Anda di halaman 1dari 10

PEKERJAAN : PEMBANGUNAN COLD STORAGE PPI DOLAN POK POK KABUPATEN FAK FAK CURVA REALISASI PEKERJAAN

SATUAN KERJA : DIREKTORAT LOGISTIK


TAHUN ANGGARAN : 2018
LOKASI : KABUPATEN FAK FAK BULAN KE : I ( SATU )
WILAYAH : PAPUA BARAT MINGGU KE : 4 ( EMPAT )
WAKTU PELAKSANAAN : 92 (Sembilan Puluh Dua) Hari kalender PERIODE : 22 Oktober 2018 s/d 28 Oktober 2018
TANGGAL KONTRAK : 28 SEPTEMBER 2018 RENCANA : 9,024 %
KONTRAKTOR PELAKSANA : PT. KARYA BARONA GROUP REALISASI : 5,437 %
KONSULTAN SUPERVISI : CV. NUSANTARA CIPTA KONSULTANT DEVIASI : -3,587 %

WAKTU PELAKSANAAN 92 HARI KALENDER


BULAN KE-I BULAN KE-II BULAN KE-III
BOBOT
NO URAIAN PEKERJAAN JUMLAH HARAGA 1 2 3 4 5 6 7 8 9 10 11 12 13 KET
FISIK (%)
28/09/18 05/10/18 12/10/18 19/10/18 26/10/18 02/11/18 09/11/18 16/11/18 23/11/18 30/11/18 07/12/18 14/12/18 21/12/18
04/10/18 11/10/18 18/10/18 25/10/18 01/11/18 08/11/18 15/11/18 22/11/18 29/11/18 06/12/18 13/12/18 20/12/18 28/12/18

- 100 %
I PEKERJAAN PENDAHULUAN Rp 82.276.960,00 1,591 0,133 0,133 0,133 0,133 0,133 0,133 0,133 0,133 0,133 0,133 0,133 0,133

II PEKERJAAN GEDUNG
A PEKERJAAN STRUKTUR
- 90 %
a Pekerjaan Galian dan Urugan Rp 441.417.726,00 8,537 1,423 1,423 1,423 1,423 1,423 1,423
b Pekerjaan Pondasi Rp 457.713.636,88 8,852 1,475 1,475 1,475 1,475 1,475 1,475
c Pekerjaan Beton Rp 283.317.170,00 5,479 1,370 1,370 1,370 1,370 - 80 %
d Pekerjaan Baja Rp 57.319.689,31 1,109 0,370 0,370 0,370
e Pekerjaan Atap Rp 370.524.062,52 7,166 1,791 1,791 1,791 1,791
B PEKERJAAN ARSITEKTUR
a Pekerjaan Pasangan dan Plesteran Rp 65.839.104,00 1,273 0,318 0,318 0,318 0,318 - 70 %
b Pekerjaan Keramik Lantai dan Dinding Rp 17.250.825,00 0,334 0,111 0,111 0,111
c Pekerjaan Plafond Rp 5.790.300,00 0,112 0,037 0,037 0,037
d Pekerjaan Pengecatan Rp 84.551.350,00 1,635 0,818 0,818
e Pekerjaan Kosen Pintu dan Jendela Rp 34.400.000,00 0,665 0,222 0,222 0,222 - 60 %
f Pekerjaan Gutter L. 20 cm Rp 6.241.622,40 0,121 0,060 0,060
g Pekerjaan Sanitair Fixture Rp 87.146.800,00 1,685 0,843 0,843
h Pekerjaan Saluran Rp 85.624.253,00 1,656 0,414 0,414 0,414 0,414
i Pekerjaan ACP + Rangka Hollow galvanis Rp 194.478.210,50 3,761 1,881 1,881 - 50 %

III PEKERJAAN SARANA DAN PRASARANA


a Pekerjaan Halaman Rp 70.859.608,00 1,370 0,228 0,228 0,228 0,228 0,228 0,228
b Pekerjaan Beton Duiker Rp 85.127.271,40 1,646 0,549 0,549 0,549
- 40 %

IV PEKERJAAN SISTEM PENDINGIN


A PANEL INSULASI Rp 766.450.200,00 14,823 2,471 2,471 2,471 2,471 2,471 2,471 - 30 %
B PINTU DAN ACCESSORIS Rp 377.450.000,00 7,300 2,433 2,433 2,433
C MESIN PENDINGIN DAN ACCESSORIS Rp 1.093.000.000,00 21,139 3,523 3,523 3,523 3,523 3,523 3,523

V PEKERJAAN MEKANIKAL DAN ELEKTRIKAL - 20 %


A PEKERJAAN MEKANIKAL
a.1 Pekerjaan Plambing Rp 267.425.000,00 5,172 0,081 0,081 1,250 1,250 1,250 1,261
a.2 Pekerjaan AC Rp 14.390.000,00 0,278 0,139 0,139
a.3 Pekerjaan Alat Pemadam Api Ringan (APAR) Rp 4.500.000,00 0,087 0,044 0,044
- 10 %
B PEKERJAAN ELEKTRIKAL
b.1 Pekerjaan Instalasi Listrik Rp 185.500.000,00 3,588 0,168 0,168 1,150 1,150 0,951
b.2 Pekerjaan Penangkal Petir Rp 32.060.000,00 0,620 0,310 0,310
- 0%

J U M L A H T O T A L Rp 5.170.653.789,01 100,00 0,213 1,804 3,199 3,808 5,592 6,280 14,988 15,046 17,762 16,623 8,559 6,126 0,000

RENCANA PROGRES FISIK MINGGUAN (%) - 0,213 2,017 5,216 9,024 14,616 20,896 35,884 50,930 68,692 85,31 93,87 100,00 100,00
SKALA
REALISASI PROGRES FISIK MINGGUAN (%) - 0,000 1,489 4,101 5,437

DEVIASI (%) -0,213 -0,529 -1,115 -3,587


PEKERJAAN : PEMBANGUNAN COLD STORAGE PPI DOLAN POK POK KABUPATEN FAK FAK
SATUAN KERJA : DIREKTORAT LOGISTIK
PROGRES REALISASI MINGGUAN
TAHUN ANGGARAN : 2018
LOKASI : KABUPATEN FAK FAK BULAN KE : I ( SATU )
WILAYAH : PAPUA BARAT MINGGU KE : 4 ( EMPAT )
WAKTU PELAKSANAAN : 92 (Sembilan Puluh Dua) Hari kalender PERIODE : 22 Oktober 2018 s/d 28 Oktober 2018
TANGGAL KONTRAK : 28 SEPTEMBER 2018 RENCANA : 9,024 %
KONTRAKTOR PELAKSANA : PT. KARYA BARONA GROUP REALISASI : 5,437 %
KONSULTAN SUPERVISI : CV. NUSANTARA CIPTA KONSULTANT DEVIASI : -3,587 %

VOLUME MINGGU LALU MINGGU INI S/D MINGGU INI


BOBOT Presentase
NO URAIAN PEKERJAAN Sat. Bobot
KONTRAK MC-0 (%) Volume Volume Bobot (%) Volume Bobot (%) (%)
(%)

I PEKERJAAN PENDAHULUAN
1 Papan Nama Proyek ( Banner ) Ls 1,00 1,00 0,008 - - 1,00 0,008 1,00 0,008 100%
2 Air kerja Ls 1,00 1,00 0,116 - - - - - 0%
3 Listrik kerja Ls 1,00 1,00 0,232 - - 1,00 0,232 1,00 0,232 100%
4 Bedeng pekerja dengan lantai plesteran + sarana MCK m2 23,04 23,04 0,360 23,04 0,360 - 23,04 0,360 100%
5 Gudang bahan dengan lantai plesteran m2 25,92 25,92 0,405 25,92 0,405 - 25,92 0,405 100%
6 Direksi Keet dengan lantai plesteran ( termasuk meja kerja, meja rapat, AC split 1 PK dan
m2 MCK ) 17,28 17,28 0,469 17,28 0,469 - 17,28 0,469 100%

II PEKERJAAN GEDUNG
A PEKERJAAN STRUKTUR
a Pekerjaan Galian dan Urugan
1 Pengukuran dan bouwplank m' 80,00 80,00 0,136 80,00 0,136 - 80,00 0,136 100%
2 Galian tanah pondasi
2,1 Pondasi Plat Setempat Type P. 1 Uk. 120x120x30 cm m3 19,60 19,60 0,036 19,60 0,036 - 19,60 0,036 100%
2,2 Pondasi Plat Setempat Type P. 2 Uk. 80x80x30 cm m3 12,00 12,00 0,022 12,00 0,022 - 12,00 0,022 100%
2,3 Pondasi Tie Beam Type TB. 1 Uk. 20x40 cm m3 40,00 40,00 0,073 40,00 0,073 - 40,00 0,073 100%
3 Urugan pasir bawah pondasi dan lantai
3,1 Urugan pasir bawah pondasi dan lantai T. 10 cm
3.1.1 Pondasi Plat Setempat Type P. 1 Uk. 120x120x30 cm m3 1,96 1,96 0,034 - - - - - 0%
3.1.2 Pondasi Plat Setempat Type P. 2 Uk. 80x80x30 cm m3 1,20 1,20 0,021 - - - - - 0%
3.1.3 Pondasi Tie Beam Type TB. 1 Uk. 20x40 cm m3 4,00 4,00 0,070 - - - - - 0%
3.1.4 Plat Lantai Tulangan Susut m3 18,15 18,15 0,316 - - - - - 0%
3,2 Urugan pasir bawah lantai T. 20 cm
3.2.1 Cold storage 30 Ton m3 10,80 10,80 0,188 - - - - - 0%
3.2.2 ABF m3 4,00 4,00 0,070 - - - - - 0%
4 Urugan tanah kembali bekas galian pondasi m3 71,60 71,60 0,036 - - - - - 0%
5 Lantai kerja bawah pondasi dan lantai Tulangan Susut T. 5 cm ad. 1:3:5
5,1 Pondasi Plat Setempat Type P. 1 Uk. 120x120x30 cm m3 0,98 0,98 0,088 - - - - - 0%
5,2 Pondasi Plat Setempat Type P. 2 Uk. 80x80x30 cm m3 0,60 0,60 0,054 - - - - - 0%
5,3 Pondasi Tie Beam Type TB. 1 Uk. 20x40 cm m3 2,00 2,00 0,179 - - - - - 0%
6 Urugan tanah peninggian Peil Lantai 0.00 m3 164,85 164,85 1,613 - - - - - 0%
7 Pekerjaan Pemasangan Pipa Vent PVC dia. 4" Perforated lapis ijuk / karung goni
7,1 Ruang ABF m' 69,00 69,00 0,093 - - - - - 0%
7,2 Accessoris ( Fitting ) ls 1,00 1,00 0,029 - - - - - 0%
8 Urugan tanah peninggianLahan T. 100 cm m3 560,00 560,00 5,480 - - 112,00 1,096 112,00 1,096 20%

b Pekerjaan Pondasi
1 Cerucuk Dolken dia. 10-15 cm P. 2-3 m
1,1 Pondasi Plat Setempat Type P. 1 Uk. 120x120x30 cm titik 90,00 90,00 0,098 45,00 0,049 - 45,00 0,049 50%
1,2 Pondasi Plat Setempat Type P. 2 Uk. 80x80x30 cm titik 48,00 48,00 0,052 24,00 0,026 - 24,00 0,026 50%
1,3 Pondasi Tie Beam Type TB. 1 Uk. 20x40 cm titik 77,00 77,00 0,084 38,50 0,042 - 38,50 0,042 50%
2 Beton Pondasi Plat Setempat
2,1 Pondasi Plat Setempat Type P. 1 Uk. 120x120x30 cm
2.1.1 Besi beton U. 39 BJTD 39 Kg 466,82 466,82 0,231 - - - - - 0%
2.1.2 Beton K. 250 m3 3,81 3,81 0,374 - - - - - 0%
2.1.3 Bekesting pasangan dinding 1/2 bata ad. 1 : 4 m2 16,80 16,80 0,149 - - - - - 0%
2,2 Pondasi Plat Setempat Type P. 2 Uk. 80x80x30 cm
2.2.1 Besi beton U. 39 BJTD 39 Kg 345,11 345,11 0,171 - - - - - 0%
2.2.2 Beton K. 250 m3 2,09 2,09 0,205 - - - - - 0%
2.2.3 Bekesting pasangan dinding 1/2 bata ad. 1 : 4 m2 17,28 17,28 0,153 - - - - - 0%
3 Pondasi Tie Beam
3,1 Pondasi Tie Beam Type TB. 1 Uk. 20x40 cm
3.1.1 Arah Horizontal
a.1 AS 1
a.1.1 Besi beton U. 39 BJTD 39 Kg 130,12 130,12 0,064 - - - - - 0%
a.1.2 Besi beton U. 24 BJTP 24 Kg 26,45 26,45 0,013 - - - - - 0%
a.1.3 Beton K. 250 m3 0,91 0,91 0,089 - - - - - 0%
a.1.4 Bekesting pasangan dinding 1/2 bata ad. 1 : 4 m2 11,52 11,52 0,102 - - - - - 0%
a.2 AS 2
a.2.1 Besi beton U. 39 BJTD 39 Kg 130,12 130,12 0,064 - - - - - 0%
a.2.2 Besi beton U. 24 BJTP 24 Kg 26,45 26,45 0,013 - - - - - 0%
a.2.3 Beton K. 250 m3 0,97 0,97 0,095 - - - - - 0%
a.2.4 Bekesting pasangan dinding 1/2 bata ad. 1 : 4 m2 11,52 11,52 0,102 - - - - - 0%
a.3 AS 3
a.3.1 Besi beton U. 39 BJTD 39 Kg 130,12 130,12 0,064 - - - - - 0%
a.3.2 Besi beton U. 24 BJTP 24 Kg 26,45 26,45 0,013 - - - - - 0%
a.3.3 Beton K. 250 m3 1,01 1,01 0,099 - - - - - 0%
a.3.4 Bekesting pasangan dinding 1/2 bata ad. 1 : 4 m2 11,52 11,52 0,102 - - - - - 0%
a.4 AS 4
a.4.1 Besi beton U. 39 BJTD 39 Kg 130,12 130,12 0,064 - - - - - 0%
a.4.2 Besi beton U. 24 BJTP 24 Kg 26,45 26,45 0,013 - - - - - 0%
a.4.3 Beton K. 250 m3 0,86 0,86 0,085 - - - - - 0%
a.4.4 Bekesting pasangan dinding 1/2 bata ad. 1 : 4 m2 11,52 11,52 0,102 - - - - - 0%
3.1.2 Arah Vertikal
b.1 AS A
b.1.1 Besi beton U. 39 BJTD 39 Kg 138,46 138,46 0,069 - - - - - 0%
b.1.2 Besi beton U. 24 BJTP 24 Kg 22,41 22,41 0,011 - - - - - 0%
b.1.3 Beton K. 250 m3 0,96 0,96 0,094 - - - - - 0%
b.1.4 Bekesting pasangan dinding 1/2 bata ad. 1 : 4 m2 12,32 12,32 0,109 - - - - - 0%
b.2 AS C'
b.2.1 Besi beton U. 39 BJTD 39 Kg 138,46 138,46 0,069 - - - - - 0%
b.2.2 Besi beton U. 24 BJTP 24 Kg 22,41 22,41 0,011 - - - - - 0%
b.2.3 Beton K. 250 m3 1,09 1,09 0,107 - - - - - 0%
b.2.4 Bekesting pasangan dinding 1/2 bata ad. 1 : 4 m2 12,32 12,32 0,109 - - - - - 0%
b.3 AS E
b.3.1 Besi beton U. 39 BJTD 39 Kg 138,46 138,46 0,069 - - - - - 0%
b.3.2 Besi beton U. 24 BJTP 24 Kg 22,41 22,41 0,011 - - - - - 0%
b.3.3 Beton K. 250 m3 1,00 1,00 0,098 - - - - - 0%
b.3.4 Bekesting pasangan dinding 1/2 bata ad. 1 : 4 m2 12,32 12,32 0,109 - - - - - 0%
VOLUME MINGGU LALU MINGGU INI S/D MINGGU INI
BOBOT Presentase
NO URAIAN PEKERJAAN Sat. Bobot
KONTRAK MC-0 (%) Volume Volume Bobot (%) Volume Bobot (%) (%)
(%)
4 Beton kolom di bawah 0.00 ( ELV. -2.85 s/d -0.05 )
4,1 Kolom Type K. 1 Uk. 30x40 cm
4.1.1 Besi beton U. 39 BJTD 39 Kg 458,05 458,05 0,227 - - - - - 0%
4.1.2 Besi beton U. 24 BJTP 24 Kg 34,74 34,74 0,017 - - - - - 0%
4.1.3 Bekisting multiplek T. 9 mm rangka kaso 5/7 cm m2 18,90 18,90 0,087 - - - - - 0%
4.1.4 Beton K. 250 m3 1,62 1,62 0,159 - - - - - 0%
4,2 Kolom Type K. 2 Uk. 25x35 cm
4.2.1 Besi beton U. 39 BJTD 39 Kg 530,97 530,97 0,263 - - - - - 0%
4.2.2 Besi beton U. 24 BJTP 24 Kg 35,27 35,27 0,017 - - - - - 0%
4.2.3 Bekisting multiplek T. 9 mm rangka kaso 5/7 cm m2 19,44 19,44 0,089 - - - - - 0%
4.2.4 Beton K. 250 m3 1,42 1,42 0,139 - - - - - 0%
5 Pasangan dinding 1 bata ad. 1 : 4 bawah 0.00 m2 114,27 114,27 2,087 - - - - - 0%
6 Plesteran dinding bata ad. 1 : 4 ( 1 sisi ) bagian luar m2 65,00 65,00 0,205 - - - - - 0%
7 Beton pondasi Sloof
7,1 Beton pondasi Sloof Type SL. 1 Uk. 25x20 cm
7.1.1 Besi beton U. 39 BJTD 39 Kg 556,77 556,77 0,276 - - - - - 0%
7.1.2 Besi beton U. 24 BJTP 24 Kg 198,76 198,76 0,098 - - - - - 0%
7.1.3 Beton K. 250 m3 4,50 4,50 0,442 - - - - - 0%
7.1.4 Bekisting multiplek T. 9 mm rangka kaso 5/7 cm m2 18,80 18,80 0,086 - - - - - 0%
7,2 Beton pondasi Sloof Type SL. 2 Uk. 25x20 cm
7.2.1 Besi beton U. 24 BJTP 24 Kg 202,31 202,31 0,100 - - - - - 0%
7.2.2 Besi beton U. 24 BJTP 24 Kg 119,13 119,13 0,059 - - - - - 0%
7.2.3 Beton K. 250 m3 2,83 2,83 0,277 - - - - - 0%
7.2.4 Bekisting multiplek T. 9 mm rangka kaso 5/7 cm m2 22,60 22,60 0,104 - - - - - 0%
8 Beton pondasi mesin Refrigerasi dan Genset T. 20 cm
8,1 Pondasi Mesin Refrigerasi
8.1.1 Besi beton U. 39 BJTD 39 Kg 508,08 508,08 0,252 - - - - - 0%
8.1.2 Beton K. 250 m3 3,20 3,20 0,314 - - - - - 0%
8.1.3 Bekisting multiplek T. 9 mm rangka kaso 5/7 cm m2 4,00 4,00 0,018 - - - - - 0%
8,2 Pondasi Mesin Genset -
8.2.1 Besi beton U. 39 BJTD 39 Kg 62,94 62,94 0,031 - - - - - 0%
8.2.2 Beton K. 250 m3 0,32 0,32 0,031 - - - - - 0%
8.2.3 Bekisting multiplek T. 9 mm rangka kaso 5/7 cm m2 1,12 1,12 0,005 - - - - - 0%

c Pekerjaan Beton
1 Beton kolom Pedestal T. 100 cm
1,1 Kolom Type K. 1 Uk. 30x40 cm
1.1.1 Besi beton U. 39 BJTD 39 Kg 186,96 186,96 0,093 - - - - - 0%
1.1.2 Besi beton U. 24 BJTP 24 Kg 17,37 17,37 0,009 - - - - - 0%
1.1.3 Bekisting multiplek T. 9 mm rangka kaso 5/7 cm m2 14,00 14,00 0,064 - - - - - 0%
1.1.4 Beton K. 250 m3 1,20 1,20 0,118 - - - - - 0%
1,2 Kolom Type K. 2 Uk. 25x35 cm
1.2.1 Besi beton U. 39 BJTD 39 Kg 112,18 112,18 0,056 - - - - - 0%
1.2.2 Besi beton U. 24 BJTP 24 Kg 8,82 8,82 0,004 - - - - - 0%
1.2.3 Bekisting multiplek T. 9 mm rangka kaso 5/7 cm m2 7,20 7,20 0,033 - - - - - 0%
1.2.4 Beton K. 250 m3 0,53 0,53 0,052 - - - - - 0%
2 Beton Kolom Praktis Type KP 13x13 cm
2,1 Besi U 24 ( Tulangan Pokok ) Kg 117,74 117,74 0,058 - - - - - 0%
2,2 Besi U 24 ( Sengkang ) Kg 43,45 43,45 0,022 - - - - - 0%
2,3 Bekisting multiplek T. 9 mm rangka kaso 5/7 cm m2 17,16 17,16 0,079 - - - - - 0%
2,4 Beton K. 175 m3 0,56 0,56 0,053 - - - - - 0%
3 Beton Ring Balk 15x20 cm
3,1 Besi U 24 ( Tulangan Pokok ) Kg 67,79 67,79 0,034 - - - - - 0%
3,2 Besi U 24 ( Sengkang ) Kg 28,89 28,89 0,014 - - - - - 0%
3,3 Bekisting multiplek T. 9 mm rangka kaso 5/7 cm m2 7,60 7,60 0,036 - - - - - 0%
3,4 Beton K. 175 m3 0,57 0,57 0,055 - - - - - 0%
4 Plat Lantai Beton
4,1 Plat Lantai Beton T. 15 cm ( Cold Storage dan ABF )
4.1.1 Besi Wiremesh M8 ( 2 lapis ) Lembar 15,00 15,00 0,270 - - - - - 0%
4.1.2 Beton K. 250 m3 11,10 11,10 1,089 - - - - - 0%
4,2 Plat Lantai Beton T. 10 cm ( Ruangan )
4.2.1 Besi Wiremesh M8 ( 1 lapis ) Lembar 15,00 15,00 0,270 - - - - - 0%
4.2.2 Besi Wiremesh M8 ( 2 lapis ) Lembar 15,00 15,00 0,270 - - - - - 0%
4.2.3 Beton K. 250 m3 22,00 22,00 2,159 - - - - - 0%
4,3 Plat Lantai Beton T. 10 cm ( Loading Dok, Ram dan Teras )
4.3.1 Besi Wiremesh M8 ( 1 lapis ) Lembar 5,00 5,00 0,090 - - - - - 0%
4.3.2 Beton K. 250 m3 4,95 4,95 0,486 - - - - - 0%
5 Plat Dinding Beton T. 10 cm
5,1 Area Cold Storage
5.1.1 Bekisting multiplek T. 9 mm rangka kaso 5/7 cm m2 2,70 2,70 0,016 - - - - - 0%
5.1.2 Beton K. 250 m2 0,27 0,27 0,026 - - - - - 0%
5,2 Area ABF
5.2.1 Bekisting multiplek T. 9 mm rangka kaso 5/7 cm m2 1,65 1,65 0,010 - - - - - 0%
5.2.2 Beton K. 250 m3 0,17 0,17 0,016 - - - - - 0%

d Pekerjaan Baja
1 Angkur baut HTB
1,1 Angkur baut HTB dia. 19 mm bh 40,00 40,00 0,029 12,00 0,009 - 12,00 0,009 30%
1,2 Angkur baut HTB dia. 16 mm bh 24,00 24,00 0,015 7,20 0,004 - 7,20 0,004 30%
2 Base plat baja # 16 mm + zingkromat
2,1 Kolom K. 1 WF. 250.125.6.9 Kg 58,28 58,28 0,035 17,48 0,011 - 17,48 0,011 30%
2,2 Kolom K. 2 WF. 200.100.5.8 Kg 24,28 24,28 0,015 7,29 0,004 - 7,29 0,004 30%
3 Stiff plat baja # 10 mm + zingkromat
3,1 Kolom K. 1 WF. 250.125.6.9 Kg 60,76 60,76 0,037 18,23 0,011 - 18,23 0,011 30%
3,2 Kolom K. 2 WF. 200.100.5.8 Kg 0,39 0,39 0,000 0,12 0,000 - 0,12 0,000 30%
4 Kolom Baja + zingkromat
4,1 Kolom K. 1 WF. 250.125.6.9 Kg 888,00 888,00 0,536 266,40 0,161 - 266,40 0,161 30%
4,2 Kolom K. 2 WF. 200.100.5.8 Kg 571,73 571,73 0,345 171,52 0,103 - 171,52 0,103 30%
5 Stiff plat baja # 10 mm + zingkromat
5,1 Kolom K. 1 WF. 250.125.6.9 Kg 121,51 121,51 0,073 36,45 0,022 - 36,45 0,022 30%
5,2 Kolom K. 2 WF. 200.100.5.8 Kg 38,88 38,88 0,023 11,67 0,007 - 11,67 0,007 30%

e Pekerjaan Atap
1 Kuda - kuda baja + zingkromat
1,1 Kuda - kuda baja R. 1
1.1.1 Kuda - kuda baja R. 1 WF.250.125.6.9 Kg 970,88 970,88 0,586 291,26 0,176 - 291,26 0,176 30%
1.1.2 Vute baja R. 1 WF. 250.125.6.9 Kg 71,04 71,04 0,043 21,31 0,013 - 21,31 0,013 30%
1.1.3 Stiff plat baja # 10 mm + zingkromat Kg 182,27 182,27 0,110 54,68 0,033 - 54,68 0,033 30%
1.1.4 Mur baut HTB dia. 19 mm bh 60,00 60,00 0,012 18,00 0,003 - 18,00 0,003 30%
1,2 Kuda - kuda baja R. 2
1.2.1 Kuda - kuda baja R. 2 WF.250.125.6.9 Kg 1.456,32 1.456,32 0,879 436,90 0,264 - 436,90 0,264 30%
1.2.2 Vute baja R. 2 WF. 250.125.6.9 Kg 106,56 106,56 0,064 31,97 0,019 - 31,97 0,019 30%
1.2.3 Stiff plat baja # 10 mm + zingkromat Kg 192,39 192,39 0,116 57,72 0,035 - 57,72 0,035 30%
1.2.4 Mur baut HTB dia. 19 mm bh 108,00 108,00 0,021 32,40 0,006 - 32,40 0,006 30%
VOLUME MINGGU LALU MINGGU INI S/D MINGGU INI
BOBOT Presentase
NO URAIAN PEKERJAAN Sat. Bobot
KONTRAK MC-0 (%) Volume Volume Bobot (%) Volume Bobot (%) (%)
(%)
1,3 Kuda - kuda baja R. 3 - - -
1.3.1
Kuda - kuda baja R. 3 WF. 150.75.5.7 Kg 532,00 532,00 0,321 159,60 0,096 - 159,60 0,096 30%
1.3.2
Vute baja R. 3 WF. 150.75.5.7 Kg 84,00 84,00 0,051 25,20 0,015 - 25,20 0,015 30%
1.3.3
Stiff plat baja # 10 mm + zingkromat Kg 54,68 54,68 0,033 16,40 0,010 - 16,40 0,010 30%
1.3.4
Mur baut HTB dia. 16 mm bh 256,00 256,00 0,030 76,80 0,009 - 76,80 0,009 30%
1.3.5
Rangka listplank CNP. 100.50.20.2,3 Kg 702,72 702,72 0,424 210,82 0,127 - 210,82 0,127 30%
1.3.6
Listpank spandek T. 0,35 mm m2 51,20 51,20 0,181 15,36 0,054 - 15,36 0,054 30%
1.3.7
Talang zingkalume plat T. 0,4 mm rangka hollow 40x40x4 cm m' 32,00 32,00 0,155 9,60 0,047 - 9,60 0,047 30%
2 Balok baja + zingkromat
2,1 Balok Sokong baja S. 1
2.1.1 Balok Sokong baja S. 1 WF. 200.100.5.8 Kg 1.024,00 1.024,00 0,618 307,20 0,185 - 307,20 0,185 30%
2.1.2 Stiff plat baja # 10 mm + zingkromat Kg 25,92 25,92 0,016 7,78 0,005 - 7,78 0,005 30%
2.1.3 Mur baut HTB dia. 19 mm bh 96,00 96,00 0,019 28,80 0,006 - 28,80 0,006 30%
3 Gording baja + zingkromat
3,1 Gording baja CNP. 150.50.20.3,2 Kg 1.948,80 1.948,80 1,176 584,64 0,353 - 584,64 0,353 30%
3,2 Stiff plat baja # 10 mm + zingkromat Kg 164,04 164,04 0,099 49,21 0,030 - 49,21 0,030 30%
3,3 Mur baut HTB dia. 12 mm bh 360,00 360,00 0,021 108,00 0,006 - 108,00 0,006 30%
4 Bracing besi dia. 19 mm + zingkromat Kg 89,00 89,00 0,044 26,70 0,013 - 26,70 0,013 30%
5 Trekstang besi dia. 10 mm + zingkromat Kg 78,98 78,98 0,039 23,69 0,012 - 23,69 0,012 30%
6 Hanger batang tarik + zingkromat
6,1 Hanger batang tarik besi siku L. 80x80x8 Kg 506,19 506,19 0,305 151,86 0,092 - 151,86 0,092 30%
6,2 Stiff plat baja # 10 mm + zingkromat Kg 21,87 21,87 0,013 6,56 0,004 - 6,56 0,004 30%
6,3 Mur baut HTB dia. 12 mm bh 72,00 72,00 0,004 21,60 0,001 - 21,60 0,001 30%
7 Dinding spandek T. 0,35 mm
7,1 Rangka dinding spandek CNP. 100.50.20.2,3 Kg 235,87 235,87 0,142 70,76 0,043 - 70,76 0,043 30%
7,2 Dinding spandek T. 0,35 mm m2 175,50 175,50 0,621 52,65 0,186 - 52,65 0,186 30%
8 Atap spandek T. 0,35 mm m2 272,00 272,00 0,963 81,60 0,289 - 81,60 0,289 30%
9 Nok atap spandek T. 0,35 mm m' 16,00 16,00 0,061 4,80 0,018 - 4,80 0,018 30%

B PEKERJAAN ARSITEKTUR
a Pekerjaan Pasangan dan Plesteran
1 Pasangan dinding 1/2 bata ad. 1 : 4
1,1 Pasangan dinding 1/2 bata ad. 1 : 4 T. 300 cm m2 61,96 61,96 0,549 - - - - - 0%
1,2 Pasangan dinding 1/2 bata ad. 1 : 4 T. 100 cm m2 11,00 11,00 0,097 - - - - - 0%
2 Plesteran dinding ad. 1 : 4 m2 145,92 145,92 0,459 - - - - - 0%
3 Acian m2 145,92 145,92 0,168 - - - - - 0%

b Pekerjaan Keramik Lantai dan Dinding


1 Keramik lantai 40x40 cm Polished
1,1 Kantor pengelola m2 9,75 9,75 0,068 - - - - - 0%
2 Keramik lantai 20x20 cm Unpolished
2,1 Toilet Kantor m2 2,25 2,25 0,013 - - - - - 0%
2,2 Toilet Pria m2 4,50 4,50 0,026 - - - - - 0%
2,3 Toilet wanita m2 4,50 4,50 0,026 - - - - - 0%
3 Keramik Dinding 20x25 cm Polished
3,1 Toilet pria m2 15,00 15,00 0,100 - - - - - 0%
3,2 Toilet wanita m2 15,00 15,00 0,100 - - - - - 0%

c Pekerjaan Plafond
1 Pasang Plafond Gypsumb T. 9 mm + rangka hollow 4x4 cm dan 2x4 cm
1,1 Pasang rangka hollow galvanis 4x4 cm dan 2x4 cm T. 0,35 mm
1.1.1 Toilet Pria m2 4,50 4,50 0,006 - - - - - 0%
1.1.2 Toilet wanita m2 4,50 4,50 0,006 - - - - - 0%
1.1.3 Selasar m2 6,00 6,00 0,008 - - - - - 0%
1,2 Pasang plafond gypsumb T. 9 mm
1.2.1 Toilet Pria m2 4,50 4,50 0,021 - - - - - 0%
1.2.2 Toilet wanita m2 4,50 4,50 0,021 - - - - - 0%
1.2.3 Selasar m2 6,00 6,00 0,028 - - - - - 0%
2 Pasang list profil gypsumb T. 8 cm
2,1 Toilet Pria m' 9,00 9,00 0,007 - - - - - 0%
2,2 Toilet wanita m' 9,00 9,00 0,007 - - - - - 0%
2,3 Selasar m' 11,00 11,00 0,008 - - - - - 0%

d Pekerjaan Pengecatan
1 Cat dinding setara Weathershield ICI
1,1 Cat dinding keliling bagian luar bawah lantai 0.00 m2 49,30 49,30 0,090 - - - - - 0%
1,2 Cat dinding keliling bagian luar atas lantai 0.00 m2 47,00 47,00 0,085 - - - - - 0%
1,3 Cat dinding keliling bagian dalam ruangan
1.3.1 Ruang Mesin m2 6,00 6,00 0,011 - - - - - 0%
1.3.2 Ruang Genset m2 9,00 9,00 0,016 - - - - - 0%
2 Cat lantai Epoxy PU - Crete 6000 micron ( ruang dingin )
2,1 Ruang Cold Storage ( Bagian dalam ) m2 54,00 54,00 0,704 - - - - - 0%
2,2 Ruang ABF ( Bagian dalam ) m2 20,00 20,00 0,261 - - - - - 0%
3 Cat lantai Epoxy 500 micron (ruang proses)
3,1 Ruang Receiving m2 10,50 10,50 0,037 - - - - - 0%
3,2 Ruang Dry Storage m2 10,50 10,50 0,037 - - - - - 0%
3,3 Ruang Loading Room m2 10,50 10,50 0,037 - - - - - 0%
3,4 Ruang Packing m2 18,00 18,00 0,064 - - - - - 0%
3,5 Ruang Handling m2 24,00 24,00 0,085 - - - - - 0%
3,6 Female Locker m2 5,00 5,00 0,018 - - - - - 0%
3,7 Male Locker m2 5,00 5,00 0,018 - - - - - 0%
3,8 Selasar m2 6,00 6,00 0,021 - - - - - 0%
3,9 Saluran Gutter m2 5,40 5,40 0,019 - - - - - 0%
3,1 Bak cuci kaki m2 7,60 7,60 0,027 - - - - - 0%
4 Acian finishing lantai
4,1 Teras Unloading m2 16,50 16,50 0,019 - - - - - 0%
4,2 Teras belakang m2 16,00 16,00 0,018 - - - - - 0%
4,3 Teras samping m2 16,00 16,00 0,018 - - - - - 0%
4,4 Ruang Mesin m2 28,00 28,00 0,032 - - - - - 0%
4,5 Ruang Genset m2 6,00 6,00 0,007 - - - - - 0%
5 Pengecatan plafond emulsion m2 15,00 15,00 0,008 - - - - - 0%

e Pekerjaan Kosen Pintu dan Jendela


1 Ruang Kantor Pengelola
1,1 Kosen Bouvenligth Type BV. 1 Unit 1,00 1,00 0,008 - - - - - 0%
1.1.1 Kosen profil allumunium 4" CA / Natural
1.1.2 Kaca Es T. 5 mm
1.1.3 Sealent
20 Ruang Mesin
2,1 Kosen Pintu Tralis Type TR. 1 Unit 1,00 1,00 0,162 - - - - - 0%
2.1.1 Kosen profil allumunium 4" CA / Natural
2.1.2 Frame daun Pintu allumunium 4" CA / Natural
2.1.3 Daun Pintu louver blade plat allumunium E CA / Natural
2.1.4 Tralis louver blade plat allumunium E CA / Natural
2.1.5 Engsel pintu 4"
2.1.6 Kunci pintu
VOLUME MINGGU LALU MINGGU INI S/D MINGGU INI
BOBOT Presentase
NO URAIAN PEKERJAAN Sat. Bobot
KONTRAK MC-0 (%) Volume Volume Bobot (%) Volume Bobot (%) (%)
(%)
3 Ruang Genset
3,1 Kosen Pintu Tralis Type TR. 2 Unit 1,00 1,00 0,162 - - - - - 0%
3.1.1 Kosen profil allumunium 4" CA / Natural
3.1.2 Frame daun Pintu allumunium 4" CA / Natural
3.1.3 Daun Pintu louver blade plat allumunium E CA / Natural
3.1.4 Tralis louver blade plat allumunium E CA / Natural
3.1.5 Engsel pintu 4"
3.1.6 Kunci pintu
4 Toilet Pria dan Wanita
4,1 Kosen Pintu Type P. 4 Unit 2,00 2,00 0,155 - - - - - 0%
4.1.1 Kosen profil allumunium 4" CA / Natural
4.1.2 Frame daun Pintu allumunium 4" CA / Natural
4.1.3 Daun Pintu louver blade plat allumunium E CA / Natural
4.1.4 Tralis louver blade plat allumunium E CA / Natural
4.1.5 Engsel pintu 4"
4.1.6 Kunci pintu
4,2 Kosen Pintu Type P. 7 Unit 2,00 2,00 0,155 - - - - - 0%
4.2.1 Kosen profil allumunium 4" CA / Natural
4.2.2 Frame daun Pintu allumunium 4" CA / Natural
4.2.3 Daun pintu Allumunium Composite Panel
4.2.4 Engsel pintu 4"
4.2.5 Kunci pintu
4,3 Kosen Bouvenligth Type BV. 1 Unit 3,00 3,00 0,023 - - - - - 0%
4.3.1 Kosen profil allumunium 4" CA / Natural
4.3.2 Kaca Es T. 5 mm
4.3.3 Sealent

f Pekerjaan Gutter L. 20 cm
1 Beton Saluran K.300 t = 8Cm m3 0,43 0,43 0,042 - - - - - 0%
2 Penutup saluran plat stainless steel perforated m' 9,00 9,00 0,078 - - - - - 0%

g Pekerjaan Sanitair Fixture


1 Tempat Cuci Kaki Pria
1,1 Washtafel gantung TOTO LW248JT1 bh 2,00 2,00 0,031 - - - - - 0%
1,2 Kran sensor wall type Selectronic LUX DM American Standard bh 2,00 2,00 0,171 - - - - - 0%
1,3 Floor drain TOTO TX1BN bh 2,00 2,00 0,023 - - - - - 0%
1,4 Clean Out San - Ei HN58 4 Inch untuk bak cuci kaki bh 2,00 2,00 0,009 - - - - - 0%
1,5 Hand dryier TOTO Type TYC322W bh 2,00 2,00 0,370 - - - - - 0%
2 Tempat Cuci Kaki Wanita
2,1 Washtafel gantung TOTO LW248JT1 bh 2,00 2,00 0,031 - - - - - 0%
2,2 Kran sensor wall type Selectronic LUX DM American Standard bh 2,00 2,00 0,171 - - - - - 0%
2,3 Floor drain TOTO TX1BN bh 2,00 2,00 0,023 - - - - - 0%
2,4 Clean Out San - Ei HN58 4 Inch untuk bak cuci kaki bh 2,00 2,00 0,009 - - - - - 0%
2,5 Hand dryier TOTO Type TYC322W bh 2,00 2,00 0,370 - - - - - 0%
3 Kantor Pengelola
3,1 Washtafel gantung TOTO LW248JT1 lengkap accessoris bh 1,00 1,00 0,053 - - - - - 0%
3,2 Closet TOTO Type CW421/SW420J bh 1,00 1,00 0,074 - - - - - 0%
3,3 Jet washer TOTO THX20NB bh 1,00 1,00 0,008 - - - - - 0%
3,4 Floor drain TOTO TX1BN bh 1,00 1,00 0,011 - - - - - 0%
4 Toilet Karyawan
4,1 Toilet Pria
4.1.1 Kloset jongkok TOTO CE 9 / TV150NWV12J bh 1,00 1,00 0,084 - - - - - 0%
4.1.2 Jet washer TOTO THX20NB bh 1,00 1,00 0,008 - - - - - 0%
4.1.3 Washtafel gantung TOTO LW248JT1 lengkap accessoris bh 1,00 1,00 0,053 - - - - - 0%
4.1.4 Floor drain TOTO TX1BN bh 1,00 1,00 0,011 - - - - - 0%
4.1.5 Pasang Kaca Cermin uk.100 x 75 cm bh 1,00 1,00 0,009 - - - - - 0%
4,2 Toilet Wanita
4.1.1 Kloset jongkok TOTO CE 9 / TV150NWV12J bh 1,00 1,00 0,084 - - - - - 0%
4.1.2 Jet washer TOTO THX20NB bh 1,00 1,00 0,008 - - - - - 0%
4.1.3 Washtafel gantung TOTO LW248JT1 lengkap accessoris bh 1,00 1,00 0,053 - - - - - 0%
4.1.4 Floor drain TOTO TX1BN bh 1,00 1,00 0,011 - - - - - 0%
4.1.5 Pasang Kaca Cermin uk.100 x 75 cm bh 1,00 1,00 0,009 - - - - - 0%

h Pekerjaan Saluran
1 Pekerjaan galian tanah saluran
1,1 Saluran keliling bangunan gedung Beton T. 8 cm Uk. 50x50x50 cm m3 15,21 15,21 0,028 - - - - - 0%
2 Urugan pasir bawah pondasi T. 10 cm
2,1 Saluran keliling bangunan gedung Beton T. 8 cm Uk. 50x50x50 cm m3 2,34 2,34 0,041 - - - - - 0%
3 Urugan tanah kembali bekas galian pondasi m3 15,21 15,21 0,008 - - - - - 0%
4 Lantai kerja bawah saluran T. 5 cm ad. 1:3:5
4,1 Saluran keliling bangunan gedung Beton T. 8 cm Uk. 50x50x50 cm m3 1,17 1,17 0,105 - - - - - 0%
5 Saluran Beton
5,1 Saluran keliling bangunan gedung Beton T. 8 cm Uk. 50x50x50 cm
5.1.1 Besi U 24 Kg 297,83 297,83 0,147 - - - - - 0%
5.1.2 Bekisting multiplek T. 9 mm rangka kaso 5/7 cm m2 85,80 85,80 0,514 - - - - - 0%
5.1.3 Beton K. 250 m3 4,68 4,68 0,459 - - - - - 0%
6 Grill besi penutup saluran keliling Gedung L. 40 cm + zingkromat
Frame besi siku 4x4 cm balustrade besi dia. 13 mm finish cat minyak m' 39,00 39,00 0,355 - - - - - 0%

i Pekerjaan ACP + Rangka Hollow galvanis


1 Pekerjaan dinding ACP ( Dinding, Listplank dan Plafond )
1,1 Pasang rangka hollow galvanis 4x4 cm dan 2x4 cm m2 116,65 116,65 0,654 - - - - - 0%
1,2 Pasang Allumunium Composide Panel / ACP m2 116,65 116,65 1,829 - - - - - 0%
2 Pekerjaan dinding ACP cover kolom Tampak depan
2,1 Pasang rangka hollow galvanis 4x4 cm m2 18,30 18,30 0,103 - - - - - 0%
2,2 Pasang Allumunium Composide Panel / ACP m2 18,30 18,30 0,287 - - - - - 0%
3 Pasang kosen jendela
3,1 Kosen profil allumunium 4" CA / Natural m' 10,70 10,70 0,025 - - - - - 0%
3,2 Kaca Rayben T. 5 mm m2 2,85 2,85 0,011 - - - - - 0%
3,3 Sealent m' 21,40 21,40 0,001 - - - - - 0%
4 Logo Neon Sign w/ Acrylic Ls 1,00 1,00 0,271 - - - - - 0%
5 Text Neon Sign w/ Acrylic Huruf Arial T. 50 cm Ls 1,00 1,00 0,580 - - - - - 0%

III PEKERJAAN SARANA DAN PRASARANA


a Pekerjaan Halaman
1 Galian tanah pondasi batas area jalan kawasan dan paving block m3 18,45 18,45 0,034 - - - - - 0%
2 Urugan pasir bawah pondasi dan lantai T. 10 cm
2,1 Galian tanah pondasi batas area jalan kawasan dan paving block m3 7,38 7,38 0,128 - - - - - 0%
2,2 Area jalan kawasan m3 19,60 19,60 0,341 - - - - - 0%
3 Urugan tanah kembali bekas galian pondasi m3 18,45 18,45 0,009 - - - - - 0%
4 Lapisan Macadam T. 20 cm padat m3 39,20 39,20 0,384 - - - - - 0%
5 Lapisan Sirtu T. 20 cm padat m3 39,20 39,20 0,475 - - - - - 0%
VOLUME MINGGU LALU MINGGU INI S/D MINGGU INI
BOBOT Presentase
NO URAIAN PEKERJAAN Sat. Bobot
KONTRAK MC-0 (%) Volume Volume Bobot (%) Volume Bobot (%) (%)
(%)
b Pekerjaan Beton Duiker
1 Pekerjaan galian tanah
1,1 Pondasi batu kali dudukan Beton Duiker Uk. 100x100x30 cm m3 18,00 18,00 0,033 - - - - - 0%
2 Urugan pasir bawah pondasi T. 10 cm
2,1 Pondasi batu kali dudukan Beton Duiker Uk. 100x100x30 cm m3 1,80 1,80 0,031 - - - - - 0%
3 Urugan tanah kembali bekas galian pondasi m3 18,00 18,00 0,009 - - - - - 0%
4 Beton Duiker Uk. 900x150x25 cm
4,1 Besi beton U. 39 BJTD 39 Kg 866,94 866,94 0,429 - - - - - 0%
4,2 Bekisting multiplek T. 9 mm rangka kaso 5/7 cm m2 18,00 18,00 0,085 - - - - - 0%
4,3 Beton K. 250 m3 4,50 4,50 0,442 - - - - - 0%
5 Pondasi batu kali 100x75x30 cm ad. 1 : 4 m3 8,78 8,78 0,489 - - - - - 0%
6 Plesteran dinding pondasi ad. 1 : 4 m2 30,00 30,00 0,094 - - - - - 0%
7 Acian m2 30,00 30,00 0,034 - - - - - 0%

IV PEKERJAAN SISTEM PENDINGIN


A PANEL INSULASI
Spesification :
- Polyurethane/PIR Density : 43-45 kg/m3
- Thikness : 50 mm, 75 mm, 100 mm dan 150 mm (Dinding, Atap, Lantai)
- Thermal Conductivity : 0.020 W/mk
- Skin : Food Grade FDA Approved Anti Bacterial untuk Ruangan Receiving, Loading Cold Storage, ABF, Handling & Packing Room
Kekuatan tarik (Tensile Strenght) Class G300
Bahan PPGI dengan lapisan anti karat Zinc Class Z275
- Certificate Fire Behaviour of building material test minimal setara dengan standard DIN 4102 CLASS B2
- Connection : Slip Joint/Camlock Joint
1 MEDIUM TEMPERATURE & SUPPORTING AREA
a LOADING ROOM (3 x 3,5 x 3 m) Eksternal Dimension
- Dinding t.75 mm m2 26,10 26,10 0,666 - - - - - 0%
- Plafond t.75 mm m2 10,50 10,50 0,268 - - - - - 0%
b RECEIVING ROOM (3 x 3,5 x 3 m) Eksternal Dimension
- Dinding t.50 mm m2 25,90 25,90 0,621 - - - - - 0%
- Plafond t.50 mm m2 16,00 16,00 0,384 - - - - - 0%
- Alumunium Coving untuk setiap sudut antara dinding dan dindingm serta atap dan
27,00dinding 27,00 0,094 - - - - - 0%
c HANDLING & PACKING ROOM Tinggi 3 m Eksternal Dimension
- Dinding t.50 mm m2 49,60 49,60 1,189 - - - - - 0%
- Plafond t.50 mm m2 37,68 37,68 0,904 - - - - - 0%
- Alumunium Coving untuk setiap sudut antara dinding dan dindingm serta atap dan
49,60dinding 49,60 0,173 - - - - - 0%
d WASTE BIN (1 x 1,5 x 3 m) Eksternal Dimension
- Dinding t.50 mm m2 5,30 5,30 0,127 - - - - - 0%
- Plafond t.50 mm m2 1,50 1,50 0,036 - - - - - 0%
e FEMALE LOCKER & BAK CUCI KAKI (3 x 1.9 x 3 m) Eksternal Dimension
- Dinding Non Food Grade t.50 mm m2 22,70 22,70 0,461 - - - - - 0%
- Plafond Non Food Grade t.50 mm m2 5,40 5,40 0,110 - - - - - 0%
f MALE LOCKER & BAK CUCI KAKI (3 x 1.9 x 3 m) Eksternal Dimension
- Dinding Non Food Grade t.50 mm m2 22,70 22,70 0,461 - - - - - 0%
- Plafond Non Food Grade t.50 mm m2 5,40 5,40 0,110 - - - - - 0%
g OFFICE ROOM (3.5 x 3 x 3 m) & Toilet (1,5 x 1.3 x 3 m) Eksternal Dimension
- Dinding Non Food Grade t.50 mm m2 25,30 25,30 0,514 - - - - - 0%
- Plafond Non Food Grade t.50 mm m2 10,50 10,50 0,213 - - - - - 0%
h DRY STORAGE (3.5 x 3 x 3 m) Eksternal Dimension
- Dinding Non Food Grade t.50 mm m2 6,70 6,70 0,136 - - - - - 0%
- Plafond Non Food Grade t.50 mm m2 14,00 14,00 0,284 - - - - - 0%
2 LOW TEMPERATURE AREA
a COLD STORAGE 30T & ANTEROOM (9 x 6 x 3,5 m) Eksternal Dimension
- Lantai (PU Slab) t.100 mm m2 54,00 54,00 0,825 - - - - - 0%
- Dinding t.100 mm m2 93,90 93,90 2,452 - - - - - 0%
- Plafond t.100 mm m2 54,00 54,00 1,410 - - - - - 0%
b AIR BLAST FREEZER (5 x 4 x 3.5 m) Eksternal Dimension
- Lantai (PU Slab) t.150 mm m2 20,00 20,00 0,425 - - - - - 0%
- Dinding t.150 mm m2 65,50 65,50 2,090 - - - - - 0%
- Plafond t.150 mm m2 20,00 20,00 0,638 - - - - - 0%
- Air Guide Flow t.50 mm m2 10,00 10,00 0,232 - - - - - 0%

B PINTU DAN ACCESSORIS


1 MEDIUM TEMPERATURE & SUPPORTING AREA
a LOADING ROOM (3 x 3,5 x 3 m) Eksternal Dimension
- Sliding Door 1200 x 2000mm, c/wHandle, Frame, Rail & Lock + Ventilator unit 1,00 1,00 0,735 - - - - - 0%
- Strip Curtain, c/w Hanger & Bracket bh 1,00 1,00 0,058 - - - - - 0%
- Weather Proof Lamp bh 2,00 2,00 0,039 - - - - - 0%
b RECEIVING ROOM (3 x 3,5 x 3 m) Eksternal Dimension
- Swing Office Door 800 x 2000mm, c/w Handle, Frame & Lock unit 1,00 1,00 0,193 - - - - - 0%
- Strip Curtain, c/w Hanger & Bracket (kuning) bh 1,00 1,00 0,039 - - - - - 0%
- Swing Window 1000 x 1000mm, c/wHandle, Frame & Lock (Buka Atas) unit 1,00 1,00 0,102 - - - - - 0%
- Strip Curtain, c/w Hanger & Bracket (kuning) bh 1,00 1,00 0,021 - - - - - 0%
- Weather Proof Lamp bh 2,00 2,00 0,039 - - - - - 0%
c HANDLING & PACKING ROOM Tinggi 3 m Eksternal Dimension
- Double Swing Office Door 1600 x 2000mm, c/w Handle, Frame & Lock unit 1,00 1,00 0,387 - - - - - 0%
- Strip Curtain, c/w Hanger & Bracket bh 1,00 1,00 0,073 - - - - - 0%
- Weather Proof Lamp bh 5,00 5,00 0,097 - - - - - 0%
d WASTE BIN (1 x 1,5 x 3 m) Eksternal Dimension
- Swing Office Door 800 x 2000mm, c/w Handle, Frame & Lock unit 1,00 1,00 0,193 - - - - - 0%
- Strip Curtain, c/w Hanger & Bracket (kuning) bh 1,00 1,00 0,039 - - - - - 0%
- Swing Window 600 x 1000mm, c/wHandle, Frame, Rail & Lock (Buka Atas) unit 1,00 1,00 0,060 - - - - - 0%
- Strip Curtain, c/w Hanger & Bracket (kuning) bh 1,00 1,00 0,021 - - - - - 0%
- Weather Proof Lamp bh 1,00 1,00 0,019 - - - - - 0%
e FEMALE LOCKER & BAK CUCI KAKI (3 x 1.9 x 3 m) Eksternal Dimension
- Swing Office Door 800 x 2000mm, c/w Handle, Frame & Lock unit 1,00 1,00 0,193 - - - - - 0%
- Strip Curtain, c/w Hanger & Bracket bh 3,00 3,00 0,116 - - - - - 0%
- Weather Proof Lamp bh 3,00 3,00 0,058 - - - - - 0%
f MALE LOCKER & BAK CUCI KAKI (3 x 1.9 x 3 m) Eksternal Dimension
- Swing Office Door 800 x 2000mm, c/w Handle, Frame & Lock unit 1,00 1,00 0,193 - - - - - 0%
- Strip Curtain, c/w Hanger & Bracket bh 3,00 3,00 0,116 - - - - - 0%
- Weather Proof Lamp bh 3,00 3,00 0,058 - - - - - 0%
g OFFICE ROOM (3.5 x 3 x 3 m) & Toilet (1,5 x 1.3 x 3 m) Eksternal Dimension
- Swing Office Door 800 x 2000mm, c/w Handle, Frame & Lock unit 2,00 2,00 0,387 - - - - - 0%
- Fix Glass Window 1000 x 1000 mm set 2,00 2,00 0,081 - - - - - 0%
- Fix Glass Window 600 x 1000 mm set 1,00 1,00 0,029 - - - - - 0%
- Weather Proof Lamp bh 3,00 3,00 0,058 - - - - - 0%
h DRY STORAGE (3.5 x 3 x 3 m) Eksternal Dimension
- Double Swing Office Door 1600 x 2000mm, c/w Handle, Frame & Lock unit 1,00 1,00 0,406 - - - - - 0%
- Strip Curtain, c/w Hanger & Bracket bh 1,00 1,00 0,073 - - - - - 0%
- Swing Window 600 x 1000mm, c/wHandle, Frame, Rail & Lock (Buka Samping) unit 1,00 1,00 0,060 - - - - - 0%
- Strip Curtain, c/w Hanger & Bracket bh 1,00 1,00 0,021 - - - - - 0%
- Weather Proof Lamp bh 2,00 2,00 0,039 - - - - - 0%
VOLUME MINGGU LALU MINGGU INI S/D MINGGU INI
BOBOT Presentase
NO URAIAN PEKERJAAN Sat. Bobot
KONTRAK MC-0 (%) Volume Volume Bobot (%) Volume Bobot (%) (%)
(%)
2 LOW TEMPERATURE AREA
a COLD STORAGE 30T & ANTEROOM (9 x 6 x 3,5 m) Eksternal Dimension
- Sliding Door 1500 x 2000mm, c/wHandle, Frame, Rail & Lock + Ventilator unit 2,00 2,00 1,934 - - - - - 0%
- Strip Curtain, c/w Hanger & Bracket bh 3,00 3,00 0,203 - - - - - 0%
- Weather Proof Lamp bh 7,00 7,00 0,135 - - - - - 0%
b AIR BLAST FREEZER (5 x 4 x 3.5 m) Eksternal Dimension
- Swing Door 1000 x 2000mm, c/w Door Heater, Handle, Frame & Lock + ventilator unit 2,00 2,00 0,890 - - - - - 0%
- Strip Curtain, c/w Hanger & Bracket bh 2,00 2,00 0,097 - - - - - 0%
- Weather Proof Lamp bh 2,00 2,00 0,039 - - - - - 0%

C MESIN PENDINGIN DAN ACCESSORIS


1 MEDIUM TEMPERATURE & SUPPORTING AREA
I Handling dan Packing Room
a. - Condensing Unit Handling & Packing Room Unit 2,00 2,00 1,741 - - - - - 0%
- Condensing Unit dirakit secara orisinil oleh pabrikan Kompressor
- Compressor min 4 HP
- Range Voltage 380-420 V/3 phase/50hz
- Refrigerant : Zero ODP, R404a
(Mengikuti brochure dan mendapat dukungan penuh dari pabrikan)
(Complete with Certificate class ISO Certification 9001:2008 atau setara)
b Evaporator Handling & Packing Room Unit 2,00 2,00 1,431 - - - - - 0%
- Dual Air Throw Model
- Cooling Capacity : Min 11 KW at Evap Temp 5 C, Room Temperature 15 C
- Fin Spacing min 4 mm
- Fan quantity min : 2
- Fin/Tube material : Alluminium/ copper
- Air Flow : Min 4000 m3/h
(Mengikuti brochure dan mendapat dukungan penuh dari pabrikan)
(Complete with Certificate class ISO Certification 9001:2008 atau setara)
c Control Panel & Installation Set 1,00 1,00 2,417 - - - - - 0%
- Dibuat oleh Panel Maker (Panel Builder)
- MCCB
- Magnetic Contactor
- Thermal Overload
- Indicator lamp
- Time Delay Relay
- Temperature and Defrost Controler
- Cable from control panel to compressor : NYY Standar SNI
- Cable From control Panel to evaporator and condensor : NYY Standar SNI
- Hard Copper Pipe ASTM B 280 atau setara
- Pipe Insulation
- With Tray/Ladder support
- pressure test min. 250 psi, 1 day (24 jam)
- R-404a
- Dilengkapi dengan wiring diagram
II Loading Room
a - Refrigeration Unit Loading Set 1,00 1,00 1,741 - - - - - 0%
- Original Assembly by Principle
- Cooling Capacity : Min 3.7 KW at Temperature 5 C Ambient Temperature 35 C
- Plug In Refrigeration System
- Air Cooled Condensor
- Voltage range 380V - 420V/3phasa/ 50hz
- Refrigerant : Zero ODP, R404a
(Mengikuti brochure dan mendapat dukungan penuh dari pabrikan)
(Complete with Certificate class ISO Certification 9001:2008 atau setara)

2 LOW TEMPERATURE AREA


I Cold Storage Kapasitas 30T
a. - Condensing Unit Unit 1,00 1,00 1,392 - - - - - 0%
- Condensing Unit dirakit secara orisinil oleh pabrikan Kompressor
- Compressor min 10 HP
- Range Voltage 380-420 V/3 phase/50hz
- Refrigerant : Zero ODP, R404a
(Mengikuti brochure dan mendapat dukungan penuh dari pabrikan)
(Complete with Certificate class ISO Certification 9001:2008 atau setara)
b Evaporator Cold Storage 30T Unit 1,00 1,00 0,909 - - - - - 0%
- Cooling Capacity : Min 8 KW at Evap Temp -32 C, Room Temperature -25 C
- Fin Spacing min 6 mm
- Fan quantity min : 2
- Air Flow : Min 6000 m3/h
- Heater Defrost Coil and Tray
(Mengikuti brochure dan mendapat dukungan penuh dari pabrikan)
(Complete with Certificate class ISO Certification 9001:2008 atau setara)
c Control Panel & Installation Set 1,00 1,00 1,644 - - - - - 0%
- Dibuat oleh Panel Maker (Panel Builder)
- MCCB
- Magnetic Contactor
- Thermal Overload
- Indicator lamp
- Time Delay Relay
- Temperature and Defrost Controler
- Cable from control panel to compressor : NYY Standar SNI
- Cable From control Panel to evaporator and condensor : NYY Standar SNI
- Hard Copper Pipe ASTM B 280 atau setara
- Pipe Insulation
- With Tray/Ladder support
- pressure test min. 250 psi, 1 day (24 jam)
- R-404a
- Dilengkapi dengan wiring diagram
II Air Blast Freezer 4 Ton/day (-35 C)
a. Condensing Unit Air Blast Freezer Set 1,00 1,00 5,260 - - - - - 0%
- Condensing Unit dirakit secara orisinil oleh pabrikan Kompressor
- Compressor dengan COO Eropa
- Two Stage Semihermetic Compressor Min 25 HP
- Voltage range 380V - 420V/3phasa/ 50hz
- Refrigerant : R404a, Zero ODP
(Mengikuti brochure dan mendapat dukungan penuh dari pabrikan)
(Complete with Certificate Of Origin dari Eropa)
(Complete with Certificate class ISO Certification 9001:2008 atau setara)
b. Evaporator Air Blast Freezer Set 1,00 1,00 2,514 - - - - - 0%
- Cooling Capacity : Min 28 KW at Evap Temp -30 C, Air Inlet Temperature -24 C
- Fin Spacing min 8 mm
- Fan quantity min : 2
- Air Flow : Min 29000 m3/h
- Heater Defrost Coil and Tray
(Mengikuti brochure dan mendapat dukungan penuh dari pabrikan)
(Complete with Certificate class ISO Certification 9001:2008 atau setara)
VOLUME MINGGU LALU MINGGU INI S/D MINGGU INI
BOBOT Presentase
NO URAIAN PEKERJAAN Sat. Bobot
KONTRAK MC-0 (%) Volume Volume Bobot (%) Volume Bobot (%) (%)
(%)
c. Control Panel & Installation Set 1,00 1,00 2,089 - - - - - 0%
- Dibuat oleh Panel Maker (Panel Builder)
- MCCB
- Magnetic Contactor
- Thermal Overload
- Indicator lamp
- Time Delay Relay
- Temperature and Defrost Controler
- Cable from control panel to compressor : NYY Standar SNI
- Cable From control Panel to evaporator and condensor : NYY Standar SNI
- Hard Copper Pipe ASTM B 280 atau setara
- Pipe Insulation
- With Tray/Ladder support
- pressure test min. 250 psi, 1 day (24 jam)
- R-404a
- Dilengkapi dengan wiring diagram

V PEKERJAAN MEKANIKAL DAN ELEKTRIKAL


A PEKERJAAN MEKANIKAL
a.1 Pekerjaan Plambing
a.1.1 Instalasi Pemipaan Air Bersih Site Plan
Pengadaan dan pemasangan pipa lengkap dengan gantungan
dan support, sesuai dengan gambar rencana dan spesifikasi teknis
Pipa air bersih dari bahan PP-R, PN 10
1 Peralatan Utama
Pengadaan dan pemasangan Unit Pompa
lengkap dengan accessories dan material bantu lainnya
sesuai dengan gambar rencana dan spesifikasi teknis.
a. Pompa Jet Pump PDH-405JP unit 1,00 1,00 0,193 - - - - - 0%
- Daya Output Listrik : 400 Watt
- Daya Hisap : 40 Meter
- Daya Dorong : 40 Meter
- Debit Air : 34 ltr/ment
b. Tanki Air Modul Panel FRP Kap. 8 m3 unit 1,00 1,00 0,677 - - - - - 0%
c. Packaged Booster Pump : pkt 1,00 1,00 0,870 - - - - - 0%
Pump Mfg : (Paralel / Alternate System)
Pump Type : 50 x 40 FSH
Cap. T-Head : 2(150 ltr/menit), 20 meter
Shaft Sealing : Mechanical Seal
Power : 2(1.5 kW) / 380 V / 3 Phase / 50 Hz / 2900 Rpm
Accessories : Control Panel, Membrane Tank, Booster Skid Basa,
Valve + Fitting, Pressure Gauge, Pressure Switch,
2(two) Pumps + Elektro Motor
2 Pemipaan sumur jet pump
a. Pipa Hisap PVC Class AW (10kg/cm2) dia 32 mm m' 35,00 35,00 0,018 - - - - - 0%
b. Pipa Hisap PVC Class AW (10kg/cm2) dia 25 mm m' 35,00 35,00 0,014 - - - - - 0%
c. Pipa Dorong PVC Class AW (10kg/cm2) dia 25 mm m' 22,00 22,00 0,009 - - - - - 0%
dari pompa ke tanki air
d. Gate Valve setara Kitz dia 25 mm bh 1,00 1,00 0,006 - - - - - 0%
e. Foot Valve setara Mizu dia 25 mm bh 1,00 1,00 0,005 - - - - - 0%
f. Ploating Valve setara Kitz dia 25 mm bh 1,00 1,00 0,004 - - - - - 0%
g. Water level kontrol (Otomatis Radar) bh 1,00 1,00 0,004 - - - - - 0%
h. Kabel kontrol NYM 3 x 2,5 mm2 c/w pipa counduit dia 20 mm m' 28,00 28,00 0,008 - - - - - 0%
dari pompa ke tanki air
i. Fitting lot 1,00 1,00 0,009 - - - - - 0%
j. Material bantu lot 1,00 1,00 0,004 - - - - - 0%
k. Pantekan sumur jet pump 40 m + pipa casing dia 4'' unit 1,00 1,00 0,135 - - - - - 0%
3 Instalasi Air Bersih dari PDAM ke Tanki Air
a. Pipa air bersih bahan PP-R, PN 10 dia 25 mm m' 47,00 47,00 0,036 - - - - - 0%
b. Ploating Valve setara Kitz dia 25 mm m' 1,00 1,00 0,004 - - - - - 0%
c. Gate Valve dia 25 mm2 setara Kitz bh 1,00 1,00 0,006 - - - - - 0%
d. Assesories : Fitting, Elbow, sock dll lot 1,00 1,00 0,010 - - - - - 0%
e. Material bantu Support & Hanger lot 1,00 1,00 0,006 - - - - - 0%
f. Biaya Penyambungan Air Bersih dari PDAM (pipa dia 25 mm2) ls 1,00 1,00 0,870 - - - - - 0%
(termasuk perijinan dari dinas terkait)
4 Instalasi Air Bersih dari Tanki Air ke Booster Pump
a. Pipa air bersih bahan PP-R, PN 10 dia 50 mm (Pipa Kuras & Over flow) m' 7,00 7,00 0,018 - - - - - 0%
b. Pipa air bersih bahan PP-R, PN 10 dia 50 mm (Pipa Hisap) m' 4,00 4,00 0,010 - - - - - 0%
c. Gate Valve dia 50 mm2 setara Kitz bh 3,00 3,00 0,046 - - - - - 0%
d. Assesories : Fitting, Elbow, sock dll lot 1,00 1,00 0,010 - - - - - 0%
e. Material bantu Support & Hanger lot 1,00 1,00 0,006 - - - - - 0%
5 Instalasi Air Bersih dari Booster Pump ke Halaman / Taman
a. Pipa air bersih bahan PP-R, PN 10 dia 25 mm m' 4,00 4,00 0,003 - - - - - 0%
b. Pipa air bersih bahan PP-R, PN 10 dia 20 mm m' 25,00 25,00 0,013 - - - - - 0%
c. Pipa air bersih bahan PP-R, PN 10 dia 15 mm m' 40,00 40,00 0,015 - - - - - 0%
d. Gate Valve dia 25 mm2 setara Kitz bh 1,00 1,00 0,006 - - - - - 0%
e. Krant Taman/Halaman T 26-13 bh 4,00 4,00 0,023 - - - - - 0%
f. Assesories : Fitting, Elbow, sock dll lot 1,00 1,00 0,010 - - - - - 0%
g. Material bantu Support & Hanger lot 1,00 1,00 0,006 - - - - - 0%

a.1.2 Instalasi Pemipaan Air Bersih, Air Kotor dan Air Bekas Dalam Gedung
Pengadaan dan pemasangan pipa lengkap dengan gantungan
dan support, sesuai dengan gambar rencana dan spesifikasi teknis
Pipa air bersih dari bahan PP-R, PN 10
1 Instalasi Air Bersih dari Booster Pump, ke Toilet -1 dan toilet -2
a. Pipa air bersih bahan PP-R, PN 10 dia 40 mm m' 14,00 14,00 0,024 - - - - - 0%
b. Pipa air bersih bahan PP-R, PN 10 dia 32 mm m' 28,00 28,00 0,032 - - - - - 0%
c. Pipa air bersih bahan PP-R, PN 10 dia 25 mm m' 8,00 8,00 0,006 - - - - - 0%
d. Pipa air bersih bahan PP-R, PN 10 dia 15 mm m' 62,00 62,00 0,024 - - - - - 0%
e. Gate valve dia 40 mm bh 1,00 1,00 0,010 - - - - - 0%
f. Gate valve dia 32 mm bh 2,00 2,00 0,015 - - - - - 0%
g. Assesories : Fitting, Elbow, sock dll lot 1,00 1,00 0,019 - - - - - 0%
h. Material bantu Support & Hanger lot 1,00 1,00 0,010 - - - - - 0%
2 Instalasi Air Bersih dari Booster Pump, ke Toilet -3
a. Pipa air bersih bahan PP-R, PN 10 dia 40 mm m' 37,00 37,00 0,064 - - - - - 0%
b. Pipa air bersih bahan PP-R, PN 10 dia 25 mm m' 7,00 7,00 0,005 - - - - - 0%
c. Pipa air bersih bahan PP-R, PN 10 dia 20 mm m' 25,00 25,00 0,013 - - - - - 0%
d. Pipa air bersih bahan PP-R, PN 10 dia 15 mm m' 22,00 22,00 0,009 - - - - - 0%
e. Gate valve dia 40 mm bh 1,00 1,00 0,008 - - - - - 0%
f. Gate valve dia 25 mm bh 1,00 1,00 0,006 - - - - - 0%
g. Assesories : Fitting, Elbow, sock dll lot 1,00 1,00 0,019 - - - - - 0%
h. Material bantu Support & Hanger lot 1,00 1,00 0,010 - - - - - 0%
VOLUME MINGGU LALU MINGGU INI S/D MINGGU INI
BOBOT Presentase
NO URAIAN PEKERJAAN Sat. Bobot
KONTRAK MC-0 (%) Volume Volume Bobot (%) Volume Bobot (%) (%)
(%)
3 Instalasi Pemipaan Air Kotor dan Air Bekas, Toilet -1, Toilet -2 dan toilet -3
Sampai ke Septicktank dan Saluran Keliling
a. Pipa Air Kotor PVC Class AW (10kg/cm2) dia 100 mm m' 52,00 52,00 0,075 - - - - - 0%
b. Pipa Air Bekas PVC Class AW (10kg/cm2) dia 80 mm m' 22,00 22,00 0,021 - - - - - 0%
c. Pipa Air Bekas PVC Class AW (10kg/cm2) dia 50 mm m' 25,00 25,00 0,017 - - - - - 0%
d. Clean Out (CO) dia 100 mm bh 2,00 2,00 0,009 - - - - - 0%
e. Clean Out (CO) dia 80 mm bh 1,00 1,00 0,004 - - - - - 0%
f. Assesories : Fitting, Elbow, sock dll lot 1,00 1,00 0,023 - - - - - 0%
g. Material bantu Support & Hanger lot 1,00 1,00 0,012 - - - - - 0%
h. Bak kontrol uk. 100 x 100 cm, c/w tutup plat beton bh 1,00 1,00 0,012 - - - - - 0%
i. Pemasangan Septicktank FRP Biocell RC3 - kap. 3 m3 unit 1,00 1,00 0,406 - - - - - 0%
(Galian dan Pondasi tidak termasuk)
j. Pekerjaan Resapan kap. 2 m3 unit 1,00 1,00 0,039 - - - - - 0%

a.1.3 Instalasi Pemipaan Air Bekas IPAL


Pengadaan dan pemasangan pipa lengkap dengan gantungan
dan support, sesuai dengan gambar rencana dan spesifikasi teknis
a. Pipa Air Limbah (IPAL) PVC Class AW (10kg/cm2) dia 150 mm m' 24,00 24,00 0,058 - - - - - 0%
b. Pipa Air Resapan PVC Class AW (10kg/cm2) dia 100 mm m' 6,00 6,00 0,009 - - - - - 0%
c. Assesories : Fitting, Elbow, sock dll lot 1,00 1,00 0,014 - - - - - 0%
d. Clean Out (CO) dia 100 mm bh 1,00 1,00 0,004 - - - - - 0%
e. Pekerjaan Pemasangan IPAL (STP) Kap. 5 m3/day, All Waste Water. unit 1,00 1,00 0,967 - - - - - 0%
sampai berfungsi dengan baik.
Included :
- Pekerjaan tanki STP Biotech
- Blower
- Pemipaan dan Instalasi
- Control Panel
- Pelatihan Operator
- 1 set Drawing dan Manual Operasi
- Sertificate Guarantee System min. 1 Tahun
- Supervising & Test Commissioning

a.1.4 Instalasi Pipa Air Hujan


Pengadaan dan pemasangan pipa lengkap dengan gantungan
dan support, pengecatan sesuai dengan gambar rencana dan
spesifikasi teknis. Pipa air hujan PVC Class AW (10kg/cm2) sampai ke saluran
a. Pipa PVC Class AW (10kg/cm2) dia 150 mm (Pipa Penghubung Saluran) m' 21,00 21,00 0,051 - - - - - 0%
b. Pipa Air Hujan PVC Class AW (10kg/cm2) dia 80 mm m' 62,00 62,00 0,066 - - - - - 0%
c. Roof drain dia 80 mm bh 10,00 10,00 0,039 - - - - - 0%
d. Assesories : Fitting, Elbow, sock dll lot 1,00 1,00 0,014 - - - - - 0%
e. Material bantu Support & Hanger lot 1,00 1,00 0,007 - - - - - 0%

a.2 Pekerjaan AC
Pengadaan dan pemasangan Unit AC, lengkap dengan pipa refrigerant, pipa drain,
gantungan, pengecatan lengkap dengan material bantu sesuai dengan gambar
dan spesifikasi teknis.
1 Pekerjaan Unit AC Kap. 1 PK (Split Wall Mounted) unit 2,00 2,00 0,174 - - - - - 0%
- Type
- Kapasitas
- Daya
- Input
- Freon
a. Instalasi power dari panel AC ke indoor AC Split Wall Mounted, 1 PK mtr 45,00 45,00 0,012 - - - - - 0%
kabel NYM 3x2.5 mm2,
b. Inst. power control dari indoor ke outdoor AC, NYM 3x2.5 mm2 mtr 15,00 15,00 0,004 - - - - - 0%
c. Outlet Stop-Kontak AC, 1 phasa 220V/16A, 1 gang, 1 Power bh 2,00 2,00 0,004 - - - - - 0%
d. Pipa Refregerant inc. Armaflex & Isolasi ( Elastromeric Nitrille Rubber ) :
0 Gas -3/8" + Liguid -1/4" mtr 15,00 15,00 0,015 - - - - - 0%
2 Pekerjaan Instalasi Pipa Drain
1 Drain PVC AW, include armaflex dan isolasi Ø 20 mm mtr 20,00 20,00 0,012 - - - - - 0%
3 Pekerjaan Tata Udara Exhaust Fan
3,1 Exhaust Fan, type Compact Axial Flow Ventilating Fan (EF-4 & EF-5) unit 1,00 1,00 0,053 - - - - - 0%
14'', kap. 2.670 Cmh / 1.571 Cfm 88W/220v/50hz N/ A m/min, 44 dB
4 Instalasi Exhaust Fan NYM 3 X 2.5mm2 + pipa counduit dia 20 mm ttk 1,00 1,00 0,005 - - - - - 0%

a.3 Pekerjaan Alat Pemadam Api Ringan (APAR)


Meliputi : Pengadaan dan pemasangan APAR, beserta accesoris
dan peralatan pendukung sehingga berfungsi dengan baik

1 Fire extinguisher Multi Purpose Dry Chemical kap. 3.5 kg bh 3,00 3,00 0,087 - - - - - 0%

B PEKERJAAN ELEKTRIKAL
b.1 Pekerjaan Instalasi Listrik
b.1.1 Pekerjaan Panel daya
pengadaan dan pemasangan Unit Panel daya dan Penerangan
beserta accesoriesnya sehingga dapat berfungsi dengan baik.
1 Panel - LVMDP, Tipe Free Standing ( 1 cell ) unit 1,00 1,00 0,967 - - - - - 0%
2 Panel PP.LP - CS unit 1,00 1,00 0,155 - - - - - 0%

b.1.2 Pekerjaan Kabel Daya


Pengadaan dan Pemasangan Pekerjaan Kabel Daya lengkap material bantu
sesuai dengan gambar dan spesifikasi teknis sehingga dapat berfungsi dg baik.
1 Kabel dari Gardu PLN ke Incoming Panel - ATS/AMF Genset :
a. Kabel NYFGbY (4 x 95 mm²) m' 52,00 52,00 0,805 - - - - - 0%
b. Skun Kabel 95 mm² bh 8,00 8,00 0,005 - - - - - 0%
c. Galian dan pengurugan kembali bekas galian kabel -60 cm m' 35,00 35,00 0,034 - - - - - 0%
2 Kabel dari Genset ke Incoming Panel - ATS/AMF Genset :
a. Kabel NYY (4 x 95 mm²) m' 11,00 11,00 - - - - - - 0%
b. Skun Kabel 95 mm² bh 8,00 8,00 - - - - - - 0%
3 Kabel dari Incoming Panel - ATS/AMF Genset ke Panel-Capacitor Bank :
a. Kabel NYY (4 x 95 mm²) m' 6,00 6,00 - - - - - - 0%
b. Skun Kabel 95 mm² bh 8,00 8,00 - - - - - - 0%
4 Kabel dari Outgoing Panel - ATS/AMF Genset ke Panel-LVMDP :
a. Kabel NYY (4 x 95 mm²) m' 6,00 6,00 0,070 - - - - - 0%
b. Skun Kabel 95 mm² bh 8,00 8,00 0,005 - - - - - 0%
5 Kabel dari Outgoing Panel-LVMDP ke :
a. Panel PP.LP - CS
- Kabel NYY 4 x 16 mm2 m' 6,00 6,00 0,014 - - - - - 0%
- Grounding NYA 1 x 16 mm2 c/w Counduit dia 20 mm² m' 6,00 6,00 0,003 - - - - - 0%
- Skun Kabel 16 mm² bh 10,00 10,00 0,001 - - - - - 0%
b. Panel PP - Booster Pump
- Kabel NYFGbY 4 x 4 mm2 m' 19,00 19,00 0,022 - - - - - 0%
- Grounding NYA 1 x 6 mm2 c/w Counduit dia 20 mm² m' 19,00 19,00 0,004 - - - - - 0%
VOLUME MINGGU LALU MINGGU INI S/D MINGGU INI
BOBOT Presentase
NO URAIAN PEKERJAAN Sat. Bobot
KONTRAK MC-0 (%) Volume Volume Bobot (%) Volume Bobot (%) (%)
(%)
c. Panel Kontrol - IPAL (STP)
- Kabel NYFGbY 4 x 4 mm2 m' 31,00 31,00 0,036 - - - - - 0%
- Grounding NYA 1 x 6 mm2 c/w Counduit dia 20 mm² m' 31,00 31,00 0,006 - - - - - 0%
d. Kontrol Panel - CS
- Kabel NYY 4 x 16 mm2 m' 12,00 12,00 0,028 - - - - - 0%
- Grounding NYA 1 x 16 mm2 c/w Counduit dia 20 mm² m' 12,00 12,00 0,006 - - - - - 0%
- Skun Kabel 16 mm² bh 10,00 10,00 0,001 - - - - - 0%
e. Kontrol Panel - ABF
- Kabel NYY 4 x 35 mm2 m' 11,00 11,00 0,053 - - - - - 0%
- Grounding NYA 1 x 35 mm2 c/w Counduit dia 20 mm² m' 11,00 11,00 0,013 - - - - - 0%
- Skun Kabel 35 mm² bh 10,00 10,00 0,002 - - - - - 0%
f. Kontrol Panel - Handling & Packing Room
- Kabel NYY 4 x 16 mm2 m' 10,00 10,00 0,023 - - - - - 0%
- Grounding NYA 1 x 16 mm2 c/w Counduit dia 20 mm² m' 10,00 10,00 0,005 - - - - - 0%
- Skun Kabel 16 mm² bh 10,00 10,00 0,001 - - - - - 0%
g. Kontrol Panel - Loading Room
- Kabel NYY 4 x 6 mm2 m' 9,00 9,00 0,009 - - - - - 0%
- Grounding NYA 1 x 6 mm2 c/w Counduit dia 20 mm² m' 9,00 9,00 0,002 - - - - - 0%
- Skun Kabel 6 mm² bh 10,00 10,00 0,000 - - - - - 0%

b.1.3 Pekerjaan Rak Kabel


Pengadaan dan Pemasangan Pekerjaan Rak Kabel lengkap material bantu
sesuai dengan gambar dan spesifikasi teknis sehingga dapat berfungsi dg baik.
1 Instalasi kabel tray 300 :
a. Kabel Tray 300 x 50 (LAK) m' 15,00 15,00 0,099 - - - - - 0%
b. Kabel Tray 300 x 50 (LAK) dari plafond turun ke panel-panel m' 10,00 10,00 0,066 - - - - - 0%
c. Cover Kabel Tray 300 x 100 (LAK) dari plafond turun ke panel-panel m' 10,00 10,00 0,048 - - - - - 0%
d. Elbow 300 X 50 bh 1,00 1,00 0,009 - - - - - 0%
e. Tee 300 X 50 bh 5,00 5,00 0,048 - - - - - 0%
2 Instalasi kabel tray 200 :
a. Kabel Tray 200 x 50 (LAK) m' 18,00 18,00 0,104 - - - - - 0%
b. Elbow 200 X 50 bh 1,00 1,00 0,006 - - - - - 0%
3 Material bantu dan gantungan/support lot 1,00 1,00 0,019 - - - - - 0%

b.1.4 Pekerjaan System Grounding ( Pentanahan )


1 Bak Kontrol uk. 400 x 400 x 400 mm c/w dari pasangan bata, tutup beton, lubang set 1,00 1,00 0,068 - - - - - 0%
rembesan, BC dia. 70 mm termasuk pipa GIP medium Φ 32 mm, Copper rod tembaga,
tahanan max. 5 Ohm & perlengkapan lain Sehingga sistem berfungsi termasuk
pengetesan sesuai gambar dan Spesifikasi untuk
Grounding Body Panel - LVMDP & Body Genset

b.1.5 Pekerjaan Instalasi Penerangan dan Stop Kontak


Pengadaan dan Pemasangan Pekerjaan instalasi, Armature, Saklar & Stop kontak
lengkap material bantu sesuai dengan gambar dan spesifikasi teknis
sehingga dapat berfungsi dengan baik.
1 Pekerjaan Instalasi Penerangan PP.LP-CS (dalam gedung)
1,1 Pekerjaan Armature
a. Lampu TL 2 X 36 W/54 Savy Type V Shape bh 13,00 13,00 0,151 - - - - - 0%
b. Lampu Exit Green 1 X 8 W ACR 1 MK, Niccad Battery bh 1,00 1,00 0,019 - - - - - 0%
c. Down Light LED Panel 12W Bulat Outbow bh 5,00 5,00 0,017 - - - - - 0%
d. Down Light LED Panel 8W Bulat Outbow bh 2,00 2,00 0,006 - - - - - 0%
e. Saklar Tunggal bh 6,00 6,00 0,004 - - - - - 0%
f. Saklar Double bh 8,00 8,00 0,006 - - - - - 0%
g. Outlet Stop-Kontak tertutup, 1 phasa 220V/13A 1 gang, 1 Power bh 17,00 17,00 0,016 - - - - - 0%

1,2 Pekerjaan Instalasi


a. Instalasi Penerangan NYM 3 x 2.5mm2 + pipa counduit dia 20 mm ttk 21,00 21,00 0,102 - - - - - 0%
b. Instalasi stop kontak NYM 3 X 2.5mm2 + pipa counduit dia 20 mm ttk 17,00 17,00 0,099 - - - - - 0%
2 Pekerjaan Instalasi Penerangan PP.LP-CS (Site Plan)
2,1 Pekerjaan Armature
a. Lampu Jalan LAYNA L 200 W c/w Pondasi, Tiang 9 m, Cabang 1 bh 2,00 2,00 0,387 - - - - - 0%
2,2 Pekerjaan Instalasi
a. Instalasi Lampu Jalan LAYNA L 200 W
- Kabel NYY 3 x 2.5 mm2 m 65,00 65,00 0,044 - - - - - 0%
b. Pengadaan dan pemasangan MCB 10A / 6kA bh 2,00 2,00 0,003 - - - - - 0%

b.2 Pekerjaan Penangkal Petir


meliputi : pengadaan dan pemasangan penangkal petir beserta kelengkapannya
termasuk assesories, alat bantu dan testing komissioning
sehingga dapat berfungsi dengan baik
1 Kabel Penghantar NYY 1 x 70mm2 m 30,00 30,00 0,087 - - - - - 0%
2 Air Terminal Head R.70 m bh 1,00 1,00 0,271 - - - - - 0%
3 FRP Mast bh 1,00 1,00 0,039 - - - - - 0%
4 Tiang Penyangga GSP dia.65 mm2 T=6M + support ls 1,00 1,00 0,039 - - - - - 0%
5 Pemasangan Grounding sistem BC 50mm (R = 0,2 Ohm) ttk 3,00 3,00 0,041 - - - - - 0%
6 Kabel BC 50 mm2 m 36,00 36,00 0,042 - - - - - 0%
7 Pipa Gip medium dia 32mm m 25,00 25,00 0,048 - - - - - 0%
8 Material bantu dan assesories ls 1,00 1,00 0,019 - - - - - 0%
9 Bak kontrol ( 40cmx40cmx30cm ) include CU Earth bar bh 1,00 1,00 0,010 - - - - - 0%
10 Test-Grounding, R = 0,2 ohm ls 1,00 1,00 0,025 - - - - - 0%

Samapai
100,00 Minggu Lalu 4,101 Minggu Ini 1,336 5,437
Minggu ini

Mengetahui, Diketahui Oleh, Dibuat Oleh,


KUASA PENGGUNA ANGGARAN, Konsultan Pengawas Konsultan Pengawas
PEJABAT PEMBUAT KOMITMEN CV. NUSANTARA CIPTA KONSULTANT CV. NUSANTARA CIPTA KONSULTANT

H A R L I N, SE., MM YUYUN ASTRIYANTI, ST SRIKIYANTI OLII, ST


NIP. 19640902 199603 1 001 DIREKTUR TEAM LEADER