NO URAIAN PEKERJAAN
A PEKERJAAN STRUKTUR
I PEKERJAAN PERSIAPAN
1 pekerjaan pembersihan lokasi
2 Pekerjaan bouplank
3 Pekerjaan air kerja
4 Pekerjaan listrik kerja
5 Pekerjaan buang tanah - pembersihan
II PEKERJAAN GALIAN
1 Pekerjaan galian pondasi Uk 1000 x 1000 x 1000 mm = 17 ttk
2 Pekerjaan galian sloof Uk. 300 x 400 mm
IV PEKERJAAN BESI
1 Pekerjaan kolom struktur besi WF 250x125x6x9
2 Pekerjaan balok ikat besi WF 150 x 75x5x7
3 Pekerjaan base plate
4 Pekerjaan Angkur Uk 60 cm
5 Pekerjaan erection + baud dan Alat bantu
B PEKERJAAN ARSITEKTUR
I PEKRJAAN PASANGAN
1 Pekerjaan pasang dinding sandwich panel T 7,5 cm
2 Pekerjaan dinding partisi gypsum rangka holllou
3 Pekerjaan dinding bata Ruang Toilet
4 Pekerjaan plester Ruang toilet
5 Pekerjaan aci Ruang Toilet
II PEKERJAAN KUSEN
I PINTU
1 Pintu Double P-1 150x220 cm ( KACA POLOS 5 mm , KUSEN Alumunium 3")
2 Pintu Single P-2 82x220 cm (KACA POLOS 5 mm , KUSEN Alumunium 3")
3 Pintu Single P-3 72x220 cm (PVC)
IV PEKERJAAN PLAFOND
1 Pekerjaan plafond gypsum
2 Pekerjaan profil T 8 cm
V PEKERJAAN PENGECATAN
1 Pekerjaan cat dinding partisi gypsum
Pekerjaan cat dinding partisi sandwich luar dalam
2 Pekerjaan cat plafond + pforil
3 Pekerjaan cat lisplank
IX PEKERJAAN KRAMIK
1 Pekerjaan pasang keramik lantai Uk . 600 x 600 mm
2 Pekerjaan pasang keramik lantai teras Uk . 600 x 600 mm
3 Pekerjaan pasang keramik lantai Uk . 400 x 400 mm
4 Pekerjaan pasang plin lantai Uk 600 x 100 mm
X PEKERJAAN SANITARY
1 Pekerjaan closed duduk
2 Pekerjaan kran air
3 Pekerjaan floor drain
4 Pekerjaan exhausfan
5 Wastafel
6 Cermin
XI PEKERJAAN AKSESORIES
1 Pekerjaan lampu neon LED beserta fitting mirror stainless
2 Pekerjaan logo WIKA ( Neon Box)
JUMLAH TOTAL
NO URAIAN PEKERJAAN
A PEKERJAAN STRUKTUR
I PEKERJAAN PERSIAPAN
II PEKERJAAN GALIAN
IV PEKERJAAN BESI
B PEKERJAAN ARSITEKTUR
I PEKRJAAN PASANGAN
II PEKERJAAN KUSEN
IV PEKERJAAN PLAFOND
V PEKERJAAN PENGECATAN
IX PEKERJAAN KRAMIK
X PEKERJAAN SANITARY
XI PEKERJAAN AKSESORIES
JUMLAH TOTAL
DISKON
21,552,000.00
672.00 M2 -
104.00 M' 125,500.00 13,052,000.00
1.00 LS 2,500,000.00 2,500,000.00
1.00 LS 5,000,000.00 5,000,000.00
1.00 LS 1,000,000.00 1,000,000.00
-
` 1,842,500.00
17.00 M2 62,500.00 1,062,500.00
12.48 M2 62,500.00 780,000.00
81,645,000.00
6.53 M3 4,500,000.00 29,385,000.00
7.28 M3 3,250,000.00 23,660,000.00
104.00 M' 275,000.00 28,600,000.00
198,759,000.00
2,841.60 Kg 18,000.00 51,148,800.00
2,856.00 Kg 18,000.00 51,408,000.00
17.00 Ttk 475,000.00 8,075,000.00
272.00 Bh 125,000.00 34,000,000.00
5,697.60 Kg 9,500.00 54,127,200.00
436,218,750.00
647.97 M2 625,000.00 404,981,250.00
127.50 M2 245,000.00 31,237,500.00
- M2 325,000.00 -
- M2 42,500.00 -
- M2 35,000.00 -
-
92,200,000.00
-
2.00 unit 1,950,000.00 3,900,000.00
8.00 unit 1,850,000.00 14,800,000.00
- unit 1,350,000.00 -
-
102,731,000.00
616.60 M2 160,000.00 98,656,000.00
326.00 M2 12,500.00 4,075,000.00
21,975,000.00
255.00 M2 46,500.00 11,857,500.00
M2 -
245.00 M' 27,500.00 6,737,500.00
104.00 M' 32,500.00 3,380,000.00
352,620,400.00
786.24 M2 175,000.00 137,592,000.00
786.24 M2 210,000.00 165,110,400.00
104.00 M' 125,000.00 13,000,000.00
36.00 M2 750,000.00 27,000,000.00
36.00 M2 275,500.00 9,918,000.00
93,764,000.00
162,819,000.00
616.60 M2 215,000.00 132,569,000.00
72.00 M2 215,000.00 15,480,000.00
6.00 M2 165,000.00 990,000.00
104.00 M' 132,500.00 13,780,000.00
-
-
- Bh 4,500,000.00 -
- Bh 145,000.00 -
- Bh 65,000.00 -
- Bh 1,500,000.00 -
- Bh 1,200,000.00 -
- Bh 450,000.00 -
13,386,500.00
2.00 Bh 450,000.00 900,000.00
1.00 Bh 5,000,000.00 5,000,000.00
1,591,593,150.00
21,552,000.00
1,842,500.00
81,645,000.00
198,759,000.00
469,818,750.00
94,900,000.00
112,345,000.00
21,975,000.00
352,620,400.00
92,868,000.00
12,080,000.00
174,730,000.00
15,720,000.00
5,900,000.00
1,656,755,650.00
11.9% 196,755,650.00
1,460,000,000.00