Anda di halaman 1dari 87

minggu bulan

4.892 APRIL 2013 1 1 (Pertama 0.09 4.31 21-Mar 24-Mar


16.027 MEI 2013 2 2 (Dua) 0.18 22.57 25-Mar 31-Mar
34.647 JUNI 2013 3 3 (Tiga) 0.67 50.56 1-Apr 7-Apr
71.654 JULI 2013 4 4 (Empat) 1.46 82.85 8-Apr 14-Apr
97.415 AGUSTUS 2013 5 5 (Lima) 2.40 99.12 15-Apr 21-Apr
100.000 SEPTEMBER 2013 6 6 (Enam) 4.31 100.00 22-Apr 28-Apr
7 7 (Tujuh) 6.36 29-Apr 5-May
8 8 (Delapan 20.96 - 6-May 12-May
9 9 (Sembila 21.77 13-May 19-May
10 10 (Sepulu 22.57 20-May 26-May
11 11 (Sebela 23.77 27-May 2-Jun
12 12 (Duabel 25.96 3-Jun 9-Jun
13 13 (Tigabe 34.30 10-Jun 16-Jun
14 14 (Empatb 42.66 17-Jun 23-Jun
15 15 (Limabe 50.56 24-Jun 30-Jun
16 16 (Enamb 58.89 1-Jul 7-Jul
17 17 (Tujuhb 67.22 8-Jul 14-Jul
18 18 (Delapa 76.67 15-Jul 21-Jul
19 19 (Sembil 82.85 22-Jul 28-Jul
20 20 (Duapul 89.04 29-Jul 4-Aug
21 21 (Duapul 95.22 5-Aug 11-Aug
22 22 (Duapul 96.24 12-Aug 18-Aug
23 23 (Duapuh 98.10 19-Aug 25-Aug
24 24 (Duapul 99.12 26-Aug 1-Sep
25 25 (Duapul 99.81 2-Sep 8-Sep
26 26 (Duapu 100.00 9-Sep 13-Sep
27 27 (Duapuluh tujuh)
28 28 (Duapuluh delapan)
29 29 (Duapuluh sembilan)
30 30 (Tigapuluh)
31 31 (Tigapuluh satu)
32 32 (Tigapuluh dua)
33 33 (Tigapuluh tiga)
34 34 (Tigapuluh empat)
35 35 (Tigapuluh lima)
SATKER : SATKER PELAKSANAAN JALAN NASIONAL WILAYAH III PROVINSI NTB
PPK : PPK. BATAS KAB. DOMPU - BANGGO - BALIBUNGA - MADAPRAMA
PAKET : PELEBARAN KAWASAN STRATEGIS JALAN KEMPO - KESI - HODO (PPK 08) SEPANJANG 7.90 KM
KONTRAK : KU.02.09/PPK08-WIL3NTB/180/2013
TANGGAL 21 MARET 2013
KONTRAKTOR : PT. DUNIA MAS

MATA QUANTITY
BOBOT
PEMBA URAIAN PEKERJAAN SAT
KONTRAK (%)
YARAN CCO.01
ASLI
DIV.1 U M U M

1.2. Mobilisasi Ls 1.00 1.00 0.281

1.8 Manajemen dan Keselamatan Lalu Lintas Ls 1.00 1.00 0.062

1.17 Pengamanan Lingkungan Hidup Ls 1.00 1.00 0.217

1.21 Manajemen Mutu Ls 1.00 1.00 0.229

Sub Total Div. 1 0.789


DIV.2 DRAINASE

2.1 Galian untuk Selokan Drainase dan Saluran Air M3 695.67 6,438.04 1.254

2.2 Pasangan Batu dengan Mortar M3 200.63 653.64 1.493

Sub Total Div. 2 2.748


DIV. 3 PEKERJAAN TANAH

3.1.1a Galian Biasa M3 6,350.40 4,428.26 1.129

3.1.1b Galian Batu Cadas Muda M3 50.00 - -

3.1.2 Galian Batu M3 50.00 - -

3.1.3 Galian Struktur dengan Kedalaman 0 - 2 meter M3 54.00 417.12 0.108

3.1.8 Galian Perkerasan Berbutir M3 25.00 - -

3.2.1 Timbunan Biasa M3 241.50 - -

3.2.2 Timbunan Pilihan M3 2,370.00 5,570.22 4.919

3.3 Penyiapan Badan Jalan M2 17,820.00 13,613.40 0.217

Sub Total Div. 3 6.373


DIV. 4 PELEBARAN PERKERASAN DAN BAHU JALAN

4.2.2 Lapis Pondasi Agregat Klas B M3 2,370.00 1,166.00 2.222

Sub Total Div. 4 2.222


DIV. 5 PERKERASAN BERBUTIR

5.1.1 Lapis Pondasi Agregat Klas A M3 9,480.00 9,435.96 19.809

5.1.2 Lapis Pondasi Agregat Klas B M3 6,824.50 8,390.32 15.650


5.1.2 Lapis Pondasi Agregat Klas B M3 6,824.50 8,390.32 15.650

Sub Total Div. 5 35.459


DIV. 6 PERKERASAN ASPAL

6.1(1)(a) Lapis Resap Pengikat - Aspal Cair Liter 39,421.56 40,263.40 2.019

6.1(2)(a) Lapis Perekat - Aspal Cair Liter 7,157.40 7,105.31 0.374

6.3(5a) Laston Lapis Aus (AC-WC) gradasi halus/kasar Ton 4,007.60 3,947.81 7.527

6.3(6a) Laston Lapis Antara (AC-BC) gradasi halus/kasar Ton 5,832.47 6,002.11 11.020

6.3.8.a Aspal Keras Ton 663.43 600.62 28.382

6.3.9 Aditif Anti Pengelupasan Kg 1,990.30 1,201.24 0.323

6.3.10a Bahan Pengisi (Filler) Tambahan (Semen) Kg 149,848.70 99,499.23 0.541

Sub Total Div. 6 50.186


DIV. 7 STRUKTUR

7.1(7) Beton mutu sedang dengan fc'=20 MPa (K-250) M3 7.02 29.21 0.206

7.3(1) Baja Tulangan BJ 24 Polos Kg 1,123.48 5,989.00 0.458

7.9 Pasangan Batu M3 274.87 424.05 1.001

Sub Total Div. 7 1.665


DIV. 8 PENGEMBALIAN KONDISI DAN PEKERJAAN MINOR

8.1(1) Lapisan Pondasi Agregat Klas A untuk Pekerjaan Minor M3 10.00 - -

8.3(3) Pohon Buah 100.00 100.00 0.018

8.4(1) Marka Jalan Termoplastik M2 2,251.50 - -

8.4(3)(a) Rambu Jalan Tunggal dgn Permukaan Pemantul Engineer Grade Buah 42.00 42.00 0.116

8.4(5) Patok Pengarah Buah 150.00 150.00 0.114

8.4(6)(a) Patok Kilometer Buah 8.00 8.00 0.017

8.4(6)(b) Patok Hektometer Buah 86.00 71.00 0.077

Sub Total Div. 8 0.343


DIV. 10 PEKERJAAN PEMELIHARAAN RUTIN

10.1(2) Pemeliharaan Rutin Bahu Jalan Ls 1.00 1.00 0.088

10.1(3) Pemeliharaan Rutin Selokan, Saluran Air, Galian dan Timbunan Ls 1.00 1.00 0.110

10.1(4) Pemeliharaan Rutin Perlengkapan Jalan Ls 1.00 1.00 0.018

Sub Total Div. 10 0.216


Total 100.000
Kontrak Rencana Kemajuan Pekerjaan (%)
Awal Rencana Kemajuan Pekerjaan Komulatif (%)
Rencana Kemajuan Pekerjaan (CCO - 01) (%)
CCO.01
Rencana Kemajuan Pekerjaan Komulatif (CCO - 01) (%)
Realisasi Kemajuan Pekerjaan (%)
Realisasi
Realisasi Kemajuan Pekerjaan Komulatif (%)
Deviasi (%)

Disetujui Oleh ;
PPK 08 Batas Kab. Dompu - Banggo - Balibunga - Madaprama

UJANG SUKMANA, ST, MM, MT.


Nip. 196202251989031005
JADWAL WAKTU PELAKSANAAN

KEMAJUAN PEKE
21-Mar 25-Mar 1-Apr 8-Apr 15-Apr 22-Apr 29-Apr 6-May 13-May 20-May 27-May 3-Jun 10-Jun
1 2 3 4 5 6 7 8 9 10 11 12 13
24-Mar 31-Mar 7-Apr 14-Apr 21-Apr 28-Apr 5-May 12-May 19-May 26-May 2-Jun 9-Jun 16-Jun

0.070 0.070

0.028 0.042 0.042 0.028 - - - - - 0.056 - - -


0.008 0.008 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002

0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002
0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.011 0.011 0.011 0.011 0.011 0.011

- - - - - - - - - - - - -
0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.009

- 0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.009

0.045 0.045 0.045

- 0.089 0.043 - - - 0.004 - - - 0.003 - -


0.103 0.103 0.103 0.103

- - 0.121 0.169 0.199 - 0.026 - - - 0.979 - -

0.405 0.405 0.405 0.405 0.255

- - 0.096 0.057 0.263 0.114 0.343 - 0.119 - 0.065 - -


0.024 0.024

- - - - - - - - - -
0.028 0.028

- - - - - - - - - -
0.013 0.013 0.043 0.043

- - - - 0.022 - - - - - 0.085 - -
0.015 0.015

- - - - - - - - - -
0.067

- - - - - - - - - -
0.984 0.984

- - - - - - - - - - - - -
0.095 0.095 0.095

- - 0.024 0.014 0.066 0.029 0.084 - - - - - -

- - - - - - - - - - - - -

7.329

- - - - - 5.139 - A 6.688 4.283 - 0.504 - 3.196


1.000 1.546 0.730 0.730 0.730 0.730
D
D
D
D
- - - 1.119 2.913 8.697 - - - - 2.921 - -
E
N
D
U
- - - - - - - M - - 0.521 - - -
K
- - - - - - - O - - - - - -
N
T
- - - - - - - R - - - - - -
A
- - - - - - - K - - 2.847 - - -
(
C
- - - - - - - C - - 4.225 - - -
O
- - - - - - - 0 - - 0.048 - - -
1
REALISASI
)
- - - - - - - - - 0.084 - - -

0.025 0.025 0.078 0.078

- - - - 0.038 0.011 - - - - 0.029 0.127 -


0.043 0.043 0.186 0.186

- - - - 0.051 0.034 - - - - 0.010 0.362 -


0.162 0.162 0.162 0.162 0.176 0.176

- - - - 0.074 0.575 - - - - 0.194 0.158 -

0.021

- - - - - - - - - - - -

- - - - - - - - - - - - -

- - - - - - - - - - - -

- - - - - - - - - - - - -

- - - - - - - - - - - - -

- - - - - - - - - - - - -

- - - - - - - - - - - - -

0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004

- - 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004
0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005

- - 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005
0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001

- - 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001
0.087 0.095 0.484 0.796 0.933 1.910 2.054 2.800 2.641 2.574 2.891 3.345 4.345
0.087 0.182 0.666 1.462 2.395 4.305 6.360 9.160 11.801 14.375 17.266 20.612 24.957
0.287 0.805 0.805 1.202 2.186 8.345
20.960 21.765 22.570 23.772 25.958 34.303
0.030 0.142 0.346 1.408 3.647 14.621 0.478 6.709 4.422 7.803 4.810 0.668 3.216
0.030 0.173 0.519 1.927 5.574 20.195 20.673 27.382 31.804 39.607 44.417 45.085 48.301
0.057 -0.010 -0.148 0.465 3.179 15.890 14.314 18.222 20.003 25.231 20.644 19.126 13.997

Diperiksa Oleh,
Konsultan Supervisi
PT. CIRIATAMA NUSAWIDYA CONSULT

LALU ARIAWAN, ST
Site Engineer
SATKER : PERENCANAAN DAN PENGAWASAN JALAN NASIONAL PROV
PAKET : 15 (Lima Belas) PENGAWASAN TEKNIK JALAN KEMPO - KE

KONTRAK : KU.03.01/KONT/SNVT P2JN-NTB/113/2013


TANGGGAL 14 FEBRUARI 2013
KONSULTAN : PT. CIRIATAMA NUSAWIDYA CONSULT
MAJUAN PEKERJAAN
17-Jun 24-Jun 1-Jul 8-Jul 15-Jul 22-Jul 29-Jul 5-Aug 12-Aug 19-Aug 26-Aug 2-Sep 9-Sep
14 15 16 17 18 19 20 21 22 23 24 25 26
23-Jun 30-Jun 7-Jul 14-Jul 21-Jul 28-Jul 4-Aug 11-Aug 18-Aug 25-Aug 1-Sep 8-Sep 16-Sep

0.056 0.084

- -
0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002

0.002 0.002
0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011

- -
0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.009

0.009 0.009

0.373 0.373 0.373

0.301 0.290
0.489 0.489

- -

- -

RENCANA ADDENDUM
KONTRAK (CCO 01)

- -

0.984 0.984 0.984

- -

- -

0.841 0.741 0.641

- -

7.341

- -
- -

0.505 0.505 0.505 0.505

0.512 0.128
0.093 0.093 0.093 0.093

- -
1.882 1.882 1.882 1.882

- -
2.755 2.755 2.755 2.755

2.803 0.701
4.055 4.055 4.055 4.055 4.055 4.055 4.055

4.159 1.040
0.046 0.046 0.046 0.046 0.046 0.046 0.046

0.047 0.012
0.077 0.077 0.077 0.077 0.077 0.077 0.077

0.083 0.021

- -

- -

- -

RENCANA KONTRAK
AWAL

- -
0.009 0.009

- -

- -
0.116

- -
0.114

- -
0.017

- -
0.077

- -

0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004

0.004 0.004
0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005

0.005 0.005
0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001

0.001 0.001
4.345 5.345 8.188 8.871 8.871 8.875 7.704 7.704 6.750 3.715 2.925 1.543 0.206
29.302 34.647 42.835 51.706 60.577 69.452 77.156 84.860 91.611 95.326 98.251 99.794 100.000
8.357 7.899 8.332 8.332 9.445 6.185 6.185 6.185 1.016 1.856 1.029 0.682 0.194
42.660 50.559 58.891 67.223 76.668 82.853 89.039 95.224 96.239 98.096 99.125 99.806 100.000
7.926 2.212
56.227 58.438
13.567 7.879

Dompu,
D
Kpntra
T PT.

Drs. Ec.
NASIONAL PROV. NTB
AN KEMPO - KESI - HODO

MASA
PEME
SKALA KET.
LIHA
RAAN

100.00

75.00
) HARI KALENDER
PEMELIHARAAN 720 (TUJUH RATUS DUA PULUH) HA

0.00
25.00
50.00
Kontrak Awal

CCO - 01

Realisasi

30 Juni 2013
Dibuat oleh,
Kpntraktor Pelaksana
PT. DUNIA MAS

Drs. Ec. JONI MUCHTAR


Direktur
SATKER : SATKER PELAKSANAAN JALAN NASIONAL WILAYAH III PROVINSI NTB
PPK : PPK. BATAS KAB. DOMPU - BANGGO - BALIBUNGA - MADAPRAMA
PAKET : PELEBARAN KAWASAN STRATEGIS JALAN KEMPO - KESI - HODO (PPK 08) SEP
KONTRAK : KU.02.09/PPK08-WIL3NTB/180/2013
TANGGAL 21 MARET 2013
KONTRAKTOR : PT. DUNIA MAS
MATA
QUANTITY
PEMBA
URAIAN PEKERJAAN SAT
YARAN KONTRAK
ASLI
DIV.1 U M U M

1.2. Mobilisasi Ls 1.00

1.8 Manajemen dan Keselamatan Lalu Lintas Ls 1.00

1.17 Pengamanan Lingkungan Hidup Ls 1.00

1.21 Manajemen Mutu Ls 1.00

Sub Total Div. 1


DIV.2 DRAINASE

2.1 Galian untuk Selokan Drainase dan Saluran Air M3 695.67

2.1 Pasangan Batu dengan Mortar M3 200.63

Sub Total Div. 2


DIV. 3 PEKERJAAN TANAH

3.1.1a Galian Biasa M3 6,350.40

3.1.1b Galian Batu Cadas Muda M3 50.00

3.1.2 Galian Batu M3 50.00

3.1.3 Galian Struktur dengan Kedalaman 0 - 2 meter M3 54.00

3.1.8 Galian Perkerasan Berbutir M3 25.00


3.1.8 Galian Perkerasan Berbutir M3 25.00

3.2.1 Timbunan Biasa M3 241.50

3.2.2 Timbunan Pilihan M3 2,370.00

3.3 Penyiapan Badan Jalan M2 17,820.00

Sub Total Div. 3


DIV. 4 PELEBARAN PERKERASAN DAN BAHU JALAN

4.2.2 Lapis Pondasi Agregat Klas B M3 2,370.00

Sub Total Div. 4


DIV. 5 PERKERASAN BERBUTIR

5.1.1 Lapis Pondasi Agregat Klas A M3 9,480.00

5.1.2 Lapis Pondasi Agregat Klas B M3 6,824.50

Sub Total Div. 5


DIV. 6 PERKERASAN ASPAL

6.1(1)(a) Lapis Resap Pengikat - Aspal Cair Liter 39,421.56

6.1(2)(a) Lapis Perekat - Aspal Cair Liter 7,157.40

6.3(5a) Laston Lapis Aus (AC-WC) gradasi halus/kasar Ton 4,007.60

6.3(6a) Laston Lapis Antara (AC-BC) gradasi halus/kasar Ton 5,832.47

6.3.8.a Aspal Keras Ton 663.43

6.3.9 Aditif Anti Pengelupasan Kg 1,990.30

6.3.10a Bahan Pengisi (Filler) Tambahan (Semen) Kg 149,848.70

Sub Total Div. 6


DIV. 7 STRUKTUR

7.1(7) Beton mutu sedang dengan fc'=20 MPa (K-250) M3 7.02


7.1(7) Beton mutu sedang dengan fc'=20 MPa (K-250) M3 7.02

7.3(1) Baja Tulangan BJ 24 Polos M3 1,123.48

7.9 Pasangan Batu M3 274.87

Sub Total Div. 7


DIV. 8 PENGEMBALIAN KONDISI DAN PEKERJAAN MINOR

8.1(1) Lapisan Pondasi Agregat Klas A untuk Pekerjaan Minor M3 10.00

8.3(3) Pohon Buah 100.00

8.4(1) Marka Jalan Termoplastik M2 2,251.50

8.4(3)(a) Rambu Jalan Tunggal dgn Permukaan Pemantul Engineer Buah 42.00

8.4(5) Patok Pengarah Buah 150.00

8.4(6)(a) Patok Kilometer Buah 8.00

8.4(6)(b) Patok Hektometer Buah 86.00

Sub Total Div. 8


DIV. 10 PEKERJAAN PEMELIHARAAN RUTIN

10.1(2) Pemeliharaan Rutin Bahu Jalan Ls 1.00

10.1(3) Pemeliharaan Rutin Selokan, Saluran Air, Galian dan Timb Ls 1.00

10.1(4) Pemeliharaan Rutin Perlengkapan Jalan Ls 1.00

Sub Total Div. 10


Total
Kontrak Rencana Kemajuan Pekerjaan (%)
Awal Rencana Kemajuan Pekerjaan Komulatif (%)
Rencana Kemajuan Pekerjaan (CCO - 01) (%)
CCO.01
Rencana Kemajuan Pekerjaan Komulatif (CCO - 01) (%)
Realisasi Kemajuan Pekerjaan (%)
Realisasi
Realisasi Kemajuan Pekerjaan Komulatif (%)
Deviasi (%)
Disetujui Oleh ;
PPK 08 Batas Kab. Dompu - Banggo - Balibunga - Madaprama

UJANG SUKMANA, ST, MM, MT.


Nip. 196202251989031005
PROVINSI NTB

I - HODO (PPK 08) SEPANJANG 7.90 KM

QUANTITY
BOBOT 21-Mar 25-Mar 1-Apr 8-Apr 15-Apr 22-Apr
(%) 1 2 3 4 5 6
CCO.01
24-Mar 31-Mar 7-Apr 14-Apr 21-Apr 28-Apr

0.070 0.070
1.00 0.281
0.028 0.042 0.042 0.028 - -
0.008 0.008 0.002 0.002 0.002
1.00 0.062
0.002 0.002 0.002 0.002 0.002 0.002
0.008 0.008 0.008 0.008 0.008 0.008
1.00 0.217
- - - - - -
0.009 0.009 0.009 0.009 0.009 0.009
1.00 0.229
- 0.009 0.009 0.009 0.009 0.009
0.789

0.418 0.418 0.418


6,438.04 1.254
- 0.089 0.043 - - -
0.299 0.299 0.299
653.64 1.493
- - 0.121 0.169 0.199 -
2.748

0.282 0.282 0.282 0.282


4,428.26 1.129
- - 0.096 0.057 0.263 0.114
0.024 0.024
- -
- - - - - -
0.028 0.028
- -
- - - - - -
0.054
417.12 0.108
- - - - 0.022 -
0.015
- -
- -
- - - - - -

- -
- - - - - -

5,570.22 4.919
- - - - - -
0.072 0.072
13,613.40 0.217
- - 0.024 0.014 0.066 0.029
6.373

1,166.00 2.222
- - - - - -
2.222

9,435.96 19.809
- - - - - 5.139
1.000
8,390.32 15.650
- - - 1.119 2.913 8.697
35.459

40,263.40 2.019
- - - - - -

7,105.31 0.374
- - - - - -

3,947.81 7.527
- - - - - -

6,002.11 11.020
- - - - - -

600.62 28.382
- - - - - -

1,201.24 0.323
- - - - - -

99,499.23 0.541
- - - - - -
50.186

0.103
29.21 0.206
29.21 0.206
- - - - 0.038 0.011
0.229 0.229
5,989.00 0.458
- - - - 0.051 0.034
0.250 0.250 0.250
424.05 1.001
- - - - 0.074 0.575
1.665

0.021
- -
- - - - - -

100.00 0.018
- - - - - -

- -
- - - - - -

42.00 0.116
- - - - - -

150.00 0.114
- - - - - -

8.00 0.017
- - - - - -

71.00 0.077
- - - - - -
0.343

0.004 0.004 0.004 0.004


1.00 0.088
- - 0.004 0.004 0.004 0.004
0.005 0.005 0.005 0.005
1.00 0.110
- - 0.005 0.005 0.005 0.005
0.001 0.001 0.001 0.001
1.00 0.018
- - 0.001 0.001 0.001 0.001
0.216
100.000
0.087 0.095 0.484 0.796 0.933 1.910
0.087 0.182 0.666 1.462 2.395 4.305

0.030 0.142 0.346 1.408 3.647 14.621


0.030 0.173 0.519 1.927 5.574 20.195
-0.057 -0.010 -0.148 0.465 3.179 15.890
JADWAL WAKTU PELAKSANA

KE
29-Apr 1-May 6-May 13-May 16-May 20-May 27-May 31-May
6a 7 8 9 9a 10 11 11a
30-Apr 5-May 12-May 15-May 19-May 26-May 30-May 2-Jun

- - - - - 0.056 - -
0.001 0.001 0.002 0.001 0.001 0.002 0.001 0.001

0.001 0.002 0.002 0.001 0.001 0.002 0.001 0.001


0.002 0.006 0.011 0.005 0.007 0.011 0.007 0.005

- - - - - - - -
0.003 0.006 0.009 0.004 0.005 0.009 0.005 0.004

0.003 0.007 0.009 0.004 0.005 0.009 0.005 0.004

0.004 0.000 - - - - 0.003 -


0.085 0.213

0.026 - - - - - 0.979 -

0.255

- 0.343 - 0.035 0.083 - 0.065 -

- - - - - - -

- - - - - - -
0.015 0.038 0.018 0.024 0.043

0.004 (0.004) - - - - 0.085 -


0.004 0.011
- - - - - - -
0.019 0.048 - - -

- - - - - - -

- - - - - - - -
0.021 0.052

- 0.084 - - - - - -

- - - - - - - -

A
- -D 6.688 1.827 2.456 - 0.504 -
0.609 1.521 0.313 0.417 0.730 0.417 0.313
D
- - E - - - - 2.921 -
N
D
U
M
- - - - - 0.521 - -

K
- -O - - - - - -
N
T
- - - - - - - -
R
A
- -K - - - 2.847 - -
(
C
- - - - - 4.225 - -
C
O
- - 0 - - - 0.048 - -
REALISASI
1
)
- - - - - 0.084 - -

0.029 0.074 0.045 0.034


- - - - - - 0.029 -
0.106 0.080

- - - - - - 0.010 -
0.072 0.179 0.101 0.075

- - - - - - 0.194 -

- - - - - - -

- - - - - - - -

- - - - - - -

- - - - - - - -

- - - - - - - -

- - - - - - - -

- - - - - - - -

0.001 0.003 0.004 0.002 0.002 0.004 0.002 0.002

0.001 0.003 0.004 0.002 0.002 0.004 0.002 0.002


0.001 0.003 0.005 0.002 0.003 0.005 0.003 0.002

0.001 0.003 0.005 0.002 0.003 0.005 0.003 0.002


0.000 0.001 0.001 0.000 0.000 0.001 0.000 0.000

0.000 0.001 0.001 0.000 0.000 0.001 0.000 0.000

0.587 1.467 2.800 1.132 1.509 2.574 1.652 1.239


4.892 6.360 9.160 10.292 11.801 14.375 16.027 17.266
0.287 0.345 0.460 0.805 0.687 0.515
20.960 21.305 21.765 22.570 23.257 23.772
0.040 0.438 6.709 1.871 2.551 7.803 4.802 0.009
20.235 20.673 27.382 29.253 31.804 39.607 44.408 44.417
15.343 14.314 18.222 18.961 20.003 25.231 21.151 20.644
Diperiksa Oleh,
Konsultan Supervisi
PT. CIRIATAMA NUSAWIDYA CONS

LALU ARIAWAN, ST
Site Engineer
ELAKSANAAN

KEMAJUAN PEKERJAAN
3-Jun 10-Jun 17-Jun 24-Jun 1-Jul 8-Jul 15-Jul 22-Jul
12 13 14 15 16 17 18 19
9-Jun 16-Jun 23-Jun 30-Jun 7-Jul 14-Jul 21-Jul 28-Jul

0.056

- - - -
0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002

0.002 0.002 0.002 0.002


0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011

- - - -
0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.009

0.009 0.009 0.009 0.009

0.373 0.373 0.373

- - 0.301 0.290
0.489 0.489

- - - -

- - - -

- - - -
RENCANA ADDENDUM
KONTRAK (CCO 01)
- - - -

- - - -
- - - -

- - - -
0.984 0.984 0.984

- - - -

- - - -

- - - -

7.329 7.341

- 3.196 - -
0.730

- - - -

0.505 0.505 0.505 0.505

- - 0.512 0.128
0.093 0.093

- - - -
1.882 1.882

- - - -
2.755 2.755 2.755 2.755

- - 2.803 0.701
4.055 4.055 4.055 4.055 4.055

- - 4.159 1.040
0.046 0.046 0.046 0.046 0.046

- - 0.047 0.012
0.077 0.077 0.077 0.077 0.077

- - 0.083 0.021

0.078
0.127 - - -
0.186

0.362 - - -
0.176

0.158 - - -

RENCANA KONTRAK
- - - - AWAL

- - - -

- - - -

- - - -

- - - -

- - - -

- - - -

0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004

0.004 0.004 0.004 0.004


0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005

0.005 0.005 0.005 0.005


0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001

0.001 0.001 0.001 0.001

3.345 4.345 4.345 5.345 8.188 8.871 8.871 8.875


20.612 24.957 29.302 34.647 42.835 51.706 60.577 69.452
2.186 8.345 8.357 7.899 8.332 8.332 9.445 6.185
25.958 34.303 42.660 50.559 58.891 67.223 76.668 82.853
0.668 3.216 7.926 2.212
45.085 48.301 56.227 58.438
19.126 13.997 13.567 7.879
Diperiksa Oleh,
Konsultan Supervisi
AMA NUSAWIDYA CONSULT

ALU ARIAWAN, ST
Site Engineer
SATKER : PERENCANAAN DAN PENGAWASAN JALAN
PEKERJAAN : 15 (Lima Belas) PENGAWASAN TEKNIK JAL

KONTRAK : KU.03.01/KONT/SNVT P2JN-NTB/113/2013


TANGGGAL 14 FEBRUARI 2013
KONSULTAN : PT. CIRIATAMA NUSAWIDYA CONSUL

29-Jul 31-Jul 5-Aug 12-Aug 16-Aug 19-Aug 26-Aug 31-Aug


20 20a 21 22 22a 23 24 24a
30-Jul 4-Aug 11-Aug 15-Aug 18-Aug 25-Aug 30-Aug 1-Sep

0.001 0.002 0.002 0.001 0.001 0.002 0.002 0.001

0.003 0.008 0.011 0.007 0.005 0.011 0.008 0.003

0.003 0.007 0.009 0.005 0.004 0.009 0.007 0.003


0.562 0.422 0.984

0.841 0.529 0.212

0.027 0.067 0.093

0.538 1.344 1.882

1.158 2.896 4.055

0.013 0.033 0.046

0.022 0.055 0.077


0.006 0.003

0.083 0.033

0.081 0.032

0.012 0.005

0.001 0.003 0.004 0.002 0.002 0.004 0.003 0.001

0.001 0.003 0.005 0.003 0.002 0.005 0.003 0.001

0.000 0.001 0.001 0.000 0.000 0.001 0.001 0.000

2.201 5.503 7.704 3.857 2.893 3.715 2.089 0.836


71.654 77.156 84.860 88.718 91.611 95.326 97.415 98.251
1.767 4.418 6.185 0.580 0.435 1.856 0.735 0.294
84.621 89.039 95.224 95.804 96.239 98.096 98.831 99.125
AN PENGAWASAN JALAN NASIONAL PROV. NTB
ENGAWASAN TEKNIK JALAN KEMPO - KESI - HODO

NVT P2JN-NTB/113/2013

NUSAWIDYA CONSULT
MASA
2-Sep 9-Sep PEME
SKALA KET.
25 26 LIHA
8-Sep 16-Sep RAAN

100.00
0.084

0.002 0.002

0.011 0.011

0.009 0.009

75.00
MASA PEMELIHARAAN 720 (TUJUH RATUS DUA PULUH) HARI KALENDER 0.641

50.00
25.00

0.009

0.077

0.004 0.004

0.005 0.005

0.001 0.001

0.00

1.543 0.206
99.794 100.000 Kontrak Awal
0.682 0.194
99.806 100.000 CCO - 01

Realisasi
Dompu, 30 Juni 2013
Dibuat oleh,
Kpntraktor Pelaksana
PT. DUNIA MAS

Drs. Ec. JONI MUCHTAR


Direktur
SATKER : SATKER PELAKSANAAN JALAN NASIONAL WILAYAH III PROVINSI NTB
PPK : PPK. BATAS KAB. DOMPU - BANGGO - BALIBUNGA - MADAPRAMA
PAKET : PELEBARAN KAWASAN STRATEGIS JALAN KEMPO - KESI - HODO (PPK 08) SEPANJANG 7.90 KM
KONTRAK : KU.02.09/PPK08-WIL3NTB/180/2013
TANGGAL 21 MARET 2013
KONTRAKTOR : PT. DUNIA MAS

MATA QUANTITY
BOBOT 21-Mar
PEMBA URAIAN PEKERJAAN SAT
KONTRAK (%) 1
YARAN CCO.01
ASLI 24-Mar
DIV.1 U M U M
0.070
1.2. Mobilisasi Ls 1.00 1.00 0.281

1.8 Manajemen dan Keselamatan Lalu Lintas Ls 1.00 1.00 0.062


0.008
1.17 Pengamanan Lingkungan Hidup Ls 1.00 1.00 0.217
0.009
1.21 Manajemen Mutu Ls 1.00 1.00 0.229
Sub Total Div. 1 0.789
DIV.2 DRAINASE
2.1 Galian untuk Selokan Drainase dan Saluran Air M3 695.67 6,438.04 1.254

2.2 Pasangan Batu dengan Mortar M3 200.63 653.64 1.493


Sub Total Div. 2 2.748
DIV. 3 PEKERJAAN TANAH
3.1.1a Galian Biasa M3 6,350.40 4,428.26 1.129

3.1.1b Galian Batu Cadas Muda M3 50.00 - -

3.1.2 Galian Batu M3 50.00 - -

3.1.3 Galian Struktur dengan Kedalaman 0 - 2 meter M3 54.00 417.12 0.108

3.1.8 Galian Perkerasan Berbutir M3 25.00 - -

3.2.1 Timbunan Biasa M3 241.50 - -

3.2.2 Timbunan Pilihan M3 2,370.00 5,570.22 4.919

3.3 Penyiapan Badan Jalan M2 17,820.00 13,613.40 0.217


Sub Total Div. 3 6.373
DIV. 4 PELEBARAN PERKERASAN DAN BAHU JALAN
4.2.2 Lapis Pondasi Agregat Klas B M3 2,370.00 1,166.00 2.222
Sub Total Div. 4 2.222
DIV. 5 PERKERASAN BERBUTIR
5.1.1 Lapis Pondasi Agregat Klas A M3 9,480.00 9,435.96 19.809

5.1.2 Lapis Pondasi Agregat Klas B M3 6,824.50 8,390.32 15.650


Sub Total Div. 5 35.459
DIV. 6 PERKERASAN ASPAL
6.1(1)(a) Lapis Resap Pengikat - Aspal Cair Liter 39,421.56 40,263.40 2.019

6.1(2)(a) Lapis Perekat - Aspal Cair Liter 7,157.40 7,105.31 0.374

6.3(5a) Laston Lapis Aus (AC-WC) gradasi halus/kasar Ton 4,007.60 3,947.81 7.527

6.3(6a) Laston Lapis Antara (AC-BC) gradasi halus/kasar Ton 5,832.47 6,002.11 11.020

6.3.8.a Aspal Keras Ton 663.43 600.62 28.382

6.3.9 Aditif Anti Pengelupasan Kg 1,990.30 1,201.24 0.323

6.3.10a Bahan Pengisi (Filler) Tambahan (Semen) Kg 149,848.70 99,499.23 0.541


Sub Total Div. 6 50.186
DIV. 7 STRUKTUR
7.1(7) Beton mutu sedang dengan fc'=20 MPa (K-250) M3 7.02 29.21 0.206

7.3(1) Baja Tulangan BJ 24 Polos Kg 1,123.48 5,989.00 0.458

7.9 Pasangan Batu M3 274.87 424.05 1.001


7.9 Pasangan Batu M3 274.87 424.05 1.001
Sub Total Div. 7 1.665
DIV. 8 PENGEMBALIAN KONDISI DAN PEKERJAAN MINOR
8.1(1) Lapisan Pondasi Agregat Klas A untuk Pekerjaan Minor M3 10.00 - -

8.3(3) Pohon Buah 100.00 100.00 0.018

8.4(1) Marka Jalan Termoplastik M2 2,251.50 - -

8.4(3)(a) Rambu Jalan Tunggal dgn Permukaan Pemantul Engineer Grade Buah 42.00 42.00 0.116

8.4(5) Patok Pengarah Buah 150.00 150.00 0.114

8.4(6)(a) Patok Kilometer Buah 8.00 8.00 0.017

8.4(6)(b) Patok Hektometer Buah 86.00 71.00 0.077


Sub Total Div. 8 0.343
DIV. 10 PEKERJAAN PEMELIHARAAN RUTIN
10.1(2) Pemeliharaan Rutin Bahu Jalan Ls 1.00 1.00 0.088

10.1(3) Pemeliharaan Rutin Selokan, Saluran Air, Galian dan Timbunan Ls 1.00 1.00 0.110

10.1(4) Pemeliharaan Rutin Perlengkapan Jalan Ls 1.00 1.00 0.018


Sub Total Div. 10 0.216
Total 100.000
Kontrak Rencana Kemajuan Pekerjaan (%) 0.087
Awal Rencana Kemajuan Pekerjaan Komulatif (%) 0.087
Rencana Kemajuan Pekerjaan (CCO - 01) (%)
CCO.01
Rencana Kemajuan Pekerjaan Komulatif (CCO - 01) (%)
Realisasi Kemajuan Pekerjaan (%) 0.030
Realisasi
Realisasi Kemajuan Pekerjaan Komulatif (%) 0.030
Deviasi (%) 0.057

Disetujui Oleh ;
PPK 08 Batas Kab. Dompu - Banggo - Balibunga - Madaprama

UJANG SUKMANA, ST, MM, MT.


Nip. 196202251989031005
JADWAL WAKTU PELAKSANAAN

KEMAJUAN PEKERJAAN
25-Mar 1-Apr 8-Apr 15-Apr 22-Apr 29-Apr 6-May 13-May 20-May 27-May 3-Jun 10-Jun 17-Jun
2 3 4 5 6 7 8 9 10 11 12 13 14
31-Mar 7-Apr 14-Apr 21-Apr 28-Apr 5-May 12-May 19-May 26-May 2-Jun 9-Jun 16-Jun 23-Jun

0.070

0.008 0.008 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002

0.008 0.008 0.008 0.008 0.008 0.008 0.011 0.011 0.011 0.011 0.011 0.011 0.011

0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.009

0.045 0.045 0.045

0.103 0.103 0.103 0.103

0.405 0.405 0.405 0.405 0.255

0.024 0.024
RENCANA
0.028 0.028 KONTRAK
0.013 0.013 0.043 0.043

0.015 0.015

0.067

0.983 0.983 0.983

0.095 0.095 0.095

A
D
D 7.335 7.335
E
1.000 1.546 0.730 0.730 0.730 0.730
N
D
U
M
REALISASI
K
O
N
T
R
A
K
(
C
C
0.025 0.025
O 0.078 0.078
0
0.043 0.043 1 0.186 0.186

0.162 0.162 0.162 0.162 ) 0.173 0.173


0.021

0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004

0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005

0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001

0.095 0.484 0.796 0.933 1.910 2.054 2.800 2.641 2.574 2.891 3.345 4.345 4.345
0.182 0.666 1.462 2.395 4.305 6.360 9.160 11.801 14.375 17.266 20.612 24.957 29.302
0.287 0.805 0.805 1.202 2.186 8.345 8.357
20.960 21.765 22.570 23.772 25.958 34.303 42.660
0.142 0.346 1.408 3.647 14.621 0.478 6.709 4.422 7.803 4.810 0.668 3.216 7.926
0.173 0.519 1.927 5.574 20.195 20.673 27.382 31.804 39.607 44.417 45.085 48.301 56.227
-0.010 -0.148 0.465 3.179 15.890 14.314 18.222 20.003 25.231 20.644 19.126 13.997 13.567

Diperiksa Oleh,
Konsultan Supervisi
PT. CIRIATAMA NUSAWIDYA CONSULT

LALU ARIAWAN, ST
Site Engineer
SATKER : PERENCANAAN DAN PENGAWASAN JALAN NASIONAL PROV. NTB
PAKET : 15 (Lima Belas) PENGAWASAN TEKNIK JALAN KEMPO - KESI - HODO

KONTRAK : KU.03.01/KONT/SNVT P2JN-NTB/113/2013


TANGGGAL 14 FEBRUARI 2013
KONSULTAN : PT. CIRIATAMA NUSAWIDYA CONSULT
ERJAAN MASA
24-Jun 1-Jul 8-Jul 15-Jul 22-Jul 29-Jul 5-Aug 12-Aug 19-Aug 26-Aug 2-Sep 9-Sep PEME
15 16 17 18 19 20 21 22 23 24 25 26 LIHA
30-Jun 7-Jul 14-Jul 21-Jul 28-Jul 4-Aug 11-Aug 18-Aug 25-Aug 1-Sep 8-Sep 16-Sep RAAN

0.056 0.084

0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002

0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011

0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.009

0.373 0.373 0.373

0.493 0.493

RENCANA ADDENDUM
KONTRAK (CCO 01)

0.983 0.983

0.841 0.741 0.641


PEMELIHARAAN 720 (TUJUH RATUS DUA PULUH) HARI KALENDER

0.505 0.505 0.505 0.505

0.093 0.093 0.093 0.093

1.882 1.882 1.882 1.882

2.755 2.755 2.755 2.755

4.055 4.055 4.055 4.055 4.055 4.055 4.055

0.046 0.046 0.046 0.046 0.046 0.046 0.046

0.077 0.077 0.077 0.077 0.077 0.077 0.077


PEM
RENCANA KONTRAK
0.009 0.009
AWAL

0.116

0.114

0.017

0.077

0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004

0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005

0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001

5.345 8.188 8.871 8.871 8.875 7.704 7.704 6.750 3.715 2.925 1.543 0.206
34.647 42.835 51.706 60.577 69.452 77.156 84.860 91.611 95.326 98.251 99.794 100.000
7.899 8.332 8.332 9.445 6.185 6.185 6.185 1.016 1.856 1.029 0.682 0.194
50.559 58.891 67.223 76.668 82.853 89.039 95.224 96.239 98.096 99.125 99.806 100.000
2.212
58.438
7.879

Dompu, 30 Juni 2013


Dibuat oleh,
Kpntraktor Pelaksana
PT. DUNIA MAS

Drs. Ec. JONI MUCHTAR


Direktur
OV. NTB
ESI - HODO

SKALA KET.

100.00

75.00

50.00
25.00

0.00

Kontrak Awal

CCO - 01

Realisasi

Juni 2013
ibuat oleh,
aktor Pelaksana
DUNIA MAS

JONI MUCHTAR
Direktur
SATKER : SATKER PELAKSANAAN JALAN NASIONAL WILAYAH III PROVINSI NTB
PPK : PPK. BATAS KAB. DOMPU - BANGGO - BALIBUNGA - MADAPRAMA
PAKET : PELEBARAN KAWASAN STRATEGIS JALAN KEMPO - KESI - HODO (PPK 08) SEPANJAN
KONTRAK : KU.02.09/PPK08-WIL3NTB/180/2013
TANGGAL 21 MARET 2013
KONTRAKTOR : PT. DUNIA MAS
MATA
QUANTITY
PEMBA
URAIAN PEKERJAAN SAT
YARAN KONTRAK
ASLI
DIV.1 U M U M
1.2. Mobilisasi Ls 1.00

1.8 Manajemen dan Keselamatan Lalu Lintas Ls 1.00

1.17 Pengamanan Lingkungan Hidup Ls 1.00

1.21 Manajemen Mutu Ls 1.00


Sub Total Div. 1
DIV.2 DRAINASE
2.1 Galian untuk Selokan Drainase dan Saluran Air M3 695.67

2.1 Pasangan Batu dengan Mortar M3 200.63


Sub Total Div. 2
DIV. 3 PEKERJAAN TANAH
3.1.1a Galian Biasa M3 6,350.40

3.1.1b Galian Batu Cadas Muda M3 50.00

3.1.2 Galian Batu M3 50.00

3.1.3 Galian Struktur dengan Kedalaman 0 - 2 meter M3 54.00

3.1.8 Galian Perkerasan Berbutir M3 25.00

3.2.1 Timbunan Biasa M3 241.50

3.2.2 Timbunan Pilihan M3 2,370.00

3.3 Penyiapan Badan Jalan M2 17,820.00


Sub Total Div. 3
DIV. 4 PELEBARAN PERKERASAN DAN BAHU JALAN
4.2.2 Lapis Pondasi Agregat Klas B M3 2,370.00
Sub Total Div. 4
DIV. 5 PERKERASAN BERBUTIR
5.1.1 Lapis Pondasi Agregat Klas A M3 9,480.00

5.1.2 Lapis Pondasi Agregat Klas B M3 6,824.50


Sub Total Div. 5
DIV. 6 PERKERASAN ASPAL
6.1(1)(a) Lapis Resap Pengikat - Aspal Cair Liter 39,421.56

6.1(2)(a) Lapis Perekat - Aspal Cair Liter 7,157.40

6.3(5a) Laston Lapis Aus (AC-WC) gradasi halus/kasar Ton 4,007.60

6.3(6a) Laston Lapis Antara (AC-BC) gradasi halus/kasar Ton 5,832.47

6.3.8.a Aspal Keras Ton 663.43

6.3.9 Aditif Anti Pengelupasan Kg 1,990.30

6.3.10a Bahan Pengisi (Filler) Tambahan (Semen) Kg 149,848.70


Sub Total Div. 6
DIV. 7 STRUKTUR
7.1(7) Beton mutu sedang dengan fc'=20 MPa (K-250) M3 7.02

7.3(1) Baja Tulangan BJ 24 Polos M3 1,123.48

7.9 Pasangan Batu M3 274.87


Sub Total Div. 7
DIV. 8 PENGEMBALIAN KONDISI DAN PEKERJAAN MINOR
8.1(1) Lapisan Pondasi Agregat Klas A untuk Pekerjaan Minor M3 10.00

8.3(3) Pohon Buah 100.00

8.4(1) Marka Jalan Termoplastik M2 2,251.50

8.4(3)(a) Rambu Jalan Tunggal dgn Permukaan Pemantul Engineer Buah 42.00

8.4(5) Patok Pengarah Buah 150.00

8.4(6)(a) Patok Kilometer Buah 8.00

8.4(6)(b) Patok Hektometer Buah 86.00


Sub Total Div. 8
DIV. 10 PEKERJAAN PEMELIHARAAN RUTIN
10.1(2) Pemeliharaan Rutin Bahu Jalan Ls 1.00

10.1(3) Pemeliharaan Rutin Selokan, Saluran Air, Galian dan Timb Ls 1.00

10.1(4) Pemeliharaan Rutin Perlengkapan Jalan Ls 1.00


Sub Total Div. 10
Total
Kontrak Rencana Kemajuan Pekerjaan (%)
Awal Rencana Kemajuan Pekerjaan Komulatif (%)
Rencana Kemajuan Pekerjaan (CCO - 01) (%)
CCO.01
Rencana Kemajuan Pekerjaan Komulatif (CCO - 01) (%)
Realisasi Kemajuan Pekerjaan (%)
Realisasi
Realisasi Kemajuan Pekerjaan Komulatif (%)
Deviasi (%)
NSI NTB

DO (PPK 08) SEPANJANG 7.90 KM

QUANTITY
BOBOT 21-Mar 25-Mar 1-Apr 8-Apr 15-Apr 22-Apr
(%) 1 2 3 4 5 6
CCO.01
24-Mar 31-Mar 7-Apr 14-Apr 21-Apr 28-Apr

0.070 0.070
1.00 0.281
0.008 0.008 0.002 0.002 0.002
1.00 0.062
0.008 0.008 0.008 0.008 0.008 0.008
1.00 0.217
0.009 0.009 0.009 0.009 0.009 0.009
1.00 0.229
0.789

0.418 0.418 0.418


6,438.04 1.254
0.299 0.299 0.299
653.64 1.493
2.748

0.282 0.282 0.282 0.282


4,428.26 1.129
0.024 0.024
- -
0.028 0.028
- -
0.054
417.12 0.108
0.015
- -

- -

5,570.22

13,613.40
4.919

0.217
0.072 0.072

NL
6.373

O
1,166.00 2.222
2.222
G
N G
9,435.96 19.809

RI
O
1.000
8,390.32 15.650

T
35.459

40,263.40 2.019

NI
O
7,105.31 0.374

M
3,947.81 7.527

6,002.11 11.020

600.62
D
28.382

E
S
1,201.24 0.323

U
99,499.23 0.541
50.186

0.103
29.21 0.206
0.229 0.229
5,989.00 0.458
0.250 0.250 0.250
424.05 1.001
1.665

0.021
- -

100.00 0.018

- -

42.00 0.116

150.00 0.114

8.00 0.017

71.00 0.077
0.343

0.004 0.004 0.004 0.004


1.00 0.088
0.005 0.005 0.005 0.005
1.00 0.110
0.001 0.001 0.001 0.001
1.00 0.018
0.216
100.000
0.087 0.095 0.484 0.796 0.933 1.910
0.087 0.182 0.666 1.462 2.395 4.305

0.030 0.142 0.346 1.408 3.647 14.621


0.030 0.173 0.519 1.927 5.574 20.195
-0.057 -0.010 -0.148 0.465 3.179 15.890
JADWAL WAKTU PELAKSANAAN

KEMAJU
29-Apr 1-May 6-May 13-May 16-May 20-May 27-May 31-May 3-Jun
6a 7 8 9 9a 10 11 11a 12
30-Apr 5-May 12-May 15-May 19-May 26-May 30-May 2-Jun 9-Jun

0.001 0.001 0.002 0.001 0.001 0.002 0.001 0.001 0.002

0.002 0.006 0.011 0.005 0.007 0.011 0.007 0.005 0.011

0.003 0.006 0.009 0.004 0.005 0.009 0.005 0.004 0.009

0.085 0.213

0.255

0.015 0.038 0.019 0.025 0.043

0.004 0.011

Y
0.019 0.048 - - -

L
0.983
A

N
0.021 0.052D

O
D

G
E
N O
D
U M
G
E
N O
D
U M
M

E D
S
0.609 1.521 0.313 0.417 0.730 0.417 0.313 0.730
K
O
N
T
U
R
A REALISASI
K
(
C
C
O
0
1
)
0.029 0.074 0.045 0.034 0.078

0.106 0.080 0.186

0.072 0.179 0.099 0.074 0.173

0.001 0.003 0.004 0.002 0.002 0.004 0.002 0.002 0.004

0.001 0.003 0.005 0.002 0.003 0.005 0.003 0.002 0.005

0.000 0.001 0.001 0.000 0.000 0.001 0.000 0.000 0.001


0.587 1.467 2.800 1.132 1.509 2.574 1.652 1.239 3.345
4.892 6.360 9.160 10.292 11.801 14.375 16.027 17.266 20.612
0.287 0.345 0.460 0.805 0.687 0.515 2.186
20.960 21.305 21.765 22.570 23.257 23.772 25.958
0.040 0.438 6.709 1.871 2.551 7.803 4.802 0.009 0.668
20.235 20.673 27.382 29.253 31.804 39.607 44.408 44.417 45.085
15.343 14.314 18.222 18.961 20.003 25.231 21.151 20.644 19.126
ANAAN

KEMAJUAN PEKERJAAN
10-Jun 17-Jun 24-Jun 1-Jul 8-Jul 15-Jul 22-Jul 29-Jul 31-Jul
13 14 15 16 17 18 19 20 20a
16-Jun 23-Jun 30-Jun 7-Jul 14-Jul 21-Jul 28-Jul 30-Jul 4-Aug

0.056

0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.001 0.002

0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.003 0.008

0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.003 0.007

0.373 0.373 0.373

0.493 0.493

LY
N
RENCANA ADDENDUM
KONTRAK (CCO 01) O
N G
R I
0.983

TO
0.983

NI
O
M
O
M
D 7.335 7.335

0.505 0.505 0.505 0.505

0.093 0.093 0.027 0.067

1.882 1.882 0.538 1.344

2.755 2.755 2.755 2.755

4.055 4.055 4.055 4.055 4.055 1.158 2.896

0.046 0.046 0.046 0.046 0.046 0.013 0.033

0.077 0.077 0.077 0.077 0.077 0.022 0.055

RENCANA KONTRAK
AWAL

0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.001 0.003

0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.001 0.003

0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.000 0.001


4.345 4.345 5.345 8.188 8.871 8.871 8.875 2.201 5.503
24.957 29.302 34.647 42.835 51.706 60.577 69.452 71.654 77.156
8.345 8.357 7.899 8.332 8.332 9.445 6.185 1.767 4.418
34.303 42.660 50.559 58.891 67.223 76.668 82.853 84.621 89.039
3.216 7.926 2.212
48.301 56.227 58.438
13.997 13.567 7.879
SATKER : PERENCANAAN DAN PENGAWASAN JALAN NASIONAL PROV. NTB
PEKERJAAN : 15 (Lima Belas) PENGAWASAN TEKNIK JALAN KEMPO - KESI - HODO

KONTRAK : KU.03.01/KONT/SNVT P2JN-NTB/113/2013


TANGGGAL 14 FEBRUARI 2013
KONSULTAN : PT. CIRIATAMA NUSAWIDYA CONSULT
MASA
5-Aug 12-Aug 16-Aug 19-Aug 26-Aug 31-Aug 2-Sep 9-Sep PEME
21 22 22a 23 24 24a 25 26 LIHA
11-Aug 15-Aug 18-Aug 25-Aug 30-Aug 1-Sep 8-Sep 16-Sep RAAN

0.084

0.002 0.001 0.001 0.002 0.002 0.001 0.002 0.002

0.011 0.007 0.005 0.011 0.008 0.003 0.011 0.011

0.009 0.005 0.004 0.009 0.007 0.003 0.009 0.009

0.562 0.421 0.983

0.841 0.529 0.212 0.641


R
MASA PEMELIHARAAN 720 (TUJUH RATUS DUA PULUH) HARI KALENDER
0.093

1.882

4.055

0.046

0.077

0.006 0.003 0.009

0.083 0.033

0.081 0.032

0.012 0.005

0.077

0.004 0.002 0.002 0.004 0.003 0.001 0.004 0.004

0.005 0.003 0.002 0.005 0.003 0.001 0.005 0.005

0.001 0.000 0.000 0.001 0.001 0.000 0.001 0.001


7.704 3.857 2.893 3.715 2.089 0.836 1.543 0.206
84.860 88.718 91.611 95.326 97.415 98.251 99.794 100.000
6.185 0.580 0.435 1.856 0.735 0.294 0.682 0.194
95.224 95.804 96.239 98.096 98.831 99.125 99.806 100.000

Dompu, 30 Juni 2013


Dimonitor oleh :
PT. CIRIATAMA NUSAWIDYA CO

LALU ARIAWAN, ST
Site Engineer
ROV. NTB
KESI - HODO

SKALA KET.

100.00

75.00
50.00

25.00
0.00

Kontrak Awal

CCO - 01

Realisasi

Juni 2013
itor oleh :
USAWIDYA CONSULT

IAWAN, ST
Engineer
LAPORAN MINGGUAN
SNVT : SATKER PELAKSANAAN JALAN NASIONAL WILAYAH III PROVINSI NTB
PPK : PPK. BATAS KAB. DOMPU - BANGGO - BALIBUNGA - MADAPRAMA
PAKET : PELEBARAN KAWASAN STRATEGIS JALAN KEMPO - KESI - HODO (PPK 08)
SEPANJANG 7.90 KM
KONTRAK : KU.02.09/PPK08-WIL3NTB/180/2013
TANGGAL 21 MARET 2013
KONTRAKTOR : PT. DUNIA MAS
KONSULTAN : PT. CIRIATAMA NUSAWIDYA CONSULT

MATA QUANTITY
PEMBA URAIAN PEKERJAAN SAT KONTRAK
YARAN ASLI

DIV.1 UMUM
1.2. Mobilisasi Ls 1.00
1.8 Manajemen dan Keselamatan Lalu Lintas Ls 1.00
1.17 Pengamanan Lingkungan Hidup Ls 1.00
1.21 Manajemen Mutu Ls 1.00
Sub Total Div. 1

DIV. 2 DRAINASE
2.1 Galian untuk Selokan Drainase dan Saluran Air M3 695.67
2.2 Pasangan Batu dengan Mortar M3 200.63
Sub Total Div. 2

DIV. 3 PEKERJAAN TANAH


3.1.1a Galian Biasa M3 6,350.40
3.1.1b Galian Batu Cadas Muda M3 50.00
3.1.2 Galian Batu M3 50.00
3.1.3 Galian Struktur dengan Kedalaman 0 - 2 meter M3 54.00
3.1.8 Galian Perkerasan Berbutir M3 25.00
3.2.1 Timbunan Biasa M3 241.50
3.2.2 Timbunan Pilihan M3 2,370.00
3.3 Penyiapan Badan Jalan M2 17,820.00
Sub Total Div. 3

DIV. 4 PELEBARAN PERKERASAN DAN BAHU JALAN


4.2.2 Lapis Pondasi Agregat Klas B M3 2,370.00
Sub Total Div. 4

DIV. 5 PERKERASAN BERBUTIR


5.1.1 Lapis Pondasi Agregat Klas A M3 9,480.00
5.1.2 Lapis Pondasi Agregat Klas B M3 6,824.50
Sub Total Div. 5

DIV. 6 PERKERASAN ASPAL


6.1(1)(a) Lapis Resap Pengikat - Aspal Cair Liter 39,421.56
6.1(2)(a) Lapis Perekat - Aspal Cair Liter 7,157.40
6.3(5a) Laston Lapis Aus (AC-WC) gradasi halus/kasar Ton 4,007.60
6.3(6a) Laston Lapis Antara (AC-BC) gradasi halus/kasar Ton 5,832.47
6.3.8.a Aspal Keras Ton 663.43
6.3.9 Aditif Anti Pengelupasan Kg 1,990.30
6.3.10a Bahan Pengisi (Filler) Tambahan (Semen) Kg 149,848.70
Sub Total Div. 6

DIV. 7 STRUKTUR
7.1(7) Beton mutu sedang dengan fc'=20 MPa (K-250) M3 7.02
7.3(1) Baja Tulangan BJ 24 Polos Kg 1,123.48
7.9 Pasangan Batu M3 274.87
Sub Total Div. 7

DIV. 8 PENGEMBALIAN KONDISI DAN PEKERJAAN MINOR


8.1(1) Lapisan Pondasi Agregat Klas A untuk Pekerjaan Minor M3 10.00
8.3(3) Pohon Buah 100.00
8.4(1) Marka Jalan Termoplastik M2 2,251.50
8.4(3)(a) Rambu Jalan Tunggal dgn Permukaan Pemantul Engineer Grade Buah 42.00
8.4(5) Patok Pengarah Buah 150.00
8.4(6)(a) Patok Kilometer Buah 8.00
8.4(6)(b) Patok Hektometer Buah 86.00
Sub Total Div. 8

DIV. 10 PEKERJAAN PEMELIHARAAN RUTIN


10.1(2) Pemeliharaan Rutin Bahu Jalan Ls 1.00
10.1(3) Pemeliharaan Rutin Selokan, Saluran Air, Galian dan Timbunan Ls 1.00
10.1(4) Pemeliharaan Rutin Perlengkapan Jalan Ls 1.00
Sub Total Div. 8
Total
PORAN MINGGUAN

QUANTITY
HARGA SATUAN TOTAL HARGA
CCO.01

67,780,000.00 67,780,000.00
15,000,000.00 15,000,000.00
52,375,000.00 52,375,000.00
55,300,000.00 55,300,000.00

47,046.67 32,728,956.92
619,156.11 124,221,290.35

61,573.88 391,018,767.55
236,267.83 11,813,391.50
268,671.82 13,433,591.00
118,221.28 6,383,949.12
293,150.43 7,328,760.75
201,804.17 48,735,707.06
213,217.57 505,325,640.90
3,856.82 68,728,532.40

460,183.46 1,090,634,800.20

506,915.30 4,805,557,044.00
450,377.62 3,073,602,067.69

12,109.93 477,392,332.09
12,699.51 90,895,472.87
460,403.98 1,845,114,990.25
443,343.89 2,585,789,938.11
11,410,000.00 7,569,736,300.00
65,000.00 129,369,500.00
1,312.00 196,601,494.40
1,702,494.96 11,951,514.62
18,448.87 20,726,936.47
570,174.35 156,723,823.58

504,696.03 5,046,960.30
43,865.83 4,386,583.00
243,482.22 548,200,218.33
665,444.95 27,948,687.90
183,052.46 27,457,869.00
527,551.83 4,220,414.64
263,360.54 22,649,006.44

21,168,620.65 21,168,620.65
26,539,909.61 26,539,909.61
4,414,175.94 4,414,175.94

24,146,302,247.64
MATA URAIAN PEKERJAAN SAT QUANTITY
PEMBA KONTRAK ASLI
YARAN

DIV.1 S
1.2. Mobilisasi Ls 1
1.8 Manajemen dan Keselamatan Lalu Lintas Ls 1
1.17 Pengamanan Lingkungan Hidup Ls 1
1.21 Manajemen Mutu Ls 1
Sub Total Div. 1

DIV. 2 DRAINASE
2.1 Galian untuk Selokan Drainase dan Saluran Air M3 696
2.2 Pasangan Batu dengan Mortar M3 201
Sub Total Div. 2

DIV. 3 PEKERJAAN TANAH


3.1.1a Galian Biasa M3 6,350
3.1.1b Galian Batu Cadas Muda M3 50
3.1.2 Galian Batu M3 50
3.1.3 Galian Struktur dengan Kedalaman 0 - 2 meter M3 54
3.1.8 Galian Perkerasan Berbutir M3 25
3.2.1 Timbunan Biasa M3 242
3.2.2 Timbunan Pilihan M3 2,370
3.3 Penyiapan Badan Jalan M2 17,820
Sub Total Div. 3

DIV. 4 PELEBARAN PERKERASAN DAN BAHU JALAN


4.2.2 Lapis Pondasi Agregat Klas B M3 2,370
Sub Total Div. 4

DIV. 5 PERKERASAN BERBUTIR


5.1.1 Lapis Pondasi Agregat Klas A M3 9,480
5.1.2 Lapis Pondasi Agregat Klas B M3 6,825
Sub Total Div. 5

DIV. 6 PERKERASAN ASPAL


6.1(1)(a) Lapis Resap Pengikat - Aspal Cair Liter 39,422
6.1(2)(a) Lapis Perekat - Aspal Cair Liter 7,157
6.3(5a) Laston Lapis Aus (AC-WC) gradasi halus/kasar Ton 4,008
6.3(6a) Laston Lapis Antara (AC-BC) gradasi halus/kasar Ton 5,832
6.3.8.a Aspal Keras Ton 663
6.3.9 Aditif Anti Pengelupasan Kg 1,990
6.3.10a Bahan Pengisi (Filler) Tambahan (Semen) Kg 149,849
Sub Total Div. 6

DIV. 7 STRUKTUR
7.1(7) Beton mutu sedang dengan fc'=20 MPa (K-250) M3 7
7.3(1) Baja Tulangan BJ 24 Polos Kg 1,123
7.9 Pasangan Batu M3 275
Sub Total Div. 7
DIV. 8 PENGEMBALIAN KONDISI DAN PEKERJAAN MINOR
8.1(1) Lapisan Pondasi Agregat Klas A untuk Pekerjaan Minor M3 10
8.3(3) Pohon Buah 100
8.4(1) Marka Jalan Termoplastik M2 2,252
8.4(3)(a) Rambu Jalan Tunggal dgn Permukaan Pemantul Engineer GBuah 42
8.4(5) Patok Pengarah Buah 150
8.4(6)(a) Patok Kilometer Buah 8
8.4(6)(b) Patok Hektometer Buah 86
Sub Total Div. 8

DIV. 10 PEKERJAAN PEMELIHARAAN RUTIN


10.1(2) Pemeliharaan Rutin Bahu Jalan Ls 1
10.1(3) Pemeliharaan Rutin Selokan, Saluran Air, Galian dan Timbu Ls 1
10.1(4) Pemeliharaan Rutin Perlengkapan Jalan Ls 1
Sub Total Div. 8
Total
VOLUME SEGMEN 1 HARGA SATUAN TOTAL HARGA TOTAL HARGA SEGMEN 1

0.258 67,780,000 67,780,000 17,502,683.544


0.258 15,000,000 15,000,000 3,873,417.722
0.258 52,375,000 52,375,000 13,524,683.544
0.258 55,300,000 55,300,000 14,280,000.000
-
-
-
179.641 47,047 32,728,957 8,451,528.116
51.808 619,156 124,221,290 32,077,396.495
-
-
-
1639.850 61,574 391,018,768 100,971,934.912
12.911 236,268 11,813,392 3,050,546.666
12.911 268,672 13,433,591 3,468,927.296
13.944 118,221 6,383,949 1,648,513.444
6.456 293,150 7,328,761 1,892,490.118
62.362 201,804 48,735,707 12,584,916.759
612.000 213,218 505,325,641 130,489,152.840
4601.620 3,857 68,728,532 17,747,621.025
-
-
-
612.000 460,183 1,090,634,800 281,632,277.520
-
-
-
2448.000 506,915 4,805,557,044 1,240,928,654.400
1762.276 450,378 3,073,602,068 793,689,647.859
-
-
-
10179.745 12,110 477,392,332 123,275,994.616
1848.240 12,700 90,895,473 23,471,742.362
1034.874 460,404 1,845,114,990 476,460,073.431
1506.106 443,344 2,585,789,938 667,722,971.360
171.316 11,410,000 7,569,736,300 1,954,716,715.443
513.951 65,000 129,369,500 33,406,807.595
38695.107 1,312 196,601,494 50,767,980.832
-
-
-
1.813 1,702,495 11,951,515 3,086,213.902
290.114 18,449 20,726,936 5,352,272.202
70.979 570,174 156,723,824 40,470,455.710
-
-
-
2.582 504,696 5,046,960 1,303,265.698
25.823 43,866 4,386,583 1,132,737.889
581.400 243,482 548,200,218 141,560,562.708
10.846 665,445 27,948,688 7,217,129.534
38.734 183,052 27,457,869 7,090,386.425
2.066 527,552 4,220,415 1,089,828.591
22.208 263,361 22,649,006 5,848,604.195
-
-
-
0.258 21,168,621 21,168,621 5,466,327.358
0.258 26,539,910 26,539,910 6,853,343.747
0.258 4,414,176 4,414,176 1,139,863.154

24,146,302,248 6,235,247,669.010
LAPORAN BULAN
SNVT : SATKER PELAKSANAAN JALAN NASIONAL WILAYAH III PROVINSI NTB
PPK : PPK. BATAS KAB. DOMPU - BANGGO - BALIBUNGA - MADAPRAMA
PAKET : PELEBARAN KAWASAN STRATEGIS JALAN KEMPO - KESI - HODO (PPK 08)
SEPANJANG 7.90 KM
KONTRAK : KU.02.09/PPK08-WIL3NTB/180/2013
TANGGAL 21 MARET 2013
KONTRAKTOR : PT. DUNIA MAS
KONSULTAN : PT. CIRIATAMA NUSAWIDYA CONSULT

MATA QUANTITY
PEMBA URAIAN PEKERJAAN SAT KONTRAK
CCO.01
YARAN ASLI

DIV.1 UMUM
1.2. Mobilisasi Ls 1.00 1.00
1.8 Manajemen dan Keselamatan Lalu Lintas Ls 1.00 1.00
1.17 Pengamanan Lingkungan Hidup Ls 1.00 1.00
1.21 Manajemen Mutu Ls 1.00 1.00
Sub Total Div. 1

DIV. 2 DRAINASE
2.1 Galian untuk Selokan Drainase dan Saluran Air M3 695.67 6,438.04
2.2 Pasangan Batu dengan Mortar M3 200.63 653.64
Sub Total Div. 2

DIV. 3 PEKERJAAN TANAH


3.1.1a Galian Biasa M3 6,350.40 4,428.26
3.1.1b Galian Batu Cadas Muda M3 50.00 -
3.1.2 Galian Batu M3 50.00 -
3.1.3 Galian Struktur dengan Kedalaman 0 - 2 meter M3 54.00 417.12
3.1.8 Galian Perkerasan Berbutir M3 25.00 -
3.2.1 Timbunan Biasa M3 241.50 -
3.2.2 Timbunan Pilihan M3 2,370.00 5,570.22
3.3 Penyiapan Badan Jalan M2 17,820.00 13,613.40
Sub Total Div. 3

DIV. 4 PELEBARAN PERKERASAN DAN BAHU JALAN


4.2.2 Lapis Pondasi Agregat Klas B M3 2,370.00 1,166.00
Sub Total Div. 4

DIV. 5 PERKERASAN BERBUTIR


5.1.1 Lapis Pondasi Agregat Klas A M3 9,480.00 9,435.96
5.1.2 Lapis Pondasi Agregat Klas B M3 6,824.50 8,390.32
Sub Total Div. 5

DIV. 6 PERKERASAN ASPAL


6.1(1)(a) Lapis Resap Pengikat - Aspal Cair Liter 39,421.56 40,263.40
6.1(2)(a) Lapis Perekat - Aspal Cair Liter 7,157.40 7,105.31
6.3(5a) Laston Lapis Aus (AC-WC) gradasi halus/kasar Ton 4,007.60 3,947.81
6.3(6a) Laston Lapis Antara (AC-BC) gradasi halus/kasar Ton 5,832.47 6,002.11
6.3.8.a Aspal Keras Ton 663.43 600.62
6.3.9 Aditif Anti Pengelupasan Kg 1,990.30 1,201.24
6.3.10a Bahan Pengisi (Filler) Tambahan (Semen) Kg 149,848.70 99,499.23
Sub Total Div. 6

DIV. 7 STRUKTUR
7.1(7) Beton mutu sedang dengan fc'=20 MPa (K-250) M3 7.02 29.21
7.3(1) Baja Tulangan BJ 24 Polos Kg 1,123.48 5,989.00
7.9 Pasangan Batu M3 274.87 424.05
Sub Total Div. 7

DIV. 8 PENGEMBALIAN KONDISI DAN PEKERJAAN MINOR


8.1(1) Lapisan Pondasi Agregat Klas A untuk Pekerjaan Minor M3 10.00 -
8.3(3) Pohon Buah 100.00 100.00
8.4(1) Marka Jalan Termoplastik M2 2,251.50 -
8.4(3)(a) Rambu Jalan Tunggal dgn Permukaan Pemantul Engineer Grade Buah 42.00 42.00
8.4(5) Patok Pengarah Buah 150.00 150.00
8.4(6)(a) Patok Kilometer Buah 8.00 8.00
8.4(6)(b) Patok Hektometer Buah 86.00 71.00
Sub Total Div. 8

DIV. 10 PEKERJAAN PEMELIHARAAN RUTIN


10.1(2) Pemeliharaan Rutin Bahu Jalan Ls 1.00 1.00
10.1(3) Pemeliharaan Rutin Selokan, Saluran Air, Galian dan Timbunan Ls 1.00 1.00
10.1(4) Pemeliharaan Rutin Perlengkapan Jalan Ls 1.00 1.00
Sub Total Div. 8
Total

Disetujui oleh : Diperiks


Satuan Kerja Pelaksanaan Jalan Nasional Wilayah III Prov. NTB Konsultan
PPK 08 Batas Kab. Dompu-Banggo-Balibunga-Madaprama PT. CIRIATAMA NUS

UJANG SUKMANA, ST.MM. MT. LALU ARI


Nip. 19620225 198903 1 005 Site En
LAPORAN BULAN
SNVT : SATKER PELAKSANAAN JALAN NASIONAL WILAYAH III PROVINSI NTB
PPK : PPK. BATAS KAB. DOMPU - BANGGO - BALIBUNGA - MADAPRAMA
PAKET : PELEBARAN KAWASAN STRATEGIS JALAN KEMPO - KESI - HODO (PPK 08)
SEPANJANG 7.90 KM
KONTRAK : KU.02.09/PPK08-WIL3NTB/180/2013
TANGGAL 21 MARET 2013
KONTRAKTOR : PT. DUNIA MAS
KONSULTAN : PT. CIRIATAMA NUSAWIDYA CONSULT

MATA QUANTITY
PEMBA URAIAN PEKERJAAN SAT KONTRAK
CCO.01
YARAN ASLI

DIV.1 UMUM
1.2. Mobilisasi Ls 1.00 1.00
1.8 Manajemen dan Keselamatan Lalu Lintas Ls 1.00 1.00
1.17 Pengamanan Lingkungan Hidup Ls 1.00 1.00
1.21 Manajemen Mutu Ls 1.00 1.00
Sub Total Div. 1

DIV. 2 DRAINASE
2.1 Galian untuk Selokan Drainase dan Saluran Air M3 695.67 6,438.04
2.2 Pasangan Batu dengan Mortar M3 200.63 200.63
2.2 Pasangan Batu dengan Mortar M3 - 453.01
Sub Total Div. 2

DIV. 3 PEKERJAAN TANAH


3.1.1a Galian Biasa M3 6,350.40 4,428.26
3.1.1b Galian Batu Cadas Muda M3 50.00 -
3.1.2 Galian Batu M3 50.00 -
3.1.3 Galian Struktur dengan Kedalaman 0 - 2 meter M3 54.00 54.00
3.1.3 Galian Struktur dengan Kedalaman 0 - 2 meter M3 363.12
3.1.8 Galian Perkerasan Berbutir M3 25.00 -
3.2.1 Timbunan Biasa M3 241.50 -
3.2.2 Timbunan Pilihan M3 2,370.00 5,570.22
3.3 Penyiapan Badan Jalan M2 17,820.00 13,613.40
Sub Total Div. 3

DIV. 4 PELEBARAN PERKERASAN DAN BAHU JALAN


4.2.2 Lapis Pondasi Agregat Klas B M3 2,370.00 1,166.00
Sub Total Div. 4

DIV. 5 PERKERASAN BERBUTIR


5.1.1 Lapis Pondasi Agregat Klas A M3 9,480.00 9,435.96
5.1.2 Lapis Pondasi Agregat Klas B M3 6,824.50 8,390.32
Sub Total Div. 5

DIV. 6 PERKERASAN ASPAL


6.1(1)(a) Lapis Resap Pengikat - Aspal Cair Liter 39,421.56 40,263.40
6.1(2)(a) Lapis Perekat - Aspal Cair Liter 7,157.40 7,105.31
6.3(5a) Laston Lapis Aus (AC-WC) gradasi halus/kasar Ton 4,007.60 3,947.81
6.3(6a) Laston Lapis Antara (AC-BC) gradasi halus/kasar Ton 5,832.47 6,002.11
6.3.8.a Aspal Keras Ton 663.43 600.62
6.3.9 Aditif Anti Pengelupasan Kg 1,990.30 1,201.24
6.3.10a Bahan Pengisi (Filler) Tambahan (Semen) Kg 149,848.70 99,499.23
Sub Total Div. 6

DIV. 7 STRUKTUR
7.1(7) Beton mutu sedang dengan fc'=20 MPa (K-250) M3 7.02 29.21
7.3(1) Baja Tulangan BJ 24 Polos Kg 1,123.48 5,989.00
7.9 Pasangan Batu M3 274.87 424.05
Sub Total Div. 7

DIV. 8 PENGEMBALIAN KONDISI DAN PEKERJAAN MINOR


8.1(1) Lapisan Pondasi Agregat Klas A untuk Pekerjaan Minor M3 10.00 -
8.3(3) Pohon Buah 100.00 100.00
8.4(1) Marka Jalan Termoplastik M2 2,251.50 -
8.4(3)(a) Rambu Jalan Tunggal dgn Permukaan Pemantul Engineer Grade Buah 42.00 42.00
8.4(5) Patok Pengarah Buah 150.00 150.00
8.4(6)(a) Patok Kilometer Buah 8.00 8.00
8.4(6)(b) Patok Hektometer Buah 86.00 71.00
Sub Total Div. 8

DIV. 10 PEKERJAAN PEMELIHARAAN RUTIN


10.1(2) Pemeliharaan Rutin Bahu Jalan Ls 1.00 1.00
10.1(3) Pemeliharaan Rutin Selokan, Saluran Air, Galian dan Timbunan Ls 1.00 1.00
10.1(4) Pemeliharaan Rutin Perlengkapan Jalan Ls 1.00 1.00
Sub Total Div. 8
Total

Disetujui oleh : Diperiks


Satuan Kerja Pelaksanaan Jalan Nasional Wilayah III Prov. NTB Konsultan
PPK 08 Batas Kab. Dompu-Banggo-Balibunga-Madaprama PT. CIRIATAMA NUS

UJANG SUKMANA, ST.MM. MT. LALU ARI


Nip. 19620225 198903 1 005 Site En
ORAN BULANAN
BULAN KE 1 (Pertama)

21 Maret 2013 30 April 2013

KEMAJUAN QUANTITY BOBOT TERHADAP KONTRAK BOBOT


BOBOT BULAN BULAN S/D BULAN BULAN BULAN S/D BULAN TERHADAP
(%)
LALU INI INI LALU INI INI ITEM PEK.

0.281 - 0.50 0.50 - 0.140 0.140 50.00


0.062 0.24 0.23 - 0.015 0.015 24.18
0.217 - - - - - -
0.229 0.21 0.20 - 0.048 0.048 21.14
0.789 - 0.204 0.204

0.136 695.67 677.05 - 0.136 0.136 100.00


0.514 200.63 190.35 - 0.514 0.514 100.00
0.650 - 0.650 0.650

1.619 2,081.25 2,081.25 - 0.531 0.531 32.77


0.049 - - - - - -
0.056 - - - - - -
0.026 54.00 45.15 - 0.026 0.026 100.00
0.030 - - - - - -
0.202 - - - - - -
2.093 - - - - - -
0.285 8,325.00 8,325.00 - 0.133 0.133 46.72
4.360 - 0.690 0.690

`
4.517 - - - - - -
4.517 - - -

19.902 2,448.00 2,448.00 - 5.139 5.139 25.82


12.729 6,824.50 6,824.50 - 12.729 12.729 100.00
32.631 - 17.868 17.868

1.977 - - - - - -
0.376 - - - - - -
7.641 - - - - - -
10.709 - - - - - -
31.349 - - - - - -
0.536 - - - - - -
0.814 - - - - - -
53.403 - - -

0.049 7.02 7.02 - 0.049 0.049 100.00


0.086 1,123.48 1,123.48 - 0.086 0.086 100.00
0.649 274.87 274.87 - 0.649 0.649 100.00
0.784 - 0.784 0.784

0.021 - - - - - -
0.018 - - - - - -
2.270 - - - - - -
0.116 - - - - - -
0.114 - - - - - -
0.017 - - - - - -
0.094 - - - - - -
2.650 - - -

0.088 0.18 0.17 - 0.016 0.016 17.86


0.110 0.18 0.17 - 0.020 0.020 17.86
0.018 0.18 0.17 - 0.003 0.003 17.86
0.216 - 0.039 0.039
100.00 - 20.235 20.235
Kemajuan Pekerjaan Bulan Lalu : - (%)
Kemajuan Pekerjaan Bulan Ini : 20.235 (%)
Kemajuan Pekerjaan s/d Bulan Ini : 20.235 (%)
Rencana Kemajuan Pekerjaan s/d Bulan ini : 4.892 (%)
Deviasi : 15.343 (%)

Dompu, 30 April 2013


Diperiksa oleh : Dibuat oleh :
Konsultan Supervisi Kontraktor Pelaksana
PT. CIRIATAMA NUSAWIDYA CONSULT PT. DUNIA MAS

LALU ARIAWAN, ST ZAINAL FADLI NURAN, ST


Site Engineer General Superintendent
ORAN BULANAN
BULAN KE 2 (Dua)

01 Mei 2013 31 Mei 2013

KEMAJUAN QUANTITY BOBOT TERHADAP KONTRAK BOBOT


BOBOT BULAN BULAN S/D BULAN BULAN BULAN S/D BULAN TERHADAP
(%)
LALU INI INI LALU INI INI ITEM PEK.

0.281 0.50 0.20 0.70 0.140 0.056 0.196 70.00


0.062 0.23 0.18 0.41 0.014 0.011 0.025 40.66
0.217 - - - - - - -
0.229 0.20 0.18 0.38 0.046 0.042 0.088 38.29
0.789 0.200 0.109 0.309

1.254 677.05 33.02 710.07 0.132 0.006 0.138 11.03


0.514 190.35 10.28 200.63 0.488 0.026 0.514 100.00
0.979 - 453.01 453.01 - 0.979 0.979 100.00
2.748 0.620 1.012 1.632

1.129 2,081.25 2,067.01 4,148.26 0.531 0.527 1.058 93.68


-
-
0.026 45.15 8.85 54.00 0.022 0.004 0.026 100.00
0.081 - 363.12 363.12 - 0.081 0.081 100.00
-
-
4.919 - - - - - - -
0.217 8,325.00 5,288.40 13,613.40 0.133 0.084 0.217 100.00
6.373 0.686 0.697 1.383

2.222 - - - - - - -
2.222 - - -

19.809 2,448.00 5,465.82 7,913.82 5.139 11.475 16.614 83.87


15.650 6,824.50 1,565.82 8,390.32 12.729 2.921 15.650 100.00
35.459 17.868 14.395 32.264

2.019 - 10,396.78 10,396.78 - 0.521 0.521 25.82


0.374 - - - - - - -
7.527 - - - - - - -
11.020 - 1,550.66 1,550.66 - 2.847 2.847 25.84
28.382 - 89.41 89.41 - 4.225 4.225 14.89
0.323 - 178.82 178.82 - 0.048 0.048 14.89
0.541 - 15,506.58 15,506.58 - 0.084 0.084 15.58
50.186 - 7.726 7.726

0.206 7.02 4.14 11.16 0.049 0.029 0.079 38.21


0.458 1,123.48 127.18 1,250.66 0.086 0.010 0.096 20.88
1.001 274.87 82.30 357.17 0.649 0.194 0.843 84.23
1.665 0.784 0.233 1.018

-
0.018 - - - - - - -
-
0.116 - - - - - - -
0.114 - - - - - - -
0.017 - - - - - - -
0.077 - - - - - - -
0.343 - - -

0.088 0.17 0.19 0.36 0.015 0.017 0.031 35.71


0.110 0.17 0.19 0.36 0.018 0.021 0.039 35.71
0.018 0.17 0.19 0.36 0.003 0.003 0.007 35.71
0.216 0.036 0.041 0.077
100.00 20.195 24.213 44.408
Kemajuan Pekerjaan Bulan Lalu : 20.195 (%)
Kemajuan Pekerjaan Bulan Ini : 24.213 (%)
Kemajuan Pekerjaan s/d Bulan Ini : 44.408 (%)
Rencana Kemajuan Pekerjaan s/d Bulan ini : 23.257 (%)
Deviasi : 21.151 (%)

Dompu, 31 Mei 2013


Diperiksa oleh : Dibuat oleh :
Konsultan Supervisi Kontraktor Pelaksana
PT. CIRIATAMA NUSAWIDYA CONSULT PT. DUNIA MAS

LALU ARIAWAN, ST ZAINAL FADLI NURAN, ST


Site Engineer General Superintendent
LAPORAN BULAN
SNVT : SATKER PELAKSANAAN JALAN NASIONAL WILAYAH III PROVINSI NTB
PPK : PPK. BATAS KAB. DOMPU - BANGGO - BALIBUNGA - MADAPRAMA
PAKET : PELEBARAN KAWASAN STRATEGIS JALAN KEMPO - KESI - HODO (PPK 08)
SEPANJANG 7.90 KM
KONTRAK : KU.02.09/PPK08-WIL3NTB/180/2013
TANGGAL 21 MARET 2013
KONTRAKTOR : PT. DUNIA MAS
KONSULTAN : PT. CIRIATAMA NUSAWIDYA CONSULT

MATA QUANTITY
PEMBA URAIAN PEKERJAAN SAT KONTRAK
CCO.01
YARAN ASLI

DIV.1 UMUM
1.2. Mobilisasi Ls 1.00 1.00
1.8 Manajemen dan Keselamatan Lalu Lintas Ls 1.00 1.00
1.17 Pengamanan Lingkungan Hidup Ls 1.00 1.00
1.21 Manajemen Mutu Ls 1.00 1.00
Sub Total Div. 1

DIV. 2 DRAINASE
2.1 Galian untuk Selokan Drainase dan Saluran Air M3 695.67 6,438.04
2.2 Pasangan Batu dengan Mortar M3 200.63 200.63
2.2 Pasangan Batu dengan Mortar M3 - 453.01
Sub Total Div. 2

DIV. 3 PEKERJAAN TANAH


3.1.1a Galian Biasa M3 6,350.40 4,428.26
3.1.1b Galian Batu Cadas Muda M3 50.00 -
3.1.2 Galian Batu M3 50.00 -
3.1.3 Galian Struktur dengan Kedalaman 0 - 2 meter M3 54.00 54.00
3.1.3 Galian Struktur dengan Kedalaman 0 - 2 meter M3 363.12
3.1.8 Galian Perkerasan Berbutir M3 25.00 -
3.2.1 Timbunan Biasa M3 241.50 -
3.2.2 Timbunan Pilihan M3 2,370.00 5,570.22
3.3 Penyiapan Badan Jalan M2 17,820.00 13,613.40
Sub Total Div. 3

DIV. 4 PELEBARAN PERKERASAN DAN BAHU JALAN


4.2.2 Lapis Pondasi Agregat Klas B M3 2,370.00 1,166.00
Sub Total Div. 4

DIV. 5 PERKERASAN BERBUTIR


5.1.1 Lapis Pondasi Agregat Klas A M3 9,480.00 9,435.96
5.1.2 Lapis Pondasi Agregat Klas B M3 6,824.50 8,390.32
Sub Total Div. 5

DIV. 6 PERKERASAN ASPAL


6.1(1)(a) Lapis Resap Pengikat - Aspal Cair Liter 39,421.56 40,263.40
6.1(2)(a) Lapis Perekat - Aspal Cair Liter 7,157.40 7,105.31
6.3(5a) Laston Lapis Aus (AC-WC) gradasi halus/kasar Ton 4,007.60 3,947.81
6.3(6a) Laston Lapis Antara (AC-BC) gradasi halus/kasar Ton 5,832.47 6,002.11
6.3.8.a Aspal Keras Ton 663.43 600.62
6.3.9 Aditif Anti Pengelupasan Kg 1,990.30 1,201.24
6.3.10a Bahan Pengisi (Filler) Tambahan (Semen) Kg 149,848.70 99,499.23
Sub Total Div. 6

DIV. 7 STRUKTUR
7.1(7) Beton mutu sedang dengan fc'=20 MPa (K-250) M3 7.02 29.21
7.3(1) Baja Tulangan BJ 24 Polos Kg 1,123.48 5,989.00
7.9 Pasangan Batu M3 274.87 424.05
Sub Total Div. 7

DIV. 8 PENGEMBALIAN KONDISI DAN PEKERJAAN MINOR


8.1(1) Lapisan Pondasi Agregat Klas A untuk Pekerjaan Minor M3 10.00 -
8.3(3) Pohon Buah 100.00 100.00
8.4(1) Marka Jalan Termoplastik M2 2,251.50 -
8.4(3)(a) Rambu Jalan Tunggal dgn Permukaan Pemantul Engineer Grade Buah 42.00 42.00
8.4(5) Patok Pengarah Buah 150.00 150.00
8.4(6)(a) Patok Kilometer Buah 8.00 8.00
8.4(6)(b) Patok Hektometer Buah 86.00 71.00
Sub Total Div. 8

DIV. 10 PEKERJAAN PEMELIHARAAN RUTIN


10.1(2) Pemeliharaan Rutin Bahu Jalan Ls 1.00 1.00
10.1(3) Pemeliharaan Rutin Selokan, Saluran Air, Galian dan Timbunan Ls 1.00 1.00
10.1(4) Pemeliharaan Rutin Perlengkapan Jalan Ls 1.00 1.00
Sub Total Div. 8
Total

Disetujui oleh : Diperiks


Satuan Kerja Pelaksanaan Jalan Nasional Wilayah III Prov. NTB Konsultan
PPK 08 Batas Kab. Dompu-Banggo-Balibunga-Madaprama PT. CIRIATAMA NUS

UJANG SUKMANA, ST.MM. MT. LALU ARI


Nip. 19620225 198903 1 005 Site En
ORAN BULANAN
BULAN KE 2 (Dua)

01 Mei 2013 31 Mei 2013

KEMAJUAN QUANTITY BOBOT TERHADAP KONTRAK BOBOT


BOBOT BULAN BULAN S/D BULAN BULAN BULAN S/D BULAN TERHADAP
(%)
LALU INI INI LALU INI INI ITEM PEK.

0.281 0.50 0.20 0.70 0.140 0.056 0.196 70.00


0.062 0.23 0.18 0.41 0.014 0.011 0.025 40.66
0.217 - - - - - - -
0.229 0.20 0.18 0.38 0.046 0.042 0.088 38.29
0.789 0.200 0.109 0.309

1.254 677.05 - 677.05 0.132 - 0.132 10.52


0.514 190.35 10.28 200.63 0.488 0.026 0.514 100.00
0.979 - 453.01 453.01 - 0.979 0.979 100.00
2.748 0.620 1.005 1.625

1.129 2,081.25 2,067.01 4,148.26 0.531 0.527 1.058 93.68


-
-
0.026 45.15 8.85 54.00 0.022 0.004 0.026 100.00
0.081 - 257.52 257.52 - 0.058 0.058 70.92
-
-
4.919 - - - - - - -
0.217 8,325.00 5,288.40 13,613.40 0.133 0.084 0.217 100.00
6.373 0.686 0.673 1.359

2.222 - - - - - - -
2.222 - - -

19.809 - 4,248.00 4,248.00 - 8.918 8.918 45.02


15.650 3,606.25 4,784.07 8,390.32 6.726 8.923 15.650 100.00
35.459 6.726 17.841 24.568

2.019 - - - - - - -
0.374 - - - - - - -
7.527 - - - - - - -
11.020 - - - - - - -
28.382 - - - - - - -
0.323 - - - - - - -
0.541 - - - - - - -
50.186 - - -

0.206 7.02 4.14 11.16 0.049 0.029 0.079 38.21


0.458 1,123.48 127.18 1,250.66 0.086 0.010 0.096 20.88
1.001 274.87 82.30 357.17 0.649 0.194 0.843 84.23
1.665 0.784 0.233 1.018

-
0.018 - - - - - - -
-
0.116 - - - - - - -
0.114 - - - - - - -
0.017 - - - - - - -
0.077 - - - - - - -
0.343 - - -

0.088 0.17 0.19 0.36 0.015 0.017 0.031 35.71


0.110 0.17 0.19 0.36 0.018 0.021 0.039 35.71
0.018 0.17 0.19 0.36 0.003 0.003 0.007 35.71
0.216 0.036 0.041 0.077
100.00 9.053 19.903 28.956
Kemajuan Pekerjaan Bulan Lalu : 9.053 (%)
Kemajuan Pekerjaan Bulan Ini : 19.903 (%)
Kemajuan Pekerjaan s/d Bulan Ini : 28.956 (%)
Rencana Kemajuan Pekerjaan s/d Bulan ini : 23.257 (%)
Deviasi : 5.699 (%)

Dompu, 31 Mei 2013


Diperiksa oleh : Dibuat oleh :
Konsultan Supervisi Kontraktor Pelaksana
PT. CIRIATAMA NUSAWIDYA CONSULT PT. DUNIA MAS

LALU ARIAWAN, ST ZAINAL FADLI NURAN, ST


Site Engineer General Superintendent
RINGKASAN KEMAJUAN PEKERJAAN
PELEBARAN KAWASAN STRATEGIS JALAN KEMPO - KESI - HODO (PPK 08) SEPANJANG 7,90 KM
PERIODE 21 Maret 2013 - 30 April 2013
DATA PROYEK RINGKASAN PROGRESS STATUS PROYEK
NAMA PAKET : PELEBARAN KAWASAN STRATEGIS JALAN KEMPO - KESI - KONTRAK 180 HARI
HODO (PPK 08) SEPANJANG 7.90 KM WAKTU TERPAKAI 41 HARI > Galian utk Selokan Drainase dan Sal Air
PENYEDIA JASA : PT. DUNIA MAS SISA 139 HARI > Pasangan Batu dgn Mortar
NOMOR KONTRAK : KU.02.09/PPK08-WIL3NTB/180/2013 BULAN INI 20.235 % > Galian Biasa
TANGGAL KONTRAK TANGGAL 21 MARET 2013 REALISASI 20.235 % > Galian Struktur dgn Kedalaman 0-2 m
PROGRESS FISIK
NOMOR ADD. 01 :- RENCANA 4.892 % > Penyiapan Badan Jalan
TANGGAL ADD.01 :- DEVIASI 15.343 % > LPA Klas A
NOMOR ADD. 02 :- > LPA Klas B
TANGGAL ADD. 02 : FOTO KEGIATAN PEKERJAAN > Beton mutu sedang dgn fc'=20 Mpa(K-250)
NILAI KONTRAK AWAL Rp26,560,932,000.00 > Baja tulangan BJ 24 polos
NILAI ADDENDUM 01 :- > Pasangan Batu
SUMBER DANA : APBN Murni
SURAT PENYERAHAN LAPANGAN : 183/BA-PLK/PPK 08.WIL3NTB/2013
: 21 Maret 2013
SURAT PERINTAH MULAI KERJA : 184/SPMK/PPK 08.WIL3NTB/2013 MASALAH
: 21 Maret 2013
PANJANG JALAN EFEKTIF : 7.900 KM Kondisi existing ruas Jalan Kempo-Kesi-Hodo yang akan ditangani adalah rusak berat
PANJANG JALAN FUNGSIONAL : 26.200 KM (KM. 101+550 s/d KM. 127+750) dengan minimnya bangunan pelengkap untuk pengarah air (side drainage and cross
LEBAR JALUR : 1 x 6.00 M drainage).
SEGMEN I (Panjang) : 2.040 KM Kebutuhan kuantitas hasil rekayasa lapangan jauh lebih besar dari kuantitas yang ada di
KOORDINAT (GPS) AWAL : S = 8°31'35.2" E = 118°12'43.6" dalam kontrak, sehingga diperlukan penambahan dana untuk menyelesaikan pelaksanaan
KOORDINAT (GPS) AKHIR : S = 8°32'04.9" E = 118°11'52.1" pekerjaan tersebut secara optimal.
SEGMEN II (Panjang) : 3.550 KM
KOORDINAT (GPS) AWAL : S = 8°30'16.5" E = 118°08'24.8"
KOORDINAT (GPS) AKHIR : S = 8°28'54.1" E = 118°07'53.9" SOLUSI
SEGMEN III (Panjang) : 2.310 KM
KOORDINAT (GPS) AWAL : S = 8°28'40.8" E = 118°07'56.8" Mengusulkan tambahan biaya yang akan dituangkan dalam addendum kontrak (masih
KOORDINAT (GPS) AKHIR : S = 8°27'59.2" E = 118°07'24.6" dalam proses).
MASA PELAKSANAAN PEKERJAAN : 180 (SERATUS DELAPAN PULUH) HARI KALENDER
MASA PEMELIHARAAAN : 720 (TUJUH RATUS DUA PULUH) HARI KALENDER Bila penambahan dana tidak memungkinkan , maka perlu adanya penyesuaian kuantitas
AKHIR MASA PELAKSANAAN (PHO) : 16 SEPTEMBER 2013 pekerjaan dengan tolak ukur skala prioritas tanpa harus mengubah design yang ada
AKHIR MASA KONTRAK (FHO) : 06 SEPTEMBER 2015 secara ekstrim.
PEJABAT PEMBUAT KOMITMEN : UJANG SUKMANA, ST. MM. MT.
KONSULTAN SUPERVISI : PT. CIRIATAMA NUSAWIDYA CONSULT

PROGRES FISIK
BOBOT (%) PROGRESS FISIK (%) KURVA MONITORING PROGRESS
DIV. URAIAN KONTRAK S/D BLN
ADD. 01 ADD. 02 BLN LALU BLN INI
AWAL INI
I UMUM 0.789 - 0.204 0.204
II DRAINASE 0.650 - 0.650 0.650
CURVA S PROGRESS
III PEKERJAAN TANAH 4.360 - 0.690 0.690 100.000 100.000
IV PELEBARAN PERKERASAN DAN BAHU JALAN 4.517 - - - Kontrak 97.415
V PERKERASAN BERBUTIR 32.631 - 17.868 17.868 Awal
Addendum
VI PERKERASAN ASPAL 53.403 - - -
01
VII STRUKTUR 0.784 - 0.784 0.784 Addendum
VIII PENGEMBALIAN KONDISI DAN PEKERJAAN MINOR 2.650 - - - 02
IX PEKERJAAN PEMELIHARAAN RUTIN 0.216 - 0.039 0.039 Realisasi
TOTAL 100.000 - 20.235 20.235 75.000
71.654
MONITORING PROGRESS FISIK
TAHUN 2013
BULAN BULAN APRIL MEI JUNI JULI AGUST SEPT
RENCANA KEMAJUAN PEKERJAAN BULANAN (%) 4.892 11.135 18.620 37.007 25.762 2.585
RENCANA KEMAJUAN PEKERJAAN KOMULATIF (%) 4.892 16.027 34.647 71.654 97.415 100.000

PROGRESS
RENCANA KEMAJUAN PEKERJAAN BULANAN (ADD. 01) (%) - 50.000
RENCANA KEMAJUAN PEKERJAAN KOMULATIF (ADD. 01) (%) -
RENCANA KEMAJUAN PEKERJAAN BULANAN (ADD. 02) (%) -
RENCANA KEMAJUAN PEKERJAAN KOMULATIF (ADD. 02) (%) -
REALISASI KEMAJUAN PEKERJAAN BULANAN (%) 20.235
34.647
REALISASI KEMAJUAN PEKERJAAN KOMULATIF (%) 20.235
DEVIASI (%) 15.343
25.000
MONITORING PROGRESS KEUANGAN
20.235
RENCANA KEMAJUAN PEMBAYARAN BULANAN (Rp. 103) UANG MUKA 1,299,469 2,957,556 4,945,528 9,829,292 6,842,560 686,528
RENCANA KEMAJUAN PEMBAYARAN KOMULATIF (Rp. 103) 5,312,186 1,299,469 4,257,025 9,202,553 19,031,844 25,874,404 26,560,932
16.027
RENCANA KEMAJUAN PEMBAYARAN BULANAN (ADD. 01) (Rp. 103) - - - - - -
RENCANA KEMAJUAN PEMBAYARAN KOMULATIF (ADD. 01) (Rp. 103) - - - - - -
4.892
RENCANA KEMAJUAN PEMBAYARAN BULANAN (ADD. 02) (Rp. 103) - - - - - -
RENCANA KEMAJUAN PEMBAYARAN KOMULATIF (ADD. 02) (Rp. 103) - - - - - - 0.000 -
APRIL MEI JUNI JULI AGUST SEPT
REALISASI KEMAJUAN PEMBAYARAN BULANAN (Rp. 103) 5,374,646 - - - - -
REALISASI KEMAJUAN PEMBAYARAN KOMULATIF (Rp. 103) 5,374,646 - - - - - BULAN
DEVIASI (Rp. 103) 4,075,177 - - - - -
RINGKASAN KEMAJUAN PEKERJAAN
PELEBARAN KAWASAN STRATEGIS JALAN KEMPO - KESI - HODO (PPK 08) SEPANJANG 7,90 KM
PERIODE 01 Mei 2013 - 26 Mei 2013
DATA PROYEK RINGKASAN PROGRESS STATUS PROYEK
NAMA PAKET : PELEBARAN KAWASAN STRATEGIS JALAN KEMPO - KESI - KONTRAK 180 HARI
HODO (PPK 08) SEPANJANG 7.90 KM WAKTU TERPAKAI 67 HARI > Galian utk Selokan Drainase dan Sal Air
PENYEDIA JASA : PT. DUNIA MAS SISA 113 HARI > Pasangan Batu dgn Mortar
NOMOR KONTRAK : KU.02.09/PPK08-WIL3NTB/180/2013 BULAN INI 19.371 % > Galian Biasa
TANGGAL KONTRAK TANGGAL 21 MARET 2013 REALISASI 39.607 % > Galian Struktur dgn Kedalaman 0-2 m
PROGRESS FISIK
NOMOR ADD. 01 :- RENCANA 22.570 % > Penyiapan Badan Jalan
TANGGAL ADD.01 :- DEVIASI 17.036 % > LPA Klas A
NOMOR ADD. 02 :- > LPA Klas B
TANGGAL ADD. 02 : FOTO KEGIATAN PEKERJAAN > Lapis Resap Pengikat
NILAI KONTRAK AWAL Rp26,560,932,000.00 > Laston Lapis Antara (AC-BC)
NILAI ADDENDUM 01 :- > Aspal Keras, Aditif dan Filler
SUMBER DANA : APBN Murni > Beton mutu sedang dgn fc'=20 Mpa(K-250)
SURAT PENYERAHAN LAPANGAN : 183/BA-PLK/PPK 08.WIL3NTB/2013 > Baja tulangan BJ 24 polos
: 21 Maret 2013 > Pasangan Batu
SURAT PERINTAH MULAI KERJA : 184/SPMK/PPK 08.WIL3NTB/2013 MASALAH
: 21 Maret 2013
PANJANG JALAN EFEKTIF : 7.900 KM Kondisi existing ruas Jalan Kempo-Kesi-Hodo yang akan ditangani adalah rusak berat
PANJANG JALAN FUNGSIONAL : 26.200 KM (KM. 101+550 s/d KM. 127+750) dengan minimnya bangunan pelengkap untuk pengarah air (side drainage and cross
LEBAR JALUR : 1 x 6.00 M drainage).
SEGMEN I (Panjang) : 2.040 KM Kebutuhan kuantitas hasil rekayasa lapangan jauh lebih besar dari kuantitas yang ada di
KOORDINAT (GPS) AWAL : S = 8°31'35.2" E = 118°12'43.6" dalam kontrak, sehingga diperlukan penambahan dana untuk menyelesaikan pelaksanaan
KOORDINAT (GPS) AKHIR : S = 8°32'04.9" E = 118°11'52.1" pekerjaan tersebut secara optimal.
SEGMEN II (Panjang) : 3.550 KM
KOORDINAT (GPS) AWAL : S = 8°30'16.5" E = 118°08'24.8"
KOORDINAT (GPS) AKHIR : S = 8°28'54.1" E = 118°07'53.9" SOLUSI
SEGMEN III (Panjang) : 2.310 KM
KOORDINAT (GPS) AWAL : S = 8°28'40.8" E = 118°07'56.8" Mengusulkan tambahan biaya yang akan dituangkan dalam addendum kontrak (masih
KOORDINAT (GPS) AKHIR : S = 8°27'59.2" E = 118°07'24.6" dalam proses).
MASA PELAKSANAAN PEKERJAAN : 180 (SERATUS DELAPAN PULUH) HARI KALENDER
MASA PEMELIHARAAAN : 720 (TUJUH RATUS DUA PULUH) HARI KALENDER Bila penambahan dana tidak memungkinkan , maka perlu adanya penyesuaian kuantitas
AKHIR MASA PELAKSANAAN (PHO) : 16 SEPTEMBER 2013 pekerjaan dengan tolak ukur skala prioritas dengan mengoptimasi ketebalan LPA Klas A
AKHIR MASA KONTRAK (FHO) : 06 SEPTEMBER 2015
PEJABAT PEMBUAT KOMITMEN : UJANG SUKMANA, ST. MM. MT.
KONSULTAN SUPERVISI : PT. CIRIATAMA NUSAWIDYA CONSULT

PROGRES FISIK
BOBOT (%) PROGRESS FISIK (%) KURVA MONITORING PROGRESS
DIV. URAIAN KONTRAK S/D BLN
ADD. 01 ADD. 02 BLN LALU BLN INI
AWAL INI
I UMUM 0.789 0.204 0.099 0.303
II DRAINASE 0.650 0.650 0.000 0.650
CURVA S PROGRESS
III PEKERJAAN TANAH 4.360 0.690 0.542 1.232 100.000 100.000
IV PELEBARAN PERKERASAN DAN BAHU JALAN 4.517 - - - Kontrak 97.415
V PERKERASAN BERBUTIR 32.631 17.868 10.971 28.839 Awal
Addendum
VI PERKERASAN ASPAL 53.403 - 7.726 7.726
01
VII STRUKTUR 0.784 0.784 0.000 0.784 Addendum
VIII PENGEMBALIAN KONDISI DAN PEKERJAAN MINOR 2.650 - - - 02
IX PEKERJAAN PEMELIHARAAN RUTIN 0.216 0.039 0.033 0.072 Realisasi
TOTAL 100.000 20.235 19.371 39.607 75.000
71.654
MONITORING PROGRESS FISIK
TAHUN 2013
BULAN BULAN APRIL MEI JUNI JULI AGUST SEPT
RENCANA KEMAJUAN PEKERJAAN BULANAN (%) 4.892 17.678 12.077 37.007 25.762 2.585
RENCANA KEMAJUAN PEKERJAAN KOMULATIF (%) 4.892 22.570 34.647 71.654 97.415 100.000

PROGRESS
RENCANA KEMAJUAN PEKERJAAN BULANAN (ADD. 01) (%) - 50.000
RENCANA KEMAJUAN PEKERJAAN KOMULATIF (ADD. 01) (%) -
RENCANA KEMAJUAN PEKERJAAN BULANAN (ADD. 02) (%) -
RENCANA KEMAJUAN PEKERJAAN KOMULATIF (ADD. 02) (%) - 39.607
REALISASI KEMAJUAN PEKERJAAN BULANAN (%) 20.235 19.371
34.647
REALISASI KEMAJUAN PEKERJAAN KOMULATIF (%) 20.235 39.607
DEVIASI (%) 15.343 17.036
25.000
MONITORING PROGRESS KEUANGAN 22.570
20.235
RENCANA KEMAJUAN PEMBAYARAN BULANAN (Rp. 103) UANG MUKA 1,299,469 4,695,348 3,207,736 9,829,292 6,842,560 686,528
RENCANA KEMAJUAN PEMBAYARAN KOMULATIF (Rp. 103) 5,312,186 1,299,469 5,994,817 9,202,553 19,031,844 25,874,404 26,560,932
RENCANA KEMAJUAN PEMBAYARAN BULANAN (ADD. 01) (Rp. 103) - - - - - -
RENCANA KEMAJUAN PEMBAYARAN KOMULATIF (ADD. 01) (Rp. 103) - - - - - -
4.892
RENCANA KEMAJUAN PEMBAYARAN BULANAN (ADD. 02) (Rp. 103) - - - - - -
RENCANA KEMAJUAN PEMBAYARAN KOMULATIF (ADD. 02) (Rp. 103) - - - - - - 0.000 -
APRIL MEI JUNI JULI AGUST SEPT
REALISASI KEMAJUAN PEMBAYARAN BULANAN (Rp. 103) 5,374,646 5,145,223 - - - -
REALISASI KEMAJUAN PEMBAYARAN KOMULATIF (Rp. 103) 5,374,646 10,519,869 - - - - BULAN
DEVIASI (Rp. 103) 4,075,177 4,525,052 - - - -
RINGKASAN KEMAJUAN PEKERJAAN
PELEBARAN KAWASAN STRATEGIS JALAN KEMPO - KESI - HODO (PPK 08) SEPANJANG 7,90 KM
PERIODE 01 Mei 2013 - 31 Mei 2013
DATA PROYEK RINGKASAN PROGRESS STATUS PROYEK
NAMA PAKET : PELEBARAN KAWASAN STRATEGIS JALAN KEMPO - KESI - KONTRAK 180 HARI
HODO (PPK 08) SEPANJANG 7.90 KM WAKTU TERPAKAI 72 HARI > Galian utk Selokan Drainase dan Sal Air
PENYEDIA JASA : PT. DUNIA MAS SISA 108 HARI > Pasangan Batu dgn Mortar
NOMOR KONTRAK : KU.02.09/PPK08-WIL3NTB/180/2013 BULAN INI 24.213 % > Galian Biasa
TANGGAL KONTRAK TANGGAL 21 MARET 2013 REALISASI 44.408 % > Galian Struktur dgn Kedalaman 0-2 m
PROGRESS FISIK
NOMOR ADD. 01 : KU.01.02/ADD-01/PPK08.WIL3NTB/353/2013 RENCANA 22.570 % > Penyiapan Badan Jalan
TANGGAL ADD.01 TANGGAL 03 MEI 2013 DEVIASI 21.838 % > LPA Klas A
NOMOR ADD. 02 :- > LPA Klas B
TANGGAL ADD. 02 : FOTO KEGIATAN PEKERJAAN > Lapis Resap Pengikat
NILAI KONTRAK AWAL Rp26,560,932,000.00 > Laston Lapis Antara (AC-BC)
NILAI ADDENDUM 01 :- > Aspal Keras, Aditif dan Filler
SUMBER DANA : APBN Murni > Beton mutu sedang dgn fc'=20 Mpa(K-250)
SURAT PENYERAHAN LAPANGAN : 183/BA-PLK/PPK 08.WIL3NTB/2013 > Baja tulangan BJ 24 polos
: 21 Maret 2013 > Pasangan Batu
SURAT PERINTAH MULAI KERJA : 184/SPMK/PPK 08.WIL3NTB/2013 MASALAH
: 21 Maret 2013
PANJANG JALAN EFEKTIF : 7.900 KM Kondisi existing ruas Jalan Kempo-Kesi-Hodo yang akan ditangani adalah rusak berat
PANJANG JALAN FUNGSIONAL : 26.200 KM (KM. 101+550 s/d KM. 127+750) dengan minimnya bangunan pelengkap untuk pengarah air (side drainage and cross
LEBAR JALUR : 1 x 6.00 M drainage).
SEGMEN I (Panjang) : 2.040 KM Kebutuhan kuantitas hasil rekayasa lapangan jauh lebih besar dari kuantitas yang ada di
KOORDINAT (GPS) AWAL : S = 8°31'35.2" E = 118°12'43.6" dalam kontrak, sehingga diperlukan penambahan dana untuk menyelesaikan pelaksanaan
KOORDINAT (GPS) AKHIR : S = 8°32'04.9" E = 118°11'52.1" pekerjaan tersebut secara optimal.
SEGMEN II (Panjang) : 3.550 KM
KOORDINAT (GPS) AWAL : S = 8°30'16.5" E = 118°08'24.8"
KOORDINAT (GPS) AKHIR : S = 8°28'54.1" E = 118°07'53.9" SOLUSI
SEGMEN III (Panjang) : 2.310 KM
KOORDINAT (GPS) AWAL : S = 8°28'40.8" E = 118°07'56.8" Mengoptimalkan dana yang ada dengan perubahan volume pekerjaan yang tertuang
KOORDINAT (GPS) AKHIR : S = 8°27'59.2" E = 118°07'24.6" dengan CCO 01 (Balance Budget)
MASA PELAKSANAAN PEKERJAAN : 180 (SERATUS DELAPAN PULUH) HARI KALENDER
MASA PEMELIHARAAAN : 720 (TUJUH RATUS DUA PULUH) HARI KALENDER
AKHIR MASA PELAKSANAAN (PHO) : 16 SEPTEMBER 2013
AKHIR MASA KONTRAK (FHO) : 06 SEPTEMBER 2015
PEJABAT PEMBUAT KOMITMEN : UJANG SUKMANA, ST. MM. MT.
KONSULTAN SUPERVISI : PT. CIRIATAMA NUSAWIDYA CONSULT

PROGRES FISIK
BOBOT (%) PROGRESS FISIK (%) KURVA MONITORING PROGRESS
DIV. URAIAN KONTRAK S/D BLN
ADD. 01 ADD. 02 BLN LALU BLN INI
AWAL INI
I UMUM 0.789 0.789 0.200 0.109 0.309
II DRAINASE 0.650 2.748 0.620 1.012 1.632
CURVA S PROGRESS
III PEKERJAAN TANAH 4.360 6.373 0.686 0.697 1.383 100.000 100.000
IV PELEBARAN PERKERASAN DAN BAHU JALAN 4.517 2.222 - - - Kontrak 97.415
V PERKERASAN BERBUTIR 32.631 35.459 17.868 14.395 32.264 Awal
Addendum
VI PERKERASAN ASPAL 53.403 50.186 - 7.726 7.726
01
VII STRUKTUR 0.784 1.665 0.784 0.233 1.018 Addendum
VIII PENGEMBALIAN KONDISI DAN PEKERJAAN MINOR 2.650 0.343 - - - 02
IX PEKERJAAN PEMELIHARAAN RUTIN 0.216 0.216 0.036 0.041 0.077 Realisasi
TOTAL 100.000 100.000 - 20.195 24.213 44.408 75.000
71.654
MONITORING PROGRESS FISIK
TAHUN 2013
BULAN BULAN APRIL MEI JUNI JULI AGUST SEPT
RENCANA KEMAJUAN PEKERJAAN BULANAN (%) 4.892 17.678 12.077 37.007 25.762 2.585
RENCANA KEMAJUAN PEKERJAAN KOMULATIF (%) 4.892 22.570 34.647 71.654 97.415 100.000

PROGRESS
RENCANA KEMAJUAN PEKERJAAN BULANAN (ADD. 01) (%) 3.062 27.302 34.062 14.210 1.169 50.000
RENCANA KEMAJUAN PEKERJAAN KOMULATIF (ADD. 01) (%) 23.257 50.559 84.621 98.831 100.000
RENCANA KEMAJUAN PEKERJAAN BULANAN (ADD. 02) (%) - 44.408
RENCANA KEMAJUAN PEKERJAAN KOMULATIF (ADD. 02) (%) -
REALISASI KEMAJUAN PEKERJAAN BULANAN (%) 20.195 24.213
34.647
REALISASI KEMAJUAN PEKERJAAN KOMULATIF (%) 20.195 44.408
DEVIASI (%) 15.303 21.838
25.000
MONITORING PROGRESS KEUANGAN 22.570
20.195
RENCANA KEMAJUAN PEMBAYARAN BULANAN (Rp. 103) UANG MUKA 1,299,469 4,695,348 3,207,736 9,829,292 6,842,560 686,528
RENCANA KEMAJUAN PEMBAYARAN KOMULATIF (Rp. 103) 5,312,186 1,299,469 5,994,817 9,202,553 19,031,844 25,874,404 26,560,932
RENCANA KEMAJUAN PEMBAYARAN BULANAN (ADD. 01) (Rp. 103) 5,363,971 813,332 7,251,607 9,047,127 3,774,319 310,576
RENCANA KEMAJUAN PEMBAYARAN KOMULATIF (ADD. 01) (Rp. 103) 5,363,971 6,177,303 13,428,910 22,476,037 26,250,356 26,560,932
4.892
RENCANA KEMAJUAN PEMBAYARAN BULANAN (ADD. 02) (Rp. 103) - - - - - -
RENCANA KEMAJUAN PEMBAYARAN KOMULATIF (ADD. 02) (Rp. 103) - - - - - - 0.000 -
APRIL MEI JUNI JULI AGUST SEPT
REALISASI KEMAJUAN PEMBAYARAN BULANAN (Rp. 103) 5,363,971 6,431,226 - - - -
REALISASI KEMAJUAN PEMBAYARAN KOMULATIF (Rp. 103) 5,363,971 11,795,197 - - - - BULAN
DEVIASI (Rp. 103) 4,064,502 5,800,380 - - - -
RINGKASAN KEMAJUAN PEKERJAAN
PELEBARAN KAWASAN STRATEGIS JALAN KEMPO - KESI - HODO (PPK 08) SEPANJANG 7,90 KM
PERIODE 01 Juni 2013 - 30 Juni 2013
DATA PROYEK RINGKASAN PROGRESS STATUS PROYEK
NAMA PAKET : PELEBARAN KAWASAN STRATEGIS JALAN KEMPO - KESI - KONTRAK 180 HARI
HODO (PPK 08) SEPANJANG 7.90 KM WAKTU TERPAKAI 102 HARI > Galian utk Selokan Drainase dan Sal Air
PENYEDIA JASA : PT. DUNIA MAS SISA 78 HARI > LPA Klas A
NOMOR KONTRAK : KU.02.09/PPK08-WIL3NTB/180/2013 BULAN INI 14.030 % > Lapis Resap Pengikat
TANGGAL KONTRAK TANGGAL 21 MARET 2013 REALISASI 58.438 % > Laston Lapis Antara (AC-BC)
PROGRESS FISIK
NOMOR ADD. 01 : KU.01.02/ADD-01/PPK08.WIL3NTB/353/2013 RENCANA 50.559 % > Aspal Keras, Aditif dan Filler
TANGGAL ADD.01 TANGGAL 03 MEI 2013 DEVIASI 7.879 % > Beton mutu sedang dgn fc'=20 Mpa(K-250)
NOMOR ADD. 02 :- > Baja tulangan BJ 24 polos
TANGGAL ADD. 02 : FOTO KEGIATAN PEKERJAAN > Pasangan Batu
NILAI KONTRAK AWAL Rp26,560,932,000.00
NILAI ADDENDUM 01 :-
SUMBER DANA : APBN Murni
SURAT PENYERAHAN LAPANGAN : 183/BA-PLK/PPK 08.WIL3NTB/2013
: 21 Maret 2013
SURAT PERINTAH MULAI KERJA : 184/SPMK/PPK 08.WIL3NTB/2013 MASALAH
: 21 Maret 2013
PANJANG JALAN EFEKTIF : 7.900 KM
PANJANG JALAN FUNGSIONAL : 26.200 KM (KM. 101+550 s/d KM. 127+750)
LEBAR JALUR : 1 x 6.00 M
SEGMEN I (Panjang) : 2.040 KM
KOORDINAT (GPS) AWAL : S = 8°31'35.2" E = 118°12'43.6"
KOORDINAT (GPS) AKHIR : S = 8°32'04.9" E = 118°11'52.1"
SEGMEN II (Panjang) : 3.550 KM
KOORDINAT (GPS) AWAL : S = 8°30'16.5" E = 118°08'24.8"
KOORDINAT (GPS) AKHIR : S = 8°28'54.1" E = 118°07'53.9" SOLUSI
SEGMEN III (Panjang) : 2.310 KM
KOORDINAT (GPS) AWAL : S = 8°28'40.8" E = 118°07'56.8"
KOORDINAT (GPS) AKHIR : S = 8°27'59.2" E = 118°07'24.6"
MASA PELAKSANAAN PEKERJAAN : 180 (SERATUS DELAPAN PULUH) HARI KALENDER
MASA PEMELIHARAAAN : 720 (TUJUH RATUS DUA PULUH) HARI KALENDER
AKHIR MASA PELAKSANAAN (PHO) : 16 SEPTEMBER 2013
AKHIR MASA KONTRAK (FHO) : 06 SEPTEMBER 2015
PEJABAT PEMBUAT KOMITMEN : UJANG SUKMANA, ST. MM. MT.
KONSULTAN SUPERVISI : PT. CIRIATAMA NUSAWIDYA CONSULT

PROGRES FISIK
BOBOT (%) PROGRESS FISIK (%) KURVA MONITORING PROGRESS
DIV. URAIAN KONTRAK S/D BLN
ADD. 01 ADD. 02 BLN LALU BLN INI
AWAL INI
I UMUM 0.789 0.789 0.309 0.051 0.361
II DRAINASE 0.650 2.748 1.632 0.591 2.223
CURVA S PROGRESS
III PEKERJAAN TANAH 4.360 6.373 1.383 - 1.383 100.000 100.000
IV PELEBARAN PERKERASAN DAN BAHU JALAN 4.517 2.222 - - - Kontrak 97.415
V PERKERASAN BERBUTIR 32.631 35.459 32.264 3.196 35.459 Awal
Addendum
VI PERKERASAN ASPAL 53.403 50.186 7.726 9.505 17.231
01
VII STRUKTUR 0.784 1.665 1.018 0.647 1.665 Addendum
VIII PENGEMBALIAN KONDISI DAN PEKERJAAN MINOR 2.650 0.343 - - - 02
IX PEKERJAAN PEMELIHARAAN RUTIN 0.216 0.216 0.077 0.040 0.117 Realisasi
TOTAL 100.000 100.000 - 44.408 14.030 58.438 75.000
71.654
MONITORING PROGRESS FISIK
TAHUN 2013
BULAN BULAN APRIL MEI JUNI JULI AGUST SEPT
RENCANA KEMAJUAN PEKERJAAN BULANAN (%) 4.892 17.678 12.077 37.007 25.762 2.585 58.438
RENCANA KEMAJUAN PEKERJAAN KOMULATIF (%) 4.892 22.570 34.647 71.654 97.415 100.000

PROGRESS
RENCANA KEMAJUAN PEKERJAAN BULANAN (ADD. 01) (%) 3.022 27.302 34.062 14.210 1.169 50.000
RENCANA KEMAJUAN PEKERJAAN KOMULATIF (ADD. 01) (%) 23.257 50.559 84.621 98.831 100.000
RENCANA KEMAJUAN PEKERJAAN BULANAN (ADD. 02) (%) - 44.408
RENCANA KEMAJUAN PEKERJAAN KOMULATIF (ADD. 02) (%) -
REALISASI KEMAJUAN PEKERJAAN BULANAN (%) 20.235 24.173 14.030
34.647
REALISASI KEMAJUAN PEKERJAAN KOMULATIF (%) 20.235 44.408 58.438
DEVIASI (%) 15.343 21.151 7.879
25.000
MONITORING PROGRESS KEUANGAN 22.570
20.235
RENCANA KEMAJUAN PEMBAYARAN BULANAN (Rp. 103) UANG MUKA 1,299,469 4,695,348 3,207,736 9,829,292 6,842,560 686,528
RENCANA KEMAJUAN PEMBAYARAN KOMULATIF (Rp. 103) 5,312,186 1,299,469 5,994,817 9,202,553 19,031,844 25,874,404 26,560,932
RENCANA KEMAJUAN PEMBAYARAN BULANAN (ADD. 01) (Rp. 103) 5,374,646 802,657 7,251,607 9,047,127 3,774,319 310,576
RENCANA KEMAJUAN PEMBAYARAN KOMULATIF (ADD. 01) (Rp. 103) 5,374,646 6,177,303 13,428,910 22,476,037 26,250,356 26,560,932
4.892
RENCANA KEMAJUAN PEMBAYARAN BULANAN (ADD. 02) (Rp. 103) - - - - - -
RENCANA KEMAJUAN PEMBAYARAN KOMULATIF (ADD. 02) (Rp. 103) - - - - - - 0.000 -
APRIL MEI JUNI JULI AGUST SEPT
REALISASI KEMAJUAN PEMBAYARAN BULANAN (Rp. 103) 5,374,646 6,420,551 3,726,548 - - -
REALISASI KEMAJUAN PEMBAYARAN KOMULATIF (Rp. 103) 5,374,646 11,795,197 15,521,745 - - - BULAN
DEVIASI (Rp. 103) 4,075,177 5,617,894 2,092,835 - - -

Anda mungkin juga menyukai