANTITAS DAN HARGA
PEKERJAAN PENGADAAN DAN PEMASANGAN PATOK KILOMETER
PADA JALAN TOL SEMARANG TAHUN 2018
MATA
URAIAN SATUAN KUANTITAS HARGA SATUAN JUMLAH HARGA
PEMBAYARAN
a b c d e f = d x e
BAB 3 PEMBONGKARAN
TOTAL HARGA PENAWARAN UNTUK BAB 3 7.050.000,00
(Pindahkan ke Rekapitulasi)
BAB 12 PEKERJAAN LAIN ‐ LAIN
TOTAL HARGA PENAWARAN UNTUK BAB 12 192.900.000,00
(Pindahkan ke Rekapitulasi)
TOTAL 199.950.000,00
PPN 10% 19.995.000,00
TOTAL + PPN 10% 219.945.000,00
DAFTAR KUANTITAS DAN HARGA
PEKERJAAN PENGADAAN DAN PEMASANGAN RAMBU LALU LINTAS
PADA RUAS JALAN TOL SEMARANG TAHUN 2019
a b c d e f = d x e
BAB 3 PEMBONGKARAN
3.01 (4) Pembongkaran Rambu Lalu Lintas buah 3,00 509.000,00 1.527.000,0
TOTAL HARGA PENAWARAN UNTUK BAB 3 1.527.000,0
(Pindahkan ke Rekapitulasi)
BAB 12 PEKERJAAN LAIN ‐ LAIN
PASANG BARU
12.06 (1) Rambu Petunjuk, Peringatan & Larangan, Tipe A‐1 bh 1,00 15.302.000,00 15.302.000,0
12.06 (2) Rambu Petunjuk, Peringatan & Larangan, Tipe A‐2 bh 2,00 16.930.000,00 33.860.000,0
12.06 (3) Rambu Petunjuk, Peringatan & Larangan, Tipe A‐3 bh 1,00 19.284.000,00 19.284.000,0
12.06 (4) Rambu Petunjuk, Peringatan & Larangan, Tipe A‐4 bh 8,00 21.822.000,00 174.576.000,0
12.06 (5) Rambu Petunjuk, Peringatan & Larangan, Tipe B‐1 bh 2,00 42.489.000,00 84.978.000,0
12.07 (1) Rambu Petunjuk, Tipe A‐1 bh 10,00 1.639.000,00 16.390.000,0
12.07 (2) Rambu Petunjuk, Tipe A‐2 bh 7,00 2.663.000,00 18.641.000,0
12.07 (4) Rambu Petunjuk, Tipe C‐1 bh 8,00 1.360.000,00 10.880.000,0
12.07 (7) Rambu Masif bh 7,00 1.021.000,00 7.147.000,0
PENGGANTIAN PANEL
12.06 (1) a Rambu Petunjuk, Peringatan & Larangan, Tipe A‐1 bh 9,00 8.417.000,00 75.753.000,0
12.06 (2) a Rambu Petunjuk, Peringatan & Larangan, Tipe A‐2 bh 5,00 9.870.000,00 49.350.000,0
12.06 (3) a Rambu Petunjuk, Peringatan & Larangan, Tipe A‐3 bh 6,00 10.760.000,00 64.560.000,0
12.06 (4) a Rambu Petunjuk, Peringatan & Larangan, Tipe A‐4 bh 1,00 14.741.000,00 14.741.000,0
12.06 (5) a Rambu Petunjuk, Peringatan & Larangan, Tipe B‐1 bh 3,00 21.785.000,00 65.355.000,0
12.06 (7) a Rambu Petunjuk, Peringatan & Larangan, Tipe C‐1 bh 6,00 41.530.000,00 249.180.000,0
12.07 (1) a Rambu Petunjuk, Tipe A‐1 bh 20,00 1.060.000,00 21.200.000,0
12.07 (2) a Rambu Petunjuk, Tipe A‐2 bh 16,00 2.159.000,00 34.544.000,0
12.07 (4) a Rambu Petunjuk, Tipe C‐1 bh 15,00 1.007.000,00 15.105.000,0
PENINGGIAN TIANG
12.06 (1) b Rambu Petunjuk, Peringatan & Larangan, Tipe A‐1 bh 2,00 831.000,00 1.662.000,0
12.06 (2) b Rambu Petunjuk, Peringatan & Larangan, Tipe A‐2 bh 3,00 831.000,00 2.493.000,0
12.06 (3) b Rambu Petunjuk, Peringatan & Larangan, Tipe A‐3 bh 4,00 831.000,00 3.324.000,0
12.06 (4) b Rambu Petunjuk, Peringatan & Larangan, Tipe A‐4 bh 1,00 831.000,00 831.000,0
12.07 (1) b Rambu Petunjuk, Tipe A‐1 bh 4,00 457.000,00 1.828.000,0
12.07 (2) b Rambu Petunjuk, Tipe A‐2 bh 2,00 457.000,00 914.000,0
PENGGANTIAN STICKER
12.06 (1) c Rambu Petunjuk, Peringatan & Larangan, Tipe A‐1 bh 1,00 2.609.000,00 2.609.000,0
12.06 (2) c Rambu Petunjuk, Peringatan & Larangan, Tipe A‐2 bh 1,00 2.771.000,00 2.771.000,0
12.06 (3) c Rambu Petunjuk, Peringatan & Larangan, Tipe A‐3 bh 1,00 3.699.000,00 3.699.000,0
12.07 (1) c Rambu Petunjuk, Tipe A‐1 bh 13,00 517.000,00 6.721.000,0
12.07 (2) c Rambu Petunjuk, Tipe A‐2 bh 13,00 1.142.000,00 14.846.000,0
12.07 (4) c Rambu Petunjuk, Tipe C‐1 bh 14,00 475.000,00 6.650.000,0
LAIN‐LAIN
12.09 (1) Guide Post, Tipe A bh 200,00 63.440,00 12.688.000,0
12.09 (2) Guide Post, Tipe B bh 200,00 63.440,00 12.688.000,0
SK 2.02 (7) Pemindahan Rambu Petunjuk, Peringatan & Larangan, Tipe C‐1 bh 1,00 7.540.000,00 7.540.000,0
SK 2.03 Pengecatan Tiang Rambu m2 100,00 47.000,00 4.700.000,0
TOTAL HARGA PENAWARAN UNTUK BAB 12 1.056.810.000,0
(Pindahkan ke Rekapitulasi)
BAB 13 PENCAHAYAAN, LAMPU LALU LINTAS DAN PEKERJAAN LISTRIK
TOTAL HARGA PENAWARAN UNTUK BAB 13 38.350.000,0
(Pindahkan ke Rekapitulasi)
TOTAL 1.096.687.000,0
PPN 10% 109.668.700,0
TOTAL + PPN 10% 1.206.355.700,0