HARGA SATUAN
NO URAIAN SATUAN KETERANGAN
(Rp)
1 2 3 4 5
HARGA SATUAN
NO URAIAN SATUAN KETERANGAN
(Rp)
1 2 3 4 5
C. PEKERJAAN PONDASI
G. PEKERJAAN BETON
E. PEKERJAAN PLESTERAN
HARGA JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT
SATUAN HARGA
A PEKERJAAN PENDAHULUAN
1 Pengukuran Dan Pematokan 1.000 Ls 456,000.00 456,000.00
2 Papan Nama Proyek 1.000 Ls 350,000.00 350,000.00
3 Barak Kerja 1.000 Ls 750,000.00 750,000.00
3 Dokumentasi & Administrasi Proyek 1.000 Ls 650,000.00 650,000.00
JUMLAH 2,206,000.00
B PEKERJAAN PARIT PAS. BATU PANJANG 19,00 M
1 Pembersihan Lokasi 22.800 M2 1,205.00 27,474.00
2 Galian Tanah Parit 10.640 M3 37,430.00 398,255.20
3 Urugan Tanah Tebing 1.900 M3 37,430.00 71,117.00
4 Urugan Pasir Bawah Tbl 3,0 cm 0.285 M3 120,310.00 34,288.35
5 Pasangan Batu Gunung 10.830 M3 770,036.00 8,339,489.88
6 Cor Beton 1 : 3 : 4 (K-175) Tbl 5,0 cm 0.380 M3 856,406.00 325,434.28
7 Plesteran Dinding Parit 29.500 M2 43,400.00 1,280,300.00
JUMLAH 10,476,358.71
450,000.00
625,000.00
350,000.00
650,000.00
Panj Prt
19.00
Lbr Prt Rt-2
Kurang :
-
REKAPITULASI
JUMLAH 12,682,358.71
PPN 10% 1,268,235.87
JUMLAH 13,950,594.58
TOTAL ( pembulatan ) 13,950,000.00
TERBILANG : " TIGA BELAS JUTA SEMBILAN RATUS LIMA PULUH RIBU RUPIAH "