Anda di halaman 1dari 4

RENCANA ANGGARAN BIAYA

RESTORASI SUNGAI SEKANAK DAN LAMBIDARO

No. Item Uraian Pekerjaan


Pekerjaan
I PEKERJAAN PERSIAPAN
I.1 Uitset (per m')
I.2 Papan Nama Pekerjaan
I.3 Mobilisasi Dan Demobilisasi
I.4 Fasilitas Sementara
Sub Total I
II NORMALISASI
II.1 Galian Tanah Dengan Excavator
II.2 Membuang Material Sejauh 10km
Sub Total II
III PERKUATAN TALUD SUNGAI
III.1 Pengadaan Turap Baja B-400 L=8 m
III.2 Pemancangan Turap Baja B-400 L=8 m
III.3 Pekerjaan Beton Pilecap
III.4 Pekerjaan Pembesian
III.5 Mendatangkan Material Tanah Untuk Tanggul
III.6 Timbunan Dan Pemadatan Tanggul Banjir
Sub Total III
IV KOLAM RETENSI
III.1 Galian Tanah Dengan Excavator
III.2 Membuang Material Sejauh 10km
III.3 Pengadaan Dan Pemancangan Cerucuk Gelam (L = 5 - 10 m)
III.4 Lantai Kerja
III.5 Bekisting
III.6 Pembesian
III.7 Beton
III.8 Plesteran
III.9 Bronjong
III.10 Pintu Sorong b = 1
III.11 Mendatangkan Material Tanah Untuk Tanggul
III.12 Timbunan Dan Pemadatan Tanggul Banjir
Sub Total IV
V PEKERJAAN PEDESTRIAN DAN LANDSCAPING
III.1 Pekerjaan Paving Block
III.2 Landscaping
Sub Total V
VI PEKERJAAN PENINGGIAN JEMBATAN
III.1 Jembatan Kendaraan (Bentang ±150 meter)
III.2 Jembatan Orang
Sub Total VI

Total
PPN 10%
Jumlah Total
Dibulatkan
Terbilang
Dua Ratus Tujuh Puluh Lima Milyar Tiga Puluh Sembilan Juta Lima
AN BIAYA
DAN LAMBIDARO

Kuantitas / Harga Satuan


Satuan Jumlah Harga (Rupiah)
Volume (Rp)

m' 10,440.00 11,293 117,898,920


Ls 1.00 1,475,000 1,475,000
Ls 1.00 35,000,000 35,000,000
Ls 1.00 25,000,000 25,000,000
Rp 179,373,920

m³ 132483.6 44,092 5,841,442,885


m³ 132483.6 63,500 8,412,708,600
Rp 14,254,151,485

Buah 11,470.00 5,700,000 65,379,000,000


meter 91,760.00 262,873 24,121,240,684
m³ 180.00 1,572,655 283,077,926
kg 17,100.00 18,720 320,112,000
m³ 29,340.60 81,820 2,400,658,748
m³ 29,340.60 165,595 4,858,656,657
Rp 97,362,746,016

m³ 113246.0 44,092 4,993,222,112


m³ 113246.0 63,500 7,191,121,000
buah 1,510.00 12,000 18,120,000
m³ 42.14 1,095,470 46,165,850
m² 165.93 77,265 12,820,300
kg 22,471.12 23,117 519,466,443
m³ 377.91 1,572,655 594,322,106
m² 378.24 54,646 20,669,047
m³ 36.00 1,122,951 40,426,239
Unit 2.00 55,000,000 110,000,000
m³ 3,714.00 81,820 303,880,854
m³ 3,714.00 165,595 615,019,830
Rp 14,465,233,781

m² 41,760.00 261,040 10,901,030,400


m³ 20,880.00 1,095,470 22,873,416,358
Rp 33,774,446,758

m³ 12.0 6,750,000,000 81,000,000,000


m² 12.0 750,000,000 9,000,000,000
Rp 90,000,000,000

Rp 250,035,951,959
Rp 25,003,595,196
Rp 275,039,547,155
Rp 275,039,500,000
Sembilan Juta Lima Ratus Ribu Rupiah

Anda mungkin juga menyukai