HARGA DASAR UPAH DAN BAHAN

A DAFTAR HARGA DASAR UPAH

HARGA SATUAN
NO URAIAN SATUAN KETERANGAN
(Rp)
1 2 3 4 5

1 Mandor Hari 81,000.00


2 Pekerja Hari 50,000.00
3 Tukang Hari 70,000.00
4 Kepala Tukang Hari 76,000.00

B DAFTAR HARGA DASAR BAHAN

HARGA SATUAN
NO URAIAN SATUAN KETERANGAN
(Rp)
1 2 3 4 5

I BAHAN BATU DAN TANAH


1 Pasir urug M3 85,000.00
2 Pasir pasangan (Tenggarong) M3 162,000.00
3 Koral palu M3 378,000.00
4 Koral Long Iram M3 250,000.00
5 Batu gunung M3 280,250.00
6 Semen (Portland Cement) 40 Kg Zak 46,000.00
-
1 Alat Bantu ( Set @ 3 Unit ) Set 60,000.00
DAFTAR ANALISA PEKERJAAN
A. PEKERJAAN PENDAHULUAN

KODE HARGA HARGA JUMLAH


INDEKS SATUAN URAIAN
ANALISA SATUAN (Rp) BAHAN (Rp) UPAH (Rp) HARGA (Rp)
A3 1M 2 PEMBERSIHAN LOKASI

0.0050 Set Alat Bantu (Set @ 3 Alat) 60,000.00 300.00


0.0100 OH Pekerja 50,000.00 500.00
0.0050 OH Mandor 81,000.00 405.00

300.00 905.00 1,205.00

B. PEKERJAAN PASIR DAN TANAH

KODE HARGA HARGA JUMLAH


INDEKS SATUAN URAIAN
ANALISA SATUAN (Rp) BAHAN (Rp) UPAH (Rp) HARGA (Rp)
B1 1M 3 GALIAN TANAH BIASA

0.6000 OH Pekerja 50,000.00 30,000.00


0.0300 OH Mandor 81,000.00 2,430.00
0.1000 Paket Alat Bantu 50,000.00 5,000.00
- 37,430.00 37,430.00

B9 1M URUGAN PASIR DENGAN PENYIRAMAN


3

1.2000 M3 Pasir Urugan 85,000.00 102,000.00


0.3000 OH Pekerja 50,000.00 15,000.00
0.0100 OH Mandor 81,000.00 810.00
0.0500 Paket Alat Bantu 50,000.00 2,500.00
102,000.00 18,310.00 120,310.00

C. PEKERJAAN PONDASI

KODE HARGA HARGA JUMLAH


INDEKS SATUAN URAIAN
ANALISA SATUAN (Rp) BAHAN (Rp) UPAH (Rp) HARGA (Rp)
C6 PASANGAN BATU GUNUNG 1 Pc : 4 Ps

1.2000 M3 Batu Gunung 280,250.00 336,300.00


4.0720 Zak Semen Pc 46,000.00 187,312.00
0.5220 M3 Pasir Pasangan 162,000.00 84,564.00
0.0750 OH Tukang 70,000.00 5,250.00
0.0800 OH Kepala Tukang 76,000.00 6,080.00
2.6000 OH Pekerja 50,000.00 130,000.00
0.1300 OH Mandor 81,000.00 10,530.00
0.2000 Paket Alat Bantu 50,000.00 10,000.00
608,176.00 161,860.00 770,036.00

G. PEKERJAAN BETON

KODE HARGA HARGA JUMLAH


INDEKS SATUAN URAIAN
ANALISA SATUAN (Rp) BAHAN (Rp) UPAH (Rp) HARGA (Rp)
GI 1 M3 BETON COR BATU PALU CAMP 1 : 3 : 5

5.6650 Zak Semen Pc 46,000.00 260,590.00


0.5440 M3 Pasir Pasangan 162,000.00 88,128.00
0.9700 M3 Koral Palu 378,000.00 366,660.00
0.3300 OH Tukang 70,000.00 23,100.00
0.0330 OH Kepala Tukang 76,000.00 2,508.00
3.5000 OH Pekerja 50,000.00 175,000.00
0.1800 OH Mandor 81,000.00 14,580.00
1.0000 Paket Alat Bantu 50,000.00 50,000.00
715,378.00 265,188.00 980,566.00
G 1.1 1 M3 BETON COR BATU LONG IRAM CAMP 1 : 3 : 5

5.6650 Zak Semen Pc 46,000.00 260,590.00


0.5440 M3 Pasir Pasangan 162,000.00 88,128.00
0.9700 M3 Koral Long Iram 250,000.00 242,500.00
1.0000 Upah diambil sama dengan G 1 265,188.00 265,188.00

591,218.00 265,188.00 856,406.00

E. PEKERJAAN PLESTERAN

KODE HARGA HARGA JUMLAH


INDEKS SATUAN URAIAN
ANALISA SATUAN (Rp) BAHAN (Rp) UPAH (Rp) HARGA (Rp)
E1 1 M2 PLESTERAN DINDINGAN 1 Pc : I Ps Tebal 1 Cm

0.2780 Zak Semen Pc 46,000.00 12,788.00


0.0080 M3 Pasir Pasangan 162,000.00 1,296.00
0.1500 OH Tukang 70,000.00 10,500.00
0.0150 OH Kepala Tukang 76,000.00 1,140.00
0.4000 OH Pekerja 50,000.00 20,000.00
0.0300 OH Mandor 81,000.00 2,430.00

14,084.00 34,070.00 48,154.00


E3 1 M2 PLESTERAN DINDINGAN 1 Pc : 3 Ps Tebal 1 Cm

0.1500 Zak Semen Pc 46,000.00 6,900.00


0.0150 M3 Pasir Pasangan 162,000.00 2,430.00
1.0000 Upah diambil sama dengan E 1 34,070.00 34,070.00

9,330.00 34,070.00 43,400.00


RENCANA ANGGARAN BIAYA ( RAB )

PROYEK : PROGRAM PEMBANGUNAN PEDESAAN KABUPATEN KUTAI KARTANEGARA


PEKERJAAN : PEMBUATAN PARIT RT I
LOKASI : KELURAHAN SANIPAH, KECAMATAN SAMBOJA

HARGA JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT
SATUAN HARGA

A PEKERJAAN PENDAHULUAN
1 Pengukuran Dan Pematokan 1.000 Ls 456,000.00 456,000.00
2 Papan Nama Proyek 1.000 Ls 350,000.00 350,000.00
3 Barak Kerja 1.000 Ls 750,000.00 750,000.00
3 Dokumentasi & Administrasi Proyek 1.000 Ls 650,000.00 650,000.00

JUMLAH 2,206,000.00
B PEKERJAAN PARIT PAS. BATU PANJANG 19,00 M
1 Pembersihan Lokasi 22.800 M2 1,205.00 27,474.00
2 Galian Tanah Parit 10.640 M3 37,430.00 398,255.20
3 Urugan Tanah Tebing 1.900 M3 37,430.00 71,117.00
4 Urugan Pasir Bawah Tbl 3,0 cm 0.285 M3 120,310.00 34,288.35
5 Pasangan Batu Gunung 10.830 M3 770,036.00 8,339,489.88
6 Cor Beton 1 : 3 : 4 (K-175) Tbl 5,0 cm 0.380 M3 856,406.00 325,434.28
7 Plesteran Dinding Parit 29.500 M2 43,400.00 1,280,300.00

JUMLAH 10,476,358.71
450,000.00
625,000.00
350,000.00
650,000.00

Panj Prt
19.00
Lbr Prt Rt-2

Dlm Prt Rt-2

Kurang :
-
REKAPITULASI

PROYEK : PROGRAM PEMBANGUNAN PEDESAAN KABUPATEN KUTAI KARTANEGARA


PEKERJAAN : PEMBUATAN PARIT RT I
LOKASI : KELURAHAN SANIPAH, KECAMATAN SAMBOJA

NO URAIAN PEKERJAAN JUMLAH HARGA

A PEKERJAAN PENDAHULUAN 2,206,000.00

B PEKERJAAN PARIT PAS. BATU PANJANG 19,00 M 10,476,358.71

JUMLAH 12,682,358.71
PPN 10% 1,268,235.87
JUMLAH 13,950,594.58
TOTAL ( pembulatan ) 13,950,000.00

TERBILANG : " TIGA BELAS JUTA SEMBILAN RATUS LIMA PULUH RIBU RUPIAH "

Mengetahui/Menyetujui Dibuat Oleh,


Pengguna Anggaran Pejabat Pelaksana Teknis Kegiatan Cluster I
Camat Samboja Kecamatan Samboja

( H. SAIFUDDIN HS, S.Sos. MM. ) ( REIN MULCO, S. Sos )


Nip. 080 091 315 NIP. 010 224 227